25
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd , 2009

IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Embed Size (px)

Citation preview

Page 1: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

IHEP 1.3 GHz Cryomodule and Cryogenics

IHEP Cryogenic group

2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2nd, 2009

Page 2: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Outline

• Cryogenic test scheme of 9cell cavity

• Design of vertical test cryostat

• Design of horizontal test cryostat

Page 3: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Block Diagram of Cavity Test Cryogenic system

Recovery and Purify system

Vacuum Pump Collection BoxHeater

2KValve Box4KValve Box

2000LDewar

Cold Box500W 4.5K

compressorHorizontal Cryostat

Ve

rtica

l C

ryo

sta

t

Page 4: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Three Methods of Obtaining 1.8K Superfluid Helium

• Direct pumping

• Pumping & Throttling

• Pumping & Throttling & Pre-cooling

Page 5: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Direct Pumping

• m (hL1一 hL2 )+(hG1—hG2)(mL1-mL2 )=r (mL1-mL2 )

• Liquefaction rate 59.8%

IHEP old vertical test system

position 1980mm

Effective height

2200mm 2500mm

Bottom of baffle

Heat load 9.14W 15.87W 19.35W

Pumping

1.8K16mbar

Vertical test Dewar

Page 6: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Pumping & Throttling

• h1=h2 =h2Gx+h2L(1-x)

• mh2+Q=mh4

• Liquefaction rate 60%

3

Pumping Storage Dewar

4.2K1.0bar

1.8K,16mbar

1

24

JT

Vertical test Dewar

Page 7: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Pumping & Throttling & Pre-cooling

3

Pumping Storage Dewar

4.2K, 1.0bar

1.8K,16mbar

1

5

4JT

6

T 5( K) 4.2 3 2.2

Liquefaction rate 61% 80% 87.7%

Vertical test Dewar

Heat exchanger

Page 8: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

• TESLA cavity: R/Q=1036Ω, L=1.038m

• Vertical test– 35MV/m, Q=8×109

– Ploss =160W

• Horizontal test– 31MV/m, Q=1×1010

– Ploss =100W

0

2

/ QQR

lEP accloss

Heat loads of the 9cell Cavity Test

Page 9: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Pump Selection• Assume the heat loads 100W.• Without considering the pressure drop between Dewar and

vacuum pump.• 300k, 16mbar, density of helium gas is 2.57×10-3 Kg/m3

Method1 Method2 Method3

Mass flow rate (g/s) 4.37 7.01 4.88

Pumping speed (L/s)

1700 2728 1899

KEK-STF

Cavity Loss is about 100W at the max. field in V.T.Compressor limit is 1200m3/h~333L/s

Need to be discussed

Page 10: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Comparison of Three Methods

• Direct pumping The structure is simple. Bigger test Dewar is needed for the storage

of much more LHe to keep the test time longer. Otherwise, the process need be stopped to refill LHe.

• Pumping & Throttling No heating exchanger and low efficiency.

• Pumping & Throttling & Pre-cooling Need more instrumentations and bigger investment. Test process is

stable. Sensible heat of 1.8K Helium gas can be used, leading to higher liquefaction rate.

Page 11: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Pre-design of 9cell Cavity Test Cryogenic System

Heat exchanger

Horizontal test cryostat

Vertical test cryostat

Page 12: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Vertical Test Cryostat

FNAL vertical test cryostat

Page 13: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

IHEP Vertical Test Cryostat

Page 14: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Vertical Test Cryostat Flow Chart

Page 15: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Progress of Vertical Test Cryostat

• Components’ 3D models have been finished and the assembling model need to be checked;

• Key materials have been counted;• Standard components’ selection and layouts are under d

oing and design ( throttling valves, safety valves, hose-burst valve, temperature sensors, pressure sensors, standard cryogenic connectors);

• Key part heat exchanger is under design and need further discussion with FERMILAB;

• The first version of drawings is planed to be finished at the end of this year;

Page 16: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Horizontal Test Cryostat• Single 9cell cavity horizontal test cryostat with length of 1800mm and diamet

er of 966mm;• Cross-section almost the same as EXFEL cryomodule;• A 300 mm He Gas-Return-Pipe (GRP) acting as support structure, together

with 2 adjustable posts on top of the vacuum vessel. One post is the fixed-point, the other post can slide in longitudinal direction;

• A 1.8 K forward line transferring single phase helium, a 1.8 K two phase line connected to the cavity helium vessels, a 4-8 K forward and return line, a 40/80 K forward and return line, and a warm-up/cool-down line with capillary to the bottom of cavity vessel;

• Aluminum thermal shields with stiff upper parts for 4/8K and 40/80 K are attached to the support structure, with 10 layers and 30 layers of super-insulation (MLI) for 4/8K and 40/80 K respectively;

• In the end of cryostat, there is a small helium vessel with a liquid level meter inside, which is connected with He GRP and 1.8K supplying line of 9cell cavity. The cavity can be kept in the 1.8K LHe by monitoring the liquid level meter.

Page 17: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Horizontal Test Cryostat

Page 18: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009
Page 19: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009
Page 20: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009
Page 21: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009
Page 22: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Horizontal Test Cryostat Flow Chart

Page 23: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Progress of Horizontal Test Cryostat

• Structure design has been finished;• Model design is nearly finished;• POST support is under design;• Parts of components’ structure need to be improved;

• The first version of drawings is planed to be finishe

d at the end of this year.

Page 24: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Next Years’ Plan

• Complete the thermal dynamic simulation analysis;

• Finish the drawings of vertical Test cryostat and horizontal Test Cryostat and put into machining;

• Complete the whole flow chart of the 9cell cavity test cryogenic system;

• ………….

Page 25: IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009

Thanks