13
6/19/2012 1 Standpipe Systems Continuation of Series for Technical Tuesdays NFPA 25 and Standpipe Systems Inspection, Testing, and Maintenance For Standpipe Systems Tech Tuesday Presentation For June 19, 2012 AIA Certification AIA CES Program #: NFSATV0112 Provider #: G131 1.5 LU/HSW National Fire Sprinkler Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and nonAIA members are available upon request. This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation 1 Copyright Materials Program Objectives This program will cover the basic requirements for the inspection, testing, and maintenance of standpipe systems. It will review the procedures found in the NFSA inspection form used to perform the inspection, testing, and maintenance as prescribed in NFPA 25. References NFPA 25, Standard for the Inspection, Testing, and Maintenance of WaterBased Fire Protection Systems, 2011 edition WaterBased Fire Protection Systems Handbook, 2011 edition

ITM for Standpipe Handout

Embed Size (px)

Citation preview

Page 1: ITM for Standpipe Handout

6/19/2012

1

Standpipe Systems

Continuation of Series

for

Technical Tuesdays 

NFPA 25 and Standpipe Systems

Inspection, Testing, and Maintenance

For Standpipe Systems

Tech Tuesday Presentation

For June 19, 2012 

AIA Certification

AIA CES Program #: NFSATV0112Provider #: G1311.5 LU/HSW

National Fire Sprinkler Association is a Registered Provider with The American p gInstitute of Architects Continuing Education Systems (AIA/CES).  Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members.  Certificates of Completion for both AIA members and non‐AIA members are available upon request.

This program is registered with AIA/CES for continuing professional education.  As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.  

Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation

1

Copyright Materials

Program Objectives

• This program will cover the basic requirements for the inspection, testing, and maintenance of standpipe systems. 

• It will review the procedures found in the NFSA inspection form used to perform the inspection, testing, and maintenance as prescribed in NFPA 25.

References

• NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water‐Based Fire Protection Systems, 2011 edition 

• Water‐Based Fire Protection Systems Handbook, 2011 edition

Page 2: ITM for Standpipe Handout

6/19/2012

2

Referenced Standards What are Standpipe Systems?

Standpipe systems are an extension of hydrant systems into a building so that firefighters (or other people) do not need to stretch hoseother people) do not need to stretch hose deep into big buildings

Firefighting Operations from the Protected Stairwell

Standpipe Systems

• Protection with hose streams used by:

1. Fire Service

2. Building Occupants

3. Fire Brigades

Design and Installation Standard – NFPA 14

Maintenance Standard – NFPA 25

NFPA 25

• Not a design standard

• Does not require upgrades to current edition of NFPA 14 

• Only intends to inspect and test to standard in y pplace at the time of system approval

• Emphasize the importance of maintaining the standpipe system to the property owner or facility manager

Classification of Standpipes

• Class I

‐ Fire Department use

‐ 2 ½ inch connection

• Class II

B ildi O t‐ Building Occupants

‐ 1 ½ inch Connection (Exception: a minimum 1   

inch hose is permitted in light hazard  

occupancies where approved by the AHJ)

• Class III

‐ All the rules of Class I and Class II 

Page 3: ITM for Standpipe Handout

6/19/2012

3

Standpipe Systems Standpipe Systems

Typical Installation Inspections May Include the AHJ Fire Inspector, Insurance Rep, Others

NFPA 25

• Identifies the standard inspections and maintenance procedures for standpipes in  Chapter 6

• NFSA provides forms for the Monthly, Quarterly,  Annual, Third Year and Fifth Year

minimum requirements for standpipes and hose systems

NFPA 25

• Inspection, Testing and Maintenance are to be performed with water supplies (including fire pumps) in service, unless the impairment procedures of Chapter 14 of NFPA 25 are f ll dfollowed

Page 4: ITM for Standpipe Handout

6/19/2012

4

Part I ‐ Owner’s Section

• Is the building occupied?

• Has the occupancy classification and hazard of contents remained the same since the last inspection?

• Are all fire protection systems in service?

• Has the system remained in service without modification since the last inspection?

• Was the system free of actuation devices or alarms since the last inspection?

Typical Locations for Standpipes

Part II ‐ Inspector’s Section

A. Inspections

1. Daily and Weekly Items

a.  Dry‐pipe valve enclosures (without low    

temperature alarm):

1. Enclosure maintaining at least 40⁰?

2. Gages in good condition and showing g g g

normal air and water pressure?

b. Relief port on RPZ backflow devices not 

continuously discharging?

c. Sealed control valves and valves on backflow devices

in normal (open or closed) position, accessible, with

seals in place, free from external leaks, and provided with

appropriate identification?      

Inspector’s Section

2. Monthly Inspection Items  (in addition to above items)

a. Control valves with locks or electrical supervision in correct

(open or closed) position, with locks or supervision in 

place, accessible, free from external leaks, provided with

appropriate wrenches, and provided with identification?

b. Alarm valves free from physical damage, trim in correct

(open or closed) position and no leakage from retard 

chamber or drains, and gages indicating normal water 

pressure? 

Control valve Inspector’s Section

2. Monthly Inspection Items (continued)

c. Dry pipe valve enclosures (with low temp.

alarm):

1. Enclosure maintaining at least 40⁰?

2 F f h i l d ?2. Free from physical damage?

3. Trim in correct position (open or closed)

4. No leakage from intermediate chamber?

d. Gages (on dry system with low pressure 

alarm or on wet system) in good condition

and showing normal air and water pressure?    

Page 5: ITM for Standpipe Handout

6/19/2012

5

Inspector’s Section

3. Quarterly Inspection Items (in addition to 

above items)

a. Alarm devices free from physical damage?

b. Pressure reducing valves and hose valve 

tl toutlets:

1. Hand wheels there and in good 

condition?

2. Hose threads in good condition?

3. Valves not leaking? 

Inspector’s Section

3. Quarterly Inspection Items (continued)4. Reducers in place and good condition?5. No visible obstructions to outlet?6. Valve handle, cap, gasket and restricting

devices in place and in good condition?Fi d t t ti i iblc. Fire department connections visible,  accessible, couplings and swivels not damaged, gaskets in place and in good condition, identification sign(s) in place, check valve is not leaking, clapper in place and operating properly and automatic drain valve in place and operating properly? 

Fire Department Connection

• (if plugs or caps are not in place, inspect interior for obstructions)

Inspector’s Section

4. Annual Inspection Items (in addition to above items)

a. Hose free from mildew, cuts and 

deterioration, couplings of compatible 

threads and undamaged gaskets in place andthreads and undamaged, gaskets in place and 

in good condition, and hose connected?

b. Hose Nozzles:

1. Nozzles and gaskets in place and in good 

condition with no visible obstructions?

2. Nozzles operate smoothly? 

Inspector’s Section

c. Hose Storage Devices:

1. Hose properly racked or rolled?

2. Nozzle clips in place & nozzle contained?

3. Undamaged, unobstructed and operable?3. Undamaged, unobstructed and operable?

4. Racks swing out of cabinet at least 90⁰?

Inspector’s Section

d. Storage cabinets:

1. Cabinets have no corroded or damaged 

parts, are easy to fully open, are  

accessible and identified?accessible and identified?

2. Door glazings in good condition?

3. Break‐glass type cabinet lock functions?

4. All parts, valves, hoses and fire 

extinguishers accessible? 

Page 6: ITM for Standpipe Handout

6/19/2012

6

Inspector’s Section

e. Adequate heat available in areas where 

water filled pipe is located? (done prior to 

cold weather)

f. Interior of dry‐pipe valves (which must bef. Interior of dry pipe valves (which must be 

open to be reset) passed internal 

inspections?

g. Visible pipe and supports in good condition?

h. Hydraulic nameplate attached and legible?

Examples of Hydraulic Nameplates

Inspector’s Section

5. Fifth Year Inspection Items (in addition to above items)

a. Check valves internally inspected, all parts 

operate properly and are in good condition?

b f l d f db. Strainers, filters, restricted orifices and 

diaphragm chambers on dry‐pipe and alarm 

valves and trim passed internal inspection?

c. Dry‐pipe valves that can be externally reset 

passed internal inspection? 

Inspector’s Section

B. Testing – Report any failures1. Quarterly Tests

a. Mechanical waterflow alarm devices passed tests by opening the test or bypass connection with alarms actuating and flow observed?g

b. Post indicating valves opened until spring or torsion felt in the rod then closed back ¼ turn?

Mechanical Waterflow Alarm Device Examples

Example of Post Indicating Valve

Page 7: ITM for Standpipe Handout

6/19/2012

7

Inspector’s Section

1. Quarterly Tests (continued)

c. Priming level correct?

d. Low air pressure signal passed?

e. Quick opening device passed?

f. Main drain test for system downstream of 

backflow device or pressure reducing valve:

1. Record static ___ psi & residual  pressure       

___ psi

2. Flow observed and results comparable?

Inspector’s Section

2. Semiannual Tests (in addition to previous items)

a. Valve supervisory switches indicate 

movement?

b. Electrical waterflow alarm device passed 

tests by opening test or bypass connection   

with alarms actuating and flow observed?

Inspector’s Section

3. Annual Tests (in addition to previous items)

a. Main drain test for systems not tested quarterly:

1. Record static ___psi and residual pressure ___psi

2. Was flow observed?

3. Are results comparable to previous tests?p p

b. All control valves operated through full range and   

returned to normal position?

c. Low temperature alarms passed test?

Main Drain Test

Inspector’s Section

3. Annual tests (continued)

d. Dry‐pipe valve partial flow trip test:

1. Record initial air pressure ___psi and 

water pressure psiwater pressure ___psi

2. Record tripping pressure ___psi and time 

___seconds

3. Results comparable to previous tests?

Inspector’s Section

3. Annual Tests (continued)

e. Automatic air maintenance devices passed?

f. Backflow devices passed backflow test?

g. Backflow devices passed forward flow test?

h. Hose valves for Class I and Class III systems 

passed opening and closing test?

i. Pressure reducing valves on hose  

connections and hose rack assemblies  

passed partial flow test?

Page 8: ITM for Standpipe Handout

6/19/2012

8

Example of Air Maintenance Device Inspector’s Section

4. Third Year Tests (in addition to above items)a. Dry‐pipe valve full flow trip test:1. Record initial air pressure ___psi and water pressure ___psi

2. Record tripping pressure ___psi and time        seconds___seconds

3. Water delivered to inspector’s test?4. Results comparable to previous tests?

b. Hose more than 5 years old passed test?c. Hose valve for Class II systems passed opening and closing test?   

Inspector’s Section

5. Tests for every fifth year (in addition to appropriate items)

a. Gages checked by calibrated gage or      

replaced?p

b. Pressure reducing valves passed full flow  

test?

Example of Pressure Reducing valve

Inspector’s Section

5. Tests for every fifth year (continued)

c. Automatic systems tested at required flows:

1. Record static pressure ___psi and 

residual pressure ___psi

2 R d t t l fl2. Record total flow ___gpm

3. Above flows and pressures acceptable?

d. Manual systems not a part of a sprinkler or    

standpipe system and semi‐automatic dry 

standpipe systems passed hydrostatic test?

5 Year Flow Test

• The test only needs to be run at 500 gpm, even if the standpipe demand is 1000 gpm or 1250 gpm

Page 9: ITM for Standpipe Handout

6/19/2012

9

Inspector’s Section

C. Maintenance

1. Regular Maintenance Items

a. Dry systems kept in dry condition?

b. Items missing or in disrepair have been 

repaired or replaced?

c. Air leaks in dry‐pipe systems causing 

more than 10 psi loss per week repaired?

d. If any of the following were discovered, 

was an obstruction investigation conducted?  

Inspector’s Section

Explain reason(s) and obstruction investigation findings in Part III of NFSA form

1. Defective intake screen on pump supplied 

from open sources

2 Obstructive material discharged during flow2. Obstructive material discharged during flow 

tests

3. Foreign material in dry‐pipe valves, check 

valves or pumps

4. Foreign material in water during drain test or

plugging of inspector’s test connection

Example of Pump Intake Screen Inspector’s Section

5. Plugging of pipe or sprinklers found during 

activation or work

6. Failure to flush yard piping or surrounding 

mains following new installation or repairsmains following new installation or repairs

7. Record of broken mains in the vicinity

8. Abnormally frequent false‐tripping of dry‐

pipe valves 

Example of Plugged Piping Inspector’s Section

e. If conditions were found that required 

flushing, was flushing of system 

conducted?

f. Adjusted, repaired, reconditioned orf.  Adjusted, repaired, reconditioned or 

replaced components that had  the 

associated tests and/or inspections 

required by Table 6.1.2 of NFPA 25 

performed?

Page 10: ITM for Standpipe Handout

6/19/2012

10

Inspector’s Section

9. System is returned to service after an 

extended period of time out of service 

(more than one year)

10. There is reason to believe the system 

contains sodium silicate or its derivatives or

highly corrosive fluxes in copper pipe

11. A system supplied with raw water via the 

fire department connection

12. Pinhole leaks 

Inspector’s Section

2. Annual Maintenance Items (in addition to

previous items)

a. Operating stem of all OS&Y valves 

lubricated, completely closed, & reopened?

b. Low points drained before freezing 

weather?

c. Hose re‐racked or re‐rolled so folds do not 

occur in the same position?

d. Interior of dry‐pipe valves cleaned?  

Example of Low Point Drain Testing for Standpipe & Hose Systems

• EVERY FIVE YEARS 

Hydrostatic test every five years for manual and automatic dry systems only ( and dry portions of wet systems)

200 psi for 2 hrs or 50 psi over working pressure if greater than 150 psi measured at the low point of each zone

No inside pipe leakage allowed 

Testing

• Where water damage is a possibility, an air test shall be conducted on the system at 25 psi prior to introducing water to the system.

Testing for Standpipe & Hose Systems

Since 1992, NFPA 25 has required pressure testing of manual–dry standpipe systems every five years

Versus

Manual wet standpipe systems – water in the pipe goes a long way to establishing that the pipe and fittings are secure

Page 11: ITM for Standpipe Handout

6/19/2012

11

Testing for Standpipe & Hose Systems 

• Manual wet part of combined sprinkler and standpipe systems shall not be required to be hydrostatically tested

• After any repairs/modifications or indication of system failure

HYDROSTATIC TEST

Example of Standpipe Roof Connection

Testing for Standpipe & Hose Systems

What you and your customers need to know!

Because of the increased exposure compared to a new installation, the language, scope, and terms of your NFPA 25 inspection agreement or contract are very important. It is very important for you to know the Standard better than anyone. If you have questions, get help; if you need to, get an interpretation.

Automatic Wet Standpipe, circa 1909

Automatic Wet Class I Standpipe, missing handwheel and cap 

Class II Hose Station, Damaged hanger

Page 12: ITM for Standpipe Handout

6/19/2012

12

Class I Dry Standpipe Missing Valve Operating (Direction) Instructions (Open w/Arrow) is on inside of handwheel,  handwheel reversed

Riser Piping Should be corrosion resistant; protective bollards?

Visual Inspection 

Obstruction Investigation needed? Dry Standpipe, Parking Garage

Page 13: ITM for Standpipe Handout

6/19/2012

13

Deficiency or Impairment? Summary

• Standpipe systems are mostly for fire department use

• Outlets for Class I standpipes will be located in stairwells or other protected spaces

• Inspections need to be performed to prove that the water supply will be available and that the pipe maintains its integrity