Large Scale Cyber Physical Robust Grid Smart Power Control

Embed Size (px)

Citation preview

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    1/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    15

    Large Scale Cyber Physical Robust Grid SmartPower Control

    Amit Sachan, Preeti Sachan

    Department of Electrical [email protected]

    HCL Technology, Noida, [email protected]

    ABSTRACT

    Large-scale cyber-physical substructures, such as the Smart Power Grid, are future as some of the core

    rudiments of the future Internet of Gears. These serious substructures transfer additional and more

    elsewhere federal supervision and control by system machinists and commissioners. Overcapacity and

    disappointments in the Smart Power Grid impend the identical of demand-supply expressly when new

    evolving technologies are combined such as micro-generation, renewable energy resources and electrical

    vehicles. The addition of these technologies in the Smart Power Grid types the impression of Internet ofGears highly appropriate in the energy field. The introduction of automated and distributed protection

    mechanisms entails embedded control rudiments that perform structural reconfigurations themselves in a

    spatially distributed situation. The dynamic input and output binding between such control rudiments is an

    instance of an association reconfiguration that is conventionally achieved offline during the design phase

    of a cyber-physical system. An presented computational intelligence for the resolution of such structural

    control reconfigurations involves the interoperation with the rest of the control logic through runtime. This

    papers hows a model that types this interoperation potential: ALSOS-ICS, the Application-level Self-

    Organization Services for Internet-scale Control Systems. Four incremental protection levels for the

    robustness of the Smart Power Grid show the rations of structural control reconfigurations and the

    applicability of ALSOS-ICS in this area.

    KEYWORDS

    ALSOS-ICS, Sensor, Protection controller, Stabilization actuator,blackout restoration

    1. INTRODUCTION

    Cyber-physical schemes within the Internet of Gears are constructed by physical and softwarerudiments of embedded control whose group has conventionally been an offline design feature.

    Input and output (I/O) of control rudiments are destined physically to procedure the control loops

    of a control presentation [1]. This is a design phase that is typically not automated and transpires

    formerly system runtime [2]. Yet, the Internet of Gearsentail online and automated structuralcontrol reconfigurations as cyber-physical systems balance and their rudiments develop additional

    consistent, distributed and communicating. Reconfigurations develop an integral part of thecomputational intelligence that control rudiments should have. In this case, structural control

    resources that the response control loops molded by the I/O compulsory of the control rudimentsare controlled within a large-scale networked and distributed location of Internet of Gears.

    Network concept, fault-tolerance, potential, limited connectivity and communal possessions arecertain of the challenges that need to be addressed [3]. Presenting and demonstrating dynamic

    reconfigurations of the operational control in an Internet-scale control system is challenging. This

    is since the physical resources of a cyber-physical system interoperate created on I/O signals and

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    2/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    16

    response loops, while, distributed software essentials are frequently occasion created,information-driven and are assembled by abundant coatings of network concept.

    This modeling slit presents several addition and interoperation problems that are recognized in

    works [3,4]. Cyber-physical systems without operational control reconfigurations cannot

    provision the developing application rations of Internet of Gears. Hence, the modeling of

    operational control reconfigurations is significant and connects together of these associated studyparts [5]. a modeling approach of operational control reconfigurations in the presentation area of

    the Smart Power Grid. This is a critical solicitation domain for the Internet of Gears as a large

    number of physical and software resources of the outdated electrical grid develop additional

    interconnected, intelligent and self-aware of socio-technical issues that directive their design and

    operation [6].

    The protection of the Smart Power Grid from overloading or failures is a serious condition thatincludes several operational control reconfigurations such as regulating the load of a power line,

    switching the power flow to alternate distribution lines, turning on gridlock generators andreinstating the system subsequently a black-out. These reconfigurations are synchronized

    physically by proficient systems operators maintained by frequently centralized data acquirement

    information systems [7]. This method is limited and cannot continue as a long-term resolution inthe future Smart Power Grid. The overview of micro-generation, renewable energy properties and

    electrical vehicles are some instances that designate the future experiment and difficulty ofidenticall request and source inside a robust and dynamic Smart Power Grid. Hence operational

    control reconfigurations in an location of Internet of Gears need to be dynamic, automated and

    synchronized by the computational intelligence of control principles intelligent to interoperate forthis resolution.

    2. DYNAMIC I/O BINDING RECONFIGURATIONS

    Two control essentials are destined if around is at minimum one output from the first control

    module wired to the input of a second control module. A required reconfiguration is clear by therenovating of the input/output of a control module to a different output/input individually of the

    similar or of additional control module. A dynamic required reconfiguration means that thisrenovating is automated through system operation (online) with a minimum or inattentive

    centralized interference. Dynamic I/O required reconfiguration involves system rudiments thatshould be accomplished to achieve these reconfigurations and should be intelligent to interoperate

    with the rest of system control logic. Surviving solutions afford an offline [2], external [8] and/orcentralized [9,10,11] configuration of I/O bindings. Our previous work [12] presents a model for

    application-level reconfiguration of dynamic I/O required in Internet-scale control systems that is

    mentioned to in this paper as ALSOS-ICS, the Application-Level Self-Organization Facilities in

    Internet scale Control Systems. This model presents a new type of control application that

    delivers reconfiguration facilities for dynamic I/O binding to other control applications.

    This type of control application is modeled as a control system, assembled by control rudiments

    that are intelligent to network with additional control rudiments of the same API but realized for a

    different application opportunity. This method permits a advanced interoperability and modularityamid control applications and a higher flexibility, integration and applicability of dynamic I/O

    required reconfigurations in the area of cyber-physical systems and Internet of Gears. ALSOS-ICS is collected of three types of control rudiments: (i) the I/O discovery sensor, (ii) the I/O

    decision controller and (iii) the I/O reconfiguration actuator.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    3/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    17

    These rudiments are destined to all other and also to rudiments that constitute a dissimilar controlsolicitation. The advanced application is the one that involvements dynamic I/O binding

    capabilities if by an ALSOS-ICS control application. The I/O discovery sensor senses for

    conceivable I/O bindings and outputs these imaginable bindings to the I/O resolution controller.

    The prospect of gossip-based detection sensors is conversed in our previous work [12]. The I/O

    conclusion controller chooses to add or remove I/O bindings based on the objectives of the

    control application that ALSOSICS ropes. These purposes may be signified as a suitabilitypurpose or high-level commercial rules and policies. The added and uninvolved I/O bindings are

    the output to the I/O reconfiguration actuator that adapts the I/O binding of the aided control

    solicitation.

    The connector of ALSOS-ICS with control solicitations can be done at dissimilar planes as shownin our previous work [12]: (i) system-level, (ii) node-level and (iii) module-level. This paper

    shows additional exactly the application of these levels in the Smart Power Grid. Figure 1 showsan indication of ALSOSICS and its coupling to the Smart Power Grid. In the system-level

    coupling, ALSOS-ICS is linked to a Distribution Automation System (DAS) that may achieveseveral system optimizations such as power current optimization [13], protected fault isolation

    [14] etc. Data acquisition is, to an magnitude, centralized. A node-level distribution of ALSOS-

    ICS distributes I/O binding control over the Smart Power Grid at different control points such aspower lines, substations, etc. As of a advanced devolution in node-level associated to system-

    level, the ALSOS-ICS control rudimentsentail in this situation additional complex networks thatassurance access to remote information. Finally, coupling ALSOSICS at the module-level

    presents dynamic I/O binding control at the very low-end control rudiments of the Smart Power

    Grid.

    3. APPLICATION DEVELOPMENTS

    The Smart Power Grid may contribution several (cascading) system failures or malfunctions such

    as overloaded power lines, failures of power lines, physical disasters, demand-supply inequities or

    black-outs. These actions need a broad range of system reconfigurations and maintenances toassurance robustness and aincessant system obtain ability of the Smart Power Grid. Power

    reconfigurations that prevent system failures or curtail their influence by dividing them,need aretro of time to be practical, contingent on the type of reconfiguration. Time is a critical factor for

    the deterrence of system failures or the minimization of their influence by, for instance, isolatingthese failures. System operators cannot repeatedly type optimum assumptions mainly when

    multiple transmission lines are affected concurrently. Automated and dynamic I/O bindingreconfigurations are obligatory to stabilize the operation of the Smart Power Grid by

    computational intelligence embedded in control rudiments.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    4/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    18

    Fig. 1 Positioning of ALSOS-ICS in the context of the Smart Power Grid

    This four application developments that composed propose an incremental four-level protection

    approach based on dynamic I/O binding reconfigurations. The purpose of these application

    developments is not to contemporary a new actual protection mechanism but to underline the

    position of dynamic I/O binding requirements for the robustness of the Smart Power Grid. Thefour levels of Smart Power Grid reconfigurations are the following:

    1. Dynamic load-balancing of power lines: Power flow may exceed the capacity of optimisticpower lines when demand surges or neighboring power lines fail. Rerouting power to alternative

    analogous power lines involves rapid I/O binding reconfigurations to avoid cascading failures to aconvinced magnitude.

    2. Dynamic switching of power flow: Generation, transmission and principally distributionnetworks are maintained by several gridlock power lines and switches that deliver alternate power

    flow of the load assisted by a substation but too among dissimilar substations. Arrangementdisappointments and maintenance can be achieved by dynamic and automated I/O binding

    reconfigurations of power lines and switches in its place of physical arrangements by system

    machinists.

    3. Dynamic allocation of operating reserves: Demand-supply imbalances due to system failures ora sudden demand peak require system scaling. Operating reserves are back-up power generation

    that can be made available within a varied time span depending on various technical constraints.Dynamic I/O binding reconfigurations are required to activate/deactivate operating reserves for a

    given system situation.4. Dynamic restoration after blackout: If a system failure arises despite the above mentioned

    protection arrangements, the power system is the restoration of the system back to its normal

    operation is challenging. Any place should be integrated again, generators should be activated

    steadily and this activation should be synchronized with the rest of the generation obtainable in

    the system.This four-level protection approach can be realized by one or more cyber physical control

    applications built by three types of control rudiments bound in an overlay network (application

    graph):

    a. Load sensor: This control module monitors load information from several physical resources of

    the Smart Power Grid. It is certain to protection controllers to provide them with the essential

    information.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    5/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    19

    b. Protection controller: This control module synchronizes the stabilizations obligatory to securitythe protection and robustness of the Smart Power Grid.

    c. Stabilization actuator: This control module regulates the operation of several fundamental

    physical resources that subsidize to the stabilization of the Smart Power Grid.

    The power supply required for the overlay network to purpose is central and is designed to be

    independent of the state in the primary structure. This can be technically accomplished by theconvenience of dedicated small-scale backup generators or the utilization of batteries [15]. This

    section shows the dynamic I/O binding requirements and services that such a control solicitation

    can meet and consume respectively by using ALSOS-ICS.

    3.1. DYNAMIC LOAD-BALANCING OF POWER LINES

    This is the first level of dynamic reconfigurations functional for the deterrence of flowing and

    other failures. It anxieties the load-balancing of power lines positioned in parallel within the

    generation and transmission system. If a deeply loaded line transmits an additional power load,this additional load can be rerouted to another under loaded power line positioned in parallel.

    This load rerouting is possible in two ways: (i) Shifting the phase angle amid the voltages in the

    nodes together to a power line or (ii) altering the line impedance. The first method is technicallyconceivable via a phase shifting transformer device chiefly used for the load-balancing of powerlines [16,17]. The second method is possible via a thyristor controlled series capacitor [18,19].

    This device is mostly used for minimizing power oscillations. Other additional complex devicesthat combine these two functionalities with supplementary topographies are projected in works

    [20,21] resulting in improved stability of power lines.

    Figure 2 shows the concept of load-balancing amid two power lines. When the power of a linespreads its capacity of 100 units, power balancing is achieved by switching 20 units to a line with

    power flow of 70 units and capacity of 130 units. These 20 units are the result of any the

    alteration in the voltage phase angle or in the impedance of the power line. Note that, from an

    engineering point of observation, these modifications can be accomplished rapidly. Though, thebalancing recompense that can be attained is connected to the technical specification of the lines

    and therefore this approach has limitations. These limitations are out of the possibility of thispaper and are discussed in related work [16,17,18,19].

    Fig. 2 Load-balancing of power lines by rerouting load from an overloaded line to an under loaded one.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    6/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    20

    Fig. 3 The overlay network of control rudiments that balances the load between parallel transmission lines

    Figure 3 shows the destined control principles that achieve the load-balancing of transmission

    lines. Note that the control principles are bound in an overlay network that accomplishes theinformation produced by the physical resources of the transmission lines.

    The load sensors in each power line output the load information to the protection controllers of

    the end-to-end nodes. Based on this info, the balancing controllers execute decision-making

    approximately the power rerouting. This result is implemented by a maintenance actuator that

    controls the phase angle or the impedance of its controlled power line. More exactly, theinformation about the rerouted load is translated by the stabilization actuator to an actual

    configuration in the phase shifting transformer or the thyristor controlled series capacitor.This isbecause a load balancing action should not cause an overload to other power lines in the

    transmission topology. Therefore, the protection controllers require an on-demand dynamic I/Obinding provided by an ALSOS-ICS control application. Both (i) the I/O binding control

    application and (ii) the load-balancing control application are realized by embedded softwarecontrol rudiments and so interoperation between these two control applications is potential.

    3.2. DYNAMIC SWITCHING OF POWER FLOW

    A generation and transmission system as well as (ii) a distribution system, power is potential to

    flow in different methods. This is vital for (i) the protection of the power grid [22] and (ii) itsoptimization based on market strategies or economic and environmental policies [23,24]. One

    way to control the power flow is by switching the power flow on or off amid dissimilar nodes in atopology, e.g. in the topology of the distribution system. Switching is technically possible by

    using relays, switches, circuit breakers or recloses [22]. Switching provides some form ofseverance or flexibility as power can be through accessible via alternative distribution paths. This

    provides the alternative to perform some serious operations [22,1] such as (i) system clearance,

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    7/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    21

    maintenance, repair or construction, (ii) load-balancing and (iii) system restoration afterblackouts.

    Fig. 4: Dynamic switching guarantees the power delivery in the loads of a distribution system

    Once a failure of power lines occurs. One or additional switches can close enabling a load to draw

    power from a adjacent control area that is aided by a different feeder. Control essentials aredynamically bound with each additional to manage the dynamic switching of power flow.

    Figure 4 shows a dynamic switching situation in a distribution system. The topology involves ofnodes that signify loads, such as households, that draw power from exact feeders that are

    connected to substations. The control of the distribution system is hierarchical and isaccomplished by nested control areas [22] (i) A substation defines its control area, (ii) within

    which the feeders have their own control areas, (iii) within which feeder lines may too form their

    own control area. So, the distribution system can be controlled at dissimilar granularity levels. For

    design drives, Figure 4 focuses only on the control areas clear by the feeders. Adopt that a

    number of simple closed switches can transfer power amid loads (i) within a control area and (ii)

    between different control areas. The switches are configured at on or off according to a system

    optimization [22,23,24]. This optimization securities that all loads are aided and that there are nooverloaded feeder lines.Though, as it is stated be forehand, failures may happen due to demand

    peaks, physical disasters or even cyber-attacks in the power grid. Failures result in power outage

    in one or more households and may even cascade and cause new failures in the distribution

    system. A coordinated switching of power flow is required to stabilize the distribution system.Note that an automated control of switches is possible via pole-top remote terminal units (RTUs)

    [25].

    Control rudiments undertake this coordination by dynamically binding themselves to control theswitches and, therefore, manage the power flow in a distribution system. Load sensors monitor

    the power flowing in a power line. This info is output to the protection controller of the feedercontrol area. If a failure is detected by this controller based on the input load information, an

    alternative power flow needs to be discovered and utilized. Protection controllers are dynamically

    bound and communicate to guarantee that switching of power flow does not influence other parts

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    8/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    22

    of the system. Next, the protection controller of the affected control area is dynamically boundwith stabilization actuators that control switches within the same control area and in neighboring

    ones. These switches are turned on for a period of time to deliver power to the affected

    households. This binding configuration may last as long as the failures occur and during

    repair/maintenance operations. Physical actions by system operators are not required as long as

    the protection controllers are able to organize the switching of the power flow.

    3.3. DYNAMIC ALLOCATION OF OPERATING RESERVES

    There are power lines that do not maintenance the technology for power balancing or do not have

    automated switches. Also, load-balancing has its limits particularly when the power demand

    increases and supplementary power supply is needed in the system. Gridlock generation is

    essential in the power setup to match supply and demand without instigating cascading failures by

    overloaded power lines. This backup generation is the operating reserves ofa power grid.

    Usually, an operating standby is a generating power capacity presented on demand to the systemoperator within a period of time. An operating standby is usually activated to meet power demand

    in case of system disturbances, such as power line failures or system maintenance. While there

    are several operating assets that match different system requirements, two main types of operatingstandby are used by system operators [26]:

    a. Spinning reserve: This is supplementary synchronized generated capacity obtainable in thesystem by increasing the power output of the online power generators. Spinning standby can too

    mention to receptive loads as a result of demand-side energy supervision [27,28].

    b. Non-spinning reserve: This is supplementary non-synchronized generated capacity that can bemade available to the system by offline power generators within a longer retro of time than

    spinning standby. The power exchanged via power flow gates amid different transmission zones

    is also a system of non-spinning standby.

    Figure 5 shows a simplified diagram of spinning and non-spinning assets. This additional

    capacity can be made presented within 10 minutes approximately for a period of approximately30 minutes conditional on the type of standby and the technical topographies of the physical

    resources that enable it [29]. Failures of power lines and cascading failures can be prohibited byindicating the point where the supplementary power is injected. For example, if the power lines

    adjacent in the main power supply of Figure 5 cannot support the extra power of spinningstandby, an alternative standby that is end-to-end to lines with higher capacity can be designated.

    Also, offline power generators have a varying startup time that is too related to the actual power

    activated, mentioned to as slope frequency [29]. Multiple assets can be activated and combined to

    confirm the robustness of power transmission. Finally note that the traditional spinning standby is

    usually additional expensive than the non-spinning one and consequently the cost can also be a

    assortment issue.

    Operating standby is traditionally activated physically by system operators as arranged offline by

    market indentures [29]. As Smart Power Grids scale and develops additional complex anddynamic, failures and their cascading effects cannot be managed by system operators. An online,

    automated and dynamic allocation of operating assets is required. So, this section proposes thedynamic allocation of operating assets by software embedded control systems. Figure 6 shows the

    control fundamentals of a power line that is protected by three operating assets: (i) A spinningstandby in the supply node, (ii) a second spinning standby that acts as a receptive load enabled by

    a demand-side energy management mechanism and (iii) a non-Spinning standby that remains

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    9/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    23

    offline under normal system operation. All power line and node, including the ones of the non-spinning assets, has a load sensor and a protection controller individually. Also, all node that acts

    as an operating standby has a stabilization actuator that activates and deactivates the operating

    standby. The protection controllers, that are adjacent to an overloaded power line, check if a first-

    level reconfiguration is possible and adequate to balance the load of the affected power line. If the

    first-level reconfiguration cannot be applied, the protection controllers either activate their local

    reserve, if they have one, or coordinate with other remote protection controllers the allocation oftheir assets.

    Fig. 5 A power system with different operating reserves

    Dynamic binding is required between the remote protection controllers to synchronize the

    activation of operating assets in a cost-effective method. Additionally, if a non-spinning standbyis activated, the load sensor of its end-to-end power lines may need to be dynamically bound with

    the other end-to-end nodes. An ALSOS-ICS application can do this facility by inter-operating and

    arranging the I/O bindings in the control application of dynamically allocated operating assets.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    10/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    24

    Fig. 6: The overlay network of control rudiments that allocate and control operating reserves for the

    protection of a power line from an overload

    3.4. DYNAMIC RESTORATION AFTER BLACKOUT

    The transmission and distribution system is gathered in one or additional place that cannot

    conversation power due to failed power lines or nodes. These failures may be remote or

    cascading. The concluding is the key source of blackouts in power systems. Throughout acascading failure, a power flow is forced to a rerouting that makes other lines and nodesoverloaded and failing. This failing procedure is recursive. The system restoration after such a

    condition is highly complex. A modest and arbitrary restoration of the failed units does notsecurity the system restoration back to normal operation. Demand draws the power that is made

    presented after restoration causing a new failure. Synchronization is essential during therestoration process by interconnecting the synchronizing the power flow that is complete

    presented after a blackout. This management means that the I/O binding of the cyber-physicalcontrol principles should be adjusted dynamically during this process. Current restoration

    methods are principally achieved by system operators that apply manual actions based on their

    involvement [7].

    Figure 7 shows an instance of synchronization performed for the restoration of a system after a

    blackout. Note that this situation adopts that there is available reserved power for the controlrudiments to perform their control tasks. So, the overlay network of the control rudiments is

    eager, connected and manageable compared to the affected physical setup. A modest cascading

    failure causes this blackout. The system, in which the events occur, is numbered and shown inorder as follows: First, an unexpected failure occurs to one of the generators that Causes (i) a

    lower power inoculation in the system and (ii) the absence of its adjacent transmission lines

    (event #1). Since of this failure, two events monitor: (i) The power of the second generator is

    redirected to its second power line and (ii) the spinning standby of the second generator isactivated. The activation occurs since of the frequency drop that the failure of the first generator

    sources (event #2). This increased load makes a second node overloaded and failing (event #3).

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    11/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    25

    This cascading failure clusters the power network. A blackout has occurred and the system needsto be restored in a synchronized and opportune mode.

    Fig. 7: A sequence of coordination actions for a blackout restoration

    The goal of the restoration approach is to interconnect the substation that resulted after the

    blackout. This can be attained by retrogressive the overload in the failing node. Three

    arrangements are applied: (i) Activation of spinning standby using demand-side energy

    management (event #4), (ii) activation of non-spinning standby by turning on a backup generator(event #5) and (iii) adjusting the generation in A to restore the failed node (event #6). After

    these actions, the substation are again interconnected (event #7). Though, the activated non-

    spinning standby cannot run for extended and it is an exclusive power source. So, power isimported from a neighboring zone via a flow gate that interconnects the two zones (event #8). At

    the same time, the non-spinning standby turns off (event #9), the initial power generation is

    stabilized (event #10) and demand is fully aided over (event #11). These arrangements whole thesystem restoration. Later on, if the failed generator is fixed, new alterations can be applied toremove the power dependency from the bordering transmission zone.

    All these arrangements should be implemented in a convinced priority and timely method.

    Synchronization is vital. For example, the generator in A should be dynamically bound to theback-up generator in B to coordinate and adjust the allocation of power that will enable the

    overloaded node to be obtainable again and interconnect the two substation. If arrangements arenot synchronized, then new failures may occur that may result in more isolated that cannot be

    energized. For this reason, an situation in the physical layer should not be reflected in the overlay

    network of control rudiments. The overlay network should continue connected and allow thecontrol rudiments of ALSOS-ICS to inter-communicate between different place and then supportthe synchronization and restorations arrangements. Note that, as mentioned in Section 2, a

    conversing protocol implementation for the I/O detection sensors is a significant high-quality inthis case. Conversing builds and maintains a dynamic well connected and non-clustered overlay

    network that remnants robust even in case of disastrous failures [30]. Note that, dynamic blackoutrestoration arrangements are based on dynamic load balancing of power lines, switching of power

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    12/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    26

    flow and allocation of operating assets. So, more effective mechanisms for blackout preventionsupport additional operative blackout restoration in case it occurs.

    4. DISCUSSIONS

    The protection of the power grid is a highly inspiring and complex problem that should bedisintegrated and achieved at different levels. This paper shows coordination scenarios withinfour incremental Smart Power Grid protection levels. The protection supplies in all situation are

    conventionally content by experienced system operators that apply manual arrangements aided bycentralized data acquisition and supervisory systems. Yet, as micro-generation scales and

    develops additional decentralized, such an methodology converts cost-ineffective. A higher level

    of automation is essential, which resources that control rudiments supervision several physical

    properties need to converted additional interactive and intelligent. Distributed computational

    intelligence involves a situational awareness that can be attributed to a system if and only if its

    rudiments have the potential to be dynamically bound with all other on-demand. Deprived of

    dynamic I/O binding of control rudiments, coordination cannot always be achieved. This isaccurately what the four incremental situations for the protection of the Smart Power Grid show.

    For example, binding an offline generator to the rest of the control rudiments when operating

    reserves are utilized is essential to control and synchronize the injected power flow in the system.Without such a binding, a protection measure may cause new cascading failures.

    The modeling approach of ALSOS-ICS couples dynamic I/O binding capabilities with the rest ofthe control logic of a cyber-physical system. he Internet of Gears requires reconfigurable physical

    and software control essentials that ALSOSICS can dynamically bind and organize. ALSOS-ICScontrol rudiments are able to interoperate as a control application with the rest of the control

    rudiments. This difference proposes a split of apprehensions for system developers, yet, thesetting remains within control systems of Internet of Gears and their solicitations. Additional

    specifically, ALSOS-ICS developers, extending the work of application integrators, build control

    rudiments that provide dynamic I/O binding capabilities to additional set of control rudiments,

    developed by domain-experts that embed the key control application logic. In the four applicationsetups shown in Section 3, the main domain-expert developer has knowledge about the protection

    of the Smart Power Grid, and additional exactly about the available repair and maintenancemechanisms.

    This inventor delivers the load-sensors, protection controllers and stabilization actuators. It adopts

    a certain level of interaction and communication capabilities that ALSOS-ICS developers exposevia, for instance, interfaces. The actual I/O binding discovery, assortment and reconfiguration is

    moved by the control rudiments of ALSOS-ICS developed by network communication

    professionals.

    5. CONCLUSIONS

    This application setups of operational control reconfigurations for the robustness of the Smart

    Power Grid. Each of these setups involves some degree of coordination amid control rudimentsthat achieve various physical assets. With the appearance of micro-generation and renewableresources, matching supply and demand becomes challenging with an impact on the robustness of

    the power grid. Coordination needs to evolve beyond the control of system operators, develop

    additional automated, decentralized and adaptable by control rudiments.

    The synchronization and computational intelligence of control rudiments entails capabilities for

    dynamic binding reconfigurations in this instance. Dynamic binding reconfigurations required for

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    13/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    27

    applications of the Internet of Gears can be modeled as a control application using the ALSOS-ICS model summarized in this paper. ALSOS-ICS allows a higher interoperation and modularity

    amid control applications and a higher flexibility, integration and applicability of dynamic

    binding reconfigurations in the domains of the Internet-scale cyber-physical control systems.

    Operational control reconfigurations are vital in other application domains beyond the Smart

    Power Grid. ALSOS-ICS is application-independent and therefore various domains of Internet of

    Things, such as transportation systems, air vehicles etc.

    REFERENCES

    [1] A. Meier. Electric power systems: a conceptual introduction. Wiley survival guides in engineering

    and science. IEEE Press, 2006.

    [2] T. Gensler and C. Zeidler.Rule-Driven Component Composition for Embedded Systems. In

    International Conference on Software Engineering (ICSE): Workshop on Component-Based

    Software Engineering, 2001.

    [3] E. Lee. Cyber physical systems: Design challenges. In Object Oriented Real-Time Distributed

    Computing (ISORC), 2008 11th IEEE International Symposium on, pages 363 369, May 2008.

    [4] D. Hammerstrom, T. Oliver, R. Melton, and R. Ambrosio. Standardization of a hierarchicaltransactive control system.In Proceedings of the Grid Interop 09 Conference, 2009.

    [5] A. Koubaa and B. Andersson.A Vision of Cyber-Physical Internet.In 8th International Workshop

    on Real-Time Networks (RTN09), 2009.

    [6] S. Karnouskos. Cyber-physical systems in the smartgrid. In Industrial Informatics (INDIN), 2011

    9th IEEE International Conference on, pages 20 23, july 2011.

    [7] F. L. Greitzer, R. Podmore, M. Robinson, and P. Ey.Naturalistic decision making for power

    system operators. International Journal of Human-Computer Interaction, 26(2-3):278291, 2010.

    [8] L. Wang, S. Balasubramanian, and D. H. Norrie. Agent-based Intelligent Control System Design

    For Real-time Distributed Manufacturing Environments. pages 115152. In Working Notes of the

    Agent Based Manufacturing Workshop, 1998.

    [9] I. Georgiadis, J. Magee, and J. Kramer. Self-organising software architectures for distributed

    systems. In Proceedings of the first workshop on Self-healing systems - WOSS 02, page 33, New

    York, NY, USA, Nov. 2002. ACM Press

    [10] M. Guler, S. Clements, N. Kejriwal, L. Wills, B. Heck, and G. Vachtsevanos. Rapid Prototyping

    of Transition Management Code for Reconfigurable Control Systems.In Proceedings of the 13th

    IEEE International Workshop on Rapid System Prototyping (RSP02), Washington, 2002.IEEE

    Computer Society.

    [11] J. Kramer and J. Magee. Self-Managed Systems: an Architectural Challenge. In Future of

    Software Engineering (FOSE 07), pages 259268. IEEE, May 2007.

    [12] E. Pournaras, M. Yao, and R. Ambrosio. Dynamic composition and reconfiguration of internet-

    scale control systems. In Digital Ecosystems and Technologies Conference (DEST), 2011

    Proceedings of the 5th IEEE International Conference on, pages 233 240, June 2011.

    [13] C.-S. Chen, C.-T.Tsai, C.-H.Lin, W.-L.Hsieh, and T.-T. Ku.Loading balance of distribution

    feeders with loop power controllers considering photovoltaic generation. Power Systems, IEEE

    Transactions on, 26(3):1762 1768, Aug. 2011.

    [14] M. Ahmed and W. Soo. Development of customized distribution automation system (DAS) for

    secure fault isolation in low voltage distribution system. In Power and Energy Society General

    Meeting - Conversion and Delivery of Electrical Energy in the 21st Century, 2008 IEEE, pages 1

    7, July 2008.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    14/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    28

    [15] K. Divya and J. stergaard.Battery energy storage technology for power systemsan overview.

    Electric Power Systems Research, 79(4):511 520, 2009.

    [16] D. Van Hertem, J. Verboomen, K. Purchala, R. Belmans, and W. Kling. Usefulness of DC power

    flow for active power flow analysis with flow controlling devices.In AC and DC Power

    Transmission, 2006.ACDC 2006.The 8th IEE International Conference on, pages 58 62, Mar.

    2006.

    [17] J. Verboomen, D. Van Hertem, P. Schavemaker, W. Kling, and R. Belmans. Phase shifting

    transformers: principles and applications. In International Conference on Future Power Systems,

    2005, page 6, Nov. 2005.

    [18] R. Grunbaum and J. Pernot.Thyristor-controlled series compensation: A state of the art approach

    for optimization of transmission over power links. In 1st International Forum on Innovations in

    Power Links, pages 1520, Mar. 2001.

    [19] N. I. Maruf, A. Mohsin, A. Shoeb, K. Islam, and M. Hossain. Study of Thyristor Controlled Series

    Capacitor (TCSC) as a Useful Facts Device. International Journal of Engineering Science and

    Technology, 2(9):43574360, 2010.

    [20] M. Abdel-Moamen and N. Padhy.Optimal power flow incorporating FACTS devices

    bibliography and survey. In Transmission and Distribution Conference and Exposition, 2003 IEEE

    PES, volume 2, pages 669 676, Sept. 2003.

    [21] X. Jiang. Operating Modes and their Regulations of Voltage-sourced Converter Based Facts

    Controllers.PhD thesis, Faculty of Rensselaer Polytechnic Institute, Rensselaer Polytechnic

    Institute, 2007.

    [22] R. Greer, W. Allen, J. Schnegg, and A. Dulmage. Distribution automation systems with advanced

    features. In Rural Electric Power Conference (REPC), 2011 IEEE, pages C41C4 15, Apr.

    2011.

    [23] S. Jalilzadeh, H. Hosseini, V. Nabaei, G. Govar, and M. Zandi. Multipurpose reconfiguration of

    deregulated distribution networks using BGA. In Power and Energy Conference, 2008.PECon

    2008. IEEE 2nd International, pages 1222 1226, Dec. 2008.

    [24] X. Mamo, S. Mallet, T. Coste, and S. Grenard. Distribution automation: The cornerstone for smart

    grid development strategy. In Power Energy Society General Meeting, 2009.PES 09.IEEE, pages

    1 6, July 2009.

    [25] J. Santos, N. Silva, P. Rodrigues, A. Rodrigues, D. Marsh, F. Gomes, C. M. Pinto, A. Blanquet,

    and A. Carrapatoso. Electric grid versus data network architectures and standards Smart Grid as

    plug & play. IET Conference Publications, 2009(CP550):912, 2009.

    [26] F. D. M. Ch, D. B. Bedoya, G. D. M. Jannuzzi, and L. C. P. Da Silva. Operating reserves provided

    by distributed generation. In Proceedings of the 3rd IASME/WSEAS International Conference on

    Energy & Environment, pages 219224, Stevens Point,Wisconsin, USA, 2008. World Scientific

    and Engineering Academy and Society (WSEAS).

    [27] B. Kirby. Load response fundamentally matches power system reliability requirements. In Power

    Engineering Society General Meeting, 2007. IEEE, pages 16, June 2007.

    [28] E. Pournaras, M. Warnier, and F. M. Brazier.Local Agent-based Self-stabilisation in Global

    Resource Utilisation. International Journal of Autonomic Computing, 1(4):350 373, Dec.2010.

    [29] J. Chen, J. Thorp, R. Thomas, and T. Mount.Locational pricing and scheduling for an integratedenergy-reserve market.In System Sciences, 2003.Proceedings of the 36th Annual Hawaii

    International Conference on, page 10 pp., Jan. 2003.

    [30] M. Jelasity, S. Voulgaris, R. Guerraoui, A.-M.Kermarrec, and M. van Steen. Gossip-based peer

    sampling.ACM Trans. Comput. Syst., 25(3), Aug. 2007.

  • 7/28/2019 Large Scale Cyber Physical Robust Grid Smart Power Control

    15/15

    Electrical & Computer Engineering: An International Journal (ECIJ) Volume 2, Number 2, June 2013

    29

    Authors

    1Mr. Amit Sachan has completed M.Tech degree in department of Electrical

    Engineering. He continuing his profession as Assistant Professor in Regional College

    for Education Research & Technology and doing research work in the field of Electrical

    power Engineering.

    2Preeti Sachan has completed B Tech in Computer Science & Engineering from NIT Raipur. She did

    M.Tech in Information Security from NIT Rourkela. Currently working as Software Engineer in HCL

    Technologies & also involved in research work.