12
GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004 GLAST Large Area GLAST Large Area Telescope: Telescope: Performance & Safety Assurance Pat Lujan TEM & TEM-PS MRR – Part 3 LAT Senior Quality Engineer at General Technology Corporation (505) 345-5591 Ext. 3022 Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope

GLAST LAT ProjectTEM &TEM-PS Manufacturing Readiness Review – September 16, 2004 GLAST Large Area Telescope: Performance & Safety Assurance Pat Lujan TEM

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

GLAST Large Area Telescope:GLAST Large Area Telescope:

Performance & Safety Assurance

Pat Lujan

TEM & TEM-PS MRR – Part 3

LAT Senior Quality Engineer at General Technology Corporation

(505) 345-5591 Ext. 3022

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

2

Quality System RequirementsQuality System Requirements

General Technology Corporation (GTC) is Certified to ISO 9001:2000 and

AS9100-B in accordance with AIR5359B

GTC has provided a copy of their Quality Assurance Manual

(GTC-1000) Rev. B

– Applicable 2nd tier documents include:

• GTC-1007, Customer Supplied Product

• GTC-1008, Material and Product Identification

• GTC-1009, Process Control

• GTC-1010, Inspection and Testing

• GTC-1011, Calibration Control

• GTC-1013, Nonconformal Material and Product

• GTC-1014, Corrective and Preventive Action

• GTC-1015, Material Control

• GTC-1022, Quality Planning

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

3

TEM & TEM-PS Assemblies QA ActivitiesTEM & TEM-PS Assemblies QA Activities

TEM assembly vendor qualification A quality survey was performed June 15-16 at General Technology

Corp. in Albuquerque, New Mexico– Survey team included LAT QA and GSFC QE– No issues were identified

• Excerpt from Survey Report» “General Technology Corporation (GTC) has demonstrated

their ability to fabricate a flight worthy product through their process and quality controls.”

Technical Exchange Meeting took place at General Technologies on June 30th LAT QA, Electronics Engineering, and Manufacturing Engineering

met with General Technologies technical staff to review and discuss technical requirements

On-site Quality Assurance and source inspection LAT Quality Assurance Engineer will be on site, full time for

source inspection and oversight at General Technologies– Individual will participate in Technical Exchange Meetings– Full time throughout all phases of hardware assembly and test

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

4

Workmanship StandardsWorkmanship Standards

ESD GTC-2004 Electrostatic Discharge Sensitive (ESDS) Material

Handling Procedure for Protection of Electronic Parts and Assemblies

– MIL-STD-1686 Electrostatic Discharge Control Program– MIL-HDBK-263 Electrostatic Discharge Control Handbook

Training– All personnel who handle ESDS components are required

to complete an ESD training course– Annual training is provided and documented

Facilities– Work Stations equipped with means for operator to

connect with ground– Work Stations equipped with static dissipative work

surface and inspected on monthly basis

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

5

Workmanship StandardsWorkmanship Standards

IPC/EIA J-STD-001C Requirements for Soldered Electrical and Electronic Assemblies. Personnel trained and certified by in-house instructor.

IPC J-STD-001CS Space Applications Electronic Hardware Addendum to Requirements for Soldered and Electrical and Electronic Assemblies. Personnel trained and certified by in-house instructor.

NASA STD 8739.4 Crimping, Interconnecting Cables, Harnesses and Wiring. Individual operator certification to NASA STD is not

required. GTC’s internal workmanship standards have been approved.

– Excerpt from NASA QE Survey Report• “The criteria for implementing NASA 8739.4 can be included in

the statement of work and would require no further action.”

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

6

Inspection RequirementsInspection Requirements

GTC will perform Receiving Inspection, In-Process Inspections and

Final Inspections per their internal inspection plan and procedures.

SLAC Quality Assurance Engineer will approve plan prior to any

assembly activities

Mandatory Inspection Points (MIP’s) to be performed by SLAC Source

Inspector. MIP’s will be documented on GTC’s traveler and stamped

by the SLAC Source Inspector after the inspection/witness activity.

100% Prior to conformal coat

100% Post conformal coat

Witness of environmental test activities

Witness of functional and acceptance electrical test

Final Inspection and End Item Data Package review

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

7

Oversight and Surveillance ActivitiesOversight and Surveillance Activities

Surveillance

SLAC Source Inspector on-site full time with full access to all

production activities associated with GLAST.

– Conformance to drawing specifications, SOW, GTC

procedures and workmanship standards

– Polymeric material shelf life dates

– Adhesive mix records

– Mate/Demate logs

– Calibration records

– Torque Logs

– ESD

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

8

Oversight and Surveillance ActivitiesOversight and Surveillance Activities

Audits

SLAC Source Inspector has the right to conduct audits with prior

coordination with GTC.

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

9

MRB ProcessMRB Process

Documents

GTC-1013 Nonconforming Material and Product

GTC-2075 Process Specification, In-Process Material/Product

Nonconformance

NCMR Nonconformance Material/RMA report

Procedure

GTC will identify, segregate, document and report all parts, materials,

CCA’s and electronic assemblies/units which do not meet drawing or

specification requirements.

– Defects that can not be reworked using approved procedures

– Receipt of SLAC supplied material

– Failures or anomalies

– Nonconformances found at final Inspection

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

10

MRB ProcedureMRB Procedure

GTC will provide immediate notification to SLAC source inspector of NCMR initiated

– Description of nonconformance• Violation of drawing or specification• IS and S/B conditions

– Location by drawing reference zones

– Part number

– Serial number

– Quantity

– Corrective/Preventive Action as available SLAC Source Inspector will convene a MRB with SLAC within

24 hours

– Darren Marsh, LAT Performance Assurance

– Gunther Haller, LAT DAQ Subsystem Manager (or designee)

– LAT Manufacturing Engineering (as applicable)

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

11

MRB ProcedureMRB Procedure

Disposition– Quality Manager from GTC receives disposition

instructions from SLAC Source Inspector.• Use as Is

• Repair

• Scrap

GLAST LAT Project TEM &TEM-PS Manufacturing Readiness Review – September 16, 2004

12

End Item Data Package End Item Data Package

Certifications of Compliance for each assembly

Copies of travelers/shop orders

Nonconformance Reports

As-Built drawing and parts list

As-Built configuration record

In process and final test reports

End Item acceptance test data including environmental test

Inspection reports as applicable

Mate/Demate log for flight connectors

Digital Photos