Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
FEASIBILITY STUDY
US 127 / US 224 / MARSH ROAD INTERSECTION IMPROVEMENTS
PID 110430
JANUARY 2020
Prepared For:
ODOT District 1
1885 North McCullough Street
Lima, Ohio 45801
Prepared By:
Fishbeck, Thompson, Carr & Huber, Inc.
1 East Campus View Boulevard, Suite 310
Columbus, Ohio 43235
The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have
been, carried‐out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated June 6, 2018, and executed by FHWA and ODOT.
2
Table of Contents
I. Introduction ............................................................................................................................. 3
II. Purpose & Need ....................................................................................................................... 4
III. Alternatives ............................................................................................................................. 5
IV. Key Issues ................................................................................................................................ 7
V. Alternatives Comparison ........................................................................................................ 13
VI. Conclusion ............................................................................................................................. 13
List of Figures
Figure 1 – Project Location Map
Figure 2 – Project Issues Map
Figure 3 – Intersection Evaluation Matrix
List of Tables
Table 1 – Design Speed and Functional Class
Table 2 – Traffic Data
Table 3 – ODOT L&D Standard Design Criteria
Table 4 – Anticipated Right‐of‐Way Impacts
Table 5 – Preliminary Construction Costs
List of Appendices
Appendix A – Alternative Layouts
Appendix B – Traffic Data and Capacity Analysis
Appendix C – Crash Data and Safety Analysis
Appendix D – Alternative Typical Sections
Appendix E – Maintenance of Traffic Concepts
Appendix F – Alternatives Construction Costs
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 3
I. Introduction
The purpose of this report is to present alternative improvements for the U.S. 127/U.S. 224 intersection with Marsh
Road in Van Wert County, Ohio and identify a preferred alternative for detailed engineering design. This project will
include the safety improvements to the U.S. 127/U.S. 224 intersection with Marsh Road. The project will improve
safety by means of adding turn lanes and roadway realignment as Alternative 1 or by providing a single lane
roundabout as Alternative 2. The recommended alternative will be considered by evaluating overall improvement to
safety, construction costs, environmental impacts, right of way impacts, utility adjustments, and maintenance of
traffic. The project footprint will include approximately 1,500 ft west of the intersection on U.S. 127/U.S. 224, 1,200
ft south of the intersection on Marsh Road, 1,700 ft east of the intersection on U.S. 224, and 800 ft north of the
intersection on U.S. 127.
Background
The intersection of US 127 (north-west legs), US 224 (east-west legs), and Marsh Road (south leg) is located at US
127 mile marker 12.22 and US 224 mile marker 15.86. The west leg of the intersection operates as both US 127 and
US 224, the north leg operates as US 127, the east leg operates as US 224, and the south leg operates as Marsh Road
(CR 13). The intersection lies just north of the city of Van Wert in Van Wert County. US 127, US 224, and Marsh Road
are all 2-lane highways. The lane widths on the north, east, and west legs are 12’ with 2’ paved and 2’ aggregate
shoulders. Marsh Road is comprised of two 10’ wide lanes and negligible improved shoulders. The intersection is
stop-controlled in the northbound and southbound directions. The northbound and southbound approaches both
have dual stop ahead and dual stop signs. The stop ahead signs on the right side of the northbound and southbound
lanes have solar powered flashing LED lights. The east and west approach legs both have dual intersection ahead
signs. The westbound approach has a right reverse curve ahead sign with a 45 mph advisory speed while the
eastbound approach has left directed chevrons through the intersection.
Figure 1 – Project Location Map
Figure 2 – Project Issues Map
Previous Safety Reports and Studies:
This intersection has been studied multiple times, most recently as a Safety Study in 2018. This study recommended
the removal of overhead flasher heads and that a flashing stop ahead sign be added to the right side of the
southbound direction. A left turn lane (eastbound to northbound) and a right turn lane (southbound to westbound)
appeared to be warranted based upon turning movement counts. As was determined during previous studies, it was
determined that right-of-way takes would be too costly to implement the necessary roadway widening.
Prior to the 2018 study, there was discussion of installing a left turn lane on the west approach in 1998 and another
Safety Study in 2015. The 2015 study resulted in no recommendations and noted that while the left turn lane was
likely still warranted, the R/W cost would be too great. Signal warrants were investigated as part of the 2018 Safety
Study. As part of the 2018 safety study, turning movement counts were taken at this intersection on Thursday
January 25, 2018. The turning movement counts were seasonally adjusted and signal warrants were reviewed for
the intersection. The site did not meet any of OMUTCD warrants 1-3.
Governor Mike DeWine Intersection Safety Initiative
After securing additional funding for transportation infrastructure through the increased gas user fee, Governor
Mike DeWine designated $50 million annually for roadway locations, such as intersections, where a project could
improve its safety. Statewide, more than 150 rural, suburban and urban intersections have been selected by
Governor DeWine for review and safety improvements. Improvements range from signal and signage improvements
to a complete intersection redesign. As a result of the increase, ODOT now has the third largest road safety program
in the country. Over the next four years, ODOT will spend $159 million annually on preventing crashes on Ohio
roads. The U.S. 127/U.S. 224 intersection with Marsh Road in Van Wert County was identified on the list as a
location where a project held good potential of yielding an improvement in safety.
Project
Location
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 4
II. Purpose & Need
Project History
The project area is located at the US Route 127, Marsh Road (County Road 13) and US Route 224 intersection, which
is just to the north of the City of Van Wert, in Van Wert County, Ohio. This intersection is part of Governor Dewine’s
list of 150 projects that improve safety in Ohio’s intersections with the highest incidences of crashes. The intersection
has been studied several times, most recently in a Safety Study that was completed in 2018. Prior to the 2018 study,
the intersection also had a Safety Study conducted in 2015, and in 1998, ODOT considered installing a left turn lane
on the west approach of the intersection. The intersection has had several low-cost safety countermeasures installed
previously, including items such as:
• Overhead two-way flasher heads with stop red flashers for northbound & southbound approaches and
caution yellow flashers for eastbound & westbound approaches. These have since been removed as the poles
supporting the two-way flasher heads restricted sight distance;
• Dual stop signs for both the northbound and southbound approaches with “Cross Traffic Does Not Stop”
placards on the near mounted stop signs;
• Dual stop ahead warning signs on both the northbound and southbound approaches;
• Dual intersection ahead warning signs on both the eastbound and westbound approaches;
• Chevron curve warning signs for eastbound traffic and a curve ahead 45 mph speed advisory warning sign for
westbound traffic
Despite these enhanced lower cost safety measures, crashes continue to occur. In the 2016 HSIP (2014-2016) Rural
Intersection Peak Excess Locations this intersection ranked #29 for rural intersections in Ohio. A traffic signal was
considered for the intersection, however traffic signal warrants conducted in the 2018 Safety Study revealed that no
signal warrants could be met based on current traffic volumes.
Purpose Statement
The purpose of the project is to reduce crashes/improve safety and improve roadway geometrics at an intersection
that currently experiences a high-level crash rate.
Need Elements
Need Elements for the project are identified as contributing factors to crash history patterns; intersection and
geometric issues; and are supported in planning documents. The needs identified include:
• Current Crash Types & Frequency – A review of the most recent three-year crash data using ODOT’s CAM-Tool
for the period of 2016-2018 revealed the crash frequencies, severity, and types of crashes listed below. These
categories continue to exceed statewide averages for injury crashes, rear-end crashes, and angle crashes.
Crash Data (2016‐2018)
Crash Frequency by Year 2016 2017 2018
5 2 2
Crash Severity Injury Crash Property Damage Only Crash
3 (33.3%) 6 (66.7%)
Type of Crash Rear‐End Angle
6 (66.7%) 3 (33.3%)
• Safety Study & Crash Listing – An ODOT Safety Study was conducted in 2018, which revealed the intersection
had 17 crashes over the period of 2014-2016, with nine (52.9%) being injury crashes, which is double the
statewide average of 26.1% for similar roadways. There were three types of crashes at this intersection with
percentages higher than statewide averages.
2018 Safety Study Crash Types (2014‐2016)
Crash Type Number of
Crashes
Percentage of
US 127 / US 224
Intersection Crashes
State Average
Rear End 10 58.8% 31.1%
Angle 4 23.5% 16.0%
Head On 1 5.9% 0.7%
The Ohio Strategic Highway Safety Plan (SHSP) lists intersection crashes as a key Target Emphasis Area to
reduce these types of crashes; and, in the 2016 HSIP (2014-2016) Rural Intersection Peak Excess Locations
listings published by ODOT, the US 127 & US 224 intersection ranked #29 for high crash intersections in Ohio.
• Intersection Geometrics - The 2018 Safety Study identified that the east-west movement through the
intersection involves horizontal curvature in the roadway. Intersection sight distance was reviewed for a
50 mph design speed standard, and it was found that the southbound approach does not have sight distance
issues up to 50 mph; however, the speed limit of all approaches is 55 mph with a 60 mph design speed
standard. Given this limit on adequate sight distance being a 50 mph design speed threshold, this existing
condition has been addressed with short-term low cost countermeasures involving chevron curve warning
signs for the eastbound traffic. For the westbound traffic, there is a curve warning sign with an advisory speed
limit of 45 mph posted prior to the curve. Longer-term solutions should address this geometric issue.
Summary Statement
The purpose of the project is to enhance intersection safety to alleviate crash patterns that are contributing to injury
crash occurrences higher than statewide percentages; and to improve intersection geometrics. The need elements
include:
• Crash history listing
• Safety Study crash pattern findings
• Intersection geometrics
Logical Termini and Independent Utility
The intersection of US 127/Marsh Road (CR-13) and US 224 located in Van Wert County is located just north of the
city of Van Wert, Ohio. The intersection serves as a transitional area from rural areas of Van Wert County to the urban
areas of the city of Van Wert. The proposed project has independent utility in that it will address the transportation
needs at this problematic intersection that was ranked as the #29 high crash rural intersections per the ODOT 2016
HSIP listings. The safety project would improve intersection safety and address geometric issues. No other
improvements outside of the identified intersection area are necessary to address the purpose and need of the
proposed project.
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 5
III. Alternatives
The project’s Scope of Services and Purpose & Need guided the development and evaluation of alternatives. Two
different build alternatives were considered for this rural, four-leg intersection. These alternatives are conceptually
shown with larger detail in Appendix A. The two alternatives studied are as follows:
Alternative 1 – Added Turn Lanes
• Left turn lanes provided for both the eastbound and westbound directions
• Eastbound-westbound tangent through intersection
• Southbound right turn only slip lane that joins westbound lane parallel to and then merges with thru lane
• Major realignment of east approach leg with driveway access road
• Minor realignment of north and south approach legs
Alternative 2 – Single Lane Roundabout
• Single lane roundabout with a 130’ (minimum) inscribed diameter
• Approximately centered about the existing intersection
• Minor realignment of each approach leg for deflection
• Elongated splitter islands
The following concepts were initially considered and subsequently dismissed as part of the early vetting process, in
coordination with District 1 staff.
A. No Build
The No Build concept does not achieve the Purpose & Need of the project, to improve intersection safety and
reduce crashes.
B. Unsignalized RCUT with Loons
This concept considered eastbound and westbound approach dedicated left turns, right turn only for the
northbound and southbound approaches, and U-turn loons on east and west approaches (approximately 1000 ft
away from intersection). The concept eliminated due to higher amount of right-of-way acquisition and construction
costs than Alternatives 1 and 2, and the alternative is generally unfamiliar to the public.
C. RCUT w/Medians
This concept was considered as a similar configuration as the Unsignalized RCUT with Loons, but to provide the U-
turns as median style U-turns and without the pavement loons. This concept would have required a much higher
amount of right-of-way acquisition and construction costs than Alternatives 1 or 2.
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 6
D. Dual Roundabouts
This concept considered the use of two 3-legged roundabout intersections, one on the northwest quadrant and one
on the southwest quadrant. This would meet the desired safety results while avoiding impacts to the houses on the
northeast and southwest quadrant. A large amount of right-of-way would be required in the northwest and
southeast quadrants. The surrounding area is not familiar with roundabouts so going from no roundabouts to a
double roundabout would likely not be positively received by the public.
E. Peanut Roundabout
Like the double roundabout concept, a peanut shaped roundabout was considered. This would meet the desired
safety results while avoiding impacts to the houses on the northeast and southwest quadrant. A large amount of
right-of-way would be required in the northwest and southeast quadrants. A peanut shaped roundabout is
unconventional and would likely not be positively received by the public. Truck drivers driving from west to north on
US 127 would not likely welcome this alternative.
F. US 127 Realignment w/US 224 & Marsh Road Realignments
This concept was a realignment of US 127 to become the through movement while US 224 would be realigned to
form a T-intersection with US 127. Marsh Road would be realigned to form a T-intersection with US 224. This
alternative would also add more left turns and may not alleviate much of the existing safety issues. The US 127
horizontal realignment could only provide a 50 mph design speed curve without impact to the Town Creek bridge.
G. US 127 Realignment w/US 224 & Marsh Road Realignments, Access to Mega Build Site
This concept kept the US 127 realignment while Marsh Road and US 224 would be realigned to form an intersection
with an entrance to the Mega Build Site. A short roadway segment would connect US 127 to the Mega Build Site
intersection. While at some point in the future, access to the Mega Build Site may be incorporated, there is currently
no plan to develop and there is potential it would not develop anytime soon. This concept would also add another
intersection with left turns and may not alleviate any of the safety issues with the current intersection. The US 127
horizontal realignment could only provide a 50 mph design speed curve without impact to the Town Creek bridge.
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 7
H. US 127 Realignment w/US 224 Bridge
This concept considered the US 127 realignment with Marsh Road being realigned to form a T-intersection at US
127. US 224 would be realigned away from Marsh Road to intersect US 127 just north of the Town Creek bridge, at
the Union Pleasant Road intersection. The alternative would seem to alleviate some of the safety issues with the
current intersection; however, this alternative would involve a new bridge structure, work within Town Creek, a
large right-of-way footprint, and a very high construction cost. The US 127 horizontal realignment could only provide
a 50 mph design speed curve without impact to the existing Town Creek bridge.
I. Add Turn Lanes & Improved East‐West Horizontal Curve Through Intersection
This concept considered adding dedicated left turn lanes for the east and west approach, a southbound to
westbound slip lane, and providing an improved horizontal curve through the intersection in the east-west direction.
the US 127 realignment with Marsh Road being realigned to form a T-intersection at US 127. US 224 would be
realigned away from Marsh Road to intersect US 127 just north of the Town Creek bridge, at the Union Pleasant
Road intersection. The US 127 horizontal realignment could not provide a 60 mph design speed curve with a
superelevation less than 4% without generating adverse impacts to the properties on the northeast corner of the
intersection. In addition, the Marsh Road approach would have required lengthening for a proposed profile to tie
into the superelevated section.
IV. Key Issues
A. Traffic Analysis
US 127 and US 224 within the project limits are both classified as Rural, Minor Arterials with posted speed limits of
55 mph and design speeds of 60 mph. Marsh Road is considered a Rural Major Collector with a posted speed limit of
55 mph and design speed of 60 mph. See Appendix B for current (2018) traffic counts and turning movements as
well as opening year (2022), and design year (2042) traffic data and turning movement forecasts. Growth rates
utilized in the traffic analysis were based upon the traffic data provided by ODOT for the 2022 opening year ADT and
the 2042 design year ADT. US 127 has a growth rate of 0.88%, US 224 has a growth rate of 0.56%, and Marsh Road
has a growth rate of 0.50%. The design speeds, functional class, and traffic data are summarized in Tables 1 and 2.
Table 1 – Design Speed and Functional Class
Route Posted Speed Design Speed Functional Class
US 127 55 mph 60 mph 04 Minor Arterial (Rural)
US 224 55 mph 60 mph 04 Minor Arterial (Rural)
Marsh Road 55 mph 60 mph 05 Major Collector (Rural)
Table 2 – Traffic Data
Route 2022 ADT 2042 ADT Trucks
US 127 6,600 7,900 18%
US 224 2,700 3,100 14%
Marsh Road 1,400 1,500 3.2%
The alternatives were analyzed using Highway Capacity Software (HCS) and it was found that the level-of-service
(LOS) for all approaches were acceptable, at LOS C or better for the opening year and design year AM and PM peak
hour volumes. A summary of the capacity analysis for 2022 opening year and 2042 design year can be seen below;
full details of the HCS analyses can be found in Appendix B.
B. Crash Analysis:
A review of crash data (2014-2016) from the 2018 Safety Study revealed the intersection experienced 17 crashes,
with 9 (52.9%) being injury crashes, which is double the statewide average of 26.1% for similar roadways. Three
types of crashes occur at this intersection at percentages higher than statewide averages including 10 “rear-end”
crashes (58.8% vs. statewide average of 31.1%); four “angle” crashes (23.5% vs. statewide average of 16.0%); and
one “head on” crash (5.9% vs. statewide average of 0.7%). In the more recent crash period of 2016-2018, the
intersection experienced 9 crashes with over 33% of those crashes involving injury crashes, thus the trend of
exceeding statewide averages continues at the intersection. “Rear-end” and “angle” crashes accounted for 66.7%
and 33.3% of the crashes respectively, which continue to surpass the statewide averages. Seven of the crashes (four
rear-end, three angle) involved traffic heading southbound on US 127. From 2016-2018, the intersection
experienced fewer crashes than what was expected or predicted per ODOT’s Economic Crash Analysis Tool (ECAT).
Each of the alternatives provides safety improvements. See Appendix C for crash analyses and predicted crash
reductions with each alternative.
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 8
C. Roadway Assessment
Roadway Design Criteria
Roadway geometrics and typical sections were developed referencing the ODOT’s Location and Design (L&D)
Manual, Volume 1 as well as AASHTO’s A Policy on Geometric Design of Highways and Streets. This project is not
anticipated to have any design exceptions. Table 3 summarizes the ODOT L&D design criteria for this project.
Table 3 – ODOT L&D Standard Design Criteria
US 127 / US 224 Marsh Road
Design Feature L&D Figure Rural Minor Arterial,
2042 ADT 7,900/3,100 (60 mph)
Rural Major Collector,
2042 ADT 1,500 (60 mph)
Lane Width Fig. 301-2 12 ft 11 ft
Graded Shoulder Width, Rural Fig. 301-3 13 ft w/barrier;
12 ft w/o barrier, steeper than 6:1;
8 ft w/o barrier, flatter than 6:1
7 ft w/barrier;
6 ft w/o barrier, steeper than 6:1;
5 ft w/o barrier, flatter than 6:1
Treated Shoulder Width, Rural Fig. 301-3 8 ft paved (preferred) 4 ft stabilized aggregate
Guardrail Offset Fig. 301-3 10 ft 4 ft
Stopping Sight Distance Fig. 201-1 570 ft 570 ft
Maximum Degree of Curve Fig. 202-2 4° 45' 4° 45'
Maximum Grade Fig. 203-1 3% 5%
Maximum Grade Break Fig. 203-2 0.30% 0.30%
K Value (Crest) Fig. 203-3 151 151
K Value (Sag) Fig. 203-6 140 140
Typical Sections
The existing cross sections of US 127 and US 224 consist of two 12’ travel lanes with 2’ paved and 2’ aggregate
shoulders. The existing cross slopes is superelevated at 3.5% within the intersection and superelevated for the curve
west of the intersection. The existing cross section of Marsh Road consists of two 10’ travel lanes and 1’-2’ wide
shoulders with existing cross slopes having a normal crown. The proposed typical section for each roadway will vary
depending upon the alternative. Both alternatives will be able to accommodate WB-67 trucks and farm equipment
via paved shoulders or mountable curb with concrete aprons. For Alternative 1, the typical section for US 127 and
US 224 will include two 12’ travel lanes outside the intersection and 12’ turn lanes within the intersection as
needed. Proposed treated shoulder widths for US 127 and US 224 will be 8’ paved; where a left shoulder is included
for a slip lane, the paved shoulder will be 4’. Treated shoulders for Marsh Road will be 4’ stabilized aggregate. For
the roundabout alternative, the typical section for each roadway would have two lanes separated by a raised
median, varying from 12’ to 16’ wide. Preliminary Typical Sections are found in Appendix D.
Roadway Geometrics
The existing alignments of US 127 north of the intersection and Marsh Road south of the intersection is tangent. The
west-east approach (US 127/US 224 combined west, US 224 east) has a 5-degree curve approximately 1200’ west of
the intersection. Within the intersection the west-east approach has an originally constructed deflection of
approximately 20-degree which over the years has been slightly smoothed out to resemble a horizontal curve of
approximately a 700’ radius. This curve through the intersection has a curve ahead with advisory speed posting of 45
mph, including chevrons.
For Alternatives 1, the west-east horizontal alignment will be improved to meet 60 mph design speed requirements.
The proposed profiles for the approaches of each alternative will closely match the existing profiles and be relatively
flat (grades 1.0% or less). Where curbing is utilized in Alternative 2, minimum grade of the gutters will be designed
for 0.50%.
For Alternative 2, the intersection will provide an inscribed diameter of 130’ (minimum) for the 18’ wide circular
roadway and 16’ truck apron. Exit curve radii would be 400’ or larger, while approach entry curve radii will be
approximately 100’. Elongated splitter islands are being proposed for all approach directions with chicanes being
provided for the southbound US 127 and northbound Marsh Road approaches. Elongated splitter islands
(approximately 150’ or longer) and chicanes on the approaches will provide a step-down speed reduction curve of a
250’ radius to promote speed reduction from 60 mph to 20 mph.
Pavement Design
Preliminary pavement design per the Pavement Design Manual (PDM) has been completed for US 127, US 224, and
Marsh Road. For the purposes of this study, existing soil California Bearing Ratios (CBR) were assumed to be
conservative at a value of 3.0, resulting in a Subgrade Resilient Modulus (MR) of 3,600 psi.
Pavement buildup using the following buildup for US-127:
Item 441 – 1.50” Asphalt Concrete Surface Course, Type 1, (448), PG64-22
Item 407 – Non-Tracking Tack Coat
Item 441 – 1.75” Asphalt Concrete Intermediate Course, Type 2, (448)
Item 407 – Non-Tracking Tack Coat
Item 301 – 8” Asphalt Concrete Base, PG64-22
Item 304 – 6” Aggregate Base
Item 204 – Subgrade Compaction
Pavement buildup using the following buildup for US-224:
Item 441 – 1.50” Asphalt Concrete Surface Course, Type 1, (448), PG64-22
Item 407 – Non-Tracking Tack Coat
Item 441 – 1.75” Asphalt Concrete Intermediate Course, Type 2, (448)
Item 407 – Non-Tracking Tack Coat
Item 301 – 6” Asphalt Concrete Base, PG64-22
Item 304 – 6” Aggregate Base
Item 204 – Subgrade Compaction
Pavement buildup using the following buildup for Marsh Road:
Item 441 – 1.50” Asphalt Concrete Surface Course, Type 1, (448), PG64-22
Item 407 – Non-Tracking Tack Coat
Item 441 – 1.75” Asphalt Concrete Intermediate Course, Type 2, (448)
Item 407 – Non-Tracking Tack Coat
Item 301 – 4” Asphalt Concrete Base, PG64-22
Item 304 – 6” Aggregate Base
Item 204 – Subgrade Compaction
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 9
Final pavement design will be completed after a geotechnical subsurface investigation has been performed and a
design CBR value has been received.
D. Drainage Assessment
The intersection and surrounding area are relatively flat and lacking a sufficient means for runoff to drain away.
Existing roadway surface drainage within the intersection is conveyed via sheet flow into roadside ditches that
generally flow toward Town Creek. On the west side of Marsh Road and US 127 are a few catch basins which convey
runoff to an outfall at Town Creek. Driveways along US 127 and US 224 each have small (12” – 15”) drive pipes
which are partially to nearly completely buried. As observed during a site visit soon after a rainfall event, the
roadside ditches become filled and drain very slowly, causing ponding on adjacent properties.
The proposed drainage patterns will closely match the existing drainage patterns of sheet flow into improved
roadside ditches. The ditches will be improved by providing a more defined channel cross section. Catch basins are
planned on each of the intersection corners, connected together, to ultimately drain north to outfall at Town Creek.
New driveway culverts will be provided for each approach requiring reconstruction. For Alternative 2, curb and
gutter will be implemented around the circulatory roadway and the extents of the splitter islands. In lieu of
providing storm inlets throughout the intersection, curb cuts with paved gutters will be provided to convey runoff to
the roadside ditches.
All proposed alternatives result in more than one acre of new impervious area in new right-of-way, requiring BMP
treatments for water quality and water quantity. Locations for proposed BMP implementation have been considered
for each alternative, related to the need of additional right-of-way. We do not anticipate the need for additional
right-of-way for BMP implementation as each alternative has ample room available for construction. Alternative 1
could utilize the infield area adjacent to the southbound US 127 slip lane or any of the area east of the intersection
where US 224 alignment has been shifted to the south. Alternative 2 can construct BMPs adjacent to the
roundabout approaches where the approaches are off existing alignment. Preferred method of BMP
implementation will be determined during preliminary engineering of the preferred alternative but a bioretention
cell, extended detention basin, or a manufactured system are prime candidates for consideration.
E. Right‐of‐way Assessment
Preliminary construction limits were developed for each alternative based upon the proposed project footprint.
Anticipated parcel impacts are as shown in Table 4.
Table 4 – Anticipated Right‐of‐Way Impacts
Alternative 1
Right-of-way would need to be acquired from 13 property owners for a total of approximately 4.487 acres
permanent and 0.1458 acres temporary.
Alternative 2
Right-of-way would need to be acquired from 12 property owners for a total of approximately 2.6266 acres
permanent and 0.2657 acres temporary.
F. Utility Assessment
An Ohio Utilities Protection Services (OUPS) ticket was called in to request plans for utilities within the study area.
The following utilities are located within the project area or vicinity:
• AEP Ohio
• Charter Communications
• CenturyLink
• Dominion Energy Ohio
• Independents Fiber Network
• Paulding Putnam Electric
All alternatives will require relocation of various utilities to complete the project.
G. Maintenance of Traffic
Several considerations are warranted for maintaining traffic during the construction of the proposed improvements.
Due to the number of trucks utilizing US 127, it is desirable to avoid closure of the route, but not an absolute
requirement. The construction schedule should make considerations for the area harvest season as well as the US
127 Yard Sale which has been nicknamed “World’s Longest Yard Sale” and is typically held during the first full
weekend in August (1st Thursday in August thru Sunday). During the planned construction season in 2022, the event
is likely to be held August 4-7. Concept level maintenance of traffic operations has been investigated for each
Parcel # Owner ROW Take Alt. 1 (Acres) TMP Take Alt. 1 (Acres) ROW Take Alt. 2 (Acres) TMP Take Alt. 2 (Acres)
95 Lela Laemmle Farm LLC 0.3168 0.0000 0.0034 0.0000
96 Glenn E. Sanders & Paula A. Sanders 0.1128 0.0042 0.0000 0.0201
97 Andrew C. Heaslip 0.0511 0.0000 0.0000 0.0511
98 Mark R. Johnston & Vicki L. Johnston 0.0168 0.0164 0.0000 0.0336
99 George H. Saxton, SR. & Karen M. Saxton 0.0000 0.0000 0.0000 0.0138
100 Kevin M. Gramling & Randi R. Gramling 0.0167 0.0163 0.0000 0.0313
101 Carlos N. Tyas 0.0000 0.0000 0.0000 0.0189
102 Daniel Barry Jerome 0.0264 0.0158 0.0097 0.0533
103 Virginia Marbaugh 0.1703 0.0000 0.0527 0.0000
104 Ammpack Properties LLC 0.8373 0.0000 0.7203 0.0000
112 Marsh Foundation Trustees 2.9111 0.0000 1.7933 0.0000
113 Troy Baldwin 0.0681 0.0930 0.0506 0.0436
116 Sherry Graham 0.0233 0.0000 0.0000 0.0000
150398180000 Marsh Foundation Trustees 0.2402 0.0000 0.0000 0.0000
123 Robert G. Bladen & Kelly M. Laden 0.0000 0.0000 0.0000 0.0000
190412680000 Marsh Foundation Trustees 0.0129 0.0000 0.0000 0.0000
150398300000 VH Cooper & Co., Inc. 0.0000 0.0000 0.0000 0.0000
4.4870 0.1458 2.6266 0.2657Approximate ROW Take Per Alternative (Acres)
Right‐of‐Way Takes for US 127 / US 224 / Marsh Road Intersection Improvements
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 10
alternative and are described, with associated concept drawings shown in Appendix E. Use of the innovative
contracting manual has been considered for implementation on this project to expedite construction and minimize
disruptive detours.
Alternative 1
Phase 1
Maintain traffic in one (1) eleven-foot (11’) lane in each direction on existing pavement. Construct all offline
pavement including southbound US 127 and westbound US 224 west of Marsh Rd. The eastern connection
with US 224 will be done part-width with flaggers as PER ODOT SCD MT-97-10 or with a temporary signal as per
ODOT SCD MT-96.11, MT-96.20 and MT-96.26.
Phase 2
Construct temporary pavement along the south side of US 224 / US 127. Shift eastbound and westbound US 127 /
US 224 traffic onto temporary pavement. Maintain one (1) eleven-foot (11’) lane in each direction. Close US 127 and
detour traffic. Phase 2 duration not to exceed 21 consecutive calendar days following the closure of the north leg of
the intersection.
Detour US 127 traffic on US 224, SR 673, SR 114, and US 127 (25 miles). This detour has an average delay cost of
$106,569.00. Therefore, the disincentive per the ODOT Innovative Contracting Manual should be $106,569.00 per
day or $4,441.00 per hour the contractor goes over the 30 consecutive day time frame.
Phase 3
Close Marsh Road to traffic and provide a short duration detour route. Shift all US 127 / US 224 eastbound and
westbound traffic onto the completed pavement. Construct Marsh Road proposed pavement. Use the ODOT
Innovative contracting manual PN 121 Disincentive Contract. Phase 2 duration not to exceed 21 consecutive
calendar days following the closure of Marsh Road.
The Marsh Road detour would utilize Marsh Road, Towne Center Boulevard, North Towne Boulevard, Towne Center
Boulevard, and US 127 / US 224 (2.1 miles). Following the completion of Marsh Road, remove all temporary
pavement and restore to original condition. This detour has an average delay cost of $37,712. Therefore, the
disincentive per the ODOT Innovative Contracting Manual should be $37,712 per day or $1,571 per hour the
contractor goes over the 30 consecutive day time frame.
Alternative 2
Pre-Phase 1
Construct temporary pavement along the eastbound side of SR 224.
Phase 1
Detour southbound US 127 / CR 154 using the same detour as in Alternative 1. Maintain northbound US 127 / CR
154 on existing pavement. Maintain eastbound and westbound US 224 and southbound US 127 on existing and
temporary pavement in one (1) eleven-foot (11’) lane in each direction. Maintain Marsh Rd on existing and
temporary pavement in one (1) eleven-foot (11’) lane in each direction.
Phase 2
Detour northbound US 127/CR 154 using the same detour as described in Alternative 1. Maintain southbound US
127/CR 154 on proposed pavement. Maintain eastbound and westbound US 224 and southbound US 127 on existing
and temporary pavement in one (1) eleven-foot (11’) lane through the intersection using a temporary signal.
Maintain Marsh Rd on existing and temporary pavement in one (1) eleven-foot (11’) lane in each direction.
Construct the remainder if the west leg and the north leg of the roundabout. Construct the connections to existing
pavement part-width with flaggers. Construct temporary pavement with the center island and truck apron.
Phase 3
Detour Marsh Rd while maintaining access to residential properties. Detour southbound Marsh Rd. traffic using the
same detour as described in Alternative 1. Detour northbound Marsh Rd thru traffic using the same detour as
described in Alternative 1. Close and detour westbound SR 224. Residential traffic will travel east on SR 224 to CR
637, then north on CR 637 to CR 114, then west on CR 114 to US 127, then south on US 127 to SR 224. Close and
detour eastbound SR 224 north on US 127 to CR 114, then east on CR 114 to CR 637, then south on CR 637 to SR
224. Construct the remainder of the roundabout and then construct the connections to existing pavement part-
width with flaggers.
Phase 4
Shift traffic onto the completed pavement, complete the center island portion of the roundabout, and remove all
remaining existing and temporary pavement.
H. Lighting Assessment
Existing Lighting
The VAN-127/224 intersection currently is not illuminated by either public utility or ODOT owned lighting systems.
No private lighting with appreciable spillover light is evident on the adjacent properties.
Need for Lighting
Highway lighting has several benefits, and while warrants for highway lighting exist for freeway and interchanges, no
such warrant process exists for surface streets. The decision to install lighting may consider traffic
volume, aesthetics, speed, nighttime accident rates, road geometrics, and economic benefits. Impact to adjacent
properties and aesthetics may also be a consideration. The decision to install lighting on US 127 and US 224 will be a
judgement based on the above factors.
Locations not covered by warrants are usually illuminated for safety reasons. Since crashes often occur
at intersections, lighting may be provided at intersections to improve visibility of the intersection and the approach.
ODOT’s Traffic Engineering Manual (TEM) states illumination is particularly needed at intersections with sight
distance limitations, unusual geometry, channelization, turning roadways, or where driver recognition may be a
problem. Alternatives with unusual geometry or characteristics benefit from nighttime illumination. Roadways
between closely spaced intersections may also receive lighting to reduce both the number of times and length of
time required for driver’s eyes to adjust to a different illumination level.
Lighting Levels
The initial average horizontal lighting intensity for non-freeway lighting is listed in the TEM. The Illuminating
Engineering Society of North America (IES) criteria found in RP-8-18 (Recommended Practice for Design and
Maintenance of Roadway and Parking Facility Lighting) varies based on adjacent land use and the type of facility.
Subsequent applications of RP-8 to unusual intersection types has resulted in common layouts of luminaires
for Restricted Crossing U-turn intersections (RCUTs) and roundabouts documented in design guidance for those
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 11
intersection types. Other alternatives can be broken down into component geometries for T intersections and 4-leg
intersections which ODOT has “Key Unit” layouts as documented in the TEM and Traffic Academy materials.
Land Use
The Illuminating Engineering Society (IES) guidelines define three general categories for land use: commercial,
intermediate and residential to be considered when determining the intensities of light needed. In addition, the
roadway is classified in a manner similar to the functional classification system used in transportation planning.
Commercial - Commercial areas tend to create a heavy area of background lighting. High-mast or low-mast
towers blend in more with the surrounding area and yet still light the roadway to the needed level.
“Commercial” areas often have large numbers of pedestrians and a heavy demand for off-street parking space.
Intermediate - These areas have a blend of commercial or residential types of land use. Multifamily residential
rental properties, industrial areas, and commercial properties need lighting for security. Low-mast towers or
conventional poles tend to work best in these areas as common complaints arise from the use of high mounting
heights that result in light trespass on non-roadway areas and glare. This definition includes densely developed
apartment areas, hospitals, public libraries, and neighborhood recreational centers.
Residential - Single-family residences are more sensitive to light trespass from adjacent highway lighting
units. However, the needs of the traveling public must be balanced with the concerns of the surrounding
residents. Low-mast towers and conventional lighting offer the best solution, especially considering the
concerns of residents regarding the aesthetics of highway lighting units that stand above the surrounding area
or have drop glass refractors. “Residential” may also refer to a mixture of residential and commercial
establishments, characterized by few pedestrians and a low parking demand or turnover at night. This definition
includes areas with single family homes, townhouses, small apartments, regional parks, cemeteries, and vacant
lands.
Crash History
Lighting can provide an improvement in highway safety by impacting the factors mentioned below. A review of the
accident history of the intersection indicates 3 crashes (33%) were recorded during dark conditions. All involved the
southbound driver either failing to stop at the STOP sign or rear ending another vehicle that was stopped.
Nighttime accidents may be due to:
1. Lack of adequate reflective signing or pavement markings.
2. Glare (from background lighting and headlights).
3. Problems with an individual vehicle’s lighting system.
4. Driver fatigue or physical condition (alcohol, substance abuse, age).
A review of the crash reports indicates the three drivers were either fatigued or distracted. The level and
character of nighttime crashes indicates there is not a need to greatly increase the lighting level at the existing
intersection for safety.
Recommended Lighting Strategy
US Route 127 and US Route 224 are functionally classified as Minor Arterials in a predominately agricultural area
with adjacent residential uses. Marsh Road is a county road in an area which is currently agricultural but is intended
to become commercial/industrial in the future. The use of Major roadway class and Intermediate land use
classifications is recommended. The corresponding values indicate an average illuminance on the pavement of 1.2
foot-candles with a 3:1 average-to-minimum uniformity.
For the reasons described above, lighting will be provided at all intersections to enhance safety and to improve
visibility of the intersection and approaches. Lighting is recommended to be provided between intersections for the
RCUT alternative to reduce the time for the drivers’ eyes to adjust to the differing light intensities.
Conceptual layouts for lighting of each alternative are as follows.
Alternative 1 – Turn Lanes Lighting
Alternative 2 – Roundabout Lighting
I. Environmental Assessment
The environmental effort for the Feasibility Study focused on utilizing secondary data sources and the previously
completed VAN-US 127-12.25 (PID 83797) project environmental documents in identifying, analyzing and
quantifying any environmental differences among the studied alternatives to assist in the preferred alternative
selection. The project team identified the following environmental areas that were previously investigated:
• Social/Economic and Environmental Justice
• Ecological Resource
• Cultural Resource
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 12
• Regulated Material Site
While the analyses performed for each of these tasks identified locations that need to be further studied, no
discernable differences among the alternatives were found; the resources were present/not present regardless of
the alternative.
Environmental Concerns And Analysis
As part of the Feasibility Study, the project team completed a review of the previously completed VAN-US 127-12.25
(PID 83797) project environmental documents and a review of ODOT’s Transportation Information Mappings System
(TIMS) for other potential environmental issues. The team did not identify any potential environmental impacts that
would have any measurable bearing on the decision on the Preferred Alternative selection.
The following is a summary of the review:
Parks and Recreation – Based upon a review of property ownership information, no park or recreational resource is
located within the proposed project area.
Public Facilities – Based upon a review of property ownership information, no public facilities are located within the
proposed project area.
Noise and Air Quality – Residences are located within 500 feet of US 127, US 224, and the proposed project area
corridor. The proposed project will require the reconfiguration of the intersection and additional roadway lanes; it is
anticipated that a noise analysis will be required for the project in the next phase. Should a noise analysis be
required, noise impacts would likely be similar regardless of the alternative selected.
Social/Economic and Underserved Populations – Based on a review of TIMS Underserved Populations, the Minority
Population ranged from 1% to 8%, the Low-Income Population ranged from 12% to 22%, the Over 64 Population
ranged from 15% to 19%, and the Linguistic Isolated Population was 0% within the Census Block Groups located with
the proposed project area. The community in the vicinity of the proposed project area is primarily comprised of
agricultural fields intermixed with single family residential properties. An agricultural meat processing industrial
plant is located north of the project limits. No public transit routes, sidewalks, bike lanes or multiuse paths are
located within the proposed project area.
The proposed project area may experience short-term indirect effects due to traffic pattern changes during
construction. Any indirect effects of the construction are expected to be the same regardless of the alternative
selected.
Ecological Resources – A review of ODOT TIMS database and the VAN- US 127-12.25 (PID 83797) Project Level 1
Ecological Survey Report (EMH&T 2018), determined that wetland, stream or ecological resources area may be
located within the proposed project area adjacent to Town Creek.
Cultural Resources – A review of the Ohio Historic Preservation Office on-line database and the VAN-US 127-12.25
(PID 83797) Project Section 106 Request for Review (EMH&T 2018) did not identify any historic properties, districts
or sites listed on or eligible for the National Register of Historic Places (NRHP) within the proposed project area.
One previously completed cultural resources investigation was identified within the proposed project area. The
Phase I Cultural Resource Management Survey for the 647.5 ha (1600 ac) Ohio Jobs Ready Site in Ridge, Hoaglin, and
Pleasant Townships, Van Wert County, Ohio (Weller 2009) identified twenty-eight previously unrecorded
archaeological sites (33-VW-[203-230]) and evaluated ten architectural resources (VAN-[452-460]-8 and VAN-461-7).
Additional work was recommended for archaeological site 33-VW-203; the remaining sites and architectural
resources were recommended as not eligible. Site 33-VW-203 is not located within the proposed project area and
would not have a measurable bearing on the decision on the Preferred Alternative selection.
Environmentally Regulated Materials – A review of the ODOT’s Ohio Regulated Properties Search (ORPS) Tool, the
VAN-127-12.25 (PID 83797) RMR Screening Form ( EMH&T, 2018), and the RMR Investigation VAN-127-12.25 (PID
83797) RM-008: 7265 SR 127 RM-040: 4854 SR 127 Van Wert Ohio (EMH&T, 2018) identified that that site RM-008:
7265 SR 127, a former undocumented gasoline service station, is located within the proposed project area at the
northwest corner of US 127 and US 224.
A 2018 RMR Investigation was conducted on a limited portion of site RM-008: 7265 SR 127 that was within the VAN-
US 127-12.25 (PID 83797) project area. The 2018 RMR Investigation identified two sets of underground storage
tanks and possible fuel distribution piping on the site. Two soil samples were collected from the portion of the site
within the VAN-US 127-12.25 project area and tested. None of the detections were above the Bureau of
Underground Storage Tank Regulations (BUSTR) Soil Re-Use Action Levels or the Ohio EPA Voluntary Action Program
(VAP) Generic Direct Contact Soil Standards (GDCSS) for Residential Land Use. Based on the geophysical results, the
2018 RMR Investigation recommend that the Underground Storage Tanks (UST)s identified within the VAN-US 127-
12.25 project limits be properly closed and removed. The removal of these tanks would occur during constriction of
PID 110430 VAN-127-12.22.
The VAN-127/224-12.22/15.86 (PID 110430) project area covers a larger area of the RM-008: 7265 SR 127 site. With
each alternative under consideration requiring permanent right-of-way and deep excavations from the site, further
RMR Investigations would be warranted. Additional RMR Investigations and coordination would be conducted with
ODOT during the design phase of the project; RMR involvement would be similar regardless of the alternative.
J. Public Involvement
The key stakeholders for this project have been identified and are included in the project’s Public Engagement Plan
(PEP). The PEP identifies key steps in the project coordination with key stakeholders and adjacent property owners.
All key stakeholders will receive notifications letters for the project. Property owner notification letters, giving a
short description of the proposed alternatives and information for a public open house, will be sent at least 14 days
prior to the meeting. A public meeting for this project was held on the evening of November 19, 2019 at VantageCareer Center Community Room in Van Wert, Ohio. No comments received as a result of this meeting altered the selection of the preferred alternative.
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 13
V. Alternatives Comparison
Each alternative was compared with the other alternatives based on the following categories:
• Intersection Safety
• Right-of-Way Impacts
• Traffic Operations
• Maintenance of Traffic / Constructability
• Environmental Impacts
• Utilities Impacts
• Construction Costs
Intersection Safety
This criteria evaluates the safety benefit each alternative is anticipated to provide, both quantitatively and
qualitatively, when applicable. All build alternatives provide greater safety benefit for the traveling public than the
existing condition, noted by a forecast reduction in crashes predicted. Alternative 2 will provide the maximum safety
benefit by promoting reduced vehicular speeds, reduced conflict points, and elimination of angle crashes.
Right‐of‐Way Impacts
This criteria evaluates the need for permanent and temporary right-of-way acquisition and easements. All
alternatives will require the purchase of private property for Right-of-way for construction. Alternative 2 will require
the least amount of acreage purchased as well as least amount of parcels impacts. Alternative 1 requires the most
acreage of right-of-way to purchase and second most parcel impacts. Each alternative will require corner cuts at the
northeast and southwest quadrants that may incur damages to the properties.
Traffic Operations
This criteria evaluates the proposed movement of traffic after the implementation of each alternative. Factors in
determining the operational benefit include identifying delays, Level of Service (LOS), and 95th Queue (# vehicles in
queue). All alternatives present adequate capacity in the opening year (2022) and design year (2042). However,
Alternative 1 analysis indicates LOS B and C for the northbound and southbound approaches during the opening
year and design year, whereas Alternative 2 analysis indicates LOS A across the board for all approaches.
Maintenance of Traffic / Constructability
This criteria evaluates the impact to traffic during the construction phase of each alternative. Possible MOT
scenarios mentioned previously include short term lane and road closures, part-width construction, and full roadway
closure with detour for various roadway segments. Alternative 1 could be performed in three phases whereas
Alternative 2 will likely require construction in four phases. Alternative 2 would require the most complex
maintenance of traffic in order to complete the roundabout islands which is approximately centrally located about
the existing intersection.
Environmental Impacts
This criteria evaluates the impact to the environment within the project area including waterways, endangered
species, and environmental issue due to hazardous waste at a property. These impacts may affect the project
delivery and construction schedule. The project is located within a Zone A floodplain of Town Creek and each option
will require minor work adjacent to Town Creek to outlet storm drainage. Environmental impacts of each alternative
will be relatively identical, and no alternative is measurably better or worse.
Utilities Impacts
This criteria evaluates the impact to utilities, determining if a relocation is reimbursable, as well as any impacts to
existing utility easements, including relocations. All alternatives will require the relocation of various existing utilities
in the immediate intersection corners and along the approach legs, particularly overhead electric and
communications. Alternative 1 will impact the least amount of overhead utilities by having construction off existing
alignment. Alternative 2 approach legs will impact the most amount of overhead utilities, impacting those on each
approach leg.
Construction Costs
This criteria estimates the cost for construction for each of the proposed alternatives. Alternative 2 presents the
least construction costs and Alternative 1 would be the costliest alternative. A summary of the alternatives
construction cost is shown below with a breakdown of construction costs for each alternative found in Appendix F.
Table 5 – Preliminary Construction Costs
Alternative Construction Costs
Alternative 1 $2,720,000
Alternative 2 $2,130,000
VI. Conclusion
All alternatives will require right-of-way purchase, utility relocation, environmental impacts and upgrades to the
configuration of the intersection to varying degrees. Each alternative will affect the adjacent properties and utilities
differently. Each alternative meets the Purpose & Need of the project, to improve safety and reduce crashes.
Alternative 2 has a lower construction cost, has the least amount of right-of-way impacts, and has improved safety
benefits compared to Alternative 1. While it is anticipated to have the most impact on utilities and maintaining
traffic will be the most complex of the two alternatives, it is recommended to proceed with Alternative 2 as the
preferred alternative.
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 14
Figure 3 – Intersection Evaluation Matrix
Next Steps
The next steps of this project’s development will be coordination and presentation of the Feasibility Study to the key
stakeholders and property owners at a public meeting, to be held on November 19. This meeting will garner their
feedback on the study and the recommended alternative.
Evaluation Criteria 1 2
Intersection Safety
Right-of-Way Impacts
Traffic Operations
Maintenance of Traffic /
Constructability
Environmental Impacts
Utilities Impacts
Total Construction Costs 2,720,000$ 2,130,000$
KEY: Good
Fair
Satisfactory
Poor
Each alternative requires a degree of utility relocation. Alternative 1 avoids more
overhead utility poles than Alternative 2; Alternative 2 requires utility pole relocation
on each approach leg.
Each alternative has an expected relatively minor impact on environmental within
the area and no alternative was conceptually determined better or worse.
Alternative 2 impacts the least amount of parcels and requires the least amount of
acreage. Alternative 1 impacts more parcels and requires the most acreage.
EVALUATION MATRIX
US 127 / US 224 / MARSH ROAD INTERSECTION
Remarks
Alternative 2 yields the least amount of expected crashes, especially injury and
fatal types. Alternatives 1 results in a comparable safety improvement of less
conflict points but still will have higher speeds.
Alternative 2 yields the best results for opening day and future traffic capacity
analyis, all LOS A whereas Alternative 1 has LOS B and LOS C in the design year
for northbound and southbound directions.
Alternatives 1 offers the most flexibility for maintaining traffic with more
construction offline east of the intersection and with the bypass lane. Alternative 2
requires an additional phase of construction compared to Alternative 1.
Alternative
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 15
Appendix A – Alternative Layouts
N
HO
RIZ
ON
TA
L
SC
AL
E IN F
EE
T
CA
LC
UL
AT
ED
CH
EC
KE
D
Z:\
2019\19
1218\
CA
D\
OD
OT\110430\
Desig
n\
Road
way\
Sheets\110430_
Alt-1_
Turn-
Lanes.d
gn
Sheet 11/18/2019 11:0
2:2
7
AM jahiller
1
2
0
100
50
200
AL
TE
RN
ATIV
E
1V
AN-12
7-12.2
2T
UR
N
LA
NE
S
HO
RIZ
ON
TA
L
SC
AL
E IN F
EE
T
CA
LC
UL
AT
ED
CH
EC
KE
D
Z:\
2019\19
1218\
CA
D\
OD
OT\110430\
Desig
n\
Road
way\
Sheets\110430_
Alt-2_
Ro
undabo
ut.d
gn
Sheet 11/18/2019 11:0
4:14
AM jahiller
2
2
0
100
50
200
AL
TE
RN
ATIV
E
2
N
RO
UN
DA
BO
UT
VA
N-12
7-12.2
2
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 16
Appendix B – Traffic Data and Capacity Analysis
Intersection
US-127 @ US-224 Delay (s) LOS 95th Queue* Delay (s) LOS 95th Queue*
NB 12.5 B 0.2 4.0 A 0.1
SB 15.1 C 0.5 5.2 A 0.6
EB 4.7 A 0.2 5.1 A 0.6
WB 2.0 A 0.1 4.7 A 0.6
Overall 5.0 A
Intersection
US-127 @ US-224 Delay (s) LOS 95th Queue* Delay (s) LOS 95th Queue*
NB 15.5 C 1.1 5.3 A 0.5
SB 18.2 C 0.8 5.8 A 1.1
EB 4.3 A 0.4 5.8 A 1.1
WB 1.9 A 0.0 4.7 A 0.3
Overall 5.6 A
* - All 95th percentile queues are measured in number of vehicles
Intersection
US-127 @ US-224 Delay (s) LOS 95th Queue* Delay (s) LOS 95th Queue*
NB 13.3 B 0.3 4.2 A 0.1
SB 16.7 C 0.7 5.7 A 0.8
EB 4.7 A 0.3 5.4 A 0.7
WB 2.0 A 0.1 5.0 A 0.7
Overall 5.3 A
Intersection
US-127 @ US-224 Delay (s) LOS 95th Queue* Delay (s) LOS 95th Queue*
NB 17.6 C 1.5 5.7 A 0.6
SB 21.5 C 1.2 6.5 A 1.4
EB 4.4 A 0.5 6.3 A 1.3
WB 1.9 A 0.1 5.0 A 0.4
Overall 6.1 A
* - All 95th percentile queues are measured in number of vehicles
1 2
Opening (2022) AM Peak Hour
Alternative
1 2
Opening (2022) PM Peak Hour
Alternative
Future (2042) PM Peak Hour
Alternative
1 2
Future (2042) AM Peak Hour
Alternative
1 2
at US-224
102 56 0
90 3
60 TWO WAY STOP 114
4 44
0 20 11
184 64 6
155 5
120 TWO WAY STOP 57
2 21
0 72 49
AM Peak Hour
2018 WEEKDAY INTERSECTION COUNTS
US-127
US
-12
7
US-224
PM Peak Hour
US
-12
7
US-224
Z:\2019\191218\WORK\Calcs\TRANSPORTATION\Traffic Analysis\VAN127 Traffic Volumes.xls 10/10/2019
at US-224
106 58 0
92 3
61 TWO WAY STOP 117
4 45
0 20 11
191 66 6
159 5
123 TWO WAY STOP 58
2 21
0 73 50
US
-12
7
US-224
PM Peak Hour
2022 WEEKDAY INTERSECTION COUNTS
US-127
US
-12
7
US-224
AM Peak Hour
Z:\2019\191218\WORK\Calcs\TRANSPORTATION\Traffic Analysis\VAN127 Traffic Volumes.xls 10/10/2019
at US-224
126 69 0
103 3
69 TWO WAY STOP 130
5 50
0 23 12
227 79 7
177 6
137 TWO WAY STOP 65
2 24
0 81 55
US
-12
7
US-224
PM Peak Hour
2042 WEEKDAY INTERSECTION COUNTS
US-127
US
-12
7
US-224
AM Peak Hour
Z:\2019\191218\WORK\Calcs\TRANSPORTATION\Traffic Analysis\VAN127 Traffic Volumes.xls 10/10/2019
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh Road
Agency/Co. Jurisdiction
Date Performed 9/24/2019 East/West Street US-224
Analysis Year 2022 North/South Street US-127
Time Analyzed 2022 AM Peak Hour Peak Hour Factor 0.92
Intersection Orientation East-West Analysis Time Period (hrs) 0.25
Project Description Alternative 1
Lanes
Major Street: East-West
Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12
Number of Lanes 0 1 1 0 0 1 1 0 0 1 0 0 1 0
Configuration L TR L TR LTR LT
Volume (veh/h) 92 61 4 45 117 3 0 20 11 0 58
Percent Heavy Vehicles (%) 26 2 3 15 18 3 5
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized
Median Type | Storage Undivided
Critical and Follow-up Headways
Base Critical Headway (sec) 4.1 4.1 7.1 6.5 6.2 7.1 6.5
Critical Headway (sec) 4.36 4.12 7.13 6.65 6.38 7.13 6.55
Base Follow-Up Headway (sec) 2.2 2.2 3.5 4.0 3.3 3.5 4.0
Follow-Up Headway (sec) 2.43 2.22 3.53 4.14 3.46 3.53 4.05
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 100 49 34 63
Capacity, c (veh/h) 1319 1528 512 421
v/c Ratio 0.08 0.03 0.07 0.15
95% Queue Length, Q₉₅ (veh) 0.2 0.1 0.2 0.5
Control Delay (s/veh) 8.0 7.4 12.5 15.1
Level of Service (LOS) A A B C
Approach Delay (s/veh) 4.7 2.0 12.5 15.1
Approach LOS B C
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.8 Generated: 10/10/2019 7:07:57 AM
2022 VAN127_Alt1_AM.xtw
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh Road
Agency/Co. Jurisdiction
Date Performed 9/24/2019 East/West Street US-224
Analysis Year 2022 North/South Street US-127
Time Analyzed 2022 PM Peak Hour Peak Hour Factor 0.92
Intersection Orientation East-West Analysis Time Period (hrs) 0.25
Project Description Alternative 1
Lanes
Major Street: East-West
Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12
Number of Lanes 0 1 1 0 0 1 1 0 0 1 0 0 1 0
Configuration L TR L TR LTR LT
Volume (veh/h) 159 123 2 21 58 5 0 73 50 6 66
Percent Heavy Vehicles (%) 11 2 3 6 4 17 3
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized
Median Type | Storage Undivided
Critical and Follow-up Headways
Base Critical Headway (sec) 4.1 4.1 7.1 6.5 6.2 7.1 6.5
Critical Headway (sec) 4.21 4.12 7.13 6.56 6.24 7.27 6.53
Base Follow-Up Headway (sec) 2.2 2.2 3.5 4.0 3.3 3.5 4.0
Follow-Up Headway (sec) 2.30 2.22 3.53 4.05 3.34 3.65 4.03
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 173 23 134 78
Capacity, c (veh/h) 1477 1446 475 350
v/c Ratio 0.12 0.02 0.28 0.22
95% Queue Length, Q₉₅ (veh) 0.4 0.0 1.1 0.8
Control Delay (s/veh) 7.8 7.5 15.5 18.2
Level of Service (LOS) A A C C
Approach Delay (s/veh) 4.3 1.9 15.5 18.2
Approach LOS C C
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.8 Generated: 10/10/2019 7:09:44 AM
2022 VAN127_Alt1_PM.xtw
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh Road
Agency/Co. Jurisdiction
Date Performed 9/24/2019 East/West Street US-224
Analysis Year 2042 North/South Street US-127
Time Analyzed 2042 AM Peak Hour Peak Hour Factor 0.92
Intersection Orientation East-West Analysis Time Period (hrs) 0.25
Project Description Alternative 1
Lanes
Major Street: East-West
Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12
Number of Lanes 0 1 1 0 0 1 1 0 0 1 0 0 1 0
Configuration L TR L TR LTR LT
Volume (veh/h) 103 69 5 50 130 3 0 23 12 0 69
Percent Heavy Vehicles (%) 26 2 3 15 18 3 5
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized
Median Type | Storage Undivided
Critical and Follow-up Headways
Base Critical Headway (sec) 4.1 4.1 7.1 6.5 6.2 7.1 6.5
Critical Headway (sec) 4.36 4.12 7.13 6.65 6.38 7.13 6.55
Base Follow-Up Headway (sec) 2.2 2.2 3.5 4.0 3.3 3.5 4.0
Follow-Up Headway (sec) 2.43 2.22 3.53 4.14 3.46 3.53 4.05
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 112 54 38 75
Capacity, c (veh/h) 1303 1515 470 384
v/c Ratio 0.09 0.04 0.08 0.20
95% Queue Length, Q₉₅ (veh) 0.3 0.1 0.3 0.7
Control Delay (s/veh) 8.0 7.5 13.3 16.7
Level of Service (LOS) A A B C
Approach Delay (s/veh) 4.7 2.0 13.3 16.7
Approach LOS B C
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.8 Generated: 10/10/2019 7:10:50 AM
2042 VAN127_Alt1_AM.xtw
HCS7 Two-Way Stop-Control Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh Road
Agency/Co. Jurisdiction
Date Performed 9/24/2019 East/West Street US-224
Analysis Year 2042 North/South Street US-127
Time Analyzed 2042 PM Peak Hour Peak Hour Factor 0.92
Intersection Orientation East-West Analysis Time Period (hrs) 0.25
Project Description Alternative 1
Lanes
Major Street: East-West
Vehicle Volumes and Adjustments
Approach Eastbound Westbound Northbound Southbound
Movement U L T R U L T R U L T R U L T R
Priority 1U 1 2 3 4U 4 5 6 7 8 9 10 11 12
Number of Lanes 0 1 1 0 0 1 1 0 0 1 0 0 1 0
Configuration L TR L TR LTR LT
Volume (veh/h) 177 137 2 24 65 6 0 81 55 7 79
Percent Heavy Vehicles (%) 11 2 3 6 4 17 3
Proportion Time Blocked
Percent Grade (%) 0 0
Right Turn Channelized
Median Type | Storage Undivided
Critical and Follow-up Headways
Base Critical Headway (sec) 4.1 4.1 7.1 6.5 6.2 7.1 6.5
Critical Headway (sec) 4.21 4.12 7.13 6.56 6.24 7.27 6.53
Base Follow-Up Headway (sec) 2.2 2.2 3.5 4.0 3.3 3.5 4.0
Follow-Up Headway (sec) 2.30 2.22 3.53 4.05 3.34 3.65 4.03
Delay, Queue Length, and Level of Service
Flow Rate, v (veh/h) 192 26 148 93
Capacity, c (veh/h) 1466 1428 433 311
v/c Ratio 0.13 0.02 0.34 0.30
95% Queue Length, Q₉₅ (veh) 0.5 0.1 1.5 1.2
Control Delay (s/veh) 7.8 7.6 17.6 21.5
Level of Service (LOS) A A C C
Approach Delay (s/veh) 4.4 1.9 17.6 21.5
Approach LOS C C
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ TWSC Version 7.8 Generated: 10/10/2019 7:11:55 AM
2042 VAN127_Alt1_PM.xtw
HCS7 Roundabouts Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh
Agency or Co. E/W Street Name US-224
Date Performed 9/24/2019 N/S Street Name US-127
Analysis Year 2022 Analysis Time Period (hrs) 0.25
Time Analyzed 2022 AM Peak Hour Peak Hour Factor 0.92
Project Description Alternative 2 Jurisdiction
Volume Adjustments and Site Characteristics
Approach EB WB NB SB
Movement U L T R U L T R U L T R U L T R
Number of Lanes (N) 0 0 1 0 0 0 1 0 0 0 1 0 0 0 1 0
Lane Assignment LTR LTR LTR LTR
Volume (V), veh/h 0 92 61 4 0 45 117 3 0 0 20 11 0 0 58 106
Percent Heavy Vehicles, % 3 26 13 3 3 2 9 33 3 3 15 18 3 3 5 18
Flow Rate (vPCE), pc/h 0 126 75 4 0 50 139 4 0 0 25 14 0 0 66 136
Right-Turn Bypass None None None None
Conflicting Lanes 1 1 1 1
Pedestrians Crossing, p/h 0 0 0 0
Critical and Follow-Up Headway Adjustment
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Critical Headway (s) 4.9763 4.9763 4.9763 4.9763
Follow-Up Headway (s) 2.6087 2.6087 2.6087 2.6087
Flow Computations, Capacity and v/c Ratios
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Entry Flow (ve), pc/h 205 193 39 202
Entry Volume, veh/h 170 180 34 178
Circulating Flow (vc), pc/h 116 151 201 189
Exiting Flow (vex), pc/h 89 275 155 120
Capacity (cpce), pc/h 1226 1183 1124 1138
Capacity (c), veh/h 1018 1101 969 1003
v/c Ratio (x) 0.17 0.16 0.03 0.18
Delay and Level of Service
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Lane Control Delay (d), s/veh 5.1 4.7 4.0 5.2
Lane LOS A A A A
95% Queue, veh 0.6 0.6 0.1 0.6
Approach Delay, s/veh 5.1 4.7 4.0 5.2
Approach LOS A A A A
Intersection Delay, s/veh | LOS 5.0 A
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ Roundabouts Version 7.8 Generated: 10/10/2019 7:13:44 AM
2022 VAN127_Alt2_AM.xro
HCS7 Roundabouts Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh
Agency or Co. E/W Street Name US-224
Date Performed 9/24/2019 N/S Street Name US-127
Analysis Year 2022 Analysis Time Period (hrs) 0.25
Time Analyzed 2022 AM Peak Hour Peak Hour Factor 0.92
Project Description Alternative 2 Jurisdiction
Volume Adjustments and Site Characteristics
Approach EB WB NB SB
Movement U L T R U L T R U L T R U L T R
Number of Lanes (N) 0 0 1 0 0 0 1 0 0 0 1 0 0 0 1 0
Lane Assignment LTR LTR LTR LTR
Volume (V), veh/h 0 159 123 2 0 21 58 5 0 0 73 50 0 6 66 191
Percent Heavy Vehicles, % 3 11 11 0 2 0 14 0 3 0 6 4 3 17 3 19
Flow Rate (vPCE), pc/h 0 192 148 2 0 23 72 5 0 0 84 57 0 8 74 247
Right-Turn Bypass None None None None
Conflicting Lanes 1 1 1 1
Pedestrians Crossing, p/h 0 0 0 0
Critical and Follow-Up Headway Adjustment
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Critical Headway (s) 4.9763 4.9763 4.9763 4.9763
Follow-Up Headway (s) 2.6087 2.6087 2.6087 2.6087
Flow Computations, Capacity and v/c Ratios
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Entry Flow (ve), pc/h 342 100 141 329
Entry Volume, veh/h 308 91 134 286
Circulating Flow (vc), pc/h 105 276 348 95
Exiting Flow (vex), pc/h 213 319 281 99
Capacity (cpce), pc/h 1240 1041 968 1253
Capacity (c), veh/h 1118 949 920 1090
v/c Ratio (x) 0.28 0.10 0.15 0.26
Delay and Level of Service
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Lane Control Delay (d), s/veh 5.8 4.7 5.3 5.8
Lane LOS A A A A
95% Queue, veh 1.1 0.3 0.5 1.1
Approach Delay, s/veh 5.8 4.7 5.3 5.8
Approach LOS A A A A
Intersection Delay, s/veh | LOS 5.6 A
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ Roundabouts Version 7.8 Generated: 10/10/2019 7:14:44 AM
2022 VAN127_Alt2_PM.xro
HCS7 Roundabouts Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh
Agency or Co. E/W Street Name US-224
Date Performed 9/24/2019 N/S Street Name US-127
Analysis Year 2042 Analysis Time Period (hrs) 0.25
Time Analyzed 2042 AM Peak Hour Peak Hour Factor 0.92
Project Description Alternative 2 Jurisdiction
Volume Adjustments and Site Characteristics
Approach EB WB NB SB
Movement U L T R U L T R U L T R U L T R
Number of Lanes (N) 0 0 1 0 0 0 1 0 0 0 1 0 0 0 1 0
Lane Assignment LTR LTR LTR LTR
Volume (V), veh/h 0 103 69 5 0 50 130 3 0 0 23 12 0 0 69 126
Percent Heavy Vehicles, % 3 26 13 3 3 2 9 33 3 3 15 18 3 3 5 18
Flow Rate (vPCE), pc/h 0 141 85 6 0 55 154 4 0 0 29 15 0 0 79 162
Right-Turn Bypass None None None None
Conflicting Lanes 1 1 1 1
Pedestrians Crossing, p/h 0 0 0 0
Critical and Follow-Up Headway Adjustment
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Critical Headway (s) 4.9763 4.9763 4.9763 4.9763
Follow-Up Headway (s) 2.6087 2.6087 2.6087 2.6087
Flow Computations, Capacity and v/c Ratios
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Entry Flow (ve), pc/h 232 213 44 241
Entry Volume, veh/h 193 198 38 213
Circulating Flow (vc), pc/h 134 170 226 209
Exiting Flow (vex), pc/h 100 316 174 140
Capacity (cpce), pc/h 1204 1160 1096 1115
Capacity (c), veh/h 1001 1080 945 983
v/c Ratio (x) 0.19 0.18 0.04 0.22
Delay and Level of Service
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Lane Control Delay (d), s/veh 5.4 5.0 4.2 5.7
Lane LOS A A A A
95% Queue, veh 0.7 0.7 0.1 0.8
Approach Delay, s/veh 5.4 5.0 4.2 5.7
Approach LOS A A A A
Intersection Delay, s/veh | LOS 5.3 A
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ Roundabouts Version 7.8 Generated: 10/10/2019 7:17:52 AM
2042 VAN127_Alt2_AM.xro
HCS7 Roundabouts Report
General Information Site Information
Analyst FTCH Intersection US-127/US-224/Marsh
Agency or Co. E/W Street Name US-224
Date Performed 9/24/2019 N/S Street Name US-127
Analysis Year 2042 Analysis Time Period (hrs) 0.25
Time Analyzed 2042 AM Peak Hour Peak Hour Factor 0.92
Project Description Alternative 2 Jurisdiction
Volume Adjustments and Site Characteristics
Approach EB WB NB SB
Movement U L T R U L T R U L T R U L T R
Number of Lanes (N) 0 0 1 0 0 0 1 0 0 0 1 0 0 0 1 0
Lane Assignment LTR LTR LTR LTR
Volume (V), veh/h 0 177 137 2 0 24 65 6 0 0 81 55 0 7 79 227
Percent Heavy Vehicles, % 3 11 11 0 2 0 14 0 3 0 6 4 3 17 3 19
Flow Rate (vPCE), pc/h 0 214 165 2 0 26 81 7 0 0 93 62 0 9 88 294
Right-Turn Bypass None None None None
Conflicting Lanes 1 1 1 1
Pedestrians Crossing, p/h 0 0 0 0
Critical and Follow-Up Headway Adjustment
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Critical Headway (s) 4.9763 4.9763 4.9763 4.9763
Follow-Up Headway (s) 2.6087 2.6087 2.6087 2.6087
Flow Computations, Capacity and v/c Ratios
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Entry Flow (ve), pc/h 381 114 155 391
Entry Volume, veh/h 343 104 147 340
Circulating Flow (vc), pc/h 123 307 388 107
Exiting Flow (vex), pc/h 236 375 314 116
Capacity (cpce), pc/h 1217 1009 929 1237
Capacity (c), veh/h 1097 921 883 1077
v/c Ratio (x) 0.31 0.11 0.17 0.32
Delay and Level of Service
Approach EB WB NB SB
Lane Left Right Bypass Left Right Bypass Left Right Bypass Left Right Bypass
Lane Control Delay (d), s/veh 6.3 5.0 5.7 6.5
Lane LOS A A A A
95% Queue, veh 1.3 0.4 0.6 1.4
Approach Delay, s/veh 6.3 5.0 5.7 6.5
Approach LOS A A A A
Intersection Delay, s/veh | LOS 6.1 A
Copyright © 2019 University of Florida. All Rights Reserved. HCS™ Roundabouts Version 7.8 Generated: 10/10/2019 7:18:53 AM
2042 VAN127_Alt2_PM.xro
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 17
Appendix C – Crash Data and Safety Analysis
#REF!
1/02-24-16/O/Dry/We
2/02-29-16/D/Dry/Mo
3/06-15-16/O/Dry/We
4/07-12-16/D/Dry/Tu
5/11-03-16/O/Wet/Th
6/05-18-17/D/Dry/Th
7/07-31-17/D/Dry/Mo
8/08-16-18/D/Wet/Th
9/08-21-18/D/Dry/Tu
KA B C O Total
0.3843 0.3843 1.1673 3.3333 5.2692
0.3254 0.7885 0.5251 2.7407 4.3797
-0.0589 0.4042 -0.6422 -0.5926 -0.8895
0.2065 0.2065 0.6280 1.7923 2.8333
KA B C O Total
US127; 12.22 US-127 @ US-224 0.3843 0.3843 1.1673 3.3333 5.2692
KA B C O Total
US127; 12.22 US-127 @ US-224 0.3254 0.7885 0.5251 2.7407 4.3797
KA B C O Total
US127; 12.22 US-127 @ US-224 -0.0589 0.4042 -0.6422 -0.5926 -0.8895
KA B C O Total
VAN-127-12.22 US-127 @ US-224 0.2065 0.2065 0.628 1.7923 2.8333
Proposed
Predicted Crash
Frequency
Expected Crash
FrequencyPSI
Predicted Crash
Frequency
Unknown 0.8025 0.0172 -0.7853 0.4317
Head On 0.0454 0.0380 -0.0074 0.0243
Rear End 0.8639 0.9345 0.0706 0.4645
Backing 0.2013 0.1745 -0.0268 0.1083
Sideswipe - Meeting 0.1447 0.1274 -0.0173 0.0779
Sideswipe - Passing 0.2110 0.1972 -0.0138 0.1135
Angle 1.7010 1.6770 -0.0240 0.9146
Parked Vehicle 0.1724 0.1547 -0.0177 0.0927
Pedestrian 0.0250 0.0217 -0.0033 0.0133
Animal 0.0000 0.0000 0.0000 0.0000
Train 0.0003 0.0008 0.0005 0.0002
Pedalcycles 0.0161 0.0162 0.0001 0.0087
Other Non-Vehicle 0.0000 0.0003 0.0003 0.0000
Fixed Object 0.7768 0.7328 -0.0440 0.4176
Other Object 0.0291 0.0254 -0.0037 0.0156
Overturning 0.0479 0.0446 -0.0033 0.0258
Other Non-Collision 0.0668 0.0577 -0.0091 0.0360
Left Turn 0.1650 0.1597 -0.0053 0.0886
Right Turn 0.0000 0.0000 0.0000 0.0000
Summary by Crash Type
Existing Conditions Project Element Potential for Safety Improvement Summary (Without Animal Crashes)
Project Element ID Common NameCrash Severity Level
Proposed Conditions Project Element Predicted Crash Summary (Without Animal Crashes)
Project Element ID Common NameCrash Severity Level
General Information
Project Safety Performance Report
Existing Conditions Project Element Expected Crash Summary (Without Animal Crashes)
Project Element ID
Nexpected - Proposed Conditions
Npotential for improvement - Existing Conditions
Common NameCrash Severity Level
Analyst
Agency/Company
Jerod Hiller
Fishbeck
Summary of Anticipated Safety Performance of the Project (average crashes/year)
Existing Conditions Project Element Predicted Crash Summary (Without Animal Crashes)Crash Severity Level
Project Summary Results (Without Animal Crashes)
Nexpected - Existing Conditions
Project Element ID
Existing
Crash Type
Common Name
Contact Email
Contact Phone
Date Performed
Analysis Year
Project Description
Reference Number
Alternative 1 - Turn Lanes
Project Name VAN-127-12.22
Npredicted - Existing Conditions
0.4 0.4
1.2
3.3
5.3
0.3
0.80.5
2.7
4.4
-0.1
0.4
-0.6 -0.6-0.9
0.2 0.20.6
1.8
2.8
-2.0
-1.0
0.0
1.0
2.0
3.0
4.0
5.0
6.0
KA B C O Total
Existing ConditionsPredicted Average CrashFrequency
Existing ConditionsExpected Average CrashFrequency
Existing CondtionsPotential for SafetyImprovement
Proposed ConditionsPredicted Average CrashFrequency
Created by the Office of Systems Planning and Program Management
KA B C O Total
0.3843 0.3843 1.1673 3.3333 5.2692
0.3254 0.7885 0.5251 2.7407 4.3797
-0.0589 0.4042 -0.6422 -0.5926 -0.8895
0.0539 0.0539 0.1638 1.0433 1.3149
KA B C O Total
US127; 12.22 US-127 @ US-224 0.3843 0.3843 1.1673 3.3333 5.2692
KA B C O Total
US127; 12.22 US-127 @ US-224 0.3254 0.7885 0.5251 2.7407 4.3797
KA B C O Total
US127; 12.22 US-127 @ US-224 -0.0589 0.4042 -0.6422 -0.5926 -0.8895
KA B C O Total
VAN-127-12.22 US-127 @ US-224 0.0539 0.0539 0.1638 1.0433 1.3149
Proposed
Predicted Crash
Frequency
Expected Crash
FrequencyPSI
Predicted Crash
Frequency
Unknown 0.8025 0.0172 -0.7853 0.1153
Head On 0.0454 0.0380 -0.0074 0.0091
Rear End 0.8639 0.9345 0.0706 0.2552
Backing 0.2013 0.1745 -0.0268 0.0630
Sideswipe - Meeting 0.1447 0.1274 -0.0173 0.0361
Sideswipe - Passing 0.2110 0.1972 -0.0138 0.0613
Angle 1.7010 1.6770 -0.0240 0.4174
Parked Vehicle 0.1724 0.1547 -0.0177 0.0531
Pedestrian 0.0250 0.0217 -0.0033 0.0042
Animal 0.0000 0.0000 0.0000 0.0000
Train 0.0003 0.0008 0.0005 0.0001
Pedalcycles 0.0161 0.0162 0.0001 0.0031
Other Non-Vehicle 0.0000 0.0003 0.0003 0.0000
Fixed Object 0.7768 0.7328 -0.0440 0.2179
Other Object 0.0291 0.0254 -0.0037 0.0088
Overturning 0.0479 0.0446 -0.0033 0.0102
Other Non-Collision 0.0668 0.0577 -0.0091 0.0195
Left Turn 0.1650 0.1597 -0.0053 0.0407
Right Turn 0.0000 0.0000 0.0000 0.0000
Common Name
Contact Email
Contact Phone
Date Performed
Analysis Year
Project Description
Reference Number
Alternative 2 Roundabout
Project Name VAN-127-12.22
Npredicted - Existing Conditions
Project Element ID
Existing
Crash Type
Common NameCrash Severity Level
Analyst
Agency/Company
Jerod Hiller
Fishbeck
Summary of Anticipated Safety Performance of the Project (average crashes/year)
Existing Conditions Project Element Predicted Crash Summary (Without Animal Crashes)Crash Severity Level
Project Summary Results (Without Animal Crashes)
Nexpected - Existing Conditions
Summary by Crash Type
Existing Conditions Project Element Potential for Safety Improvement Summary (Without Animal Crashes)
Project Element ID Common NameCrash Severity Level
Proposed Conditions Project Element Predicted Crash Summary (Without Animal Crashes)
Project Element ID Common NameCrash Severity Level
General Information
Project Safety Performance Report
Existing Conditions Project Element Expected Crash Summary (Without Animal Crashes)
Project Element ID
Nexpected - Proposed Conditions
Npotential for improvement - Existing Conditions
0.4 0.4
1.2
3.3
5.3
0.3
0.80.5
2.7
4.4
-0.1
0.4
-0.6 -0.6-0.9
0.1 0.1 0.2
1.01.3
-2.0
-1.0
0.0
1.0
2.0
3.0
4.0
5.0
6.0
KA B C O Total
Existing ConditionsPredicted Average CrashFrequency
Existing ConditionsExpected Average CrashFrequency
Existing CondtionsPotential for SafetyImprovement
Proposed ConditionsPredicted Average CrashFrequency
Created by the Office of Systems Planning and Program Management
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 18
Appendix D – Alternative Typical Sections
Z:\
2019\19
1218\
CA
D\
OD
OT\110430\
Desig
n\
Road
way\
Base
maps\110430_
GY001.dgn
Sheet 10/11/2019 9:0
0:5
4
AM
mds
mit
h
1
3
V
AN-12
7-12.2
2T
YPIC
AL
SE
CTIO
NS -
AL
TE
RN
ATIV
E
1
0.016 0.016 0.040.080.040.08
MARSH RD - NORMAL SECTION
4:14:1
4:14:1
US 127 - NORMAL SECTION
4:14:1
0.080.08
4:14:1
0.02 0.04 0.04
0.08
0.08
0.08
0.08
0.04
0.04
0.04
0.04
0.016
0.016 0.016
0.016
0.016 0.016
0.016 0.016 0.080.08
4:14:1
4'-0"8'-0"12'-0"6'-0"6'-0"12'-0"8'-0"4'-0"
4'-0"8'-0"12'-0"12'-0"8'-0"4'-0"
2'-0"4'-0"11'-0"11'-0"4'-0"2'-0"
2'-0"8'-0"12'-0"4'-0"2'-0"2'-0"12'-0"12'-0"2'-0"
CUT SECTION
CUT SECTION
CUT SECTION
CUT SECTIONCUT SECTION
FILL SECTION
US 127 / US 224 - NORMAL SECTION
| CONST.
| CONST.
| CONST.
| CONST.
| CONST.
SLIP LANE - TYPICAL SECTIONOLD US 224 CONNECTOR - TYPICAL SECTION
FILL SECTION
FILL SECTION
FILL SECTION
FILL SECTION
Z:\
2019\19
1218\
CA
D\
OD
OT\110430\
Desig
n\
Road
way\
Base
maps\110430_
GY001.dgn
Sheet 10/11/2019 9:0
0:5
9
AM
mds
mit
h
2
3
V
AN-12
7-12.2
2T
YPIC
AL
SE
CTIO
NS -
AL
TE
RN
ATIV
E
2
0.020.02
6'-0"2'-6"18'-0"2'-6"16'-6"33'-0"
| ISLAND
0.020.02
4:14:1
0.02 0.02
SPLITTER ISLAND - TYPICAL SECTION
ROUNDABOUT - TYPICAL SECTION
6'-0"2'-6"VARIES2'-6"VARIES2'-6"VARIES2'-6"6'-0"
12'-0" TO 21'-0"1'-0" TO 28'-6"
0.02
0.016 0.016 0.040.080.040.08
MARSH RD - NORMAL SECTION
4:14:1
4:14:1
0.08 0.080.04 0.040.016 0.016
4'-0"8'-0"12'-0"12'-0"8'-0"4'-0"
2'-0"4'-0"11'-0"11'-0"4'-0"2'-0"
CUT SECTION
CUT SECTION
US 127 & US 224 - NORMAL SECTION
| CONST.
| CONST.
| CONST.
12'-0" TO 17'-11"
4:14:1
4:1
4:1
CUT SECTION CUT SECTION
CUT SECTION
FILL SECTION FILL SECTION
FILL SECTION
FILL SECTION
FILL SECTION
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 19
Appendix E – Maintenance of Traffic Concepts
CA
LC
UL
AT
ED
CH
EC
KE
D
Q:\
OD
OT_
D1\
0117820
A.0
0 -
VA
N-12
7_224-12
22_15
86\110430\
Desig
n\
MO
T\
Base
maps\110430_
MO
T_
Ty
pic
als.d
gn
Sheet 10/10/2019 1:36:5
2 P
M cle
wis
1
2
XX
X
XX
X
V
AN-127/
224-12.2
2/
15.8
6M
AIN
TE
NA
NC
E
OF
TR
AF
FIC
TY
PIC
AL
SE
CTIO
NS
12' 12' WORK ZONE
WORK ZONE
2'
11'11' 2'6'WORK ZONE
2'
11'11' 2'6'
2'
WORK ZONE
2'
11'11' 2'6'
WORK ZONE WORK ZONE
WORKZONE12'12' 6'
2'9' 12' 12'ZONE
WORK
2'
WORK ZONE
2'
11'11' 2'6'WORK ZONE
2'
11'11' 2'6'
2'
WORKZONE12'12' 6'
2'9'
WORKZONE6'12'12'
2' 2'
ALTERNATE 1 PHASE 2
US 127 / CR 154
| R/W US 224 / US 127
EAST OF MARSH RD
US 224 / US 127
11'11' 6'
2'
WORK ZONE
TEMPORARY PAVEMENT
WEST OF MARSH RD
US 224 / US 127
ALTERNATE 1 PHASE 1
ALTERNATE 1 PHASE 3
| R/W US 224 / US 127
2'
WEST OF MARSH RD
US 224 / US 127
EAST OF MARSH RD
US 224 / US 127US 127 / CR 154
| R/W US 224 / US 127
15.6'13.4'
| R/W US 224 / US 127
15.6'13.4'ALTERNATE 2 PHASE 1
WEST OF MARSH RD
US 224 / US 127
| R/W US 224
EAST OF MARSH RD
US 224 / US 127
| R/W US 127
US 127 / CR 154
ALTERNATE 2 PHASE 2
ALTERNATE 2 PHASE 3
US 127 / CR 154
WEST OF MARSH RD
US 224 / US 127
EAST OF MARSH RD
US 224 / US 127
PAVEMENT
TRAFFIC ON PROPOSED
MAINTAIN
PAVEMENT
TRAFFIC ON PROPOSED
MAINTAIN
PAVEMENT
TRAFFIC ON PROPOSED
MAINTAIN
MARSH RD. CLOSED WITH TRAFFIC DETOURED
| R/W US 224 / US 127
15.6'13.4'
| R/W US 127
4' 15'13'
| R/W US 127
4'
14'14'
CLOSE AND DETOUR
US 127 / CR 154
| R/W US 127
10'10'
MARSH RD
| R/W US 127
10'10'
MARSH RD
EAST AND WEST OF MARSH RD
US 224 / US 127
MARSH RD
CLOSE AND DETOUR
US 127 / CR 154
CLOSE AND DETOUR
| R/W US 224 / US 127
15.6'13.4'
| R/W US 224 / US 127
15.6'13.4'
WEST OF MARSH RD
US 224 / US 127
| R/W US 224
EAST OF MARSH RD
US 224 / US 127
| R/W US 224
PAVEMENT
TRAFFIC ON PROPOSED
MAINTAIN
| R/W US 127
10'10'
MARSH RD
10'10'
MARSH RD
| R/W US 127
WORK ZONE
WORK ZONE
| R/W US 127
ALT 1 PHASE 1
| R/W US 127
POT Sta. 645+83.82
646
647
648
649
650
651
652
653
654
POT Sta. 654+25.28
824
825
826
827
828
829
PT Sta. 829+57.59
830
831
832
833
834
835
PC Sta. 835+62.91
836
837
PT Sta.
837+92.6
5
838
839
840
841
842
843
844
845
846
847
848
849
850
PO
T Sta.
850+28.4
5
1314
1516
1718
POT Sta. 18+21.59
PO
T Sta. 500
+00.00
500 501
PO
T Sta. 502+00.00
POT Sta. 653+45.28
654
655
656
WORK ZONE
2'
6'VARIES
11'11' 2'6'
2'
12' 12'
| R/W US 127
| R/W US 224 / US 127
ALT 1 PHASE 2
ALT 1 PHASE 3
PO
T Sta. 500
+00.00
500 501
PO
T Sta. 502+00.00
POT Sta. 653+45.28
ALT 2 PHASE 1
500 501
POT Sta. 653+45.28
ALT 2 PHASE 2
ALT 2 PHASE 4
ALT 2 PHASE 3
Feasibility Study
VAN-127/224-12.22/15.86
PID 110430
Page 20
Appendix F – Alternatives Construction Costs
UNIT PRICE CONSTRUCTION COST
202 23010 PAVEMENT REMOVED, ASPHALT 8256 SY $8.19 $67,630
202 38000 GUARDRAIL REMOVED 300 FT $2.12 $640
203 10000 EXCAVATION 6044 CY $13.07 $78,980
203 20000 EMBANKMENT 7862 CY $8.72 $68,590
204 10000 SUBGRADE COMPACTION 23360 SY $1.94 $45,360
301 46000 ASPHALT CONCRETE BASE, PG64-22 3616 CY $170.00 $614,740
304 20000 AGGREGATE BASE 3755 CY $56.96 $213,900
407 10000 TACK COAT 3129 GAL $2.39 $7,480
411 10000 STABILIZED CRUSHED AGGREGATE 50 CY $73.60 $3,680
441 10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG64-22 725 CY $170.00 $123,250
441 10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2, (446) 1014 CY $170.00 $172,380
606 15050 GUARDRAIL, TYPE MGS 300 FT $18.56 $5,570
611 06400 15" CONDUIT, TYPE D 224 FT $55.73 $12,480
611 10600 24" CONDUIT, TYPE C 1050 FT $110.58 $116,110
625 10490 LIGHT POLE, CONVENTIONAL 20 EACH $2,161.10 $43,220
625 14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP 20 EACH $1,595.42 $31,910
625 26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED) 20 EACH $586.21 $11,720
659 10000 SEEDING AND MULCHING 17722 SY $1.17 $20,670
ASPHALT DRIVEWAYS 1484 SY $40.00 $59,380
CONCRETE DRIVEWAYS 104 SY $50.00 $5,180
TEMPORARY PAVEMENT 3400 SY $60.00 $204,000
UTILITY RELOCATIONS 1 LUMP $105,000 $105,000
Subtotal: $2,011,87035% $704,150
$2,720,000
PROJECT NOTES & ASSUMPTIONS:
3.3%
2018
2022Assumed Construction Year:
Contingency %:
TOTAL COST:
Assumed Annual Inflation (%)
Unit Price Basis Year:
2022 TOTAL 2022
VAN-127/224-12.22/15.86 INTERSECTION IMPROVEMENTS
PID 110430
FEASIBILITY STUDY COST ESTIMATE
ALTERNATIVE 1 - TURN LANES
ITEMITEM
EXTENSIONITEM DESCRIPTION TOTAL
QUANTITY UNIT
UNIT PRICE CONSTRUCTION COST
202 23010 PAVEMENT REMOVED, ASPHALT 10010 SY $8.19 $82,000
202 38000 GUARDRAIL REMOVED 100 FT $2.12 $210
203 10000 EXCAVATION 2575 CY $13.07 $33,650
203 20000 EMBANKMENT 6420 CY $8.72 $56,010
204 10000 SUBGRADE COMPACTION 10833 SY $1.94 $21,040
301 46000 ASPHALT CONCRETE BASE, PG64-22 1677 CY $170.00 $285,100
304 20000 AGGREGATE BASE 2111 CY $56.96 $120,250
407 10000 TACK COAT 1452 GAL $2.39 $3,470
441 10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG64-22 336 CY $170.00 $57,120
441 10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2, (446) 471 CY $170.00 $80,070
452 12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC1 541 SY $80.98 $43,810
606 15050 GUARDRAIL, TYPE MGS 100 FT $18.56 $1,860
609 12000 COMBINATION CURB AND GUTTER, TYPE 2 2430 FT $26.12 $63,460
609 26000 CURB, TYPE 6 214 FT $21.70 $4,640
609 98000 CURB, MISC.: 2464 FT $36.04 $88,800
611 06400 15" CONDUIT, TYPE D 416 FT $55.73 $23,190
611 10600 24" CONDUIT, TYPE C 1050 FT $110.58 $116,110
625 10490 LIGHT POLE, CONVENTIONAL 17 EACH $2,161.10 $36,740
625 14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP 17 EACH $1,595.42 $27,120
625 26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED) 17 EACH $586.21 $9,970
659 10000 SEEDING AND MULCHING 10262 SY $1.17 $11,970
ASPHALT DRIVEWAYS 1054 SY $40.00 $42,170
CONCRETE DRIVEWAYS 167 SY $50.00 $8,330
TEMPORARY PAVEMENT 2750 SY $60.00 $165,000
UTILITY RELOCATIONS 1 LUMP $195,000 $195,000
Subtotal: $1,577,09035% $551,980
$2,130,000
PROJECT NOTES & ASSUMPTIONS:
3.3%
2018
2022
VAN-127/224-12.22/15.86 INTERSECTION IMPROVEMENTS
PID 110430
FEASIBILITY STUDY COST ESTIMATE
ALTERNATIVE 2 - ROUNDABOUT
ITEMITEM
EXTENSIONITEM DESCRIPTION TOTAL
QUANTITY UNIT
2022 TOTAL 2022
Assumed Construction Year:
Contingency %:
TOTAL COST:
Assumed Annual Inflation (%)
Unit Price Basis Year: