39
IEEE Boston PES - November 16, 2010 Offshore Wind

IEEE Boston PES - November 16, 2010 - IEEE PES Boston

  • Upload
    others

  • View
    11

  • Download
    0

Embed Size (px)

Citation preview

Page 1: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

IEEE Boston PES - November 16, 2010

Offshore Wind

Page 2: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Offshore Wind

A high-level overview of offshore wind project development identifying current technologies, challenges, risks and costs.

Presented by: Brook Knodel Electrical Group Manager, Mott MacDonald [email protected]

Page 3: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Discussion Outline

• Industry Overview

• Components– Turbines/Foundations

– 33 kV Collector System (Inter-Array Cables)

– Offshore and Onshore Substations

– HV Submarine Cable

• Risks and Obstacles

• Costs

• Questions

Page 4: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Industry OverviewWind turbine technology has proven to be one of the most effective sources of renewable energy. By the end of 2009 worldwide capacity reached 159 GW, generating 340 TWhannually.

Offshore wind offers many performance benefits versus onshore wind generation including strong, steady winds and proximity to metropolitan centers.

Source: WWEA World Wind Energy Report 2009

Page 5: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Industry Overview – cont.

• Over 3 GW of offshore wind installed globally– Mainly Europe and UK

– Roughly 2 GW currently in construction

• Growth has been exponential with 32 GW targeted for the UK by 2020 and 30 GW for Germany by 2030

• Ability to meet these targets limited by several factors– Technology

– Supply Chain

– Construction Capacity

Page 6: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Industry Overview – cont.

• In North America, several developers are proposing offshore wind along the North Atlantic Coast and Great Lakes.– Deepwater Wind, Fisherman’s, Bluewater Wind/NRG, Cape Wind

– Trillium, Great Lakes Offshore Wind, Windstream Energy

• Developers are jumping into large scale 500 MW+ projects

• Progress has been slowed due to many factors:– Financing, permitting (land rights/BOEMRE), supply chain,

infrastructure, regulatory, lack of long-term federal guidance

Page 7: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

ComponentsOffshore wind farms have many similarities to their onshore counterparts but the marine environment poses unique technical design challenges.

Major components of an offshore wind farm include:

• Turbines

• Foundations

• Inter-Array Cables

• Offshore Platform Substation/High Voltage Export Cable

• Interconnection Facilities

Page 8: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Components – cont.

Page 9: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Components – cont.

Page 10: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Components – cont.

Page 11: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Components – cont.

Page 12: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Components – cont.

Page 13: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Thornton Bank Phase I, BelgiumREpower 5 MW turbines (30 MW)

Components - Turbines

Page 14: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Turbines – cont.

• Typical types– High-Speed Multi-Stage Gearbox (Vestas)

– Direct Drive PM/Converter (GE, Siemens, Vestas)

– Multibrid Low-Speed Gearbox (AREVA, REpower)

• Projects in development now will probably utilize 5+ MW turbines as the technology continues to develop

• Costs average $2.5M per MW (not installed)

• Factories are fully booked for the next few years and global capacity is not sufficient for even a small subset of the proposed projects currently in development.

Page 15: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Turbines – cont.

• Manufacturers:– Clipper (USA) 10 MW Scanwind 6 MW

– GE 4 MW Mitsubishi 5 MW

– Vestas 3 MW * Nordex 2.5 MW*

– Repower 5 MW* Sinovel 3 MW*

– Siemens 3.6 MW* Econtechnia 2.5 MW

– Multibrid/AREVA 5 MW* Enercon 6 MW

– Darwin 5 MW Bard 6 MW*

– Rolls Royce 5 MW * - available now

Page 16: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Typical Dimensions:

REpower 5M (5 MW)Doubly-Fed Induction Generator Type

Rotor Diameter: 414 feet

Hub Height: 328 feet + transition piece

Nacelle Weight: 430 tons

From sea level to top of rotor blade is equivalent to a 50 story building!

Turbines are spaced approx. ½ mile apart to reduce wake effect.

Turbines – cont.

Page 17: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Thornton Bank Phase I, BelgiumFoundations

Components - Foundations

Page 18: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Foundations – cont.

• Types– Monopile (most popular type)

– Gravity Foundation (previous slide - 10 stories high, 3000 tons!)

– Jackets (inexpensive and most suitable for deep water projects)

– Tripods (specialty for some turbine manufacturers)

– Floating? (currently being developed)

• Past projects were in shallow waters (60 ft) and current projects are in 100 ft depths. Future projects are planned for much greater depths which will create installation challenges.

Page 19: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Foundations – jackets and mono-piles

Page 20: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Foundations – tripods and gravity type

Page 21: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Foundations – cont.

• Currently the foundations and turbines are erected using large jack-up barges customized for turbine erection. The depth of water is a limiting factor and alternate means of erection are being investigated for future deep water projects.

• The east coast has relatively shallow depths along the continental shelf, but current US jack-up barges may not be suitable.

• Foundation selection is very dependent upon subsurface conditions. In-depth marine geotech studies are essential.

• Costs range from $2.5M to $4M each (not installed)

Page 22: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

ABB XLPE Submarine Cable36kV, 3 core copper conductor with steel wire armor

Components – Inter-Array Cables

Source: ABB Submarine Cable Systems User Guide

Page 23: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Inter-Array Cables – cont.

• Utilize solid-dielectric 36 kV insulation – offshore generator vendors provide a standard 33 kV primary on each generator step-up transformer. Optical fiber integrated for communications.

• Each cable can ‘collect’ up to 35 MW of generation. Larger projects require offshore consolidation of multiple feeders.

• Installed costs are a small portion of the project, but…

• Installation has proven a challenge (over 80% of insurance claims $$ for offshore wind are related to the inter-array cabling). Many installation contractors have gone bankrupt.

Page 24: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Barrow Offshore Wind Farm, East Irish Sea, UKOffshore High Voltage Substation Platform

Components – Offshore Substation Platform/High Voltage Export Cable

Page 25: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Offshore Platform/Export Cable – cont.

• Necessary for projects larger than 35 MW to consolidate inter-array cable feeders and step voltage up to suitable transmission levels

• Design Considerations:– Weight and real estate are restrictive. Gas insulated designs (GIS)

are utilized for 33 kV and High Voltage AC switchgear.

– Location of the platform is selected to optimize cost of inter-array and export cable installation

– For projects larger than 200 MW multiple platforms may be preferable/necessary.

Page 26: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Offshore Platform/Export Cable – cont.

• Export cables are solid dielectric XLPE. Not much track record above 245 kV.

• Long distance submarine cables have high losses and can generate significant VARs necessitating reactors to control power factor.

• Splices are potential weaknesses so preference is a continuous cable per phase from shore to platform.

Page 27: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Offshore Platform/Export Cable – cont.

• Routing of the export cables requires significant planning.– Cable crossings need to be coordinated with the affected party.

Existing cables need to be physically protected and crossings need to be perpendicular. Negotiations may impact schedule.

– Subsurface investigations may show obstacles that need to be avoided (shipwrecks).

– Closer in to shore, human, fish, plant and animal habitats may restrict access. Typically the shore landing requires directional drilling or sawing. There are heavy duty saws available but they cost $2M to mobilize, $0.1M per day to operate and another $2M to demobilize.

Page 28: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

As projects get larger and further offshore, new voltage source converter HVDC technology is being considered.

• Standard HVDC converter technology is too space intensive to fit on an offshore platform. VSC converter technology, such as ABB’s HVDC Light, can be configured to fit and provides significant benefits at the point of interconnection including enhanced voltage/VAR support, black start capability and minimal short circuit contribution.

•Many countries (including the UK, Europe and the United States) are looking into developing offshore HVDC backbones for interconnection of renewable energy and strengthening of regional transmission networks.

•Current designs accommodate up to 1200 MW per +/-320 kVdcconverter although these technologies are new and have not been in commercial operation. (400 MW offshore has been operational)

•Installing HVDC requires an onshore converter station which can be costly in densely populated regions such as New York City.

•Lack of HVDC circuit breakers make multi-terminal designs a challenge. Temporary solutions utilize AC CBs as switches.

•Costs on order of $1M per MW installed (including submarine cable)

Offshore Platform/Export Cable – cont.

Source: ABB “It is Time to Connect”

Page 29: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Offshore Platform/Export Cable – cont.

• Export cable and HVDC technologies represent a lot of risk for the currently proposed projects over 500 MW. There is little or no track record for the submarine cable and converter equipment although many major manufacturers are focusing on bringing these technologies to market.

Page 30: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

NYPA’s Ryan Substation, New York230 kV Substation

Components – Interconnection Facilities

Page 31: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Interconnection Facilities – cont.

• In much of Europe, utilities are required to bring the point of interconnection to the offshore platform. In the United States, the export cable and substation upgrades required to support the project are the responsibility of the developer.

• Details are defined by the interconnection studies conducted by the region’s Independent System Operator in coordination with the interconnecting transmission owner.

• Costs vary widely based on voltage and the area’s ability to accommodate the proposed plant output.

Page 32: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Risks and ObstaclesOffshore wind projects face many obstacles to success. Mitigation of these risks becomes a project unto itself.

Getting a project from conceptual phase to commercial operation requires coordination and cooperation with investment capital, local and federal government, permitting authorities, engineers, contractors, utilities, vendors, banks, etc. This is true of both offshore and onshore projects. Unlike it’s onshore cousin, offshore construction projects are particularly susceptible to the vagaries of weather. All the coordination in the world cannot remove mother nature from the equation.

Page 33: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Risks and Obstacles – cont.

• How will you finance it? (Multibillion dollar projects)

• Who will buy the electricity? (FIT, PPA)

• What ships will you use? (Jones Act, St Lawrence Seaway)

• What labor force? (Jones Act)

• Where are you going to stage the construction? (Ports)

• Will your technology survive the conditions?

• Will political support remain in place? (Federal, State)

• Will the weather impact your schedule?

• How will you maintain it?

Page 34: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

CostsCompared to onshore wind, offshore wind costs approximately three times as much to install. These increased costs are partially offset by increased efficiency due to steady winds and closer access to metropolitan areas along the coast.

Land based wind projects typically require $1.5M per MW investment. Offshore wind costs have been increasing over time as the projects move from shallow coastal waters to deeper regions. Current investment projections vary from $3M to $5M per MW.

Page 35: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Comparative generating costs, base case– 2009 start

Discounted lifetime cost / productionMid 2010 datum

Page 36: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Costs – cont.

• A typical breakdown of the costs associated with large-scale offshore wind:

– Development 2.5%

• Permitting, Legal Fees, Preliminary Design, Interconnection Studies, Site Investigation, Land Acquisition

– Turbine Procurement 40 %

– Foundation Procurement 10 %

– Other Supply Costs 7.5 %

• Platforms, Cables, Substation Equipment

– Installation and Erection 15 %

– Other Costs 25 %

• Owner Management Costs, Contingencies, Bank Fees, Insurance, Interest

Page 37: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Costs – cont.

• Operation and maintenance costs are difficult to project for US projects. Vendors are not regional and there are no experienced ships or crews in existence.

• O&M Costs, based on what is being done in Europe are $150k - $200k per MW depending on distance from shore and contract conditions.

• This equates to approximately $0.05 per kWh for O&M alone.

Page 38: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

Questions?

Page 39: IEEE Boston PES - November 16, 2010 - IEEE PES Boston

www.mottmac.com