Load Calculation Presentation

Embed Size (px)

Citation preview

  • 8/13/2019 Load Calculation Presentation

    1/32

    AN-NAJAH NATIONAL UNIVERSITY

    FACULTY OF ENGINEERING DEPARTEMENT OF MECHANICAL ENGINEERING

    MECHANICAL SYSTEMS OF AL-OYOON HOSPITAL-NABLUS

    Graduation Project Submitted In Partial Fulfillment Of theRequirements For The Degree Of B.Sc. In Mechanical Engineering.

    Supervisor: The Students:Dr. Ramiz Alkhaldi Amin Udeh (10611326)

    Salem Hassoun (10615008)

    Omar Sabanah (10644946)Mohammad jawabri (10717105)

    May - 2011

  • 8/13/2019 Load Calculation Presentation

    2/32

    INTRODUCTION.

    Al-oyoon hospital, north of Nablus, located at the top of the north mountain at Nablus-Aseera street.

    The hospital has four departments A,B,C and D.

    In this project, only the mechanical systems of department A and C are calculated , A and C department has

    four stores , each one has an area of more than 2000 m 2.

    In this project, there is many mechanical systems was designed, like:

    HVAC systems (heating, cooling, ventilation, fresh air, exhaust are systems).

    Potable water system (hot water supply and return, cold water supply).

    Drainage system, Venting system, Fire fighting system, Medical gases system.

  • 8/13/2019 Load Calculation Presentation

    3/32

    1) HVAC SYSTEM :

    Hot water heating system :

    Hot water heating system consists of:

    Boiler.

    Piping net work.

    Expansion tank.

    Circulation pump.

  • 8/13/2019 Load Calculation Presentation

    4/32

    General procedure for calculating total heat load:

    Select inside design condition (Temperature, relative humidity).Select outside design condition (Temperature, relative humidity).Select unconditioned temperature.Find over all heat transfer coefficient Uo for wall, ceiling, floor, door,windows, below grade.Find area of wall, ceiling, floor, door, windows, below grade.Find Qs conduction.Find V inf , V vent .

    Find Qs, QL vent, inf.Find Q domestic hot water.Find Q total and Q boiler.

    The heating load calculation begins with the determination of heat lossthrough a variety of building envelope components and situations.

    1- Walls2- Roofs3- Windows4- Doors5- Basement Walls Basement Floors6- Infiltration Ventilation

  • 8/13/2019 Load Calculation Presentation

    5/32

    The Heat Loss Equation:

    Qs)cond = U* A* ( Ti - To ). Q s)vent = 1.2 V vent *(T i-To)

    Qs = Q s)cond + Q s)vent ......... Q boiler = (Q s+Q w)*1.1

    Uext = 1.24 W/m 2.oCU int = 2.53 W/m 2.oC

    Ti = 22 oCT o = 5.7 oC

    Uwind = 5 W/m 2.oC... U door = 3.6 W/m 2.oC

    Uceiling = 0.88 W/m 2.oC

    Where:

    U: overall heat transfer coefficientA: areaTi: inside design temperatureTo: outside design temperature

  • 8/13/2019 Load Calculation Presentation

    6/32

    Cooling Load Calculation:

    For ceiling :

    Q=U*A*(CLTD) corr

    Where:

    (CLTD) corr = (CLTD + LM) K + (25.5 Ti )+ (To 29.4)

    Where :

    CLTD: cooling load factor

    K:color factor:

    K=1 dark color

    K=0.5 light color

  • 8/13/2019 Load Calculation Presentation

    7/32

    For walls :

    Q=U*A*(CLTD) corr

    Where:

    (CLTD) corr =(CLTD + LM) K + (25.5 Ti )+ (To 29.4)

    Where :

    CLTD: cooling load factor

    K:color factor: K=1 dark color

    K=0.83 medium color

    K=0.5 light color

  • 8/13/2019 Load Calculation Presentation

    8/32

    For glass :

    Heat transmitted through glass

    Q=A*(SHG)*(SC)*(CLF)

    SHG: solar heat gain

    SC: shading coefficient

    CLF: cooling load factor

    Convection heat gain:

    Q=U*A*(CLTD) corr

    (CLTD) corr = (CLTD)+(25.5 Ti )+ (To 29.4)

  • 8/13/2019 Load Calculation Presentation

    9/32

    For people :

    Qs=q s*n*CLF

    qL=qL*n

    where:

    Qs,QL: sensible and latent heat gain

    qs,qL: sensible and latent gains per person

    n: number of people

    CLF: cooling load factor

  • 8/13/2019 Load Calculation Presentation

    10/32

    For lighting :

    Qs=W*CLF

    Where:

    Qs: net heat gain from lighting

    W:lighting capacity: (watts)

  • 8/13/2019 Load Calculation Presentation

    11/32

    For equipments :

    Qs=q s*CLF

    QL=qL

    Qs,QL: sensible and latent heat gain.

    CLF: cooling load factor

  • 8/13/2019 Load Calculation Presentation

    12/32

    4 th Floor3 rd Floor2nd Floor1st FloorFloor No.

    34.32630.932.7HeatingLoad (ton)

    60.2485659.8CoolingLoad (ton)

    Results of heating and cooling load for each floor:

  • 8/13/2019 Load Calculation Presentation

    13/32

    Ventilation and exhaust air:

    Definition of ventilation:Ventilating (the V in HVAC) is the process of "changing" or replacing air in any space to provide highindoor air quality (i.e. to control temperature, replenish oxygen, or remove moisture, odors, smoke,heat, dust, airborne bacteria, and carbon dioxide). Ventilation is used to remove unpleasant smellsand excessive moisture, introduce outside air, to keep interior building air circulating, and to preventstagnation of the interior air.

    Method of calculating ventilation: Its calculated from tables depending on the number of people or on the area of the roam in general.

    Definition of exhaust air: Its the air which withdrawn from the room to the atmosphere to make complete cycle in which weallow fresh air to enter the room and withdraw the exhaust air to the atmosphere.

    Method of calculating exhaust air: Its equal to the fresh air rate in general but we can make it larger than fresh air if we need positive

    pressure or smaller than fresh air if we want negative pressure.

  • 8/13/2019 Load Calculation Presentation

    14/32

    2) POTABLE WATER :

    The pipes conveying water to water closets shall be of sufficient sizeto supply the water at a rate required for adequate flushing withoutunduly reducing the pressure at other fixtures Separate sewer connections.

    Every building intended for human habitation or occupancy on premises abutting on a street in which there is a public sewershall have a separate connection.

  • 8/13/2019 Load Calculation Presentation

    15/32

    How to size pipe based on flow rates.

    Identify the gpm requirement of the furthest head from the zone valve.For systems with only one zone use the head furthest from the main line point of connection (POC).

    On a Friction Loss Chart for the type of pipe selected, find the gpm amount from 1st item in the far leftcolumn.

    In that row, move right across the chart until a velocity of less than 5 feet per second is reached.

    Move up that column to find the minimum pipe size necessary to carry the flow to this head.

    Add the gpm requirement of the last and the next to the last head together to size the next pipe.

    Find the total gpm in the 1st column of the Friction Loss Chart and repeat steps 3 and 4.

    Continue this process until you reach the zone valve or main line POC.

    Select the largest of the pipe sizes for the entire zone.

  • 8/13/2019 Load Calculation Presentation

    16/32

    3) DRINAGE AND VENT SYSTEMS :

    In modern plumbing, a drain-waste-vent is a system that removes sewage and grey water from a building and

    vents the gases produced by said waste. Waste is produced at fixtures such as toilets, sinks and showers, and

    exits the fixtures through a trap, a dipped section of pipe that always contains water. All fixtures must contain

    traps to prevent gases from backing up into the house. Through traps, all fixtures are connected to waste

    lines, which in turn take the waste to a soil stack, or soil vent pipe, which extends from the building drain at

    its lowest point up to and out of the roof. Waste is removed from the building through the building drain and

    taken to a sewage line, which leads to a septic system or a public sewer. Cesspits are generally prohibited in

    developed areas.

  • 8/13/2019 Load Calculation Presentation

    17/32

    Drainage system sizing :

    Fixture unit values presently recommended for assignment to various kinds of plumbing fixtures whichdischarged into sanitary drainage systems are stated in table10-1.

    They are provides as a means for computing sizes of soil, waste, and vent piping bases upon the loadingeffects produced by the discharge of many different kinds of plumping fixtures commonly installed in

    buildings.

  • 8/13/2019 Load Calculation Presentation

    18/32

    Venting mechanisms :

    To prevent the problems of high pressure in a drain system,

    sewer pipes will usually vent via one of two mechanisms.

    Sizing of vent piping :

    Table 4-3 used for sizing vent stacks in accordance with drainage stack capacity loads.

  • 8/13/2019 Load Calculation Presentation

    19/32

    4) FIRE FIGHTING SYSTEM :

    Fire protection is the prevention and reduction of the hazards associated with fire. If involves the study of the behavior compartment, suppression and investigation of fire and its related emergencies as will as theresearch and development production, testing and application of mitigating.

    The wet stand pipe system is designed in our project for its advantages on dry system and the Palestiniansystem in fire fighting.

    Fire dampers are installed in the supply of each fan coil to not allow fire to spread of fire and stop the oxygensource.

    Sizing :

    Each pipe of landing valve is 2 , each pipe of cabinet is 1 and the rest of pipes is 4.

  • 8/13/2019 Load Calculation Presentation

    20/32

    5) MEDICAL GASES :

    Medical gases are very important in hospitals, the main application of it inside the surgery operations roomsand in patient rooms to help the patients.

    There is many medical gases are used in hospitals, like :

    Oxygen (O 2) Medical Air (MA) Medical Vacuum (MV) Nitrous Oxide (N 2O) Nitrogen (N 2) Instrumental Air (IA)

    Carbon Dioxide (CO 2) Waste Anesthesia Gas Disposal (WAGD or EVAC)

  • 8/13/2019 Load Calculation Presentation

    21/32

    Designing Medical Gas Systems :

    Estimating flow requirements

    Selecting equipment

    Pipe sizing

    Zone valves and alarms

    Electrical service

    Equipment space requirements

    Number of outlets

    Flow rate per outlet (depends on the specific gas and outlet type)

    Diversity factor (depends on the number and type of outlets)

  • 8/13/2019 Load Calculation Presentation

    22/32

    Pipe Sizing :

    Flow Rate (considering diversity), the flow rate inside the pipes arecalculated due to the diversity factor, in the pipes outlets the flow rate is (1),in the other lines the ones in outlets that the pipe supplies it are calculatedand multiplied by the diversity factor because not all the outlets are used inthe same time, then the pipe sizes are calculated from table 6-4.

    The friction loss in the pipes are shown in table 6-4, and it's depend on the sizethat was selected in the previous step, the friction loss are calculated for each pipeof the longest line, and this help us to now the medical gas compressor power,then calculate the equivalent length of the longest pipe line by multiplying thetotal length by 1.5 and then the friction loss inside the elbows are including inthe calculations.

    From table 6-4, increasing in the pipe diameter will decrease the friction lossand that useful for the compressor power and keep money.

  • 8/13/2019 Load Calculation Presentation

    23/32

    WBDGPMSensible

    capacity(BT

    UH)

    Total

    capacity

    (BTUH)

    Entering

    wet bulb

    temp ( oF)

    DBTAirflowrate

    Fanspeed

    modelFan coilno.

    4.029.954394654976763761816HDC18

    4Rows

    1

    6) SELECTION :

    Example of Fan coil unit selection:

  • 8/13/2019 Load Calculation Presentation

    24/32

    MODELLWTAmbient

    temp.(o

    F)

    CAPGPMKWWPD

    APS 205-

    2S

    5085229.9551.82076.25

    Chiller selection :

  • 8/13/2019 Load Calculation Presentation

    25/32

    .

    Maximum

    pressure (PSIG)

    Maximum

    temp ( oF)

    KWDescriptionModel

    135358500High capacityCHS

    Boiler selection :

    Q(boiler) = Q(heating) + Q(domestic)

    Q(domestic) = m*Cp*T

    M = 59 GPM = 59*3.7/60 = 3.64 L/S

    Q(domestic) = m*Cp*T = 3.64*4.18*60/24 = 35 Kw/hour

    Assuming that hot water is used for 2 hours then:

    Q(domestic) = 35*2 = 70 Kw

    Q(boiler) = Q(heating) + Q(domestic) = 430 + 70 = 500 Kw

  • 8/13/2019 Load Calculation Presentation

    26/32

    CFMNeck size in mmTotal pressureOutlet velocity

    FPM

    410225*2250.25 2000

    Diffuser selection:

  • 8/13/2019 Load Calculation Presentation

    27/32

  • 8/13/2019 Load Calculation Presentation

    28/32

    .

    PUMPMODEL

    Flow(GPM)

    Pressure(Psi)

    CastingMaterial

    Ports(Inlet*Discharge)

    Horsepower(HP)

    MotorType

    4K192MT325082304S2-1/2*1- 1/2 ANSI 10215FRElectric

    3PH

    Potable water pump selection:

    Pump head = Friction losses(F.L)-Back Pressure(B.P)+Residual Pressure (Fixture pressure) Now to Find Friction losses(F.L):The longest distance and the largest residual pressure was taken in the top story of the buildingFriction losses (F.L) = (16*3.28*22.5 + 4.5*3.28*17.2 + 23*3.28*12.8 + 6.5*3.28*10.8)/100

    Multiplying by 1.5 to compensate the losses in fittings:-F.L = 1.5*26.5 = 40 Psi

    Back Pressure (B.P) = 5PsiResidual Pressure ( Fixture pressure) = 8 PsiPump head = 40+85 = 43PsiPump flow rate =190 GPM (Using fixture unit (880F.U))

  • 8/13/2019 Load Calculation Presentation

    29/32

    .

    PUMP

    MODEL

    Flow

    (GPM)

    Pressure

    (Psi)

    Casting

    Material

    Ports

    (Inlet*Discharge)

    Horsepower

    (HP)

    Motor

    Type3K392B

    T05213304S1-1/2*1 NPT 1/256FR

    Electric1PH

    Hot water pump selection :

    Pump head = Friction losses(F.L)+Back Pressure(B.P)+Residual Pressure (Fixture pressure) Now to Find Friction losses(F.L):The longest distance and the largest residual pressure was taken in the top story of the buildingFriction losses (F.L) = (16*3.28*40 + 4.5*3.28*31 + 23*3.28*22.5 + 6.5*3.28*17.2)/100

    Multiplying by 2 because there is a return line:F.L = 2*46 = 93 Psi

    Multiplying by 1.5 to compensate the losses in fittings:F.L=1.5*93=140 PsiBack Pressure(B.P) = 4*5= 20PsiResidual Pressure ( Fixture pressure) = 10 PsiPump head = 140+20+10=170PsiPump flow rate =50 GPM (Using fixture unit 120F.U)

  • 8/13/2019 Load Calculation Presentation

    30/32

    .

    Fire duty

    Usgpm

    Range PsigRange (m)Pump

    Model

    Pump Item

    No.

    Diesel

    EngineKW/rpm

    Motor

    KW/rpm

    1000193.2-210.2133-145100-315K451A000170/2900185/2900

    Fire pump selection and tank size :

    Pump head = Friction losses (F.L)Back Pressure(B.P)+Residual Pressure Fire Fighting. Now to Find Friction losses (F.L):The longest distance was taken in the top story of the buildingFriction losses (F.L) = (4.95*9*3.28 +4.73*38*3.28 +15*3.5*3.28+4.95*69+3.28+ 18.9*12*3.28)/100Multiplying by 1.5 to compensate the losses in fittings:-F.L=1.5*27.8=42 PsiBack Pressure(B.P)=5PsiResidual Pressure( Fire Fighting)=100 PsiPump head = 42+100-5=137PsiPump flow rate =1000 GPMTank size =1000*90 = 90000Gallon = 90000*3.7/1000 = 333 m 3

  • 8/13/2019 Load Calculation Presentation

    31/32

    Boiler chimney :

    The assumption of the boiler chimney:

    H = 15 m, CV=39000 , = 80%, g= 1.1, v = 5m/sPb=101.32, Ra= 287, Ta=25+273=298, Tg=250+273=523.

    mf = Qb/ CV* = 500/39000*0.8 = .016kg/smg = 25.2*m f = .403 kg \sAc = m g / g v = 0.0733 m 2

    Ac = / 4 * D 2 - D = 30.5cm =35 cmQ flow= m g/ g =.403 / 1.1= 0.366 m 3/s

    ---- p/ L = 0.5 pa/m

    p= 0.5*(15*1.5) = 11.25 pa

    But

    P boiler = (Pb*g*H)/Ra * ((1/Ta)-(1/Tg)) = 71.5 paP boiler > p= 0.5*(15*1.5) = 11.25 pa

    So, no need for fan.

  • 8/13/2019 Load Calculation Presentation

    32/32

    Finished

    Thank you for your attention