1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Procurements Thomas C. Nehring, PE Lead Electrical Engineer Conventional Facilities Advisory Committee - Review March 10-11, 2009

Electrical Procurements

Embed Size (px)

DESCRIPTION

Electrical Procurements. Thomas C. Nehring, PE Lead Electrical Engineer Conventional Facilities Advisory Committee - Review March 10-11, 2009. Outline. Substation Expansion 69 kV to 13.8 kV Substations Expansion Pre-Purchased Equipment Estimated Costs Construction/Procurement Schedule - PowerPoint PPT Presentation

Citation preview

Page 1: Electrical Procurements

1 BROOKHAVEN SCIENCE ASSOCIATES

Electrical Procurements

Thomas C. Nehring, PELead Electrical Engineer

Conventional Facilities Advisory Committee - Review March 10-11, 2009

Page 2: Electrical Procurements

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline

• Substation Expansion• 69 kV to 13.8 kV Substations Expansion• Pre-Purchased Equipment• Estimated Costs• Construction/Procurement Schedule• Construction Package Management/Oversight

• Secondary Unit Substations – for Ring Building Contract• Pre-Purchased Equipment• Estimated Cost• Procurement Schedule

• Concerns

Page 3: Electrical Procurements

3 BROOKHAVEN SCIENCE ASSOCIATES

69 -13.8 kV Substation Expansion

• Scope• Modify 69 kV Yard and Tower @ B 603• Add 69 kV Breaker• Install 20 MVA Transformer and oil retention pit• Install 15 kV Switchgear and bus duct• Install new ductbank to vicinity of NSLS-2 Site

Page 4: Electrical Procurements

4 BROOKHAVEN SCIENCE ASSOCIATES

Overall Electrical Utility Plan

Substation expansion and new ductbank

Page 5: Electrical Procurements

5 BROOKHAVEN SCIENCE ASSOCIATES

Pre-Purchased Equipment

• Pre-Purchased Equipment• 69 kV Breaker• 20 MVA Transformer• 15 kV Switchgear

Page 6: Electrical Procurements

6 BROOKHAVEN SCIENCE ASSOCIATES

Estimated Costs

• Estimated Costs• $1,975K Construction Contract• $80K 69 kV Breaker• $1,200K 20 MVA Transformer• $445K 15 kV Switchgear

Page 7: Electrical Procurements

7 BROOKHAVEN SCIENCE ASSOCIATES

Construction/Procurement Schedule

• Construction Package Schedule Baseline CWE• Bid Package available 3/20/09 3/23/09

• Bid Solicitation 4/14/09 4/13/09

• Bids Returned 5/6/09 4/28/09

• Contract Award 6/17/09 5/29/09

• Notice to Proceed (Construction Start) 6/24/09 6/17/09

• Construction Complete 4/14/11 4/14/11

Page 8: Electrical Procurements

8 BROOKHAVEN SCIENCE ASSOCIATES

Construction/Procurement Schedule

Page 9: Electrical Procurements

9 BROOKHAVEN SCIENCE ASSOCIATES

Construction Package Management/Oversight

• Design• Design by HDR• Design review by NSLS-II

• Procurement• Bid solicitation by NSLS-II Procurement & Property Management

Group (PPM)• Review by NSLS-II Conventional Facilities (CF)

• Construction• Construction management/oversight by NSLS-II CF

Page 10: Electrical Procurements

10 BROOKHAVEN SCIENCE ASSOCIATES

Pre-Purchased Equipment for Ring Bldg

• Secondary Unit Substations (SUS) • 8 SUS’s that include:

• 15 kV Switching• 15 kV Circuit Breaker• 2.5 MVA Transformer• 480 Outdoor Switchgear• 480 Indoor Switchgear

Page 11: Electrical Procurements

11 BROOKHAVEN SCIENCE ASSOCIATES

Site Plan

Substations

Page 12: Electrical Procurements

12 BROOKHAVEN SCIENCE ASSOCIATES

Construction/Procurement Schedule

Page 13: Electrical Procurements

13 BROOKHAVEN SCIENCE ASSOCIATES

Concerns

• Storage of indoor pre-purchased equipment• To be received around the time it can be installed• Indoor Storage Space is available in C-AD complex if needed

• Work in 69 kV yard• Needs to be coordinated around the Lab’s operating schedule• Needs to be coordinated around LIPA’s summer demands• Need to be able to de-energize a portion of the 69 kV bus• Construction scheduled extended to incorporate two summer/fall

periods to allow ample time for shutdowns and coordination with site operating schedules

Page 14: Electrical Procurements

14 BROOKHAVEN SCIENCE ASSOCIATES

69 kV Gas Insulated Circuit Breaker

Page 15: Electrical Procurements

15 BROOKHAVEN SCIENCE ASSOCIATES

20 MVA Main Transformer

Page 16: Electrical Procurements

16 BROOKHAVEN SCIENCE ASSOCIATES

15 kV Switchgear

Page 17: Electrical Procurements

17 BROOKHAVEN SCIENCE ASSOCIATES

Main Substation Installation

Page 18: Electrical Procurements

18 BROOKHAVEN SCIENCE ASSOCIATES

Secondary Unit Substation