Upload
others
View
13
Download
0
Embed Size (px)
Citation preview
1
INDONESIA’S ELECTRICITY SECTOR PROGRAM- CURRENT AND PLANNING -
2 Juli 2020
2
OUTLINE
OUTLOOK OF ELECTRICITY SECTOR DEVELOPMENT 73
5ELECTRICITY IN INDONESIA – CURRENT STATUS2
ELECTRICITY CONDITION DURING PANDEMIC 104
POLICY IN INDONESIA’S ELECTRICITY SECTOR 31
NUCLEAR POWER PLANT 115
CLOSING 136
3
INDONESIA’S ENERGY TRILEMMA
Increase accessibility/
Electrification ratio.
Additional Capacity.
Increase
acceptability (reliability, quality
and eco-friendly).
National
Electricity
Sustainability.
Affordable of
electricity price.
Source: World Energy Council
“ The basic philosophy of developing the electricity sector in Indonesia must be carried out in a balanced manner between Energy Security, Energy Equity, and Environmental Sustainability ”
4
POLICY DIRECTION FOR ELECTRICITY SUPPLY DEVELOPMENT
Source: National Electricity Master Plan
2019 - 2038
• Minimum share of RE 23% by 2025.
• Diesel generation is only for emergency and temporary power supplies such as crisis areas.
• GTPP/CC/GE/CCGE platform.• CFPP uses Clean Coal
Technology (CCT).• Utilization of local primary
energy sources.• The use of nuclear energy is
in line with National Energy Policy (KEN).
• Dispatching electricity to business and industrial centers (Special Economic Zones, Tourism and Industrial Zones).
• HVDC transmission for long distance power evacuation (point to point / inter-island).
• Expansion of access to electricity in remote and scattered areas.
• In 2020 smart grids is began to be implemented in Java-Bali.
GENERATION TRANSMISSION
• At least 1 substation for each district/city.
• The addition transformer of the substation if the load capacity of transformer has reached about 70%.
• Development of Gas Insulated Switchgear (GIS) for limited land.
• Reducing losses and rehabilitation of old network.
SUBSTATION RURAL ELECTRICITY AND SMART GRID
AFFORDABLE PRICEGOOD QUALITYSUFFICIENT Rp
GUARANTEE
THE AVAILABILITY
OF ELECTRICITY
5
INSTALLED CAPACITY OF NATIONAL POWER GEN.
69,6GW
PLTG/GU/MG
19.860
PLTU
34.737
PLTD
4.674
PLTA/M/MH
5.975
PLTP
2.131
PLT EBT
Lainnya2.194
1,4GW
14,3GW
PLTG/GU/MG
4.166
PLTU
4.584
PLTD
1.230
PLTA/M/MH
1.950
PLTP
744
PLT EBT
Lainnya1.629
PLTG/GU/MG
476
PLTU
243
PLTD
637
PLTA/M/MH
33
PLT EBT
Lainnya20
INDONESIA
MALUKU PAPUA
JAWA-BALI-NUSRA
SUMATERA KALIMANTAN
SULAWESI
Geothermal. PP
Other NRE PP
Hydro/Micro PP
Diesel PP
Gas PP/CC/Gas Engine
CFPP
5,6GW
4,0GW
44,3GW
PLTG/GU/MG
828
PLTU
2.571
PLTD
911
PLTA/M/MH
919
PLTP
120
PLT
EBT Lainnya
212
PLTG/GU/MG
833
PLTU
1.651
PLTD
1.183
PLTA/M/MH
265
PLT EBT
Lainnya81
PLTG/GU/MG
13.558
PLTU
25.689
PLTD
713
PLTA/M/MH
2.808PLTP
1.266
PLT
EBT Lainnya
251
The total capacity of NRE power generation reaches 10,301 MW or 14.81% of the total installed capacity of national power gen.
48.353 50.41854.658
58.38662.203 64.925
2013 2014 2015 2016 2017 2018
PLN Non PLN
INSTALLED CAP. OF NRE POWER GEN.
JENIS PEMBANGKIT ONGRID OFFGRIDPLTP 2.131 -PLTA 4.621 938 PLTB 154 0,5 PLTBg 42 68
PLTBm 142 1.617 PLTBn 5 PLTM 311 -PLTMH 99 7 PLTS 77 49 PLTS Atap 5 15 PLTS Hybrid - 4 PLTSa 16 -
TOTAL 7.603 2.698
ACHIEVEMENT
PLN42,35
60,9%
IPP18,12
26,0%
PPU3,58 5,1%
Pemerintah0,05
0,1%
IO5,46 7,8%
IPP : Independent Power ProducerPPU : Private Power UtilityIO : Izin Operasi
BASED ON OWNERSHIP
69,6GW
*) Berdasarkan Data Hasil Verifikasi koordinasi dengan Ditjen EBTKE, PUDATIN KESDM dan PT PLN (Persero) tanggal 20 Januari 2020.
Sumber: Ditjen Ketenagalistrikan 2020
2019
6
TREND OF NATIONAL POWER GENERATION CAPACITY (MW)
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
PLT EBT Lainnya 29 29 46 69 768 1.385 1.427 1.780 1.831 1.913 2.090 2.194
PLTP 1.069 1.206 1.206 1.226 1.336 1.398 1.403 1.438 1.533 1.808 1.948 2.131
PLTA/M/MH 4.785 4.802 4.822 4.925 5.128 5.181 5.207 5.277 5.621 5.658 5.742 5.976
PLTD 2.509 2.597 3.074 3.250 3.362 3.562 3.637 3.824 3.979 4.396 4.631 4.674
PLTG/GU/MG 10.137 10.747 11.019 12.459 14.117 14.552 14.885 15.890 17.070 17.660 18.926 19.860
PLTU 12.634 13.071 13.371 16.751 20.741 22.275 23.858 26.448 28.352 30.768 31.587 34.737
Total 31.162 32.451 33.537 38.680 45.452 48.353 50.418 54.658 58.386 62.203 64.925 69.572
31.162 32.451 33.537 38.680
45.452 48.353 50.418
54.658 58.386
62.203 64.925
69.572
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
80.000
KA
PA
SIT
AS
PE
MB
AG
KIT
(M
W)
• Conventional of CFPP• Type of NRE power plant (Hydro, Geothermal, & Biomass)
• Utilization of CCT (SC & USC) in Java Bali system (June & Oct 2012: CFPP Paiton III (815 MW) & CFPP Cirebon (660 MW); Year 2019 (CFPP Jawa 7 (1000 MW) & CFPP Jawa 8 (1000 MW)
• Conventioanl of CFPP in outside Java Bali system
• VRE development (Wind & Solar PP) (Wind PP Sidrap (75 MW) , Wind PP Tolo (7,2 MW) & Rooftop Solar PV (20 MW)
6
Source : Ditjen Ketenagalistrikan 2020
7
POWER GENERATION DEVELOPMENT PLAN • The total additional capacity of power generation to be built up to 2028 is about of 56.39 GW.
• Coal fired power generation will be still developed in the next 5 years from 2019 and then it will be
gradually reduced.
• Gas fired power generation will be developed relatively constant after 2019.
• Renewable Energy (RE) power generation will be developed relatively constant up to 2024 and then it will
be increased significantly by 2025.
Source: PLN’s RUPTL 2019-2028
8
NRE POWER GENERATION DEVELOPMENT PLAN
Source: PLN’s RUPTL 2019-2028
56,39GW
56,39GW
56,39
GW
16,72GW
9
ENERGY MIX OF PLN’s POWER GENERATION
Source: Ditjen Ketenagalistrikan dan PLN’s RUPTL 2019-2028
Oil (include Biofuel)4,18%
Gas21,40%
Coal62,98%
Others NRE
11,44%
Realization Target 2025
(RUPTL PT PLN (Persero) 2019-2028)
In the future, coal and oil share in energy mix of power generation will decrease, while gas and NRE will increase.
Oil (include Biofuel)0,40%
Gas22,00%
Coal54,60%
Others NRE23,00%
Energy Mix (%) 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Oil 4,0 2,9 1,5 0,5 0,5 0,4 0,4 0,4 0,4 0,4
Gas 21,2 19,3 18,0 18,4 19,6 19,8 22,0 22,0 22,0 22,0
Coal 62,7 65,5 68,2 67,8 66,6 63,7 54,6 54,4 54,4 54,4
New and Renewable Energy 11,4 11,7 12,2 13,1 13,2 16,0 23,0 23,2 23,2 23,2
IMPORT 0,6 0,6 0,1 0,1 0,1 - - - - -
Oil (include Biofuel)6,04%
Gas21,70%
Coal60,28%
Others NRE
11,98%
Year 2019Year 2018
10
ELECTRICITY CONDITION DURING PANDEMIC
IMPACT:
• Peak Load System declines between 10-15% due to consumers cut their business activities
• Electricity supply is overload, more than 3.000 MW power plant cannot operate.
• Some projects are having difficulties in material supply distribution and labour dispatched (expert).
• Financial difficulties in PLN’s cash flow.
THE GOVERNMENT ACTION:
• For Costumer: Provide tariff discount for households, business, and industry costumer (over THREE
MONTHS, that are in April, May, and June 2020 for electricity consumer 450 VA (households, business,
and industry) shall be free of charge, and for households consumer 900 VA subsidized shall receive a
discount at 50%).
• For Developer: Allowing the overseas labor (expert) to enter Indonesia by following the health protocols
of Covid-19 to complete the project work; Issuing the government letter of statement of Health
Emergency Response due to Covid-19 including Force Majeure; and Renegotiate IPP/EPC Contractor
contract for extension of COD.
• For PLN: Increasing the State’s Capital Participation (PMN) for PLN; and Accelerating the compensation
payment to PLN (in year 2018 is about Rp. 23.17 T).
11
NUCLEAR POWER PLANT – IN ELECTRICITY SECTOR
National Energy Policy (NEP)Nuclear energy is utilized by considering the security of national energy supply on a large scale, reducing carbon
emissions and still prioritizing the potential of new and renewable energy according to its economic value, and
considering it as a last option by paying attention to high safety factors.
National Electricity Master Plan 2019 – 2038
• In line with NEP, the utilization of nuclear energy is carried out by considering the security of national
energy supply on a large scale, reducing carbon emissions and still prioritizing the potential of new and
renewable energy according to its economic value, and considering it as a last option by paying attention to
high safety factors.
• Every nuclear enterprise must pay attention to the safety and risk of accidents and bear all compensation to
third parties who have suffered losses due to nuclear accidents. Another factor to consider is the
independence of supporting industries and national support services in the use of nuclear energy.
• In an effort to encourage greater use of new and renewable energy sources for electricity supply, research
and feasibility studies are one of the important factors that must be considered to be carried out so that
development can be carried out to the fullest. Thus, it is possible to study the use of nuclear energy in the
supply of electricity.
12
NUCLEAR POWER PLANT – INDICATION TARGET
Mid-term National Development Plan 2020 – 2024 (RPJMN)
Priority Program Indicator Indication of Target
2020 2021 2022 2023 2024
Construction of
commercial NPP
Commerci
al NPP to
be built
Researching
the
development
of NPP
technology
with
economic
and safety
aspects
Encouraging
the mastery
of NPP
technology in
line with the
latest
development
s in NPP
technology
advances in
the World
Building
international
cooperation
related to the
study of the
development
of NPP
Conducting multi-
criteria analysis of
the implementation
of NPP including
urgent interests,
large scale,
guarantee of supply,
balance of energy
supply, reduction of
carbon emissions,
safety factors and
economies of scale
by involving various
views from
stakeholders
Preparing a
roadmap for
the
implemen-
tation of
NPP as a last
option in the
priority of
national
energy
development
13
CLOSING
• Electricity sector development in Indonesia must be carried out in a balanced
manner between Energy Security, Energy Equity, and Environmental
Sustainability.
• Renewable energy will gradually to be boosted by considering the readiness
of electricity system, particularly intermittent power generation in order to
achieve 23% of share of renewable energy by 2025.
• As an effort to master energy technology, including nuclear energy, R&D
Agency of Ministry of EMR continues to encourage research activities in
collaboration with other parties and countries.
Jl. Ciledug Raya Kav. 109 Cipulir
Kebayoran Lama – Jakarta
Selatan 12230
Address
14
THANK
YOU