GCC 04/2019 GENERAL COMMERCIAL CONDITIONS for the Purchase of Plants, Plant Components and Services Bilfinger VAM Anlagentechnik GmbH Dieselstraße 2 4600 Wels APRIL 2019 (GCC 04/2019)

GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

GCC 04/2019

GENERAL COMMERCIAL CONDITIONS

for the Purchase of

Plants, Plant Components and Services

Bilfinger VAM Anlagentechnik GmbH

Dieselstraße 2

4600 Wels

APRIL 2019

(GCC 04/2019)

Page 2: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

2

_________________________________________________________________________________________

GCC 04/2019

TABLE OF CONTENTS

Article Page

1. DEFINITION OF TERMS 3

2. GENERAL 3

3. PRICES 5

4. TERMS OF PAYMENT 6

5. SUBCONTRACTS 7

6. DOCUMENTATION 8

7. INSPECTION, TEST, EXPEDITING 9

8. DISPATCH 10

9. DEADLINES 11

10. CONTRACTOR'S LIABILITY 12

11. GUARANTEE 12

12. ACCEPTANCE 14

13. EXPORT LICENCE 14

14. INDUSTRIAL PROPERTY RIGHTS 15

15. FORCE MAJEURE 16

16. TERMINATION OF CONTRACT 16

17. OTHER TERMS AND CONDITIONS 18

18. APPLICABLE LAW AND PLACE OF

JURISDICTION 19

19. CIVIL WORKS AS WELL AS ERECTION- AND

COMMISSIONING ACTIVITIES 20

20. VENDOR DECLARATION 20

Page 3: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

3

_________________________________________________________________________________________

GCC 04/2019

1. DEFINITION OF TERMS

1.1 The following terms apply in these General Commercial Terms:

PU = Purchaser (name of company and address in order) CO = Contractor who is the legal entity responsible for the fulfilment

of deliveries and services in accordance with the order FC = Final Customer to whom the plant is supplied total plant = the entire system or plant technically or contractually intended

for the Final Customer and for which the supplier is responsible for deliveries and services

customer contract = contract between the Final Customer and the Purchaser for the

supply of the plant order = contract between the Purchaser and the Contractor with regard

to the supplies and services to be provided by the Contractor. supplies/services = all supplies and services to be performed by the Contractor in

accordance with the order. The term services shall also be understood to refer to supplies (deliveries) and services.

1.2 The following definitions shall apply with reference to the step-by-step

acceptance of a plant or parts thereof:

Completion of Erection = Completion of the entire plant, including the no-load test. The no-load test shall be deemed to be completed at the time the entire facility has been tested without utilities in individual and in full interlocking operation, etc., and all systems, plant components as well as controls and safety installations, etc., have been functionally tested and appropriately adjusted to their respective nominal ratings. Furthermore, all control circuits shall be functionally tested and pre-adjusted. Start of trial run = start up = beginning of hot tests = runup of the entire plant under operating conditions.

Performance test = operation of the plant under continuous full load for a time period specified in the customer contract.

Positive performance test = achievement of all specified performance parameters of the entire plant and confirmation of plant operation in accordance with the requirements of the Final Customer contract under the supposition that the supplies/services comply with the requirements of the contract and are free of defects.

Acceptance = the Final Customer's written confirmation that the entire plant comprised of the Contractor's supplies and services has been completed in accordance with the Final Customer contract and is free of defects. This includes proof that all performance data (e.g. capacity, quality of the product, consumption, emissions) have been achieved in a performance test.

2. GENERAL

2.1 Order The date of the order shall be the date the order is sent.

The order shall be either confirmed or rejected in writing within 10 days. In the event the Contractor does not confirm the order within 10 days by means of an unconditional

Page 4: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

4

_________________________________________________________________________________________

GCC 04/2019

order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed.

2.2 Significance of Supplies and Services of the Contractor

The supplies and services of the Contractor shall become an integral part of the complex plant to be erected. Difficulties in individual services generally cause disturbances to the organisation of the entire project, thus resulting in additional costs, for example in connection with delays that affect the project schedule, claims of third parties, disturbance of logistics, delayed acceptance of the plant by the customer, idle time, etc. The financial consequences are particularly serious for plants erected overseas. For this reason the Contractor shall exercise utmost care in the fulfilment of the contract in order to properly deal with such circumstances. This includes, but is not limited to, the responsibility for collecting all information required to ensure due completion of the order, in particular with regard to transport and conditions at the site and to the integration of supplies and services in the plant.

2.3 Quality Assurance

The Contractor and all subcontractors shall undertake to apply the principles of quality assurance pursuant to the applicable standards in executing the scope of supplies and services. The Purchaser and the Final Customer shall reserve the right to audit the quality-assurance systems, the applicable quality-assurance regulations and the quality-assurance plan of the Contractor and subcontractors at any time.

2.4 Validity of the General Commercial Conditions

The subject General Commercial Conditions shall govern the relationship between the Contractor and the Purchaser to the extent that the order does not stipulate any deviations for individual cases.

The conditions of the Contractor (such as offers, conditions of sale) shall apply only in the event that they have been expressly recognised in written form by the Purchaser. Reference made in the order placed by the Purchaser to offers from the Contractor does not automatically entail recognition of the commercial conditions of the Contractor. The subject General Commercial Conditions shall be considered accepted with the commencement of the execution of the order by the Contractor.

2.5 Validity of Statements

Any statement made by the Purchaser regarding orders or amendments or additions thereto shall be legally binding on the Purchaser only to the extent that they have been issued in writing or by telefax by the responsible purchasing department. The Contractor shall have the right to refer to declarations of other persons only in the event he immediately informs the responsible purchasing department and the purchasing department issues a confirmation of the same. The only exceptions are – the selection of options concerning packing and transport by issuing definite shipping

instructions. – individual calls on general orders.

Page 5: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

5

_________________________________________________________________________________________

GCC 04/2019

2.6 Clarification of Inconsistencies

The following order of precedence shall apply in the event of inconsistencies in the terms of the contract between the Contractor and the Purchaser:

– the written order (in form of a letter, telefax) – the annexes mentioned in the written order, particularly the minutes of meetings – the subject General Commercial Conditions. To the extent this order of precedence does not give clarification, the best suitability of the Contractor’s supplies and services for the purpose intended shall be decisive as pertaining to the scope of supplies and services. In the event the Contractor does not clearly understand his scope of commitments, he shall immediately inform the Purchaser. The Purchaser and Contractor shall mutually determine a solution. The Contractor shall undertake to immediately inform the Purchaser of any inconsistencies in the specification. Headings exclusively serve the purpose of orientation and shall have no bearing on the interpretation of respective articles.

2.7 Contract Language

In the event the contract language is not specifically mentioned, the contract language shall be German.

The Contractor shall ensure that its managerial staff speak and write this language fluently.

2.8. Statutory Claims Nothing contained in the subject General Commercial Conditions shall diminish the Purchaser's statutory (legal) claims.

3. PRICES

3.1 Definition of Prices

The prices in the order are understood to be fixed prices that do not include value-added tax and that cover all expenditures of the Contractor as they relate to the fulfilment of his supplies and services. This particularly includes all costs for transport, insurance, packing, taxes, customs fees and other charges in connection with the fulfilment of the supplies and services in those countries in which these services are actually rendered. The Purchaser shall be held liable exclusively for costs that are specified in the order as the express responsibility of the Purchaser. The conditions of the main order shall apply to any amendments and additions to the order as well as orders for spare and wear parts.

3.2 Basis of Prices

Unless stipulated otherwise in the order, the prices shall be quoted “Delivered at place” (DAP), in accordance with Incoterms 2010. The price shall include all costs for related documentation, technical inspection, painting, corrosion protection, marking, etc. The costs and responsibilities for export customs clearance (with the Contractor’s own documentation) for supplies to foreign countries shall also be borne by the Contractor.

Page 6: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

6

_________________________________________________________________________________________

GCC 04/2019

4. TERMS OF PAYMENT

4.1 Invoicing

Invoices shall be submitted to the Purchaser (company name and address as on the order) together with all necessary documentation for identification, such as the order number, etc, in a single copy.

In addition to providing the legally required information, Contractors from member states of the European Union shall indicate the following information on all invoices: - the applicable tax rate or reference to tax-exemption status and the movement of

goods - date of issue - number of invoice - the UID (unique identification number) of the Contractor

Incomplete or otherwise non-auditable invoices may be rejected.

The rejection of invoices shall imply that respective payment periods are not effective and shall not become effective until the respective invoice has been resubmitted.

4.2 Payment

Unless otherwise agreed, payment shall be made in accordance with the agreed payment terms upon receipt of an auditable invoice and after all requirements have been fulfilled, including but not limited to the due delivery of documentation, within 21 days of receipt of invoice with 3 % discount or within 30 days with 2% discount or within 60 days net at the discretion of the Purchaser.

Money transfers shall be conducted such that the fees of the commissioning bank shall be paid by the Purchaser and those of the receiving bank shall be paid by the Contractor (receiver).

Payment shall not be understood as recognition of orderly fulfilment of the supplies and services and does not represent a waiver of the rights of the Purchaser to demand fulfilment, warranty, claims to damages, contractual penalties, etc.

4.3 Retention

The Purchaser shall be entitled to retain agreed monies as a non-interest bearing security to cover any claims for the proper fulfilment of the contract, guarantee or warranty claims as well as claims to damages for up to 45 days after termination of the guarantee period. The same shall apply in the event of insolvency proceedings against the Contractor.

4.4 Final Invoice

The final payment shall not be effected prior to the Contractor’s presentation of a final invoice for the performed supplies and services as well as the related claims.

By presenting the final invoice the Contractor declares that any and all claims in connection with the respective contract have been settled and that no further claims will be raised.

4.5 Offset The Purchaser shall be entitled to offset claims, against claims that companies in which Bilfinger SE has a direct or indirect holding of at least 50 % (companies in the Bilfinger

Page 7: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

7

_________________________________________________________________________________________

GCC 04/2019

Group) have against the supplier or the Contractor. Furthermore, the Purchaser shall be entitled to offset his claims against counterclaims which the supplier or the Contractor has against one of the afore-mentioned companies in the Bilfinger Group. All the companies in which Bilfinger has a direct or indirect holding of at least 50 % and which have the registered trade mark, the logo, indicating Bilfinger, are members of the Bilfinger Group.

4.6 Retention of Payment

Furthermore, the Purchaser shall reserve the right to retain payment at any time in the event the Contractor does not fulfil his contractual obligations (such as pertaining to quality, schedule, function, etc.) or as long as the Contractor does not remedy errors. The retention of payment shall not authorise the Contractor to interrupt or cease execution of the order.

5. SUBCONTRACTS

5.1 Approval

The Contractor shall provide timely information to the Purchaser of any planned subcontracting and shall seek prior written approval for the same. At the request of the Purchaser, the Contractor shall provide the Purchaser with a copy of the respective order.

In the event of non-compliance with these obligations, the Contractor shall fully indemnify the Purchaser of all consequences which may arise. Such consequences may directly result from - quality - deadline risks - compensation requirements - technical cross-standardisation - subcontracting requirements set by the Final Customer - customs regulations concerning temporary admission, transit, import and transportation

In the event a subcontract has not been approved by the Purchaser, the Purchaser shall, irrespective of any other rights, be entitled to terminate the contract in whole or in part.

Approval of a subcontract by the Purchaser shall not limit the obligations of the Contractor in any way. Even in the event that subcontracts have been assigned, the Contractor shall remain fully responsible to the Purchaser for fulfilment of the entire order. The Contractor shall be held liable for the actions and omissions of his subcontractors as well as his own actions or omissions. The Purchaser has the right to fulfil claims of subcontractors or of suppliers of the Contractor directly and – without having to renounce other rights – may retain these claims on payments due to the Contractor. In such cases, the Purchaser shall inform the Contractor.

5.2 Origin of Supplies/Services

The minimum value of supplies/services from a certain country and the relevant regulations pertaining to certificates of origin required under the regulations of the Österreichische Kontrollbank (ÖKB) or other financial or insurance institutions, as stated in the order, shall be strictly adhered to and proven to the Purchaser. The Purchaser, ÖKB or the respective financial or insurance institution shall be entitled to request verification from the Contractor, which verification shall be provided free of charge. In addition to the transfer of the exporter’s liability to the Contractor by way of a back guarantee to the Purchaser (if agreed upon), the latter shall in case of a breach of the above obligation be fully indemnified by the Contractor with respect to

Page 8: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

8

_________________________________________________________________________________________

GCC 04/2019

– additional cost caused by loss of a government-backed export credit for the entire

financing period – the consequences arising from withdrawal of the insurance coverage for the

commercial or political non-payment risk.

5.3 Inquiries/Countertrade

The Contractor and subcontractors shall send inquiries for items contained in the production program in the companies of the Bilfinger Group to the relevant companies.

Fulfilment of time schedules or any other conditions of the order shall not be affected.

6. DOCUMENTATION

6.1 Significance of Documentation

Documentation includes all written, drawn or otherwise created documents relating to the Contractor’s supplies and services and serving to assist the Contractor and the Purchaser in fulfilling their obligations toward their respective contracting partners and the involved authorities in due time and in the most economical manner. Such documentation may be related to manufacture, quality control, potential risks, safety instructions, dispatch, transport, export, transit, import, customs clearance, excise, identification of parts, logistics, storing, erection, commissioning, training, accounting, invoicing, operation, repair, maintenance, procurement of spare parts, etc.

Should the Purchaser make an electronic platform (e.g. Microsoft Sharepoint) available

for storing documents, it is obligatory to use it. Any violation or non-observance of this obligation shall be deemed to be a material breach of this agreement. The preparation and delivery of the documentation shall form an essential part of the Contractor’s supplies and services. The Purchaser shall be granted the right to use the documentation and, inter alia, shall be entitled to pass on any documentation received from the Contractor or subcontractors to other contracting partners of the Purchaser and/or to the Final Customer.

6.2 Scope

The documentation shall be submitted to the Purchaser as specified in the order. To the extent not specified in detail, the documentation shall be adequate for the respective case regarding volume, standard and due availability and shall be in the prescribed language. All documentation shall be “Delivered at place” (DAP) to the Purchaser in accordance with Incoterms 2010, unless agreed otherwise.

6.3 Shipping Documents

Shipping documents shall be in accordance with the Purchaser’s shipping and packing instructions. The documents shall clearly state the correct and complete order number, identification number, position and item number as well as the designation of the goods for clear identification of the applicable customs tariffs. The designations of individual items shall be maintained throughout the documentation. In particular, the designations used in the drawings, part lists, packing lists and shipping documents shall be exactly the same.

6.4 Documentation of Origin

Page 9: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

9

_________________________________________________________________________________________

GCC 04/2019

The Contractor shall enclose, free of charge, valid evidence of entitlement to preferential tariff treatment (movement certificate, preferential certificate of origin, certificate of origin, confirmation of origin, declaration of origin, etc.) with the goods supplied across frontiers, as necessary for preferential clearance for import in the country of destination of the goods. In particular, the certificate shall also include the order number and project number of the Purchaser. The value of goods shall not be indicated. Unless agreed otherwise, the country of the Contractor shall be the country of origin. Certificate of Origin At the request of the Purchaser, the Contractor shall provide at his own cost a certificate of origin certified by the competent chamber of commerce and the competent consulate or embassy, respectively.

Confirmation of Origin In the event the certificate of origin is made out by the Purchaser, the Contractor shall provide at the request of the Purchaser a confirmation of origin for each single part of his supplies and shall specify the manufacturer (including the exact address) and/or the country of origin.

All fees, duties and extra charges resulting from failure to submit such documents, or from incorrect statements, shall be borne by the Contractor.

6.5 Inspection Documents

To the extent required in each individual case, the inspection documents to be provided by the Contractor shall consist of reports on quality control, test certificates, etc., as well as time schedules and progress reports.

6.6 Erection Documents

In order to ensure orderly and economical erection, the required documents shall be provided in accordance with the time schedule and the actual progress of the erection activities.

6.7 CE Labelling

The Contractor shall be obligated to mark with a CE label all supplies and services which require or permit a CE label and/or a declaration of conformity and submit to the Purchaser all necessary declarations of conformity in the language prescribed for the documentation.

7. INSPECTION, TEST, EXPEDITING

7.1 Tests and Inspections

The Contractor shall allow personnel authorised by the Purchaser or by the Final Customer to carry out inspections on items/activities in connection with the order and at any time. This includes inspection of planning, production insofar as quality and time schedule are concerned, taking of samples, packing regarding its quality and conformity of the packing list with the contents of the various packages, loading, etc. For this purpose the Contractor shall admit representatives of the Purchaser or of the Final Customer to offices and workshops of the Contractor and subcontractors, make available all records in connection with the contract and shall keep the Purchaser informed of the progress in the work activities. Possible changes in the time schedule are to be advised immediately. The Contractor shall carry out a complete inspection program on his own and make available a detailed list of test results (test certificates, dimensional check reports, etc.) before final inspection by the Purchaser’s inspection team. At the request of the Purchaser, the Contractor shall be present at the final inspection. The Contractor shall provide free of charge services, material, labour,

Page 10: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

10

_________________________________________________________________________________________

GCC 04/2019

interpreters, energy, suitable test equipment, testing media, skilled and unskilled workers for moving packages, opening and closing of cases/crates, etc., in order to ensure orderly and efficient inspection.

The Contractor shall ensure that all equipment/components are easily accessible and shall take adequate safety precautions. The equipment and components thereof presented for inspection shall be unpainted and pre-assembled, unless specifically requested otherwise.

An inspection, whether carried out or waived by the Purchaser, shall not limit the Contractor’s obligations and shall in no case be construed as a waiver of any of the Purchaser's rights, including but not limited to penalties, damages, guarantees/warranties, etc., even if a respective reservation has not been asserted. Defects determined in the course of an inspection or test shall be immediately rectified by the Contractor at his own cost.

7.2 Documentation

For inspection the required inspection documents and for inspection of packing the relevant packing lists shall be provided by the Contractor. Incomplete or incorrect documents may necessitate repeated inspections.

All inspection documents shall be handed over to the Purchaser’s inspector or the requested number of copies sent within an agreed period. In the event an inspection is waived, all documents shall be sent to the Purchaser immediately or within the agreed time limit or at the latest before dispatch of the respective equipment/components.

The inspection documents shall be divided according to position numbers in a clear and logical order with a corresponding index and shall be placed in a file.

7.3 Costs

The Contractor and the Purchaser/final customer shall each bear the respective costs for their own personnel and inspection teams.

Should an inspection not be satisfactorily completed for reasons attributable to the Contractor, the Contractor shall bear all costs incurred by repeated inspection.

8. DISPATCH

8.1 Shipping Instructions

The Contractor shall adhere to the Purchaser’s shipping and packing instructions.

The Purchaser shall reserve the right to revise the shipping instructions if deemed necessary during implementation of the project. All cost arising from non-compliance with the Purchaser’s instructions or from delays, such as costs for special transportation, air freight, extra packing, etc., shall be borne entirely by the Contractor.

8.2 Export Clearance

Export clearance shall be carried out by the Contractor with his own documents. The incurred costs and fees shall be borne by the Contractor.

8.3. Part Deliveries

Unless otherwise agreed, the Contractor shall deliver or prepare for collection the supplies ordered in complete loads. Incomplete part deliveries are only to be executed

Page 11: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

11

_________________________________________________________________________________________

GCC 04/2019

or planned respectively after prior agreement with and written approval of the Purchaser. All additional costs/expenses (e.g. transportation and packaging costs, obstructions to assembly, handling fees, etc.) arising due to part deliveries which were neither agreed upon nor approved by the Purchaser shall be borne by the Contractor.

9. DEADLINES

9.1 Delivery Date For documentation purposes, the date of delivery shall be the date shown in the “received” stamp of the Purchaser or the date of an individual receipt in the event all documents have been completely and correctly presented in accordance with the contract.

For supplies and services, the date of delivery shall be the date on which all of the Contractor’s respective obligations pursuant to the contract (including those regarding documentation) have been completely fulfilled and are free of defect.

9.2 Delays

The Contractor shall immediately advise the Purchaser in the event it becomes known that the agreed deadlines cannot be met. A full written report of the reasons and extent of such delays shall be sent immediately to the Purchaser.

In the event the contract requires the Purchaser to take action by a certain date in order to meet a delivery date, the Contractor shall notify the Purchaser in due time. In the event the Contractor does not request compliance by the Purchaser and comes into delinquency as a result, the Contractor may not hold the Purchaser responsible for default. In the event the Contractor is hindered in duly fulfilling his commitments under the contract as a result of the Purchaser’s late delivery despite due notification, the agreed dates and periods shall be extended by no more than the number of days of delay caused by the Purchaser. The Purchaser shall not be held liable for any additional cost. The original contractual dates/periods extended by such delays shall be the new due dates, e.g., for calculation of penalties, etc.

In the event of possible or actual delays, the Contractor shall be required to minimise such delays by taking all constructive measures, regardless of the cause of such delays.

9.3 Storage

In the event the delivery dates set out in the contract be changed for reasons not attributable to the Contractor, the Contractor shall provide adequate storage of the goods at his own risk and his own cost for a period of up to 3 months.

Due payments incurred by such storage may be made against a warehouse certificate or certificate of transfer of property and/or bank guarantee, etc.

In case of storage, shipments in whole or in part shall only be carried out in the event the release has been confirmed in writing by the Purchaser.

9.4 Premature Fulfilment

Deliveries/services prior to the due date shall only be accepted where approved in writing by the Purchaser and shall not advance agreed payment dates.

Page 12: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

12

_________________________________________________________________________________________

GCC 04/2019

10. CONTRACTOR’S LIABILITY

The contractor is fully liable in accordance with the legal provisions, provided that nothing different is expressly stipulated in these GCC or the order.

10.1 Penalties for Delay

In the event the Contractor does not comply with the agreed time periods, nor meet the intermediate or final deadlines set forth in the contract, the following penalties, in each case to be calculated from the total contract value, shall apply for the time that passes until the actual date of delivery. Such penalties may also be deducted from the Contractor’s account receivable or any open invoices.

- Supplies and Services 1% per week or part thereof for delay, up to a maximum of 10% of the total order

value. - Documentation 0.5% per week or part thereof for delay, up to a maximum of 5% of the total order

value.

The obligation to pay a contractual penalty shall commence for the Contractor at the time delinquency first occurs, in which case any fault of the Contractor shall not apply.

The contractual penalty shall be due in the event the Contractor defaults with a partial service or only minute or unimportant defects hinder acceptance of the entire facility. The basis for calculation of the penalty shall be the respective total order value. The Purchaser shall reserve the right to assert claims to actual damages above and beyond the contractual penalty.

In the event of a defective delivery or supply, the time between taking over and the official complaint by the Purchaser shall not be subject to a contractual penalty. Reservations of the Purchaser upon acceptance of the delivery shall not be required to maintain a claim for contractual penalty. The payment of a contractual penalty shall not relieve the Contractor from his obligation of fulfilment and any related liabilities.

11. GUARANTEE

11.1 General

The Contractor is liable not only for the conditions/qualities expressly specified or promised in any other way or to be reasonably expected but also for completeness of his supplies and services and their best suitability for the specific purpose intended. This guarantee particularly covers the suitability of the Contractor’s supplies/services for continuous operation of the plant under the operating conditions prevailing at the site, conformity with all standards and regulations applicable at the site (such as safety, environmental protection), uninterrupted availability with adequate performance and consumption data, easy erection, maintenance and repair. The design and manufacture shall represent the most modern state of the art at the time of contractual execution by the Contractor.

Each advertising statement made by the Contractor about his product/services shall be understood as a guaranteed expression of the characteristics of the respective product/service.

11.2 Guarantee Period, Remedy of Defects

The guarantee period ends 24 months after the date of acceptance of the entire plant, however 36 months at the latest from the date of final delivery in accordance with the order. For corrosion protection, the guarantee period ends 60 months from the date of acceptance of the entire plant.

Page 13: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

13

_________________________________________________________________________________________

GCC 04/2019

The guarantee period shall be extended by any downtimes caused by defects. In the event of replacement or repair of a part, a new guarantee period equal to the one for the original supply shall apply and shall commence on the date of installation of the new part or completion of the repair.

The Contractor shall not be released from guarantee and warranty obligations by reason of the Purchaser refraining to issue a notification of defects. A notification of defects can be issued by the Purchaser while maintaining full guarantee and warranty obligations of the Contractor up until one month following the end of the guarantee period. The limitation period pursuant to the contract or provided by law for instituting legal proceedings against the Contractor with respect to guarantee claims shall commence upon expiry of the guarantee period.

The Purchaser shall have no obligation whatsoever to inspect the supplies and services of the Contractor before the agreed functional and performance tests are carried out.

In the event of any defects, including serial defects, even in the event a defect has not yet occurred in all supplies of the same kind, that arise before or within the guarantee period, the Contractor shall carry out all necessary repair on site within the shortest possible time or shall replace the defective item on site in accordance with the Purchaser’s instructions. All related services and any additional costs, such as for transportation, customs, dismantling and erection, shall be carried out by the Contractor or at the Contractor’s expense.

In the event of minor defects (up to approximately EUR 10,000.00 for each individual case) or if immediate repair is imperative (in critical stages such as trial runs), the Purchaser shall be entitled to remedy or have remedied any such defects immediately and without prior notification to the Contractor. Such work shall be carried out at the expense of the Contractor and shall not affect the Purchaser’s rights or other claims. The same shall apply in the event the Contractor fails to remedy defects in time, despite having been requested to do so.

11.3 Non-compliance with Guaranteed Characteristics

Even in the event the order includes contractual penalties for defects, non-fulfilled guaranteed characteristics or other guarantees (such as performance penalties), the Contractor shall be obligated to ensure that his deliveries and services meet the respective intended requirements.

11.4 Liability for Documentation The Contractor declares that he is aware of the special significance of meeting his obligations with respect to the documentation and that for this reason he is held liable for the consequences of any defaults and defects.

11.5 Liability for Engineering

The Contractor shall guarantee correctness and completeness with respect to engineering services, consultations and documentation.

Information regarding the design of the Purchaser are not binding and shall be monitored by the Contractor accordingly. Information regarding the design of the Purchaser shall not release the Contractor in any way from his obligations to perform his respective services. The Contractor is particularly obligated to inform himself about the actual conditions on site and to consider these accordingly in scheduling his respective activities.

The Contractor shall take special note that the information regarding the design of the Purchaser relates solely to unbinding concepts geared toward project completion and have not been structurally nor statically nor technically evaluated as to their implementation. The Contractor shall be held fully responsible for his own activities in spite of the information regarding the design of the Purchaser.

Page 14: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

14

_________________________________________________________________________________________

GCC 04/2019

11.6 Product Liability

In case of any claim against the Purchaser in connection with the violation of safety regulations or on the basis of product liability laws/regulations the Contractor shall indemnify and save the Purchaser harmless and shall be fully liable for all losses and damages incurred by the Purchaser as a result of such claim provided such claim is based on or ascribable to defects or failures in the supplies and services of the Contractor, or unsafe products of the Contractor as per the applicable product liability laws/regulations.

The Contractor shall be obligated to insure himself sufficiently against all risks arising from product liability and, upon request, shall present the Purchaser with the respective insurance policy.

The purchase of this insurance shall in no way limit the obligations and liability of the Contractor, even in the event the Purchaser makes no objection to the presented insurance policy.

11.7 Spare Parts

In the event not otherwise agreed, the Contractor guarantees that the mutually selected spare-, wear- and exchange parts completely suffice in non-stop operation for a period of 2 years from the time the plant is started up. In the event of any shortages of parts during this period, the Contractor shall supply additional parts “Delivered at place” (DAP), place of destination to be specified by the Purchaser (in most cases the site) in accordance with Incoterms 2010, free of charge, including packaging. The guarantee period ends 24 months from the date of installation and startup of these parts. The Contractor guarantees availability of spare-, wear- and exchange parts for a period of 10 years from the end of the guarantee period.

12. ACCEPTANCE

12.1 Performance Test

Generally the supplies/services shall be tested as to their conformity with the contract during the performance test of the plant. However, the Purchaser shall be entitled to additional specific tests in order to examine the respective supplies/services.

12.2 Delay of Acceptance caused by to the Contractor

In the event a Performance Test fails or acceptance is hindered by other defects, the Purchaser shall grant the Contractor adequate time (under due consideration of the consequences for the entire plant) to carry out the necessary repairs/improvements. All costs for labour, material, media, etc. incurred by the Purchaser as a result of the Contractor’s unsuccessful performance test shall be borne by the Contractor.

In the event the plant is not accepted within a reasonable time as a result of causes attributable to the Contractor, the Purchaser in his sole discretion shall be entitled to the penalties stipulated in the order and/or to a price reduction or to terminate the contract while reserving the right to claim damages.

13. EXPORT CONTROL

The seller is obliged and undertakes to comply with any German, EU and US laws and provisions applicable to the import, export or re-export of the goods* being subject of this contract. The seller is not entitled to supply or incorporate in its supply any US goods which are subject to US EAR (Export Administration Regulation) or to involve US persons, unless the purchaser has given its express prior consent. The seller shall inform the purchaser of all information necessary for the export of the goods and provide the purchaser without delay, but no later than two weeks after the binding order, the

Page 15: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

15

_________________________________________________________________________________________

GCC 04/2019

relevant data by means of the form "Export Restriction Statement" (see attachment) for all goods supplied under this contract and agrees to keep the purchaser informed at any time of any changes by written notice. Within said period of time, the seller shall provide to the purchaser in writing the suppliers-declaration of preferential origin (for EU suppliers) and certificates of preference (for non-EU suppliers). The seller shall indemnify and hold harmless the purchaser from all loss, damage and third party claims resulting from a breach of any of the aforementioned obligations, unless such breach is not attributable to the seller. * Definition of goods: goods (merchandise), software, technology and information

14. INDUSTRIAL PROPERTY RIGHTS

14.1 Third Parties’ Rights

The Contractor shall ensure that the use of its supplies and services is not affected in any way by claims of third parties regarding trademarks, copyrights, patents, protected territories, etc., and that no boycott clauses, black lists, etc., are violated.

The Contractor shall immediately inform the Purchaser of any infringement of third parties’ rights or any violation of boycott clauses or black lists, etc.

In the event of any such infringement or violation, the Contractor shall fully indemnify and hold the Purchaser and the Final Customer harmless against any claims of third parties and shall guarantee the Purchaser and the Final Customer unlimited use of the supplies and services, or shall provide other acceptable alternatives free of charge to the Purchaser/final customer.

14.2 Obligation of Secrecy

Without the Purchaser’s written consent, the Contractor shall not disclose to the public nor use for advertising or any other purposes any information related to the order or to the project or any other information obtained directly or indirectly from the Purchaser or the Final Customer, including all information developed by the Contractor on the basis thereof. In particular, engineering documents provided by the Purchaser and the documentation shall be treated in strict confidence and shall not be used for any purpose other than for executing the respective order. This obligation of secrecy shall also be imposed by the Contractor on any person who receives such information. In the event of a breach of this obligation of secrecy, the Contractor shall also indemnify the Purchaser against third parties’ claims.

14.3 Copyright

The property and the exclusive right of use for all drawings, information and know-how made available by the Purchaser to the Contractor remains with the Purchaser. The Contractor acknowledges the Purchaser’s exclusive copyright thereof.

14.4 Inventions and Improvements

The Contractor is obligated to inform the Purchaser about inventions and improvements made by the Contractor or the Contractor's staff in connection with the implementation of the order on the basis of information and documentation provided by the Purchaser and at the Purchaser's request in accordance with the applicable provisions of the relevant patent law to make use of the inventions. The Contractor shall transfer without reservation the invention (patent) with all rights and obligations to the Purchaser against reimbursement of the inventor's compensation and of the cost incurred by the Contractor resulting from the patent application.

The utilisation of the invention, the application for a patent and the determination of reimbursement to which the inventor is entitled by law will be agreed upon mutually by

Page 16: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

16

_________________________________________________________________________________________

GCC 04/2019

the Contractor and the Purchaser, in the course of which the Contractor shall take all necessary measures.

The Contractor shall ensure that its subcontractors will take over a similar obligation in favour of the Purchaser.

14.5 Follow-up Orders

In order to protect the know-how obtained by the Contractor from the Purchaser in connection with the contract and to ensure optimal operation of the entire plant also after expiration of the guarantee period, the Contractor shall not conduct any direct business with the Final Customer or its representatives for a period of 10 years with respect to follow-up orders for the plant from the date of final delivery. The Contractor shall not submit direct nor indirect offers to the Final Customer with respect to spare and wear parts without agreement of the Purchaser as a marketing partner.

15. FORCE MAJEURE

The Contractor shall be released either fully or partially from his obligation to meet deadlines in fulfilment of the contract in the event he is hindered by force majeure.

Events of force majeure are limited to fire, floods, acts of God, war and riot.

In the event the Contractor is impeded by an event of force majeure, he shall only be entitled to claim force majeure in the event he submits to the Purchaser immediately, or within 5 days at the latest, by registered mail a certificate issued by the authorities or the chamber of commerce of the Contractor’s country, confirming the reasons, the commencement date and the expected duration and consequences of the event.

The Contractor shall make every effort to remove or minimise the hindrance caused by force majeure and any consequential damages as well as to continually inform the Purchaser of the current status of affairs. Dates and deadlines which cannot be kept as a result of force majeure shall be postponed/extended by the duration of the effects of force majeure.

In the event force majeure exceeds 4 weeks, the Purchaser shall have the right to terminate the contract in whole or in part.

The Purchaser shall not be liable towards the Contractor for the consequences arising from any hindrance to the implementation of the contract due to force majeure.

16. TERMINATION OF CONTRACT

16.1 Breach of Contract

In the event of a serious breach of contract that is not remedied by the Contractor after having been granted a reasonable grace period (generally 2 weeks), the Purchaser shall have the right to terminate the contract in whole or in part.

The Purchaser reserves the right to terminate the contract without granting a grace period under the following conditions:

- The Contractor receives a reminder requesting fulfilment of contractual obligations

and is given a reasonable grace period, even in the event the reminder does not expressly set a grace period or threaten with termination.

- In the event the Purchaser has reason before the respective due date to assume that

the Contractor is not or will not be willing or able to fulfil essential contractual obligations in due time.

Page 17: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

17

_________________________________________________________________________________________

GCC 04/2019

Delays or imminent delays with respect to final or other contractual dates or defects that would jeopardise the fulfilment of the Purchaser’s obligations toward the contracting partners shall particularly be considered serious breaches of the contract, even in the event a respective penalty is attached.

In such cases the Purchaser shall reserve the right to execute or have executed the deliveries and services not performed or insufficiently performed by the Contractor at the cost of the Contractor. The costs incurred in this respect can be either directly invoiced by the Purchaser with an agreed payment period of 45 days after invoicing or deducted from the next due payment made by the Purchaser to the Contractor.

The Contractor shall reimburse the amounts already paid by the Purchaser for supplies and/or services not performed, including all related financing costs incurred by the Purchaser.

In the event that substituted services require access to equipment or materials at the Contractor or subsuppliers, the Contractor shall be obligated to provide this equipment and/or materials to the Purchaser.

In the event that substituted services require access to protected privileges, to documentation (such as workshop drawings, calculations) or other information, the Contractor shall be obligated to provide the required privileges, documentation or information to the Purchaser.

Right of Use In case of termination or cancellation of the contract the Purchaser and/or the Final Customer has the right to use the supplies and services of the Contractor free of charge until acceptance of an alternative solution.

16.2 Credit-Worthiness of the Contractor/Insolvency

In the event of bankruptcy or other insolvency proceedings imminent or instituted against the Contractor or its subcontractors, or in the event of changes to the status of ownership of the Contractor, the Purchaser shall be fully informed by written notice without delay. In the event of bankruptcy or other insolvency proceedings against the Contractor, or in the event of changes to the status of ownership of the Contractor, the Purchaser shall be entitled to immediately take over the supplies and/or services of the Contractor or his subcontractors and/or to terminate the contract in whole or in part.

16.3 Transferral of Goods for Use In the event of cancellation in accordance with article 16.1 and 16.2 of the subject

General Commercial Conditions, irrespective of his other contractual or legal claims, the Purchaser shall reserve the right to use the tools and the erection equipment such as cranes, scaffolding, etc., of the Contractor for the completion of the activities to be carried out in accordance with the contract. The use of this equipment shall be reimbursed in an adequate amount which shall be deducted by the Purchaser from claims to damages or other valid claims against the Contractor. The Contractor expressly agrees at this time to the above transferral of goods for use.

16.4 Cancellation

The Purchaser reserves the right to cancel the contract either partially or in full without any reason attributable to the Contractor. In this case the Purchaser shall pay the Contractor that portion of the contract value which corresponds to the supplies and services already delivered, plus verified direct cost related to work in progress, and compensation payable to its subcontractors. After the Contractor has been notified of a cancellation, he shall make every effort to minimise all cost and compensation arising therefrom.

Page 18: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

18

_________________________________________________________________________________________

GCC 04/2019

16.5 Suspension

The Purchaser shall have the right to call for a suspension of the further work at any time. In such case the Contractor shall specify in detail to the Purchaser all the consequences resulting therefrom and suggest the best possible and most economical alternatives available for the further implementation of the project. The Contractor shall not claim any damages resulting from an interruption period of up to a maximum of 3 months.

17. OTHER TERMS AND CONDITIONS

17.1 Transfer of Risk

For transfer of risk the regulations contained in Incoterms 2010 shall apply. However, in the event the erection of the supplies is included in the scope of work of the Contractor the risk shall transfer to Purchaser upon acceptance.

17.2 Transfer of Property

The transfer of property to the Purchaser shall take place simultaneously with the transfer of risk.

17.3 Erection Equipment

Equipment for erection and commissioning, etc., required for temporary use at the site shall remain the property and within the full responsibility of the Contractor. The Contractor shall particularly indemnify the Purchaser against any costs arising from the export and import of such equipment. For activities performed at site Purchaser’s conditions for execution of erection works shall apply additionally.

17.4 Insurance

Unless otherwise agreed in particular, the Contractor shall be responsible for obtaining all insurance coverage considered to be necessary. Such insurance coverage obtained by the Contractor shall contain a waiver of subrogation in favour of the Purchaser and the Final Customer. Unless the order contains any alternative provisions, the following applies: in the case of orders up to an order value of EUR 10,000.00 the Contractor is obliged to maintain a corporate liability insurance, a product liability insurance and a planning liability insurance in accordance with international standards with minimum coverage of the equivalent of EUR 2,000,000.00 per claim, to retain it until the order has been fulfilled and to substantiate this to the Purchaser within a period of 3 days if required.

In the event the Contractor is co-insured or otherwise covered by an insurance policy taken out by the Purchaser, the Contractor shall accept the respective insurance conditions as binding on himself. The Contractor shall therefore also adhere to all respective obligations, such as providing all the required information, following instructions, complying with stipulations, etc.

17.5 Power of Attorney

The Contractor shall be obligated to name those persons at the time of order confirmation at the latest who are authorised to make and receive legally binding declarations. In the event the Contractor fails to name such persons, those who actually act on his behalf shall be deemed as duly empowered.

Page 19: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

19

_________________________________________________________________________________________

GCC 04/2019

17.6 Liability toward the Contractor

The Purchaser shall not be liable for losses or damages caused by the Final Customer or any third party.

Incidentally, the client is only liable in the event of wilful intent or gross negligence.

17.7 Third Parties’ Claims

The Contractor shall fully indemnify the Purchaser for all claims of third parties caused by defects in, or improper execution of, the Contractor’s supplies and services.

17.8 Assignment

The contractor is obliged to immediately inform the client in advance about a planned assignment of their payment claims against the client to third parties.

17.9 Changes to Services

The Contractor shall notify the Purchaser of any possible improvement to the supplies and services and offer such improvements to the Purchaser. However, any changes to the supplies and/or services under the contract shall require an additional order.

17.10 Statutory Liens/Rights of Retention

The Contractor shall not create or do anything which would result in the creation of any statutory lien, encumbrance, right of retention or any other kind of security on the free- issue parts provided by the Purchaser or on the supplies/services or any part thereof.

The Contractor shall ensure that a similar provision is included in each of its subcontracts.

17.11 Reorganisation

The Contractor shall immediately inform the Purchaser of the initiation, annulment or cancellation of reorganisation proceedings in accordance with the company reorganisation law and shall report monthly to the Purchaser during the period of reorganisation on the status of the reorganisation.

17.12 Salvatory Clause

In the event that individual stipulations of the subject General Commercial Conditions become invalid, ineffective, illegal or unfeasible, this shall have no influence on the validity of the remaining stipulations.

In such an event the Contractor and the Purchaser are obligated to mutually agree on a stipulation that will replace the stipulation that has become invalid, ineffective, illegal or unfeasible. The mutually agreed stipulation shall come as close as possible within the bounds of the law to the economic intent of the original stipulation.

17.13 Privacy Policy on Contract

The Contractual Parties undertake to process the personal data transferred in the course of the master agreement in compliance with the provisions of the GDPR and the DSG [Data Protection Act]. In particular, the Contractual Parties shall use such personal data and their processing results only for the purposes of fulfilling their contractual and legal obligations in connection with the master agreement.

Page 20: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

20

_________________________________________________________________________________________

GCC 04/2019

The Contractual Parties shall erase the data immediately if they are no longer required for the above purposes and if such erasure does not conflict with any legal retention obligations.

The Contractual Parties undertake to oblige all persons engaged with data processing, in particular

their own employees, to maintain data secrecy pursuant to the GDPR before commencing their

activities. This shall in particular apply to any collection, processing and use of personal and

company data performed by the Contractual Parties in connection with the master agreement. In

particular, the obligation to secrecy for persons commissioned with data traffic shall survive even

after they conclude their activities and are no longer employed by the Contractual Parties.

The Contractual Parties declare that sufficient security measures pursuant to the GDPR have been taken in order to prevent data from being used unlawfully or becoming accessible to third parties without authorisation.

18. APPLICABLE LAW AND PLACE OF JURISDICTION

18.1 The following shall apply to orders placed with Contractors whose headquarters

are outside the Republic of Austria:

Subject to Article 18.3 hereof, all disputes arising in connection with the subject order or related to its violation, termination of nullity which cannot be settled by mutual agreement shall be finally settled under the Rules of Arbitration and Conciliation of the International Arbitral Center of the Economic Chamber in Vienna by one or more arbitrators appointed in accordance with these Rules. Austrian substantive law under exclusion of the UN Convention on Contracts for the International Sale of Goods 1980 shall apply. The place of arbitration shall be Vienna.

18.2 The following shall apply to orders placed with Contractors whose headquarters

are within the Republic of Austria:

Subject to Article 18.3 hereof all disputes arising in connection with the subject order which cannot be settled by mutual agreement shall be finally settled in accordance with the Rules of Arbitration of the permanent Court of Arbitration at the Economic Chamber at the headquarters of the Purchaser.

This order is subject to Austrian substantive law.

18.3 Regular Course of Law In both cases above, the Purchaser reserves the right to assert claims against the

Contractor in accordance with regular legal procedure at an ordinary Austrian court at the seat of the Purchaser in Wels, Austria, in accordance with Austrian substantive law (under exclusion of the UN Convention on Contracts for the International Sale of Goods 1980) instead of through the Court of Arbitration.

19. CIVIL WORKS AS WELL AS ERECTION- AND COMMISSIONING

ACTIVITIES

19.1 In the event of civil works as well as erection and commissioning activities, the regulations for the "Specific terms and conditions for the execution of civil works as wells as erection- and commissioning activities" apply in accordance with Annex 1 of the GCC.

20. VENDOR DECLARATION

20.1 The contractor is obliged to comply with the following Vendor Declaration.

Page 21: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

21

_________________________________________________________________________________________

GCC 04/2019

Vendor Declaration

As part of our commitment to following the principals contained in the Bilfinger Code of Conduct, we expect our business partners to follow comparable standards in their conduct. Our expectations are set out here, in our Vendor Declaration, which you are contractually obliged to follow.

Compliance with laws and adherence to generally accepted standards As a vendor to Bilfinger we will:

Comply with applicable laws and regulations, including relevant anti-corruption legislation

Operate in accordance with generally accepted principles and standards relating to social and environmental responsibility, and internationally recognized human rights including laws preventing modern slavery

Anti-Bribery and Anti-corruption

As a vendor to Bilfinger we will:

Not partake in any form of corruption or bribery, and ensure that business decisions are not influenced through any improper or illegal payments, either through cash, gifts, travel or anything else of value including intangible benefits

Refrain from presenting any invitations or gifts, or anything of value, to Bilfinger employees with an intention to gain any form of influence

Disclose to Bilfinger any requests or pressure to provide bribes (any kind of benefit) in any form, either to Public Officials or any other parties, directly or indirectly, that may try to influence or provide an unfair business advantage

Books and records

As a vendor to Bilfinger we will:

Maintain complete books and records that accurately reflect all business transactions and expenditures that are prepared in accordance with applicable laws and regulations

Conflicts of interest

As a vendor to Bilfinger we will:

Avoid situations where our own interests conflict, or could conflict, with the business interests of Bilfinger

Notify Bilfinger without delay, if we become aware of a conflict of interest, including if a Bilfinger employee has a financial interest in our company or is related to our company in any other way

Protection of assets and information As a vendor to Bilfinger we will:

Contribute to safeguarding Bilfinger's assets from theft, misuse or waste

Take necessary measures to protect, and keep Bilfinger data and information that is avaiable to us confidential

Anti-competition and economic and trade sanctions As a vendor to Bilfinger we will:

Not engage in any activities that could reasonably be construed as being anti-competitive, abusive or unfair, and comply with applicable anti-trust and anti-competition laws and regulations

Comply with laws and regulations governing the export or import of goods, products and services, and those relating to economic and trade sanctions, and anti-boycott

Insider trading As a vendor to Bilfinger we will:

Avoid insider trading by not buying or selling Bilfinger or another company’s securities when in possession of insider information about Bilfinger that is not available to the investing public, and that could influence an investor’s decision to buy or sell the security

Employees

As a vendor to Bilfinger we will:

Provide for safe workplaces that comply with international labour standards

Ensure fair employment practices, and refrain from any form of unethical or illegal employment practices (such as harassment or physical assault, any form of slavery, servitude and forced or compulsory labour including, but not limited to child- labour)

Not discriminate against employees on the grounds of their ethnicity, gender, sexual orientation, religion, ideology, disability or age

Assure the rights of association and collective bargaining and provide employees with written agreements of employment, as governed by local legislation

Ensure that wages, working hours, vacation and leave periods provided to employees and hired external contractors are in accordance with applicable law and/or agreements

Adhere to all applicable data protection laws

Page 22: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

22

_________________________________________________________________________________________

GCC 04/2019

Environment

As a vendor to Bilfinger we will:

Conduct our operations safely and minimize the environmental impact of our business activities

Comply with applicable environmental legislation and permits

Communities

As a vendor to Bilfinger we will:

Respect the local community and seek to prevent and mitigate adverse impact on local community

Standards towards our own Vendors

As a vendor to Bilfinger we will:

Demand from our own vendors and subcontractors to adhere to the principles set forth in this Vendor Declaration

Systematically include and follow up on these obligations in our business relationships with them

Material compliance and conflict minerals

As a vendor to Bilfinger we will:

Ensure that goods and materials provided to Bilfinger are not sourced in illegal or unethical ways

Confirm the implementation of appropriate due diligence measures for the responsible sourcing of minerals to ensure compliance with relevant regulations.

In case we produce, buy or trade with regulated Conflict Minerals (tantalum, tin, tungsten, gold, or any other mineral or its derivatives determined to be financing conflict) from the Democratic Republic of Congo (DRC) or adjoining countries, inform Bilfinger and upon request make our due diligence measures and results available to Bilfinger, to eliminate the possibility that such minerals are supplied to Bilfinger

__________________________________________________________ By signing this document, you confirm that you will fulfill the requirements in this Vendor Declaration. To the extent you are not able to provide supporting documentation, you confirm your willingness to start a process of documenting your performance against these requirements. Bilfinger reserves the right to request further self-declarations, certifications or to take any other reasonable action as contractually agreed where there may be concerns. In cases of concern or, if you become aware of any inappropriate action by Bilfinger personnel, you are encouraged to report these to the Bilfinger Reporting Line (see http://www.bilfinger.com/en/responsibility/compliance/ for global phone numbers) or anonymously through our online reporting portal, available at the same link.

Page 23: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

ANNEX 1

to the

GENERAL COMMERCIAL CONDITIONS for the Purchase of

Plants, Plant Components and Services APRIL 2019

(GCC 04/2019)

21. SPECIFIC TERMS AND CONDITIONS FOR THE EXECUTION OF CIVIL

WORKS AS WELL AS ERECTION- AND COMMISSIONING ACTIVITIES

21.1 Validity

The following terms and conditions shall be valid in addition to and in connection with the General Commercial Conditions (GCC 04/2019), Article 1 through 20.

21.2 Standards, Regulations, Laws in the Country of Deployment

21.2.1 The Contractor shall be obligated to strictly obey all applicable laws, directives, regulations and guidelines effective or becoming effective in the country of deployment during execution of the contract.

21.2.2 The Contractor expressly states that he has full knowledge of the subject contract, the local conditions, material conditions, the conditions of deployment on site and of all circumstances related to implementation of the project. In the event the Contractor does not have sufficient information with respect to the above, he shall obtain such information in due time at his own expense. Furthermore, the Contractor confirms that he has familiarised himself prior to the conclusion of the contract with the site and its surroundings, the local soil conditions, working conditions, traffic conditions and all other circumstances relevant to the execution of supplies/services as well as with all information and documents of the Purchaser and/or Final Customer. Any cost and damages resulting from the Contractor’s failure to comply with this obligation shall be borne by the Contractor.

21.2.3 The relevant professional standards and regulations as well as internal standards of the Final Customer, shall apply unless otherwise specified in the order and/or the specifications.

21.2.4 The Contractor states that he is entitled to execute and perform the services agreed upon in the country of deployment.

Page 24: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

2

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

The Contractor is responsible for an adequate registration of his company in compliance with commercial and fiscal laws, if required in the country of deployment.

All costs incurred in this connection shall be borne exclusively by the Contractor.

21.3 Prices

The following regulation shall apply in deviation to Article 3 of GCC 04/2019:

21.3.1 The prices are fixed prices for the complete, proper and workmanlike execution on time of the services under this contract in accordance with the standards of engineering and in compliance with the terms and conditions of this contract. They are understood to be free site.

21.3.2 The prices agreed upon include all expenditures for consideration of the governmental, legal and other regulations and provisions in force, etc., and particularly comprise the following:

21.3.2.1 salaries and wages including all extra pays, difficulty allowances, as well as reimbursement of overnight stays, travelling expenses, bad weather allowance, social insurance, costs for visas, work and residence permits, etc.

21.3.2.2 all material costs including transport costs as well as loading and unloading, packing costs and costs for packing disposal, item-related costs of construction equipment including fuels, stock-keeping of devices, services of subcontractors and related extra charges, etc.

21.3.3 All expenditures incurred for meeting the requested deadlines of implementation are included in the prices agreed upon.

21.3.4 Furthermore, the prices include all taxes, levies, customs, duties, etc., incurred with regard to the Contractor’s supplies and services.

21.3.5 Unless otherwise specified in the order, the prices for supplies are “Delivered at place” (DAP) according to Incoterms 2010.

21.4 Consortiums

Any planned organisation of a consortium shall be reported to the Purchaser and shall be subject to the Purchaser’s prior written consent. All individual members of a consortium shall be jointly and severally liable towards the Purchaser for performed services. In the event of non-fulfilment or improper fulfilment of the contract in whole or in part by one member, no member shall be released from his liability with reference to a default of another member, but all members shall be jointly and severally liable for the complete and proper fulfilment of the contract.

21.5 Implementation

21.5.1 Purchaser’s Site Manager

The Purchaser’s site manager shall control and supervise the implementation of contractual work activities. These activities shall in no way restrict the extensive responsibilities of the Contractor.

Page 25: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

3

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

In particular, the Purchaser shall be entitled to personally carry out all tests and inspections of materials and components considered to be necessary or to have them executed by third parties.

All delays and costs resulting from these tests and inspections shall be borne by the Contractor.

The Purchaser’s site manager shall reserve the right at any time to issue binding instructions, such as the following:

- removal of materials and components from the site to the extent that the Purchaser’s site

manager is of the opinion that they are not in conformity with the contract. - removal and adequate reconstruction of structures or parts thereof, which in the

Purchaser’s site manager’s opinion have not been constructed in compliance with the specification.

- order to remove the Contractor’s personnel or subcontractors from the site (also see Section 20.5.5).

- in the event of non-compliance with the contractual obligations relating to deliveries and services: disposition of further use of site facilities, construction equipment, tools, materials, etc., on site.

All such instructions shall be followed immediately by the Contractor at his own cost. In the event the Contractor fails to comply with such instructions, the Purchaser shall be entitled to entrust third parties with the execution thereof without granting additional extension of time. All related costs shall be borne by the Contractor.

At the Purchaser’s request, the Contractor shall make available samples and material specimens for testing free of charge.

21.5.2 Contractor’s Site Management

The Contractor shall nominate an authorised site manager and give adequate notice in writing. The replacement of the site manager shall be subject to the Purchaser’s approval. The Contractor shall be obligated to thoroughly check the construction documents prepared by the Purchaser and to request instructions from Purchaser’s site manager in the event of discrepancies. Any objections to the instructions by the Purchaser or his site manager shall be indicated in writing in due time prior to execution of the work activities.

The Contractor shall provide the site supervision required until the work is completed.

At the request of the Purchaser, the Contractor shall be obligated to participate in the discussions with the Final Customer. Furthermore, the Contractor shall undertake to discuss the subject matter of the contract with the Final Customer exclusively in the presence of a representative of the Purchaser.

21.5.3 Commencement of Work

Prior to the start of each work segment the Contractor’s site manager shall check with the

Purchaser’s site manager as to whether the work shall be performed in accordance with the contract documents or whether changes have been made. The Contractor shall bear all consequences arising from failure to seek confirmation prior to the start of any work segment.

21.5.4 Interruptions

The Contractor shall have no right to claim compensation for waiting and outage times and for reimbursement of other costs if the following applies: - The services have been interrupted upon order of the Purchaser’s site

management because of doubts as to the proper fulfilment - Force majeure

Page 26: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

4

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

- Performance of Services was interrupted on account of undisciplined behaviour of the Contractor’s personnel.

- Performance has been interrupted upon order of public authorities. - Services from the Final Customer/Purchaser cannot be provided in accordance

with the technical specification due to disturbances of supply.

21.5.5 Contractor’s Personnel

The Contractor shall provide personnel in sufficient number and of adequate qualification. Unless otherwise specified in the order, the Contractor shall be held responsible for personnel transportation, accomodation and board. All costs incurred in this respect shall be borne by the Contractor.

The Contractor shall be held responsible for compliance of his own personnel and those of the subcontractors with the laws and other regulations in the country of deployment. This shall apply particularly to the import, possession or use of weapons, alcoholic beverages, food, drugs, currency, etc. The Contractor shall ensure that holidays, days of rest, and other customs of the country are respected by his personnel. The Contractor shall take adequate measures to avoid illegal or wrongful conduct of his personnel and shall be responsible for the protection of persons and property at the site and surroundings.

The Contractor shall inform demonstrably his personnel of the applicable site and erection regulations. The qualifications required of the personnel deployed are to be substantiated at the request of the Purchaser by certificates (e.g. welding certificates) from an institute approved by the Purchaser. Without giving any reason, the Purchaser may require the personnel deployed by the Contractor to undergo a practical examination, at the expense and risk of the Contractor. The Purchaser reserves the right to expel Contractor's personnel from site that is not adequately qualified or conducts improperly toward representatives of the Purchaser or the Final Customer or other persons. All related costs shall be borne by the Contractor.

The personnel delegated by the Contractor to the site shall exclusively execute the subject contract. The Contractor shall not employ the personnel for other purposes nor transfer them in whole or in part without the approval of the Purchaser.

The Contractor shall ensure that his managerial staff members are able to speak and write English fluently. In the event the managerial staff members do not speak English fluently, the Contractor shall make available adequately trained interpreters for the entire period of deployment on site.

21.5.6 Materials, Construction Equipment

The Contractor shall make available all materials and construction equipment required for the fulfilment of the Contract, unless otherwise expressly specified in the order. The quality of the materials shall be in compliance with the specification and standards and regulations indicated in the order and shall be documented at the Purchaser’s request.

In the event materials are used that are not subject to any quality regulation, the Contractor shall furnish adequate quality certificates. The use of such materials is subject to the express approval of the Purchaser.

The Contractor shall ensure in a timely manner that there is an adequate stock of construction material, materials and consumables on site in due time.

Any consequences regarding delays attributable to delayed availability of materials, construction materials and consumables shall be borne by the Contractor.

Page 27: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

5

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

All devices, construction equipment, consumables, temporary structures, construction materials and other supplies by the Contractor are intended to be used exclusively for the implementation and completion of the contractual work. The Contractor shall not remove such devices and materials in whole or in part without approval of the Purchaser’s site manager in writing (which shall not be withheld unreasonably) nor shall they be used for other purposes.

The Purchaser shall be informed immediately about the Contractor’s objection to the materials, components and equipment specified by the Purchaser and to instructions given in this regard to the Contractor.

21.5.7 Purchaser’s or Final Customer’s Supplies

In the event materials, prefabricated parts, construction materials, consumables, documentation, etc., are provided by the Purchaser or the Final Customer, the Contractor shall be fully responsible for their proper use. The use of the materials shall be substantiated by a materials accounting system in accordance with the bill of quantity items based on construction drawings. Any deficiencies due to improper storage or use, loss, waste, etc., shall be charged to Contractor's account at current prices. Final invoices without material accounting shall be regarded as incomplete.

The Contractor shall request such supplies in a timely manner and present a list of the materials, etc., to the Purchaser’s site manager. The list shall be grouped according to the delivery deadlines and quantities.

21.6 Modifications to the Scope of Supplies and Services

The Purchaser shall have the right to modify and/or supplement the scope of supplies and services at any time. The Contractor shall implement any modifications or supplements to the supplies and services under the terms and conditions set forth in the order.

Modifications in quantities in comparison with the data given in the bill of quantities in no case entitles to a change in the agreed unit prices. Claims under this title, e.g., additional remuneration or compensation are excluded.

The Purchaser shall be given written notice of any changes in the time schedule within 2 working days. The changes to the time schedule shall be approved by the Purchaser.

21.7 Unspecified Supplies and Services, Work on an Hourly Basis

21.7.1 The Contractor shall not execute any supplies and services which are not included in the order without receiving prior instructions in writing from the Purchaser.

In the event the work activities becomes necessary in the course of executing

contractually stipulated supplies and services for which the order does not specify any unit prices, and in the event such work is ordered by the Purchaser’s site manager, the Contractor shall carry out such work and immediately present a supplementary offer in addition to entering the performed work activities into the site diary.

Supplementary offers shall be presented prior to the performance of these services,

provided the progress of the works permits. The calculation of supplementary offers shall be accomplished on the basis of the order.

Supplementary offers shall be given only for work which in the opinion of the

Purchaser’s site manager cannot be allocated to any item in the bill of quantities. Supplementary offers will be checked by the Purchaser, discussed with the Contractor and confirmed as a supplementary order.

Page 28: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

6

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

21.7.2 The Contractor shall undertake to carry out hourly work within the scope of the contract, to the extent the Purchaser instructs the Contractor to do so. Each day the Contractor

shall list such services performed on an hourly and materials basis and present this list to the Purchaser’s site manager or his representative for approval on the following working day at the latest. Lists presented late shall not be accepted.

Materials used during such work – to the extent not already determined in the order –

shall be charged at reasonable current prices subject to revision by the Purchaser. The rates for hourly work shall be determined prior to the commencement of work,

unless otherwise specified, and shall be subject to confirmation/agreement of the Purchaser for accounting purposes. The rates determined shall be valid for the contract period.

21.7.3 The work carried out by the Contractor in accordance with Article 21.7.1 and 21.7.2 shall have no effect on the time schedule, and reimbursement in accordance with Article 20.7.1 and 20.7.2 shall constitute the full and final compensation for the work.

21.8 Deadlines

The Contractor shall be obligated to strictly adhere to the agreed time schedule. Flexible execution of the contract includes increased labour forces and/or equipment, overtime hours and shift operations in the event of impending or actual delays.

The take-over of delayed supplies and/or services by the Purchaser shall not be regarded as a waiver of any legal or contractual claim by the Purchaser which might result from such delays.

The Purchaser shall not grant any compensation for schedule or sequence changes

during the construction and assembly period.

21.9 Safety/Order/Environmental Protection

21.9.1 The Contractor and his subcontractors shall have a functional safety, health and environmental protection organisation for all activities at the construction site and shall furnish proof of this by a certificate of a safety system such as SCC, BS 8800, OHSAS, etc. The Contractor shall be held solely responsible and liable in every respect for compliance with the legal and otherwise applicable safety measures, particularly for those pertaining to the site and the type of work activities, as well as for all laws pertaining to the employment of foreign workers, etc.

The Contractor shall repair or have repaired any defect that does not meet the

respective safety standards in the equipment and machines. In the event the Contractor disregards this stipulation, the Purchaser shall be entitled to have repaired any defect that does not meet the respective safety standards in the equipment and machines at the expense of the Contractor.

The Contractor is solely responsible for the safety and quality of his supplies and

services, even in the event they have been provided by the Purchaser or Final Customer. No inspection shall release the Contractor from his full responsibility.

The Contractor shall report all accidents directly and immediately to the competent

authority and the Purchaser in the event such accidents involve the Contractor's personnel.

The Contractor’s representative shall request the Purchaser’s site manager to provide

information on the operating conditions and additional safety measures involved prior to commencement of work and shall confirm in writing that he took notice of and received

Page 29: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

7

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

the instruction sheets on the prevention of accidents. Any instructions given by the Purchaser’s site manager or the safety personnel shall be observed in each case.

21.9.2 During the implementation of the work activities, all measures shall be taken to prevent damage or contamination of existing plants, railroad facilities and roads and to avoid any hindrances to plant operation. As pertaining to work activities carried out within the Plant area, the Contractor shall observe the restrictions regarding the transportation of passengers and goods (entry and exit, obligation to identify oneself, etc.).

The Contractor shall be held responsible for protecting the equipment and materials

used on site against abuse and theft within and without the fenced-in site area. The workplaces and transportation routes shall be kept clean at all times, waste and

packing material shall be removed, taken outside and stored in such a manner that it is protected from fire and storm and disposed in accordance with the applicable legal regulations. All unclean areas resulting from the Contractor’s work activities shall be cleaned immediately by the Contractor. In the event the Contractor fails to do his own cleaning, the work shall be outsourced to a third party at the expense of the Contractor.

In the event the party responsible for the unclean area is not determined, the costs

incurred for cleaning shall be charged to the account of the Contractor on site at the respective time and shall be calculated proportionally to the respective contractual sums.

All parties involved shall be obligated to ensure smooth co-operation on site and to

settle discrepancies in due time in conjunction with the Purchaser’s site manager.

21.9.3 The Contractor shall be obligated to take all required measures (for casings, disposal of waste material, etc.) in upholding the environmental-protection laws.

21.9.4 Any breach of safety regulations, regulatory provisions and/or environmental protection regulations whatsoever shall be subject to a contractual penalty, the amount of which shall be regulated in the individual contracts/orders.

21.10 Liability

21.10.1 The Contractor shall be held fully liable for all damages attributable to him.

21.10.2 Any insurance policies provided by the Purchaser shall not release the Contractor from his liability. In the event that the Purchaser takes out insurance policies for the benefit of the Contractor, the Purchaser shall undertake to safeguard the insurance claims of the Contractor, however, without assuming the Contractor’s risks, rights and obligations thereunder. Deductibles shall be borne by the Contractor.

21.10.3 For the elimination/correction of any damage and/or contamination within the construction area of the Contractor which cannot be determined to have been caused by a certain party, all companies involved in construction at the time of the event shall be liable in proportion to their individual order values to the extent ordered by the Purchaser.

21.10.4 In the event of any damage and/or accidents involving the Contractor’s personnel, the Contractor shall be obligated to indemnify the Purchaser/the Final Customer as well as any third party.

21.10.5 The Contractor shall be fully responsible for actions of his personnel both on and off site. The Contractor shall indemnify the Purchaser and/or the Final Customer and/or third parties for all damages caused by his personnel.

Page 30: GENERAL COMMERCIAL CONDITIONS for the Purchase ... - Bilfinger · order confirmation or commences with the execution of the order, the order shall be deemed as unconditionally confirmed

8

_________________________________________________________________________________________

Annex 1 to GCC 04/2019

21.10.6 Contrary to Article 11.2 of the GCC 04/2019, the guarantee period for civil works as well as erection/commissioning activities shall be in accordance with legal provisions applicable at the location of the work activities, however, the guarantee period shall in no event expire prior to 36 months from acceptance of the entire plant by the Final Customer.

21.10.7 Contrary to Article 17 of the GCC 04/2019, the passing of risk and ownership shall be in compliance with the Final Customer contract. The relevant provisions are known to the Contractor.

21.11 Invoicing

The following shall additionally apply to Article 4 of GCC 04/2019:

21.11.1 Unless otherwise defined in the order, partial accounts can be rendered on a monthly basis for services carried out by the end of a month.

A preliminary invoice which is subject to confirmation by the Purchaser’s site manager shall be enclosed with the partial accounts.

21.11.2 The structure of all accounts shall be in compliance with the items of the bill of quantities.

21.11.3 The accounts on hourly wages and materials shall be numbered consecutively and rendered separately.

21.11.4 The final invoice in accordance with Article 4 of GCC 04/2019 shall not be issued until after elimination of defects or clarification of remaining items, if any.

All necessary accounting documents, such as mass calculations, accounting drawings, site measurements, time and material sheets, material accountings, etc., shall be enclosed with the final invoice. All dimensions of the mass calculations shall be indicated in the drawings and measurements and clearly allocable to the calculation.

The Purchaser is granted a period of up to 3 months to audit the final invoice.

21.11.5 At the time of invoicing, the fiscal regulations applicable in the respective EU country shall be taken into consideration (particularly the value-added tax).