Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Prepared for:
Severn Trent Water Ltd
Severn Trent Water Ltd
Macclesfield Old Road, Buxton
Planning, Design and Access Statement
December 2009
Severn Trent Water
Macclesfield Old Road, Buxton
D122851/21B1
This document has been prepared in accordance with the scope of Scott Wilson's appointment with its client and is subject to the terms of that appointment. It is addressed to and for the sole and confidential use and reliance of Scott Wilson's client. Scott Wilson accepts no liability for any use of this document other than by its client and only for the purposes for which it was prepared and provided. No person other than the client may copy (in whole or in part) use or rely on the contents of this document, without the prior written permission of the Company Secretary of Scott Wilson Ltd. Any advice, opinions, or recommendations within this document should be read and relied upon only in the context of the document as a whole. The contents of this document do not provide legal or tax advice or opinion.
© Scott Wilson Group PLC 2007
Scott Wilson West One Wellington Street Leeds LS1 1BA Tel: 0113 204 5000 Fax: 0113 204 5001 www.scottwilson.com
Erection of two control kiosks, a lifting gantry, pole mounted task lamp, vent stack, stone wall and alterations to an existing field access and vehicle turning area at land south of Bishops Lane, Buxton Macclesfield Old Road, Buxton December 2009
Rev Date Details Prepared by Reviewed by Approved by
01 Dec 2009 Final David Stephenson Graduate Planner
Matthew Smedley Principal Planner
Alex Smith Associate
Severn Trent Water
Macclesfield Old Road, Buxton
D122851/21B1
Table of Contents
1 Introduction ....................................................................................... 1
Need for Development.................................................................................................... 1
2 Site Description and Setting .............................................................. 2
3 The Development Proposals ............................................................. 3
Location.......................................................................................................................... 3
Layout............................................................................................................................. 3
Scale and Massing and Appearance............................................................................... 3
Access............................................................................................................................ 4
Construction ................................................................................................................... 4
Post Construction ........................................................................................................... 4
Environmental Considerations ........................................................................................ 4
4 Planning Policy Context..................................................................... 6
National Planning Policy ................................................................................................. 6
Regional Planning Policy ................................................................................................ 6
Local Planning Policy...................................................................................................... 6
Appraisal ........................................................................................................................ 7
5 Summary........................................................................................... 9
Appendix 1: Site Photographs.................................................................... 10
Planning, Design and Access Statement December 2009 1
1 Introduction
1.1 Severn Trent Water Ltd (STWL) is a regulated business with statutory responsibilities for the
provision of water and sewerage services to over 8 million people in an area stretching from the
Severn Estuary to the mouth of the Humber.
1.2 Severn Trent Water is currently implementing its Asset Management Plan for April 2005 to
March 2010 (known as AMP4), which is the mechanism by which the regulator OFWAT defines
a 5-year capital expenditure program for water companies. Investment during the AMP4 period
is in response to a number of key drivers. These drivers include new environmental and quality
obligations, and investment to ensure our existing water distribution and sewerage networks,
and other assets both above and below ground, operate efficiently and effectively.
1.3 This Planning, Design and Access Statement has been prepared for STWL to accompany a full
planning application for the erection of two kiosks, a lifting gantry, pole mounted task lamp, vent
stack, stone wall and alterations to an existing field access and vehicle turning area at land
south of Bishops Lane, Buxton.
1.4 The above is required in association with an underground flow meter chamber, valve chamber
and DIA storage tank and underground pipework.
1.5 Article 6 of the Town and Country Planning (General Development Procedure) (Amendment)
(England) GPDO 2006 now requires that planning applications be accompanied by a Design
and Access Statement. The appropriate criteria are addressed within the context of this
document. The following aspects are the main underlying principles; location, layout, scale and
massing, appearance, landscaping and access.
1.6 This document clearly sets out these topics and discusses and appraises how they relate to
this application.
Need for Development
1.7 The proposed development is required to alleviate internal property flooding at various
locations on Macclesfield Old Road. As such, a localised solution is required and comprises of
new below ground shaft storage tank and pumping station with above ground kiosks, lighting
and vent facilities. The proposed works shall prevent internal and external flooding to local
private properties up to a 40 year storm event.
1.8 The following drawings are submitted in support of the planning application:
• S388771-PA-002 Rev E – Planning Application Drawing
• Phase 1 Ecology Survey (Grontmij, November 2007)
• Phase 2 Ecology Survey (Grontmij 2008)
1.9 This document will continue by providing a site description in Section 2 and detailing the
proposed development in Section 3. Section 4 will appraise this application against national,
regional and local planning policy.
Planning, Design and Access Statement December 2009 2
2 Site Description and Setting
2.1 The site is located on an area of undulating, undeveloped land to the south of Bishops Lane,
Buxton.
2.2 Bishops Lane is situated in Burbage on the western edge of Buxton.
2.3 Macclesfield is approximately 8 miles to the west, Chapel-en-le-Frith is 6 miles to the north and
Bakewell is approximately 10 miles to the south east.
2.4 The immediate area is rural in character, mainly consisting of open fields to the south and west
and the residential area of Buxton to the north and east.
2.5 There is a golf course within 500m to the north and Stanley Moor Reservoir approximately 1km
to the south. The Peak District National Park border is west of the site.
2.6 Please refer to drawing no. S388771-PA-002 Rev E for a Location Plan.
2.7 Access to the site will be taken from the adjacent highway (Bishops Lane). Existing access
arrangements to the field are to be improved as part of the proposals.
2.8 The site is located within Flood Zone 1 of the Environment Agencies Flood Risk Map. There is
a small stream which runs north to south adjacent to the site’s western boundary and is located
in Flood Zone 2.
2.9 The site is outside of Buxton’s development boundary and therefore designated as countryside
within the High Peak Local Plan (Adopted March 2005). The site is also adjacent to a Special
Landscape Area (to the west) and Conservation Area (to the north east).
Planning, Design and Access Statement December 2009 3
3 The Development Proposals
3.1 The erection of two kiosks, a lifting gantry, pole mounted task lamp, vent stack, stone wall and
alterations to an existing field access and vehicle turning area at land south of Bishops Lane,
Buxton.
3.2 One kiosk will be a telemetry control kiosk and the other will be for the storage of safety
equipment when not in use by STWL operatives. The lighting column is required to illuminate
the pumping station area to allow for safe maintenance (particularly in winter months).
3.3 The above is required in association with underground flow meter chamber, valve chamber and
DIA storage tank and underground pipework. These will not require planning permission as
they constitute permitted development under Part 16, Class A (a) of the Town and Country
Planning (GPDO) Order 1995:
‘Development by or on behalf of a sewerage undertaker consisting of (a) development not
above ground level required in connection with the provision, improvement, maintenance
or repair of a sewer, outfall pipe, sludge main or associated apparatus.’
Location
3.4 The site is located on an area of undeveloped land to the south of Bishops Lane, on the
western edge of Buxton.
Layout
3.5 The site will comprise of an improved access from the north of the site and an internal access
track with turning area running along the western boundary. Two kiosks and a lighting column
will be erected to the east of the site and a vent stack will sit on the site’s northern boundary.
The underground chambers will run in a line down the centre of the site. Existing hedgerows
will provide screening along the north and east boundary.
Scale and Massing and Appearance
3.6 One kiosk will be a telemetry control kiosk and the other will be for the storage of safety
equipment when not in use by STWL operatives. The kiosks will be 2m x 0.6m x 1.5m high,
constructed from Glass Reinforced Plastic and coloured holly green to BS 4800 shade 14-C-
39.
3.7 The vent stack will be ‘swan necked’ and 0.6m high.
3.8 A task lamp will be mounted on a 100mm diameter galvanised pole, 3m high, to provide
background task lighting to the compound during operational and maintenance visits. It is
activated by a manually operated switch located inside a control kiosk and anticipated that the
light will only be used in response to operational emergencies (i.e. pump failure during periods
of low natural light).
Planning, Design and Access Statement December 2009 4
3.9 The lifting gantry will comprise a horizontal lifting beam and mounted on two vertical columns. It
will be 2.5m high and used to aid safe lifting and removal of pumps from the storage tank
during routine maintenance visits and emergency situations. Elements of the mechanical lifting
aid will be required for the operation of the storage tank.
3.10 The colour of the vent stack, lifting gantry and pole mounted task lamp will be agreed with the
Local Planning Authority during the planning application.
3.11 The stone wall will be the same height, appearance and materials as the existing.
3.12 The access track will be constructed from grasscrete with a concrete entrance off the highway.
The use of small sections of concrete hardstanding will be required for operational safety (i.e.
outside the kiosk and around access covers).
Access
3.13 Access to the site will be taken from the adjacent highway (Bishops Lane). Existing access
arrangements to the field are to be improved as part of the proposals.
Construction
3.14 Construction is anticipated to commence on receipt of planning permission and due to be
completed within six months.
3.15 A full construction timetable is unavailable at this time, however anticipated vehicle movements
during this period are expected to include an excavator, 18 tonne lorry and delivery vehicles.
Post Construction
3.16 The proposed works will not result in a significant increase in traffic movements. Occasional
visits by STWL maintenance vans will be required for inspection of the Sewage Pumping
Station.
Environmental Considerations
3.17 Baker Shepherd Gillespie produced a Phase 1 Habitat Survey in November 2007. Due to
seasonal constraints a further Phase 2 botanical survey was recommended at an appropriate
time of year, this was subsequently undertaken in August 2008.
3.18 The recommendations of the Phase 1 survey are listed below:
• If the proposed works requires disturbance of the brook and its associated features, then it
is recommended that further survey work is carried out, in order to determine the presence
of water voles and crayfish.
Planning, Design and Access Statement December 2009 5
• If the pipeline is likely to involve the clearance, during the bird breeding season, of the
woodland or scrub habitat then there is potential for an adverse impact. Recommendations
are therefore made regarding the timing of the works working practices.
• Given the potential for roosting bats, the removal of tress should be avoided.
3.19 The Phase 1 survey states ‘whilst it is noted the site does not contain suitable breeding habitat
for Great Crested Newts, further detailed survey work is required to determine the presence of
GCN due to the connect and proximity of the pond to the site’. However, following further
discussions between Grontmij engineers and BSG ecologists the need for a newt survey was
discounted as the pond in question is an artificial ornamental pond which contains fish and is
not believed to be connected to the watercourse. Therefore, only further surveys with regards
crayfish and vegetation were considered necessary and are addressed in the context of the
Phase 2 Survey.
3.20 The Phase 2 Survey makes the following recommendations:
• With regards to the semi-improved grassland, it is recommended that the relining technique
is used in order to prevent any loss to the neutral grassland habitat. Further
recommendations are also regarding the methodology during the construction period.
• If the works are to affect the watercourse directly, it is recommended that further survey
work involving a manual daytime search for crayfish is carried out to determine the presence
of crayfish in the stream, prior to the start of works.
3.21 Severn Trent Water will adhere to all recommendations outlined in the Phase 1 and Phase 2
Habitat surveys.
Planning, Design and Access Statement December 2009 6
4 Planning Policy Context
National Planning Policy
• PPS1: Delivering Sustainable Development;
• PPS10 Planning for Sustainable Waste Management; and
• PPS25: Flood Risk and Development.
Regional Planning Policy
The Derby and Derbyshire Joint Structure Plan (2001 – Saved September 2007)
4.1 The Derby and Derbyshire Joint Structure Plan (January 2001) sets out strategic policies for
the scale and general location of development to 2011. The following policies are relevant:
• Environment Policy 1: Landscape Character.
Local Planning Policy
Adopted Derbyshire Waste Local Plan (March 2005)
• Policy W1b Need for the development;
• Policy W6 Pollution and related nuisances; and
• Policy W7 Landscape and other visual impacts.
High Peak Borough Council Local Plan
4.2 The site is not allocated or designated within the High Peak Local Plan (adopted March 2005).
However, the following policies apply:
4.3 Policy OC1 - Countryside development states the countryside will cover all land beyond the
built-up area boundaries defined on the proposals map, including the green belt and special
landscape area. Within the countryside, planning permission will be granted for development
which is an integral part of the rural economy and which can only be carried out in the
countryside provided that individually or cumulatively:
• the development will not detract from an area where the open character of the countryside is
particularly vulnerable because of its prominence or the existence of a narrow gap between
settlements; and
Planning, Design and Access Statement December 2009 7
• the development will not generate significant numbers of people or traffic to the detriment of
residential amenity, highway safety, landscape or air quality or otherwise have an
unacceptable urbanising influence; and
• The development will not have a significant adverse impact on the character and
distinctiveness of the countryside policies relating to specific categories of development
acceptable in the countryside can be found under individual topic headings elsewhere in the
plan.
4.4 Policy BC5 - within Conservation Areas and Their Settings planning permission will be
granted for development, including extensions, alterations and changes of use, provided that
the listed criteria are met.
4.5 Policy OC3 - Special Landscape Area Development states within the special landscape area
defined on the Proposals Map, development in accordance with policies OC1 and OC2 will be
permitted, provided that it will not detract from the special qualities and character of the special
landscape area. Where development is permitted in the special landscape area the developer
will be required to have special regard to the landscape quality of the area in relation to siting,
design and landscaping.
4.6 Policy GD4 – Character, Form and Design states planning permission will be granted for
development, provided that its scale, siting, layout, density, form, height, proportions, design,
colour and materials of construction will be sympathetic to the character of the area and there
will not be undue detrimental effect on the visual qualities of the locality or the wider landscape.
4.7 Policy BC1 – External Materials notes planning permission will be granted for development,
provided that the type, colour and specification of all external materials and the way they are
applied will be sympathetic to the character and appearance of the immediate surroundings
and the wider area.
4.8 Policy TR5 – Access, Parking and Design notes planning permission will be granted for
development, provided that it includes a high standard of design and layout having regard to
the parking, access, manoeuvring, servicing and highway guidelines and relevant government
guidance and good practice, where appropriate.
4.9 Paragraphs 10.24 – 10.28 also seek to ensure adequate utility provision to the local plan area.
Appraisal
4.10 PPS10 and Policies W1b and W6 of the Derbyshire Waste Plan all provide for the development
of appropriate waste management facilities.
4.11 The proposed development is required to alleviate internal property flooding at various
locations on Macclesfield Old Road. As such, a localised solution is required and comprises of
new below ground shaft storage tank and pumping station with above ground kiosks, lighting
and vent facilities. The proposed works shall prevent internal and external flooding to local
private properties up to a 40 year storm event.
Planning, Design and Access Statement December 2009 8
4.12 The above ground structures have been reduced to a minimum necessary to meet operational
requirements. On completion, the scheme will offer significant benefits to the local community
by alleviating known flood issues and provide improved infrastructure at Old Macclesfield Road.
4.13 PPS1, Policy W7 of the Derbyshire Waste Plan and Policies GD4 and BC1 of the Local Plan all
promote sustainable development and a high quality of design which protects the local
environment. Policies OC1 and OC3 seek to protect the countryside and adjacent special
landscape area.
4.14 The design of the development has been carefully considered to respect the developments
setting within the residential area of Buxton and adjacent to a Special Landscape Area. The
operational structures have been reduced to a minimum necessary for operational
requirements.
4.15 The kiosks will be 1.5m high and have been positioned to ensure they benefit from natural
screening provided by hedgerows to the north and east of the site. They have also been
coloured holly green to blend with their surrounds. The access track will be constructed in
grasscrete thus significantly reducing the amount of hardstanding areas at the site. The lifting
gantry, pole mounted task lamp and vent stack have been redesigned to ensure they are not
visually obtrusive on the surrounding landscape whilst still maintaining their operational
function.
4.16 Owing to the site’s location, distances involved and scale of the above ground structures, the
proposed development will have no adverse impact on the Conservation Area to the north east.
4.17 In light of the above it is considered that this application adheres to national, regional and local
planning policy.
Planning, Design and Access Statement December 2009 9
5 Summary
5.1 This Planning, Design and Access Statement has been prepared for STWL to accompany a full
planning application for the erection of two kiosks, a lifting gantry, lighting column, vent stack
and alterations to an existing field access and vehicle turning area at land south of Bishops
Lane, Buxton.
5.2 The proposed development is required to alleviate internal property flooding at various
locations on Macclesfield Old Road. As such, a localised solution is required and comprises of
new below ground shaft storage tank and pumping station with above ground kiosks, lighting
and vent facilities. The proposed works shall prevent internal and external flooding to local
private properties up to a 40 year storm event.
5.3 The site is located on an area of undeveloped land to the south of Bishops Lane, Buxton.
5.4 Access to the site will be taken from the adjacent highway (Bishops Lane). Existing access
arrangements to the field are to be improved as part of the proposals.
5.5 The site is outside of Buxton’s development boundary and therefore designated as countryside
within the High Peak Local Plan (Adopted March 2005). The site is also adjacent to a Special
Landscape Area (to the west) and Conservation Area (to the north east).
5.6 The above ground structures have been reduced to a minimum necessary to meet operational
requirements. On completion, the scheme will offer significant benefits to the local community
by alleviating known flood issues and provide improved infrastructure at Old Macclesfield Road.
5.7 The design of the development has been carefully considered to respect the developments
setting within the residential area of Buxton and adjacent to a Special Landscape Area. The
operational structures have been reduced to a minimum necessary for operational
requirements. The kiosks will be 1.5m high and have been positioned to ensure they benefit
from natural screening provided by hedgerows to the north and east of the site. They have also
been coloured holly green to blend with their surrounds. The access track will be constructed in
grasscrete thus significantly reducing the amount of hardstanding areas at the site. The lifting
gantry, pole mounted task lamp and vent stack have been redesigned to ensure they are not
visually obtrusive on the surrounding landscape whilst still maintaining their operational
function.
5.8 Owing to the site’s location, distances involved and scale of the above ground structures, the
proposed development will have no adverse impact on the Conservation Area to the north east.
5.9 The proposals comply with national, regional and local policy.
5.10 In light of the above it is respectfully requested that planning permission is granted for the
proposal outlined within this statement.