    Marginal Field Development The Sea Swift Conductor Supported Platform (CSP)

    Ken Crawford

  • Page 2

    Our Company

    Our Services

    Offshore Structures for Marginal Field Development utilising a MOPU development solution

    Agenda

  • Page 3

    Exceptional Innovation in Offshore Engineering Solutions

    Concept, design, procurement and installation

    Offshore systems, products and technical support services

    Offshore Structures

    Riser Systems

    Hydraulic Systems

    Service & Rental

    Our Engineering Solutions Delivering Your Vision

  • Page 4

    Global Track Record and Experience

    Operational experience and on-ground representation in Asia Pacific, Africa, Europe, Middle East, North Sea and USA

    Worked completed for over 110 customers in 32 countries

    Growing Team

    Degree Qualified Engineers to PHD level

    Affiliation with Cambridge University

    Experienced hands-on Offshore Field Engineers

    Offer practical solutions to offshore challenges

    Our Company Structured for Your Success

  • Page 5

    Our Commitment To Your Success

    Innovative, Robust and Reliable Solutions

    to Drilling and Platform Requirements

    Innovation: based on hands on experience

    Safety: first before all else

    Service & Quality: responsive and tailored to customer needs

    Cost Control: delivering reduced platform costs. Lower installation costs, minimum drilling downtime, simplified critical path and reduced intervention costs

  • Page 6

    Our Company Structured for your Success

    Project Management

    Analysis & Engineering

    Procurement Fabrication & Testing

    Offshore Installation

    & Operations

  • Page 7

    Offshore Structures Sea Swift Conductor Supported

    Platform

    Subsea Drilling Templates

    Subsea Protective Structures

    Wellhead Tower

    Tension Decks

    Bespoke Offshore Structures

    Our Innovation Bringing Your Specification to Life

    Design, Procure, Supply, Install

  • Page 8

    Riser Systems Riser Analysis

    Subsea Riser Systems

    Surface Riser Systems

    Pipeline Riser

    VIV Suppression Systems

    Connectors

    Tie-back Engineering

    Centralisers

    Our Innovation Bringing Your Specification to Life

  • Page 9

    Hydraulic Systems Hydraulic Power Unit

    Wellhead Control Panel

    Spare Parts

    Image Based Information System

    System Appraisal / Troubleshooting

    Fluid Analysis

    Our Innovation Bringing Your Specification to Life

  • Page 10

    Service & Rental SUREgrip Tension Ring

    PROten Riser Tensioning System

    Rig Floor Tensioning System

    Conductor / Riser Tensioning Unit

    Cement Top Up System

    Aquascope Subsea Camera

    Trash Caps

    Conductor Tie-back Rental Tools

    Our Innovation Bringing Your Specification to Life

  • Page 11

    Offshore Structures Sea Swift Conductor Supported Platform

  • Page 12

    Offshore Structures MOPU Wellbay Modules

    Bespoke wellbay modules designed to be used in conjunction with a MOPU

    Quick and low cost solution for rapid development of normally uneconomical fields

    Attaching the wellbay module to the hull of the FPSO removes the need for a NUI or standard jacket

    Systems are designed to be either fitted to new build rigs or retrofit to existing rigs

    Allows multiple wells to be tied back to an FPSO

  • Page 13

    Offshore Structures Tension Decks

    Bespoke tension decks designed for explorations and development drilling

    Systems are designed to be either fitted to new build rigs or retrofit to existing rigs

    Allows multiple wells to be drilled at one single location

    Can provide up to 1500 Tones of tension across 6 individual well slots

  • Page 14

    Typically NUI platforms using well conductors as structural members.

    Designed to current API and Verification body rules.

    Designed for installation by standard cantilever Jack-up and supply vessel. No need specialist vessel assistance.

    Conductors can be drilled and cemented or piled.

    Three main applications

    Normally Unmanned Installation

    Pre drill wellhead platform

    Slot addition wellhead platform

    Offshore Structures Sea Swift Conductor Supported Platforms

  • Page 15

    Sea Swift CSP Component Montage

  • Page 16

    Sea Swift CSP Configurable Topsides

  • Page 17

    Typically 36 or 30 diameter Grade X52.

    Premium fatigue grade connectors (e.g. National Oilwell Varco XLC-S connectors) with excellent strength and fatigue performance.

    Pile or drill conductors.

    Four conductors will form the main structural support to the platform and will be effectively fixed within the subsea structures via use of grout.

    Corrosion protection will be provided.

    Sea Swift CSP Conductors

  • Page 18

    Example of 4 Well Sea Swift

    Overall dimensions of approximately: H: 13.6m W: 6.9m L: 8.1m

    4 wells in a 2 x 2 array @ 6m x 4.8m spacing plus a central running slot which can also be used as a well slot (future requirement).

    Approximate weight 160 Tonnes.

    4 x 42 O/D leg sleeves, and an arrangement of smaller tubular sections interconnecting bracing members.

    The subsea structure will be located at or just above the seabed and initially supported on a central support pile. This can also accommodate an additional well if required in the future.

    All required cement grouting equipment, installation cameras, subsea gyrocompass location fittings and guides for the export riser and subsea power umbilical cable.

    Conductors will be grouted within the sleeves.

    Sea Swift CSP Subsea Structures

  • Page 19

    Offers support/protection to the export riser and umbilical cable.

    Approximate weight will be 2.5 Tonnes

    Locates over two well conductors.

    Installed either following or during the installation of the 4 well conductors and prior to installation of the topsides module.

    Incorporates guide modules for the export riser and the subsea power umbilical cable.

    Will be installable using AEL patented technology.

    Sea Swift CSP Riser Guide

  • Page 20

    Sea Swift CSP Typical Topsides Facilities Equipment

    Production Test & Manifolds, piping and valves

    Wellhead control panel and Hydraulic Power Unit (HPU)

    Platform control interface

    Pig launcher

    Flare / Emergency Vent Boom

    Emergency personnel shelter (located within designated Safe Area)

    Electrical Equipment Room (located within designated Safe Area)

    Chemical injection package

    Platform Control System

    Sump tank and pump

    Vent scrubber and pump

    Service water pump

    Diesel driven crane and diesel tank

    Multiphase flow meter

    ESP Control Transformers

    CCTV

    Emergency Lighting

    Life escape devices e.g. life buoys

    Platform Safety Equipment

  • Page 21

    Sea Swift CSP Delivery of the Complete Solution

    Project Management

    Analysis & Engineering

    Procurement Fabrication & Testing

    Offshore Installation

    & Operations

  • Page 22

    Dedicated Project Team

    Structural & Fatigue Analysis

    Process simulations

    Topsides Facilities Equipment Analysis

    Mechanical

    - Instrument & Control

    - Electrical & Power

    - Piping

    - Telecommunication

    - Technical Safety

    - Detailed Design

    Production of BOD

    Development of design specifications & key documents

    Sea Swift CSP Project Management

  • Page 23

    FEED Study / Review & verification of FEED design documents

    Structural & Fatigue Analysis

    Process simulations

    Topsides Facilities Equipment Analysis

    Mechanical

    - Instrument & Control

    - Electrical & Power

    - Piping

    - Telecommunication

    - Technical Safety

    - Detailed Design

    Production of BOD

    Development of design specifications & key documents

    Sea Swift CSP Analysis & Engineering

  • Page 24

    Sea Swift CSP Procurement

    Sub contractor evaluation and selection:

    Sub contractor audits and final selection of sub contractors driving down costs where possible

    Procurement of long lead items

    Conductor joints and connectors

    Structural sections and subsea structure cans

    Pig Launcher

    Topside facilities equipment & Piping

    WHCP / HPU

  • Page 25

    Sea Swift CSP Fabrication

    Sub contractor evaluation and selection:

    Sub contractor audits and final selection of sub contractors driving down costs where possible

    Procurement of long lead items

    Conductor joints and connectors

    Structural sections such as the subsea structure cans

    Topside facilities equipment & Piping

    Manufacturing phase:

    Topsides module fabrication and painting

    Subsea structure fabrication and painting

    Platform ancillaries fabrication and painting

    Platform and riser Installation equipment fabrication

    QA, QC

    Installation of facilities equipment

    Riser pre-fabrication

    Platform FAT

    Full Aquaterra management team on site to manage fabrication

    Delivery of complete solution

  • Page 26

    Sea Swift CSP Example Schedule

  • Page 27

    Sea Swift CSP

  • Page 28

    Sea Swift CSP

  • Page 29

    Sea Swift CSP

  • Page 30

    Sea Swift CSP

  • Page 31

    26m Water Depth

    Four 30 Conductors run to 50m below mudline

    Provision for 5 wells (3 initial + 2 optional)

    25 year design life. Minimal processing facilities - will incorporate manifolds, multi-phase analyser/meter, utilities and a pig launcher.

    6m x 4.8m well spacing with additional centre running / support slot

    One subsea structure approximately

    H: 13.6m W: 6.9m L: 8.1m

    Weight: Approximately 160T

    Topside 3 deck levels approximately

    H: 9.5m W: 12m L: 15m

    Weight (including process equipment): Approx. 260T (based on current understanding of requirements)

    Crude transported to shore via a 15km long, 8 pipeline to a 12,000BPD capacity onshore facility.

    Power will be supplied via one combined subsea power and fibre optic data communication cable.

    Umbilical and Riser guides.

    Access via boat landing and ladder

    Sea Swift CSP Seme Development - General Platform Configuration

  • Page 32

    Sea Swift CSP

  • Page 33

    Sea Swift CSP Installation

    1. Pick up and Hang off Subsea Structure

    2. Drill Centre Slot Conductor

    3. Pickup & Install Lower Subsea Structure

    4. Pickup and Install Upper Subsea Structure

    5. Drill and Run Four Environmental Conductors

    Attach riser guides and boat access ladder as conductor ran

    Cut conductors to height as each is drilled

    6. Space Out & Grout Lower Subsea Structure to Depth

    7. Space Out & Grout Upper Subsea Structure to Depth

    8. Pick up and Hang-off Topside Structure

    9. Transfer and Set Down Topside Structure

    10. Complete Hook Up & Commissioning

  • Page 34

    Sea Swift CSP Installation

  • Page 35

    Sea Swift CSP Gallery

  • Page 36

    Sea Swift CSP Gallery

  • Page 37

    Sea Swift CSP Gallery

  • Page 38

    Sea Swift CSP Gallery

  • Page 39

    Sea Swift CSP Gallery

  • Page 40

    Sea Swift CSP Gallery

  • Page 41

    Sea Swift CSP Gallery

  • Page 42

    Sea Swift CSP Gallery

  • Page 43

    Sea Swift CSP Gallery

  • Page 44

    Sea Swift CSP Gallery

  • Page 45

    Sea Swift CSP Gallery

  • Page 46

    Sea Swift CSP Gallery

  • Page 47

    Sea Swift CSP Gallery

  • Page 48

    Sea Swift CSP Gallery

  • Page 49

    Sea Swift CSP Installation

    1. Drill Centre Hole. Pick up and Install Lower Subsea Structures

  • Page 50

    Sea Swift CSP Installation

    2. Pick up and Install Upper Subsea Structures

  • Page 51

    Sea Swift CSP Installation

    3. Pick up Topside and Boat Landing Structures

  • Page 52

    Sea Swift CSP Installation

    4. Commence Drilling Operations

  • Page 53

    Sea Swift CSP Installation

    5. Prepare Cement Hoses

  • Page 54

    Sea Swift CSP Installation

    6. Spaceout and Secure Subsea Structures

  • Page 55

    Sea Swift CSP Installation

    7. Position & Install Topsides

  • Page 56

    Sea Swift CSP Installation

    8. Complete Hook-up and Commissioning