38
KEEPING HOUSTON AIRPORTS OPENING DAY FRESH Copyright © 2016. Houston Airport System. All rights reserved. Devon Tiner, P.E., PMP Assistant Director – Asset Engineering June 9, 2016

KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

KEEPINGHOUSTON AIRPORTS OPENING DAY FRESH

Copyright © 2016. Houston Airport System. All rights reserved.

Devon Tiner, P.E., PMPAssistant Director – Asset EngineeringJune 9, 2016

Page 2: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

Copyright © 2016. Houston Airport System. All rights reserved.

VISION AND MISSIONSTATEMENT

MISSION: WE EXIST TO CONNECT PEOPLE, BUSINESSES, CULTURES AND ECONOMIES OF THE WORLD TO HOUSTON.

VISION: ESTABLISH HOUSTON AS A FIVE-STAR GLOBAL AIR SERVICE GATEWAY WHERE THE MAGIC OF FLIGHT IS CELEBRATED.

2

Page 3: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

Copyright © 2016. Houston Airport System. All rights reserved.3

ABOUT HOUSTON AIRPORT SYSTEM

Page 4: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

ABOUT HOUSTON AIRPORTS

Copyright © 2016. Houston Airport System. All rights reserved.4

IAH

EFDHOU

• George Bush

Intercontinental

Airport (IAH) – the largest airport ,43 million passengers annually

• William P. Hobby

Airport (HOU) –12 million passengers annually, with international flights Oct 2015

• Ellington Airport

(EFD) – GA/Military potential spaceport site

Page 5: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

PASSENGER GROWTH:1988 TO 2014ABOUT HOUSTON AIRPORTS

Copyright © 2016. Houston Airport System. All rights reserved.5

Page 6: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

INFRASTRUCTURE

$0

$20,000,000

$40,000,000

$60,000,000

$80,000,000

$100,000,000

$120,000,000

2011 2012 2013 2014 2015 2016

Annual Project Invoicing

Construction Professional Services

Copyright © 2016. Houston Airport System. All rights reserved.6

INFRASTRUCTURE - PROJECT SPENDING

Page 7: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

INFRASTRUCTURE

• 3 Contracts with 5-year duration:– Civil – RS&H– Architectural – PGAL– MEP - Jacobs

• Origination date: 9/19/2012• Total Contract to date: $30,600,000

– Original Appropriation: $6,000,000– Additional Appropriation on 12/18/2013 for $6,600,000– Additional Appropriation on 12/1/2014 for $18,000,000

• Proposed additional appropriation for $12,650,000 in June 2016• Total proposed contract is $43,250,000• Expiration date 9/26/2017

Copyright © 2016. Houston Airport System. All rights reserved.7

DESIGN ON CALL CONTRACTS - OVERVIEW

Page 8: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

INFRASTRUCTURE

$0

$1,000,000

$2,000,000

$3,000,000

$4,000,000

$5,000,000

$6,000,000

$7,000,000

$8,000,000

$9,000,000

FY2013 FY2014 FY2015 FY2016

Invoicing

Civil MEP Architectural

Copyright © 2016. Houston Airport System. All rights reserved.8

DESIGN ON-CALL CONTRACTS ANNUAL EXPENDITURES

Page 9: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

DESIGN ON-CALL - TOTAL EXPENDITURESINFRASTRUCTURE

$10,741,100 $4,316,173

$3,468,591

Billed to Date $18,525,866

Civil MEP Architectural

55%26%

19%

Total LOAs $26,814,412

Civil MEP Architectural

Copyright © 2016. Houston Airport System. All rights reserved.9

Page 10: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

Copyright © 2016. Houston Airport System. All rights reserved.10

2016 INFRASTRUCTURERFQSINFRASTRUCTURE: $110,000,000

Page 11: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

• Infrastructure– Architectural/Engineering Design On-Call Services

• IAH– Multi-Use Airport Resource Center (MARC) - Design/Build– Vehicle / Fleet Maintenance Facility - Design/Build – Taxiway SA & SB Rehabilitation - Design– Landside Roadway Repairs - CMAR– Sanitary Sewer Improvements - CMAR

Copyright © 2016. Houston Airport System. All rights reserved.11

OVERVIEW

Page 12: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

• HOU– Taxiways D & E Reconfiguration - Design

• EFD– Spaceport Incubator Building – Design Build– Spaceport Phase 1 Infrastructure – Design Build

Copyright © 2016. Houston Airport System. All rights reserved.12

OVERVIEW

Page 13: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

• Five (5)-year contract• Anticipated projects include:

Copyright © 2016. Houston Airport System. All rights reserved.13

ARCHITECTURAL/ENGINEERING DESIGN ON-CALL SERVICES

– Fuel Farm Expansion– Signage Improvements– BHS Enhancements– Central Utility Plant (CUP) Upgrades– Parking Garage Rehabilitation– Automated People Mover (APM)

Rehabilitation– Drainage Improvements

– Electrical Distribution System Upgrades

– Terminal Restroom Remodel– Airfield Pavement Rehabilitation– Landside Roadway Improvements– Parking Development &

Improvements

RFQ anticipated to advertise in November 2016

Page 14: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

IAH – MULTI-USE AIRPORT RESOURCE CENTER (MARC)

2016 INFRASTRUCTURE RFQS

• Airport Emergency Operations Center (AEOC)

• Division Operations Center (DOC)

• Airport Communications Center (ACC)

• Data Center (Tier 3-ish)• IT Division Office• Design / Build• Approximately $30,000,000• RFQ anticipate October 2016

Copyright © 2016. Houston Airport System. All rights reserved.14

ACCDataCenter

DOC

AEOC

Page 15: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

IAH – VEHICLE / FLEET MAINTENANCE FACILITY2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.15

• 24,000-SF Facility• Design/Build• Approx. $8,500,000• RFP anticipated Sept. 2016

Proposed Location

Page 16: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

IAH – TAXIWAY SA & SB REHABILITATION2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.16

• Reconstruction of asphalt taxiways• $40,000,000 AIP Entitlement Program• RFQ anticipated September 2016• Bids in hand by May 2017

Page 17: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

IAH – LANDSIDE ROADWAY REPAIRS2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.17

• RFQ for CMAR • Approx. $14,000,000

• RFP anticipated July 2016

Page 18: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

IAH – SANITARY SEWER IMPROVEMENTS2016 INFRASTRUCTURE RFQS

• CMAR for rehabilitation of sanitary sewer mains.

• Estimate is $9,000,000• RFQ anticipated Sept. 2016.

Copyright © 2016. Houston Airport System. All rights reserved.18

Page 19: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.19

WILLIAM P. HOBBY AIRPORT

Page 20: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.20

HOU - HOT SPOTS - DRAFT

Page 21: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

HOU - TAXIWAY D & E RECONSTRUCTION2016 INFRASTRUCTURE RFQS

• Demolish and reconstruct taxiways to FAA standards.

• Program Estimate: $27,000,000• RFQ for design services going to

advertise in December 2016• Bids in hand by May 2018

Copyright © 2016. Houston Airport System. All rights reserved.21

Page 22: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.22

EFD – SPACEPORT DEVELOPMENT

Future

Phases of

Development

PHASE I

DEVELOPMENT

Page 23: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.23

EFD – SPACEPORT PHASE 1

Page 24: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.24

EFD – SPACEPORT PHASE 1 - INFRASTRUCTURE

• RFQ for Design/Build to go out in December 2016

• Estimated value is $20,000,000

• RFQ for Design/Build to go out in December 2016

• Estimated value is $12,000,000

Incubator Building

Boeing

Building

Incubator

Building

Phase 1 Infrastructure

Page 25: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

2016 INFRASTRUCTURE RFQS

Copyright © 2016. Houston Airport System. All rights reserved.25

EFD – SPACEPORT PHASE 1 – WEST VIEW

Boeing

Building

Phase I

Incubator

Building

Page 26: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

Copyright © 2016. Houston Airport System. All rights reserved.26

2016 CONSTRUCTIONFORECASTINFRASTRUCTURE: $228,150,000

Page 27: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

CONSTRUCTION FORECAST

Copyright © 2016. Houston Airport System. All rights reserved.27

0 TO 3 MONTH PROCUREMENT FORECAST - INFRASTRUCTURE

Identifier Title Estimated Value Release DateEFD PN629 Control Tower Replacement 9,600,000 May-16

IAH PN565 Landside Roadway Rehabilitation 13,800,000 Jul-16

IAH PN749 Terminal A & B Up Ramps and

Approach Slab Reconstruction

1,600,000 Jul-16

EFD PN733 T-Hangar Pavement, Twy D/Rwy 4-22 3,000,000 Jun-16

IAH PN460C Airfield Pavements Rehabilitation 4,500,000 Aug-16

IAH PN675 Taxiway NA 54,000,000 Jun-16

IAH PN721 Cell Phone Lot 4,000,000 Aug-16

IAH PN737 Terminal B Core Electrial Upgrades 21,000,000 Aug-16

HOU PN703 Curbside Drop Off Canopy 4,000,000 Jun-16

Page 28: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

CONSTRUCTION FORECAST

Copyright © 2016. Houston Airport System. All rights reserved.28

3 TO 6 MONTH PROCUREMENT FORECAST - INFRASTRUCTURE

Identifier Title Estimated Value Release Date

IAH PN746 IAH Tower Demolition 4,500,000 Sep-16

IAH PN740 Design/Build for Vehicle / Fleet

Maintenance Facility

6,000,000 Sep-16

IAH PN736 Design/Build for Multi-Use Airport

Resource Center (MARC)

30,000,000 Oct-16

IAH O&M D/E Garage Structural Repairs 150,000 Oct-16

IAH PN 646 Design - Taxiway SA & SB

Rehabilitation

2,000,000 Sep-16

IAH PN699 Sanitary Sewer Improvements $9,000,000 Sep-16

IAH PN686 Storm Water Pollution Control

System -Environmental Stations

$6,000,000 Nov-16

Page 29: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

CONSTRUCTION FORECAST

Copyright © 2016. Houston Airport System. All rights reserved.29

6 TO 9 MONTH PROCUREMENT FORECAST - INFRASTRUCTURE

Identifier Title Estimated Value Release DateIAH PN741 Terminal A North & South Restroom

Remodel

6,000,000 Dec-16

HOU PN770 Taxiway D & E Rehabilitation 20,000,000 Dec-16

EFD Spaceport Incubator Building 20,000,000 Dec-16

EFD Spaceport Phase 1 Infrastructure 12,000,000 Dec-16

Page 30: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

CONSTRUCTION FORECAST

Copyright © 2016. Houston Airport System. All rights reserved.30

9 TO 12 MONTH PROCUREMENT FORECAST - INFRASTRUCTURE

Identifier Title Estimated Value Release DateNone None - N/A

Page 31: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

CONSTRUCTION FORECAST

Copyright © 2016. Houston Airport System. All rights reserved.31

2016 CONSTRUCTION PROCUREMENTS – ITRP DRAFT

Page 32: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

CONSTRUCTION FORECAST

Copyright © 2016. Houston Airport System. All rights reserved.32

2016 CONSTRUCTION PROCUREMENTS – ITRP CURRENT RFQS

• MLIT CMAR Services– Advertised on April 22, 2016– Proposals are due 6/10/2016 @ 10:00 AM– Contact Andre Morrow – [email protected]

• East Aircraft Parking Hardstand Design/Build– Advertised on April 22, 2016– Proposals are due 6/10/2016 @ 10:00 AM– Contact Al Oracion – [email protected]

Page 33: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

Copyright © 2016. Houston Airport System. All rights reserved.

HOW TO DO BUSINESS WITH HOUSTON AIRPORT SYSTEM

Page 34: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

HOW TO DO BUSINESS WITH HOUSTON AIRPORT SYSTEM

Copyright © 2016. Houston Airport System. All rights reserved.34

HTTP://FLY2HOUSTON.COM

Page 35: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

HOW TO DO BUSINESS WITH HOUSTON AIRPORT SYSTEM

Copyright © 2016. Houston Airport System. All rights reserved.35

WWW.HOUSTONAIRPORTS.BIZ/BUSINESSWELCOME

Page 36: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

HOW TO DO BUSINESS WITH HOUSTON AIRPORT SYSTEM

Copyright © 2016. Houston Airport System. All rights reserved.36

HTTP://WWW.HOUSTONAIRPORTS.BIZ/CONTRACTINGOPPORTUNITIES

Page 37: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

HOW TO DO BUSINESS WITH HOUSTON AIRPORT SYSTEM

EVENT DATE LOCATION

ASCE International Conference on Transportation & Development 2016

June 26th-29th, 2016 Omni Houston Galleria Hotel

Copyright © 2016. Houston Airport System. All rights reserved.37

UPCOMING EVENTS

Page 38: KEEPING HOUSTON AIRPORTS OPENING DAY FRESH · 2016-06-13 · 2016 CONSTRUCTION PROCUREMENTS –ITRPCURRENTRFQS • MLIT CMAR Services – Advertised on April 22, 2016 – Proposals

THANK YOU

Copyright © 2016. Houston Airport System. All rights reserved.

fly2houston.com