6
Knottingley Power Project March 2013 Page 1 Prepared by Parsons Brinckerhoff Project Information Note The Gas Pipeline Introduction The CCGT power plant will be fuelled by a supply of natural gas. The supply of natural gas will be taken from a new underground Gas Pipeline (together with associated infrastructure, principally an Above Ground Installation (AGI)) which will be constructed between the CCGT power plant site and the National Grid National Gas Transmission System. The new underground Gas Pipeline will be approximately 8 kilometres (km) in length. The AGI will be constructed at the connection point to the existing National Grid pipeline. Description of Gas Pipeline and Above Ground Infrastructure The proposed route for the Gas Pipeline takes a northerly exit from the CCGT power plant site, running under the Aire and Calder Navigation Canal and the A645 (Weeland Road). The proposed route then turns north-east and continues on to Kellington. The proposed route then turns towards the north, but is still heading in a roughly north-east direction. The proposed route crosses the River Aire, and continues north-east towards the National Transmission System. The connection to the National Transmission System is made south of Gateforth, off Pale Lane. The proposed route of the new underground Gas Pipeline is shown in the attached Plan. The AGI will be an un-manned facility. The AGI will comprise two separate compounds: one compound owned and operated by National Grid; and, one compound owned and operated by Knottingley Power Limited. Each compound will be enclosed by a steel security fence approximately 2.7 m high. Furthermore, both compounds will be located within the overall AGI site enclosed by a stock-proof fence. The equipment within the AGI (with the exception of lighting columns which will be approximately 4.5 m) will be lower than approximately 2.7 m. The proposed layout for the AGI is shown in the attached Plan. Proposed Programme The proposed programme, comprising construction / operation / decommissioning dates, is as follows: Start of Construction: 2015 Connection to and Commissioning of CCGT Power Plant: 2017 Full Operation of CCGT Power Plant: 2018 Decommissioning: 2043 These dates have been selected to tie in with the proposed dates for the construction / connection and commissioning / operation and decommissioning of the CCGT power plant. The construction of the Gas Pipeline is expected to take one year, however two years are allowed such that there is a construction contingency. Construction The majority of environmental impacts arising from the development of gas pipelines (and their associated infrastructure) occur during construction. The construction methods to be used on the KPP Gas Pipeline represent proven methods that have been developed over many years from experience on similar projects. All construction activities are undertaken within a temporarily fenced-off strip of land, which is referred to as the "working width". The working width will typically be 26 to 30 m wide. Access to the “working width” will be at defined points to be

Knottingley Power Project Power Project March 2013 Page 1 Prepared by Parsons Brinckerhoff Project Information Note The Gas Pipeline Introduction The CCGT power plant will be fuelled

Embed Size (px)

Citation preview

Knottingley Power Project

March 2013 Page 1 Prepared by Parsons Brinckerhoff

Project Information Note The Gas Pipeline

Introduction The CCGT power plant will be fuelled by a supply of natural gas. The supply of natural gas will be taken from a new underground Gas Pipeline (together with associated infrastructure, principally an Above Ground Installation (AGI)) which will be constructed between the CCGT power plant site and the National Grid National Gas Transmission System. The new underground Gas Pipeline will be approximately 8 kilometres (km) in length. The AGI will be constructed at the connection point to the existing National Grid pipeline.

Description of Gas Pipeline and Above Ground Infrastructure The proposed route for the Gas Pipeline takes a northerly exit from the CCGT power plant site, running under the Aire and Calder Navigation Canal and the A645 (Weeland Road). The proposed route then turns north-east and continues on to Kellington. The proposed route then turns towards the north, but is still heading in a roughly north-east direction. The proposed route crosses the River Aire, and continues north-east towards the National Transmission System. The connection to the National Transmission System is made south of Gateforth, off Pale Lane.

The proposed route of the new underground Gas Pipeline is shown in the attached Plan.

The AGI will be an un-manned facility. The AGI will comprise two separate compounds: one compound owned and operated by National Grid; and, one compound owned and operated by Knottingley Power Limited. Each compound will be enclosed by a steel security fence approximately 2.7 m high. Furthermore, both compounds will be located within the overall AGI site enclosed by a stock-proof fence. The equipment within the AGI (with the exception of lighting columns which will be approximately 4.5 m) will be lower than approximately 2.7 m. The proposed layout for the AGI is shown in the attached Plan.

Proposed Programme The proposed programme, comprising construction / operation / decommissioning dates, is as follows:

Start of Construction: 2015

Connection to and Commissioning of CCGT Power Plant: 2017

Full Operation of CCGT Power Plant: 2018

Decommissioning: 2043

These dates have been selected to tie in with the proposed dates for the construction / connection and commissioning / operation and decommissioning of the CCGT power plant. The construction of the Gas Pipeline is expected to take one year, however two years are allowed such that there is a construction contingency.

Construction The majority of environmental impacts arising from the development of gas pipelines (and their associated infrastructure) occur during construction. The construction methods to be used on the KPP Gas Pipeline represent proven methods that have been developed over many years from experience on similar projects.

All construction activities are undertaken within a temporarily fenced-off strip of land, which is referred to as the "working width". The working width will typically be 26 to 30 m wide. Access to the “working width” will be at defined points to be

Knottingley Power Project

March 2013 Page 2 Prepared by Parsons Brinckerhoff

agreed by the Local Planning Authority and Land Owners / Land Occupiers. Points of access will be carefully controlled and signposted.

During construction of the Gas Pipeline, construction activities will normally be progressed in the following order: pre-construction activities (i.e. fencing, hedgerow removal, land drainage schemes); top-soil stripping; pipe stringing; welding and joint coating; trenching and laying; commissioning (i.e. cleaning, gauging, testing); and permanent re-instatement.

In addition to the typical construction activities, special teams will be set up to undertake any works associated with “special crossings” (i.e. road /rail / water crossings). Accordingly, in addition to the more standard ‘open cut’ construction technique, typical (trenchless) special crossing construction techniques include: auger boring; tunnelling; and, HDD.

Operation After full commissioning of the Gas Pipeline, it will be operated and maintained in such a manner as to keep it safe and in good condition. Regular monitoring will be undertaken.

Decommissioning The Gas Pipeline will be decommissioned when it reaches the end of its useful life. Based on current best practice, it is likely that the Gas Pipeline will be left in place and stabilised.

Environmental Impact Assessment The potential environmental impacts of the Gas Pipeline during construction / pre-commissioning / commissioning / operation / decommissioning have been assessed in relation to the following aspects of the environment: air quality; noise and vibration; ecology; water resources; geology and soils; landscape and visual; traffic, transport and access; cultural heritage / archaeology; and, socioeconomics.

Following the implementation of mitigation and monitoring measures, the assessment has indicated that the residual impacts associated with the Gas Pipeline are considered to be Not Significant.

Safety Safety is of fundamental importance during every stage of planning, routing, design, construction and subsequent operation of a high pressure gas pipeline. As such, a number of appropriate safety considerations have been considered to ensure compliance with the requirements of the Health and Safety Executive (HSE) and ensure safe operation of the Gas Pipeline.

Further information is available in the Preliminary Environmental Information Report.

Date: Scale: Sheet:

Designed:

Drawn:

Approved:

Checked:

Title:

Site/Project:

Client:

© Copyright Parsons Brinckerhoff

Tel: 44-(0)161-200-5000Fax: 44-(0)161-200-5001

A3

Manchester Technology CentreOxford RoadManchester M1 7ED

07/03/2013

Plo

t Dat

e:07

/03/

2013

14:

16:3

5Z:

\Oil

& G

as\8

.0 -

Pro

ject

s\8.

1 - L

ive\

3511

480

- Kno

tting

ley

- Rou

te S

elec

tion

Stu

dy a

nd P

lann

ing

Con

sent

\Pha

se 2

\DW

G\S

ectio

n 42

Dra

win

gs\E

SB

I-KP

L-P

A-0

07_3

0000

.dw

gFi

le N

ame:

Tick

le, M

ark

Logi

n:

AppChkByDescriptionDateRev

Pro

ject

Num

ber:

Rev

isio

n:D

raw

ing

Num

ber:

Project Number: Revision:Drawing Number:

AESBI/KPL/PA/007N/A

N/A1:30,000

B.W.

A.J.

B.W.

M.T.

GAS PIPELINE PLAN KEY

POWER LTDKNOTTINGLEY

N

Legend:-

Proposed Gas Pipeline Route

Proposed Location of AGI

Reproduced from '10k Raster Data' by permission of Ordnance Survey ® on behalfof the Controller of Her Majesty's Stationery Office. © Crown Copyright 2011.All rights reserved. Reference number 10001998.

KPL Site Plot

SCALE 1:30000 @ A3

GAS PIPELINE PLAN (1)

500 1000m0

GAS PIPELINE PLAN (2)

GAS PIPELINE PLAN (3)

A 07/03/2013 First Issue M.T. A.J. B.W.

Date: Scale: Sheet:

Designed:

Drawn:

Approved:

Checked:

Title:

Site/Project:

Client:

© Copyright Parsons Brinckerhoff

Tel: 44-(0)161-200-5000Fax: 44-(0)161-200-5001

A3

Manchester Technology CentreOxford RoadManchester M1 7ED

07/03/2013

Plo

t Dat

e:07

/03/

2013

09:

59:0

2Z:

\Oil

& G

as\8

.0 -

Pro

ject

s\8.

1 - L

ive\

3511

480

- Kno

tting

ley

- Rou

te S

elec

tion

Stu

dy a

nd P

lann

ing

Con

sent

\Pha

se 2

\DW

G\S

ectio

n 42

Dra

win

gs\E

SB

I-KP

L-P

A-0

04_1

0000

.dw

gFi

le N

ame:

Tick

le, M

ark

Logi

n:

AppChkByDescriptionDateRev

Pro

ject

Num

ber:

Rev

isio

n:D

raw

ing

Num

ber:

Project Number: Revision:Drawing Number:

AESBI/KPL/PA/004N/A

N/A1:10,000

B.W.

A.J.

B.W.

M.T.

GAS PIPELINE PLAN (1)

POWER LTDKNOTTINGLEY

N

Legend:-

Proposed Gas Pipeline Route

Reproduced from '10k Raster Data' by permission of Ordnance Survey ® on behalfof the Controller of Her Majesty's Stationery Office. © Crown Copyright 2011.All rights reserved. Reference number 10001998.

KPL Site Plot

00 250

SCALE 1:10000 @ A3

500m

Date: Scale: Sheet:

Designed:

Drawn:

Approved:

Checked:

Title:

Site/Project:

Client:

© Copyright Parsons Brinckerhoff

Tel: 44-(0)161-200-5000Fax: 44-(0)161-200-5001

A3

Manchester Technology CentreOxford RoadManchester M1 7ED

07/03/2013

Plo

t Dat

e:07

/03/

2013

09:

59:4

2Z:

\Oil

& G

as\8

.0 -

Pro

ject

s\8.

1 - L

ive\

3511

480

- Kno

tting

ley

- Rou

te S

elec

tion

Stu

dy a

nd P

lann

ing

Con

sent

\Pha

se 2

\DW

G\S

ectio

n 42

Dra

win

gs\E

SB

I-KP

L-P

A-0

05_1

0000

.dw

gFi

le N

ame:

Tick

le, M

ark

Logi

n:

AppChkByDescriptionDateRev

Pro

ject

Num

ber:

Rev

isio

n:D

raw

ing

Num

ber:

Project Number: Revision:Drawing Number:

AESBI/KPL/PA/005N/A

N/A1:10,000

B.W.

A.J.

B.W.

M.T.

GAS PIPELINE PLAN (2)

POWER LTDKNOTTINGLEY

N

Legend:-

Proposed Gas Pipeline Route

Reproduced from '10k Raster Data' by permission of Ordnance Survey ® on behalfof the Controller of Her Majesty's Stationery Office. © Crown Copyright 2011.All rights reserved. Reference number 10001998.

00 250

SCALE 1:10000 @ A3

500m

Date: Scale: Sheet:

Designed:

Drawn:

Approved:

Checked:

Title:

Site/Project:

Client:

© Copyright Parsons Brinckerhoff

Tel: 44-(0)161-200-5000Fax: 44-(0)161-200-5001

A3

Manchester Technology CentreOxford RoadManchester M1 7ED

07/03/2013

Plo

t Dat

e:07

/03/

2013

10:

00:2

2Z:

\Oil

& G

as\8

.0 -

Pro

ject

s\8.

1 - L

ive\

3511

480

- Kno

tting

ley

- Rou

te S

elec

tion

Stu

dy a

nd P

lann

ing

Con

sent

\Pha

se 2

\DW

G\S

ectio

n 42

Dra

win

gs\E

SB

I-KP

L-P

A-0

06_1

0000

.dw

gFi

le N

ame:

Tick

le, M

ark

Logi

n:

AppChkByDescriptionDateRev

Pro

ject

Num

ber:

Rev

isio

n:D

raw

ing

Num

ber:

Project Number: Revision:Drawing Number:

AESBI/KPL/PA/006N/A

N/A1:10,000

B.W.

A.J.

B.W.

M.T.

GAS PIPELINE PLAN (3)

POWER LTDKNOTTINGLEY

N

Legend:-

Proposed Gas Pipeline Route

Proposed Location of AGI

Reproduced from '10k Raster Data' by permission of Ordnance Survey ® on behalfof the Controller of Her Majesty's Stationery Office. © Crown Copyright 2011.All rights reserved. Reference number 10001998.

KPL Site Plot

00 250

SCALE 1:10000 @ A3

500m