Lecture 7 PMIS

Embed Size (px)

Citation preview

  • 7/27/2019 Lecture 7 PMIS

    1/55

    HEP 3104: PROJECT

    MANAGEMENT INFORMATIONSYSTEMS

    19th July 2012

    Lecturer: Emma Longei

    Email: [email protected]

    1

    Lecture 7: Tracking

    Budget

    Reports

  • 7/27/2019 Lecture 7 PMIS

    2/55

    BASIC FEATURES OF PROJECT MANAGEMENT

    SOFTWARE

    1. Creating work breakdown structures, Gantt charts, andnetwork diagrams

    2. Integrating scope, time, and cost data WBS is a key tool for summarizing the scope of a project

    Gantt chart summarizes the time or schedule for a project3. Setting a baseline and tracking progress Project management software allows you to assign cost and

    other resources to tasks on the WBS, which are tied to theschedule.

    This allows you to create a cost baseline and use earned valuemanagement to track project performance in terms of scope,time, and cost in an integrated fashion

    4. Providing other advanced project management features

    2

  • 7/27/2019 Lecture 7 PMIS

    3/55

    Change Highlighting for Task and

    Schedule Analysis

    The Change Highlighting feature presents a nicereminder of the interrelatedness of many tasks in yourproject, it is only a temporary visual clue. As soon asyou save the project file or make another change, the

    original change highlighting is removed and oftenreplaced with a new set of change data.

    If you don't want to see changes appear in blue, youcan turn off Change Highlighting altogether. To do that,

    follow these steps: Choose View.

    Choose Hide Change Highlighting.

    http://www.brighthubpm.com/software-reviews-tips/4559-project-2007-using-change-highlighting-for-task-and-schedule-analysis/

    3

  • 7/27/2019 Lecture 7 PMIS

    4/55

    4

  • 7/27/2019 Lecture 7 PMIS

    5/55

    TRACKING

    Schedule

    Budget

    5

  • 7/27/2019 Lecture 7 PMIS

    6/55

    Calendars

    The standard Project 2007 calendar assumes

    that working hours are Monday through

    Friday, from 8:00 a.m. to 5:00 p.m., with an

    hour for lunch from noon until 1:00 p.m.

    You can create a different calendar to meet

    your unique project requirements.

    6

  • 7/27/2019 Lecture 7 PMIS

    7/55

    Creating a New Calendar

    To create a new base calendar using the Tasks

    pane use the Tasks pane to create a new

    calendar. Click Define general working times in

    the Tasks pane. (If the Tasks pane does not

    appear on your screen, click View on the

    Menu bar, and then click Turn On Project

    Guide to see the Project Guide Task pane).

    7

  • 7/27/2019 Lecture 7 PMIS

    8/55

    8

    Creating a New Calendar

  • 7/27/2019 Lecture 7 PMIS

    9/55

    To create a new base calendar using the Tools menu:

    1. Access the Change Working Time dialog box. Click Toolson the Menubar, and then click Change Working Time.The Change Working Time dialog box opens.

    2. Name the new base calendar. In the Change Working

    Time dialog box, click Create New Calendar. The CreateNew Base Calendar dialog box opens. Click the Createnew base calendar radio button, type Project A+ as thename of the new calendar in the Name text box, andthen click OK. Click OK to close the Change Working

    Time dialog box.

    You can use this new calendar for the whole project, oryou can assign it to specific resources on the project.

    9

  • 7/27/2019 Lecture 7 PMIS

    10/55

    To assign the new calendar to the whole project:

    1. Open the Project Information dialog box. ClickProject on the Menu bar, and then clickProject Information. The Project Information

    dialog box opens.2. Select a new calendar. Click the Calendar list

    arrow to display a list of available calendars.Select your new calendar named Project A+

    from this list, and then click OK.

    10

  • 7/27/2019 Lecture 7 PMIS

    11/55

    To assign a specific calendar to a specific resource:

    1. Assign a new calendar. Click View on the Menu bar, and

    then click Resource Sheet. Type Adam in the ResourceName column, press Enter, and then select the wordAdam.

    2. Select the calendar. Click the Base Calendar cell on theright part of the screen for Adam. If the Base Calendarcolumn is not visible, click the horizontal scroll bar toview more columns. Click the Base Calendar list arrowto display the options, and then select Project A+, asshown in Figure A-22.

    11

  • 7/27/2019 Lecture 7 PMIS

    12/55

    3. Block off vacation time. Double-click the resourcename Adam to display the Resource Informationdialog box, and then click the Change Working

    Time button, located on the General tab in theResource Information dialog box.

    You can block off vacation time for people byselecting the appropriate days on the calendar

    and marking them as nonworking days. Click OKto accept your changes, and then click OK toclose the Resource Information dialog box.

    12

  • 7/27/2019 Lecture 7 PMIS

    13/55

    Entering Task Durations

    You probably noticed that when you enter a

    task, Project 2007 automatically assigns it a

    duration of one day, followed by a question

    mark. To change this default duration, type atasks estimated duration in the Duration

    column or use the scroll box to select the

    duration.

    13

  • 7/27/2019 Lecture 7 PMIS

    14/55

    If you are unsure of an estimate and want to

    review it again later, enter a question mark

    after it. For example, you could enter 8d? for a

    task with an estimated duration of eight daysthat you want to review later.

    14

    Entering Task Durations

  • 7/27/2019 Lecture 7 PMIS

    15/55

    Duration Units

    Duration unit symbols include:

    d = days (default)

    w = weeks

    m = minutes

    h = hours

    mo or mon = months

    ed = elapsed days

    ew = elapsed weeks

    15

  • 7/27/2019 Lecture 7 PMIS

    16/55

    Elapsed time

    You would use an elapsed duration for a tasklike Allow cement to dry. The cement will dryin exactly the same amount of time regardless

    of whether it is a workday, a weekend, or aholiday. Projects default calendar does notassume that work is done on weekends.

    Elapsed time includes weekends

    Differentiate between 10d? 10ed 10d ==Estimated / Elapsed / Normal duration

    16

  • 7/27/2019 Lecture 7 PMIS

    17/55

    RULES WHEN ENTERING DURATIONS

    Do not enter durations for summary tasks.Summary task durations are calculated

    automatically based on the subtasks. Project

    2007 will not allow you to enter or change the

    duration of a summary task.

    To mark a task as a milestone, enter 0 for the

    duration. You can also mark tasks that have a

    non-zero duration as milestones by checking theMark task as milestone option in the Task

    Information dialog box on the Advanced tab.

    17

  • 7/27/2019 Lecture 7 PMIS

    18/55

    You can enter the exact start and finish datesfor activities instead of entering durations. To

    enter start and finish dates, move the split bar

    to the right to reveal the Start and Finishcolumns.

    If you want task dates to adjust according to

    any other task dates, do not enter exact startand finish dates. Instead, enter durations and

    then establish dependencies to related tasks.

    18

    RULES WHEN ENTERING DURATIONS

  • 7/27/2019 Lecture 7 PMIS

    19/55

    Critical Path Analysis You can view the critical tasks by changing the

    color of those items in the Gantt Chart view.Tasks on the critical path will automatically be redin the Network Diagram view. You can also viewcritical path information in the Schedule table or

    by using the Critical Tasks report.1. Click Format on the Menu bar, and then click

    Text Styles. The Text Styles dialog box opens.

    2. Click the Item to Change list arrow, and then

    select Critical Tasks. Click the Color list arrow,and then select Red. Click OK to accept thechanges to the text styles.

    3. No red tasks means that the project has slack

    19

  • 7/27/2019 Lecture 7 PMIS

    20/55

    Entering Fixed Costs in the Cost Table

    Click View on the Menu bar, point to Table:

    Entry, and then click Cost. The Cost table

    replaces the Entry table to the left of the

    Gantt chart.

    In the Fixed Cost column for Surveying, enter

    20,000/-.

    20

  • 7/27/2019 Lecture 7 PMIS

    21/55

    Fixed Costs: Surveying

    21

  • 7/27/2019 Lecture 7 PMIS

    22/55

    Entering Resource Information

    Enter basic information about each person

    into the Resource Sheet and assign them to

    tasks using the Entry table

    This we have already done

    22

  • 7/27/2019 Lecture 7 PMIS

    23/55

    Assigning Resources to Tasks

    Click the Gantt Chart view on the View bar

    Widen the Task Name column and move the

    split bar to reveal all of the entry table

    columns, if needed.

    Click in the Resource Names cell and select a

    resource

    23

  • 7/27/2019 Lecture 7 PMIS

    24/55

    To assign several resources to a

    task

    Click the Assign Resources button on thetoolbar. (If the Assign Resources button is notvisible, click the Toolbar Options button on

    the toolbar, and then click the AssignResources button. You can also press Alt+F10.)

    You can select one resource at a time and clickAssign, or click on the first name, hold downthe Shift key, click on the last name to selectall of the names at once, and then click Assign.

    24

  • 7/27/2019 Lecture 7 PMIS

    25/55

    To assign resources using the split

    window

    Click Window on the Menu bar, and then click

    Split. The Cost Table and Gantt Chart view is

    displayed at the top of the screen and a

    resource information table is displayed at thebottom of the screen

    Right-click anywhere in the bottom window

    and select Resource Cost.

    25

  • 7/27/2019 Lecture 7 PMIS

    26/55

    Removing the Effort driven option

    Uncheck the Effort driven box in the lower

    window so Project does not change task

    durations based on resource entries for that

    task.

    26

  • 7/27/2019 Lecture 7 PMIS

    27/55

    Resolving overallocations

    One of the most difficult things to do whenplanning a project is resolving the inevitableoverallocation of resources. When assigning yourresources, you will likely assign too many hours of

    work for a given period. For example, you might assign Steve to work

    five hours on Task One and six hours on Task Twoon the same day, yet Steve only works an eight-

    hour day. This is an obvious overallocation, sinceSteve has been scheduled to work three hoursmore than he is available.

    27

    http://www.techrepublic.com/article/microsoft-project-tutorial-

    assigning-resources/1031578

  • 7/27/2019 Lecture 7 PMIS

    28/55

    Assign a few more costs and resources

    .

    28

  • 7/27/2019 Lecture 7 PMIS

    29/55

    Setting a Baseline

    Click Tools on the Menu bar, point to Tracking,and then click Set Baseline

    Display the Tracking toolbar. Click View on theMenu bar, point to Toolbars, and then click

    Tracking. Click View > Table: Entry > Tracking

    A grey bar shows the baseline, a blue bar isactual progress, and tasks on the critical path

    shown in red Percentages indicate progress/completion of

    individual tasks

    29

  • 7/27/2019 Lecture 7 PMIS

    30/55

    30

  • 7/27/2019 Lecture 7 PMIS

    31/55

    Tracking task completion

    Select a task or several tasks

    Click the % Complete button on the Trackingtoolbar.

    The columns with dates, durations, and costinformation should now contain data instead ofthe default values, such as NA or 0. The % Compcolumn should display 100%. Adjust columnwidths if needed.

    Notice that the Gantt chart bars for those tasksnow have a blank line through them.

    31

  • 7/27/2019 Lecture 7 PMIS

    32/55

    Enter actual completion dates for Task

    Select the task

    Click the Update Tasks button on right side of

    the Tracking toolbar next to the 100% button

    Enter the Actual Start date and the Actual

    Finish date. Click OK. Notice how the

    information in the tracking sheet has changed.

    32

  • 7/27/2019 Lecture 7 PMIS

    33/55

    View the Tracking Gantt chart

    Click View on the Menu bar, and then clickTracking Gantt. Alternatively, you can click theTracking Gantt button on the View Bar, if it isdisplayed.

    Use the horizontal scroll bar in the Gantt chartwindow (move it to the left) to see symbols onthe Tracking Gantt chart.

    To view the entire Gantt chart, right click on thedates at the top of the chart > select Zoom >select Entire Project

    33

  • 7/27/2019 Lecture 7 PMIS

    34/55

    Viewing the Tracking Gantt chart allows you to

    easily see your schedule progress against the

    baseline plan. After you have entered some

    actuals, you can review earned valueinformation for the initiating tasks of this

    project.

    34

  • 7/27/2019 Lecture 7 PMIS

    35/55

    VIEWING EARNED VALUE

    MANAGEMENT

    Earned value management is an importantproject management technique for measuringproject performance.

    Click View on the Menu bar, point to Table:Entry, select More Tables, and double-clickEarned Value

    Note that the date on your computer must beset later than the date of a completed task forthe data to calculate properly.

    35

  • 7/27/2019 Lecture 7 PMIS

    36/55

    Earned Value Abbreviations

    EAC: Estimate at Completion

    BAC: Budget at Completion

    VAC : Variance at Completion

    36

  • 7/27/2019 Lecture 7 PMIS

    37/55

    Earned Value Report

    Click Report on the Menu bar, and then click

    Custom Reports, click Earned Value Report

    37

  • 7/27/2019 Lecture 7 PMIS

    38/55

    INTEGRATING PROJECT 2007 WITH

    OTHER APPLICATIONS

    Project 2007 provides many different tables,

    views, reports, and formatting features to aid

    in project communications, as have seen in

    the previous sections.

    One can insert hyperlinks within Project 2007

    to other project documents, and use the copy

    picture feature to insert Project 2007 screensinto other documents.

    38

  • 7/27/2019 Lecture 7 PMIS

    39/55

    Common Reports

    Click on Reports > Reports

    39

  • 7/27/2019 Lecture 7 PMIS

    40/55

    Overview reports include:

    Project Summary

    Top-Level Tasks

    Critical Tasks

    Milestones

    Working Days

    40

  • 7/27/2019 Lecture 7 PMIS

    41/55

    Current Activities reports include:

    Unstarted Tasks

    Tasks Starting Soon

    Tasks In Progress

    Completed Tasks

    Should Have Started Tasks

    Slipping Tasks

    41

  • 7/27/2019 Lecture 7 PMIS

    42/55

    Cost reports include:

    Cash Flow

    Budget

    Overbudget Tasks

    Overbudget Resources

    Earned Value

    42

  • 7/27/2019 Lecture 7 PMIS

    43/55

    Assignments reports include:

    Who Does What

    Who Does What When

    To-do List

    Overallocated Resources

    43

  • 7/27/2019 Lecture 7 PMIS

    44/55

    Workload reports include:

    Task Usage

    Resource Usage

    Custom allows you to customize and save your

    own report formats.

    44

  • 7/27/2019 Lecture 7 PMIS

    45/55

    Visual Reports Baseline Cost Report

    Baseline Work Report

    Budget Cost Report

    Budget Work Report

    Cash Flow Report Earned Value Over Time Report

    Resource Cost Summary Report

    Resource Remaining Work Report

    Resource Work Availability Report

    Resource Work Summary Report

    45

  • 7/27/2019 Lecture 7 PMIS

    46/55

    Activity

    Print the Critical Path Report

    Print the report showing tasks starting in the

    next 1 month (4 weeks)

    Print your Project Budget

    Print a to-do report for the Site Foreman

    Print a report showing the allocation ofresources to tasks (Workload)

    46

  • 7/27/2019 Lecture 7 PMIS

    47/55

    Creating Hyperlinks to Other Files

    A Project Manager may use their Project 2007file as a main source of information for manydifferent project documents.

    Select the task in which you want to insert ahyperlink. Click Insert on the Menu bar, andthen click Hyperlink. Double-click the filenameof the hyperlink file. Double-click the file to be

    linked to. A hyperlink should appear in theIndicator column.

    47

  • 7/27/2019 Lecture 7 PMIS

    48/55

    Missing Indicator Column

    Right click Task Name Column

    Select Insert Column

    Select Indicators, and click OK

    48

  • 7/27/2019 Lecture 7 PMIS

    49/55

    Using the Copy Picture Feature

    The Copy Picture feature helps you easily copyimages from Project 2007 into other applications,e.g. the Project Plan Document in Word.

    You may need to remove some of the toolbars byselecting Tools from the Menu bar andunchecking them to get the entire image to showon your screen. Drag the split bar so the entire

    Predecessors column is showing. Click in the TaskName column for task 0. Make sure you can seethe entire Gantt chart on your screen.

    49

  • 7/27/2019 Lecture 7 PMIS

    50/55

    Click Report on the Menu bar, and then click

    Copy Picture to display the Copy Picture dialog

    box. Keep the default settings. Click OK.

    50

    Using the Copy Picture Feature

  • 7/27/2019 Lecture 7 PMIS

    51/55

    51

    Project Screen without predecessors

    You can also post this screen in a Word Document, or in an

    email

  • 7/27/2019 Lecture 7 PMIS

    52/55

    52

    Project Screen with predecessors

  • 7/27/2019 Lecture 7 PMIS

    53/55

    10 insights to better master MS Project

    1. MS Project is a databaseAll views and tables show the same data from different perspectives.

    2. MS Project is a calculator

    Everything is recalculated to minutes. And then shown in time units asper your configuration settings.

    3. Start each project schedule by checking your basic configurationsettings

    These include your default calendar, the calendar calculations,metadata, currency and time settings.

    4. Let MS Project calculate

    Let it calculate start and end times for you !5. MS Project is already programmed to be asap ;

    Dont put constraints initially; if needed put them in when project isongoing.

    53

  • 7/27/2019 Lecture 7 PMIS

    54/55

    6. Use an outline code to discern your task levelsand WBS structure.

    You can use the default one or your own.

    7. Each of the input fields have 3 faces,personalities or characteristics

    Input happens in duration | work | cost fieldsbut to be able to manage a project you need 3

    versions of those fields: scheduled | baseline |actual different versions are shown in differentviews and tables.

    54

    10 insights to better master MS Project

  • 7/27/2019 Lecture 7 PMIS

    55/55

    8. Set the timescales to weeks and month for easier management The default setting is by days and weeks in many cases a key to

    mastering views and schedules is triggered off by zooming out thetime scale to weeks and months. This makes assessing overallocation (in weeks) much easier to handle too.

    9. Think in work-terms as much as possible. Distinguish between work and hours. If you prefer work in man

    days, do so, but then express duration in weeks. Work only existswhen resources are assigned, which triggers off the formula W = D* U . Have a good eye on the task type at all times.

    10. Tracking a project = entering actuals

    To track values, search for the appropriate actual field and enterthe data.

    10 insights to better master MS Project