MATERIAL Complete

Embed Size (px)

Citation preview

  • 8/3/2019 MATERIAL Complete

    1/16

    Table of Contents

    Introduction 11.0 Batching 22.0 Mixing 33.0 Transporting 7

    4.0 Placing1

    0

    5.0 Compacting1

    2

    6.0 Curing1

    3

    7.0 References1

    6

  • 8/3/2019 MATERIAL Complete

    2/16

    INTRODUCTION

    High-rise building is a trend around the globe to the architects and engineers. It is also

    becoming a race for all of them. But how are they are made, especially the important

    part of any building in the world concrete.

    Concrete is a structural material made from natural ingredients. It is extremely versatile

    and simple to use but too often, in basic rules are ignored and an inferior product results.

    A column is a vertical support structure while beam is a horizontal support structure of

    the building.

    The complete process of concrete production is followed from the basic materials

    employed until curing of the concrete.

    Concreting process has 6 processes, which are:

    1. Batching

    2. Mixing

    3. Transporting

    4. Placing

    5. Compacting

    6. Curing

    Those processes are needed for any concrete. As for high-rise building, such

    as Kuala Lumpur City Centre (KLCC), Kuala Lumpur or Burj Dubai, Dubai,

    that we used for as references, is going for something different. In this report

    we include the explanation for those. So what are the process that these

    types of building going through?

    2

  • 8/3/2019 MATERIAL Complete

    3/16

    1.0 BATCHING CONCRETE

    Batching is the process of weighing or volumetrically measuring and introducing

    into a mixer the ingredients for a batch of concrete. To produce a uniform quality

    concrete mix, measure the ingredients accurately for each batch. Most concrete

    specifications require that the batching be performed by weight, rather than by volume,

    because of inaccuracies in measuring aggregate, especially damp aggregate. Water

    and liquid air-entraining admixtures can be measured accurately by either weight or

    volume. Batching by using weight provides greater accuracy and avoids problems

    created by bulking of damp sand. Volumetric batching is used for concrete mixed in a

    continuous mixer, and the mobile concrete mixer (crate mobile) where weighing

    facilities are not at hand. Specifications generally require that materials be measured

    in individual batches within the following percentages of accuracy: cement 1%,

    aggregate 2%, water 1%, and air-entraining admixtures 3%. Equipment within the

    plant should be capable of measuring quantities within these tolerances for the smallest

    to the largest batch of concrete produced. The accuracy of the batching equipment must

    be checked and adjusted when necessary.

    Batching that used for high-rise building is grade 80.

    3

  • 8/3/2019 MATERIAL Complete

    4/16

    2.0 MIXING

    Concrete should be mixed until it is uniform in appearance and all the ingredients are

    evenly distributed. Mixers should not be loaded above their rated capacities and should

    be operated at approximately the speeds for which they were designed. If the blades of

    the mixer become worn or coated with hardened concrete, the mixing action will be less

    efficient. Worn blades should be replaced and the hardened concrete removed

    periodically, preferably after each production of concrete.

    When a transit mixer (TM) is used for mixing concrete, 70 to 100 revolutions of the drum

    at the rate of rotation designated by the manufacturer as mixing speedare usually

    required to produce the specified uniformity. No more than 100 revolutions at mixing

    speed should be used. All revolutions after 100 should be at a rate of rotation designated

    by the manufacturer as agitating speed. Agitating speed is usually about 2 to 6

    revolutions per minute, and mixing speed is generally about 6 to 18 revolutions per

    minute. Mixing for long periods of time at high speeds, about 1 or more hours can result

    in concrete strength loss, temperature rise, excessive loss of entrained air, and

    accelerated slump loss.

    Concrete mixed in a transit mixer should be delivered and discharged within 1

    1/2 hours or before the drum has revolved 300 times after the introduction of water to

    cement and aggregates or the cement to the aggregates. Mixers and agitators should

    always be operated within the limits of the volume and speed of rotation designated by

    the equipment manufacturer.

    Separate paste mixing has shown that the mixing of cement and water into a paste

    before combining these materials with aggregates can increase the compressive

    strength of the resulting concrete. The paste is generally mixed in a high-speed, shear-

    type mixer at a w/cm (water to cement ratio) of 0.30 to 0.45 by mass. The cement pastepremix may include admixtures, e.g. accelerators or retarders, plasticizers, pigments, or

    fumed silica. The latter is added to fill the gaps between the cement particles. This

    reduces the particle distance and leads to a higher final compressive strength and a

    higher water impermeability. The premixed paste is then blended with aggregates and

    4

  • 8/3/2019 MATERIAL Complete

    5/16

    any remaining batch water, and final mixing is completed in conventional concrete

    mixing equipment.

    High-Energy Mixed Concrete (HEM concrete) is produced by means of high-speed

    mixing of cement, water and sand with net specific energy consumption at least 5

    kilojoules per kilogram of the mix. It is then added to a plasticizer admixture and mixed

    after that with aggregates in conventional concrete mixer. This paste can be used itself

    or foamed (expanded) for lightweight concrete. Sand effectively dissipates energy in this

    mixing process. HEM concrete fast hardens in ordinary and low temperature conditions,

    and possesses increased volume of gel, drastically reducing capillarity in solid and

    porous materials. It is recommended for pre-cast concrete in order to reduce quantity of

    cement, as well as concrete roof and siding tiles, paving stones and lightweight concrete

    block production.

    2.1Overmixing Concrete

    Overmixing concrete damages the quality of the concrete, tends to grind the aggregate

    into smaller pieces, increases the temperature of the mix, lowers the slump, decreases

    air entrainment, and decreases the strength of the concrete. Also, overmixing puts

    needless wear on the drum and blades of the transit mixer. To select the best mixing

    speed for a load of concrete, estimate the travel time to the project (in minutes) and

    divide this into the minimum desired number of revolutions at mixing speed-70. The

    results will be the best drum speed; for instance, if the haul is 10 minutes, 70 divided by

    10 equals 7. With this drum speed, the load will arrive on the jobsite with exactly 70

    turns at mixing speed.

    5

  • 8/3/2019 MATERIAL Complete

    6/16

    Reversing drum

    Batch mixers are of four main types:

    1. Tilting drum

    2. Non-tilting drum

    3. Reversing drum

    4. Forced action

    For high-rise building, it is suitable to use tilting drum. Its for medium strength concretes

    in the capacity range 100 to 200 litres, and for producing mass concrete with large

    (150mm) aggregate. Materials are poured into the drum and allow it to fall, encouraging

    mixing.

    6

  • 8/3/2019 MATERIAL Complete

    7/16

    3.0 TRANSPORTING

    All concrete that already has been mixed need to transported from where it mixed to its

    final position. It can be simple job of discharging it down a chute from a ready-mix truck

    into a trench on the other hand it may have to be conveyed long distances or pumped

    to great heights. The precaution to be taken while transporting concrete is that the

    homogeneity obtained at the time of mixing should be maintained while being

    transported to the final place of deposition.

    4.1 Selection of Transportation Method

    The best solution for a particular project is usually reached after consulting company

    personnel who can provide information and advice on the following:

    a) Access available to and on the site;

    b) Plant availability;

    c) Quantity of concrete;

    d) Quality of concrete;

    e) Material;

    f) Quality and number

    4.2 Methods and plant

    There are many methods and plant that can be used. There are:

    a) Manual handling

    The escalating cost of manpower means a hard look must be taken at all

    forms of concrete transport involving labour. Nevertheless, there are jobs

    where wheelbarrows, prams or motorised prams are most suitable and

    have the advantage of low plant hire cost.

    7

  • 8/3/2019 MATERIAL Complete

    8/16

    b) Lorry-mounted boom pumps

    Its used for concrete pours for everything from slabs and medium high-

    rise buildings, to large volume commercial and industrial projects. They

    range from single-axle truck mounted pumps used for their high

    maneuverability, suitability for confined areas, and cost/performance

    value, to huge, six-axle rigs used for their powerful pumps and long reach

    on high-rise and other large-scale projects.

    c) Lorries

    It is used to transport concrete from factory to the site.

    d) Ready-mix trucks

    It is a very convenient way of transporting concrete and the concrete

    should be discharged if possible, directly into its final position.

    e) Mobile cranes with buckets

    This mobile can be used to transporting a bucket of concrete into the

    higher area, when ready-mix concrete is at bottom of the site.

    f) Mobile and static pumps

    The 150mm static pump with metal quick-release pipes is suitable for

    large pours spread over considerable distances.

    Those above requirements are important because each selection will effect on the care

    of the concrete. The cost that have been given to produce a workable concrete of the

    correct strength and durability which leaks from lorries can seriously reduce the qualities

    of good concrete.

    As for high-rise building like Kuala Lumpur City Center (KLCC) or Burj Dubai, the

    methods they used were:

    1. Ready-mix trucks

    2. Mobile cranes with buckets

    3. Mobile and static pumps

    4. Lorry-mounted boom pumps

    8

  • 8/3/2019 MATERIAL Complete

    9/16

    Ready-mix trucks

    and pumps

    Bucket Lorry-mounted boom pump

    9

  • 8/3/2019 MATERIAL Complete

    10/16

    4.0 PLACING

    The main objective when placing concrete is to deposit the concrete as close as possible

    to its final position, quickly and efficiently to minimise segregation.

    No water should be added to the concrete once it has left the mixer, otherwise the

    properties might be adversely affected. The concrete should not be allowed to fall in

    heaps and then moved along the form. It should be spread evenly, to ensure placement

    as near as possible to its final position.

    The most suitable plant should be provided, for example a crane bucket with a controlled

    chute if filling walls with baffle boards to direct the concrete to prevent spillage over the

    forms.

    The placing of concrete successfully in deep lifts requires the concrete mix to be

    designed to minimise the risk of segregation. The concrete should also be discharged

    down some form of trunking as this reduces the likelihood of damage to the forms and

    misplacement of reinforcement. Trunking will also prevent the loss of grout which, if

    allowed to remain on the forms and steel above the concrete level, will result in gap

    concrete at the bottom of the pour. The hose of a concrete pump acts in the same

    manner as trunking, providing it is place at the bottom of the pour at commencement and

    slowly raised to suit the filling process.

    Segregation can occur in transporting concrete where the vibration of the lorry, dumper,

    etc. will cause the mortar to flow away from the coarse aggregate. With low workability

    concrete, the larger aggregate can segregate from the bulk of the concrete.

    By considering above factors, the high-rise buildings would probably place the concrete

    by the pump and bucket. This is because since it is high-rise building, concrete cannotbe easily to be transported to the required place. Therefore, concrete must be place

    directly and quickly but carefully to prevent segregation.

    10

  • 8/3/2019 MATERIAL Complete

    11/16

    Concrete placing by bucket

    Concrete placing by ready-mix lorry

    11

  • 8/3/2019 MATERIAL Complete

    12/16

    5.0 COMPACTING

    Compaction is also very important wherever concrete exposed to view. Compaction

    also, should be done as soon as possible once water has been added to concrete.

    Compacting by machine can only be thoroughly compacted by vibrator, rollers, press or

    by centrifugal casting.

    For high-rise building, usually they used vibration. This is because it has a chemical

    action with the cement which unites the aggregates to form a hardened material.

    Second, it allows easy placement of the concrete. External vibrators are use also but

    they are restricted to heavy robust forms that are use for repeated manufacture for

    example large deep frame and slab having webs which are inaccessibly with a poker

    vibrator.

    Vibrating tables are used in pre-cast manufacture for repeat items such as kerbs, and

    bollards. Moulds are filled with concrete and placed on the vibrating table which vibrates

    and effectively compact the concrete.

    All vibrators must be treated with care and be properly maintained if breakdowns are to

    be avoided site management must have and use the manufacture instruction booklet to

    follow the recommendation for both operation and maintenance.

    Care must be taken to avoid disturbance to any fixings to the formwork. They should be

    firmly fixed with the screws in preference to nails.

    12

  • 8/3/2019 MATERIAL Complete

    13/16

    6.0 CURING

    Curing is the process of controlling the rate and extent of moisture loss from concrete

    during cement hydration. It may be either after it has been placed in position (or during

    the manufacture of concrete products), thereby providing time for the hydration of the

    cement to occur. Since the hydration of cement does take time. Curing must be

    undertaken for a reasonable period of time if the concrete is to achieve its potential

    strength and durability.

    Curing may also encompass the control of temperature since this affects the rate at

    which cement hydrates. Cement requires a moist, controlled environment to gain

    strength and harden fully, gaining in strength in the days and weeks following. In around

    3 weeks, over 90% of the final strength is typically.

    Hydration and hardening of concrete during the first three days is critical. Abnormally

    fast drying and shrinkage due to factors such as evaporation from wind during

    placement may lead to increased tensile stresses at a time when it has not yet gained

    significant strength, resulting in greater shrinkage cracking. Minimizing stress prior to

    curing minimizes cracking. High early-strength concrete is designed to hydrate faster,

    often by increased use of cement which increases shrinkage and cracking.

    During this period concrete needs to be in conditions with a controlled temperature and

    humid atmosphere, in practice this is achieved by spraying or ponding the concrete

    surface with water. The pictures to the right show two of many ways to achieve this,

    ponding submerging setting concrete in water, and wrapping in plastic to contain the

    water in the mix.

    Properly curing concrete leads to increased strength and lower permeability, and avoids

    cracking where the surface dries out prematurely. Care must also be taken to avoidfreezing, or overheating due to the exothermic setting of cement. Improper curing can

    cause scaling, reduced strength, poor abrasion resistance and cracking.

    13

  • 8/3/2019 MATERIAL Complete

    14/16

    6.1 Curing Method

    Impermeable-membrane Curing

    Formwork leaving formwork in place is often an efficient and cost-effective method of

    curing concrete, particularly during its early stages. In very hot dry weather, it may be

    desirable to moisten timber formwork, to prevent it drying out during the curing period,

    thereby increasing the length of time for which it remains effective. It is desirable that

    any exposed surfaces of the concrete (e.g. the tops of beams) be covered with plastic

    sheeting or kept moist by other means. It should be noted that, when vertical formwork is

    eased from a surface (e.g. from a wall surface) its effectiveness as a curing system is

    significantly reduced.

    Plastic sheeting

    Plastic sheets, or other similar material, form an effective barrier against water loss,

    provided they are kept securely in place and are protected from damage. Their

    effectiveness is very much reduced if they are not kept securely in place. The movement

    of forced draughts under the sheeting must be prevented. They should be placed over

    the exposed surfaces of the concrete as soon as it is possible to do so without marring

    the finish. On flat surfaces, such as pavements, they should extend beyond the edges of

    the slab for some distance, eg or at least twice the thickness of the slab, or be turned

    down over the edge of the slab and sealed.

    For horizontal work, sheeting should be placed on the surface of the concrete and, as far

    as practical, all wrinkles smoothed out to minimise the mottling effects (hydration

    staining), due to uneven curing, which might otherwise occur. Flooding the surface of the

    slab under the sheet can be a useful way to prevent mottling. Strips of wood, or

    windrows of sand or earth, should be placed across all edges and joints in the sheetingto prevent wind from lifting it, and also to seal in moisture and minimise drying. For

    decorative finishes or where colour uniformity of the surface is required sheeting may

    need to be supported clear of the surface if hydration staining is of concern. This can be

    achieved with wooden battens or even scaffolding components, provided that a

    complete seal can be achieved and maintained.

    14

  • 8/3/2019 MATERIAL Complete

    15/16

    For vertical work, the member should be wrapped with sheeting and taped to limit

    moisture loss. As with flatwork, where colour of the finished surface is a consideration,

    the plastic sheeting should be kept clear of the surface to avoid hydration staining. Care

    must also be taken to prevent the sheeting being torn or otherwise damaged during use.

    A minimum thickness is required to ensure adequate strength in the sheet. Plastic

    sheeting may be clear or coloured.

    Care must be taken that the colour is appropriate for the ambient conditions. For

    example, white or lightly coloured sheets reflect the rays of the sun and, hence, help to

    keep concrete relatively cool during hot weather. Black plastic, on the other hand,

    absorbs heat to a marked extent and may cause unacceptably high concrete

    temperatures. Its use should be avoided in hot weather, although in cold weather its use

    may be beneficial in accelerating the rate at which the concrete gains strength.

    Curing

    15

  • 8/3/2019 MATERIAL Complete

    16/16

    7.0 REFERENCES

    Baker, E. M. (1985). Making and Placing Concrete. Construction Press.

    Davis, E. Harmer (1956). Composition and Properties of Concrete. McGraw-Hill.

    Wikipedia (11.30 AM, 8 February 2009). Concrete. Retrieved from

    http://en.wikipedia.org/wiki/Concrete

    Wikipedia (11.36 AM, 8 February 2009). Skycraper. Retrieved from

    http://en.wikipedia.org/wiki/Skyscraper

    Superseal (11.42 AM, 8 February 2009). Concrete pumping. Retrieved from

    http://www.concretefoundation.net/page2.html

    Concrete Network (12.00 PM, 8 February 2009). Pumps. Retrieved from

    http://www.concretenetwork.com/concrete/concrete_pumping

    16