Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
3. CIVIL AND STRUCTURAL WORKS
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
3.1 SCHEME GENYEM HPP1 Maximum Generation Flow.
The maximum design generation flow shall be the flow through
the scheme which is necessary to produce the Contractor’s
guaranteed power output (i.e., with all generating equipment
operating), taking account of the available gross head, hydraulic
losses, compensation flow, turbine efficiency, generator
efficiency and transformer / switchyard efficiency.
13 m3/sec Confirmed
2 Compensation flow (not less than 0.50 m³/s) Addendum No.1 item No.10
and item No.14.
0.50 m3/sec Confirmed
3 Full supply level El. 414.5 masl. El. 414.5 masl. Confirmed
4 Minimum operating level El. 412.0 masl. Confirmed
5 Turbine runner centreline level El. 215.0 masl. Confirmed
6 Tailrace operating level at max generation flow El. 219.0 masl. El. 219.0 masl. Confirmed
7 Gross head 195.5 m. 195.5 m Confirmed
8 Net Head:
Condition (i) Maximum generation flow, with river level at weir
crest level.
190.80 m Confirmed
PT. PLN (PERSERO) Page 7C - 1 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
Condition (ii) Minimum generation flow with river level at weir
crest level.
Condition (iii) Maximum generation flow with design flood.
188.30 m
194.86 m
Confirmed
Confirmed
9 Water Hammer and Surge Hydraulic Analysis:
The results of the analyses shall be presented to the Employer in
both numerical and graphical format. The graphical formats shall,
as a minimum, show the surge pressures / wave heights that are
developed in the penstock, tunnel, surge chamber and headrace
with respect to time for the following conditions:
i) Water hammer analysis to determine the maximum and
minimum water pressure in the headrace, tunnel, surge
chamber, and penstock resulting from a sudden shut down of
all the generating equipment operating at the maximum
generation flow, with:- The head pond water level at the full supply level.
- The head pond water level at the maximum flood level.
ii) Water hammer analysis to determine the maximum and
minimum water pressure in the headrace, tunnel, surge
chamber, and penstock resulting from a normal start-up of all
the generating equipment to the maximum generation flow,
with the head pond water level at the full supply level.
iii) Surge analysis to determine the maximum height of the
surge wave in the headrace, tunnel, and surge chamber
resulting from a sudden shut down of all the generating
equipment operating at the maximum generation flow, with:- The head pond water level water level at the full supply
Part 1, Sub-Clause 1.28.6.5
Complies with Employer’s
Requirements as specified
in the Bid Document
Complies with Employer’s
Requirements as specified
in the Bid Document
Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
Confirmed, description at
detailed design stage
Confirmed, description at
detailed design stage
PT. PLN (PERSERO) Page 7C - 2 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
level.- The head pond water level at the maximum flood level.
iv) Surge analysis to determine the maximum height of the
negative surge wave in the headrace, tunnel and surge
chamber resulting from a normal start-up of all the generating
equipment to the maximum generation flow, with the
headpond water level at the full supply level.
Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
10 Provide / attach flood rating curves for the Sermo River at the:
i) Weir
ii) Powerhouse
Attachment No.1:
Curve Rating at Weir or
Intake at Sermo River
Attachment No.2:
Curve Rating at Power
House at Sermo River
Confirmed
Confirmed
3.2 WEIR Part 1, Sub-Clause 1.28.7.2
1 Weir type Gravity Confirmed
2 Construction materials Stone masonry Confirmed
3 Crest level (not greater than El. 415.0 masl) El. 414.50 masl Confirmed
4 Crest length 50 m Confirmed
5 Design flood event Part 1, Sub-Clause 1.28.7.2 d)
(i)
500 years ARI Confirmed
PT. PLN (PERSERO) Page 7C - 3 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
6 Flood capacity 2,030 m3/sec Confirmed
7 Sluice gate type Part 4, Sub-Clause 4.3 Radial gate Confirmed
8 No. of sluice gates 1 no. Confirmed
9 Sluice gate opening dimensions 3.00m x 2.00m Confirmed
10 Sluice gate actuating equipment type (attach description) Part 4, Sub-Clause 4.3.11 Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
11 Sluice gate bulkhead dimensions 3.40m x 2.50m Confirmed
12 Sluice gate bulkhead actuating equipment type (attach
description)
Addendum No.1 item No.63.
Part 4, Sub-Clause 4.3.11
Complies with Addendum
No.1 and Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
13 Compensation flow bypass arrangements (provide description) Addendum No.1 item No.10
and item No.14. Valves see
Part 1, Sub-Clause 1.29.6.5
Complies with Addendum
No.1 and Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
3.3 RIVER INTAKE Part 1, Sub-Clause 1.28.7.3
1 Intake type Front Type Confirmed
2 Invert level El. 409.00 masl Confirmed
PT. PLN (PERSERO) Page 7C - 4 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
3 Submergence at normal head pond operating level
(El.415.0 masl)
8.10 m Confirmed
4 Submergence at minimum head pond operating level 5.60 m Confirmed
5 No. of intakes 1 no. Confirmed
6 Intake operating dimensions 7.50m x 3.00m Confirmed
7 Intake capacity 13.50 m3/sec
At normal operating level.
Confirmed
8 Intake gate type Part 4, Sub-Clause 4.2 Sliding gate Confirmed
9 No. intake gates 2 nos. Confirmed
10 Intake gate opening dimensions 3.65m x 3.00m (2 unit) Confirmed
11 Intake gate actuating equipment type (attach description) Addendum No.1 item No.63.
Part 4, Sub-Clause 4.3.11.
Complies with Addendum
No.1 and Employer’s
Requirements as specified
in the Bid Document
Confirmed
12 Intake bulkhead type Part 4, Sub-Clause 4.2 Structural steel Confirmed
13 No. of intake bulkheads 2 nos. Confirmed
14 Intake bulkhead dimensions 3.70m x 3.00m Confirmed
PT. PLN (PERSERO) Page 7C - 5 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
15 Intake bulkhead actuating equipment type (attach description) Addendum No.1 item No.63.
Part 4, Sub-Clause 4.3.11.
Complies with Addendum
No.1 and Employer’s
Requirements as specified
in the Bid Document
Confirmed
16 Intake screen inclination (angle to horizontal) Part 4, Sub-Clause 4.4 85 degrees (max) Confirmed
17 Intake screen overall dimensions 7.50m x 3.00m Confirmed
18 Intake screen clear bar spacing 50 mm Confirmed
19 Intake screen bar type Square Confirmed
20 Mechanical screen cleaner type / capacity (attach supporting
brochure and technical data relating to screen cleaner)
Part 4, Sub-Clause 4.5 Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
By Pass Valve ???
3.4 DE-SEDIMENTATION BASIN Part 1, Sub-Clause 1.28.7.5
1 De-sedimentation basin type - Confirmed, description at
detailed design stage
2 Construction materials Stone masonry Confirmed
3 Capacity 13.50 m3/sec Confirmed
4 Design flow velocity 1.40 m/sec Confirmed
5 Gradient of invert of de-sedimentation basin (V:H) 0.0465 Confirmed
PT. PLN (PERSERO) Page 7C - 6 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
6 Dimensions Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
7 Spillway length 73.10 M Confirmed
8 Spillway capacity 13.50 m3/sec
At normal operating level
Confirmed
9 Sluice gate type Part 4, Sub-Clause 4.2 Sliding gate Confirmed
10 Sluice gate capacity (at normal operating level) 2 x 6.75 m3/sec Confirmed
11 No. of sluice gates 2 nos. Confirmed
12 Sluice gate dimensions 6.75m x 4.00m Confirmed
13 Sluice gate actuating equipment type (attach description) Addendum No.1 item No.63.
Part 4, Sub-Clause 4.3.11.
Complies with Addendum
No.1 and Employer’s
Requirements as specified
in the Bid Document
Confirmed
14 Invert level of sluice gates El. 409.00 – 405.60 masl Confirmed
3.5 HEADRACE CULVERT Part 1, Sub-Clause 1.28.7.6
1 Headrace type Rectangular Confirmed
PT. PLN (PERSERO) Page 7C - 7 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
2 Construction material Reinforced concrete Confirmed
3 Capacity 13.00 m3/sec Confirmed
4 Maximum velocity 1.445 m/sec Confirmed
5 Gradient (V:H) 0.0023 Confirmed
6 Dimensions 3.00m x 3.00m Confirmed
7 Soffit level immediately downstream of intake El. 405.50 masl Confirmed
8 Soffit level at upstream tunnel portal El. 409.00 masl Confirmed
9 Headrace culvert intake screen inclination (angle to horizontal) 85 degrees (max) Confirmed
10 Headrace culvert intake screen overall dimensions 3.00m x 3.00m Confirmed
11 Headrace culvert intake screen clear bar spacing 30 mm Confirmed
12 Headrace culvert intake screen bar type Square Confirmed
3.6 TUNNEL AND SURGE SHAFT Part 1, Sub-Clause 1.28.7.7
1 Minimum tunnel dimensions 3.00 m Confirmed
2 Capacity 13.00 m3/sec Confirmed
3 Maximum velocity 1.7015 m/sec ConfirmedPT. PLN (PERSERO) Page 7C - 8 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
4 Tunnel gradients (V:H) 0.0010 Confirmed
5 Tunnel soffit level at surge shaft location El. 404.00 masl Confirmed
6 Surge shaft finished internal diameter 8.00 m Confirmed
7 Surge shaft throttle diameter 2.00 m Confirmed
8 Ground elevation at surge shaft El. 426.00 masl Confirmed
9 Tunnel lining internal diameter: - Section 1, from 0.00 m to 150 m,
- Section 2, from 150 m to 1,500 m,
- Section 3, from 1,500 m to 1,779 m.
3.00 m
3.00 m
2.25 m
Confirmed
Confirmed
Confirmed
10 Tunnel lining soffit levels:- Section 1, from 0.00 m to 150 m,
- Section 2, from 150 m to 1,500 m,
- Section 3, from 1,500 m to 1,779 m.
El. 405.50 masl
El. 405.15 masl
El. 404.09 masl
Confirmed
Confirmed
Confirmed
11 Tunnel concrete wall thickness- Section 1, from 0.00 m to 150 m,
- Section 2, from 150 m to 1,500 m,
- Section 3, from 1,500 m to 1,779 m.
0.35 m
0.25 m
0.50 m
Confirmed
Confirmed
Confirmed
12 Tunnel lining material type and properties:- Section 1, from 0.00 m to 150 m,
- Section 2, from 150 m to 1,500 m,
- Section 3, from 1,500 m to 1,779 m.
Reinforced concrete
Reinforced concrete
Steel can
Confirmed
Confirmed
Confirmed
PT. PLN (PERSERO) Page 7C - 9 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
13 Steel door at Surge Tank Canopy Addendum No.1 (item No.66) Complies with Addendum
No.1 (item No.66)
Confirmed, description at
detailed design stage
14 Penstock Inspection Manhole Addendum No.1 (item No.67) Complies with Addendum
No.1 (item No.67)
Confirmed, description at
detailed design stage
15 Steel Gate at Junction of Inspection Adit and Tunnel Addendum No.1 (item No.68) Complies with Addendum
No.1 (item No.68)
Confirmed, description at
detailed design stage
3.7 PENSTOCK Part 1, Sub-Clause 1.28.7.8
1 No. penstocks / Type 1 no. / Surface type Confirmed
2 Penstock(s) capacity 13.00 m3/sec Confirmed
3 Penstock internal diameter: - Section 1, from 1,511.5 m to 1,770 m,
- Section 2, from 1,770 m to 2,310 m.2.25 m
2.25 m
Confirmed
Confirmed
4 Penstock soffit levels:- Section 1, from 1,511.5 m to 1,770 m,
- Section 2, from 1,770 m to 2,310 m.El. 398.00 m
El. 229.00 m
Confirmed
Confirmed
5 Penstock wall thickness- Section 1, from 1,511.5 m to 1,770 m,
- Section 2, from 1,770 m to 2,310 m.20 mm
20 mm
Confirmed
Confirmed
6 Penstock material type and properties:
PT. PLN (PERSERO) Page 7C - 10 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
- Section 1, from 1,511.5 m to 1,770 m,
- Section 2, from 1,770 m to 2,310 m.ASTM-A516, Grade 60
ASTM-A516, Grade 60
Confirmed
Confirmed
7 Penstock external coating type: - Section 1, from 1,511.5 m to 1,770 m,
- Section 2, from 1,770 m to 2,310 m.Polyurethane
Polyurethane
Confirmed
Confirmed
8 Penstock internal coating type: - Section 1, from 1,511.5 m to 1,770 m,
- Section 2, from 1,770 m to 2,310 m.Epoxy
Epoxy
Confirmed
Confirmed
9 Penstock Guard Valve House Part 1, Sub-Clause 1.28.7.12 Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed
3.8 POWER STATION AND TAILRACEPart 1, Sub-Clause 1.28.7.9
and Sub-Clause 1.28.7.10
1 Power station platform levels:- Loading / erection bay
- Switchgear floor
- Generator floor
- Turbine floor
- Drainage gallery and sump
El. 221.30 masl
El. 220.50 masl
El. 220.50 masl
El. 215.50 masl
El. 212.90 masl
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
2 Design flood event 500 years ARI Confirmed
3 Design flood flow 2,060 m3/sec Confirmed
4 Design flood level El. 219.00 masl Confirmed
PT. PLN (PERSERO) Page 7C - 11 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
5 Tailrace bulkhead type Part 4, Sub-Clause 4.2 Structural steel Confirmed
6 No. of tailrace bulkheads 2 nos. Confirmed
7 Sluice gate actuating equipment type (attach description) Addendum No.1 item No.63.
Part 4, Sub-Clause 4.3.11.
Complies with Addendum
No.1 and Employer’s
Requirements as specified
in the Bid Document
Confirmed
8 Tailrace bulkhead opening dimensions 4.50m x 1.30m Confirmed
9 Workshop and Office facilities minimum guaranteed floor area:- Electrical/mechanical workshop
- Electronic workshop
- Main store
- Oil store
- Chemical store
- Hazardous goods store
- Managers office
- Engineering office
- Control room
- Formal reception and secretary office
- Eating and kitchen area
- Medical/first aid facility
- Food/utilities/office store
- Changing room
Part 1, Sub-Clause 1.28.7.9
- 30 m2
-
- 30 m2
- 20 m2
- 12 m2
- 12 m2
- 30 m2
- 40 m2
- 35 m2
- 45 m2
- 25 m2
- 25 m2
- 30 m2
- 40 m2
Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
3.9 SWITCHYARD1 Switchyard area
PT. PLN (PERSERO) Page 7C - 12 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
- Area
- Stone surfacing 15 cm thickness
16.0m x 12.0m
15 cm thickness
Confirmed, description at
detailed design stage
Confirmed
2 Fencing- Security Fencing
- Other Fencing
Part 2, Sub-Clause 2.14.1
Sub-Clause 2.14.1.1
Sub-Clause 2.14.1.2
60.0m length
150.0m length
(around the Power House)
Confirmed
Confirmed
3 Cable Ducting Part 2, Sub-Clause 2.14.2 Complies with Employer’s
Requirements as specified
in the Bid Document
Confirmed, description at
detailed design stage
3.10 ROAD WORKS AND BRIDGES Part 2, Sub-Clause 2.4
1 Access road to weir / intake area:- Length
- Finished width
- Access road surface type
- Parking / turning area at weir / intake
- Parking / turning area surface type
1,100 m
6.00 m
Asphalt pavement 50 mm
940.00 m2
Asphalt pavement 50 mm
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
2 Access road to tunnel access adit:- Length
- Finished width
- Access road surface type
- Parking / turning area at weir / intake
- Parking / turning area surface type
600.00 m
6.00 m
Permanent unsealed
200.00 m2
Confirmed
Confirmed
Confirmed
Confirmed
PT. PLN (PERSERO) Page 7C - 13 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
3 Access road to surge tank:- Length
- Finished width
- Access road surface type
- Parking / turning area at weir / intake
- Parking / turning area surface type
300.00 m
6.00 m
Permanent unsealed
900.00 m2
Permanent unsealed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
4 Access road to penstock guard valve:- Length
- Finished width
- Access road surface type
- Parking / turning area at penstock guard valve
- Parking / turning area surface type
150.00 m
6.00 m
Permanent unsealed
Permanent unsealed
-
Confirmed
Confirmed
Confirmed
Confirmed
5 Access road to powerhouse:- Length
- Finished width
- Access road surface type
- Parking / turning area at power house
- Parking / turning area surface type
1,000 m
6.00 m
Asphalt pavement 50 mm
1,518 m2
Asphalt pavement 50 mm
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
3.11 CONSTRUCTION EQUIPMENT Section 7, Schedule of
Qualification, Sub-Clause 7.1
General construction equipment shall not be less than the
following:- Hydraulic excavator (backhoe) (minimum capacity 150 kW)
- Mobile Crane of sufficient lifting capacity for construction of
the works
- Dump truck (minimum capacity 6 cubic metres)
3 nos. (minimum)
6 nos. (minimum)
4 nos.
1 nos.
7 nos.
Confirmed
Confirmed
Confirmed
PT. PLN (PERSERO) Page 7C - 14 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
- Tracked bulldozer (minimum capacity 100 kW)
- Concrete batching plant (5 m3/h minimum capacity)
- Transmission Line and Switchyard/ Substation Construction
Equipment (Bidders shall provide details of all transmission
line and switchyard/substation construction equipment
including transmission line conductor stringing equipment):
Motor string
Messenger wire
Swivle
Tackle wheel dia.400mm
Temporary anchor
Dynamo meter
Handy Talky
Drum support
3 nos. (minimum)
2 nos. (minimum)
4 nos.
2 nos.
2 nos.
3 nos.
3 nos.
60 nos.
8 nos.
2 nos.
4 nos.
3 nos.
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
2 Tunnelling Equipment. Bidders shall provide details of all
tunnelling equipment to be provided for the construction of the
Works including:
- Equipment for excavating the tunnel effectively in the ground
conditions to be encountered at the progress rates necessary
to complete the work within the specified time of completion.
- Equipment for removal and disposal of materials (spoil)
excavated from the tunnel.
- Pressure grouting equipment for fracture grouting,
consolidation grouting, contact grouting, backfill grouting, etc.
- Shotcreting equipment.
- Equipment for forming steel ribs and lattice girders for tunnel
support.
- Water collection and pumping equipment to handle ground
3 nos.
2 nos.
3 nos.
4 nos.
3 nos.
2 nos.
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
Confirmed
PT. PLN (PERSERO) Page 7C - 15 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
No Description Employer’s Requirement
(Section 4)
Bidder’s Data Remarks
water and storm water that enters the tunnel during its
construction.
- Blower / Exhaust fan 8 nos. Confirmed
4. REQUIRED BID DRAWINGS
The Bidder shall provide, as a minimum, the following drawings with his Bid:
N
o
Employer’s Requirement Bidder’s Data
[drawing (s)]
Remarks
1 General Layout and Long-Section (1) 1 GN-HEPP-C-002
2 Additional Land Acquisition Plan (1) (if required)
3 Diversion Weir, Spillway and Intake Plan, Sections and Typical Details (2) 2 GN-HEPP-C-001 and GN-HEPP-C-003
4 De-Sedimentation Basin Plan, Sections and Typical Details (1) 1 GN-HEPP-C-004
5 Headrace Culvert Plan, Sections and Details (1) 1 GN-HEPP-C-007
PT. PLN (PERSERO) Page 7C - 16 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
6 Tunnel, Portal, Side Adit and Surge Shaft, Plan, Sections and Details including tunnel
support (2)
6 GN-HEPP-C-008, GN-HEPP-C-009,
GN-HEPP-C-010, GN-HEPP-C-011,
GN-HEPP-C-012, GN-HEPP-C-013
7 Penstock Plan, Sections and Typical Details (1) 4 GN-HEPP-C-014 Rev-1, GN-HEPP-C-015,
GN-HEPP-C-016, GN-HEPP-C-017
8 Powerhouse and Tailrace Plan and Sections (2) 1 GN-HEPP-C-018
9 Powerhouse Superstructure and Administration Building - Elevations and Sections (showing
the proposed architectural designs)
3 GN-HEPP-C-019 Rev-1, GN-HEPP-C-020a,
GN-HEPP-C-020
10 Access Road and Drainage Plan, Long - Section and Typical Details (4) 2 GN-HEPP-C-021 and GN-HEPP-C-023
11 Drawings showing main features and dimensions of all plant offered together with clearances
required for installation, operation and generator rotor removal.
3 GXED-001, GXED-002, GXED-003
12 Drawing showing hydraulic gradients for steady state and extreme hydraulic conditions for
the whole system from the intake to the power house, (refer to Section 4, Part 5, Clause 1.8
– Hydraulic Transients) in particular:
(a) Sudden shut down of all the generating equipment operating at the maximum
generation flow with the head pond water level at full supply level.
(b) Sudden shut down of all the generating equipment operating at the maximum
generation flow with the head pond water level at maximum flood level.
(c) Normal start-up of all the generating equipment to the maximum generation flow, with
the head pond water level at the full supply level.
2 GN-HEPP-C-022 and GN-HEPP-C-024
13 Contractor’s site establishment, including contractor’s office, workshops and temporary
construction establishment, Employer’s office, temporary access roads, etc.
4 GN-HEPP-TW-001, GN-HEPP-TW-002, GN-
HEPP-TW-003, GN-HEPP-TW-004
PT. PLN (PERSERO) Page 7C - 17 April 08
Renewable Energy Development Sector Project Contract Discussion Agreement
Genyem Hydro Power Project
14 Disposal areas for excavated materials. 1 GN-HEPP-C-025
15 Contractor’s proposed construction implementation schedule. 1 GN-HEPP-C-026-1 to C-026-4
Note:
Drawings shall show all major structure levels, diameters, dimensions, sizes, thicknesses, water levels, etc., in sufficient detail to enable a technical
evaluation of the hydraulic adequacy of the power plant to be carried out. The intended surface finish of all waterways shall be shown, so as to enable an
independent evaluation of the hydraulic loss coefficients to be made. The construction materials from which each component of the scheme is to be
constructed shall be shown on the drawings.
The Contractor’s proposed construction implementation schedule (bar chart) shall cover the full construction period, shall provide details of all major
activities, and shall indicate key milestones and the critical path.