Page 1: K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009

K. Long, 18 April 2023

Target

K. Long, Friday, 24th April 2009

Page 2: K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009

Critical path:

• No particular issues, but:– Vacuum tubes ready to be sent to Sheffield– Stator assembly ready for vacuum tubes at Sheffield– Weld trials successful– Parts in manufacture

Page 3: K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009

Manufacturing: highlights:

Page 4: K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009

Installation and commissioning schedule:• Presented / discussed at Target w/s last Friday• Revised version to be presented / discussed at

CM24• Need to have Target w/s with ISIS in June:

– Make sure manufacturing remains on track;– Discuss installation and commissioning plans;– Ensure manpower assumptions for shutdown are valid