Flexible Budgets, Variances, and Management Control: I. Chapter 7. Distinguish a static budget from a flexible budget. Learning Objective 1. Static and Flexible Budgets. Planned level of output at start of the budget period. Based on. Static Budget. Budgeted revenues and cost based on - PowerPoint PPT Presentation

Citation preview

Page 1: Flexible Budgets, Variances, and Management Control: I

7 - 1©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgets, Variances,and Management Control: IFlexible Budgets, Variances,and Management Control: I

Chapter 7

Page 2: Flexible Budgets, Variances, and Management Control: I

7 - 2©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Distinguish

a static budget

from a flexible budget.

Learning Objective 1Learning Objective 1

Page 3: Flexible Budgets, Variances, and Management Control: I

7 - 3©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static and Flexible BudgetsStatic and Flexible Budgets

Static BudgetPlanned level ofoutput at start ofthe budget period

Based on

Flexible BudgetBudgeted revenuesand cost based on

actual level of output

Based on

Page 4: Flexible Budgets, Variances, and Management Control: I

7 - 4©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static Budget ExampleStatic Budget Example

Assume that Pasadena Co. manufacturesand sells dress suits.

Budgeted variable costs per suit are as follows:Direct materials cost $ 65

Direct manufacturing labor 26Variable manufacturing overhead 24

Total variable costs $115

Page 5: Flexible Budgets, Variances, and Management Control: I

7 - 5©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static Budget ExampleStatic Budget Example

Budgeted selling price is $155 per suit.

Fixed manufacturing costs are expectedto be $286,000 within a relevant range

between 9,000 and 13,500 suits.

Variable and fixed period costs are ignored.

The static budget for year 2004 is basedon selling 13,000 suits.

What is the static-budget operating income?

Page 6: Flexible Budgets, Variances, and Management Control: I

7 - 6©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static Budget ExampleStatic Budget Example

Revenues (13,000 × $155) $2,015,000Less Expenses:Variable (13,000 × $115) 1,495,000Fixed 286,000Budgeted operating income $ 234,000

Assume that Pasadena Co. produced and sold10,000 suits at $160 each with actual variablecosts of $120 per suit and fixed manufacturing

costs of $300,000.

Page 7: Flexible Budgets, Variances, and Management Control: I

7 - 7©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static Budget ExampleStatic Budget Example

Revenues (10,000 × $160) $1,600,000 Less Expenses: Variable (10,000 × $120) 1,200,000 Fixed 300,000 Actual operating income $ 100,000

What was the actual operating income?

Page 8: Flexible Budgets, Variances, and Management Control: I

7 - 8©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static-Budget Variance ExampleStatic-Budget Variance Example

What is the static-budget variance ofoperating income?

Actual operating income $100,000Budgeted operating income 234,000Static-budget variance of operating income $134,000 U

This is a Level 0 variance analysis.

Page 9: Flexible Budgets, Variances, and Management Control: I

7 - 9©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static-Budget Variance ExampleStatic-Budget Variance Example

Static-Budget Based Variance Analysis(Level 1) in (000) Static Budget Actual Variance

Suits 13 10 3 URevenue $2,015 $1,600 $415 UVariable costs 1,495 1,200 296 FContribution margin $ 520 $ 400 $120 UFixed costs 286 300 14 UOperating income $ 234 $ 100 $134 U

Page 10: Flexible Budgets, Variances, and Management Control: I

7 - 10©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 2Learning Objective 2

Develop a flexible budgetand compute flexible-budgetvariances and sales-volume

variances.

Page 11: Flexible Budgets, Variances, and Management Control: I

7 - 11©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Steps in Developing Flexible Budgets

Steps in Developing Flexible Budgets

Step 1:Determine budgeted selling price, variable

cost per unit, and budgeted fixed cost.

Budgeted selling price is $155,variable cost is $115 per suit, and

the budgeted fixed cost is $286,000.

Page 12: Flexible Budgets, Variances, and Management Control: I

7 - 12©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Steps in Developing Flexible Budgets

Steps in Developing Flexible Budgets

Step 2:Determine the actual quantity of output.

In the year 2004, 10,000 suits wereproduced and sold.

Step 3:Determine the flexible budget for revenues.

$155 × 10,000 = $1,550,000

Page 13: Flexible Budgets, Variances, and Management Control: I

7 - 13©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Steps in Developing Flexible Budgets

Steps in Developing Flexible Budgets

Step 4:Determine the flexible budget for costs.

Variable costs: 10,000 × $115 = $1,150,000Fixed costs 286,000Total costs $1,436,000

Page 14: Flexible Budgets, Variances, and Management Control: I

7 - 14©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

VariancesVariances

Level 2 analysis provides informationon the two components of the

static-budget variance.

1. Flexible-budget variance

2. Sales-volume variance

Page 15: Flexible Budgets, Variances, and Management Control: I

7 - 15©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible-Budget VarianceFlexible-Budget Variance

Flexible-Budget Variance(Level 2) in (000)

Flexible Budget Actual Variance

Suits 10 10 0Revenue $1,550 $1,600 $ 50 FVariable costs 1,150 1,200 50 UContribution margin $ 400 $ 400 $ 0Fixed costs 286 300 14 UOperating income $ 114 $ 100 $ 14 U

Page 16: Flexible Budgets, Variances, and Management Control: I

7 - 16©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible-Budget VarianceFlexible-Budget Variance

Actual quantity sold: 10,000 suits

Flexible-budgetvariance

$14,000 U

Actual resultsoperating income

$100,000

Flexible-budgetoperating income

$114,000

Page 17: Flexible Budgets, Variances, and Management Control: I

7 - 17©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible-Budget VarianceFlexible-Budget Variance

Total flexible-budget variance= Total actual results

– Total flexible budget for actual sales level

Page 18: Flexible Budgets, Variances, and Management Control: I

7 - 18©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible-Budget VarianceFlexible-Budget Variance

Actual Budgeted Amount Amount

Selling price $160 $155Variable cost 120 115Contribution margin $ 40 $ 40

Page 19: Flexible Budgets, Variances, and Management Control: I

7 - 19©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible-Budget VarianceFlexible-Budget Variance

Why is the flexible-budget variance $14,000 U?

Selling-price variance $50,000 F

Actual variable costs exceededflexible budget variable costs 50,000 U

Actual fixed costs exceededflexible budget fixed costs 14,000 U

Total flexible-budget variance $14,000 U

Page 20: Flexible Budgets, Variances, and Management Control: I

7 - 20©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Sales-Volume VarianceSales-Volume Variance

Sales-Volume Variance(Level 2) in (000)

Flexible Static Sales-VolumeBudget Budget Variance

Suits 10 13 3 URevenue $1,550 $2,015 $465 UVariable costs 1,150 1,495 295 FContr. margin $ 400 $ 520 $120 UFixed costs 286 286 0Operating income $ 114 $ 234 $120 U

Page 21: Flexible Budgets, Variances, and Management Control: I

7 - 21©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Sales-Volume VarianceSales-Volume Variance

Actual quantity sold: 10,000 suits

Sales-volumevariance

$120,000 U

Flexible-budgetoperating income

$114,000

Static-budgetoperating income

$234,000

Page 22: Flexible Budgets, Variances, and Management Control: I

7 - 22©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Sales-Volume VarianceSales-Volume Variance

Total sales-volume variance $120,000 U

=

Actual sales unit – Master budgeted sales units13,000 – 10,000 = 3,000×

Budgeted contribution margin per unit $40

Page 23: Flexible Budgets, Variances, and Management Control: I

7 - 23©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Budget VariancesBudget Variances

Static-budgetvariance

$134,000 U

Flexible-budgetvariance

$14,000 U

Level 1

Sales-volumevariance

$120,000 ULevel 2

Page 24: Flexible Budgets, Variances, and Management Control: I

7 - 24©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 3Learning Objective 3

Explain why standard costs areoften used in variance analysis.

Page 25: Flexible Budgets, Variances, and Management Control: I

7 - 25©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

StandardsStandards

Pasadena’s budgeted cost for each variabledirect cost item is computed as follows:

Standard inputallowed for

one output unit

Standard costper input unit

×

Page 26: Flexible Budgets, Variances, and Management Control: I

7 - 26©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

StandardsStandards

4.00 square yards allowed per output unit at $16.25 standard cost per square yard.

Standard cost per output unit 4.00 × $16.25 = $65.00

Page 27: Flexible Budgets, Variances, and Management Control: I

7 - 27©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

StandardsStandards

2.00 manufacturing labor-hours of inputallowed per output unit at $13.00 standard

cost per hour.

Standard cost per output unit2.00 × $13.00 = $26.00

Page 28: Flexible Budgets, Variances, and Management Control: I

7 - 28©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 4Learning Objective 4

Compute price variancesand efficiency variances

for direct-cost categories.

Page 29: Flexible Budgets, Variances, and Management Control: I

7 - 29©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Actual DataActual Data

Direct materials purchased and used:42,500 square yards at $15.95

Labor hours: 21,500 at $12.90

Cost of direct materials = $677,875

Cost of direct manufacturing labor = $277,350

Page 30: Flexible Budgets, Variances, and Management Control: I

7 - 30©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Price Variance ExamplePrice Variance Example

Direct-material price variance

Actual price – Budgeted price

× Actualquantity

($15.95 – $16.25) × 42,500 = $12,750 F=

=

Page 31: Flexible Budgets, Variances, and Management Control: I

7 - 31©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Price Variance ExamplePrice Variance Example

Direct-labor price variance

Actual price – Budgeted price

× Actualquantity

($12.90 – $13.00) × 21,500 = $2,150 F=

=

Page 32: Flexible Budgets, Variances, and Management Control: I

7 - 32©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Price Variance ExamplePrice Variance Example

What is the journal entry when the materials pricevariance is isolated at the time of purchase?

Materials Control 690,625Direct-Materials Price Variance 12,750Accounts Payable Control 677,875To record direct materials purchased

Page 33: Flexible Budgets, Variances, and Management Control: I

7 - 33©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Efficiency Variance ExampleEfficiency Variance Example

Direct-material efficiency variance

Actual quantity – Standard

quantity× Standard

price

(42,500 – 40,000) × $16.25 = $40,625 U=

=

Page 34: Flexible Budgets, Variances, and Management Control: I

7 - 34©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Efficiency Variance ExampleEfficiency Variance Example

Direct-labor efficiency variance

Actual quantity – Standard

quantity× Standard

price

(21,500 – 20,000) × $13.00 = $19,500 U=

=

Page 35: Flexible Budgets, Variances, and Management Control: I

7 - 35©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Efficiency VarianceEfficiency Variance

What is the journal entry to record materials used?

Work in Process Control 650,000Direct-Materials Efficiency Variance 40,625

Materials Control 690,625To record direct materials used

Page 36: Flexible Budgets, Variances, and Management Control: I

7 - 36©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Price and Efficiency VariancePrice and Efficiency Variance

What is the journal entry for direct manufacturing labor?

Work in Process Control 260,000Direct ManufacturingLabor Efficiency Variance 19,500

Direct-ManufacturingLabor Price Variance 2,150Wages Payable 277,350

To record liability for direct manufacturing labor

Page 37: Flexible Budgets, Variances, and Management Control: I

7 - 37©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budget MaterialVariance Example

Flexible Budget MaterialVariance Example

ActualCost

$677,875

BQ × BP40,000 × $16.25

$650,000

AQ × BP42,500 × $16.25

$690,625

$12,750 F $40,625 U

$27,875 U

Page 38: Flexible Budgets, Variances, and Management Control: I

7 - 38©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budget LaborVariance Example

Flexible Budget LaborVariance Example

ActualCost

$277,350

BQ × BP20,000 × $13.00

$260,000

AQ × BP21,500 × $13.00

$279,500

$2,150 F $ 19,500 U

$17,350 U

Page 39: Flexible Budgets, Variances, and Management Control: I

7 - 39©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Static-budget varianceMaterials $167,125 FLabor 60,650 FTotal $227,775 F

Flexible-budget varianceMaterials $27,875 ULabor 17,350 UTotal $45,225 U

Sales-volume varianceMaterials $195,000 FLabor 78,000 FTotal $273,000 F

Level 1

Level 2

Variance AnalysisVariance Analysis

Level 2

Page 40: Flexible Budgets, Variances, and Management Control: I

7 - 40©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible-budget varianceMaterials $27,875 ULabor 17,350 UTotal $45,225 U

Price varianceMaterials $12,750 FLabor 2,150 FTotal $14,900 F

Efficiency varianceMaterials $40,625 ULabor 19,500 UTotal $60,125 U

Level 2

Level 3

Variance AnalysisVariance Analysis

Level 3

Page 41: Flexible Budgets, Variances, and Management Control: I

7 - 41©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 5Learning Objective 5

Explain why purchasingperformance measures should

focus on more factors thanjust price variances.

Page 42: Flexible Budgets, Variances, and Management Control: I

7 - 42©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Performance MeasurementUsing Variances

Performance MeasurementUsing Variances

Effectiveness is the degree to which apredetermined objective or target is met.

Efficiency is the relative amount of inputsused to achieve a given level of output.

Variances should not solely be used toevaluate performance.

Page 43: Flexible Budgets, Variances, and Management Control: I

7 - 43©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

When to Investigate VariancesWhen to Investigate Variances

When should variances be investigated?

Subjective judgments

Rules of thumb as “investigate all variancesexceeding $10,000 or 25% of expected cost,

whichever is lower.”

Page 44: Flexible Budgets, Variances, and Management Control: I

7 - 44©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 6Learning Objective 6

Integrate continuousimprovement

into variance analysis.

Page 45: Flexible Budgets, Variances, and Management Control: I

7 - 45©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Continuous ImprovementContinuous Improvement

Assume that the budgeted direct materials cost foreach suit that Pasadena Co. manufactures is $65.

Pasadena Co. wants to implement continuousimprovement budgets based on a target 1%

materials cost reduction each period.

What should the budgeted cost be for thenext 3 subsequent periods?

Page 46: Flexible Budgets, Variances, and Management Control: I

7 - 46©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Continuous ImprovementContinuous Improvement

Prior Period Reduction Revised Budgeted in

Budgeted Amount Budget

AmountThis Period: – – $65.00Period 1: $65.00 $0.650

$64.35Period 2: $64.35 $0.644

$63.71Period 3: $63.71 $0.637

$63.07

Page 47: Flexible Budgets, Variances, and Management Control: I

7 - 47©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 7Learning Objective 7

Perform variance analysis inactivity-based costing systems.

Page 48: Flexible Budgets, Variances, and Management Control: I

7 - 48©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgeting andActivity-Based CostingFlexible Budgeting andActivity-Based Costing

Materials costs and direct manufacturing laborcosts are examples of output-unit level costs.

Batch-level costs are resources sacrificedon activities that are related to a group of

units of product(s) or service(s) rather thanto each individual unit of product or service.

Page 49: Flexible Budgets, Variances, and Management Control: I

7 - 49©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgeting andActivity-Based CostingFlexible Budgeting andActivity-Based Costing

Denver Co. produces metal planters (MP).

Assume that material-handling labor costs varywith the number of batches produced rather

than the number of units in a batch.

Material-handling labor costs are direct batchlevel costs that vary with the number of batches.

Page 50: Flexible Budgets, Variances, and Management Control: I

7 - 50©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgeting and Activity-Based Costing

Flexible Budgeting and Activity-Based Costing

Static ActualBudget Amounts

Units produced and sold 18,000 15,660Batch size 180 174Number of batches 100 90Material-handling labor-hours per batch 5.00 5.20

Page 51: Flexible Budgets, Variances, and Management Control: I

7 - 51©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgeting and Activity-Based Costing

Flexible Budgeting and Activity-Based Costing

Static Actual

Budget AmountsTotal labor-hours 500

468Cost per material-handling labor-hour

$14.00 $14.50Total material-handling

labor cost$7,000 $6,786

Page 52: Flexible Budgets, Variances, and Management Control: I

7 - 52©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgeting andActivity-Based CostingFlexible Budgeting andActivity-Based Costing

How many batches should have been employedto produce the actual output units?

15,660 units ÷ 180 units per batch = 87 batches

How many material-handling hoursshould have been used?

87 batches × 5 hours/batch = 435 hours

Page 53: Flexible Budgets, Variances, and Management Control: I

7 - 53©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Flexible Budgeting andActivity-Based CostingFlexible Budgeting andActivity-Based Costing

What is the flexible budget formaterial-handling labor-hours?

435 hours × $14.00/labor-hour = $6,090

Flexible-budget costs $6,090 Actual costs 6,786 Flexible-budget variance $ 696 U

Page 54: Flexible Budgets, Variances, and Management Control: I

7 - 54©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Price and Efficiency VariancesPrice and Efficiency Variances

Price variance = ($14.50 – $14.00) × 468 = $234 U

Efficiency variance = (468 – 435) × $14.00 = $462 U

Total variance $696 U

Page 55: Flexible Budgets, Variances, and Management Control: I

7 - 55©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

Learning Objective 8Learning Objective 8

Describe benchmarkingand how it is used

in cost management.

Page 56: Flexible Budgets, Variances, and Management Control: I

7 - 56©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

BenchmarkingBenchmarking

It refers to the continuous process ofmeasuring products, services, and activities

against the best levels of performance.

Page 57: Flexible Budgets, Variances, and Management Control: I

7 - 57©2003 Prentice Hall Business Publishing, Cost Accounting 11/e, Horngren/Datar/Foster

End of Chapter 7End of Chapter 7