Marginal Field Incentive - Benny

Embed Size (px)

Citation preview

  • 7/24/2019 Marginal Field Incentive - Benny

    1/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S Marginal Field Incentive

    by

    Benny Lubiantara

    Evaluation & Dev. Plan Division, BPMIGAS

    The Executive Agency for Upstream Oil & Gas Activities

  • 7/24/2019 Marginal Field Incentive - Benny

    2/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    2

    DEFINITION

    A marginal field is an oil field located within a producing

    block that, under the current PSC terms and conditions, isnot economics to be developed.

    Marginal Field is the first field of the Contract Area proposed by

    Contractor for development and approved, capable of Crude Oilproduction not exceeding 10,000 Barrels daily average projected for

    the initial two (2) production years (24 production months).

    Old Definition in PSC Contract:

  • 7/24/2019 Marginal Field Incentive - Benny

    3/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    3

    Conditions for Marginal Field

    Located within a producing block.

    Its main product is oil.

    The exploration costs for that field has been fully recovered,i.e. no more sunk costs considered.

    If calculate based on the current PSC terms and conditionsand other incentive packages that may be applied for thatfield in accordance with laws and regulations, the InternalRate of Return (IRR) is estimated less than 15%.

  • 7/24/2019 Marginal Field Incentive - Benny

    4/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    4

    Working Area / Block

    Field "A"

    (producing)

    Field "B"

    (producing)

    Undeveloped Field

    Marginal Field Candidates

  • 7/24/2019 Marginal Field Incentive - Benny

    5/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    5

    Type of Incentive

    20% Operating Cost*) recovery up-lift.

    Other incentive packages that may be applied for thatfield in accordance with the prevailing PSC, laws andregulations.

    *) Under Definition of the PSC, the Operating Cost consist of:

    1. Current Years Non Capital Costs

    2. Current Years Depreciation for Capital Costs

  • 7/24/2019 Marginal Field Incentive - Benny

    6/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    6

    Marginal Field Incentive

    The Mechanism

    Incentive is not permanently given and will be evaluated onyearly basis.

    The new incentive package is issued in order to improve the

    economics of the field, after receiving the incentive, the IRR ofthe field is expected at least 15%. (The Incentive is ON)

    The Incentive will be removed if the actual cumulative IRR hasreached 30% (The Incentive is OFF).

    The Incentive will be re-apllied if the actual cumulative IRR inthe followong year has dropped below 15%.

  • 7/24/2019 Marginal Field Incentive - Benny

    7/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    7

    (15,000)

    (10,000)

    (5,000)

    -

    5,000

    10,000

    2005 2006 2007 2008 2009 2010 2011 2012 2013

    Year

    US$

    (000)

    Net Cash Flow

    IRR = 18.5%

    The Concept of IRR Cumulative

  • 7/24/2019 Marginal Field Incentive - Benny

    8/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    8

    -40%

    -30%

    -20%

    -10%

    0%

    10%

    20%

    2005 2006 2007 2008 2009 2010 2011 2012 2013

    IRR Cumulative

    (15,000)

    (10,000)

    (5,000)

    -

    5,000

    10,000

    2005 2006 2007 2008 2009 2010 2011 2012 2013

    Net Cash Flow

    IRR = 18.5%

  • 7/24/2019 Marginal Field Incentive - Benny

    9/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    9

    -30%

    -20%

    -10%

    0%

    10%

    20%

    30%

    40%

    50%

    2005 2006 2007 2008 2009 2010 2011 2012 2013

    IRR Cumulative if Incentive not OFFIRR Cumulative

    Incentive OFF

  • 7/24/2019 Marginal Field Incentive - Benny

    10/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    10

    Most Likely Case

    Year

    15%

    30%

    IRRCumulative

    "On - Off" Mechanism

    Incentive "On"

    Incentive "Off"

    Expected IRR Cumulativ e Trend if the Incentive is NOTRemoved

  • 7/24/2019 Marginal Field Incentive - Benny

    11/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    11

    Year

    15%

    30%

    IRRCumulative

    "On - Off" Mechanism

    Incentive "On" Incentive "Off"

    Incentive "On"Incentive "Off"

    Expected IRR Cumulative Trend if Incentive is NOT Removed

    Extreme - Case

  • 7/24/2019 Marginal Field Incentive - Benny

    12/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    12

    Illutration

    Field "A"

    (producing)

    Field "B"

    (producing)

    Marginal Field

    ( Realization)

    Marginal Field

    ( Initial Condition )

  • 7/24/2019 Marginal Field Incentive - Benny

    13/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    13

    Year

    15%

    30%

    IRRCumulative

    "On - Off" Mechanism

    Incentive always "On"

    Always On - Case

  • 7/24/2019 Marginal Field Incentive - Benny

    14/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    14

    Procedure

    1. PSC could register the candidates for marginal field by submitting thesummary of POD. BPMIGAS will response by sending the written answer nolonger than 10 working days.

    2. No longer than 6 months following the registration, PSC should submitcomplete POD (in order to speed-up the process, the draft of AFE proposalneed also to be attached).

    3. Registration period is 12 months (25 April 2005 24 April 2006)

    Registration & Submission

  • 7/24/2019 Marginal Field Incentive - Benny

    15/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    15

    1. When submitting the POD, the assumption for oil price isUS$ 25 per barrel.

    2. BPMIGAS will approve or not approve the POD proposal bysending the written answer to the PSC no longer than 30days after receiving the POD proposal.

    3. PSC should commence the activities no longer than one yearafter POD approved.

    Evaluation, Approval & Implementation

    Procedure

  • 7/24/2019 Marginal Field Incentive - Benny

    16/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    16

    4. The commencement of the activies isdeclared if:

    Tender Plan is appoved; or

    Tender Announced; or

    Execution of the Field Development

    Procedure

    Evaluation, Approval & Implementation

  • 7/24/2019 Marginal Field Incentive - Benny

    17/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    17

    1. PSC should make the special book account for marginal field.

    2. The marginal field insentive is taxable.

    Implementing and Reporting

    Procedure

  • 7/24/2019 Marginal Field Incentive - Benny

    18/18

    PMIG S

    PMIG S

    PMIG S

    PMIG S

    Thank You