Major Report on Energy Mgt

Embed Size (px)

Citation preview

  • 7/30/2019 Major Report on Energy Mgt

    1/79

    A

    PROJECT REPORT

    ON

    COMPREHENSIVE STUDY ON ENERGY MANAGEMENT

    Submitted in the partial fulfillment for the award of degree of

    Bachelor of technology

    In

    ELECTRICAL & ELECTRONICS ENGINEERING

    H.C.T.MTECHNICAL

    CAMPUS,

    KAITHAL

    SUBMITTED

    TO:-

    SUBMITTEDBY:-

    Er. VINOD

    KUMAR

    MANISH

    UPPAL

    (1709731)

    ASSISTANT

    PROF.

    HIMANSHU

    CHANCHAL

    (1709742) EEE DEPARTMENT MOHIT GIRDHAR

    (1709744)

    H.C.T.M TECHNICAL CAMPUS, KAITHAL

    KURUKSHETRA UNIVERSITY KURUKSHETRA

    CANDIDATE's DECLARATION

  • 7/30/2019 Major Report on Energy Mgt

    2/79

    We hereby declare that the work which is being presented in this project entitled "

    COMPREHENSIVE STUDY ON ENERGY MANAGEMENT" in partial fulfillment of the

    requirement for the award of the degree of bachelor of technology in the field

    of Electrical & Electronics Engineering submitted to HCTM TECHNICAL

    CAMPUS , Kaithal is an authentic record of my work carried out under the

    guidance of Er. Vinod Kumar , Assistant Professor , in the Department of

    Electrical & Electronics Engineering , HCTM TECHNICAL CAMPUS , Kaithal .

    Date : Manish Uppal (1709731)

    Place : Kaithal Himanshu Chanchal ( 1709742)

    Mohit Giridhar ( 1709744)

    B.Tech. ( Electrical & Electronics

    Engineering)

    Certificate

    This is to certify that the above statement made by the candidate is correct to the best of my

    knowledge and belief.

    Er. Vinod Kumar Er. Vivek Phawa

    Assistant Professor Professor & H.O.D.

    Department of Electrical& Department of Electrical&

    Electronics Engineering Electronics Engineering

    HCTM Technical Campus , Kaithal HCTM Technical Campus , Kaithal

    ACKNOWLEDGEMENT

  • 7/30/2019 Major Report on Energy Mgt

    3/79

    As the saying goes WE set ourselves to bite the hands that feed us if we fail to

    thank such of those to whom our thanks are really due.

    In view of the help extended and opportunities given to us to work on

    this study based project on "Energy Management" , we are compelled to thank

    to all those who took an initiative and helped us in providing input for theproject.

    First of all , we consider this an utmost duty to extend our heartiest

    thanks to the HOD (EEE Dept) , Mr.Vivek Pahwa for necessary co-operation /

    consideration for our successful completion of this project.

    Above all we would like to convey our esteemed thanks to Er. Vinod

    Kumar , Assistant Professor ( EEE Dept) , for providing necessary guidelines

    and nourishing us thorough out with his best experiences in the field of power

    system and energy management.

    At last but not the least, we would like to extend our thanks to all staff

    members and officers of the concerned department of HPSEBL for providing

    necessary material for successful completion of the project.

    Manish Uppal (1709731)

    Himanshu Chanchal ( 1709742)

    Mohit Giridhar ( 1709744)

    B.Tech. ( Electrical & Electronics

    Engineering)

  • 7/30/2019 Major Report on Energy Mgt

    4/79

    ABSTRACT

    Energy management is a vital issue in the present scenario when the system under

    integration mode runs under deficit or surplus conditions. The term energy management

    includes planning and operation of energy & its consumption. The application of energy

    management is well visualized when an organization receives energy from outside the state

    as well as from its own generation within the state. In the modern era, when the energy is

    available from renewable energy sources in the pure form and its disposal to the

    beneficiaries in the bundled form, uses intensive application of energy management

    methodologies.

    This study based project is a comprehensive study on Energy Management. Thebasic idea of this project is to get awareness of the energy management methodologies

    when some states are surplus in power and some states are deficit in power. Mostly, the

    snow fed states like Himachal have less generation during winters and due to melting of

    snow during summer, have maximum flow of water in the rivers which ultimately

    attributes to enhanced generation during summers. This project also focuses on under

    drawal and overdrawal under different frequency conditions under UI regime.

    In order to approach step by step hierarchy of energy management, the project has

    been divided into two sections. Section-I focuses on role of energy management in power

    system and general approach towards energy management methodologies and Section II

    is a special case study on energy management in Himachal Pradesh.

    Section-I comprises 8 Chapters. The first chapter gives introduction on the

    necessity of Energy management when the system is passing through abnormal conditions.

    The second chapter stresses the importance of SLDC as an essential tool to energy

    management. The third chapter puts light on the very important feature of energy

    management i.e. Availability Based Tariff (ABT) , which apprises about the scheduling of

    power by the utilities as special feature and importance of ABT in energy management.The

    fourth chapter gives knowledge about the role of frequency in energy management under

    different frequency conditions.The fifth chapter presents very important aspect of energy

    management as to how the energy is managed when deviates from the schedule. The sixth

    chapter provides , how the trading opportunities are available both for Generator as well as

    Beneficiary under the shadow of energy management.The seventh chapter has its

  • 7/30/2019 Major Report on Energy Mgt

    5/79

    importance as without this tool of energy management it is not possible to make trading

    with the utilities who are available at some other places. Apart from above , now Indian

    Exchange is also one of the players available in the market to take care of disposal /

    procurement of power on day to day basis and eighthchapterprovides special features of

    power Exchange established in India.

    Section-II is very important section which deals with Himachal Pradesh as a special case

    of Energy Management and puts light on the tools and methodology being adopted by

    Himachal Pradesh for disposal of its surpluses and mitigating deficits.This section

    comprises three chapters. The first chapter focuses on status of SLDC in HPSEBL and

    second chapter highlights utility of SLDC as an essential tool for energy management.

    This provides inputs of different components used in establishing SLDC units , thus gave

    an ease to manage energy transactions in effective manners. The third chapter highlights

    Himachal Pradesh as a special case of Energy management and provides details of share of

    H.P in different sources and modes of energy management .

    .

  • 7/30/2019 Major Report on Energy Mgt

    6/79

    CONTENTS

    SECTION -I

    ROLE OF ENERGY MANAGEMENT

    IN

    POWER SYSTEM OPERATION

    CHAPTER 1 INTRODUCTION

    1.1 Vital Role of Energy Management

    1.2 Basics of Energy Management

    1.3 Constraints in Energy Management

    CHAPTER 2 SLDC AN ESSENTIAL TOOL TO ENERGY

    MANAGEMENT

    2.1 Introduction

    2.2 Load Dispatch Centers in Northern India

    2.3 Real Time Dynamic Security Assessment

    CHAPTER 3 AVAILABILITY BASED TARIFF(ABT)

    3.1 Introduction

    3.2 Details about ABT

    3.3 Scheduling

    3.3.1 Introduction

    3.3.2 Day Ahead Scheduling

    3.4 Features of ABT

  • 7/30/2019 Major Report on Energy Mgt

    7/79

    CHAPTER 4 ROLE OF FREQUENCY IN ENERGY MANAGEMENT

    4.1 Frequency is good and High and the state is overdrawing.

    4. 2 Frequency is good and High and the state is Underdrawing.

    4.3 Frequency is Low and the state is overdrawing.

    4.4 Frequency is Low and the state is Underdrawing.

    CHAPTER 5 DEVIATIONS FROM SCHEDULE

    5.1 Unscheduled Interchange (UI)

    5.2 UI rate determination

    5.3 Unscheduled Interchange (UI) Vs Marginal Cost.

    CHAPTER 6 A TRADING OPPORTUNITY UNDER THE SHADOW

    OF ENERGY MANAGEMENT

    6.1 Trading Opportunity to be Availed by the GENERATOR

    6.2 Trading Opportunity to be Availed by the BENEFICIARY

    CHAPTER 7 OPEN ACCESS , WHEELING AS AN IMPORTANT

    TOOL OF ENERGY MANAGEMENT .

    7.1 Open Access and Wheeling

    7.2 Issues Involved in the Transactions

    CHAPTER 8 POWER EXCHANGE IMPLEMENTATION

    IN INDIA

    8.1 Introduction

    8.2 Regulatory Framework for power exchange Implementation

    8.3 Power Exchange Implementation in India

    8.4 Functional Power Exchange

  • 7/30/2019 Major Report on Energy Mgt

    8/79

    8.5 Competition among Exchanges

    8.6 Information Exchange between NLDC and Power Exchanges

    8.7 Regulations governing the process of Energy Management

    SECTION -II

    ENERGY MANAGEMENT

    IN

    HPSEBL

    AS

    A SPECIAL CASE

    CHAPTER 1 STATUS OF SLDC in HPSEBL

    0 Setting up SLDC/SUB-LDCs in Himachal Pradesh

    1.2 Sub-LDC at Kunihar

    1.3 Sub-LDC at Hamirpur

    1.4 Interconnectivity of SLDCSUB-LDCs of H.P.

    CHAPTER 2 SLDC AN ESSENTIAL TOOL TO ENERGY

    MANAGEMENT

    2.1 Introduction

    2.2 OPGW and its Installation

    2.3 Testing of Optical Fiber Links.

    2.4 Monitoring of Status of OPGW

    2.5 PLCC System

    2.6 PABX System

  • 7/30/2019 Major Report on Energy Mgt

    9/79

    2.7 RTU (Remote Terminal Unit)

    2.8 UPS (Uninterrupted power supply)

    CHAPTER 3 ENERGY MANAGEMENT A "SPECIAL

    CASE" OF HIMACHAL PRADESH.

    3.1 Introduction

    3.2 Grid Diagram of Himachal Pradesh

    3.3 Modes for Managing Energy Deficits

    3.4 Description Of Different Modes of Energy Management

    3.5 HPSEBL Share in different Projects

    3.6 STATUS of Energy Managed from different sources in FY 2010-11

    3.7 STATUS of Energy Managed different sources in FY 2011-12

    Conclusion

    Future Scope

    References

  • 7/30/2019 Major Report on Energy Mgt

    10/79

    LIST OF TABLES

    Table No. Description Page

    No.

    1. HPSEBL Share in different Projects

    2. STATUS of Energy Managed in FY 2011-12

    3.STATUS of Energy Managed in FY 2012-13

  • 7/30/2019 Major Report on Energy Mgt

    11/79

    LIST OF FIGURES

    Fig. No. Description Page No.

    1. Hierarchical Structure of Load Dispatch Centres in Northern

    India.

    2. Relationship between UI rate and Grid Frequency

    3. Location of SLDC and Sub-LDCs in Himachal Pradesh

    4. Hierarchical Structure of SLDC & Sub- LDCs

    5. SUB-LDC KUNIHAR (Connectivity of RTUs)

    6. SUB-LDC HAMIRPUR (Connectivity of RTUs)

    7. Inter Connectivity Diagram Of SLDC , Sub -LDCs of H.P.

    8. Combined Connectivity Diagram

    9. OPGW (Optical Ground Wire)

    10. Types of Fibre Connectors.

    11. Test Diagram for Monitoring of Status of OPGW

    12. Map of Network Elements of Different Locations

    13. Connectivity Between RTU and SUB-LDC Kunihar &Solan

    14. PABX Room In SLDC Shimla

  • 7/30/2019 Major Report on Energy Mgt

    12/79

    15. Connectivity of PABX Exch. at SLDC with MDF& Console

    16. RTU at 132 KV substation Jutogh

    17. General Outlook of UPS

    18. About Status Of Himachal Pradesh

    19. Grid Diagram of Himachal Pradesh

    SECTION -I

    ROLE OF ENERGY MANAGEMENT

    IN

    POWER SYSTEM OPERATION

  • 7/30/2019 Major Report on Energy Mgt

    13/79

    CHAPTER 1 INTRODUCTION

    1.1 Vital Role of Energy Management

    Energy management is a vital issue in the present scenario when the system under

    integration mode runs under deficit or surplus conditions. The term energy management

    includes planning and operation of energy & its consumption. The application of energy

    management is well visualized when an organization receives energy from outside the state

    as well as from its own generation within the state. In the modern era, when the energy is

    available from renewable energy sources in the pure form and its disposal to the

    beneficiaries in the bundled form, uses intensive application of energy management

    methodologies.

    Although, many issues such as energy procurement, disposal, consumption, and itssaving falls under the preview of energy management but this comprehensive study mostly

    focuses on the energy management of bulk power procurement under different conditions

    such as through nuclear, hydro, thermal based stations, and from REC(Renewable Energy

    Certifications).

    Energy management study of this project focuses on the status of the states which

    have surplus power during summer and deficit power during winter months. Mostly, the

    snow fed states have less generation during winters and due to melting of snow during

  • 7/30/2019 Major Report on Energy Mgt

    14/79

    summer, have maximum flow of water in the rivers which ultimately attributes to enhanced

    generation during summers.

    Such states which have surplus power during summer months, their organizations

    tie up with the states which have deficit power in summer and provide assistance to these

    states to mitigate their shortages by either selling the power or making arrangement under

    banking which is one of the important aspects of energy management.

    Mostly, the organizations prefer disposal/procurement of power under banking

    arrangement as this being considered as cashless transaction. However, even under banking

    arrangements also, certain rates are kept so as to settle the accounts on account of

    unadjusted quantum, if any, by the end of banking cycle. This project shall mainly focus on

    the energy management methodologies being adopted by Himachal State for

    disposal/procurement of power under different modes.

    1.2 Basics of Energy Management

    Most of the states uses following modes for mitigating the shortages of power:

    1, By availing free power entitlement of their own states in Central sector / Joint

    sector projects .

    2. By availing equity power entitlement of their government if any.

    3. Through banking arrangements.

    4. Unscheduled Interchanges (Over Drawl) transactions under real time operation.

    5. Unallocated quota allotted by Govt. of India for deficit months.

    In the above stated arrangements, the power from Central Sector Projects is

    managed under the guidelines of CERC regulations. This power is initially made available

    at generator terminal and is wheeled through Power Grid system to make it available at HP

    periphery. Similarly, the free power entitlement of GoHP (Govt. of H.P.) is availed through

    traders appointed by the government for this purpose. The banking arrangement is made

    with different neighboring utilities. Many states also manages power deficits through

    perforce transactions, i.e. under UI (Unscheduled Interchange) arrangements.

    0 a. Central Sector Projects:

  • 7/30/2019 Major Report on Energy Mgt

    15/79

    Utilities receive power from central sector projects in proportion to their entitlement in

    line with guide lines as per CERC regulations. This power is made available at

    generator terminal of the respective projects and is wheeled through Power Grid

    system till it is made available at their respective periphery. The bills in respect of

    generator comprises two parts . One part is energy availed at generator terminal and

    the other part of the bill is raised by Power Grid on account of wheeling of power

    through their system up to the state periphery. The quantum of energy which reflects

    in a monthly bills is based on the Regional Energy account prepared by NRPC

    (Northern Regional Power Committee).

    1 b. Free power Entitlement:

    Every state has free power Entitlement in all those projects which have been

    commissioned in their respective territory . This entitlement is due to home state

    benefits on account of sacrificing its potential as well as water usage rights of the

    people of that state. In addition to above free power entitlement of the state , the utilities also

    avail equity power entitlements if any which is at the discretion of the respective governments

    and is given to the state as first right to mitigate the shortages during deficit months.

    c. Through Banking :

    Transaction / procurement of Power through Banking is also one of the modes which is

    considered as a cashless transaction and this energy exchange arrangement is on equal basis

    i.e. the obligation of the state to return the banked energy is restricted to the extent to which

    the energy has been banked with it during the deficit months. The average rate as agreed as per

    agreements (Unscheduled Interchange rates based on prevailing grid frequency conditions at

    that point of time) are kept to account for unadjusted quantum at the end of banking cycle.

    This arrangement facilitates when there is large variation in demand pattern during deficit

    months on account of fluctuating weather conditions and provides real time operation and

    increase or decrease of quantum with the mutual consent of both the parties without any

    financial implications on either party. With the above arrangement the surplus power available

    during the monsoon months is returned for meeting the previous year banking obligations as

    well as for Advance Banking (contra banking) arrangements.

    d. Unscheduled Interchange (UI):

    This does not fall under any category of mode of transaction of power, but under

  • 7/30/2019 Major Report on Energy Mgt

    16/79

    prevailing grid frequency conditions, power does flow perforce which also provides

    additional assistance to mitigate the instantaneous shortage of power. This perforce

    transaction of power is regulated as per CERC regulation on Unscheduled interchange

    of power issued by Central Electricity Regulatory Commission from time to time.

    However, the under drawl/over drawl of power should not exceed the specific limit or

    otherwise, the same shall lead to the collapsing of grid. It is also added that any

    violation through UI against the prescribed norms shall lead to penalty to the

    concerned utility.

    e. Transaction of power through energy exchange:

    In this mode of transaction of power, the surplus power available on day-ahead basis is

    disposed off through exchange on the available rates. Similarly through this mode,

    procurement of power is also carried out to meet the immediate demand of shortages.

    f. Sale/ purchase of power through Tendering process:

    In this mode of transaction, bids are invited from different utilities for their

    participation in the tendering process and the bidder who qualifies the desired terms

    and conditions is given order for supply of power.

    1.3 Constraints in Energy Management

    In the real time operation generally power system is encountered with

    situations which cannot be foreseen and tied up for sale/purchase arrangements due to

    unexpected variations in demand and supply position. This is more predominant in the case

    of states where on one hand load is dependent upon the weather conditions and on the other

    hand on own generation, which is purely hydro based through run of the river schemes,

    depends upon the inflows that can also not be very accurately predicted. Under such

    conditions the utilities have to rely upon their thermal power shares which are costlier than

    hydro power and affects the economy of the state.

    Some surplus power perforce, under real time operation gets transacted

    through Unscheduled Interchange mode (Under Drawl) and exporting utilities are paid for

    this unscheduled energy in accordance with the prevailing frequency conditions in the grid

    under UI mechanism.

  • 7/30/2019 Major Report on Energy Mgt

    17/79

    A part of energy assessed surplus on day a head basis (24 hrs) is sold through

    Energy Exchange on the best available rates which are more or less influenced by the

    frequency prevalent in the grid.

    ---------------X--------------------X-------------

    CHAPTER 2 SLDC AN ESSENTIAL TOOL TO ENERGY

    MANAGEMENT

    2.1 Introduction

    SLDCs (State Load Dispatch Center) have brought a revolution in the field of Energy

    management . In fact it has proved its worth in giving clear picture of day to day energy

    transactions. Communication System is considered as backbone of the SLDC which

    provides support to the SCADA system and plays a vital role to ensure interconnectivity of

    various control centres. The various modes of communication have given birth to SLDC

    centres and fulfilled many dreams which were impossible before the establishment of such

    centres. They have given us the following gifts:

    0 Created Grid Discipline.

    1 Improved voltage profile and frequency.

    2 Reduced frequent Grid failures.

    3 Optimum utilization of available resources.

    4 Visualization of real time availability of data/ events occurrence.

    Efficient Power System Operation & Load Management.

    Reduced gap in Demand - Supply position (Better regulation).

    Better voltages at Consumer end.

    Low per Unit cost.

    In fact the above stated gifts have given wide opening to a very important aspect i.e energy

    management in an efficient manners. The energy management is an ultimate goal for an

    electrical utility which could be achieved effectively with the birth of SLDC. Thus SLDC

  • 7/30/2019 Major Report on Energy Mgt

    18/79

    has made possible all kinds of developments in the field of power system such as

    development of trading market, power exchange , effectiveness in power transactions

    through different modes.

    Application of SLDC/NRLDC made possible , quick restoration of

    the system during transaction of power, when there is a chance thatthe system may have

    to face instability which ultimately leads to collapsing of the grid owing to over drawl by

    some utilities under low frequency conditions attributing to grid indiscipline and violation

    of regulations.

    2.2 Load Despatch Centres in Northern India

    As per the decision of Govt. of India it became mandatory to set Regional Load DespatchCenters and State Load Despatch centres alongwith Sub-Load Despatch Centres with

    ultimate aim of National Grid.

    In compliance to above orders of Govt. of India, under ULDC scheme (Unified load

    Despatch Centre), all the states established SLDCs as well as SUB-LDCs in line with terms

    and conditions of MOU(Memorandum of Understanding) signed between the all concerned

    utilities which are as under:

    5 Regional Despatch Centre at Delhi

    6 SLDC at HPSEBL Shimla

    7 SLDC at HVPNL Panipat

    8 SLDC at UPPCL Lucknow

    9 SLDC at DTL Delhi

    10 SLDC at BBMB Chandigarh

    11 SLDC at PSPCL Patiala

    12 SLDC at RSEB Rajasthan

    13 SLDC at JKPPD Gladni

    With the increasing demand and utilization of electricity, an electrical

    engineer should be well versed or at least acquainted with the various

  • 7/30/2019 Major Report on Energy Mgt

    19/79

    aspects of generation, transmission and distribution of electricity, and at

    the same time must be capable of analysing energy management

    aspects. The introduction of SLDC units in the states have made

    it possible to ascertain the eventualities in an effective mannerand has given a wide opening for energy management as a tool.

    In this scenario of integrated system it has become essential to

    have SLDC unit in every state of the country which provides

    economical despatch and regulation of power.This system uses an

    application of optical fibre ground wire as a mode of communication ,

    PLCC system, SCADA system. Above all, UPS also plays an important

    role to provide uninterrupted power supply to the power system and

    ensures reliable system. The installation technique of fibre optics is

    critical one in the commissioning process. The special connectors and

    techniques are used for joining fibres. The tool used for splicing purpose

    is special one. That instrument is known as splicer

    In the Northern Region , SLDCs have been established in the following hierarchi andeach SLDC unit collects data from remote with the help of RTUs (Remote Terminal

    Unit) . To facilitate effictive collection of data , each SLDC is further classified into Sub -

    LDCs.

    The hierarchical structure of above stated units is as shown in the fig below :

  • 7/30/2019 Major Report on Energy Mgt

    20/79

    Fig. 1 Hierarchical structure of Load Dispatch Centres in Northern India

    2.3 Real Time Dynamic Security Assessment

    The Electrical Grid changes constantly with generation plants frequently coming online or

    off-line as required to meet electrical demand. In state of the art electric utility control

    centres, grid operators use energy management systems (EMS) to perform network and

    load monitoring. Limits to flows and voltages are assigned on the basis of transmission line

    thermal limits and off load studies of voltage and transient dynamic stability. Theassumptions that the grid power flows settle down to steady state condition is reexamined

  • 7/30/2019 Major Report on Energy Mgt

    21/79

    in real time as the transmission grid conditions change in real time. In real time operation it

    becomes essential to watch grid discipline under dynamic conditions. A software

    designated as Dynamic Security Assessment is used to simulate the impact of the potential

    of electric fault conditions and grid disturbances.

    The SLDCs (Load Dispatch Centres) have made it possible to run

    such models attributing to dynamic grid security and hence, contributed maximum towards

    grid discipline under real time operations. All these functions perform effectively after the

    establishment of SLDCs. These load despatch centres have given birth to power exchange

    and development of power trading market .

    With grid frequency point of view , any action taken by SLDC shall

    depend on the grid frequency. This action is initiated by SLDC only when there is a

    change in the system status i.e tripping of generating station . A load crash within the state

    or a frequency change due to imbalance in load- generation.

    CHAPTER 3 AVAILABILITY BASED TARIFF (ABT)

    3.1 Introduction

  • 7/30/2019 Major Report on Energy Mgt

    22/79

    The term Availability Tariff stand for a tariff structure for power spply from generating

    stations on contracted basis . The power plants have fixed and variable cost . The fixed cost

    elements are interest on loans , return on equity , depreciation , O&M expenses ,

    insurance , taxes and interest on working capital. The variable cost comprises of the fuel

    cost i.e coal and oil in case of thermal plants and nuclear fuel in case of nuclear plants . In

    the availability based tariff mechanism , the fixed and variable cost components are treated

    separately . The payment of fixed cost to generating stations is linked to a availability of

    the plant , i.e its capability to deliver MWs on a day - by- day basis. The total amount

    payable to the generating company over a year towards the fixed cost would depend on the

    average availability of the plant over the year.In case the average actually achieved over the

    year is higher than the specified norm for the plant availability , the generating company

    would get a higher payment . In case the average actually achieved over the year is lower

    than the specified norm for the plant availability , the generating company would get a less

    payment . Hence, name Availability Tariff. This is first component of Availability Tariff

    and is termed as capacity charges.

    The second component of ABT is the energy charge and this would

    comprise of variable cost of power plant for generating energy as per the given schedule.

    The third component attributes towards payment for deviations from

    schedule at a rate dependent on system conditions.

    Initially, ABT was made applicable only to the central generating stations

    which were having more than one beneficiary. But with its application, Central Electricity

    Regulatory Commission (CERC), found its suitability towards quality improvement of

    power and thought of its expansion to cover even Intrastate systems as well as. ABT has

    shown improvement towards following disruptive trends in power sector:

    a. Rapid and high frequency deviations causing damage and disruption to large scale

    indusrial consumers.

    b. Frequent grid disturbances resulting in generators tripping, power outages and

    power grid disintegration.

    3.2 Details about ABT

    Availability for the purpose of ABT means the readiness of the generating stations to

  • 7/30/2019 Major Report on Energy Mgt

    23/79

    deliver ex-bus output expressed as % of its related output capability as per rated capacity.

    Availability of thermal generating station for any period shall be the percentage ratio of

    average Sent Out Capability for all the time blocks during that period and rated Sent Out

    Capability of the generating station.

    Availability based tariff includes :

    a. CAPACITY CHARGES

    a function of the Ex- bus MW availability of power plant for the day

    b. ENERGY CHARGES

    MWh for the day as per ex- bus drawal schedule for the utility.

    c. ADJUSTMENT FOR DEVIATIONS (UI Charges)

    (Actual energy interchange in a 15 min time block- scheduled energy Interchange

    for the same time block) x UI rate for that time block.

    Total payment for the day = a + b (+/-) c

    3.3 Scheduling

    3.3.1 Introduction

    The following procedure is adopted for scheduling:

    0 Each day of 24 hrs starting from 00.00hrs is divided into 96 time

    blocks of 15 minutes each.

    1 The generating stations make advance declaration of their capacities for

    generation in terms of MWh delivery of power for each time block of the next

    day.

    0 While declaring capability , the generator should ensure that the

    capability during peak hours should not be less than that during other

    hours.

    1 Based upon such declaration , the Regional Load Dispatch Centre

  • 7/30/2019 Major Report on Energy Mgt

    24/79

    (RLDC) shall communicate to the various beneficiaries their respective

    shares of the available capability.

    2 After the beneficiaries give their requisition for power based on the

    generation schedules , the RLDC shall prepare the generation schedules

    and drawl schedules for each time block after taking into account

    technical limitations and transmission constraints.

    3 The schedule of actual generation is quantified on ex- bus basis ,

    whereas for beneficiaries , scheduled drawls shall be quantified at their

    receiving points.

    4 For calculating the drawal schedule for beneficiaries , the

    transmission losses shall be apportioned in proportion to their drawls. In

    case of any forced outage of the unit, or in case of any transmission

    bottleneck , RLDC will revise the schedules. The revised schedules shall

    become effective from the 4th time block, counting the time block in

    which the revision is advised by the generator, to be te 1 st one.

    3. 3.2 Day Ahead Scheduling

    10 A.M - Central Generating stations advise foreseen plant-wise ex-

    bus MW, MWh availability for next day.

    11 AM - RLDC advises SEBs their MW , MWh shares in the foreseen availability

    of central plants.

    3 PM - SLDCs furnish their time-wise MW requisition from the above, and

    schedule of bilateral exchanges, if any.

    5PM - RLDC complies these and issues generation schedules for central plants

    and drawl schedules for SEBs, for the next day starting at midnight.

    10 PM - Revision of the above, if required , by any new development during the

    day.

    11 PM - Schedules frozen for the next day.

    3.4 Features of ABT

  • 7/30/2019 Major Report on Energy Mgt

    25/79

    The availability based tariff has the following features.

    0 It brings about enhanced grid discipline.

    0 Economically viable power with right pricing.

    1 Encourages usage of Merit Order Dispatch / Economic Dispatch in India.

    2 It helps in addressing grid disturbance issues

    1 It helps observing any kind of gaming and avoiding the same.

    2 It requires special meters , remote metering and communication

    mechanisms to facilitate reading of the meters in time.

    3 Facilitates addressing regularity assets.

    4 It acts as an interface with various stakeholders to enable

    implementation and benefits to all.

  • 7/30/2019 Major Report on Energy Mgt

    26/79

    CHAPTER 4 ROLE OF FREQUENCY IN ENERGY

    MANAGEMENT

    4.1 Frequency is good or high and the state is Overdrawing.

    - No Problem and No. Action Required-

    However for enhanced Optimization may resort to following :

    i. Reduce own generation to the extent possible and increase overdrawal so long as

    frequency is above 49.8 Hz.

    ii. Restore consumer load that had been shed, provided Tariff/ Realization rate is higherthan current UI rate.

    iii. Increase, CGS requisition , if some part of the entitlements had not been requisitioned

    earlier.

    4.2 Frequency is good or High and the state is Underdrawing.

    Action required is as under:

    i. Reduce own generation to the extent possible , if the frequency is above about 49.8 Hz.

    ii. Restore consumer load that had been shed, and reduce under-drawn

    iii. Reduce CGS requisition, provided the previous two actions have been taken and the

    frequency continues to be above 50.2 Hz, bialateral sale to the needy neighbour can be

    tried.

    4. 3 Frequency is Low , and the state is Overdrawing.

    Action required is as under:

    i Increase own generation to the maximum possible extent.

    ii. Curtail consumer load . Load shedding to be graded balancing between UI price and

    consumer category .

    iii. Increase CGS requisition to full entitlement( If not requisitioned fully earlier ) and

  • 7/30/2019 Major Report on Energy Mgt

    27/79

    arrange for bilateral purchase from another SEB/CGS.

    4.4 Frequency is Low and the state is Underdrawing.

    i. Increase own generation to the extent possible, provided the frequency is belowabout 49.5 Hz (comparing variable cost with current UI price).

    ii. Curtail consumer load, by shedding low priority load (provided UI earning for the

    SEB justifies such load shedding). This is totally optional, and helps the grid.

    iii. Increase C GS requisition to full entitlement ( if not requisitioned fully earlier) and

    earn UI or sell the surplus through a bilateral agreement)

    The above scenarios shows that action to be taken for managing energy turbulences

    depends upon the prevailing frequency and is independent of whether over-drawing or

    underdrawing .

    CHAPTER 5 DEVIATIONS FROM SCHEDULE

  • 7/30/2019 Major Report on Energy Mgt

    28/79

    5.1 Unscheduled Interchange (UI)

    The energy actually supplied by the generator may differ from what was scheduled . If the

    actual energy supplied were higher than scheduled , the generating station would be

    entitled to receive a payment for excess energy (deviation from schedule, termed as

    Unscheduled Interchange(UI) ) at a rate dependent on frequency at that time. I f the energy

    actually supplied is less than what is scheduled , the generating station shall have to pay

    back for the energy shortfall, at the same frequency .

    The relationship between the above UI rate and grid frequency for

    interstate system is specified by CERC. The relationship between n UI and Frequency is as

    shown in the fig. below.

    Fig. 2. Relationship between UI rate and Grid Frequency

    48.8 49 49.2 49.4 49.6 49.8 50

    50.2 50.4 50.6

    Frequency (Hz)

    600

    400

    200

    0UIRate(P

    aisa

    /kWh)

  • 7/30/2019 Major Report on Energy Mgt

    29/79

    It is seen from the above figure that when the frequency is 50.5 Hz or higher , the UI rate is

    zero , which means that the generating station would not get any payment for the extra

    energy supplied . It would burn fuel for producing this extra energy , but would not get any

    payment for it.If the actual energy supplied were less than scheduled energy , the

    generating station would still be paid for the scheduled energy (at its energy charge rate )

    without having to pay back anything for the energy shortfall. I t would thus be able to save

    on fuel cost ( for the energy not generated) and retain the energy charge as net saving .

    There is thus a strong commercial incentive to back down generating during high

    frequency situations .

    On the other hand , when frequency goes down, the UI rate ( for both

    over supply and under supply ) goes up like anything and touches the level of Rs. 5.7 per

    unit at frequency of 49.0 Hz. At a frequency of 49.5 Hz , the UI rate is Rs. 3.45 per unit.

    For any short fall , the generating station shall have to pay back at the same rate . It would

    thus have a strong commercial incentive to maximize its generation during periods of such

    low frequency.

    A similar scheme operates for the States ( beneficiaries) as well. Any

    state drawing power in excess of its schedule has to pay for the excess energy at the same

    frequency - dependent rate. The high UI rate during low frequency conditions would

    induce all states to reduce their drawal from the grid, by maxamizing their own generation

    and / or by curtailing their consumer load. If a state draws less power than scheduled , it

    payus for scheduled energy quantum at the normal rate and gets paid back for energy not

    drawn at a much higher UI rate . On the other hand , during high- frequency conditions , a

    state draw extra power at a low rate and is thus encouraged to back down its own costlier

    generating stations . An under-drawal during high- frequency conditions means that the

    state pays for the scheduled power quantum unnecessarily. It should either reduce its

    schedule or increase its drawal.

    5.2 UI rate determination

    For the purpose of determination of UI rate , the energy is metered in 15 - minute time

    blocks, since frequency keeps on changing and subsequent UI rate . The metered energy is

    compared with the scheduled energy for that 15- minute time block and the difference (+

    or -) becomes the UI energy . The corresponding UI rate is determined by taking the

  • 7/30/2019 Major Report on Energy Mgt

    30/79

    average frequency for the same 15- minute time block into account.

    For each Central generating station and state , the actual energy has

    to be metered on a net basis , i.e algebraic sum of energy metered on all its peripheral

    interconnection points for every 15- minute time block. All UI payments are made into and

    from a regional UI pool account, operated by the concerned RLDC.

    5.3 Unscheduled Interchange (UI) Vs Marginal Cost.

    UI rate is tightly linked to grid frequency. As the frequency is same all over an A.C.

    system and can be readily seen through a simple frequency meter , it is easily possible to

    know the prevailing UI rates anywhere in the system . With this on line knowledge of the

    current UI rate , a state would know what it would have to pay for an extra MW that it

    may draw from the regional . It can readily compare this with the fuel cost it would save if

    generation were reduced by one MW at its own station, having the highest variable cost. If

    the UI ratre is lower than the latter, it would be beneficial; for the state to reduce its own

    generation and draw the replacement energy from the regional grid, till it has backed down

    all generation having a variable cost higher than the current UI rate . In the process state's

    marginal generation cost would move down, towards the prevailing UI rate.

    Meanwhile, other states too would take a similar action in the same time

    frame and total generation in the system would come down, resulting in a downward

    movement of frequency and an upward movement of UI rate , till the attainment of a state

    of equilibrium wherein the marginal generation cost of every state would become equal to

    the UI rate.

    On the other hand , if a state finds the UI rate to be higher than the variable

    cost of any of its partly loaded generating units at any time , it would be financiallybeneficial for the state to maximize the output of all such generating units and thereby

    reduce its drawal from the regional grid. The state would have an under- drawal, for which

    it would get paid a UI rate higher than its marginal generation cost.

    With similar action being taken by other states as well, the frequency would

    tend to rise and UI rate would decline correspondingly, till equilibrium is reached wherein

    the marginal generation cost of every state would equal the UI rate.

    CHAPTER 6 A TRADING OPPORTUNITY UNDER THE

  • 7/30/2019 Major Report on Energy Mgt

    31/79

    SHADOW OF ENERGY MANAGEMENT

    Let us refer fig. Given below. The two areas marked 'X' represent the off peak hour

    capability of the central generating station , which State-C has not requisitioned, although

    within its entitlement . The trading opportunities can be encashed both by the Generator as

    well as Beneficiary , which are as under:

    6.1 Trading Opportunity to be Availed by the GENERATOR

    The capability (160MW) is now available with the Central Station and it has three options

    before it ,which are as follows:

    I. Back down the station during off peak hpurs,. I.e. Generate power onlyaccording to the schedule given by RLDC by aggregating the rerusition of the

    three states.In this case , the station gets capacity charge for the day corresponding

    to its availability declaration (900 MW) and energy charge to fully recover its fuel

    cost for generating the scheduled quantum of energy during the day.

    II. Find a buyer ( other than State -C) for the above off - peak surplus and generate

    power adding the MW agreed to be taken by this buyer to the aggregate schedule

    for states - A,B and C. A s the station is already being paid capacity charges for

    900 MW, it may not be too particular about further fixed cost recovery. As long as

    the energy agreed upon is higher than the fuel cost per KWh of the station , it

    would be beneficial for the station to enter into such a deal. I t would also reduce

    the technical problems associated with backing down of the station and improve

    the station's efficiency.

    III. Instead of selling the off- peak surplus power through a bilateral agreement as

    described above , the station may accept the schedule given by RLDC, but

    generate power to its full capability of 900 MW even during off peak hours .The

    result would be an over supply of 160 MW ( as a deviation from schedule) , for

    which the station would get paid from the regional UI pool account at the

    prevailing UI rate. In fact , it would be a stale to the regional pool and would

    make a financial sense as long as the prevailing UI rate is higher than the fuel cost

    per KWh of the station.

    6.2 Trading Opportunity to be Availed by the BENEFICIARY

  • 7/30/2019 Major Report on Energy Mgt

    32/79

    The above options for the generating stations arise only in case a state has not requisitioned

    its full entitlement . In fact, the same three options are available to State -C , before they

    get passed on to the Central station and are as follows:

    i. Requisition power from the Central station only as per its own requirement and

    draw power as per the resulting schedule.

    ii. Requisition full entitlement from the Central station for the entire 24- hour period,

    find a buyer for the off peak surplus and schedule a bilateral sale. This would

    make sense as long as the sale rate per kWh is more than the energy charge rate of

    the Central station.

    iii. Requisition the full entitlement for the entire 24 - hour period , but draw power

    only according to its actual requirement. In fact , this would be a pre-planned

    deviation from schedule for which State - C would get UI payment. A ll that State

    - C has to watch for and be vigilant about is that UI rate during the off- peak hours

    remains above the energy charge rate of the Central Station . In case the

    frequency rises and UI rate falls below the energy charge rate of the concerned

    Central station , State -C shuld reduce its requistion and thereby stop under -

    drawing.

    The above methodology for trading shows that under the Energy Management regime

    there are equal opportunities both for Generator as well as Beneficiaries.

    CHAPTER 7 OPEN ACCESS , WHEELING AS AN

  • 7/30/2019 Major Report on Energy Mgt

    33/79

    IMPORTANT TOOL OF ENERGY MANAGEMENT .

    7.1 Open Accessand Wheeling

    Open Access and Wheeling are supposed to be one of the important tools as far as

    Interstate trading is concerned.Without these components , it is not possible to go in for

    trading between the two utilities . The following reasons attribute to the necessity of such

    tools formanaging energy in Interstate trading:

    1. When utility 'A' trades power to utility 'B' and both are at different places, then

    Utility A has to take open access from the utility whose system shall be used by A

    to make the power available at the periphery of B and for such open access , A has

    to pay Wheeling charges to the owner whose system A is using.

    2. Without this arrangement , the transactions of power so made shall lead to

    litigations as there is a chance for many disputes to arise.

    OPEN ACCESS and WHEELING generally involve two parties , One supplying a certain

    quantum of power to the other through the regional / state grid. Any such transactions

    involves a number of parties and disputes could arise in scheduling , energy accounting and

    commercial settlement , unless an appropriate framework is in place.

    Let us take a case where party A has contracted to supply 10 MW round the

    clock to party B at a certain price. Party A has to transact that power through regional Grid

    system to make that power available at the periphery ofparty B . Since , the losses in the

    system are expected to the tune of .5 MW , A has to bear these losses also as per contract to

    supply power at the periphery of B. In such a deal A shall bear expenditure of loss as well as

    pay wheeling charges to the regional grid system so as to settle the transaction without

    litigation.

    A contracted sale or purchase involves the following:

    Identification of counterpart

    Agreeing on power quantum, duration, price and other terms

    Ascertaining the adequacy of transmission system

    Payment of applicable transmission / wheeling charges and absorption of

  • 7/30/2019 Major Report on Energy Mgt

    34/79

    wheeling losses

    Day ahead scheduling through SLDC/RLDC concerned.

    Payment security for transaction.

    An agreement is also executed between both the parties which ensures commitment by both

    the parties to ensure transaction of power as per terms and conditions of the agreement

    without litigation.

    7.2 Issues Involved in the Transactions

    There may be certain constraints in supplying powers which are as under:

    There may be a chance that a seller fails to schedule the supply of the agreed

    quantum of power due to short fall in its own power availability or the buyer fails to

    schedule the drawal of the agreed quantum of power due to fall in its requirement , it

    will mean a contractual default . The agreement between the parties must specify as

    to how much defaults can be handled .

    Another issue would be as to how a party selected its counterpart and agreed on the

    price and whether these have been done judiciously.

    Required checks and balances may even delay the finalization of agreement and

    trading opportunities may be missed.

    Regarding settlement of above issues one may adopt the route of

    UI , but it may lead to other complications as there is no certainty of the price and further

    RLDC may ask to curtail the supply due to transmission constraint. However, it has the major

    advantage such as there is no commitment about the quantum. A lso no question can be raisedon price from audit angle. Thus UI rate provides an alternative to "Open Access" and

    "Wheeling" and can be taken when one prefers flexibility over certainty .

  • 7/30/2019 Major Report on Energy Mgt

    35/79

    CHAPTER 8 POWER EXCHANGE IMPLEMENTATION

    IN INDIA

    8.1 Introduction

    In line with the mandate provided by the Indian Electricity Act 2003 and the National

    Electricity Policy , the Central Electricity Regulatory Commission (CERC) has issued a

    number of Regulations to facilitate trading and introduction of competition in the

    Electricity Sector in the country . Open Access in inter-state transmission was introduced

    in May 2004 which facilitated the development of the bilateral market in the country.

    The responsibility for the development of the Electricity Market in the country has beenentrusted to the Appropriate commission as per electricity act 2003 . The Indian electricity

    grid code was introduced in Feb 2000 with subsequent revision in April,2006 and the

    settlement system was introduced in 2002-2003 . The ABT mechanism provided the

    framework for scheduling and handling of imbalances . These two building blocks together

    provided the basic rules for system operation and the commercial settlement . Open Access

    in interstate transmission was introduced in May 2004 and gave birth to bilateral market in

    the country. On the basis of such developments , CERC issued guidelines for

    establishment of Power Exchange in Feb 2007 and in principal approval ws granted to the

    first Power Exchange in August 2007.

    8.2 Regulatory Framework for power exchange Implementation

    The Open Access in the Interstate Transmission Regulations 2004 provided only for the

    bilateral Transactions and the system of application of transmission charges was in Rs. /

    MW/Day. These methodologies for transmission charges & Losses were not conductive to

    the operation of a common platform for electricity trading i.e power Exchange operations.

    So necessary amendments in the regulation was required for implementation of Power

    Exchange . Accordingly, the regulation s for Open Access in Interstate Transmission were

    revised by CERC to include Collective Transactions Discovered on a Power Exchange and

    anew regulation became effective fro 1st April 2008. So , the CERC Open Access

    Regulations , 2008 made the following provisions :

    a . Transactions were categorized as Bilateral and Collective ( through PowerExchange)

  • 7/30/2019 Major Report on Energy Mgt

    36/79

    b. Nodal Agency for two types of transactions was identified. National Load

    Despatch Centre (NLDC) was designated as nodal agency for Collective

    Transactions . The Regional Load Despatch Centres (RLDC) were the

    designated agencies for bilateral transactions.

    c. Transmission losses were applied at both the points of injection and drawal .

    The sellers are required to inject more and the buyers draw less than the

    traded quantum to compensate for losses.

    d. Regulations placed great emphasis on the empowerment of the SLDCs. NOC/

    Standing clearance was required to be obtatined by State Utilities / Intra - State

    Entities from the SLDC. The SLDCs are obliged to respond within 3 days to

    any request for an NOC as per the regulations. The SLDC may charge an

    appropriate fee for such NOC/ Standing Clearance .

    e. T he methodology of application of transmission charges moved from 'Contract

    Path' to a methodology closer to the 'Point of Connection' Charges ' for

    collective transaction.

    f. Operating charges for collective transactions @ Rs. 5000 per day per entity

    involved are applied. All buyers within a state are clubbed together into one

    group and all sellers within a state are clubbed together into another group by

    the power exchange . Each group of buyers and sellers is counted as a separate

    entity for scheduling and leavy of operating Charges.

    8.3 Power Exchange Implementation in India

    The power exchange in India has many features such as Voluntary participation, Day ahead

    transactions , Physical delivery of Energy , Double sided bidding , Hourly bids ,

    Uniform pricing , Multiple Exchanges envisaged and Congestion Management .

    8.4 Functional Power Exchange

    Indian Energy Exchange ( IEX ) , the country's first power exchange , made an application

    for grant of permission to setup a Power Exchange in March 2007 and an in- principle

    approval was accorded by the CERC on 31st August 2007 . IEX commenced operation

    from the 27th June 2008 after the Rules and Bye Laws were approved by CERC and

  • 7/30/2019 Major Report on Energy Mgt

    37/79

    permission was granted to commence operations . The second Power Exchange of India

    (PXIL) was granted in- principle approval on 27th May 2008 . PXIL went through a

    process of Regulatory approval similar to that of it's predecessor and it commenced

    operations on 22nd October 2008.

    8.5 Competition among Exchanges

    The Regulators have provided for multiple Power Exchanges to exist simultaneously in one

    physical market . Light handed regulation has been adopted and the Power Exchanges have

    been given full functional autonomy. This allows for competition amongst the existing

    Power Exchanges and an automatic system of checks and balances .The charges collected

    by the power exchanges for the services rendered are automatically regulated by the market

    forces.

    8.6 Information Exchange between NLDC and Power Exchanges

    The exchange of information is fully automated between NLDC and Power Exchanges ,

    NLDC and the Regional Load Dispatch centers (RLDCs) . The bidding window for

    submission of bids in the Power Exchange is from 1000 Hrs. to 1200 Hrs. Information is

    exchanged between NLDC , Power Exchange and the RLDC as per a protocol defined in

    the procedure for Scheduling of collective Transactions . A provisional solution is given by

    the Power Exchanges to the NLDC at 1300 Hrs for congestion if any. In case of

    congestion , NLDC advises the Power Exchanges about the limits of scheduling . The

    Power Exchange submits the application for scheduling of collective Transactions by

    1500Hrs and the approval for scheduling is communicated by NLDC by 1730 Hrs.

    8.7 Regulations governing the process of Energy Management

    The following regulations/codes govern the process of procurement o/ disposal of power:

    0 Central Electricity Regulatory Commission (Unscheduled Interchange

    charges and related matters) Regulations, 2012.

    1 Central Electricity Regulatory Commission (Indian Electricity Grid Code

    Regulations, 2012.

    2 Central Electricity Regulatory Commission (Sharing of inter-StateTransmission Charges and Losses) (Second Amendment) Regulations, 2012.

  • 7/30/2019 Major Report on Energy Mgt

    38/79

    3 CERC(Terms and Conditions for Tariff determination from Renewable

    Energy Sources) Regulations, 2012.

    4 Indian Electricity Grid Code Regulations, 2010

    5 Terms and Conditions of Tariff, Regulations for 2009-14

  • 7/30/2019 Major Report on Energy Mgt

    39/79

    SECTION -II

    ENERGY MANAGEMENT

    HPSEBL

    AS

    A SPECIAL CASE

  • 7/30/2019 Major Report on Energy Mgt

    40/79

    CHAPTER 1 STATUS OF SLDC IN HPSEBL

    1.1 Setting up SLDC/SUB-LDCs in Himachal Pradesh

    In compliance to the decision of Govt. of India, HPSEBL under ULDC Scheme, incoordination with PGCIL established a State Load Despatch & Communication Centre

    (SLDC) at Shimla and 1No. Sub-LDC at Kunihar and 1No. Sub-LDC at Hamirpur with

    RTUs at different locations.

  • 7/30/2019 Major Report on Energy Mgt

    41/79

    Fig 3. Location of SLDC and Sub-LDCs in Himachal Pradesh

    The hierarchical structure of SLDCs and Sub-LDC is also given in the fig. below which

    presents the load centers in Himachal Pradesh alongwith the location of their respective

    RTUs (Remote Terminal Units) situated at different locations . These RTUs are mostly

    connected to their Sub-LDCs through Power Line Carrier Communication System and

    further to SLDC through wideband system.

  • 7/30/2019 Major Report on Energy Mgt

    42/79

    Fig.4 Hierarchical Structure of SLDC & Sub- LDCs

    1.2 Sub-LDC at Kunihar

    It comprises 8 No. RTUs(Remote Terminal Units) installed at different locations inthe upper reaches of Himachal Pradesh :

    0 Kunihar

    1 Bhaba

    2 Jeori

    3 Giri

    4 Andhra

    5 Solan

    6 Jutogh

    7 Baddi

    The connectivity of the above stated RTUs is as shown in the fig. below. The RTUs are

    connected to SUB-LDC Kunihar through PLCC link. Each RTU is provided with a modem

    which converts digital signal into analog signal. The analog signal, thus transmits through

    PLCC system upto SUB-LDC. After reaching SUB-LDC, again the signal is converted into

    digital signal with the help of modem which are placed in the equipment called

    CFE(communication front end). The signal after its conversion to digital form, enters theMUX placed in the control room of SUB-LDC where it gets multiplexed and enters

    OLTE(optical line terminal equipment) where the digital/electrical signal is converted into

    optical signal and transmits through OPGW(optical ground wire) and reaches SLDC Jutogh

    where the signal again enters OLTE at Jutogh at the rate of 155 mbps as an optical signal

    and further enters MUX as digital/electrical signal at the rate of 2 mbps and gets

    demultiplexed when it comes out from the MUX .Here the signal gets divided into two

    parts. First part is a signal of 64kbps which enters the exchange through MDF(main

    distribution frame) and facilitates speech, whereas the second part of the signal is of 19.2

    kbps which enters the HUB of control room at Jutogh as data signal and is processed with

    the help of SCADA system.

  • 7/30/2019 Major Report on Energy Mgt

    43/79

    Fig.5 SUB-LDC KUNIHAR (Connectivity of RTUs)

  • 7/30/2019 Major Report on Energy Mgt

    44/79

    1.3 Sub-LDC at Hamirpur

    It comprises 10 No. RTUs(Remote Terminal Units) installed at different locationsin the upper reaches of Himachal Pradesh :

    8 Hamirpur-I

    9 Hamirpur-II

    10 Dera

    11 Kangra

    12 Malana

    13 Jassore

    14 Bassi

    15 Mandi

    16 Kangoo

    17 Largi

    The connectivity of the above stated RTUs is as shown in the fig. below. All RTUs are

    connected to SUB-LDC Hamirpur through PLCC link except Kangoo which is connected

    through wideband link. Each RTU is provided with a modem which converts digital signal

    into analog signal. The analog signal, thus transmits through PLCC system upto SUB-

    LDC. After reaching SUB-LDC, again the signal is converted into digital signal with the

    help of modem which are placed in the equipment called CFE(communication front end).

    The signal after its conversion to digital form, enters the MUX placed in the control room

    of SUB-LDC where it gets multiplexed and enters OLTE(optical line terminal equipment)

    where the digital/electrical signal is converted into optical signal and transmits through

    OPGW(optical ground wire) and reaches SLDC Jutogh where the signal again enters

    OLTE at Jutogh at the rate of 155 mbps as an optical signal and further enters MUX as

    digital/electrical signal at the rate of 2 mbps and gets demultiplexed when it comes out

    from the MUX .Here the signal gets divided into two parts. First part is a signal of 64kbps

    which enters the exchange through MDF(main distribution frame) and facilitates speech,

    whereas the second part of the signal is of 19.2 kbps which enters the HUB of control room

    at Jutogh as data signal and is processed with the help of SCADA system.

  • 7/30/2019 Major Report on Energy Mgt

    45/79

  • 7/30/2019 Major Report on Energy Mgt

    46/79

    Fig.6SUB-LDC HAMIRPUR (Connectivity of RTUs)

  • 7/30/2019 Major Report on Energy Mgt

    47/79

    1.4 Interconnectivity of SLDC & SUB-LDCs of H.P.

    Fig.7 INTER CONNECTIVITY DIAGRAM OF SLDC -

    SUB-LDCs OF H.P.

    The above diagram shows interconnectivity of SLDC Shimla with SUB-LDC Hamirpur

    and Kunihar. The data from Hamirpur reaches Kunihar on wideband system through

    OPGW where it combines with data of SUB-LDC Kunihar and a combined data packet

    reaches Jutogh through wideband system through OPGW and is processed in the control

    room at Jutogh separately. Then afterwards,again a combined data packet comprising data

    of SLDC Jutogh, SUB-LDC Hamirpur and SUB-LDC Kunihar takes its way to NRLDC on

    OPGW through wideband system.

    The combined connectivity diagram showing combined connectivity of both the

    SUB-LDCs alongwith SLDC and RTUs of respective SUB-LDCs is as shown in the figbelow.

  • 7/30/2019 Major Report on Energy Mgt

    48/79

    The figure shows the connectivity between RTUs and SUB-LDCs on

    PLCC system and between SUB-LDCs and SLDC on wideband through OPGW. The

    connectivity of Kangoo substation is on wideband system. The communication through

    wideband system has been experienced to be more reliable than through other mode of

    system. In the existing SUB-LDCs, there is enough provision for future expansion. Thesystem will prove its worth when atomization shall come into existence.

    Fig.8 COMBINED CONNECTIVITY DIAGRAM

    CHAPTER2 BACKBONE TO COMMUNICATION

  • 7/30/2019 Major Report on Energy Mgt

    49/79

    SYSTEMAT SLDC SHIMLA

    2.1 Introduction

    In the absence of certain tools, communication system standsnowhere. These tools act as backbone to the system and assists the system in all respects.

    These are as under:

    0 OPGW (Optical Ground Wire) and its Installation

    1 PLCC System

    2 PABX System

    3 RTU

    4 UPS

    The details are as under:

    2.2 OPGW and its Installation

    OPGW provides overhead telecommunication system.

    Fig.9 OPGW (Optical Ground Wire)

    The central part of this cable is composed by a dielectric optical core comprising six fibres

    stranded around a central support. An aluminium tube is extruded around this optical core

    and the cable is finished with one or two layers of an aluminium clad steel. Tight Buffered

    Optical Fibre (multi mode)

    50 m Core

    125 m

    Optical Cladding

    250 m

    Primary Coating

    50 m Core

    Guided Light Propagation

    Glas

    Plastic

  • 7/30/2019 Major Report on Energy Mgt

    50/79

    cable is used for cable routing within buildings. Typically containing around 16 fibres (12

    cores, 4 cores and 8 cores are also common) this type of cable offers ease of installation

    and fibre protection suitable for internal use. each of the fibres within the cable is

    individually protected by a plastic coating with kevlar strengthening and sheathing giving

    overall protection. Low Smoke Zero Halogen Sheaths are common in this type of cable. To

    withstand harsher external conditions Loose Tube cables are used for outside installations

    in duct work or trenches. As the name suggests groups of fibres are suspended in a gel

    filled tube within a heavily protected cable. As the fibre has no physical contact with the

    tube it is less prone to damage during the stresses associated with installation and

    temperature contraction and expansion. The gel used within the tubes protects against the

    ingress water. Many different fibre counts are available as few as four or as many as 96

    cores are common. Thus origination of OPTICAL fibre has made communication system

    reliable and effective and acted as an efficient tool in the energy management syste

    2.3 Testing of Optical Fiber Links

    To test a link, the correct mating connectors must be fitted to the test leads.There are many

    types of fibre connectors as each fibre type (multimode, single mode and POF) has its own

    family of connectors. The most common types are ST, SC and SMA.

    Before testing the link, you must know how much loss to expect at the wavelength of

    interest. If you want accurate results, the testing should be performed at the wavelength at

    which the fibre is to be used. Link loss can be readily calculated from the manufacturers

    data (loss per unit length in dBs), the actual link length, and the number of connectors and

    joints (if any) in the link. Without this data, you cannot determine whether or not the links

    performance is satisfactory. Do not assume there are no problems because a link works

    when connected to the terminaL equipment. Some faults degrade link performance withtime (e.g. bad terminations).

  • 7/30/2019 Major Report on Energy Mgt

    51/79

    Fig. 10 TYPES OF FIBRE CONNECTORS

    2.4 Monitoring of Status of OPGW

    The status of OPGW whether healthy or faulty is monitored by using the equipment

    named as FLXER PLUS. This equipment confirms that the broadband is as per actual and

    functioning properly. If there is fault in the OPGW network, the alarm appears on the map

    of the network. The faulty part of the OPGW appears red on the screen of FLXER PLUS.

    The following diagram represents the connectivity of FLXER PLUS and FLXER with

    OPGEW map.

    Fig.11 Test Diagram for Monitoring of Status of OPGW

    The map on the screen of FLXER PLUS shows the network connectivity of different

    stations connected through OPGW appears as under:

    Fiber Optic Connectors

    F

    C

    P

    C

    FCPC

    SCPC

    STPCSCPC

    FLXER

    PLUS

    FLX

    150/6

    FLX

    150/6

    Hamirpur Gaggal Kunihar Jutogh

  • 7/30/2019 Major Report on Energy Mgt

    52/79

    Fig. 12 Map of Network Elements of Different Locations

    The details of status of different network elements are ascertained by using specific

    commands on FLXER PLUS. If the status is healthy, the connectivity appears green and if

    the status is unhealthy, the connectivity appears red.

    2.5 PLCC System

    PLCC system plays a vital role in the establishment of communication system. It

    connects all the RTUs with SUB-LDCs. This is considered as one of the most economical

    and reliable method of communication. In PLCC system, a bandwidth of 0-4 kHz is

    confined to different applications as under:

    The voice channel lies between 300 Hz to 2400 Hz.

    The pilot frequency which is used for sending the dialling pulses and for the automatic

    gain control of PLCC system lies within 3.57 kHz to 3.63 kHz.

    The portion of band between 2.4 kHz to 3.57 kHz is used for data transmission on real

    time basis.

    It consists of two PLCC Terminals at two stations A and B connected together with the

    help of HT transmission line and coupling equipment like wave traps (Line traps), coupling

    capacitors, coupling devices and H.F. cable. For making data available of Solan substation

    at Kunihar SUB-LDC, 2 No. Panels of BPL make, each at respective stations are placed

    and are used for speech/data transmission of Solan Substation. At Solan end, the PLCC

    panel is connected to RTU which collects various measurands of Solan substation and

    transmit it through PLCC system upto Kunihar SUB-LDC and at Kunihar end the PLCC

    panel is connected to CFE (Communication Front End) where the data from RTU is made

    available for further processing.

    The figures below shows the connectivity between RTU and SUB-LDC Kunihar in

    between two stations and in between three stations. Incase of three stations, ie Giri, Solan

    and Kunihar, the station Solan is called intermittent station and the connections of PLCC

    Panels are made back to back, ie TX of one panel is connected to RX of other panel and

    vice versa. For providing TX signal of -14 dB , oscillator is used and for measuring RX

    signal of -20 dB, the level meter is used.

  • 7/30/2019 Major Report on Energy Mgt

    53/79

    A typical arrangement is shown in fig below:

    SOLAN KUNIHAR

    TX TX

    RX RX

    RTU PLCC Panel PLCC Panel CFE

    TX= -16 dB

    RX= -20 dB

    GIRI SOLAN KUNIHAR

    RTU PLCC Panel PLCC Panel CFE

    PLCC Panels

    TX {Trans Signal} = -14 dB

    RX {Receive Signal} = -20 dB

    Fig. 13 Connectivity Between RTU and SUB-LDC Kunihar &Solan

    2.6 PABX System

    This system is one of the important tools in SLDC system which provides fast, reliable and

    efficient telephone system which is an essential requirement for the power system grid

    operation. All control centres are equipped with PABX (Private Automatic BranchExchange Network). Each PABX has a number of local and remote subscribers. In SLDC

  • 7/30/2019 Major Report on Energy Mgt

    54/79

    Jutogh,

    PABX system comprises 4 wire and two wire system. In the 4 wire

    system, four wires are used for speech and two wires are used for signal, thus the four wire

    system consists of total six wires. In the two wire system, the two wires are used for speech

    and two wires are used for signal purpose. Thus, the two wire system comprises total four

    wires. The PABX exchange is connected to the system through Main Distribution

    Frame(MDF). It provides interconnection between exchange side and line side termination.

    The implementation of integrated wideband telecommunication system network with PLC

    and PABX procured under different contracts needs to be coordinated and requires careful

    planning. The connectivity of PABX system with broadband system has made it possible

    the communication between interstate SLDC units established at different corners in NR

    Region. The requirement of PABX network in power system is unique.

    With the development of wideband system it has become possible to

    provide speech facility with the outside control centres also. This mode of communication

    proves to be very economical as it involves initial cost of installation with very less

    maintenance cost. The existing PABX exchanges are provided with a console which helps

    in planning and programming at site and very easily one can provide new connections to

    the utilities. These modern PABX systems are embedded with facilities such as provision

    for future extension. In SLDC Shimla and in its respective SUB-LDCs, the PUNCOM

    make exchanges have been provided. For maintenance purpose, AMCs (Annual

    Maintenance Contract) have been given to the respective companies. The PABX exchange

    in the existing system of SLDC Shimla provides speech communication to the remote

    stations through PLCC system, to outside states through wideband system and within the

    vicinity of SLDC campus through local subscribers.

  • 7/30/2019 Major Report on Energy Mgt

    55/79

    Fig.14 PABX Room In SLDC Shimla

    The most important part of the exchange is its MDF (main distribution frame). It is divided

    into two parts. The upper half is called exchange side and the lower half is called line side.

    The local extension and console connections are terminated on termination block E1.Trunk lines are terminated on block E2. Both of these termination blocks are called

    exchange side termination blocks. Similarly, on line side extension to all local subscribers

    are given through L1 and connections to trunks are terminated at L2. E1 & L1 and E2 & L2

    are connected through jumpers.The connectivity of PABX exchange at SLDC Jutogh with

    MDF and console which is designated as SUPCON is as shown in the fig below:

    -48 VOLT DC

    POWER INPUT

  • 7/30/2019 Major Report on Energy Mgt

    56/79

    Subscribers

    MDF

    Trunks

    POWER

    UNIT

    CONTR

    OL

    SERVICE

    UNIT

    TERMINAT

    ION

  • 7/30/2019 Major Report on Energy Mgt

    57/79

    Fig.15 The connectivity of PABX exchange at SLDC Jutogh with MDF

    and console

    The PABX exchange has four functional groups which are as under:

    Power Unit

    Control Unit

    Termination Unit

    Service Unit

    A brief description of functional groups of PABX is as given below:

    Power Unit: It consists of a power filter card which filters out -48 Volt DC supply.

    The filtered power is fed to Power supply unit card which generates

    +/- 5 V, 12V DC, -9V DC. PSU card also generates 75 volt (RMS)

    ringer voltage which is extended to telephone. The filtered -48V is

    also fed directly to termination unit.

    Control Unit: It handles all call processing functions. It takes all decisions and

    controls all the functions done within PABX. It comprises PFC card, P

    01 card. The function of P 01 card is to provide serial RS-232

    interfaces for operator console/dispatcher console and communication

    with PFC card. The PFC card scans the signalling status of each card

    of termination unit and sends them as message to P 01 card.

    CONSOLE

  • 7/30/2019 Major Report on Energy Mgt

    58/79

    Termination Unit:It provides interface with telephone instruments/other equipments.

    The various types of interfaces are:

    2-wire subscriber interface

    4-wire E&M interface

    2-wire centre office interface

    30 channel digital interface

    There is a unique card for each interface known as LCC card. Each

    analog interface card comprises 8 ports and digital interface cardcomprises 30 ports.

    Service Unit: It consists of ATD card which is used forannouncement and tones. A

    conference card which has a facility to conduct conference of 6

    parties.

    All subscriber lines and trunks are interfaced to PABX system through the terminalinterface card. The terminal interface card consists of 8 termination ports. Such cards form

    a terminal group which is designated as TG.

    TG= 4 Terminal cards = 4 X 8 = 32 ports = 32 Channel

    2.7 RTU (Remote Terminal Unit)It is one of the most important tools of SLDC. Without this it could not have been

    possible to fetch the data from the remote stations and monitor the activities of the

    remote stations. RTUs have made it possible to make many of the remote station

    man less. They are playing very active role in making day to day availability of data

    from the remote stations. One of the RTUs installed at 132 kv sub-station Jutogh at

    Shimla is as shown on the next page:

    When the RTUs were not devised, most of the potential of PLCC system remained

    unutilised. The application of RTUs has made it possible to use the hidden potential

    of PLCC in this age of state of Art. Transducers and MODEMs play a very

  • 7/30/2019 Major Report on Energy Mgt

    59/79

    important role for the establishment of Real Time Data Acquisition system. This

    system is designated with the abbreviation DAS and the whole combination of

    making data available in real time operation at SLDC is designated as SCADA i.e.

    Supervisory Control And Data Acquisition .RTU is a combination of transducers

    used for various measurands such as voltage frequency, MW, MWh, MVARh and

    converts electrical signal into digital signal which is further converted into analog

    signal using modem if the same is to be transmitted through PLCC system or

    otherwise the digital signal is sometimes directly processed without any conversion

    if the same is to be transmitted through wideband system In power system there are

    two types of measurands. One is analog type and the other is digital type. They are

    as under:

    0 Analog type measurands: Voltage, frequency, active power, reactive power,

    position of auto transformer tap.

    1 Digital type measurands: Status of circuit breaker and isolator (close/open)

    The fig. Given below shows RTU at 132 KV substation Jutogh

  • 7/30/2019 Major Report on Energy Mgt

    60/79

    Fig.16 RTU at 132 KV substation Jutogh

    2.8 UPS (Uninterrupted power supply)

    1.4.1 Uninterruptible Power Supply

    Introduction

    Uninterruptible power supply (UPS) is a device that protects electronic equipment from

    power uncertainties. A UPS is a device that is interfaced between the electric network

    (connected to utility power) and the materials that need protecting.

    The UPS allows the materials to be switched to emergency battery power for several

    minutes in case of electrical problems, in particular during:

    http://en.kioskea.net/contents/protect/onduleur.php3http://en.kioskea.net/contents/protect/onduleur.php3
  • 7/30/2019 Major Report on Energy Mgt

    61/79

    Power line disturbances, i.e. a split second power outage that can cause a computerto restart

    Power outages, corresponding to a break in the power supply for a given amount oftime

    Overvoltage, i.e. a nominal value greater than the maximum value needed for thenormal functioning of electrical appliances

    Undervoltage, i.e. a nominal value less than the maximum value needed for thenormal functioning of electrical appliances

    Voltage spikes, i.e. high amplitude transient (short-term) overvoltage. These spikesare caused when powerful devices are stopped or started and overtime can damage

    electrical components

    Lightening, which is a source of extreme overvoltage that occur suddenly duringbad weather (storms)

    Most electrical disruptions are tolerated by computer systems. However, sometimes they

    can cause data loss and service interruptions and even material damages.

    The UPS helps to "smooth out" voltage, i.e. eliminate peaks that are over a certain level.

    When there is a power outage, the energy stored in the emergency battery keeps the power

    supply flowing to equipment for a small amount of time (normally for 5 to 10 minutes).

    Beyond the minutes of autonomy that the UPS supplies, this gained time also allows the

    equipment to be switched to other energy sources. Some UPSs can also be directly attached

    to the computer (e.g. with a USB cable) so that it can order its own shutting off in case of a

    power outage and thus avoid any data loss.

    Fig. 17 General Outlook of UPS

    Under ULDC scheme(Unified Load Despatch Scheme), the following capacity of UPS

    have been installed to provide uninterrupted power supply and to have firm data.

    a) At SLDC Shimla: 2 no. UPS each 40 kVA capacity have been installed at SLDC

    Shimla. These UPS comprises two types of battery system, i.e. 384 V/200 Ah,

    48V/415Ah respectively.

    b) At Sub-LDC Hamirpur: 2 no. UPS each 20 kVA capacity have been installed at

    SLDC Shimla. These UPS comprises two types of battery system, i.e. 384 V/200

    Ah, 48V/415Ah respectively.

    c) At Sub-LDC Kunihar: 2 no. UPS each 20 kVA capacity have been installed at

    SLDC Shimla. These UPS comprises two types of battery system, i.e. 384 V/200

    Ah, 48V/415Ah respectively.

  • 7/30/2019 Major Report on Energy Mgt

    62/79

    In addition to above, at each site of SLDC, DG Sets of capacity 75 kVA at SLDC Shimla

    and 45 kVA at respective SUB-LDC sites have been provided to have standby arrangement

    for uninterrupted supply.

    CHAPTER 3 ENERGY MANAGEMENT A "SPECIAL

    CASE" OF HIMACHAL PRADESH.

    3.1 Introduction

    Himachal Pradesh being purely hydro state has surplus during monsoon months

    but face acute shortages during winter as availability from hydro Stations reduces to

    20 to 25% due to lean discharges and so happens to the Central Sector shares of

    Hydro based projects of the region. As HPSEBs committed power is not adequate

    to meet the demand as such HPSEBL meets its deficit demand by way of different

  • 7/30/2019 Major Report on Energy Mgt

    63/79

    arrangements.

    Fig. 18 ABOUT STATUS OF HIMACHAL PRADESH

    3.2 Grid Diagram of Himachal Pradesh

    7

  • 7/30/2019 Major Report on Energy Mgt

    64/79

    Fig. 19 Grid Diagram of Himachal Pradesh

    3.3 Modes of Managing Energy Deficits

    1, GoHP (Govt. of Himachal Pradesh) free power entitlement in Central sector / Joint

    sector projects as well as through GoHP entitlement available within the state.

    2. 22% equity power of GoHP in NJPC project.

    3. Through Banking arrangements.

    4. Unscheduled Interchanges (Over Drawl) transactions under real time operation.

  • 7/30/2019 Major Report on Energy Mgt

    65/79

    5. Unallocated quota allotted by Govt. of India during winter months.

    3.4 Description of different modes of Power Arrangements

    a. Central Sector Projects

    HPSEBL receives power from central sector projects in proportion to its

    entitlement and is governed under CERC regulation. This power is made

    available at generator terminal of the respective projects and is wheeled

    through Power Grid system till it is made available at H.P periphery. The bills

    in respect of generator comprises two parts . One part is energy availed by

    HPSEBL at generator terminal and the other part of the bill is raised by Power

    Grid on account of wheeling of power through their system upto H.P

    periphery. The quantum of energy which reflects in a monthly bill is based on

    the Regional Energy account prepared by NRPC (Northern Regional Power

    Committee).

    b. Govt. of H.P. free power Entitlement:

    Govt. of H.P.has its free power Entitlement in all those projects which have

    been commissioned in Himachal Pradesh . This entitlement is on account of

    the home state benefits i.e Himachal has sacrificed its potential as well as

    benefits of the people. In addition to above entitlement of GoHP free power ,

    HPSEBL also receives 22% equity during winter months or extended winter months

    which is at the discretion of GoHP and is given to HPSEBL as its first right to

    mitigate the shortages during the the said months.

    c. Through Banking :

    Transaction / procurement of Power through Banking is also one of the modes which

    is considered as a cashless transaction and this energy exchange arrangement is on

    equal basis i.e. the obligation of HPSEB to return the banked energy is restricted to

    the extent to which the energy has been banked with it during the winter months. The

    average rate as agreed as per agreements (Unscheduled Interchange rates based on

    prevailing grid frequency conditions at that point of time) are kept to account for

  • 7/30/2019 Major Report on Energy Mgt

    66/79

    unadjusted quantum at the end of banking cycle. This arrangement facilitates when

    there is large variation in demand pattern during winters on account of fluctuating

    weather conditions and provides real time operation and facilitates increase or

    decrease of quantum with the mutual consent of both the parties without any

    financial implications on either party. With the above arrangement the surplus power

    available during the monsoon months is returned for meeting the previous year

    banking obligations as well as for Advance Banking (contra banking) arrangement

    thus facilitates mitigating winter deficits.

    d. Unscheduled Interchange (UI):

    This does not fall under any category of mode of transaction of power, but

    under prevailing grid frequency conditions, power does flow perforce which

    also provides additional assistance to mitigate the instantaneous shortage of

    power. This perforce transaction of power is regulated as per CERC

    regulation on Unscheduled interchange of power issued by Central Electricity

    Regulatory Commission from time to time. However, the underdrawl

    /overdrawl of power should not exceed the specific limit or otherwise, the

    same shall lead to the collapsing of grid. It is also added that any violation

    through UI against the prescribed norms shall lead to penalty to theconcerned utility.

    e. Transaction of power through energy exchange:

    In this mode of transaction of power, the surplus power available on day-

    ahead basis is disposed off through exchange on the available rates. Similarly

    through this mode, procurement of power is also carried out to meet the

    immediate demand of shortages.

    f. Sale/ purchase of power through Tendering process:

    In this mode of transaction, bids are invited from different utilities for their

    participation in the tendering process and the bidder who qualifies the desired

    terms and conditions is given order for supply of power.

    3.5 HPSEBL Share in different Projects

    HPSEBL receives power throughout the year from the following projects against itsSOR(State of Region Share) share as shown in table below.

  • 7/30/2019 Major Report on Energy Mgt

    67/79

    Table-1

    Sr.

    No. Name of Stations Installed HPs share

    capacity % MW

    MW (Mega

    Watt.)

    A.

    HPSEBL

    Entitlement

    I.

    BBMB

    STATIONS

    Bhakra old HP FIXED

    10.00

    (1.2LU/Day)

    Bhakra complex 1478.73 7.19 84.23

    Dehr 990.00 7.19 56.83

    Pong 396 7.19 11.77

    Bhakra (Old) Fixed

    10.00

    (1.2LU/Day)

    II.

    NHPC

    STATIONS

    Chamera-I 540.00 2.90 15.66

    Tanakpur 94.20 3.84 3.62

    Salal 690.00 0.99 6.83

    Uri 480.00 2.71 13.01

    Chamera-II 300.00 3.67 11.01

    Chamera-III 231 4.36 10.06

    Dhauliganga 280.00 3.57 10.00

    III. NTPC

  • 7/30/2019 Major Report on Energy Mgt

    68/79

    PROJECTS

    Rihand-I 1000.