Upload
doque
View
215
Download
0
Embed Size (px)
Citation preview
FOCUS ON COAL AND ASH HANDLING PLANT
BYN.K.SRIVASTAVA
22nd MAY,2012
CAPACITY ADDITION ANNOUNCED
Announced Capacity
920.7 Gigawatt 914 Projects
CONTINUED
Fuel Projects Capacity (MW)Coal 571 683,402
Under Construction 124 116,761 Under Implementation 111 113,044 Under Planning 336 453,597
Gas 112 111,366 Under Construction 20 10,259 Under Implementation 18 8,465 Under Planning 74 92,642
Hydro 220 86,246 Under Construction 48 13,417 Under Implementation 30 8,377 Under Planning 142 64,452
Nuclear 11 39,700 Under Construction 3 4,800 Under Planning 8 34,900
Total 11 39,700 Under Construction 195 145,237 Under Implementation 159 129,886 Under Planning 560 645,591
Grand Total 914 920,714
Key Clearances
Project Status Under Construction
Under Implementation
Under Planning
Grand Total
Cap (MW) 145,237 129,886 645,591 920,714 Total 195 159 560 914 Land 181 126 71 378 Water 181 114 74 369 Environment 183 128 86 397 Financial 169 60 12 241 Equipment 183 58 13 254
Environment Clearance Pipeline
Announced Capacity
417 Gigawatt 370 Projects
Fuel Continues to Be the Biggest Issue
Plant Type Projects CapacityLinkage 255 283,099 Captive 47 62220Imported 30 47,500 Linkage+Imported 26 35,532 Captive+Imported 5 5,770 Captive+linkage 32 36,360 Captive+Linkage+Imported 1 600 Not Finalized 175 212,321 Grand Total 571 683,402
Fuel Pipeline for the Coal Sector
203 Projects have applied for Linkage but is pending
MAJOR PLAYERS
• Coal Companies (CIL)• Railways • Power Generation Companies • CHP Equipment suppliers and contractors
Major Issues
• Coal quality• Coal Transportation• Coal stock• Competent contractors
Coal Quality
• very variable • ash content – system capacity, component life• moisture & fines – flowability in hoppers, chutes,
housekeeping• oversize quantity – delays in unloading ,
additional handling• stones and trash – delays in unloading, removal
facilities, damage to equipment
Coal transportation
• Bunching of rakes
Coal stock
• Actual delivery less than requirement• Imported coal
- handling - blending with domestic coal
CHP /AHP suppliers- Issues• Limited numbers/Bunching of Orders.• Shortage of skilled Manpower/Capabilities• Core competency in executing Civil works• Good Civil sub contractors.• Fabrication works execution.• Standardisation by Utilities• Steel procurement/Availability of fronts• Skewed Cash Flow strategies• Interface issues with main plant& other
Vendors
Trends in manufacturing capacities of key CHP and AHP players
• CHP manufacturing companies have augmentedtheir in-house manufacturing capacities to meetthe new challenges of capacity additionprogramme of XII and XIII th Plan.
• Need for a good AHP player is there . Manycompanies are trying to enter in the fray.
Key Technology Developments
L&T:Wagon Shifters and Pushers :Developed for reducing the space requirements inouthaul side of Wagon Tippler Complex and toreduce the unloading time. Revolutionarydevelopment considering paucity of free hold land.Wagon Tipplers: Development to meet the latest requirements of
RDSO G-33 specification, which has come intoforce from 1st December 2010.
• Hydraulic Drives for Conveyors –. Low / zerorunning maintenance cost.
• Stacker Reclaimer bucket wheel & slew drives.These will increase the efficiencies over theelectro mechanical drives, lower maintenance,reduction in overall machine weight.
• Permanent Deck sheets for floor slab castingsagainst the conventional shuttering, leads tofaster construction.
Key Technology Developments
Key Technology Developments
• Flow dividing concept in the junction towers, forefficient blending
• Increased belt speed up to 4.8 m/sec.• HT and LT cables are routed through conveyor
galleries, instead of cable trestles• Single CHP for both phases of the power plant – e.g.
Adani Tiroda,etc.-High capacity CHP 3000-5000TPH• Rapid unloading system for small Track Hopper
Recently executed projects, their highlights and learning's
• Utilities are switching for Wagon Tipplers, toaddress latest RDSO guidelines and ensureminimum unloading rate of 25 tips / hr.
• Reduced Engineering approval time – for all thecustomers
• Ensure faster availability of customers’ inputs – tobe done by utilities.
Recently executed projects, their highlights and learning's
• In recent times, most of the utilities are including theBunker TP’s in the scope of CHP Contractor to avoid thedelays in overall plant completion, e.g. Malwa CHP, DBPower CHP.
• Overall CHP execution time has come down. CHPs arenow being executed in 20 months – e.g. Mahan CHP.
• Tuticorin Coal Handling Plant for NTPL (2 x 500 MW) -port based power plant, includes marine piles, 2.2 km ofoff Shore Conveyor with Hydraulic conveyor drives for12 conveyors.
TRENDS IN MANUFACTURING CAPACITIES
-NO CLEAR TRENDS SEEN IN EXPANSION OF MANUFACTURING CAPACITY IN INDUSTRY
-PLAYERS ARE GENERALLY STICKING TO CORE AREAS
KEY TECHNOLOGY DEVELOPMENT
- HIGH CONCENTRATION SLURRY DISPOSAL SYSTEM
- DRY BOTTOM ASH SYSTEM
LEARNINGS FROM PROJECTS UNDER EXECUTION-
-DELAYS IN ASH HANDLING SYSTEM:
DELAY DUE TO EXECUTION OF CIVIL & STRUCTURAL WORKS.COLLABORATORS FULL FLEDGED NON INVOLVEMENT.DELAY IN PLACEMENT OF ORDERS FOR BOUGHTOUT ITEMS.NONAVAILABILITY OF EXPERIENCED & SKILLED MANPOWER FOR PROJECT EXECUTION.NON STANDARDISATION OF SYSTEM.FINANCIAL CAPABILITIES OF CONTRACTORS.
THANK YOU
KEY TECHNOLOGICAL DEVELOPMENTS
- LATEST HIGH CAPACITY WAGON TIPPLERS (CONFORMING TO RDSO G33 Rev.1)
-HIGH CAPACITY CHPs (3000TPH-5000TPH)
- HYDRAULIC DRIVE IN PLACE OF ELECTRO-MECHANICAL DRIVE FOR MAJOR EQUIPMENTS LIKE TIPPLER, STACKER CUM RECLAIMER
TRENDS IN MANUFACTURING CAPACITIES
- HAVE GENERALLY INVESTED IN EXPANDINGMANUFACTURING CAPACITIES TO CATER TOHIGHER PRODUCTION VOLUME REQUIRED FOR UPCOMING PROJECTS
- HAVE GONE IN FOR COLLABORATION/ ASSOCIATION/ JOINT VENTURES WITH VARIOUS FOREIGN PARTIES TO EXPAND THEIR RANGE
RECENTLY EXECUTED PROJECTRECENTLY EXECUTED PROJECT-- HIGHLIGHT & HIGHLIGHT & LEARNINGLEARNING
--HIGH CAPACITY PLANT OPERATING SUCCESSFULLY.HIGH CAPACITY PLANT OPERATING SUCCESSFULLY.
--CAN PLAN FOR HIGHER CAPACITY CHP.CAN PLAN FOR HIGHER CAPACITY CHP.
-- GENERAL SHORTAGE OF SKILLED MANPOWERGENERAL SHORTAGE OF SKILLED MANPOWER