Upload
reece-watkins
View
28
Download
0
Embed Size (px)
DESCRIPTION
Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Performance & Safety Assurance WBS: 4.1.A Darren S. Marsh Stanford Linear Accelerator Center Performance & Safety Assurance Manager [email protected]. Outline. Introduction Organization Requirements - PowerPoint PPT Presentation
Citation preview
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 1
GLAST Large Area Telescope:GLAST Large Area Telescope:
Performance & Safety Assurance WBS: 4.1.A
Darren S. MarshStanford Linear Accelerator CenterPerformance & Safety Assurance Manager
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 2
OutlineOutline
• Introduction• Organization• Requirements• Safety & Mission Assurance Program Reviews• Performance Assurance System• Workmanship & Inspection• Contamination Control• Nonconformance Reporting• Materials and Processes• Systems Safety
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 3
IntroductionIntroduction
• Performance & Safety Assurance is a program consisting of:– Quality Assurance
• Hardware• Software
– Systems Safety– EEE Parts Program– Materials & Processes Program– Contamination Control– Reliability & Risk Management Program– Design Verification– Technical Reviews
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 4
Performance Assurance Functional ResponsibilitiesPerformance Assurance Functional Responsibilities
FUNCTIONAL ELEMENT INSTITUTIONS (LEAD)
Hardware Quality SLAC (Marsh), GSFC (Kolecki), NRL (Virmani)
Flight Software Assurance SLAC (Sawyer)
Reliability Engineering
Continuous Risk Management
SLAC (Thurston, Horn)
SLAC (Marcellini, Horn)
EEE Parts Program NRL (Virmani)
Materials & Processes Program SLAC (Nordby, Tice)
Instrument Design Verification- Design Verification Planning- Analytical Design Verification- Functional Design Verification
SLAC (Horn)
SLAC (Klaisner)
SLAC (Bloom)
Systems Safety SLAC (O’Neill)
SLAC (Cullinan)
Configuration Management SLAC (Horn, Cramer)
Contamination Control
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 5
Performance & Safety Assurance RequirementsPerformance & Safety Assurance Requirements
LAT Documents
GLAST Project Office Documents
Requirements apply to all work by the LAT collaboration and their subcontractors and suppliers of deliverable space flight hardware and software
Contamination Control Plan
433 -PLAN -0010
LAT Mission Assurance Reqs 433 -MAR -0001
EEE Parts MGMT Plan
433 -PLAN -0004
LAT Flight S/W Mgmt. Plan
LAT -MD -00104
LAT Mechanical Parts Plan
LAT -SS -00107
LAT Quality Manual
LAT -MD -00091
Parts Program Control Plan
LAT -MD -00099
System Safety Program Plan
LAT -MD -00078
LAT Inst. Perf. Verification Plan LAT -MD -00408
Configuration Management Plan
LAT -MD -00068
LAT Contam. Control Plan
LAT -MD -00404
LAT Risk Mgmt. Plan
LAT -MD -00067
LAT Performance AssuranceImplementation Plan
LAT-MD- 00039
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 6
Safety & Mission Assurance Program ReviewsSafety & Mission Assurance Program Reviews
Fiscal Years
2000 2001 2002 2003 2004 2005 2006 2011
GLAST scheduled for launch in September 2006
BeginLAT I&T
CriticalDesignReview
PDR PER
PreShipReview
LAT ReadyFor S/C I&T
FABRICATION PHASE COMMISSIONINGPHASE
Build & TestFlight Units
ObservatoryI&T
Final DesignEngr’g Models
LAT I&T
Ops.
Prelim. & Sys. Design
Pre-PDR S&MA Survey
PDR Delta Baseline Review Pre-CDR S&MA
Survey
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 7
Results from GSFC Pre-PDR S&MA SurveyResults from GSFC Pre-PDR S&MA Survey
• Goddard Space Flight Center (GSFC) Office of System Safety and Mission Assurance (OSSMA) performed a survey of the LAT Program April 3-4, 2001– The goal of the survey was to evaluate the status of the
LAT Safety & Mission Assurance Program and give GSFC and LAT personnel the opportunity to discuss Safety & Mission Assurance documentation
– The SLAC survey did not result in any “Findings”, there were nine “Observations” and two “Commendations”
• Nearly all the recommendations identified in the survey were addressed– Documentation updated to reflect comments provided– Secured the necessary expertise in specific disciplines
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 8
Results from PDR/Baseline ReviewsResults from PDR/Baseline Reviews
Findings from January 2002 PDR/Baseline Review:• The Committee concluded that Performance & Safety
Assurance was at PDR level and recommended baselining• One RFA was generated from the review
– Describe the LAT Metrology Program (S. Scott)• LAT Quality Procedure LAT-MD-00470, Inspection,
Measuring & Test Equipment, has been established to ensure that monitoring and measurement can be carried out and are carried out in a manner that is consistent with the monitoring and measurement requirements
Findings from the July 2002 Delta PDR/Baseline Review:• The Committee reaffirmed the decision to baseline the
Performance & Safety Assurance subsystem• No RFAs were identified for Performance Assurance
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 9
Results from GSFC Pre-CDR S&MA SurveyResults from GSFC Pre-CDR S&MA Survey
• Goddard Space Flight Center (GSFC) Office of System Safety and Mission Assurance (OSSMA) performed a survey of the LAT Program December 10-11, 2002 – The goal of the survey was to evaluate the status of the
LAT Safety & Mission Assurance Program and to assess the program’s readiness for the LAT CDR
– The SLAC survey did not result in any “Findings”, there were eight “Observations”
• Excerpt from the Survey Closeout Report– “It is the conclusion of this survey team that the LAT
Performance and Safety Assurance Program is CDR ready.”
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 10
LAT Performance Assurance SystemLAT Performance Assurance System
• LAT Performance Assurance Implementation Plan (PAIP), LAT-MD-00039, released and approved by GSFC
– Requirements for performance assurance elements are defined• LAT Quality Manual, LAT-MD-00091, completed and released
– LAT Quality Management System (QMS) is established, documented, implemented and aligned with the requirements of ISO 9001
• Documentation to ensure the effective planning, operation and control of assurance activities
– Configuration Management Plan, LAT-MD-00068– LAT EEE Parts Program Control Plan, LAT-MD-00099– LAT Contamination Control Plan, LAT-MD-00404– LAT Flight Software Management Plan, LAT-MD-00104– LAT Mechanical Parts Plan, LAT-SS-00107– LAT Continuous Risk Management Plan, LAT-MD-00067– LAT Instrument Performance Verification Plan, LAT-MD-00408
GOAL IS CONFORMANCE TO REQUIREMENTS
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 11
Performance Assurance ActivitiesPerformance Assurance Activities
• Collaborator/Supplier Surveillance Activities– Surveys of collaborators and key suppliers to evaluate
ability to produce quality flight hardware and ensure project requirements are met
– Review and approve specifications, travelers/work orders and NCRs
– Perform on-site source inspections to monitor or witness fabrication, assembly and/or integration & test activities
• Ensure contamination control requirements are met• Compliance to ESD requirements• Review travelers/routers, fabrication and workmanship
procedures• Equipment calibration review• Material handling and shelf life material storage
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 12
Fabrication, Assembly, Integration and Test ProcessFabrication, Assembly, Integration and Test Process
• Production Readiness Review (PRR)– Review of detailed fabrication and assembly plan using completed
drawings, process, tooling, and in-process test procedures• Fabrication, Assembly, Integration
– All work will be conducted in a controlled manner so that end item conforms to requirements
• Test Readiness Review– Evaluate the planned test/calibration program and test flow to assure
that it meets program needs• Comprehensive Performance Test Activities
– Instrument Performance Verification Plan, LAT-MD-00408, released and approved
– LAT Environmental Specification, LAT-SS-00788, released and approved
– Requirements traceability/verification matrix
Comprehensive Performance
Test Activities
Production Readiness
Review
Fabrication,Assembly,Integration
Test Readiness
Review
Test Readiness
Review
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 13
Delivery & Acceptance ProcessDelivery & Acceptance Process
• Pre-Ship Review– Assure the design of the item has been validated through
the environmental qualification and/or acceptance test program, that all open items have been dispositioned
• Flight Unit Delivery– Plans for shipping container, environmental control and
mode of transportation developed• Post-Ship Acceptance Test
– Verifies functionality of delivered hardware to integrator
Pre-Ship Review
Deliver Hardware to Integration
Site
Post Ship Acceptance
Test
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 14
Workmanship and Process ControlWorkmanship and Process Control
• LAT personnel working on flight hardware will be trained and certified to the following standards (or equivalent approved ESA standards):– NASA-STD-8739.1, Workmanship Standard for Staking and
Conformal Coating of Printed Wiring Boards and Electronic Assemblies
– NASA-STD-8739.2, Workmanship Standard for Surface Mount Technology
– NASA-STD-8739.3, Requirements for Soldered Electrical Connections
– NASA-STD-8739.4, Requirements for Crimping, Interconnecting Cables, Harness, and Wiring
– NASA-STD-8739.7, Electrostatic Discharge Control
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 15
Workmanship & Inspection Requirements Workmanship & Inspection Requirements
• A work order/traveler will define the steps for QA inspection– Quality records will be maintained and reviewed
• Mandatory inspections points (MIP) will be performed for integration & test at predefined inspection points– To screen out defects caused by workmanship, design,
assembly, etc.– To prevent unacceptable products from entering the next
stage of production– A final inspection verified that the hardware/software
deliverables meet requirements and are properly documented
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 16
Contamination ControlContamination Control
• Cleanroom environments– LAT assembly, integration & test activities will be
performed in class 100,000 environment– LAT personnel are trained in contamination control
• Monitoring, recording, and inspections– Continuous temperature, %RH, and multiple port airborne
particle count monitoring– Fallout witness plates, tape lifts, and/or NVR solvent
rinses/swabs are planned– Visual inspections of hardware and cleaning as required
prior to each closeout activity• LAT Contamination sensitive hardware (calorimeter, tracker,
and ACD) shall meet Level 750B surface cleanliness per MIL-STD-1246
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 17
Contamination Control (Con’t.)Contamination Control (Con’t.)
• Additional requirements– Calorimeter Cesium Iodide crystals shall not be exposed to
>45% relative humidity– ACD photomultiplier tubes are shall not be exposed to
excessive helium levels as specified in LAT Contamination Control Plan
• Atmosphere Control using GN2 and/or dry air– ACD requires purge if measured helium levels exceed 10
ppm• GN2 will be filtered and certified to Grade B, 99.99%
pure per MIL-P-27401– Dry air flow to calorimeter as required will limit Cesium
Iodide crystals exposure to humidity < 45% RH
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 18
Contamination Control (Con’t)Contamination Control (Con’t)
• Materials selection– Select materials that satisfy outgassing of ≤ 1% TML and ≤
0.1% CVCM• Bakeout
– Plan is to do a vacuum bakeout of LAT at 40˚C at start of thermal-vacuum test
– The parameters of subsystem or component bakeouts (e.g., temperature, duration, and pressure) will be individualized depending on materials used, the fabrication environment, and the established contamination allowance.
– Required thermal vacuum testing of flight hardware shall be performed and outgassing rates shall be monitored to achieve required outgassing levels
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 19
Nonconformance ReportingNonconformance Reporting
• All nonconformances will be reported through a nonconformance & corrective action (NCR/CA) system – The LAT will ensure that product which does not conform
to requirements is identified and controlled to prevent its unintended use or delivery
– Action will be taken to eliminate the cause of nonconformance in order to prevent recurrence
– Close-out of all nonconformance reports shall be verified• Work stopped until the nonconformance is reviewed and
dispositioned by Material Review Board (MRB)– Records of the nature of nonconformities and any
subsequent action taken, including concessions obtained, shall be maintained
– When nonconforming product is corrected it shall be subject to re-verification to demonstrate conformity to the requirements
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 20
Nonconformance Reporting ProcessNonconformance Reporting Process
Nonconformances will be reported to GSFC in accordance with MAR requirements
TKR CAL ACD ELEX MECH
End Item/Traveler Data Package
Program Records Database
IPO
LAT IOCOperations
End Item DataPackage
MR
B
MR
B
MR
B
MR
B
MR
B
Operations Data
FR
B
FR
B
Observatory
End Item DataPackage
FR
B
GLAST ProjectOffice
ObservatoryOffice
NC
R/C
A
NC
R/C
A
NC
R/C
A
NC
R/C
A
NC
R/C
A
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 21
LAT Materials and PartsLAT Materials and Parts• Material requirements
– Source: 433-MAR-0001, “Mission Assurance Requirements”
– LAT: LAT-SS-00107-01, “Mechanical Parts Plan”
• Material Usage Agreement (MUA) needed for non-compliant materials
– All materials have been assessed by GSFC materials branch to be compliant to standards and used in conventional methods
– Currently the project requires no MUA’s
• Relevant procedures and guidelines for material selection
– Metallic Materials for Stress Corrosion Cracking Resistance in Sodium Chloride Environment (MSFC-STD-3029)
– Fastener Integrity Requirements (541-PG-8072.1.2)
– Standard Test Method for Total Mass Loss and Collected Volatile Condensable Materials for Outgassing (ASTM-E-595)
SubmittedSLAC IPO Accepted
GSFC Approved
Pending
ACD 97 97 97 0CAL 48 48 48 0Elec 24 22 22 2I & T 0 0 0 TBDMech 114 113 113 1TKR 57 48 48 9Total 340 328 328 12
Total Materials Count on LAT M&P ListTotal Materials Count on LAT M&P List
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 22
LAT M&P List: Inorganic, Polymer and Composite MaterialsLAT M&P List: Inorganic, Polymer and Composite Materials
• Inorganic materials– Inorganic materials submitted to LAT IPO
as of 29 April 2003• Polymers and Composites
– Polymer and composite materials submitted to LAT IPO as of 29 April 2003
Inorganic Materials
SubmittedSLAC IPO Accepted
GSFC Approved
Pending
ACD 36 36 36 0CAL 13 13 13 0Elec 6 4 4 2I & T 0 0 0 TBDMech 74 74 74 0TKR 19 19 19 0Total 148 146 146 2
Inorganic Materials Count on LAT M&P ListInorganic Materials Count on LAT M&P List
Polymer and Composite Materials
SubmittedSLAC IPO Accepted
GSFC Approved
Pending
ACD 47 47 47 0CAL 29 29 29 0Elec 12 12 12 0I & T 0 0 0 TBDMech 25 24 24 1TKR 33 24 24 9Total 146 136 136 10
Polymer and Composite Materials Count on LAT M&P ListPolymer and Composite Materials Count on LAT M&P List
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 23
LAT M&P List: Lubricants and ProcessesLAT M&P List: Lubricants and Processes
• Lubricants– Lubricants used only in static applications,
largely for bolts– No moving parts within the LAT– Lubricants submitted to LAT IPO as of 29
April 2003• Processes
– M & P list collects process information for all heat treating and surface treatment processes
– Processes submitted to LAT IPO as of 29 April 2003
Lubricants
SubmittedSLAC IPO Accepted
GSFC Approved
Pending
ACD 1 1 1 0CAL 0 0 0 0Elec 2 2 2 0I & T 0 0 0 TBDMech 4 4 4 0TKR 2 2 2 0Total 9 9 9 0
Lubricant Count on LAT M&P ListLubricant Count on LAT M&P List
Processes
SubmittedSLAC IPO Accepted
GSFC Approved
Pending
ACD 13 13 13 0CAL 6 6 6 0Elec 4 4 4 0I & T 0 0 0 TBDMech 11 11 11 0TKR 3 3 3 0Total 37 37 37 0
Processes on LAT M&P ListProcesses on LAT M&P List
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 24
Materials List Pending ItemsMaterials List Pending Items
• Pending items as of 29 April 2003• Reasons for status
– Specific material not yet chosen– Waiting for “TBD’s” to be filled in– Outgassing testing in progress
• Mechanical Parts Review Board will evaluate materials once missing information is collected from test results or work with manufacturer
• Final step is to validate materials list– Cross-check against drawing list– Check for missing materials and processes
Materials Pending Approval
Material ID is TBD
Lacking Info for
Approval
Needs Qual
Testing
Change Material
Tested for Out-gassing
Total Pending
ACD 0 0 0 0 0 0CAL 0 0 0 0 0 0Elec 0 2 0 0 0 2I & T TBD TBD TBD TBD TBD TBDMech 0 1 0 0 0 1TKR 0 0 0 0 9 9Total 0 3 0 0 9 12
Materials Pending Materials Branch ApprovalMaterials Pending Materials Branch Approval
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 25
Systems SafetySystems Safety
• The purpose of the LAT Systems Safety Program is to identify the hazards of the LAT and impose design requirements and establish controls to reduce the associated risk to acceptable levels.
• Established and implemented System Safety Program Plan (SSPP), LAT-MD-00078
– Complies with EWR 127-1, Eastern and Western Range Safety Requirements
– LAT Preliminary Hazard Analysis, LAT-MD-00366
• Identifies safety critical areas, assesses risk, and establishes requisite hazard controls
– LAT Operating and Support Hazard Analysis, LAT-MD-01968
• Evaluates activities for hazards or risks introduced into the system by operational and support procedures and evaluates the adequacy of operational and support procedures used to eliminate, control, or abate identified hazards or risks.
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 26
LAT Hazard AnalysisLAT Hazard Analysis
17Hazardous MaterialsMechanical damage to
calorimeterCalorimeter
10Hazardous MaterialsRupture of heat pipesMechanical
8CollisionStructural failureMechanical
8Electrical Electrical short circuit or overloadElectronics
RAV*Hazards GroupHazardsSubsystem
Risk Priority: Unacceptable Undesirable (Acceptable With Proper Controls) Operation Permissible
• Hazard controls have been identified and established • Verification of hazard controls will be on-going
*The Risk Assessment Value (RAV) is derived from MIL-STD-882D, Standard Practices for System Safety.
GLAST LAT Project CDR/CD3 Review May 12-16, 2003
Document: LAT-PR-01967 Section 17 27
LAT Operating and Support Hazard AnalysisLAT Operating and Support Hazard Analysis
ElectricalElectromagnetic interfaceElectronics
ElectricalElectrostatic dischargeElectronics
OccupationalPersonnel contact with sharp edges, pinch points, or rotating fixtureALL
8CollisionStructural failure or improper use of MGSEI&T
10Electrical
Power distribution system overload or short circuits
I&T Electronics
RAV*Hazards GroupHazardsSubsystem
10
10
10
• All hazard identified in Preliminary Hazard Analysis apply to
Operating and Support Hazard Analysis
*The Risk Assessment Value (RAV) is derived from MIL-STD-882D, Standard Practices for System Safety.
Risk Priority: Unacceptable Undesirable (Acceptable With Proper Controls) Operation Permissible