73
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Huawei Training for Dialog Regional Engineering Staff OSP Training March 13, 2012 Prepared by: F. M. A.Junkeer

Huawei Training for Dialog Reginal Staff-1

Embed Size (px)

Citation preview

Page 1: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Huawei Training for Dialog Regional

Engineering Staff

OSP Training

March 13, 2012

Prepared by: F. M. A.Junkeer

Page 2: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Index

Page 2

2Construction & Erection of Concrete poles/Cable Installation

3 OSP Technical Concern

4 Huawei OSP Project Managment

1 Huawei OSP Turnkey Project Experience & Introduction to Dialog OFN Project

Page 3: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Dialog Huawei HDPE OFC (micro cable)

Page 3

Solution: one 8-way HDPE bundle Micro duct

Length: 140KM

Duration:11months

Max progress :25 km/month

After the excavation, a 7-way bundle micro duct

had been laid into the trench, and after the laying

of the micro duct, a 48 core micro cable had been

blowing into the micro duct. Because the total

diameter of the micro duct is less than 45mm, so

the excavation width is only 300mm.

Page 4: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

ADSS FOC for Sudan National Electricity Corporation

Page 4

How NEC Benefited

Huawei Solution

Challenges Faced by NEC

Install FOC along existing electricity cables

Cross the main road inside the capital

Cross the main bridge over River Nile inside the capital

Adopt ADSS FOC to avoid electromagnetism interfere

Drill PVC pipe to cross road and lay LDPE pipe to protect FOC

Install steel pipe beside the bridge and lay LDPE pipe to protect FOC

Save the cost of erecting new poles;

No need to get the right of the way;

Build WAN FOC to form its own telecommunication network in

the capital

Page 5: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Syria Telecommunication Optical Access Network(OAN)

Page 5

How STE Benefited

Huawei Solution

Challenges Faced by STE

Provide voice/video and internet access to more than 100 small villages

distributing all over the Syria;

The total length of O.F. is over 1100Km. Unlike backbone O.F. project,

this 1100Km distribute in 7 big province and over 80 small sections/areas.

Need to install 38 OLTs and 242 ONUs in a very short time;

Their rival Syriatel is very strong and fast development.

Professional end-to-end service solution

Professional delivery management team

Customized network technology consultant, network evaluation &

optimization including technology support, products & route maintenance

O.F. access insure the enough bandwidth and later expansion.

The project is finished 6 months ahead the deadline;

After optimizing the route and fine management, decreased the road surface

breaking and route length.

Ahead their rival Syriatel occupy the rural market.

Page 6: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

MTN Nigeria Transmission Project

Page 6

How MTN Benefited

Huawei Solution

Challenges Faced in this project

3200km cable route with complicated landscapes cause many special

crossing methods and protections;

The raining season is a bad factor for project implementation in Nigeria;

A lot of community and government issues ,about 80% interruptions come

from this item;

Varieties of advanced equipments and techniques for different terrains

Fast track method to overcome the raining season

More than 2000 labors work at the same time

Good relationship with the relevant government department.

Fast implementation brings more benefit to MTN.

Rich experience and different solution for different terrains save cost for

MTN;

Full TK service save project management cost for MTN.

Page 7: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Some of Last Five Years OSP Projects

Project Country OperatorRoute Length

Project Type Start DateEnd Date

Cote d'lvoire MTN Metro Ring Project Cote d'lvoire MTN 137 Km Duct/direct bury Apr-08 Dec-08

Malawi MTL backbone project Malawi MTL 1100 Km Duct/direct bury Apr-08 Dec-09

Senegal E-government backbone project SenegalGovernmen

t630 Km Duct/direct bury Dec-07 Nov-08

Kenya CCK national backbone project Kenya CCK 1112 Km Duct Nov-07 Nov-08

Zambia Zamtel National backbone project Zambia ZAMTEL 3800 Km Duct/direct bury Oct-07 Feb-09

Pakistan PTCL 1465 TURNKEY Pakistan PTCL 300 Km Duct Oct-07 Jun-08

Zambia Zamtel Lusaka Metro project Zambia ZAMTEL 100 Km Duct Aug-07 Dec-07

Cote d'lvoire MTN Fiber Transmission Project Cote d'lvoire MTN 1136 Km Duct/direct bury Apr-07 Dec-07

Kazakhstan Kar-Tel optical transmission project Kazakhstan Kar-Tel 840 Km Duct Mar-07 Nov-07

Ghana E-government backbone project GhanaGovernmen

t526 Km Duct/direct bury Feb-07 Nov-07

Ghana MTN backbone project Ghana MTN 606 Km Duct/direct bury Feb-07 Nov-07

Uganda E-government&National backbone project

UgandaGovernmen

t197 Km Duct Dec-06 Sep-07

Thailand CAT DWDM project Thailand CAT 7200 Km Aerial Oct-06 Dec-07

Angola MST National Optical backbone project Angola MSTelcom 110 Km Duct Aug-06 Dec-07

Pakistan PTCL OFAN TURNKEY Pakistan PTCL 1200 Km Duct Jan-05 Apr-08

Nigeria MTN National backbone project Nigeria MTN 3000 Km Duct/direct bury Nov-04 Feb-07

Page 7

More than 30,000 Km on time end-to-end Turnkey delivery experiences worldwide!

Page 8: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Dialog Broadband

Island wide Optical

fibrer Network

Phase 2B

•Routes Under SIERRA

Construction.

1. Katugastota-Hunnas

2. Dambulla-Anuradapura

3. Anuradapura-Jaffna

• Routes under Access

Engineering

1. Peliyagoda-Negamabo

2. Matara-Hambantota

3. Wattegama-Dambulla

Page 8

Page 9: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Page 9

INTORDUCTIONTo cater the ever increasing demand for Bandwidth and to achieve a “high reliable core network”, Dialog decided to expand its Optical Fibre network.

Hence new fibre routes and nodes were identified according to the existing and predicted capacity requirements as well as the identified strategic potentials.

This decision drove Dialog for the option of releasing a Request for Proposal (RFP) to look for bidders who propose solutions for the requirement.

This section covers the technical requirements and expectations of the project.

General Scope

The scope of this document is to describe the Technical Requirements & Specifications that the Bidders shall fulfil with the aim to

provide a complete end to end solution for the implementation of Optical Fibre Network as a turnkey project.

TECHNICAL REQUIREMENTS SPECIFICATION (TRS)

The TRS specifies the technical requirements to be fulfilled in order to implement a complete end-to-end solution

for the Optical Fibre Network.

Following will be key points for the bidders to adhere from the beginning of the project.

•This is an extension of Dialog’s existing Optical Fibre Network (OFN). Hence all the components and solutions proposed by bidders

will be assessed for the compatibility with the existing network and same will be treated as a must.

•The base of the cable network will be aerial and the solution should be designed in a manner that the cable implementation to be

aerial as much as possible. The scenario to choose the other options is described under the civil construction module.

•Dialog reserves the right to suggest the successful bidder/s to change and propose any of the network / project components described

under TRS. Bidders are expected to take this challenge from the beginning.

•Dialog will decide and change its priorities on implementation with respect to the fibre routes even while at the implementation

phase.

Page 10: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Page 10

Dambulla - Anuradhapura 68.33

Kekirawa 18.62 0.50 19.12 63

Galkulama 29.62 0.36 48.60 63

Anuradhapura DBN 9.67 9.56 67.47 504

Anuradhapura - Jaffna 199.96

Medawachchiya 22.03 0.01 22.04 126

Iratteperiyakulam 17.10 0.01 39.14 63

Madukanda 7.95 7.08 54.16 63

Kanagarayankulam 36.42 0.40 83.90 63

Iranamadu 33.80 0.17 117.47 63

Kaithady 62.58 1.09 180.97 63

Jaffna 10.88 0.44 191.20 441

New Sites in Existing Routes

Kurunegala-Kandy Site Connectivity 45.00

Hunnas DBN 25.50 5.00 30.50

Hanthana 12.00 2.50 14.50

Sites Main Road Distance By Road DisatnceTotal Road distance

(Cumilative) Dropping Capacity

Page 11: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Page 11

Paliyagoda-Negambo 40.13

Hekitta 3.07 1.40 4.47 189

Ragama North 7.34 1.9 12.31 63

Kandana West 1.96 1.60 13.97 63

Ekala 2.95 1.30 16.62 63

JaEla North 2.48 0.68 18.48 63

Seeduwa 3.81 0.11 21.72 567

FTZ South 1.60 2.65 25.86 63

Kurana 4.01 0.13 27.35 63

Katuwapitiya 2.49 0.65 30.36 189

Matara - Hambanthota 97.88

Kakenadura 8.05 4.5 12.55 189

Hakmana 26.04 20 54.09 189

Ambalanthota 28.72 0.20 63.01 126

Hambanthota 10.32 0.05 73.18 252

Page 12: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Page 12

Dambulla-Trinco 154.70

Habarana 21.28 0.30 21.58 63

*Girithale 31.00 1.65 53.93 126

*Polonnaruwa DBN 12.10 1.59 65.97 189

Agbopura 41.37 0.25 62.90 63

Trinco DBN 43.58 1.58 107.81 315

Trinco- Bati 153.76

Punani 92.69 17.69 110.38 63

Sittandy 16.06 1.12 109.87 63

Eravur 6.88 1.14 116.77 63

Nochchimunai 16.58 0.18 132.39 63

Kattankudy 1.29 0.13 133.63 378

Page 13: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Index

Page 13

2Construction & erection of concrete poles/Optical cable Installation/E to E net work solution

3 OSP Technical Concern

4 Huawei OSP Project Management

1Huawei OSP Turnkey Project Experience &Introduction to Dialog OFN Project

Page 14: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

E2E OSP Network Solution

Page 14

The end-to-end deployment process leads to fast implementation and roll-

out on time, within budget, to the required quality and a quick return on

customer investments. It is also our key measure of success.

For that, Huawei has developed an end-to-end delivery process to ensure

on-time completion of projects. Customer can concentrate on their core

businesses while Huawei takes care of building the infrastructure.

Phase 3 Phase 4Phase 2

End to End

Project Deployment

Project

InitiationBidding

Contract

Signing

Manufacturing,

Delivery &

Engineering

Preparation

Maintenance

ServiceImplementation,

Testing and

Acceptance

Phase 6

Pre-Sales Post-Sales

Phase 1 Phase 5

Training

ServiceProfessional

Service

Phase

7

Phase

8

Service Support

Project Management

Page 15: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Network Planning

Page 15

Fiber

Cable

Network

Planning

Network structure design

Existing Fiber Cable resource

investigation

Fiber Type selection

Cable Type selection

Quantity of Core

Cable Installation

method

Infrastructure

Node, route and repeat

section design

Link Budget

Route Telecom

Design

SDH/DWDM

Capacity

Ring/Link Protection

Page 16: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Infrastructure (Construction Method)

Page 16

Underground

Duct systems

Direct buried

systems

Aerial cabling

systems

Mainly used for urban installation

Used when ever there is existing poles because

of fast installation and easy accessible for

maintenance

Used for suburban installation

Page 17: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Comparison of Construction Methods

Method Advantages Disadvantages Usage

Underground

Conduit

System

Out of sight, adaptable for

future expansion, easy cable

placement and removal, long

lifetime, protected from most

natural disasters and low

maintenance expense.

High initial cost compared to

other systems.

Mainly used in urban areas.

Direct buried

system

Out of sight, long lifetime,

protected from most natural

disasters.

Capacity cannot be increased,

and maintenance expense is high.

Mainly use in rural areas.

Aerial Cable Low cost, fast installation, easy

maintenance and adaptable for

future expansion.

High risk to damage caused by

natural disasters, accidents or

intentional activities.

Suitable when exiting poles are

available.

Page 17

Page 18: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Cable Type

Page 18

Figure 1; Cable Design for Duct Fibre Figure 2; Cable Design for Direct Buried Fibre

Figure 3; Cable Design for Aerial Fire Figure 4; Cable Design for Aerial Fire

Page 19: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Fiber Type

Page 19

Single optical fiber's characteristic

G.652 optical fiber

(SMF)

G.653 optical fiber

(DSF)

G.654 optical fiber

(WSF)

G.655 optical fiber

(NZ-DSF)

The most mature single mode optical fiber, the

minimum attenuation is in different window with

the minimum dispersion

An inter grade type single mode optical fiber,

through shifting optical fiber cutoff wavelength, to

gain the lowest attenuation

An inter grade type single mode optical fiber , the

zero-dispersion point shift to the minimum

attenuation window

Another mature single optical fiber, the minimum

attenuation is in same window with low

dispersion

Page 20: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Field Survey and ROW

Collect existing data, maps and drawings for the site to be surveyed.

Survey the geographical area that needs services to identify the most

economical and suitable route based on demand, MH/HH locations,

identify obstructions along the routes and the soil types.

Inside building survey for space planning

and equipment layout. Includes

OSP/ISP Reports and Drawings.

Identifying material quantities (BOQ).

Coordination for the approval of necessary

OSP right of way and permits.

Page 21: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Detail Design and planning

Detailed Network Design construction drawings.

Special cases solutions.

Needed Material quantities.

Cable assignment

Tools and Equipment.

Etc.

Page 21

Page 22: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Construction

Page 22

Route detailed

survey and

design

TrenchingInstallation

of Ducts and

Manholes

Backfilling,

Reinstatement

Duct Mandrel Testing

Duct Pressure

Testing

Fibre Splicing

Fibre Cable

Installation

Terminating

and Testing

Site

preparation

Equipment

Installation

Equipment

Testing

Equipment Integration,

& Commissioning

Route detailed

survey and

design

Equipment work

Acquisitions

Underground Fibre ROW and

acquisition

Aerial Fibre

Permission

from

RDA/MC/PS

New pole

installation

Lighting protection

Cable Work

Bracket

installation

Page 23: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Underground Cables in Duct

In this method the cables are placed in

underground Duct with manholes or

handholes between the Duct sections.

There are different types of Duct that can

be used according to requirements.

• 110 mm PVC ducts with sub-ducts installed

into them.

• 55 mm PVC ducts.

• HDPE pipes

Page 23

Page 24: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Direct Buried Cables

Page 24

This type of construction is usually

applied on non-urban areas where there

are no existing manholes & conduits.

Normal burial depth is 1.5m with warning

tapes placed on equal distance to

ground level. Concrete encasement can

be applied where there are external

threats perceive such as soil erosion or

soil condition with high moisture content.

Page 25: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Page 25

Aerial Cables/Concrete Poles

Aerial cables are installed on Concrete

poles. Dialog used 8 m poles mainly, 9 m

poles used in road crossings. 5.6 m poles

used in Hunnas, because of the difficulty in

transportation & handling.

Page 26: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Concrete pole specification/design

The length of the poles which are connected to aerial cables shall be 8.0

meters.

The buried depth shall be one-fifth of pole length as per standard. In

exceptional cases, where it is technically impossible to keep the above

standard, based on DIALOG approval, the depth may be permissible up to

one-sixth of pole length. The buried depth of poles used for mounting

distribution points shall be always one-fifth of the pole length.

The poles shall in line with Sri Lanka Standard 363:1975 relating to

reinforced concrete poles for Telecommunication Lines,

Page 26

Page 27: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Concrete Pole specification/design Cement

All cement used for concrete poles shall be Portland Cement and in accordance with BS

12 or equivalent. The cement shall be stocked in such a manner as to afford easy access

for inspection. Cement shall be kept dry at all times prior to use in order to prevent

deterioration.

Fine Aggregate

The fine aggregate for concrete shall consist of natural river sand or equivalent material.

Coarse Aggregate

The coarse aggregate for concrete shall consist of gravels and/or crushed stones

having hard, strong and durable pieces free from adherent coatings such as mud or

other foreign materials. The coarse aggregate shall be graded between a maximum

sieve size of 19 mm and a minimum size corresponding to 5 mm sieve size. It must be

free from dirt, floury stone dust, earth or any similar materials.

Water

Clean, fresh water which is free from inorganic or organic matter in solution or in

suspension in such amounts that may impair the strength and durability of the concrete

shall be used during both mixing and maturing.

Page 27

•Fine Aggregate

Page 28: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Placing and curing of concrete

The concrete shall be used as soon as

possible after being mixed and no material

which has developed an initial set shall be

used in the work. Each mould shall be filled

with concrete in one continuous operation.

After the material has been placed in the

moulds it shall be compacted and shall not be

disturbed during the period of setting. After

placing, concrete shall be protected, during

setting and in the first stage of hardening from

shocks, running of surface water and the

harmful effects of sunshine and drying winds.

The concrete shall be prevented from drying

out for at least 7 days.

Page 28

Page 29: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Steel form work

Page 29

Page 30: Huawei  Training for Dialog Reginal Staff-1

40pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

40pt

: R153 G0 B0

黑体

30pt

30pt

黑色

:

FrutigerNext LT Regular

: Arial

30pt

30pt

黑色

细黑体

Reinforcement

Page 30

Reinforcement shall be cleaned and free from

loose Mill scale, loose rust, mud, oil, grease

and any other Coating which could reduce the

bond between the concrete And the steel. A

slight film of rust shall not be regarded

As harmful, but the steel shall not be visibly

pitted by rust.

Longitudinal reinforcing bars shall

where possible be continuous

throughout the length of the pole, but may

contain not more than one lap in each bar

line, subject to the following conditions.

Page 31: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole construction

Page 31

Curing & casting

Page 32: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole testing Type test

Unless otherwise specified with the enquiry or

order, a written statement that the number of

poles specified in Table 2-19, identical in all

essential features of design with those provided,

have passed the type test shall be deemed to be

sufficient evidence that the poles comply with

the requirements of this specification. The

statement shall give all tests and state the age

of the poles when tested. The poles selected for

the test shall be tested in accordance with

Clause 2.10.9 The permanent set after removal

of a test load of 60 percent of the minimum

ultimate load specified in Table 2-18 shall not

exceed 10 percent of the deflection at the test

load. The hair cracks produced in testing shall

clearly close up on removal of the test load

specified above.

Page 32

Page 33: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole testing

Applying load

Page 33

Page 34: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole testing

Destruction

Page 34

Page 35: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole testing

Connectivity Weighing slabs

Page 35

Page 36: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Ariel Cable Installation

Page 36

Page 37: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Ariel cable Installation

Page 37

Page 38: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole Numbering

Page 38

Page 39: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Pole Numbering

Page 39

Page 40: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Special Construction Cases

Rivers and Canal Crossing:

Cables are installed in a 4 inch galvanized steel pipe for extra

protection attached to the side of the bridges when ever

bridges are available.

For small canals the optical fiber cable shall be buried under

the canal.

HDD technology can also be applied.

Page 40

Page 41: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Special construction cases

Page 41

Page 42: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Special Implementation Cases

Crossing Main Roads and Railways:

The cables are installed in a 4 inch galvanized steel pipe for

extra protection.

In places were trenching will not be allowed, boring methods

(HDD) under road are used.

Page 42

Page 43: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Special Implementation Cases

Page 43

Slope protection sketch map

Collapse

Protection slope

Slope Protection:

Page 44: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

MH/Duct lebels

Page 44

Page 45: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

DUCTS:

The material to be supplied is Permanently Lubricated High Density Polyethylene (PLB

HDPE) duct for use as under-ground cable conduit for optical fiber cables, suitable for cable

installation by blowing technique

The ducts shall be suitable for both open cut laying as well as HDD (Horizontal Deviation

Drilling) method.

Specification of Permanently Lubricated High Density

Polyethylene Ducts (PLB HDPE Ducts)

The PLB HDPE duct shall consist of two concentric layers, the outer layer

being HDPE co-extruded with an inner layer of solid permanent lubricant, to

reduce internal coefficient of friction (CF). The lubricant shall be of solid layer

of uniform thickness so formulated to provide a permanent, low friction

boundary layer between the inner surface of the duct and the optical fibre

cable. The lubricant shall be clearly visible in cross section, concentric with the

outer layer.

Page 45

The ducts shall be suitable for both open cut laying as well as HDD (Horizontal Deviation Drilling) method.

Page 46: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Dimension of the duct shall be as under:

Outer diameter : 40mm+0.4 mm

Wall thickness : 3.5mm±0.2mm

Nominal inner diameter : 33mm

Lubricate inner layer thickness : 0.35mm

Identification marking on the surface of the duct

At every 02 meter along the length followings shall be marked

“Dialog identification” interleaved with

‘Manufacturer name and date of manufacture’.

In addition sequential length marking in every one (01) meter shall be provided.

The PLB HDPE duct shall be supplied in a continuous length in coil form, suitable for shipping and

handling purpose together with all necessary accessories needed for the proper duct installation.

The inner layer (solid lubricant) shall be white in colour

The duct supplier shall be able to supply ducts in different colours and all the accessories related. The

bidder shall provide all the details of the duct supplier including the company profile together with it’s

financial strength, manufacturing capacity, the full range of ducts & accessories with their detailed

specifications. Some of the standard accessories are listed below.

Page 46

1.The duct supplier shall be able to supply ducts in different colours and all the accessories related. The bidder shall provide all the details of the duct supplier including the company profile together with it1.The duct supplier shall be able to supply ducts in different colours and all the accessories related. The bidder shall provide all the details of the duct supplier including the company profile together with it

Page 47: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

– Plastic Coupler

– Split couplers

– Mandrel

– Pressure testing attachments

– End Plug

– Cable Sealing Plug

– Identification Tags

Ducts installed shall be in different colours (Other than Black colour) to be able

to identify easily.

Page 47

Page 48: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Cable connection/Rise up

Page 48

Page 49: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

View of Inside of MH

Page 49

Page 50: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Excavators

Page 50

Page 51: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Air Blowing and Compacting

Page 51

Air Blowing Compacting

Page 52: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Splicing ,Testing and Acceptance

Page 52

All fiber will be joined by means of the

fusion splice technique.

The jointing point will be contained and

organized in splicing box.

The optical cable will be spliced with

pigtails in the equipment room and

terminated on the ODF.

The optical cable will be tested by

OTDR in double direction to get overall

attenuation and splicing loss.

Splicing

Termination

Test

Page 53: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

END TO END LOSS MEASUREMENTS BY OPTICAL POWER METER & SOURCE Form No :

ISLANDWIDE OPTICAL FIBER BACKBONE NETWORK PROECT

Road KURUNEGAL-KANDY Sector Date 31/12/2011

Site Sheet No 1 OF 2

SectionFrom : KULUGAMMANA DIALOG SITE To : HUNNAS DIALOG SITE

(1) Representative Calibration Value of the Power Meter

Description P1/ dB P2/ dB E=P1-P2 (dB) Remarks No of Cores 60

1st -5 -5.24 -0.24 Actual Distance 33.25

2nd -5 -5.16 -0.16 OTDR Distance 33.62

3rd -5 -5.24 -0.24 No of Splicing 20

Rep. Calibration

Value = Sum

(P1-P2)/3 -5 -5.21333 -0.21333 Wave Length 1550

cw

(2) Optical loss of End to End.

Core No P in (1) P out (2)Rep. Calib.

Value "E" (3)

Optical Loss (1)-

(2)-(3)Core No P in (1) P out (2)

Rep. Calib. Value

"E" (3)

Optical Loss (1)-

(2)-(3)

37 -5 -19.56 -0.2133 -14.3467 67 -5 -18.95 -0.2133 14.1633

38 -5 -18.86 -0.2133 -13.6467 68 -5 -19.28 -0.2133 14.4933

39 -5 -18.99 -0.2133 -13.7767 69 -5 dis -0.2133 #VALUE!

40 -5 -21.42 -0.2133 -16.2067 70 -5 -21.71 -0.2133 16.9233

41 -5 -19.22 -0.2133 -14.0067 71 -5 -19.61 -0.2133 14.8233

42 -5 -19.25 -0.2133 -14.0367 72 -5 -19.34 -0.2133 14.5533

43 -5 -18.53 -0.2133 -13.3167 73 -5 -20.2 -0.2133 15.4133

44 -5 -18.76 -0.2133 -13.5467 74 -5 -22.25 -0.2133 -20.28

45 -5 -40.88 -0.2133 -35.6667 75 -5 -18.71 -0.2133 13.92

46 -5 -21.48 -0.2133 -16.2667 76 -5 -18.12 -0.2133 13.3333

47 -5 -19.36 -0.2133 -14.1467 77 -5 -19.22 -0.2133 14.4333

48 -5 -19.37 -0.2133 -14.1567 78 -5 -33.35 -0.2133 28.5633

49 -5 -19.46 -0.2133 14.6733 79 -5 -18.96 -0.2133 14.17

50 -5 -19.11 -0.2133 14.32 80 -5 -27.87 -0.2133 23.0833

51 -5 -20.93 -0.2133 16.1433 81 -5 -42.07 -0.2133 37.2833

52 -5 -20.28 -0.2133 15.4933 82 -5 -34.54 -0.2133 29.7533

53 -5 -20.55 -0.2133 15.7633 83 -5 -19.01 -0.2133 14.2233

54 -5 -20.35 -0.2133 15.5633 84 -5 -23.35 -0.2133 18.56

55 -5 -19.25 -0.2133 14.4633 85 -5 -19.3 -0.2133 14.51

56 -5 dis -0.2133 #VALUE! 86 -5 -18.89 -0.2133 14.1033

57 -5 -21.65 -0.2133 16.8633 87 -5 -20.46 -0.2133 15.6733

58 -5 -19.47 -0.2133 14.6833 88 -5 -19.15 -0.2133 14.3633

59 -5 -19.73 -0.2133 14.94 89 -5 -18.58 -0.2133 13.7933

60 -5 -19.83 -0.2133 15.0433 90 -5 -29.54 -0.2133 24.7533

61 -5 -19.42 -0.2133 14.6333 91 -5 -19.13 -0.2133 14.3433

62 -5 -19.06 -0.2133 14.2733 92 -5 -20.55 -0.2133 15.7633

63 -5 -19.02 -0.2133 14.2333 93 -5 -19.95 -0.2133 15.1633

64 -5 -18.85 -0.2133 14.06 94 -5 -19.96 -0.2133 15.1733

65 -5 -18.85 -0.2133 14.0633 95 -5 -19.71 -0.2133 14.9233

66 -5 -20 -0.2133 15.2133 96 -5 -19.28 -0.2133 14.4933

Acceptance Criteria: 3.For G655 (NZDSF) link loss measurement at 1310nm is not applicable.

1 Average Splice loss (both directions) for G655 at 1550nm fiber 0.1 dB 5.Acceptable link loss (0.25 x Fiber length in KM) + 0.1x No. of splices +

2 Attenuation co-ef limits for G655&G652 connectors loss (2 each x 0.5dB) = ………………..dB.

At 1310nm 0.40 dB/km 0.21*33.65+0.1*20+4*0.5 = 11.0665dB

At 1550nm 0.25 dB/km 0.4*33.65+0.1*20+4*0.5 = 17.46 dB

TESTED & SUBMITTED BY ACCEPTED BY

CONTRACTOR DIALOG

NAME

DESIGNATION

SIGNATURE

DATE

Page 53

Page 54: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Maintenance

Maintenance services ensure that outside plant cable paths are

clear of obstructions and external threats and communication

cables are kept in the optimum condition through:

Preventive maintenance.

Scheduled testing for network performance.

Equipment and spare parts management.

Cable faults localization.

Troubleshooting and emergency response.

Transmission loss allocation.

Techniques for improvement/reliability.

Control/updating of plant records

Page 54

Page 55: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Index

Page 55

2 End to End OSP Network Solution

3 OSP Technical Concern

4 Huawei OSP Project Management

1 Huawei OSP Turnkey Project Case

Page 56: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

INSTALLATION AND CONSTRUCTION STANDARD

Installation/construction of Aerial OF cable for National Backbone Optical Fiber Network shall be carried

out according to the Specifications provided below. Other installation/construction details which are not

specified in this Part shall be proposed by Huawei, for the approval of DIALOG. All installation and

construction standard method statements should be submitted to satisfy these requirements in Technical

Proposal.

Huawei shall be solely responsible for any claims or damages arising out of the execution of the work.

Huawei shall obtain all the necessary permissions for excavation of roads from authorities concerned prior

to construction. DIALOG will co-operate with and assist Huawei to obtain the necessary permission.

AERIAL CABLE INSTALLATION STANDARD

Aerial cable shall be suspended on the roadside of the pole and new cable shall be suspended underneath

the existing cable on pole line where possible. The aerial cable shall be suspended on the same side of

each pole.

The aerial cable shall be suspended at 50 cm from the top of each pole.

The minimum clearance from ground to the lowest point in the span of cable shall be at least 4.5 m along

roads and 5.5 m at road crossing. The minimum clearance from foliage and trees shall not be less than

1.75 m.

Sags of aerial cable shall not exceed 0.8 m under the worst conditions expected.

Page 56

•The minimum clearance from ground to the lowest point in the span of cable shall be at least 4.5 m along roads and 5.5 m at road crossing. The minimum clearance from foliage and trees shall not be less than 1.75 m.

Page 57: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt Aerial OFC

OPGW ADSS ADL/ADW

Page 57

Aerial Optical Fiber Type:

OPGW (Optical Ground Wire)

ADL/ADW (All Dielectric Lash)

ADSS (All Dielectric Self Supporting )

Replacing with existing wire

Can be install on tower

Install on

existing wire

Comparison between Aerial OFC

Page 58: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Page 58

Installation situations

OPGW:

Replaces with shield wire (top of

tower)

ADSS :

It depends on power of electrical

field of line

ADL / ADW:

This cables installs on shield or

phase conductor

Comparison between OPGW and ADSS

Page 59: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Comparison between OPGW and ADSS

Page 59

Figure 2; Cable Design of OPGW Figure 2; Cable Design of ADSS

Page 60: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

32pt

) :18pt

Comparison between OPGW and ADSS

Page 60

Proposal: ADSS is recommended for installation on existing electric pole, but the

existing electric pole and wire height should be considered.

Advantage Disadvantage

ADSS ADSS cable has higher tensile strength. It isapplicable for long span. The overall thermalexpansion coefficient of ADSS is very low, sothe effect of temperature on ADSS sag is small.

ADSS is made of non-metallic materials, canbe installed and maintained on live-linesituation. The feature is convenient and safefor installation and maintenance.

Anti-track material makes ADSS be able to beused in strong electric fields.

ADSS cable has good features, such as smalldiameter, light weight, and small load affectionon poles or towers.

Installed position is under existing electric cable,the safety distance between cable and ground needto be considered.

OPGW Strong Physical feature, can support long spaninstallation (more than 250m).

Suitable for new installation powertransmission system to save construction cost.

Vibration caused by wind, hurricane, ice thickness, Unsteady operation caused by temperature,

possible thunder attack, short circuit. For existing power line system, the power supply

must be break off

Page 61: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 61

Comparison between G.652D and G.655

TypeAttenuation(dB/km)

1550nm

Dispersion(ps/nm.km)1550nm

Window(nm)PMD

1550nm

G.652 0.17-0.25 17-20 1310/1550 <0.2

G.655 0.19-0.25 1-6 1550 <0.2

G.655(TWRS) 0.19-0.25 1-6 1310/1550 <0.2

G.656 0.19-0.25 8 1550 <0.2

Proposal : G.652D is recommended.

Advantage Disadvantage

G.655 lower dispersion, and it need fewer DCM

(Before DCM is high cost, using G.655 save the cost of DCM. But now the DCM price is lower down, and it is not a significant advantage)

Can not be used for 1310 nm laser. Significant non-linear effect (SPM, FWM),

not suitable for DWDM system(80*40G e.g) Higher Price

Page 62: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 62

Comparison between Direct Buried/HDPE/Microduct

Land Cable Installation Method

Direct Buried Duct

PVC DuctConcrete Duct HDPE Duct Micro Duct

Page 63: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 63

Maintenance

Advantage of HDPE Duct Solution

Replacement

• Upgrade capacity

The cable can be

replaced with new

type of OFC

Balance of CAPEX and OPEX

• According to the traditional solution, compared with duct OFC, the direct buried

OFC for the national backbone has low CAPEX, but OPEX is extremely higher.

• Maintenance

• Trouble shooting

• Repair

No need to

excavate again

and again

Expansion

• Expansion

capacity

No need to dig

and lay another

D.B. OFC

Comparison between Direct Buried/HDPE/Microduct

Page 64: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 64

Construction Process

Survey &

Design

D.B.

HDPE Duct

PVC Duct

TrenchingDuct &

Manhole BackfillCable

InstallationRepeating

Section TestNew Cable

Installation

Existing Duct

Treatment

N/a N/a

Pulling

• Different steps: Duct & manhole

• Different installation methodology: laying, blowing, pulling

The distance between the manholes increases to around

1000m compare with 100m in the traditional PVC duct

solution after the popularize of HDPE pipe and cable blowing

technique. The cost of manhole reduces.

Expansion Process

• No expansion capacity for D.B.

• Cable blowing technique makes

the maintenance and upgrade

more rapidly

Micro pipes can be blowing into

the HDPE pipe to use the duct

system more adequately

Blowing

Pulling

Laying

Blowing

Assembly

Laying

Comparison between Direct Buried/HDPE/Microduct

Page 65: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 65

Solutions Cost of Material Cost of Service

OFC and

joint box

Duct and

manhole

Excavatio

n

Backfill Duct

installation

Manhole

installation

OFC

installation

D.B. High Low (joint pit) Low Low 0 0 Low

40/33 HDPE Low Low Low Low Low Low Low*

110 PVC Low High High High High High High

• Choose the cable blowing methodology

The cost of HDPE pipe solution is quite lower than the traditional PVC solution. The additional cost of construction is mainly about the pipe and manhole compare with D.B. solution.

Advantage of HDPE pipe solution: obviously the OFC services have higher reliability and cost performance. The outside plant part is more convenient to maintain, and provided with expansion and upgrade capacity.

Comparison between Direct Buried/HDPE/Microduct

Page 66: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 66

Comparison between Direct Buried/HDPE/Microduct

Microduct Solution: Projection Duct + Microduct + Microcable

Protection Duct :HDPE duct with dimension from 32mm to 63mm (outer diameter)

Microduct :HDPE duct with dimension less than 16mm (outer diameter)

Microcable: Cable suitable for blowing installation in microduct, cable diameter is 3.0 ~ 10.5 mm.

Page 67: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 67

Comparison between Direct Buried/HDPE/Microduct

Microduct Overview

Microduct Bundles

Microduct

Note: Microduct Bundles is normally used for point to point solution, it’s not easy for branching.

Page 68: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 68

Comparison between Direct Buried/HDPE/Microduct

TypeInner

Diameter

Minimum Inner

DiameterThickness Bending Radius

7mm 5.5mm 5.1 .75 (+.0 -.1) 140mm

10mm 8mm 7.6 1.0 (+.0 -.1) 200mm

12mm 10mm 9.6 1.0 (+.0 -.1) 240mm

Microduct Overview

Normal Microduct Type Reference

Microduct Qty vs. HDPE Duct Diameter Reference

Microduct

HDPE Duct12/10mm 10/8mm 7/5.5mm

25/21mm (3/4) " - 1 3

32/28mm (1) " 2 3 5

40/33mm (1.25) " 4 5 10

50/42mm (2) " 8 10 20

Page 69: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 69

Comparison between Direct Buried/HDPE/Microduct

Note:

1. Loose tube type cable is preferred for both normal cable and microcable.

2. Normally one loose tube contains 12 cores fiber.

Fiber Type CoresLoose Tube

Diameter (mm)

Loose

Tube

Qty

Filling Rope Qty

Cable

Diameter(

mm)

Cable

Weight(kg

/km)

Max Allowed

Working Tension

(N)

Max Allowed

Crush (N/100mm)

GCYFTY-4—l2Xn 4—12 1.7 1 3 5.3 22 120 450

GCYFTY-14—24 Xn 14—24 1.7 2 2 5.3 22 120 450

GCYFTY-26—36 Xn 26—36 1 7 3 1 5.3 22 120 450

GCYFTY-38—48 Xn 38—48 1 7 4 0 5.3 22 120 450

GCYFTY-50—60 Xn 50~60 1 7 5 0 5.6 26 150 450

GCYFTY-62—72 Xn 62~72 1 7 0 6.2 33 180 450

GCYFTY-74—84 Xn 74—84 1 7 7 1 7.3 44 240 450

GCYFTY-76—96 Xn 76—96 1.7 8 0 7.3 44 240 450

Microcable Reference

Normal Duct Type Cable Microcable

Microcable Overview

Page 70: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 70

Comparison between Direct Buried/HDPE/Microduct

Tools and Accessories

Microduct Blowing Machine Microcable Blowing Machine

Air Compressor Microcable Coilpanel

Splicing Box

Splicing Box

Page 71: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 71

Comparison between Direct Buried/HDPE/Microduct

Blowing Installation method

Page 72: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 72

Comparison between Direct Buried/HDPE/Microduct

Blowing Installation method

Page 73: Huawei  Training for Dialog Reginal Staff-1

HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

35pt

: R153 G0 B0

:

FrutigerNext LT Medium

: Arial

32pt

: R153 G0 B0

黑体

22pt

) :18pt

黑色

:

FrutigerNext LT Regular

: Arial

20pt

):18pt

黑色

细黑体

Page 73

Comparison between Direct Buried/HDPE/Microduct

Advantage Disadvantage

Microdu

ct

Reduce the initial investment, and

easy for expansion.

Easy to upgrade the fiber cable type.

Fully utilize the existing duct

resource

Easy for branching.

Reduce manhole / handhole

quantities.

High requirement for the protection in

handhole and manhole.

Special tools needed for

implementation and maintainence.

Additional cost for microduct

The advantage is good for access

network and FTTx senario, but for

backbone network, it not obvious.

Proposal: HDPE with blowing installation method solution is proposed.

Depend on the requirement of SMC, Microduct & Microcable or conventional

cable can be considered to be installed inside HDPE duct.

Microduct vs. Traditional HDPE Duct