Upload
chanchal2
View
222
Download
0
Embed Size (px)
Citation preview
7/30/2019 Major Report on Energy Mgt
1/79
A
PROJECT REPORT
ON
COMPREHENSIVE STUDY ON ENERGY MANAGEMENT
Submitted in the partial fulfillment for the award of degree of
Bachelor of technology
In
ELECTRICAL & ELECTRONICS ENGINEERING
H.C.T.MTECHNICAL
CAMPUS,
KAITHAL
SUBMITTED
TO:-
SUBMITTEDBY:-
Er. VINOD
KUMAR
MANISH
UPPAL
(1709731)
ASSISTANT
PROF.
HIMANSHU
CHANCHAL
(1709742) EEE DEPARTMENT MOHIT GIRDHAR
(1709744)
H.C.T.M TECHNICAL CAMPUS, KAITHAL
KURUKSHETRA UNIVERSITY KURUKSHETRA
CANDIDATE's DECLARATION
7/30/2019 Major Report on Energy Mgt
2/79
We hereby declare that the work which is being presented in this project entitled "
COMPREHENSIVE STUDY ON ENERGY MANAGEMENT" in partial fulfillment of the
requirement for the award of the degree of bachelor of technology in the field
of Electrical & Electronics Engineering submitted to HCTM TECHNICAL
CAMPUS , Kaithal is an authentic record of my work carried out under the
guidance of Er. Vinod Kumar , Assistant Professor , in the Department of
Electrical & Electronics Engineering , HCTM TECHNICAL CAMPUS , Kaithal .
Date : Manish Uppal (1709731)
Place : Kaithal Himanshu Chanchal ( 1709742)
Mohit Giridhar ( 1709744)
B.Tech. ( Electrical & Electronics
Engineering)
Certificate
This is to certify that the above statement made by the candidate is correct to the best of my
knowledge and belief.
Er. Vinod Kumar Er. Vivek Phawa
Assistant Professor Professor & H.O.D.
Department of Electrical& Department of Electrical&
Electronics Engineering Electronics Engineering
HCTM Technical Campus , Kaithal HCTM Technical Campus , Kaithal
ACKNOWLEDGEMENT
7/30/2019 Major Report on Energy Mgt
3/79
As the saying goes WE set ourselves to bite the hands that feed us if we fail to
thank such of those to whom our thanks are really due.
In view of the help extended and opportunities given to us to work on
this study based project on "Energy Management" , we are compelled to thank
to all those who took an initiative and helped us in providing input for theproject.
First of all , we consider this an utmost duty to extend our heartiest
thanks to the HOD (EEE Dept) , Mr.Vivek Pahwa for necessary co-operation /
consideration for our successful completion of this project.
Above all we would like to convey our esteemed thanks to Er. Vinod
Kumar , Assistant Professor ( EEE Dept) , for providing necessary guidelines
and nourishing us thorough out with his best experiences in the field of power
system and energy management.
At last but not the least, we would like to extend our thanks to all staff
members and officers of the concerned department of HPSEBL for providing
necessary material for successful completion of the project.
Manish Uppal (1709731)
Himanshu Chanchal ( 1709742)
Mohit Giridhar ( 1709744)
B.Tech. ( Electrical & Electronics
Engineering)
7/30/2019 Major Report on Energy Mgt
4/79
ABSTRACT
Energy management is a vital issue in the present scenario when the system under
integration mode runs under deficit or surplus conditions. The term energy management
includes planning and operation of energy & its consumption. The application of energy
management is well visualized when an organization receives energy from outside the state
as well as from its own generation within the state. In the modern era, when the energy is
available from renewable energy sources in the pure form and its disposal to the
beneficiaries in the bundled form, uses intensive application of energy management
methodologies.
This study based project is a comprehensive study on Energy Management. Thebasic idea of this project is to get awareness of the energy management methodologies
when some states are surplus in power and some states are deficit in power. Mostly, the
snow fed states like Himachal have less generation during winters and due to melting of
snow during summer, have maximum flow of water in the rivers which ultimately
attributes to enhanced generation during summers. This project also focuses on under
drawal and overdrawal under different frequency conditions under UI regime.
In order to approach step by step hierarchy of energy management, the project has
been divided into two sections. Section-I focuses on role of energy management in power
system and general approach towards energy management methodologies and Section II
is a special case study on energy management in Himachal Pradesh.
Section-I comprises 8 Chapters. The first chapter gives introduction on the
necessity of Energy management when the system is passing through abnormal conditions.
The second chapter stresses the importance of SLDC as an essential tool to energy
management. The third chapter puts light on the very important feature of energy
management i.e. Availability Based Tariff (ABT) , which apprises about the scheduling of
power by the utilities as special feature and importance of ABT in energy management.The
fourth chapter gives knowledge about the role of frequency in energy management under
different frequency conditions.The fifth chapter presents very important aspect of energy
management as to how the energy is managed when deviates from the schedule. The sixth
chapter provides , how the trading opportunities are available both for Generator as well as
Beneficiary under the shadow of energy management.The seventh chapter has its
7/30/2019 Major Report on Energy Mgt
5/79
importance as without this tool of energy management it is not possible to make trading
with the utilities who are available at some other places. Apart from above , now Indian
Exchange is also one of the players available in the market to take care of disposal /
procurement of power on day to day basis and eighthchapterprovides special features of
power Exchange established in India.
Section-II is very important section which deals with Himachal Pradesh as a special case
of Energy Management and puts light on the tools and methodology being adopted by
Himachal Pradesh for disposal of its surpluses and mitigating deficits.This section
comprises three chapters. The first chapter focuses on status of SLDC in HPSEBL and
second chapter highlights utility of SLDC as an essential tool for energy management.
This provides inputs of different components used in establishing SLDC units , thus gave
an ease to manage energy transactions in effective manners. The third chapter highlights
Himachal Pradesh as a special case of Energy management and provides details of share of
H.P in different sources and modes of energy management .
.
7/30/2019 Major Report on Energy Mgt
6/79
CONTENTS
SECTION -I
ROLE OF ENERGY MANAGEMENT
IN
POWER SYSTEM OPERATION
CHAPTER 1 INTRODUCTION
1.1 Vital Role of Energy Management
1.2 Basics of Energy Management
1.3 Constraints in Energy Management
CHAPTER 2 SLDC AN ESSENTIAL TOOL TO ENERGY
MANAGEMENT
2.1 Introduction
2.2 Load Dispatch Centers in Northern India
2.3 Real Time Dynamic Security Assessment
CHAPTER 3 AVAILABILITY BASED TARIFF(ABT)
3.1 Introduction
3.2 Details about ABT
3.3 Scheduling
3.3.1 Introduction
3.3.2 Day Ahead Scheduling
3.4 Features of ABT
7/30/2019 Major Report on Energy Mgt
7/79
CHAPTER 4 ROLE OF FREQUENCY IN ENERGY MANAGEMENT
4.1 Frequency is good and High and the state is overdrawing.
4. 2 Frequency is good and High and the state is Underdrawing.
4.3 Frequency is Low and the state is overdrawing.
4.4 Frequency is Low and the state is Underdrawing.
CHAPTER 5 DEVIATIONS FROM SCHEDULE
5.1 Unscheduled Interchange (UI)
5.2 UI rate determination
5.3 Unscheduled Interchange (UI) Vs Marginal Cost.
CHAPTER 6 A TRADING OPPORTUNITY UNDER THE SHADOW
OF ENERGY MANAGEMENT
6.1 Trading Opportunity to be Availed by the GENERATOR
6.2 Trading Opportunity to be Availed by the BENEFICIARY
CHAPTER 7 OPEN ACCESS , WHEELING AS AN IMPORTANT
TOOL OF ENERGY MANAGEMENT .
7.1 Open Access and Wheeling
7.2 Issues Involved in the Transactions
CHAPTER 8 POWER EXCHANGE IMPLEMENTATION
IN INDIA
8.1 Introduction
8.2 Regulatory Framework for power exchange Implementation
8.3 Power Exchange Implementation in India
8.4 Functional Power Exchange
7/30/2019 Major Report on Energy Mgt
8/79
8.5 Competition among Exchanges
8.6 Information Exchange between NLDC and Power Exchanges
8.7 Regulations governing the process of Energy Management
SECTION -II
ENERGY MANAGEMENT
IN
HPSEBL
AS
A SPECIAL CASE
CHAPTER 1 STATUS OF SLDC in HPSEBL
0 Setting up SLDC/SUB-LDCs in Himachal Pradesh
1.2 Sub-LDC at Kunihar
1.3 Sub-LDC at Hamirpur
1.4 Interconnectivity of SLDCSUB-LDCs of H.P.
CHAPTER 2 SLDC AN ESSENTIAL TOOL TO ENERGY
MANAGEMENT
2.1 Introduction
2.2 OPGW and its Installation
2.3 Testing of Optical Fiber Links.
2.4 Monitoring of Status of OPGW
2.5 PLCC System
2.6 PABX System
7/30/2019 Major Report on Energy Mgt
9/79
2.7 RTU (Remote Terminal Unit)
2.8 UPS (Uninterrupted power supply)
CHAPTER 3 ENERGY MANAGEMENT A "SPECIAL
CASE" OF HIMACHAL PRADESH.
3.1 Introduction
3.2 Grid Diagram of Himachal Pradesh
3.3 Modes for Managing Energy Deficits
3.4 Description Of Different Modes of Energy Management
3.5 HPSEBL Share in different Projects
3.6 STATUS of Energy Managed from different sources in FY 2010-11
3.7 STATUS of Energy Managed different sources in FY 2011-12
Conclusion
Future Scope
References
7/30/2019 Major Report on Energy Mgt
10/79
LIST OF TABLES
Table No. Description Page
No.
1. HPSEBL Share in different Projects
2. STATUS of Energy Managed in FY 2011-12
3.STATUS of Energy Managed in FY 2012-13
7/30/2019 Major Report on Energy Mgt
11/79
LIST OF FIGURES
Fig. No. Description Page No.
1. Hierarchical Structure of Load Dispatch Centres in Northern
India.
2. Relationship between UI rate and Grid Frequency
3. Location of SLDC and Sub-LDCs in Himachal Pradesh
4. Hierarchical Structure of SLDC & Sub- LDCs
5. SUB-LDC KUNIHAR (Connectivity of RTUs)
6. SUB-LDC HAMIRPUR (Connectivity of RTUs)
7. Inter Connectivity Diagram Of SLDC , Sub -LDCs of H.P.
8. Combined Connectivity Diagram
9. OPGW (Optical Ground Wire)
10. Types of Fibre Connectors.
11. Test Diagram for Monitoring of Status of OPGW
12. Map of Network Elements of Different Locations
13. Connectivity Between RTU and SUB-LDC Kunihar &Solan
14. PABX Room In SLDC Shimla
7/30/2019 Major Report on Energy Mgt
12/79
15. Connectivity of PABX Exch. at SLDC with MDF& Console
16. RTU at 132 KV substation Jutogh
17. General Outlook of UPS
18. About Status Of Himachal Pradesh
19. Grid Diagram of Himachal Pradesh
SECTION -I
ROLE OF ENERGY MANAGEMENT
IN
POWER SYSTEM OPERATION
7/30/2019 Major Report on Energy Mgt
13/79
CHAPTER 1 INTRODUCTION
1.1 Vital Role of Energy Management
Energy management is a vital issue in the present scenario when the system under
integration mode runs under deficit or surplus conditions. The term energy management
includes planning and operation of energy & its consumption. The application of energy
management is well visualized when an organization receives energy from outside the state
as well as from its own generation within the state. In the modern era, when the energy is
available from renewable energy sources in the pure form and its disposal to the
beneficiaries in the bundled form, uses intensive application of energy management
methodologies.
Although, many issues such as energy procurement, disposal, consumption, and itssaving falls under the preview of energy management but this comprehensive study mostly
focuses on the energy management of bulk power procurement under different conditions
such as through nuclear, hydro, thermal based stations, and from REC(Renewable Energy
Certifications).
Energy management study of this project focuses on the status of the states which
have surplus power during summer and deficit power during winter months. Mostly, the
snow fed states have less generation during winters and due to melting of snow during
7/30/2019 Major Report on Energy Mgt
14/79
summer, have maximum flow of water in the rivers which ultimately attributes to enhanced
generation during summers.
Such states which have surplus power during summer months, their organizations
tie up with the states which have deficit power in summer and provide assistance to these
states to mitigate their shortages by either selling the power or making arrangement under
banking which is one of the important aspects of energy management.
Mostly, the organizations prefer disposal/procurement of power under banking
arrangement as this being considered as cashless transaction. However, even under banking
arrangements also, certain rates are kept so as to settle the accounts on account of
unadjusted quantum, if any, by the end of banking cycle. This project shall mainly focus on
the energy management methodologies being adopted by Himachal State for
disposal/procurement of power under different modes.
1.2 Basics of Energy Management
Most of the states uses following modes for mitigating the shortages of power:
1, By availing free power entitlement of their own states in Central sector / Joint
sector projects .
2. By availing equity power entitlement of their government if any.
3. Through banking arrangements.
4. Unscheduled Interchanges (Over Drawl) transactions under real time operation.
5. Unallocated quota allotted by Govt. of India for deficit months.
In the above stated arrangements, the power from Central Sector Projects is
managed under the guidelines of CERC regulations. This power is initially made available
at generator terminal and is wheeled through Power Grid system to make it available at HP
periphery. Similarly, the free power entitlement of GoHP (Govt. of H.P.) is availed through
traders appointed by the government for this purpose. The banking arrangement is made
with different neighboring utilities. Many states also manages power deficits through
perforce transactions, i.e. under UI (Unscheduled Interchange) arrangements.
0 a. Central Sector Projects:
7/30/2019 Major Report on Energy Mgt
15/79
Utilities receive power from central sector projects in proportion to their entitlement in
line with guide lines as per CERC regulations. This power is made available at
generator terminal of the respective projects and is wheeled through Power Grid
system till it is made available at their respective periphery. The bills in respect of
generator comprises two parts . One part is energy availed at generator terminal and
the other part of the bill is raised by Power Grid on account of wheeling of power
through their system up to the state periphery. The quantum of energy which reflects
in a monthly bills is based on the Regional Energy account prepared by NRPC
(Northern Regional Power Committee).
1 b. Free power Entitlement:
Every state has free power Entitlement in all those projects which have been
commissioned in their respective territory . This entitlement is due to home state
benefits on account of sacrificing its potential as well as water usage rights of the
people of that state. In addition to above free power entitlement of the state , the utilities also
avail equity power entitlements if any which is at the discretion of the respective governments
and is given to the state as first right to mitigate the shortages during deficit months.
c. Through Banking :
Transaction / procurement of Power through Banking is also one of the modes which is
considered as a cashless transaction and this energy exchange arrangement is on equal basis
i.e. the obligation of the state to return the banked energy is restricted to the extent to which
the energy has been banked with it during the deficit months. The average rate as agreed as per
agreements (Unscheduled Interchange rates based on prevailing grid frequency conditions at
that point of time) are kept to account for unadjusted quantum at the end of banking cycle.
This arrangement facilitates when there is large variation in demand pattern during deficit
months on account of fluctuating weather conditions and provides real time operation and
increase or decrease of quantum with the mutual consent of both the parties without any
financial implications on either party. With the above arrangement the surplus power available
during the monsoon months is returned for meeting the previous year banking obligations as
well as for Advance Banking (contra banking) arrangements.
d. Unscheduled Interchange (UI):
This does not fall under any category of mode of transaction of power, but under
7/30/2019 Major Report on Energy Mgt
16/79
prevailing grid frequency conditions, power does flow perforce which also provides
additional assistance to mitigate the instantaneous shortage of power. This perforce
transaction of power is regulated as per CERC regulation on Unscheduled interchange
of power issued by Central Electricity Regulatory Commission from time to time.
However, the under drawl/over drawl of power should not exceed the specific limit or
otherwise, the same shall lead to the collapsing of grid. It is also added that any
violation through UI against the prescribed norms shall lead to penalty to the
concerned utility.
e. Transaction of power through energy exchange:
In this mode of transaction of power, the surplus power available on day-ahead basis is
disposed off through exchange on the available rates. Similarly through this mode,
procurement of power is also carried out to meet the immediate demand of shortages.
f. Sale/ purchase of power through Tendering process:
In this mode of transaction, bids are invited from different utilities for their
participation in the tendering process and the bidder who qualifies the desired terms
and conditions is given order for supply of power.
1.3 Constraints in Energy Management
In the real time operation generally power system is encountered with
situations which cannot be foreseen and tied up for sale/purchase arrangements due to
unexpected variations in demand and supply position. This is more predominant in the case
of states where on one hand load is dependent upon the weather conditions and on the other
hand on own generation, which is purely hydro based through run of the river schemes,
depends upon the inflows that can also not be very accurately predicted. Under such
conditions the utilities have to rely upon their thermal power shares which are costlier than
hydro power and affects the economy of the state.
Some surplus power perforce, under real time operation gets transacted
through Unscheduled Interchange mode (Under Drawl) and exporting utilities are paid for
this unscheduled energy in accordance with the prevailing frequency conditions in the grid
under UI mechanism.
7/30/2019 Major Report on Energy Mgt
17/79
A part of energy assessed surplus on day a head basis (24 hrs) is sold through
Energy Exchange on the best available rates which are more or less influenced by the
frequency prevalent in the grid.
---------------X--------------------X-------------
CHAPTER 2 SLDC AN ESSENTIAL TOOL TO ENERGY
MANAGEMENT
2.1 Introduction
SLDCs (State Load Dispatch Center) have brought a revolution in the field of Energy
management . In fact it has proved its worth in giving clear picture of day to day energy
transactions. Communication System is considered as backbone of the SLDC which
provides support to the SCADA system and plays a vital role to ensure interconnectivity of
various control centres. The various modes of communication have given birth to SLDC
centres and fulfilled many dreams which were impossible before the establishment of such
centres. They have given us the following gifts:
0 Created Grid Discipline.
1 Improved voltage profile and frequency.
2 Reduced frequent Grid failures.
3 Optimum utilization of available resources.
4 Visualization of real time availability of data/ events occurrence.
Efficient Power System Operation & Load Management.
Reduced gap in Demand - Supply position (Better regulation).
Better voltages at Consumer end.
Low per Unit cost.
In fact the above stated gifts have given wide opening to a very important aspect i.e energy
management in an efficient manners. The energy management is an ultimate goal for an
electrical utility which could be achieved effectively with the birth of SLDC. Thus SLDC
7/30/2019 Major Report on Energy Mgt
18/79
has made possible all kinds of developments in the field of power system such as
development of trading market, power exchange , effectiveness in power transactions
through different modes.
Application of SLDC/NRLDC made possible , quick restoration of
the system during transaction of power, when there is a chance thatthe system may have
to face instability which ultimately leads to collapsing of the grid owing to over drawl by
some utilities under low frequency conditions attributing to grid indiscipline and violation
of regulations.
2.2 Load Despatch Centres in Northern India
As per the decision of Govt. of India it became mandatory to set Regional Load DespatchCenters and State Load Despatch centres alongwith Sub-Load Despatch Centres with
ultimate aim of National Grid.
In compliance to above orders of Govt. of India, under ULDC scheme (Unified load
Despatch Centre), all the states established SLDCs as well as SUB-LDCs in line with terms
and conditions of MOU(Memorandum of Understanding) signed between the all concerned
utilities which are as under:
5 Regional Despatch Centre at Delhi
6 SLDC at HPSEBL Shimla
7 SLDC at HVPNL Panipat
8 SLDC at UPPCL Lucknow
9 SLDC at DTL Delhi
10 SLDC at BBMB Chandigarh
11 SLDC at PSPCL Patiala
12 SLDC at RSEB Rajasthan
13 SLDC at JKPPD Gladni
With the increasing demand and utilization of electricity, an electrical
engineer should be well versed or at least acquainted with the various
7/30/2019 Major Report on Energy Mgt
19/79
aspects of generation, transmission and distribution of electricity, and at
the same time must be capable of analysing energy management
aspects. The introduction of SLDC units in the states have made
it possible to ascertain the eventualities in an effective mannerand has given a wide opening for energy management as a tool.
In this scenario of integrated system it has become essential to
have SLDC unit in every state of the country which provides
economical despatch and regulation of power.This system uses an
application of optical fibre ground wire as a mode of communication ,
PLCC system, SCADA system. Above all, UPS also plays an important
role to provide uninterrupted power supply to the power system and
ensures reliable system. The installation technique of fibre optics is
critical one in the commissioning process. The special connectors and
techniques are used for joining fibres. The tool used for splicing purpose
is special one. That instrument is known as splicer
In the Northern Region , SLDCs have been established in the following hierarchi andeach SLDC unit collects data from remote with the help of RTUs (Remote Terminal
Unit) . To facilitate effictive collection of data , each SLDC is further classified into Sub -
LDCs.
The hierarchical structure of above stated units is as shown in the fig below :
7/30/2019 Major Report on Energy Mgt
20/79
Fig. 1 Hierarchical structure of Load Dispatch Centres in Northern India
2.3 Real Time Dynamic Security Assessment
The Electrical Grid changes constantly with generation plants frequently coming online or
off-line as required to meet electrical demand. In state of the art electric utility control
centres, grid operators use energy management systems (EMS) to perform network and
load monitoring. Limits to flows and voltages are assigned on the basis of transmission line
thermal limits and off load studies of voltage and transient dynamic stability. Theassumptions that the grid power flows settle down to steady state condition is reexamined
7/30/2019 Major Report on Energy Mgt
21/79
in real time as the transmission grid conditions change in real time. In real time operation it
becomes essential to watch grid discipline under dynamic conditions. A software
designated as Dynamic Security Assessment is used to simulate the impact of the potential
of electric fault conditions and grid disturbances.
The SLDCs (Load Dispatch Centres) have made it possible to run
such models attributing to dynamic grid security and hence, contributed maximum towards
grid discipline under real time operations. All these functions perform effectively after the
establishment of SLDCs. These load despatch centres have given birth to power exchange
and development of power trading market .
With grid frequency point of view , any action taken by SLDC shall
depend on the grid frequency. This action is initiated by SLDC only when there is a
change in the system status i.e tripping of generating station . A load crash within the state
or a frequency change due to imbalance in load- generation.
CHAPTER 3 AVAILABILITY BASED TARIFF (ABT)
3.1 Introduction
7/30/2019 Major Report on Energy Mgt
22/79
The term Availability Tariff stand for a tariff structure for power spply from generating
stations on contracted basis . The power plants have fixed and variable cost . The fixed cost
elements are interest on loans , return on equity , depreciation , O&M expenses ,
insurance , taxes and interest on working capital. The variable cost comprises of the fuel
cost i.e coal and oil in case of thermal plants and nuclear fuel in case of nuclear plants . In
the availability based tariff mechanism , the fixed and variable cost components are treated
separately . The payment of fixed cost to generating stations is linked to a availability of
the plant , i.e its capability to deliver MWs on a day - by- day basis. The total amount
payable to the generating company over a year towards the fixed cost would depend on the
average availability of the plant over the year.In case the average actually achieved over the
year is higher than the specified norm for the plant availability , the generating company
would get a higher payment . In case the average actually achieved over the year is lower
than the specified norm for the plant availability , the generating company would get a less
payment . Hence, name Availability Tariff. This is first component of Availability Tariff
and is termed as capacity charges.
The second component of ABT is the energy charge and this would
comprise of variable cost of power plant for generating energy as per the given schedule.
The third component attributes towards payment for deviations from
schedule at a rate dependent on system conditions.
Initially, ABT was made applicable only to the central generating stations
which were having more than one beneficiary. But with its application, Central Electricity
Regulatory Commission (CERC), found its suitability towards quality improvement of
power and thought of its expansion to cover even Intrastate systems as well as. ABT has
shown improvement towards following disruptive trends in power sector:
a. Rapid and high frequency deviations causing damage and disruption to large scale
indusrial consumers.
b. Frequent grid disturbances resulting in generators tripping, power outages and
power grid disintegration.
3.2 Details about ABT
Availability for the purpose of ABT means the readiness of the generating stations to
7/30/2019 Major Report on Energy Mgt
23/79
deliver ex-bus output expressed as % of its related output capability as per rated capacity.
Availability of thermal generating station for any period shall be the percentage ratio of
average Sent Out Capability for all the time blocks during that period and rated Sent Out
Capability of the generating station.
Availability based tariff includes :
a. CAPACITY CHARGES
a function of the Ex- bus MW availability of power plant for the day
b. ENERGY CHARGES
MWh for the day as per ex- bus drawal schedule for the utility.
c. ADJUSTMENT FOR DEVIATIONS (UI Charges)
(Actual energy interchange in a 15 min time block- scheduled energy Interchange
for the same time block) x UI rate for that time block.
Total payment for the day = a + b (+/-) c
3.3 Scheduling
3.3.1 Introduction
The following procedure is adopted for scheduling:
0 Each day of 24 hrs starting from 00.00hrs is divided into 96 time
blocks of 15 minutes each.
1 The generating stations make advance declaration of their capacities for
generation in terms of MWh delivery of power for each time block of the next
day.
0 While declaring capability , the generator should ensure that the
capability during peak hours should not be less than that during other
hours.
1 Based upon such declaration , the Regional Load Dispatch Centre
7/30/2019 Major Report on Energy Mgt
24/79
(RLDC) shall communicate to the various beneficiaries their respective
shares of the available capability.
2 After the beneficiaries give their requisition for power based on the
generation schedules , the RLDC shall prepare the generation schedules
and drawl schedules for each time block after taking into account
technical limitations and transmission constraints.
3 The schedule of actual generation is quantified on ex- bus basis ,
whereas for beneficiaries , scheduled drawls shall be quantified at their
receiving points.
4 For calculating the drawal schedule for beneficiaries , the
transmission losses shall be apportioned in proportion to their drawls. In
case of any forced outage of the unit, or in case of any transmission
bottleneck , RLDC will revise the schedules. The revised schedules shall
become effective from the 4th time block, counting the time block in
which the revision is advised by the generator, to be te 1 st one.
3. 3.2 Day Ahead Scheduling
10 A.M - Central Generating stations advise foreseen plant-wise ex-
bus MW, MWh availability for next day.
11 AM - RLDC advises SEBs their MW , MWh shares in the foreseen availability
of central plants.
3 PM - SLDCs furnish their time-wise MW requisition from the above, and
schedule of bilateral exchanges, if any.
5PM - RLDC complies these and issues generation schedules for central plants
and drawl schedules for SEBs, for the next day starting at midnight.
10 PM - Revision of the above, if required , by any new development during the
day.
11 PM - Schedules frozen for the next day.
3.4 Features of ABT
7/30/2019 Major Report on Energy Mgt
25/79
The availability based tariff has the following features.
0 It brings about enhanced grid discipline.
0 Economically viable power with right pricing.
1 Encourages usage of Merit Order Dispatch / Economic Dispatch in India.
2 It helps in addressing grid disturbance issues
1 It helps observing any kind of gaming and avoiding the same.
2 It requires special meters , remote metering and communication
mechanisms to facilitate reading of the meters in time.
3 Facilitates addressing regularity assets.
4 It acts as an interface with various stakeholders to enable
implementation and benefits to all.
7/30/2019 Major Report on Energy Mgt
26/79
CHAPTER 4 ROLE OF FREQUENCY IN ENERGY
MANAGEMENT
4.1 Frequency is good or high and the state is Overdrawing.
- No Problem and No. Action Required-
However for enhanced Optimization may resort to following :
i. Reduce own generation to the extent possible and increase overdrawal so long as
frequency is above 49.8 Hz.
ii. Restore consumer load that had been shed, provided Tariff/ Realization rate is higherthan current UI rate.
iii. Increase, CGS requisition , if some part of the entitlements had not been requisitioned
earlier.
4.2 Frequency is good or High and the state is Underdrawing.
Action required is as under:
i. Reduce own generation to the extent possible , if the frequency is above about 49.8 Hz.
ii. Restore consumer load that had been shed, and reduce under-drawn
iii. Reduce CGS requisition, provided the previous two actions have been taken and the
frequency continues to be above 50.2 Hz, bialateral sale to the needy neighbour can be
tried.
4. 3 Frequency is Low , and the state is Overdrawing.
Action required is as under:
i Increase own generation to the maximum possible extent.
ii. Curtail consumer load . Load shedding to be graded balancing between UI price and
consumer category .
iii. Increase CGS requisition to full entitlement( If not requisitioned fully earlier ) and
7/30/2019 Major Report on Energy Mgt
27/79
arrange for bilateral purchase from another SEB/CGS.
4.4 Frequency is Low and the state is Underdrawing.
i. Increase own generation to the extent possible, provided the frequency is belowabout 49.5 Hz (comparing variable cost with current UI price).
ii. Curtail consumer load, by shedding low priority load (provided UI earning for the
SEB justifies such load shedding). This is totally optional, and helps the grid.
iii. Increase C GS requisition to full entitlement ( if not requisitioned fully earlier) and
earn UI or sell the surplus through a bilateral agreement)
The above scenarios shows that action to be taken for managing energy turbulences
depends upon the prevailing frequency and is independent of whether over-drawing or
underdrawing .
CHAPTER 5 DEVIATIONS FROM SCHEDULE
7/30/2019 Major Report on Energy Mgt
28/79
5.1 Unscheduled Interchange (UI)
The energy actually supplied by the generator may differ from what was scheduled . If the
actual energy supplied were higher than scheduled , the generating station would be
entitled to receive a payment for excess energy (deviation from schedule, termed as
Unscheduled Interchange(UI) ) at a rate dependent on frequency at that time. I f the energy
actually supplied is less than what is scheduled , the generating station shall have to pay
back for the energy shortfall, at the same frequency .
The relationship between the above UI rate and grid frequency for
interstate system is specified by CERC. The relationship between n UI and Frequency is as
shown in the fig. below.
Fig. 2. Relationship between UI rate and Grid Frequency
48.8 49 49.2 49.4 49.6 49.8 50
50.2 50.4 50.6
Frequency (Hz)
600
400
200
0UIRate(P
aisa
/kWh)
7/30/2019 Major Report on Energy Mgt
29/79
It is seen from the above figure that when the frequency is 50.5 Hz or higher , the UI rate is
zero , which means that the generating station would not get any payment for the extra
energy supplied . It would burn fuel for producing this extra energy , but would not get any
payment for it.If the actual energy supplied were less than scheduled energy , the
generating station would still be paid for the scheduled energy (at its energy charge rate )
without having to pay back anything for the energy shortfall. I t would thus be able to save
on fuel cost ( for the energy not generated) and retain the energy charge as net saving .
There is thus a strong commercial incentive to back down generating during high
frequency situations .
On the other hand , when frequency goes down, the UI rate ( for both
over supply and under supply ) goes up like anything and touches the level of Rs. 5.7 per
unit at frequency of 49.0 Hz. At a frequency of 49.5 Hz , the UI rate is Rs. 3.45 per unit.
For any short fall , the generating station shall have to pay back at the same rate . It would
thus have a strong commercial incentive to maximize its generation during periods of such
low frequency.
A similar scheme operates for the States ( beneficiaries) as well. Any
state drawing power in excess of its schedule has to pay for the excess energy at the same
frequency - dependent rate. The high UI rate during low frequency conditions would
induce all states to reduce their drawal from the grid, by maxamizing their own generation
and / or by curtailing their consumer load. If a state draws less power than scheduled , it
payus for scheduled energy quantum at the normal rate and gets paid back for energy not
drawn at a much higher UI rate . On the other hand , during high- frequency conditions , a
state draw extra power at a low rate and is thus encouraged to back down its own costlier
generating stations . An under-drawal during high- frequency conditions means that the
state pays for the scheduled power quantum unnecessarily. It should either reduce its
schedule or increase its drawal.
5.2 UI rate determination
For the purpose of determination of UI rate , the energy is metered in 15 - minute time
blocks, since frequency keeps on changing and subsequent UI rate . The metered energy is
compared with the scheduled energy for that 15- minute time block and the difference (+
or -) becomes the UI energy . The corresponding UI rate is determined by taking the
7/30/2019 Major Report on Energy Mgt
30/79
average frequency for the same 15- minute time block into account.
For each Central generating station and state , the actual energy has
to be metered on a net basis , i.e algebraic sum of energy metered on all its peripheral
interconnection points for every 15- minute time block. All UI payments are made into and
from a regional UI pool account, operated by the concerned RLDC.
5.3 Unscheduled Interchange (UI) Vs Marginal Cost.
UI rate is tightly linked to grid frequency. As the frequency is same all over an A.C.
system and can be readily seen through a simple frequency meter , it is easily possible to
know the prevailing UI rates anywhere in the system . With this on line knowledge of the
current UI rate , a state would know what it would have to pay for an extra MW that it
may draw from the regional . It can readily compare this with the fuel cost it would save if
generation were reduced by one MW at its own station, having the highest variable cost. If
the UI ratre is lower than the latter, it would be beneficial; for the state to reduce its own
generation and draw the replacement energy from the regional grid, till it has backed down
all generation having a variable cost higher than the current UI rate . In the process state's
marginal generation cost would move down, towards the prevailing UI rate.
Meanwhile, other states too would take a similar action in the same time
frame and total generation in the system would come down, resulting in a downward
movement of frequency and an upward movement of UI rate , till the attainment of a state
of equilibrium wherein the marginal generation cost of every state would become equal to
the UI rate.
On the other hand , if a state finds the UI rate to be higher than the variable
cost of any of its partly loaded generating units at any time , it would be financiallybeneficial for the state to maximize the output of all such generating units and thereby
reduce its drawal from the regional grid. The state would have an under- drawal, for which
it would get paid a UI rate higher than its marginal generation cost.
With similar action being taken by other states as well, the frequency would
tend to rise and UI rate would decline correspondingly, till equilibrium is reached wherein
the marginal generation cost of every state would equal the UI rate.
CHAPTER 6 A TRADING OPPORTUNITY UNDER THE
7/30/2019 Major Report on Energy Mgt
31/79
SHADOW OF ENERGY MANAGEMENT
Let us refer fig. Given below. The two areas marked 'X' represent the off peak hour
capability of the central generating station , which State-C has not requisitioned, although
within its entitlement . The trading opportunities can be encashed both by the Generator as
well as Beneficiary , which are as under:
6.1 Trading Opportunity to be Availed by the GENERATOR
The capability (160MW) is now available with the Central Station and it has three options
before it ,which are as follows:
I. Back down the station during off peak hpurs,. I.e. Generate power onlyaccording to the schedule given by RLDC by aggregating the rerusition of the
three states.In this case , the station gets capacity charge for the day corresponding
to its availability declaration (900 MW) and energy charge to fully recover its fuel
cost for generating the scheduled quantum of energy during the day.
II. Find a buyer ( other than State -C) for the above off - peak surplus and generate
power adding the MW agreed to be taken by this buyer to the aggregate schedule
for states - A,B and C. A s the station is already being paid capacity charges for
900 MW, it may not be too particular about further fixed cost recovery. As long as
the energy agreed upon is higher than the fuel cost per KWh of the station , it
would be beneficial for the station to enter into such a deal. I t would also reduce
the technical problems associated with backing down of the station and improve
the station's efficiency.
III. Instead of selling the off- peak surplus power through a bilateral agreement as
described above , the station may accept the schedule given by RLDC, but
generate power to its full capability of 900 MW even during off peak hours .The
result would be an over supply of 160 MW ( as a deviation from schedule) , for
which the station would get paid from the regional UI pool account at the
prevailing UI rate. In fact , it would be a stale to the regional pool and would
make a financial sense as long as the prevailing UI rate is higher than the fuel cost
per KWh of the station.
6.2 Trading Opportunity to be Availed by the BENEFICIARY
7/30/2019 Major Report on Energy Mgt
32/79
The above options for the generating stations arise only in case a state has not requisitioned
its full entitlement . In fact, the same three options are available to State -C , before they
get passed on to the Central station and are as follows:
i. Requisition power from the Central station only as per its own requirement and
draw power as per the resulting schedule.
ii. Requisition full entitlement from the Central station for the entire 24- hour period,
find a buyer for the off peak surplus and schedule a bilateral sale. This would
make sense as long as the sale rate per kWh is more than the energy charge rate of
the Central station.
iii. Requisition the full entitlement for the entire 24 - hour period , but draw power
only according to its actual requirement. In fact , this would be a pre-planned
deviation from schedule for which State - C would get UI payment. A ll that State
- C has to watch for and be vigilant about is that UI rate during the off- peak hours
remains above the energy charge rate of the Central Station . In case the
frequency rises and UI rate falls below the energy charge rate of the concerned
Central station , State -C shuld reduce its requistion and thereby stop under -
drawing.
The above methodology for trading shows that under the Energy Management regime
there are equal opportunities both for Generator as well as Beneficiaries.
CHAPTER 7 OPEN ACCESS , WHEELING AS AN
7/30/2019 Major Report on Energy Mgt
33/79
IMPORTANT TOOL OF ENERGY MANAGEMENT .
7.1 Open Accessand Wheeling
Open Access and Wheeling are supposed to be one of the important tools as far as
Interstate trading is concerned.Without these components , it is not possible to go in for
trading between the two utilities . The following reasons attribute to the necessity of such
tools formanaging energy in Interstate trading:
1. When utility 'A' trades power to utility 'B' and both are at different places, then
Utility A has to take open access from the utility whose system shall be used by A
to make the power available at the periphery of B and for such open access , A has
to pay Wheeling charges to the owner whose system A is using.
2. Without this arrangement , the transactions of power so made shall lead to
litigations as there is a chance for many disputes to arise.
OPEN ACCESS and WHEELING generally involve two parties , One supplying a certain
quantum of power to the other through the regional / state grid. Any such transactions
involves a number of parties and disputes could arise in scheduling , energy accounting and
commercial settlement , unless an appropriate framework is in place.
Let us take a case where party A has contracted to supply 10 MW round the
clock to party B at a certain price. Party A has to transact that power through regional Grid
system to make that power available at the periphery ofparty B . Since , the losses in the
system are expected to the tune of .5 MW , A has to bear these losses also as per contract to
supply power at the periphery of B. In such a deal A shall bear expenditure of loss as well as
pay wheeling charges to the regional grid system so as to settle the transaction without
litigation.
A contracted sale or purchase involves the following:
Identification of counterpart
Agreeing on power quantum, duration, price and other terms
Ascertaining the adequacy of transmission system
Payment of applicable transmission / wheeling charges and absorption of
7/30/2019 Major Report on Energy Mgt
34/79
wheeling losses
Day ahead scheduling through SLDC/RLDC concerned.
Payment security for transaction.
An agreement is also executed between both the parties which ensures commitment by both
the parties to ensure transaction of power as per terms and conditions of the agreement
without litigation.
7.2 Issues Involved in the Transactions
There may be certain constraints in supplying powers which are as under:
There may be a chance that a seller fails to schedule the supply of the agreed
quantum of power due to short fall in its own power availability or the buyer fails to
schedule the drawal of the agreed quantum of power due to fall in its requirement , it
will mean a contractual default . The agreement between the parties must specify as
to how much defaults can be handled .
Another issue would be as to how a party selected its counterpart and agreed on the
price and whether these have been done judiciously.
Required checks and balances may even delay the finalization of agreement and
trading opportunities may be missed.
Regarding settlement of above issues one may adopt the route of
UI , but it may lead to other complications as there is no certainty of the price and further
RLDC may ask to curtail the supply due to transmission constraint. However, it has the major
advantage such as there is no commitment about the quantum. A lso no question can be raisedon price from audit angle. Thus UI rate provides an alternative to "Open Access" and
"Wheeling" and can be taken when one prefers flexibility over certainty .
7/30/2019 Major Report on Energy Mgt
35/79
CHAPTER 8 POWER EXCHANGE IMPLEMENTATION
IN INDIA
8.1 Introduction
In line with the mandate provided by the Indian Electricity Act 2003 and the National
Electricity Policy , the Central Electricity Regulatory Commission (CERC) has issued a
number of Regulations to facilitate trading and introduction of competition in the
Electricity Sector in the country . Open Access in inter-state transmission was introduced
in May 2004 which facilitated the development of the bilateral market in the country.
The responsibility for the development of the Electricity Market in the country has beenentrusted to the Appropriate commission as per electricity act 2003 . The Indian electricity
grid code was introduced in Feb 2000 with subsequent revision in April,2006 and the
settlement system was introduced in 2002-2003 . The ABT mechanism provided the
framework for scheduling and handling of imbalances . These two building blocks together
provided the basic rules for system operation and the commercial settlement . Open Access
in interstate transmission was introduced in May 2004 and gave birth to bilateral market in
the country. On the basis of such developments , CERC issued guidelines for
establishment of Power Exchange in Feb 2007 and in principal approval ws granted to the
first Power Exchange in August 2007.
8.2 Regulatory Framework for power exchange Implementation
The Open Access in the Interstate Transmission Regulations 2004 provided only for the
bilateral Transactions and the system of application of transmission charges was in Rs. /
MW/Day. These methodologies for transmission charges & Losses were not conductive to
the operation of a common platform for electricity trading i.e power Exchange operations.
So necessary amendments in the regulation was required for implementation of Power
Exchange . Accordingly, the regulation s for Open Access in Interstate Transmission were
revised by CERC to include Collective Transactions Discovered on a Power Exchange and
anew regulation became effective fro 1st April 2008. So , the CERC Open Access
Regulations , 2008 made the following provisions :
a . Transactions were categorized as Bilateral and Collective ( through PowerExchange)
7/30/2019 Major Report on Energy Mgt
36/79
b. Nodal Agency for two types of transactions was identified. National Load
Despatch Centre (NLDC) was designated as nodal agency for Collective
Transactions . The Regional Load Despatch Centres (RLDC) were the
designated agencies for bilateral transactions.
c. Transmission losses were applied at both the points of injection and drawal .
The sellers are required to inject more and the buyers draw less than the
traded quantum to compensate for losses.
d. Regulations placed great emphasis on the empowerment of the SLDCs. NOC/
Standing clearance was required to be obtatined by State Utilities / Intra - State
Entities from the SLDC. The SLDCs are obliged to respond within 3 days to
any request for an NOC as per the regulations. The SLDC may charge an
appropriate fee for such NOC/ Standing Clearance .
e. T he methodology of application of transmission charges moved from 'Contract
Path' to a methodology closer to the 'Point of Connection' Charges ' for
collective transaction.
f. Operating charges for collective transactions @ Rs. 5000 per day per entity
involved are applied. All buyers within a state are clubbed together into one
group and all sellers within a state are clubbed together into another group by
the power exchange . Each group of buyers and sellers is counted as a separate
entity for scheduling and leavy of operating Charges.
8.3 Power Exchange Implementation in India
The power exchange in India has many features such as Voluntary participation, Day ahead
transactions , Physical delivery of Energy , Double sided bidding , Hourly bids ,
Uniform pricing , Multiple Exchanges envisaged and Congestion Management .
8.4 Functional Power Exchange
Indian Energy Exchange ( IEX ) , the country's first power exchange , made an application
for grant of permission to setup a Power Exchange in March 2007 and an in- principle
approval was accorded by the CERC on 31st August 2007 . IEX commenced operation
from the 27th June 2008 after the Rules and Bye Laws were approved by CERC and
7/30/2019 Major Report on Energy Mgt
37/79
permission was granted to commence operations . The second Power Exchange of India
(PXIL) was granted in- principle approval on 27th May 2008 . PXIL went through a
process of Regulatory approval similar to that of it's predecessor and it commenced
operations on 22nd October 2008.
8.5 Competition among Exchanges
The Regulators have provided for multiple Power Exchanges to exist simultaneously in one
physical market . Light handed regulation has been adopted and the Power Exchanges have
been given full functional autonomy. This allows for competition amongst the existing
Power Exchanges and an automatic system of checks and balances .The charges collected
by the power exchanges for the services rendered are automatically regulated by the market
forces.
8.6 Information Exchange between NLDC and Power Exchanges
The exchange of information is fully automated between NLDC and Power Exchanges ,
NLDC and the Regional Load Dispatch centers (RLDCs) . The bidding window for
submission of bids in the Power Exchange is from 1000 Hrs. to 1200 Hrs. Information is
exchanged between NLDC , Power Exchange and the RLDC as per a protocol defined in
the procedure for Scheduling of collective Transactions . A provisional solution is given by
the Power Exchanges to the NLDC at 1300 Hrs for congestion if any. In case of
congestion , NLDC advises the Power Exchanges about the limits of scheduling . The
Power Exchange submits the application for scheduling of collective Transactions by
1500Hrs and the approval for scheduling is communicated by NLDC by 1730 Hrs.
8.7 Regulations governing the process of Energy Management
The following regulations/codes govern the process of procurement o/ disposal of power:
0 Central Electricity Regulatory Commission (Unscheduled Interchange
charges and related matters) Regulations, 2012.
1 Central Electricity Regulatory Commission (Indian Electricity Grid Code
Regulations, 2012.
2 Central Electricity Regulatory Commission (Sharing of inter-StateTransmission Charges and Losses) (Second Amendment) Regulations, 2012.
7/30/2019 Major Report on Energy Mgt
38/79
3 CERC(Terms and Conditions for Tariff determination from Renewable
Energy Sources) Regulations, 2012.
4 Indian Electricity Grid Code Regulations, 2010
5 Terms and Conditions of Tariff, Regulations for 2009-14
7/30/2019 Major Report on Energy Mgt
39/79
SECTION -II
ENERGY MANAGEMENT
HPSEBL
AS
A SPECIAL CASE
7/30/2019 Major Report on Energy Mgt
40/79
CHAPTER 1 STATUS OF SLDC IN HPSEBL
1.1 Setting up SLDC/SUB-LDCs in Himachal Pradesh
In compliance to the decision of Govt. of India, HPSEBL under ULDC Scheme, incoordination with PGCIL established a State Load Despatch & Communication Centre
(SLDC) at Shimla and 1No. Sub-LDC at Kunihar and 1No. Sub-LDC at Hamirpur with
RTUs at different locations.
7/30/2019 Major Report on Energy Mgt
41/79
Fig 3. Location of SLDC and Sub-LDCs in Himachal Pradesh
The hierarchical structure of SLDCs and Sub-LDC is also given in the fig. below which
presents the load centers in Himachal Pradesh alongwith the location of their respective
RTUs (Remote Terminal Units) situated at different locations . These RTUs are mostly
connected to their Sub-LDCs through Power Line Carrier Communication System and
further to SLDC through wideband system.
7/30/2019 Major Report on Energy Mgt
42/79
Fig.4 Hierarchical Structure of SLDC & Sub- LDCs
1.2 Sub-LDC at Kunihar
It comprises 8 No. RTUs(Remote Terminal Units) installed at different locations inthe upper reaches of Himachal Pradesh :
0 Kunihar
1 Bhaba
2 Jeori
3 Giri
4 Andhra
5 Solan
6 Jutogh
7 Baddi
The connectivity of the above stated RTUs is as shown in the fig. below. The RTUs are
connected to SUB-LDC Kunihar through PLCC link. Each RTU is provided with a modem
which converts digital signal into analog signal. The analog signal, thus transmits through
PLCC system upto SUB-LDC. After reaching SUB-LDC, again the signal is converted into
digital signal with the help of modem which are placed in the equipment called
CFE(communication front end). The signal after its conversion to digital form, enters theMUX placed in the control room of SUB-LDC where it gets multiplexed and enters
OLTE(optical line terminal equipment) where the digital/electrical signal is converted into
optical signal and transmits through OPGW(optical ground wire) and reaches SLDC Jutogh
where the signal again enters OLTE at Jutogh at the rate of 155 mbps as an optical signal
and further enters MUX as digital/electrical signal at the rate of 2 mbps and gets
demultiplexed when it comes out from the MUX .Here the signal gets divided into two
parts. First part is a signal of 64kbps which enters the exchange through MDF(main
distribution frame) and facilitates speech, whereas the second part of the signal is of 19.2
kbps which enters the HUB of control room at Jutogh as data signal and is processed with
the help of SCADA system.
7/30/2019 Major Report on Energy Mgt
43/79
Fig.5 SUB-LDC KUNIHAR (Connectivity of RTUs)
7/30/2019 Major Report on Energy Mgt
44/79
1.3 Sub-LDC at Hamirpur
It comprises 10 No. RTUs(Remote Terminal Units) installed at different locationsin the upper reaches of Himachal Pradesh :
8 Hamirpur-I
9 Hamirpur-II
10 Dera
11 Kangra
12 Malana
13 Jassore
14 Bassi
15 Mandi
16 Kangoo
17 Largi
The connectivity of the above stated RTUs is as shown in the fig. below. All RTUs are
connected to SUB-LDC Hamirpur through PLCC link except Kangoo which is connected
through wideband link. Each RTU is provided with a modem which converts digital signal
into analog signal. The analog signal, thus transmits through PLCC system upto SUB-
LDC. After reaching SUB-LDC, again the signal is converted into digital signal with the
help of modem which are placed in the equipment called CFE(communication front end).
The signal after its conversion to digital form, enters the MUX placed in the control room
of SUB-LDC where it gets multiplexed and enters OLTE(optical line terminal equipment)
where the digital/electrical signal is converted into optical signal and transmits through
OPGW(optical ground wire) and reaches SLDC Jutogh where the signal again enters
OLTE at Jutogh at the rate of 155 mbps as an optical signal and further enters MUX as
digital/electrical signal at the rate of 2 mbps and gets demultiplexed when it comes out
from the MUX .Here the signal gets divided into two parts. First part is a signal of 64kbps
which enters the exchange through MDF(main distribution frame) and facilitates speech,
whereas the second part of the signal is of 19.2 kbps which enters the HUB of control room
at Jutogh as data signal and is processed with the help of SCADA system.
7/30/2019 Major Report on Energy Mgt
45/79
7/30/2019 Major Report on Energy Mgt
46/79
Fig.6SUB-LDC HAMIRPUR (Connectivity of RTUs)
7/30/2019 Major Report on Energy Mgt
47/79
1.4 Interconnectivity of SLDC & SUB-LDCs of H.P.
Fig.7 INTER CONNECTIVITY DIAGRAM OF SLDC -
SUB-LDCs OF H.P.
The above diagram shows interconnectivity of SLDC Shimla with SUB-LDC Hamirpur
and Kunihar. The data from Hamirpur reaches Kunihar on wideband system through
OPGW where it combines with data of SUB-LDC Kunihar and a combined data packet
reaches Jutogh through wideband system through OPGW and is processed in the control
room at Jutogh separately. Then afterwards,again a combined data packet comprising data
of SLDC Jutogh, SUB-LDC Hamirpur and SUB-LDC Kunihar takes its way to NRLDC on
OPGW through wideband system.
The combined connectivity diagram showing combined connectivity of both the
SUB-LDCs alongwith SLDC and RTUs of respective SUB-LDCs is as shown in the figbelow.
7/30/2019 Major Report on Energy Mgt
48/79
The figure shows the connectivity between RTUs and SUB-LDCs on
PLCC system and between SUB-LDCs and SLDC on wideband through OPGW. The
connectivity of Kangoo substation is on wideband system. The communication through
wideband system has been experienced to be more reliable than through other mode of
system. In the existing SUB-LDCs, there is enough provision for future expansion. Thesystem will prove its worth when atomization shall come into existence.
Fig.8 COMBINED CONNECTIVITY DIAGRAM
CHAPTER2 BACKBONE TO COMMUNICATION
7/30/2019 Major Report on Energy Mgt
49/79
SYSTEMAT SLDC SHIMLA
2.1 Introduction
In the absence of certain tools, communication system standsnowhere. These tools act as backbone to the system and assists the system in all respects.
These are as under:
0 OPGW (Optical Ground Wire) and its Installation
1 PLCC System
2 PABX System
3 RTU
4 UPS
The details are as under:
2.2 OPGW and its Installation
OPGW provides overhead telecommunication system.
Fig.9 OPGW (Optical Ground Wire)
The central part of this cable is composed by a dielectric optical core comprising six fibres
stranded around a central support. An aluminium tube is extruded around this optical core
and the cable is finished with one or two layers of an aluminium clad steel. Tight Buffered
Optical Fibre (multi mode)
50 m Core
125 m
Optical Cladding
250 m
Primary Coating
50 m Core
Guided Light Propagation
Glas
Plastic
7/30/2019 Major Report on Energy Mgt
50/79
cable is used for cable routing within buildings. Typically containing around 16 fibres (12
cores, 4 cores and 8 cores are also common) this type of cable offers ease of installation
and fibre protection suitable for internal use. each of the fibres within the cable is
individually protected by a plastic coating with kevlar strengthening and sheathing giving
overall protection. Low Smoke Zero Halogen Sheaths are common in this type of cable. To
withstand harsher external conditions Loose Tube cables are used for outside installations
in duct work or trenches. As the name suggests groups of fibres are suspended in a gel
filled tube within a heavily protected cable. As the fibre has no physical contact with the
tube it is less prone to damage during the stresses associated with installation and
temperature contraction and expansion. The gel used within the tubes protects against the
ingress water. Many different fibre counts are available as few as four or as many as 96
cores are common. Thus origination of OPTICAL fibre has made communication system
reliable and effective and acted as an efficient tool in the energy management syste
2.3 Testing of Optical Fiber Links
To test a link, the correct mating connectors must be fitted to the test leads.There are many
types of fibre connectors as each fibre type (multimode, single mode and POF) has its own
family of connectors. The most common types are ST, SC and SMA.
Before testing the link, you must know how much loss to expect at the wavelength of
interest. If you want accurate results, the testing should be performed at the wavelength at
which the fibre is to be used. Link loss can be readily calculated from the manufacturers
data (loss per unit length in dBs), the actual link length, and the number of connectors and
joints (if any) in the link. Without this data, you cannot determine whether or not the links
performance is satisfactory. Do not assume there are no problems because a link works
when connected to the terminaL equipment. Some faults degrade link performance withtime (e.g. bad terminations).
7/30/2019 Major Report on Energy Mgt
51/79
Fig. 10 TYPES OF FIBRE CONNECTORS
2.4 Monitoring of Status of OPGW
The status of OPGW whether healthy or faulty is monitored by using the equipment
named as FLXER PLUS. This equipment confirms that the broadband is as per actual and
functioning properly. If there is fault in the OPGW network, the alarm appears on the map
of the network. The faulty part of the OPGW appears red on the screen of FLXER PLUS.
The following diagram represents the connectivity of FLXER PLUS and FLXER with
OPGEW map.
Fig.11 Test Diagram for Monitoring of Status of OPGW
The map on the screen of FLXER PLUS shows the network connectivity of different
stations connected through OPGW appears as under:
Fiber Optic Connectors
F
C
P
C
FCPC
SCPC
STPCSCPC
FLXER
PLUS
FLX
150/6
FLX
150/6
Hamirpur Gaggal Kunihar Jutogh
7/30/2019 Major Report on Energy Mgt
52/79
Fig. 12 Map of Network Elements of Different Locations
The details of status of different network elements are ascertained by using specific
commands on FLXER PLUS. If the status is healthy, the connectivity appears green and if
the status is unhealthy, the connectivity appears red.
2.5 PLCC System
PLCC system plays a vital role in the establishment of communication system. It
connects all the RTUs with SUB-LDCs. This is considered as one of the most economical
and reliable method of communication. In PLCC system, a bandwidth of 0-4 kHz is
confined to different applications as under:
The voice channel lies between 300 Hz to 2400 Hz.
The pilot frequency which is used for sending the dialling pulses and for the automatic
gain control of PLCC system lies within 3.57 kHz to 3.63 kHz.
The portion of band between 2.4 kHz to 3.57 kHz is used for data transmission on real
time basis.
It consists of two PLCC Terminals at two stations A and B connected together with the
help of HT transmission line and coupling equipment like wave traps (Line traps), coupling
capacitors, coupling devices and H.F. cable. For making data available of Solan substation
at Kunihar SUB-LDC, 2 No. Panels of BPL make, each at respective stations are placed
and are used for speech/data transmission of Solan Substation. At Solan end, the PLCC
panel is connected to RTU which collects various measurands of Solan substation and
transmit it through PLCC system upto Kunihar SUB-LDC and at Kunihar end the PLCC
panel is connected to CFE (Communication Front End) where the data from RTU is made
available for further processing.
The figures below shows the connectivity between RTU and SUB-LDC Kunihar in
between two stations and in between three stations. Incase of three stations, ie Giri, Solan
and Kunihar, the station Solan is called intermittent station and the connections of PLCC
Panels are made back to back, ie TX of one panel is connected to RX of other panel and
vice versa. For providing TX signal of -14 dB , oscillator is used and for measuring RX
signal of -20 dB, the level meter is used.
7/30/2019 Major Report on Energy Mgt
53/79
A typical arrangement is shown in fig below:
SOLAN KUNIHAR
TX TX
RX RX
RTU PLCC Panel PLCC Panel CFE
TX= -16 dB
RX= -20 dB
GIRI SOLAN KUNIHAR
RTU PLCC Panel PLCC Panel CFE
PLCC Panels
TX {Trans Signal} = -14 dB
RX {Receive Signal} = -20 dB
Fig. 13 Connectivity Between RTU and SUB-LDC Kunihar &Solan
2.6 PABX System
This system is one of the important tools in SLDC system which provides fast, reliable and
efficient telephone system which is an essential requirement for the power system grid
operation. All control centres are equipped with PABX (Private Automatic BranchExchange Network). Each PABX has a number of local and remote subscribers. In SLDC
7/30/2019 Major Report on Energy Mgt
54/79
Jutogh,
PABX system comprises 4 wire and two wire system. In the 4 wire
system, four wires are used for speech and two wires are used for signal, thus the four wire
system consists of total six wires. In the two wire system, the two wires are used for speech
and two wires are used for signal purpose. Thus, the two wire system comprises total four
wires. The PABX exchange is connected to the system through Main Distribution
Frame(MDF). It provides interconnection between exchange side and line side termination.
The implementation of integrated wideband telecommunication system network with PLC
and PABX procured under different contracts needs to be coordinated and requires careful
planning. The connectivity of PABX system with broadband system has made it possible
the communication between interstate SLDC units established at different corners in NR
Region. The requirement of PABX network in power system is unique.
With the development of wideband system it has become possible to
provide speech facility with the outside control centres also. This mode of communication
proves to be very economical as it involves initial cost of installation with very less
maintenance cost. The existing PABX exchanges are provided with a console which helps
in planning and programming at site and very easily one can provide new connections to
the utilities. These modern PABX systems are embedded with facilities such as provision
for future extension. In SLDC Shimla and in its respective SUB-LDCs, the PUNCOM
make exchanges have been provided. For maintenance purpose, AMCs (Annual
Maintenance Contract) have been given to the respective companies. The PABX exchange
in the existing system of SLDC Shimla provides speech communication to the remote
stations through PLCC system, to outside states through wideband system and within the
vicinity of SLDC campus through local subscribers.
7/30/2019 Major Report on Energy Mgt
55/79
Fig.14 PABX Room In SLDC Shimla
The most important part of the exchange is its MDF (main distribution frame). It is divided
into two parts. The upper half is called exchange side and the lower half is called line side.
The local extension and console connections are terminated on termination block E1.Trunk lines are terminated on block E2. Both of these termination blocks are called
exchange side termination blocks. Similarly, on line side extension to all local subscribers
are given through L1 and connections to trunks are terminated at L2. E1 & L1 and E2 & L2
are connected through jumpers.The connectivity of PABX exchange at SLDC Jutogh with
MDF and console which is designated as SUPCON is as shown in the fig below:
-48 VOLT DC
POWER INPUT
7/30/2019 Major Report on Energy Mgt
56/79
Subscribers
MDF
Trunks
POWER
UNIT
CONTR
OL
SERVICE
UNIT
TERMINAT
ION
7/30/2019 Major Report on Energy Mgt
57/79
Fig.15 The connectivity of PABX exchange at SLDC Jutogh with MDF
and console
The PABX exchange has four functional groups which are as under:
Power Unit
Control Unit
Termination Unit
Service Unit
A brief description of functional groups of PABX is as given below:
Power Unit: It consists of a power filter card which filters out -48 Volt DC supply.
The filtered power is fed to Power supply unit card which generates
+/- 5 V, 12V DC, -9V DC. PSU card also generates 75 volt (RMS)
ringer voltage which is extended to telephone. The filtered -48V is
also fed directly to termination unit.
Control Unit: It handles all call processing functions. It takes all decisions and
controls all the functions done within PABX. It comprises PFC card, P
01 card. The function of P 01 card is to provide serial RS-232
interfaces for operator console/dispatcher console and communication
with PFC card. The PFC card scans the signalling status of each card
of termination unit and sends them as message to P 01 card.
CONSOLE
7/30/2019 Major Report on Energy Mgt
58/79
Termination Unit:It provides interface with telephone instruments/other equipments.
The various types of interfaces are:
2-wire subscriber interface
4-wire E&M interface
2-wire centre office interface
30 channel digital interface
There is a unique card for each interface known as LCC card. Each
analog interface card comprises 8 ports and digital interface cardcomprises 30 ports.
Service Unit: It consists of ATD card which is used forannouncement and tones. A
conference card which has a facility to conduct conference of 6
parties.
All subscriber lines and trunks are interfaced to PABX system through the terminalinterface card. The terminal interface card consists of 8 termination ports. Such cards form
a terminal group which is designated as TG.
TG= 4 Terminal cards = 4 X 8 = 32 ports = 32 Channel
2.7 RTU (Remote Terminal Unit)It is one of the most important tools of SLDC. Without this it could not have been
possible to fetch the data from the remote stations and monitor the activities of the
remote stations. RTUs have made it possible to make many of the remote station
man less. They are playing very active role in making day to day availability of data
from the remote stations. One of the RTUs installed at 132 kv sub-station Jutogh at
Shimla is as shown on the next page:
When the RTUs were not devised, most of the potential of PLCC system remained
unutilised. The application of RTUs has made it possible to use the hidden potential
of PLCC in this age of state of Art. Transducers and MODEMs play a very
7/30/2019 Major Report on Energy Mgt
59/79
important role for the establishment of Real Time Data Acquisition system. This
system is designated with the abbreviation DAS and the whole combination of
making data available in real time operation at SLDC is designated as SCADA i.e.
Supervisory Control And Data Acquisition .RTU is a combination of transducers
used for various measurands such as voltage frequency, MW, MWh, MVARh and
converts electrical signal into digital signal which is further converted into analog
signal using modem if the same is to be transmitted through PLCC system or
otherwise the digital signal is sometimes directly processed without any conversion
if the same is to be transmitted through wideband system In power system there are
two types of measurands. One is analog type and the other is digital type. They are
as under:
0 Analog type measurands: Voltage, frequency, active power, reactive power,
position of auto transformer tap.
1 Digital type measurands: Status of circuit breaker and isolator (close/open)
The fig. Given below shows RTU at 132 KV substation Jutogh
7/30/2019 Major Report on Energy Mgt
60/79
Fig.16 RTU at 132 KV substation Jutogh
2.8 UPS (Uninterrupted power supply)
1.4.1 Uninterruptible Power Supply
Introduction
Uninterruptible power supply (UPS) is a device that protects electronic equipment from
power uncertainties. A UPS is a device that is interfaced between the electric network
(connected to utility power) and the materials that need protecting.
The UPS allows the materials to be switched to emergency battery power for several
minutes in case of electrical problems, in particular during:
http://en.kioskea.net/contents/protect/onduleur.php3http://en.kioskea.net/contents/protect/onduleur.php37/30/2019 Major Report on Energy Mgt
61/79
Power line disturbances, i.e. a split second power outage that can cause a computerto restart
Power outages, corresponding to a break in the power supply for a given amount oftime
Overvoltage, i.e. a nominal value greater than the maximum value needed for thenormal functioning of electrical appliances
Undervoltage, i.e. a nominal value less than the maximum value needed for thenormal functioning of electrical appliances
Voltage spikes, i.e. high amplitude transient (short-term) overvoltage. These spikesare caused when powerful devices are stopped or started and overtime can damage
electrical components
Lightening, which is a source of extreme overvoltage that occur suddenly duringbad weather (storms)
Most electrical disruptions are tolerated by computer systems. However, sometimes they
can cause data loss and service interruptions and even material damages.
The UPS helps to "smooth out" voltage, i.e. eliminate peaks that are over a certain level.
When there is a power outage, the energy stored in the emergency battery keeps the power
supply flowing to equipment for a small amount of time (normally for 5 to 10 minutes).
Beyond the minutes of autonomy that the UPS supplies, this gained time also allows the
equipment to be switched to other energy sources. Some UPSs can also be directly attached
to the computer (e.g. with a USB cable) so that it can order its own shutting off in case of a
power outage and thus avoid any data loss.
Fig. 17 General Outlook of UPS
Under ULDC scheme(Unified Load Despatch Scheme), the following capacity of UPS
have been installed to provide uninterrupted power supply and to have firm data.
a) At SLDC Shimla: 2 no. UPS each 40 kVA capacity have been installed at SLDC
Shimla. These UPS comprises two types of battery system, i.e. 384 V/200 Ah,
48V/415Ah respectively.
b) At Sub-LDC Hamirpur: 2 no. UPS each 20 kVA capacity have been installed at
SLDC Shimla. These UPS comprises two types of battery system, i.e. 384 V/200
Ah, 48V/415Ah respectively.
c) At Sub-LDC Kunihar: 2 no. UPS each 20 kVA capacity have been installed at
SLDC Shimla. These UPS comprises two types of battery system, i.e. 384 V/200
Ah, 48V/415Ah respectively.
7/30/2019 Major Report on Energy Mgt
62/79
In addition to above, at each site of SLDC, DG Sets of capacity 75 kVA at SLDC Shimla
and 45 kVA at respective SUB-LDC sites have been provided to have standby arrangement
for uninterrupted supply.
CHAPTER 3 ENERGY MANAGEMENT A "SPECIAL
CASE" OF HIMACHAL PRADESH.
3.1 Introduction
Himachal Pradesh being purely hydro state has surplus during monsoon months
but face acute shortages during winter as availability from hydro Stations reduces to
20 to 25% due to lean discharges and so happens to the Central Sector shares of
Hydro based projects of the region. As HPSEBs committed power is not adequate
to meet the demand as such HPSEBL meets its deficit demand by way of different
7/30/2019 Major Report on Energy Mgt
63/79
arrangements.
Fig. 18 ABOUT STATUS OF HIMACHAL PRADESH
3.2 Grid Diagram of Himachal Pradesh
7
7/30/2019 Major Report on Energy Mgt
64/79
Fig. 19 Grid Diagram of Himachal Pradesh
3.3 Modes of Managing Energy Deficits
1, GoHP (Govt. of Himachal Pradesh) free power entitlement in Central sector / Joint
sector projects as well as through GoHP entitlement available within the state.
2. 22% equity power of GoHP in NJPC project.
3. Through Banking arrangements.
4. Unscheduled Interchanges (Over Drawl) transactions under real time operation.
7/30/2019 Major Report on Energy Mgt
65/79
5. Unallocated quota allotted by Govt. of India during winter months.
3.4 Description of different modes of Power Arrangements
a. Central Sector Projects
HPSEBL receives power from central sector projects in proportion to its
entitlement and is governed under CERC regulation. This power is made
available at generator terminal of the respective projects and is wheeled
through Power Grid system till it is made available at H.P periphery. The bills
in respect of generator comprises two parts . One part is energy availed by
HPSEBL at generator terminal and the other part of the bill is raised by Power
Grid on account of wheeling of power through their system upto H.P
periphery. The quantum of energy which reflects in a monthly bill is based on
the Regional Energy account prepared by NRPC (Northern Regional Power
Committee).
b. Govt. of H.P. free power Entitlement:
Govt. of H.P.has its free power Entitlement in all those projects which have
been commissioned in Himachal Pradesh . This entitlement is on account of
the home state benefits i.e Himachal has sacrificed its potential as well as
benefits of the people. In addition to above entitlement of GoHP free power ,
HPSEBL also receives 22% equity during winter months or extended winter months
which is at the discretion of GoHP and is given to HPSEBL as its first right to
mitigate the shortages during the the said months.
c. Through Banking :
Transaction / procurement of Power through Banking is also one of the modes which
is considered as a cashless transaction and this energy exchange arrangement is on
equal basis i.e. the obligation of HPSEB to return the banked energy is restricted to
the extent to which the energy has been banked with it during the winter months. The
average rate as agreed as per agreements (Unscheduled Interchange rates based on
prevailing grid frequency conditions at that point of time) are kept to account for
7/30/2019 Major Report on Energy Mgt
66/79
unadjusted quantum at the end of banking cycle. This arrangement facilitates when
there is large variation in demand pattern during winters on account of fluctuating
weather conditions and provides real time operation and facilitates increase or
decrease of quantum with the mutual consent of both the parties without any
financial implications on either party. With the above arrangement the surplus power
available during the monsoon months is returned for meeting the previous year
banking obligations as well as for Advance Banking (contra banking) arrangement
thus facilitates mitigating winter deficits.
d. Unscheduled Interchange (UI):
This does not fall under any category of mode of transaction of power, but
under prevailing grid frequency conditions, power does flow perforce which
also provides additional assistance to mitigate the instantaneous shortage of
power. This perforce transaction of power is regulated as per CERC
regulation on Unscheduled interchange of power issued by Central Electricity
Regulatory Commission from time to time. However, the underdrawl
/overdrawl of power should not exceed the specific limit or otherwise, the
same shall lead to the collapsing of grid. It is also added that any violation
through UI against the prescribed norms shall lead to penalty to theconcerned utility.
e. Transaction of power through energy exchange:
In this mode of transaction of power, the surplus power available on day-
ahead basis is disposed off through exchange on the available rates. Similarly
through this mode, procurement of power is also carried out to meet the
immediate demand of shortages.
f. Sale/ purchase of power through Tendering process:
In this mode of transaction, bids are invited from different utilities for their
participation in the tendering process and the bidder who qualifies the desired
terms and conditions is given order for supply of power.
3.5 HPSEBL Share in different Projects
HPSEBL receives power throughout the year from the following projects against itsSOR(State of Region Share) share as shown in table below.
7/30/2019 Major Report on Energy Mgt
67/79
Table-1
Sr.
No. Name of Stations Installed HPs share
capacity % MW
MW (Mega
Watt.)
A.
HPSEBL
Entitlement
I.
BBMB
STATIONS
Bhakra old HP FIXED
10.00
(1.2LU/Day)
Bhakra complex 1478.73 7.19 84.23
Dehr 990.00 7.19 56.83
Pong 396 7.19 11.77
Bhakra (Old) Fixed
10.00
(1.2LU/Day)
II.
NHPC
STATIONS
Chamera-I 540.00 2.90 15.66
Tanakpur 94.20 3.84 3.62
Salal 690.00 0.99 6.83
Uri 480.00 2.71 13.01
Chamera-II 300.00 3.67 11.01
Chamera-III 231 4.36 10.06
Dhauliganga 280.00 3.57 10.00
III. NTPC
7/30/2019 Major Report on Energy Mgt
68/79
PROJECTS
Rihand-I 1000.