6

Click here to load reader

[IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

  • Upload
    ratnesh

  • View
    232

  • Download
    8

Embed Size (px)

Citation preview

Page 1: [IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

1

Abstract—This paper investigates the effect of energy storage systems on the availability of microgrids with different architectures in the presence of renewable energy sources (RESs). When RESs are used for power generation within a microgrid, its availability may be reduced due to the intermittent nature of RESs. Thus, energy storage systems may be used as a solution to improve microgrids availability. Therefore, it is important to have a realistic evaluation of microgrids availability and to determine how added energy storage affects microgrids. Since energy storage system is not just a one-time-use reserve, charging and discharging processes in energy storage need to be considered when their availability is evaluated. Thus, a Markov chain model is used in this paper to properly represent the charging and discharging processes of energy storage systems, and minimal cut sets method is used in order to evaluate the availability of different microgrid architectures. Using the proposed method, availabilities of radial, ring, and ladder type microgrid architectures are evaluated in the presence of RESs and energy storage systems, and results are discussed.

Index Terms—Availability, distributed power generation,

energy storage, Markov processes, microgrids, solar power generation.

I. INTRODUCTION NE of the expected advantages of microgrids is having a higher availability compared to the current electrical grid

[1, 2]. Microgrids use controlled distributed energy resources to generate power which makes isolated operation possible [3, 4], thus improving the local availability of energy supply. On the other hand, availability becomes more of an issue when a greater capacity of renewable energy sources (RESs) is used to generate power within microgrids [5, 6]. This is mostly because of highly variable and intermittent nature of power generation by RESs. Hence, it is necessary to maintain the advantage of high availability that microgrids have even when a large amount of RESs' generation takes place within microgrids.

This work was supported by NEC Laboratories America, INC. (NEC

Labs). J. Song and A. Kwasinski are with the Department of Electrical and

Computer Engineering, The University of Texas at Austin, TX 78712, USA (e-mail: {tedsong, akwasins}@mail.utexas.edu).

M. C. Bozchalui and R. Sharma are with the Energy Management Department, NEC Laboratories America, Inc., Cupertino, CA 95014, USA (e-mail: {mohammad, ratnesh}@sv.nec-labs.com).

There are various strategies to improve the availability when RESs are included to generate power; one of the strategies is to add energy storage [7-9]. When added, an energy storage system can immediately improve microgrids availability; however, calculating the amount of improved availability is not simple and easy. This is mainly due to the charging and discharging processes that take place in energy storage system, which makes it difficult to predict how much power is available from energy storage system during microgrids' operation. Some works have been reported in the literature on the evaluation of microgrids availability and/or reliability indices—availability and reliability are not equal since availability here represents the probability of the load being fully powered at any given time, whereas reliability represents the probability of a component carrying out an expected function for a given period of time [1]. For instance, [10] and [11] analyzed the reliability of distributed generation without including energy storage system in the study. In [12], the presented work includes energy storage system within microgrids, however, charging and discharging processes are not taken into account for the storage model, which is not realistic since energy storage system is not a one-time-use energy reserve. In [13], the authors propose a combined distributed generations (DGs) and energy storage model to evaluates the reliability of microgrids which includes the states of DGs, energy storage, and energy stored in the storage device without considering the effect of system architectures on the availability or reliability of microgrids.

This paper proposes a method for microgrids availability evaluation using a Markov chain energy storage model and minimal cut sets (MCS). The proposed method uses a Markov chain model to properly model the charging and discharging processes in energy storage system, which makes possible to understand how RESs and energy storage function together to provide power to the load and affect microgrids availability. This model also enables calculating the effect of energy storage system connected to a microgrid with multiple energy sources and loads. Considering the effect of system architectures on the availability of microgrids—which is another important factor that affects microgrids availability—this paper uses MCS method [1]. Using this approach, it can be seen that how energy storage system takes its role within

Microgrids Availability Evaluation using a Markov Chain Energy Storage Model:

a Comparison Study in System Architectures Junseok Song, Student Member, IEEE, Mohammad Chehreghani Bozchalui, Member, IEEE,

Alexis Kwasinski, Member, IEEE, and Ratnesh Sharma, Member, IEEE

O

978-1-4673-1935-5/12/$31.00 ©2012 IEEE

Page 2: [IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

mien

stobyavsimSe

paevdepashanreppaenfulmothasto as en

S

whtheThde

when1) adj

caninslimde

whproa Mde

icrogrids withnergy storage syThe rest of theorage modelingy Section III anvailability evalumulations resuection V and V

IIMarkov chain

aper, which isvaluate the avaetails of the enaper, only basows the battery

nd discharging ppresents the e

articular, State nergy, and Statell energy levelodel has is theat is charged orage system inIf the total amX and L resp

nergy storage sy

[ , (S M M= − Δ −

here Δ is the ae maximum nuhus, the total cefined as

here T is the amnables C to be

represents thdjacent states.

Furthermore, tn be found usolation or winmiting probabiefinition

here π is thobabilities shoMarkov chain,

efined as

h different sysystem. e paper is orgag is presented nd Section IVuation method lts and the maI, respectively

. ENERGY STO

n based energy s the expandeailability in thnergy storage ic operation sy state diagramprocesses in enenergy level #1 represents

e #N representl. As shown, the ability to mo

or dischargedn reality.

mount of generapectively, the ystem can be e

1) ,..., 2 ,M − Δ − Δ

amount of enerumber of steps capacity of the

(mount of time defined in term

he total numbe

the transition psing the histo

nd speed data slity vector can

π =

he stationary ow the probabil, the loss of lo

∈ ,

stem architectu

anized as folloin Section II.

V which discusand the system

ain conclusions.

ORAGE MODELI

storage modeld version of

his paper. Sincmodel is out scheme is prem which represnergy storage sof energy sto the case whes the case whehe advantage t

odel different ad, which bette

ated power andstate space of

expanded as

, , , 2 ,..., (M−Δ Δ Δ

rgy that is excin the present

e energy storag

1) ∙ ∆ ∙

between state tms of energy. Per of state tra

probability marical data of

sets—and load n be found usi

πP

distribution. lities of being oad probability

ures that inclu

ows. First, ene This is follows the MCS-bam model. Finas are presented

ING l presented in t[14], is used

ce explaining of scope for t

esented. Figuresents the chargsystem. Each storage system. en storage has en storage is at that the presenamount of eneer models ene

d load are definf (X − L) for

1) , ]M M− Δ Δ

changed and Mted Markov chage system can

transitions, whParticularly, (Nansitions betw

atrix (P) of FigRESs—e.g. soprofile. Then, ing the follow

Since limitat certain statey (LOLP) can

ude

ergy wed ased ally, d in

this d to

the this e 1

ging tate

In no the

nted ergy ergy

ned the

(1)

M is ain.

n be

(2)

hich N − een

g. 1 olar the

wing

(3)

ting e in

n be

(4)

where probabillimitingwhich land enenumber regards

III. Availcalculatavailabicompona minimsuch thafailed cfailed stavailabisimple. are a lindividumicrograpproxim

where Mthe MCS

Figur19] micbreakersopen cirignored,componconsiderthat occCBs failfollowinMCS in

• Onl

represents Llities of disch

g probabilities ooad requires. ergy storage cof total states to the change o

MCS-BASED Alability of micted using MCSility by determnents that will mal cut set canat if all fail thecomponents is tate [1]. The Milities of diffeThis is an imp

large number ual componenrids unavailamated as [1]

MC, Kj, and P(S, and the MC

IVres 2 to 4 presecrogrid archites (CBs) are urcuit faults are, and short ci

nent failures [2red in the sim

cur when there l to open, are ng summarize

n this paper: ly short circuit

Fig. 1. Block diag

LOLP by summharging in anyof the states thFinally, the recapacity can band determini

of energy stora

AVAILABILITY

crogrids with dS method. Th

mining the combintroduce a syn be defined ae system fails b

repaired the MCS method ierent system aportant advanta

of componennts have a ability, UMG

≅ ((Kj) represent tS probability, r

V. SYSTEM Ment radial, ringectures, respecused to protece very rare in pircuit faults ar20], only sho

mulations. In ois a short circ

considered in e assumptions

failure modes

gram of an availab

ming up the pry amount and hat cannot matcelationship betwbe found by ing how LOLPage capacity.

EVALUATION Mdifferent confi

he MCS methobinations or se

ystem failure. Ias a group of but that if any system is no is selected to

architectures bage particularlynts in the sys

high availab, can be

( )the total numbrespectively.

MODEL g [15, 16], andctively. As shoct each compopower systemsre the dominanrt circuit failuother words, ocuit fault in thethis study. In athat are used

of CBs are con

ility calculation pr

2

roduct of the the sum of

ch the power tween LOLP varying the

P varies with

METHOD igurations is od evaluates ets of system In particular, components one of those longer in a evaluate the

because it is y when there stem. When bility, then

accurately

(5) ber of MCS,

d ladder [17-own, circuit onent. Since and usually nt source of ure mode is only failures e system, i.e. addition, the d determine

nsidered.

rocess

Page 3: [IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

3

• When a short circuit failure of a CB occurs, the other CBs connected to that fault will operate (or be opened).

• MCS in Tables I to III are determined for the cases when Load #1 is not powered.

• When any load fails to be powered, it is considered as a system failure (Tables VI and VII).

• Power output of PV sources and energy storage devices is variable. Whenever they cannot produce enough power for all loads it is then assumed that they are in the failed state.

Both passive event—i.e. a component failure that does not have an impact on the remaining healthy part of the system—and active event—i.e. a component failure that cause the

TABLE I MCS DESCRIPTION, PROBABILITY, AND QUANTITY FOR

THE RADIAL-TYPE SYSTEM ARCHITECTURE SHOWN IN FIG. 2

# Minimal cut sets (Load #1) Quantity and probability of occurrence

1 {L1}

2 {CB1}, {CB2}, {CB3}, {CB4}, {CB5}, {CB6}, {CB7}, {CB8} (8)( )

3 {U2S2E} 4 {U2S1E, E1}, {U2S1E, E2} (2)( )5 {U2S0E, E1, E2} 6 {U1S2E, S1}, {U1S2E, S2} (2)( )7 {U1S1E, S1, E1}, {U1S1E, S1, E2},

{U1S1E, S2, E1}, {U1S1E, S2, E2} (4)( ) 8 {U1S0E, S1, E1, E2},

{U1S0E, S2, E1, E2} (2)( )

TABLE II MCS DESCRIPTION, PROBABILITY, AND QUANTITY FOR

THE RING-TYPE SYSTEM ARCHITECTURE SHOWN IN FIG. 3

# Minimal cut sets (Load #1) Quantity and probability of occurrence

1 {L1}

2 {CB1}, {CB2}, {CB3}, {CB4}, {CB5}, {CB10} (6)( )

3 {U2S2E} 4 {U2S1E, E1}, {U2S1E, E2} (2)( )5 {U2S0E, E1, E2} 6 {U1S2E, S1}, {U1S2E, S2} (2)( )7 {U1S1E, S1, E1}, {U1S1E, S1, E2},

{U1S1E, S2, E1}, {U1S1E, S2, E2} (4)( ) 8 {U1S0E, S1, E1, E2},

{U1S0E, S2, E1, E2} (2)( )

TABLE III MCS DESCRIPTION, PROBABILITY, AND QUANTITY FOR

THE LADDER-TYPE SYSTEM ARCHITECTURE SHOWN IN FIG. 4

# Minimal cut sets (Load #1) Quantity and probability of occurrence

1 {L4} 2 {L2, L3} 3 {CB2}, {CB3} (2)( )4 {U2S2E} 5 {U2S1E, E1}, {U2S1E, E2} (2)( )6 {U2S0E, E1, E2} 7 {U1S2E, S1}, {U1S2E, S2} (2)( )8 {U1S1E, S1, E1}, {U1S1E, S1, E2},

{U1S1E, S2, E1}, {U1S1E, S2, E2} (4)( ) 9 {U1S0E, S1, E1, E2},

{U1S0E, S2, E1, E2} (2)( ) 10 {U1S0E1L, L1, L2}

11 {U1S0E1L, CB4, CB6}, {U1S0E1L, CB7, CB9}, {U1S0E1L, CB10, CB12}

(3)( )

Fig. 2. A radial-type system architecture

Fig. 3. A ring-type system architecture

Fig. 4. A ladder-type system architecture

Page 4: [IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

4

removal of other healthy components of the system—are considered in the calculation of reliability indices. In Fig. 2 to Fig. 4, Solar #1 & #2 represent the photovoltaic (PV) generation, and Storage #1 & #2 represent energy storage system. When demonstrating the simulations, both PV generations are assumed to have the same amount of generation capacity (1 MW), and both storages are assumed to have the same amount of capacity (1 MW) as well. Tables I to III present the MCS of the radial, ring, and ladder microgrid architectures, respectively. As mentioned earlier, MCS in each table are determined for Load #1 (Figs. 2 to 4). In other words, MCS are set for the case when the microgrid fails to supply Load #1. Then, the system availability can be evaluated after determining availabilities for every load in the system. This process is not a time consuming process since many MCS are redundant within the same architecture. As shown in Table I, there are 8 MCS for the radial-type system architecture which is shown in Fig. 1. MCS #1 represents the failure of a bus that connects all components in the shown radial-type system architecture. As it can be seen, the whole system fails when bus L1 fails. This means not a single generation nor storage device is able to be connected with any load due to the failure of bus L1. MCS #2 represents the failure of a single CB, which is the case a CB fails to open when there is a short circuit. Short circuit failure of a CB causes a voltage drop which introduces a system failure. Then, the other CBs connected to the fault may or may not be opened for the protection at that moment of failure. In either cases, i.e. other CBs operate to be opened or not, a short circuit failure of a CB in the radial-type architecture, then, is a single point of failure since no load is able to be powered with the presence of a short circuit failure. Therefore, the CB unavailability ( ) is multiplied by eight since MCS #2 considers the failures of all eight CBs in the system. MCS #3 represents the unavailability even when all components of the system are healthy and have no failure. In other words, MCS #3 does not describe the failure rates of component, however, describes the unavailability of power resources including energy storage system. For example, when there is no solar generation, or storage level is not enough to supply the load, the system is considered unavailable even there is no failure within the system. Hence, u2S2E of MCS #3 represents the unavailability when all components—two PV sources and two energy storage systems—are working in order but they cannot meet the power level required by load.

MCS #4 represents a case that one of the two energy storage systems is failed to operate as storage. In this case, the unavailability of power resources which includes two PV sources and one energy storage system is evaluated. This unavailability, u2S1E,—i.e. a case that one of two energy storage is failed to operate—will be greater than that of u2S2E because there is less amount of capacity to store the energy within the system. In addition, when any of two energy storages fail to operate, it is assumed that the CB connected to that storage opens to protect the system. In a same manner, the rest of unavailabilities can be found for other MCS shown in Table I and II. Particularly, Table III has different MCS from the previous ones. This is because ladder-type system architecture has a

different approach to connect power resources and loads. Unlike the other architectures, Load #1 can be disconnected from the rest of the system by CB2 and CB3, as shown in Fig. 4. This is represented as MCS #3. With this type of connection, the total number of CBs may be increased; however, this gives a lower possibility of a system failure to supply the load with regard to failures within microgrids. In addition, MCS #10 and #11 include unavailabilities with the information of how many loads are connected to that generation. This information is given only for the ladder-type architecture because when CBs that are connected to L1 and L2 fail to operate in a certain step, Load #1 is separated from the loads in other steps. For example, if CB #4 and #6 in Fig. 4 fail to operate, CB #1 and #3 will automatically be opened for the protection. Then, Solar #1 becomes the only power resource that powers Load #1 which is the only load that is connected to Solar #1. Since MCS are determined from the perspective of Load #1, the unavailability becomes u1S0E1L. As a result, u1S0E1L will be greater than u1S0E because u1S0E1L considers only a single load being powered instead of all four loads.

V. SIMULATION RESULTS Table IV shows the availability values that are used to conduct simulations. As mentioned, only short circuit failures were taken into account for CBs in the availability calculation. In addition, the availabilities of power generation with different amount of PV and energy storage are evaluated using two different energy storage system models: the Markov chain model and two-state—i.e. available or unavailable—energy storage model that is used in power system study traditionally. The Markov chain model, which was introduced in Section II,

TABLE IV AVAILABILITY VALUES OF COMPONENTS USED IN THE NUMERICAL

EXAMPLES

Item Availability ( ) Unavailability ( )Line [20] 0.99999714 Circuit Breaker [20] 0.99998858 Photovoltaic Moduleα [21] 0.99998965 Energy Storage (Battery) [22] 0.99996742 Power Generation (2S, 2E)β 0.99995859 Power Generation (2S, 2E)γ 0.99999102 Power Generation (2S, 1E)β 0.95661314 Power Generation (2S, 1E)γ 0.99999102 Power Generation (2S, 0E) 0.71430000 Power Generation (1S, 2E)β 0.97918508 Power Generation (1S, 2E)γ 0.99998437 Power Generation (1S, 1E)β 0.91262556 Power Generation (1S, 1E)γ 0.99998437 Power Generation (1S, 0E) 0.50250000 Power Generation (1S, 0E) - 1L 0.84270000

α Repair time was assumed to be 50 hours. β Acquired by the Markov chain model γ Acquired by the two-state model (0 or 1)

TABLE V SIMULATION INPUT INFORMATION

Item Capacity PV Generation Capacity (Ea.) 1000 kW (avg. generation = 317 kW) Energy Storage Capacity (Ea.) 1000 kWh Load (Ea.) 73 kW (avg.) / 153 kW (max.)

Page 5: [IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

modemoacsyregstois 1, assstoavsliM gesimdifanasscapin geloacosimassforva Mavrespredefaiwhres

odels charginefined by energodel does not count. Hence, stem is availagarded as a forage system isregarded empt

which introsumes that enorage is worvailabilities thaightly higher arkov chain enTable V intr

eneration and mulations. In fferent architec

nd storage and tsumed to be epacity of PV p

Milford, Utaeneration profilad data sets fr

ollected in the mulations. Eacsumed to reprer each load (1

alue was 153 kWTable VI andarkov chain m

vailable/unavailspectively. Avesented in the

etermined for eils to acquire phole system. Asults higher

Fig. 5. One

Fig. 6

g and dischagy levels. On ttake charging for two-state sable, i.e. wor

fully charged s not availablety. This strateg

oduce overestinergy storage rking in ordeat are found wthan that of

nergy storage mroduces the energy storageorder to inv

ctures, the totathe total amounequal. With anpanels [23], soah [24] is usle which is alrom [25], whi

State of Newch load, e.g. Loesent 100 hou00 housings) wW. This load pd VII show th

model and the twlable states) mvailability of ese tables. Weach system, itpower, it is conAs shown, the availabilities.

year PV generatio

. One year load (1

arging procesthe other hand,

and dischargistorage model,rking in orderstorage. Vice

e, i.e. fail to opgy results only imated availais fully charg

er. As shownith two-state spower genera

model. capacity value system that vestigate the al capacity of nt of load in aln assumption oolar insolation sed to generaso shown in Fch are residen

w Hampshire, oad #1, shownsings; hence, twas 73 kW, a

profile is also shhe simulation wo-state (charg

model for energeach load i

When the total t was assumed

nsidered as a lotwo-state enerHence, the

on profile in Milfor

00 housings) profi

ses using sta, two-state eneng processes i if energy storr, the storageversa, if ene

perate, the stortwo states, 0 a

abilities sinceged whenever n in Table storage model ation which u

ues of each are used for impact of uspower generatl architectures of having 1 Mdata set collec

ate one year Fig. 5. Moreovntial load prof

are used for n in Figs. 2 to 4the average va

and the maximhown in Fig. 6results using ged/discharged

gy storage systes evaluated aavailability w

d that if any looss of load for rgy storage mototal availabi

rd, Utah [24]

file [25]

ates ergy into rage e is ergy rage and it the IV, are

used

PV the

sing tion are

MW cted PV ver, files the

4 is alue

mum . the

d or em, and was oad the

odel ility

evaluateMarkovchargingavailabimicrogr Morebe seen availabicost sincarchitecdifferenhoweverthe totmodific

A neavailabiMCS. availabiusing twcharging

S

System Architec

Radial

Ring

Ladder

System Architec

Radial

Ring

Ladder

ed with the twov chain modelg and dischargilities when erids. eover, when dif

that the laddeility. But the lace it uses great

ctures. Notice nt unavailabilitr, since MCS

tal availabilityations.

ew method wility using the This approa

ility in more rwo-state energg and discharg

SYSTEM AVAILABI

cture Load

#1 #2 #3 #4 Total #1 #2 #3 #4 Total #1 #2 #3 #4 Total

SYSTEM AVAILA

cture Load

#1 #2 #3 #4 Total #1 #2 #3 #4 Total #1 #2 #3 #4 Total

o-state model il. This shows ging processesenergy storage

fferent architecer-type systemadder-type arcter number of

that the rety values are u

of system arcy can be ea

VI. CONCLUS

was proposed Markov chain

ach enables realistic way tgy storage moging processes

TABLE VI ILITY RESULTS (M

Availability ( )0.99986111 0.99986111 0.99986111 0.99986111 0.99944444 0.99988395 0.99988395 0.99988395 0.99988395 0.99953580 0.99992253 0.99992253 0.99992253 0.99992253 0.99969015

TABLE VIIABILITY RESULTS (

Availability ( )0.99989680 0.99989680 0.99989680 0.99989680 0.99958721 0.99991964 0.99991964 0.99991964 0.99991964 0.99967857 0.99996532 0.99996532 0.99996532 0.99996532 0.99986129

is higher than tthat not con

s may result ove system is

ctures are comm in Fig. 4 has

hitecture may CBs than the osults may chused for each chitectures do asily evaluate

IONS to evaluate

energy storagto evaluate

than the previodel which dointo account. B

MARKOV CHAIN M) Availabi(Number3.8573 3.8573 3.8573 3.8573 3.2553 3.9354 3.9354 3.9354 3.9354 3.3333 4.1109 4.1109 4.1109 4.1109 3.5089

(TWO-STATE MOD) Availabi

(Number3.9863 3.9863 3.9863 3.9863 3.3843 4.0950 4.0950 4.0950 4.0950 3.4929 4.4600 4.4600 4.4600 4.4600 3.8579

5

that with the nsidering the verestimated included in

mpared, it can s the highest have higher

other system hange when

component; not change,

ed by few

microgrids' e model and

microgrids ious method oes not take Based on the

ODEL)

ility r of Nines)

DEL)

ility r of Nines)

Page 6: [IEEE 2012 IEEE/PES Transmission and Distribution Conference and Exposition (T&D) - Orlando, FL, USA (2012.05.7-2012.05.10)] PES T&D 2012 - Microgrids availability evaluation using

6

proposed method, a comparison study in the system architectures—which include radial, ring, and ladder configuration—is conducted. The results are presented using actual solar PV generation and load profile data. Simulation results show that the proposed method provides more realistic estimation of the system availability compared to the two-state model which may give overestimated availability values. In addition, further research may include the methodology about how to evaluate availability when microgrids are connected to grid.

VII. REFERENCES [1] A. Kwasinski, "Quantitative Evaluation of DC Microgrids Availability:

Effects of System Architecture and Converter Topology Design Choices," IEEE Transactions on Power Electronics, vol. 26, pp. 835-851, 2011.

[2] B. Kroposki, T. Basso, and R. DeBlasio, "Microgrid standards and technologies," in Proc. IEEE PES General Meeting, 2008, pp. 1-4.

[3] R. H. Lasseter and P. Paigi, "Microgrid: a conceptual solution," in Proc. Power Electronics Specialists Conference (PESC), 2004, pp. 4285-4290.

[4] C. Marnay, "Microgrids and Heterogeneous Security, Quality, Reliability, and Availability," in Proc. Power Conversion Conference (PCC), 2007, pp. 629-634.

[5] L. Xuan and S. Bin, "Microgrids - an integration of renewable energy technologies," in Proc. China International Conference on Electricity Distribution (CICED), 2008, pp. 1-7.

[6] J. Song, R. Zhao, and A. Kwasinski, "Design considerations for energy storage power electronics interfaces for high penetration of renewable energy sources," in Proc. IEEE International Conference on Power Electronics and ECCE Asia (ICPE & ECCE), 2011, pp. 2160-2167.

[7] J. P. Barton and D. G. Infield, "Energy storage and its use with intermittent renewable energy," IEEE Transactions on Energy Conversion, vol. 19, pp. 441-448, 2004.

[8] M. R. Vallem, D. Jensen, and J. Mitra, "Reliability Evaluation and Need Based Storage Assessment for Surety Microgrids," in Proc. North American Power Symposium (NAPS), 2006, pp. 29-33.

[9] A. Joseph and M. Shahidehpour, "Battery storage systems in electric power systems," in Proc. IEEE Power Engineering Society General Meeting, 2006, pp. 8.

[10] Y. G. Hegazy, M. M. A. Salama, and A. Y. Chikhani, "Adequacy assessment of distributed generation systems using Monte Carlo Simulation," IEEE Transactions on Power Systems, vol. 18, pp. 48-52, 2003.

[11] P. M. Costa and M. A. Matos, "Reliability of distribution networks with microgrids," in Proc. IEEE Russia Power Tech, 2005, pp. 1-7.

[12] R. Yokoyama, T. Niimura, and N. Saito, "Modeling and evaluation of supply reliability of microgrids including PV and wind power," in Proc. IEEE PES General Meeting, 2008, pp. 1-5.

[13] H. Liang, J. Su, and S. Liu, "Reliability evaluation of distribution system containing microgrid," in Proc. China International Conference on Electricity Distribution (CICED), 2010, pp. 1-7.

[14] L. L. Bucciarelli Jr, "Estimating loss-of-power probabilities of stand-alone photovoltaic solar energy systems," Solar Energy, vol. 32, pp. 205-209, 1984.

[15] T. Weizhong and R. H. Lasseter, "An LVDC industrial power distribution system without central control unit," in Proc. IEEE Power Electronics Specialists Conference (PESC), 2000, pp. 979-984 vol.2.

[16] P. Karlsson and J. Svensson, "DC bus voltage control for a distributed power system," IEEE Transactions on Power Electronics, vol. 18, pp. 1405-1412, 2003.

[17] A. Kwasinski, "Advanced power electronics enabled distribution architectures: Design, operation, and control," in Proc. IEEE International Conference on Power Electronics and ECCE Asia (ICPE & ECCE), 2011, pp. 1484-1491.

[18] W. Allen and S. V. Natale, "Achieving ultra-high system availability in a battery-less -48VDC power plant," in Proc. International Telecommunications Energy Conference (INTELEC), 2002, pp. 287-294.

[19] W. Allen, D. W. Fletcher, and K. J. Fellhoelter, "Securing critical information and communication infrastructures through electric power grid independence," in Proc. International Telecommunications Energy Conference (INTELEC), 2003, pp. 170-177.

[20] R. Billington and R. N. Allan, Reliability evaluation of power systems, 2nd ed., Plenum press, New York, 1996.

[21] A. Maish, "Defining Requirements for Improved Photovoltaic System Reliability," 1998.

[22] P. S. Hale, Jr. and R. G. Arno, "Survey of reliability information on lead acid batteries for commercial, industrial, and utility installations," in Proc. IEEE Industrial and Commercial Power Systems Technical Conference, 1999, pp. 5.

[23] http://www.1soltech.com/images/1SolTech_245W_datasheet_0210.pdf [Accessed: Aug. 26, 2011]

[24] "Solar Resource & Meteorological Assessment Project (SOLRMAP) Milford," http://www.nrel.gov/midc/usep_milford [Accessed: Aug. 26, 2011]

[25] "January 2009 to September 2010 Load Profiles all classes," http://www.nhec.com/pdf/2009-Jan-2010-Sept_Load_Profiles.xls [Accessed: Aug. 26, 2011]