58
APPROVAL SHEET INDIVIDUAL ASSIGNMENT REPORT TK 4090 INTERNSHIP SEMESTER I 2014/2015 Annisa Mienda Chintyarani (13011071) Note/comment : Internship Location : Map Tha Put Industrial Estate, Rayong, Thailand. Internship Period : May 22 nd 2014 July 31 st 2014 Has been examined and approved by: Mentor Advisor Supranee Kanokwajamrus Senior Process Engineer Dr. Dwiwahju Sasongko Date : _____________ Date :____________

Feasibility study of wastewater treatment in specialty chemical plants

Embed Size (px)

DESCRIPTION

Feasibility study of wastewater treatment in propylene oxide, polyether polyol, and polymer polyol plant

Citation preview

  • APPROVAL SHEET

    INDIVIDUAL ASSIGNMENT REPORT

    TK 4090 INTERNSHIP

    SEMESTER I 2014/2015

    Annisa Mienda Chintyarani (13011071)

    Note/comment :

    Internship Location : Map Tha Put Industrial Estate, Rayong, Thailand.

    Internship Period : May 22nd

    2014 July 31st 2014

    Has been examined and approved by:

    Mentor Advisor

    Supranee Kanokwajamrus

    Senior Process Engineer

    Dr. Dwiwahju Sasongko

    Date : _____________ Date :____________

  • i

    PREFACE

    The author would like to acknowledge her countless thanks to the Most Gracious and the Most

    Merciful, Allah SWT who always gives their all the best of this life, so the author is able to

    complete the internship and its report during May 22nd

    2014 July 31st 2014 in PTT Global Chemical Company Limited. Shalawat and Salaam to the Prophet Muhammad SAW and his

    family. This script is presented to fulfill one of the requirements in accomplishing the Bachelor

    Degree at Chemical Engineering Department, Faculty of Industrial Technology, Institut

    Teknologi Bandung.

    The authors would like to take their opportunity to express their deep and sincere gratitude to the

    following:

    1. Dr. Dwiwahju Sasongko, as the advisor who has guided the authors patiently during the internship period

    2. Dr. IGBN Makertihartha, as the coordinator of TK4090 Internship 3. Nittaya Boonyarit, as Process Engineer Manager in PTT Global Chemical 4. Supranee Kanokwajamrus, as Senior Process Engineer as well as authors mentor from

    Process Engineer Division in PTT Global Chemical.

    In addition, author would also thank others who give their full help and support during the

    internship, they are:

    1. Dilok Tuekla, as Vice President of Human Resources PTT Global Chemical Company who gave an opportunity for us to get new experience throughout this internship program

    2. Supat Arunlerktawin, as Manager of Training Center Management PTT Global Chemical Company

    3. Kammasit Wichitphan, as HR Officer at PTT Global Chemical Company 4. Jaratsri Rakkaew, as Senior HR Officer at PTT Global Chemical Company 5. Sirinun Sirisaard, as HR Officer PTT at Global Chemical Company 6. Kevin Wun, as Internship Manager at PTT Global Chemimal 7. All employees in PTT Global Chemical Company 8. All family in Bandung who always give support during internship program.

    This report is not perfect and is open for corrections. Hope it will be useful for the readers.

    Rayong, 31st July 2014

    Author

  • ii

    TABLE OF CONTENTS

    CHAPTER I .................................................................................................................................... 1

    INTRODUCTION ........................................................................................................................... 1

    1.1 Background ............................................................................................................................ 1

    1.2 Objectives .............................................................................................................................. 1

    1.3 Scopes of work ...................................................................................................................... 1

    CHAPTER II ................................................................................................................................... 2

    LITERATURE ................................................................................................................................ 2

    2.1 The importance of wastewater treatment ............................................................................... 2

    2.2 Wastewater treatment selection ............................................................................................. 2

    2.3 Physical, biological, and chemical wastewater treatment ..................................................... 4

    2.4 General PO/SM, polymer polyol, and polyether polyol plants wastewater characteristics . 5

    CHAPTER III .................................................................................................................................. 6

    METHODOLOGY .......................................................................................................................... 6

    CHAPTER IV .................................................................................................................................. 7

    RESULTS AND DISCUSSION ..................................................................................................... 7

    4.1 Wastewater Characteristics .................................................................................................... 7

    4.1.1 Wastewater sources ......................................................................................................... 7

    4.1.2 Wastewater composition ................................................................................................. 7

    4.1.3 Wastewater classification .............................................................................................. 10

    4.2 Available Technology for Wastewater Treatment ............................................................... 11

    4.2.1 Technology for high polluted and low polluted stream .......................................... 11

    4.2.2 Technology for salt stream ...................................................................................... 29

    4.3 Technology Selection .......................................................................................................... 37

    CHAPTER V ................................................................................................................................. 41

    CONCLUSIONS AND RECOMMENDATIONS ........................................................................ 41

    5.1 Conclusions.......................................................................................................................... 41

    5.2 Recommendations ................................................................................................................ 41

    APPENDIX A ............................................................................................................................... 42

    REFERENCES .............................................................................................................................. 44

  • iii

    TABLE OF FIGURES

    Figure 2.1 Wastewater treatment method selection ........................................................................ 3

    Figure 2.2 Inhibitory compounds for biological treatment ............................................................. 5

    Figure 3.1 Workflow diagram of feasibility study .......................................................................... 6

    Figure 4.1 Wet air oxidation process ............................................................................................. 13

    Figure 4.2 Scheme of ozone oxidation process ............................................................................. 14

    Figure 4.3 Repsol PACT system unit ......................................................................................... 15

    Figure 4.4 Comparison between external and internal membrane configuration ......................... 17

    Figure 4.5 Process scheme of external membrane system in Commune De Monteux WWT ...... 18

    Figure 4.6 Oxidation ditch system ................................................................................................ 20

    Figure 4.7 Block diagram of TAR system .................................................................................... 25

    Figure 4.8 Schematic figures of multiple hearth (left) and fluidized bed (right) .......................... 30

    Figure 4.6 Block diagram of Ozone oxidation-MBR system ........................................................ 32

    Figure 4.7 Block diagram of Fenton oxidation-oxidation ditch .................................................... 32

    Figure 4.9. Schematic diagram of electrodialysis reversal system ................................................ 35

  • iv

    TABLE OF TABLES

    Table 4.1 Summary of wastewater characteristic from POSM, Polyether Polyol, and polymer

    polyol unit ........................................................................................................................................ 8

    Table 4.1 Summary of wastewater characteristic from POSM, Polyether Polyol, and polymer

    polyol unit (contd.) .......................................................................................................................... 9

    Table 4.2 Wastewater classification .............................................................................................. 10

    Table 4.2 Wastewater classification (contd.) ................................................................................ 11

    Table 4.3 Required wastewater specification to discharge to Hemmaraj ..................................... 11

    Table 4.4 Summary of single wastewater treatment method ........................................................ 20

    Table 4.5 Reference plants and vendors of single methods .......................................................... 21

    Table 4.5 Reference plants and vendors of single methods (contd.) ............................................. 22

    Table 4.6 Summary of TAR system .............................................................................................. 24

    Table 4.7 Summary of ozone oxidation MBR system ............................................................... 26

    Table 4.8 Summary of ozone oxidation MBR system ............................................................... 27

    Table 4.9 Summary of Fenton oxidation oxidation ditch system ............................................... 29

    Table 4.10. Comparison between fluidized bed and multiple hearth ............................................ 33

    Table 4.11 Strengths and weaknesses of thermal oxidation system .............................................. 33

    Table 4.12 Summary of technical and economic information about thermal oxidation system ... 34

    Table 4.13 Summary of technical and economic information of EDR system ............................. 36

    Table 4.14 Scoring of wastewater treatment method .................................................................... 39

    Table 4.14 Scoring of wastewater treatment method (cotd.) ........................................................ 40

    Table 4.15 Summary of HPW & LPW treatment methods ........................................................... 41

    Table 4.15 Summary of HPW & LPW treatment methods (contd.) ............................................. 42

    Table 4.16 Summary of salt treatment methods ............................................................................ 42

    Table 4.16 Summary of salt treatment methods (contd.) .............................................................. 43

    Table 4.17 Scoring result of HPW and LPW treatment methods ................................................. 44

    Table 4.17 Scoring result of HPW and LPW treatment methods (contd.) .................................... 45

    Table 4.18 Scoring result of salt stream treatment methods ......................................................... 46

    Table 4.18 Scoring result of salt stream treatment methods (cotd.) .............................................. 47

  • 1

    CHAPTER I

    INTRODUCTION

    1.1 Background

    As environmental issue has been spread widely all over the world, people are now more concern

    to the life of environment. One of the efforts that they do to save the environment is by reducing

    waste that is dumped to the surroundings. This waste reducing effort is undertaken by various

    parties, including industries which its activities are one of the largest waste producers in the

    world.

    PTT Global Chemical is an industry that has high concern to the life of environment. Though its

    running production process definitely produces waste, PTTGC always strives to meet

    specification of waste disposal. One of the projects that has been carried out recently by process

    engineers in this company is about the propylene oxide, polyether polyol, and polymer polyol

    plants, including its wastewater treatment system. Due to their concern on waste and

    environment, they are striving to look for the best wastewater treatment method that could

    reduce the wastewater contaminants and minimize its adverse impact on environment.

    1.2 Objectives

    The objectives of this feasibility study are:

    1. To explore available methods for treating propylene oxide, polymer polyol, and polyether

    polyol plants wastewater

    2. To recommend commercially available technology for the selected method

    3. To propose technology and vendor for treating the wastewater

    4. To propose the most suitable method/technology for treating the wastewater

    1.3 Scopes of work

    The scopes of work of this feasibility study are:

    1. Identify the PO, polyether polyol, and polymer polyol plants wastewater characteristics

    2. Determine the general wastewater treatment process based on the wastewaters characteristics

    3. Explore the information of the available wastewater treatment methods

    4. Compare and select the most suitable wastewater treatment method based on specified criteria

    5. Explore the information of the selected methods licenses

    6. Compare and select the most suitable license for the selected method based on specified

    criteria

  • 2

    CHAPTER II

    LITERATURE

    2.1 The importance of wastewater treatment

    Across the world, there continues to be huge volumes of wastewater pumped directly into rivers,

    streams and the ocean. The impact of this is severe, aside from the damage to the marine

    environment and to fisheries it, it does little to preserve water at a time when many are predicting

    that a global shortage is just around the corner.

    As it stands this method of disposing of wastewater any form of water that has been

    contaminated by a commercial or domestic process, including sewage and byproducts of

    manufacturing and mining is largely an issue in developing nations. The regulation of waste

    disposal in developing nations is seems not too firm, especially in monitoring the maximum

    amount of wastewater contaminants that discharged by the industries. In the other hand, perhaps

    the waste water treatment technology itself is still not capable to provide safe and

    environmentally friendly treated water due to the high cost of installation and operation of

    sophisticated wastewater treatment system. As an example, The World Bank estimated that

    Vietnam will need an investment of $8.3 billion in order to provide the necessary wastewater

    services (Wright, 2014). The underdeveloped wastewater treatment technologies and lack of

    regulation regarding wastewater disposal are indeed threats to the environmental sustainability. If

    such situation keep abandoned, we will probably no longer have water to use in everyday life.

    When water is used by our society including industrial activities, the water becomes

    contaminated with pollutants. If left untreated, these pollutants would negatively affect the water

    and environment. For example, organic matter can cause oxygen depletion in lakes, rivers, and

    streams. This biological decomposition of organics could result in fish kills and/or foul odors.

    Nutrients in wastewater, such as phosphorus, can cause premature aging of the lakes, called

    Eutrophication. Additionally, there are many pollutants that could exhibit toxic effects on aquatic

    life and the public. Therefore, pollutants must be removed from the water to protect the

    environment and public health.

    2.2 Wastewater treatment selection

    The applied wastewater treatment method actually depends on the characteristics of the

    wastewater itself. Different characteristics of wastewater will result in different wastewater

    treatment method. Therefore, it is important to determine the characteristics of the wastewater

    before deciding which wastewater treatment is best to be applied.

    Selecting wastewater treatment method based on wastewater characteristics is carried out

    through the steps shown in Figure 2.1.

  • 3

    Figure 2.1 Wastewater treatment method selection

    (Source: Setiadi, 2014)

    Aliran air limbah

    Inorganik Organik

    Pretreatment

    Insinerasi atau wet

    air oxidation

    ya

    ya

    ya

    ya

    ya

    Off-gas treatment

    Limbah Padat

    Filter atau

    regenerasi media

    adsorpsi

    Solid / Concentrated Phase

    Perlunya

    Pretreatment

    untuk netralisasi

    tidak

    Dapat

    terbiodegradasi

    Perlunya

    pretreatment

    penghilangan

    minyak dan lemak

    Tersedia ruang

    lahan yang luas

    Perlunya aerasi

    Perlunya solids

    recovery

    Kolam ekualisasi

    tidak

    tidak

    ya

    tidak

    ya

    Air / Steam

    Stripping

    Koagulasi,

    flokulasi, dan

    sedimentasi

    Filtrasi atau

    Adsorpsi karbon

    aktif

    Evaporasi atau

    ekstraksi

    Pemisahan minyak

    / air

    Trickling filter

    atau Fixed-film

    Biotreatment

    Lumpur aktif atau

    aerated lagoon

    Anaerobic

    treatment

    ya

    ya

    tidak

    yaMengandung

    kontaminan yang

    dapat di-stripping

    mis. amonia

    Mengandung

    kontaminan yang

    dapat dipresipitasi

    Mengandung

    kontaminan yang

    dapat disaring atau

    diadsorb

    Limbah dapat

    dimanfaatkan

    kembali atau

    direduksi

    volumenya

    Limbah harus

    dihancurkan

    tidak

    tidak

    tidak

    tidak

    Mengandung

    kontaminan yang

    dapat di-stripping

    Mengandung

    kontaminan yang

    dapat disaring atau

    diadsorb

    Limbah dapat

    dimanfaatkan

    kembali atau

    direduksi

    volumenya

    Limbah harus

    dihancurkan

    tidak

    tidak

    tidak

    tidak

    Mengandung

    kontaminan yang

    dapat dioksidasi

    atau direduksi

    secara kimia

    minyak

    tidak ya

    ya

    ya

    ya

    Insinerasi atau wet

    air oxidation

    Air / Steam

    Stripping

    Oksidasi / reduksi

    kimia

    Evaporasi atau

    ekstraksi

    Solid / Concentrated Phase

    Filtrasi atau

    Adsorpsi karbon

    aktif

    Filter atau

    regenerasi media

    adsorpsi

    Off-gas treatment

    Wastewater stream

    Inorganic Organic

    Requires

    pretreatment for

    neutralization

    Contains

    contaminants that

    can be stripped

    Contains

    contaminants that

    can be

    precipitated

    Contains

    contaminants that

    can be filtered or

    adsorbed

    Waste can be reused

    or its volume can be

    reduced

    Destroy the waste Incineration

    Evaporation or

    extraction

    Filtration/activated

    carbon adsorption

    Coagulation,

    flocculation,

    sedimentation

    Solid waste

    Filter /

    adsorption

    Biodegradable

    Needs

    pretreatment to

    remove oil &

    grease

    Large land area is

    available

    Requires aeration

    Requires solids

    recovery

    Equalization tank

    Activated sludge /

    aerated lagoon

    Tricking filter / fixed

    film biotreatment

    Oil water

    separation

    Contains

    contaminants that

    can be stripped

    Contains

    contaminants that

    can be filtered or

    adsorbed

    Filtration/activated

    carbon adsorption

    Filter /

    adsorption

    Contains

    contaminants that

    can be chemically

    reduced or

    oxidized

    Chemical

    oxidation/reduction

    Waste can be reused

    or its volume can be

    reduced

    Destroy the waste Incineration

    Evaporation /

    extraction

    No

    Oil

    No

    No

    No No

    No

    No

    No No

    No

    No

    No

    No

  • 4

    2.3 Physical, biological, and chemical wastewater treatment

    Physical wastewater treatment methods include processes where no gross chemical or

    biological changes are carried out and physical phenomena are used to treat the

    wastewater. Physical methods are usually carried out in order to remove large entrained

    object in the wastewater such as solids. Examples of physical wastewater treatment

    method are screening, sedimentation, clarification, filtration, and many others. Physical

    treatment is usually carried out at the preliminary step of wastewater treatment before the

    wastewater is routed to the next treatment steps.

    Biological wastewater treatment is a method to treat wastewater by biological activity,

    mostly microorganisms. Biological treatment is an important part of any wastewater

    treatment plant that treats wastewater from either municipality or industry having soluble

    organic impurities or a mix of two types of wastewater sources. Compared to chemical

    treatment, biological treatment has more obvious economic advantage, both in terms of

    capital investment and operating cost.

    Although biological treatment seems economically promising, there are stringent

    requirements for wastewater that will be treated biologically. The main requirement is that

    the wastewater has to meet a certain amount of biological oxygen demand and chemical

    oxygen demand ratio (BOD/COD). Wastewater with BOD/COD ratio is less than 0.1

    shows that the wastewater is hard to be treated biologically. Therefore, the wastewater

    should be treated by other method first before sent to biological treatment in order to

    increase its BOD/COD ratio. A BOD/COD ratio of 0.4 0.6 shows that the wastewater

    should be treated by aerobic biological treatment, which involves contacting wastewater

    with microbes and oxygen to optimize the growth and efficiency of biomass. Wastewater

    with BOD/COD ratio >0.6 shows that it should be treated by anaerobic biological

    treatment which does not require addition of oxygen.

    In biological treatment, the performance of the treatment is dependent upon the activity of

    microorganisms and their metabolism which can be dramatically affected by toxic

    compounds in the wastewater. Many materials such as organic and inorganic solvents,

    heavy metals, and biocides can inhibit the biological activity in the treatment plant. Figure

    2.2 lists inhibitory levels reported for some metals, inorganic, and organic substances

    which affect the effectiveness of biological treatment.

    If wastewater has low BOD/COD level and/or contains inhibitory compound which makes

    it infeasible to be treated by biological treatment, then other options of wastewater

    treatment needs to be carried out. One promising option is by chemical treatment, which

    consists of using chemical reactions to improve the wastewater quality. Chemicals used in

    chemical treatment are usually strong oxidizers such as chlorine, hydrogen peroxide,

    ozone, and many others. Such oxidizers can remove nearly all contaminants in the

    wastewater, including materials that are recalcitrant or even refractory to biological

    treatment.

  • 5

    Contrary to biological treatment, influent requirements to enter chemical treatment are not

    as stringent as biological treatment. However, the cost of chemical treatment is usually

    higher, especially to treat highly contaminated wastewater.

    Figure 2.2 Inhibitory compounds for biological treatment

    (Source: Wastewater Treatment Manuals, 1997)

    2.4 General PO/SM, polymer polyol, and polyether polyol plants wastewater

    characteristics

    In general, one of major wastewater sources in PO/SM, polymer polyol, and polyether

    polyol plant is the alkaline washing unit. This alkaline washing produces an aqueous

    stream, also called alkaline purge, highly loaded in organic compounds and sodium which

    can be taken integrally to water treatment, without any prior pre-treatment, which permits

    the recovery of organic matter. The typical composition of the alkaline purge is included

    between values of 4 and 8% of compounds of alcoholic nature, largely monopropylene

    glycol and methylbenzyl alcohol, between values of 3 and 6% of organic salts, largely

    sodium benzoate and phenolate and a content greater than 2% of sodium hydroxide.

    The purification treatment of waste water arising in the process of PO/SM, polyether

    polyol, and polymer polyol is very expensive, mainly due to three aspects: its high content

    in organic matter which is translated into a high value of the chemical oxygen demand

    (COD greater than 40% by weight), the high flow of said stream and, finally, the fact that

    it contains organic compounds which are not easily degradable.

  • 6

    CHAPTER III

    METHODOLOGY

    The main objective of this feasibility study is to determine the most suitable commercial

    wastewater treatment method to treat wastewater from PO/SM, polyether polyol, and

    polymer polyol plant. The objectives can be achieved through the following steps:

    1. Studying wastewater characteristics

    The aim of wastewater characteristics study is to determine the characteristics of the

    wastewater. The wastewater characteristic is determined through studying data of

    wastewaters contaminants.

    2. Studying commercially available technology for the wastewater treatment

    After determining characteristic of the wastewater, study about commercially available

    technologies that are possible to treat the wastewater is carried out. These technologies

    are further selected based on specified criteria to determine which technologies are the

    best to be applied in the wastewater treatment system.

    3. Technology selection

    Selecting wastewater treatment technology is carried out through scoring. Before

    scoring, criteria for selecting the wastewater treatment methods are determined. Those

    criteria are then being scored based on the wastewater treatment data from the study.

    Each criteria will contribute a certain percentage to the overall score. Method that has the

    highest score will be considered as the most suitable wastewater treatment method. A

    workflow diagram of this feasibility study is shown below.

    Figure 3.1 Workflow diagram of feasibility study

    Studying wastewater

    characteristic

    Wastewater

    characteristic

    Start

    Studying commercially

    available technology

    Commercially

    available

    technologies

    Technology selection The most suitable

    wastewater treatment

    method

    Finish

  • 7

    CHAPTER IV

    RESULTS AND DISCUSSION

    4.1 Wastewater Characteristics

    4.1.1 Wastewater sources

    The wastewater given in this case comes from three main units. These units are Propylene

    Oxide/Styrene Monomer (POSM) Unit, Polyether Polyol (PoP) Unit, and Polymer Polyol

    (PoP) Unit. More detailed information about the wastewater coming from each unit is

    described below:

    1. Propylene Oxide/Styrene Monomer (POSM) Unit

    The POSM Unit generates five streams of wastewater. These streams are Highly Polluted

    Water (HPW), Acid Purge (AP) Stream, Low Polluted Water (LPW), rain water, and

    laboratory residual stream. The HPW is a caustic wastewater generated from washing

    section and dehydration reaction in POSM unit, while the AP stream is generated in the

    oxidation section. The LPW comes from final emptying of equipment that could not be

    pumped out.

    2. Polyether Polyol (PeP) Unit

    The Polyol Unit consists of two subunits: Flexible and Rigid & CASE Unit. Each subunit

    generates five streams of wastewater namely HPW, LPW, rain water, laboratory residual

    stream, and by-product (high salt) stream. However, though the types and composition of

    the stream from both subunits are identical, the flow rate is different between one and

    another.

    3. Polymer Polyol (PoP) Unit

    The polymer polyol unit generates two types of wastewater: highly polluted water (HPW)

    and low polluted water (LPW). The HPW comes from monomers recovery system and

    condensate vacuum system. The LPW consists of liquid from final emptying of equipment,

    rain water collected from process area, effluent from gas abatement device, and laboratory

    residual stream.

    4.1.2 Wastewater composition

    The composition of wastewater that is generated in each unit is summarized in Table 4.1.

  • 8

    Table 4.1 Summary of wastewater characteristic from POSM, Polyether Polyol, and polymer polyol unit

    (Source: OSBL Basis Design Data for Repsol, 2014)

    Unit Type Flow rate (m

    3/h)

    Temperature (oC)

    Contaminants (mg/l) Note

    Normal Max pH COD BOD SS Oil TDS

    Propylene

    Oxide-

    Styrene

    Monomer

    (POSM)

    Highly Polluted Water

    (LPW) 27-32 32

    Depends on the waste

    water stream (usually

    30-40C from the

    washing sections).

    The storage tank for

    this streams usually

    operates between 15-

    20C

    13-14 180,000 -

    200,000 4-5

    Using either

    biological waste

    water

    treatments and

    incinerator Acid Purge (AP) Stream 5.7 6.7 6.7 75 1.8-2 75,000

    Low Polluted Water

    (LPW)

    Rainwater

    Laboratory residual

    stream

    Polyether

    Polyol

    (Flexible)

    Highly Polluted Water

    (LPW) 0.07 12-14 46% 21%

    Low Polluted Water

    (LPW) 4.38

    7.5-8.5 (vacuum

    system), 0.5

    (abatement

    device)

    1.1% (vacuum

    system), 5%

    (abatement

    device)

    0.1-0.6%

    (vacuum

    system), 3%

    (abatement

    device)

    Rainwater

    Laboratory residual

    stream

    By-product stream (high

    salt) 0.225

    Potassium

    content >14%

    Polyol content

  • 9

    Table 4.1 Summary of wastewater characteristic from POSM, Polyether Polyol, and polymer polyol unit (contd.)

    (Source: OSBL Basis Design Data for Repsol, 2014)

    Unit Type Flowrate (m

    3/h)

    Temperature (oC)

    Contaminants (mg/l) Note

    Normal Max pH COD BOD SS Oil TDS

    Polyether

    Polyol

    (RIGID &

    CASE)

    Highly Polluted Water

    (LPW) 0.078 12-14 46% 21%

    Low Polluted Water

    (LPW) 6

    7.5-8.5 (vacuum

    system), 0.5

    (abatement

    device)

    1.1% (vacuum

    system), 5%

    (abatement

    device)

    0.1-0.6%

    (vacuum

    system), 3%

    (abatement

    device)

    Rainwater

    Laboratory residual

    stream 0.15

    By-product stream (high

    salt)

    Potassium

    content >14%

    Polyol content

  • 10

    According to wastewater compositions and characteristics in Table 4.1, it is shown that

    contaminants in the wastewater are mostly organic compounds, which is represented by

    chemical oxygen demand (COD) level. The range of COD level in the wastewater streams

    varies greatly, from 3,000 ppm to 180,000 ppm. Some of the streams also have very low

    ratio of BOD/COD (< 0.1) which indicates that those streams are hard to be degraded

    biologically. In addition, by-product streams from polyether polyol plant consist of polyol,

    a chemical compound which is recalcitrant to biological treatment.

    Although some streams are seem to be hardly biodegradable, some of the remaining

    streams are likely possible to be sent to biological treatment due to its low level of COD.

    Those streams are the LPW of polyether polyol (flexible) unit which has BOD/COD level

    of 0.47, LPW from PO/SM plant, and also LPW from polyether polyol plant.Beside

    organic contaminants, some streams in the wastewater also have nitrogen, salt

    components, and even a small amount of oil.

    4.1.3 Wastewater classification

    The variety of contaminants in the wastewater makes the streams should be classified

    based on the type and level of contaminants. This is done because some types of

    contaminants may inhibit treatment process to remove the other contaminants type. For

    example, the presence of salt in the wastewater may inhibit chemical process to remove

    organic contaminants. Thus, salt and organic-containing wastewater should be separated

    and treated by different method.

    Based on the types and contaminants level, the wastewater is separated into three main

    streams. The first and the second streams are streams without salt content while the third

    streams are streams that contain salt, namely salt stream. The major contaminants in the

    first and second streams are organics and nitrogen. The first streams are those that contain

    high COD level (>10,000 ppm) as well as low BOD/COD ratio (

  • 11

    Table 4.2 Wastewater classification (contd.)

    Classification Streams Final characteristics

    Salt stream By-product from polyether polyol

    (rigid & CASE) unit

    Flow rate: 0.5 m3/h

    Potassium content: 100,382

    ppm

    Polyol content: 35,581 ppm

    BOD: 62,160 ppm

    COD: 136,160 ppm

    By-product from polyether polyol

    (flexible) unit

    HPW from polyether polyol

    (rigid & CASE) unit

    HPW from polyether polyol

    (flexible) unit

    All of the streams will be discharged to Hemmaraj Industrial Wastewater Treatment. The

    required wastewater specification to be discarged to Hemmaraj is shown in Table 4.3.

    Table 4.3 Required wastewater specification to discharge to Hemmaraj

    (Source: Hemmarajs wastewater discharge specification, 2014)

    Contaminant Maximum level

    BOD < 500 mg/l

    COD 750 mg/l

    Suspended solid 200 mg/l

    TDS 3000 mg/l

    TKN 100 mg/l

    pH 5.5 9.0

    Temperature 45oC

    Oil and fat 10 g/l

    4.2 Available Technology for Wastewater Treatment

    As we separate the wastewater into three main streams, the treatment method for each

    stream should be different. Available technologies that may be possible to treat the

    wastewater streams are described below.

    4.2.1 Technology for high polluted and low polluted stream

    4.2.1.1 Single method

    In order to reduce the contaminant as well as to meet the wastewater discharge

    requirement to Hemmaraj, the wastewater needs to be treated by several means of

    technology. The technology could be chemical, biological, or even combination of

    chemical and biological treatment. If the contaminant in the wastewater is not too high, the

    wastewater can be treated by only one technology to meet the Hemmarajs discharge

    specification. The technology is referred as a single method. The following explanation

  • 12

    will describe available single methods that could be applied to reduce the wastewater

    contaminant. All of the following single methods have been applied commercially, either

    as industrial or municipal wastewater treatment method.

    1. Wet Air Oxidation (WAO)

    The wet air oxidation process is a type of chemical treatment. It is an oxidation reaction

    that occurs in the liquid phase. The chemistry of wet oxidation is such large molecules

    which are difficult to treat biologically are oxidized by dissolved oxygen at an elevated

    pressure and temperature. The elevated pressure in wet air oxidation process is required to

    maintain the water in the liquid phase.

    Wet oxidation reaction kinetics has been the subject of numerous studies. It is then

    indicated that the oxidation proceeds by a free-radical reaction mechanism. In the absence

    of initiators, free radicals are formed by reaction of oxygen with the weakest C-H bond of

    the oxidized organic compound. The free radicals which has large electron affinity then

    oxidizes organics and other compounds, such as sulfur, halides, nitrogen, and phosphor.

    The formation of free radicals is shown in reaction (1) (4), while oxidation of wastewater

    contaminants is shown in reaction (5) (10).

    RH + O2 Ro + HO2

    0 (1)

    RH + HO2o Ro + H2O2 (2)

    H2O2 + M 2OHo (3)

    H2O2 H2O + O2 (4)

    Organics + O2 CO2 + H2O + RCOOH*

    (5)

    Sulfur species + O2 SO42-

    /other inorganic sulfates (6)

    Halides species + O2 inorganic halides (7)

    Organic Cl + O2 Cl- + CO2 + RCOOH

    * (8)

    Organic N + O2 NH3/NO3/elemental nitrogen + CO2 + RCOOH (9)

    Phosphorus + O2 PO43-

    (10) * Major fraction of residual organic compound

    Since the liquid phase in wet air oxidation is not vaporized, this process requires less

    energy for auto thermal operation rather than incineration. The nitrogen and sulfur

    compound that may present in the waste water stream are not released as gaseous NOx and

    SOx, but remain in the solution as acceptable nitrate and sulfate, meanwhile the

    hydrocarbon compounds are converted to CO2 and water. The complete oxidation is rarely

    happens, so a portion of organic COD will remain and ready to be treated biologically. The

    wet oxidized effluent usually exhibits BOD: COD ratio of 0.6-0.7

    The oxidation reaction is usually carried out at temperatures of 150oC to 320

    oC and

    pressure from 150 to 3200 psig. Oxygen as the oxidizing agent can be introduced from

    compressed air or even pure compressed oxygen. However, the use of air as oxygen source

    could lead to larger compressor cost, higher pressure rated equipment, and heat loss to

  • 13

    nitrogen component in the air. Therefore, the use of pure oxygen as the oxidizing agent is

    such an attractive option.

    During the operation, the feed of wet air oxidation system is pumped through heat

    exchangers by a high pressure pump combined with a small amount of compressed air.

    Introducing the feed stream along with small amount of compressed air is carried out in

    order to prevent fouling in the heat exchangers, which are used to heat the cold feed. For

    starting up, an external source of heat is needed to heat the cold feed. Heating the cold feed

    for starting up can be carried out in trim heater using steam or hot oil as the external

    sources of heat. The hot feed is then introduced from the bottom of the WAO reactor and

    the oxygen is introduced from another bottom part of the reactor.

    The outlet stream leaving the WAO reactor contains of two phase; hot gas and hot liquid.

    The outlet stream is then sent through heat exchanger to be cooled forthwith heating the

    incoming feed. The stream then goes through process cooler to be cooled by cooling water

    prior to pressure let-down across the pressure control valve. The cooled two-phase stream

    is sent to pressure control valve to be flashed before entering the separator. The separator

    receives the flashed two-phase stream, resulting separation of liquid effluent and non-

    condensable gas. The off-gas exits at the top of the separator and sent to the final treatment

    unit or being used for other process heating, such as in PO/SM boilers

    An application of wet air oxidation as wastewater treatment method can be seen at POSM

    plant of Repsol YPF in Tarragona, Spain. In its wastewater treatment plant, the oxidation

    of waste water occurs in bubble reactor at 295oC at 95 bar and 1.5 hour of reaction time

    using pure compressed oxygen as the oxidant.. The nominal COD reduction of waste water

    being treated by wet air oxidation is approximately 61%, resulting liquid effluent with

    COD range of 20,000-30,000 mg/L which is further treated by PACT. The scheme of wet

    oxidation process in POSM Plant of Repsol Tarragona is shown in Figure 3.

    Figure 4.1 Wet air oxidation process

    (Source: The Use of WAO and PACT for the Treatment of PO/SM Industrial Wastewater, 2002)

  • 14

    2. Ozone Oxidation

    Ozone (O3) is one of the strongest commercially available oxidizing agents. This molecule

    consists of three oxygen atoms which is unstable and very reactive under normal near-

    earth condition. When decomposes in water, ozone creates hydroxyl radicals which react

    quickly with a number of organic and inorganic compounds containing accessible amino

    groups, double bonds, or aromatic systems. A complex chain of reaction that occurs and

    results formation of OH* and superoxide

    * radicals is shown by reaction (1) (4) (Karat,

    2013).

    O3 + OH- O2

    *- + HO2

    * (1)

    O3 + O2*-

    O3*-

    + O2 (2)

    O3*-

    HO3*-

    (3)

    HO3*-

    OH* + O2 (4)

    Ozone reaction with inorganic or inorganic compounds is shown by reaction (5) and (6).

    CN- + O3 CNO

    - + O2 (5)

    RCH2OH + 2O3 RCOOH + 2O2 + H2O (6)

    Oxidation by ozone can be performed in ozonation reactor at a large range of pH. The OH*

    radical formation is dominant at high pH (>10), while the oxidative reaction with O3 is

    more selective at low pH (

  • 15

    3. Powdered Activated Carbon (PACT)

    PACT unit combines activated carbon adsorption and biological degradation to remove

    organic components in the wastewater. The biological activity is combined with carbon

    adsorption due to the wastewater components characteristic, which mostly contains

    aromatic and polyol compound that are hard to be degraded by microorganisms. The

    addition of activated carbon helps to adsorb organic components that can hardly be

    degraded by microorganisms, so they could cling to their food source more efficiently.

    An ordinary PACT unit consists of an aeration basin followed by a clarifier. The aeration

    basin is used for treating the wastewater by activated carbon absorption forthwith

    biological treatment. The effluent stream exiting the PACT unit is then sent to the clarifier

    to separate the liquid effluent and the sludge that contains microorganisms as well as

    activated carbon. Due to the presence of both biological growth and adsorption of organic

    components occurring in the PACT system, wasting of spent carbon is required. This

    wasted carbon is regenerated and returned to the PACT system.

    In order to optimize the removal of organic compound, PACT system is usually combined

    in series. Such system is applied in the waste water treatment of Repsol YPFs POSM

    plant. The PACT unit consists of two aeration basins, each followed by a clarifier. The

    first and the second set of PACT unit are called PACT-1 and PACT-2. The PACT-1

    consists of 65 m diameter concrete aeration basin and a 17 m diameter clarifier while

    PACT-2 consists of 30 m diameter aeration basin and a 17 m diameter clarifier. The flow

    rate of wastewater that enters this system is 90 m3/h and average COD level of 26,000

    ppm. The total COD reduction of both PACT tank is 97.6%. The scheme of the PACT unit

    is shown in Figure 4.3.

    Figure 4.3 Repsol PACT system unit

    (Source: The Use of WAO and PACT for the Treatment of PO/SM Industrial Wastewater, 2002)

  • 16

    In some plants, the presence of PACT system is followed by wet air regeneration (WAR).

    This system is used to recover the spent carbon from the PACT system. The recovered

    activated carbon is then sent back to PACT unit to adsorb organic contaminant in the

    wastewater.

    The process for wet air generation is actually similar to the wet air oxidation process but

    compressed air is used instead of oxygen. Before entering the wet air regeneration process,

    the PACT sludge is thickened to ~5% solids content to obtain sufficient COD content for

    auto thermal operation. The sludge is then pumped using hydraulic exchange pump and

    compressed air is added to the sludge before passing the heat exchanger to be heated to

    210oC. The hot stream sludge is then injected to the bottom of stainless steel bubble

    reactor which operates at 243oC and 63 bar. The effluent leaving the reactor passes through

    heat exchanger and cooled, resulting cooled fluid which sent to two phase separator. The

    two phase separator successfully results two separated phases: gas and slurry. The gas

    phase is sent to POSM plant boilers and the regenerated activated carbon slurry returns to

    PACT aeration tank. The inert ash from in the bottom of the reactor is collected and

    purged periodically to the storage drum, from where it is sent to filter press to be

    dewatered before disposal.

    4. Fenton Oxidation

    Fenton oxidation is a process of oxidizing contaminants in the wastewater by using a

    mixture of hydrogen peroxide (H2O2) and ferrous ion (Fe2+

    ). The process is based on

    formation of reactive oxidizing species by two reaction pathways: a radical pathway,

    which considers an OH radical formation (reaction 1) and a non-radical pathway

    considering ferryl ion production (reaction 2). Each reaction is shown as the following:

    Fe2+

    + H2O2 Fe3+

    + OH- + OH

    * (1)

    Fe2+

    + H2O2 FeO2+

    + H2O (2)

    The Fenton reagent destroys a wide variety of organic compounds without formation of

    toxic by-products (Barbusinski, 2009). Fenton oxidation process is characterized by its

    cost effectiveness, simplicity, and suitability to treat aqueous wastes with variable

    compositions. Comprehensive investigations show that Fenton oxidation is effective in

    treating various industrial wastewater contaminants including aromatics, dyes, pesticides,

    surfactans, explosives, and many other substances. Fenton reagent can also be effectively

    used to for destruction of toxic waste and non-biodegradable compounds to render them

    more suitable for a secondary biological treatment.

    An application of Fenton oxidation in wastewater treatment plant was shown by its

    effectiveness to treat a highly contaminated wastewater from a pharmaceutical plant. The

    wastewater has COD level of 300,000 ppm, BOD level of 2900 ppm, and total suspended

    solid (TSS) of 45,950 ppm. The Fenton oxidation process could reduce approximately

    90% COD level in the wastewater.

  • 17

    5. Membrane Bioreactor (MBR)

    The MBR process is a suspended growth activated sludge that utilizes microporous

    membrane for solid-liquid separation. In this system, contaminants in the wastewater are

    degraded by biological activity within the bioreactor. Treated wastewater and solids that

    include biomass are then separated by ultrafiltration or nanofiltration membrane.

    The typical arrangement of MBR system includes an aerated portion of the bioreactor,

    anoxic zone, and the membrane filter. Based on the membrane location, there are two

    configurations of MBR system: external and internal/submerged MBR sytem. Comparison

    between the two MBR systems configurations is provided in Figure 4.4.

    Figure 4.4 Comparison between external and internal membrane configuration

    (Source: MBR for Municipal Wastewater Treatment)

  • 18

    Based on the fact that our wastewater has quite high flow rate, external membrane

    configuration seems to be preferred due to its ability to handle higher flux. The external

    MBR system has been widely applied either in industrial or municipal wastewater

    treatment. One of the applied external MBR configuration is at municipal wastewater

    treatment of Commune De Monteux, where its MBR can handle maximum flow rate of

    400m3/h and has COD removal up to 96%. This MBR system is provided by Siemens

    Water. The process scheme of external MBR system is shown in Figure 4.5.

    Figure 4.5 Process scheme of external membrane system in Commune De Monteux WWT

    (Source: Siemens Water Technology, 2010).

    MBR system operates at ambient pressure and temperature and has transmembrane

    pressure (TMP) up to 150 kPa. Standard flux rate for external MBR system ranges

    between 50 to 200 L/m3/hr. Typical sludge retention time within the bioreactor is 5 30

    days.

    6. Thermophilic Membrane Bioreactor

    The principle of thermophilic MBR is actually similar to MBR; a bioreactor equipped with

    membrane filter which facilitates separation of solids and liquid effluent from the

    bioreactor. A major different between them is that the bioreactor in thermophilic MBR

    operates at temperature over 50oC, usually 75

    oC. The elevated temperature can be

    achieved by autoheating due to the heat produced by aerobic metabolism of the

    microorganisms that consume abundant organic material present in the wastewater.

    However, a minimal quantity of organic material is needed to sustain self-heating. Juteau

    (2006) stated that a theoretical minimum of 24 g/l COD, oxygen consumption of 1.42

    kg/kg organic matter oxidized, and BOD/COD ratio of 0.5 can produce heat of 20,000

    kJ/kg volatile solid destroyed (assumed specific heat: 4.2 kJ/kgoC).

  • 19

    Thermophilic bioreactor performs well at higher organic loading rates and operates at

    higher biodegradation rates compared to mesophilic (ambient temperature and pressure)

    bioreactor. This is due to the enhancement of contaminants solubility, such as organics,

    oil, and grease at higher temperatures. The effectiveness of thermophilic MBR in

    degrading contaminants results a smaller size of bioreactor which also means smaller

    footprint. On the contrary to these advantages, thermophilic conditions cause poor

    settleability of sludge due to deterioration of sludge settling properties (Abeynayaka &

    Visvanathan, 2010).

    Another characteristic revealed in the investigation of aerobic thermophilic bioreactor is

    the absence of nitrification (NH4+ NO3-) over 40oC. As a result, various hypothesis

    arise, such as there is only ammonification occurs at thermophilic bioreactor, there is direct

    aerobic deammonification, or there is actually nitrification of ammonia but quickly

    denitrified. What is clear is the fact that an important part of the nitrogen is in the form of

    ammonia. Due to the high temperature, ammonia can be completely volatilized and cause a

    very bad smells (Abeynayaka & Visvanathan, 2010). This problem can be avoided by

    recuperating ammonia vapors with scrubber or lower the ammonia volatilization by using

    highly efficient aerator with oxygen transfer rate (OTE) of >90%.

    The application of thermophilic MBR in wastewater treatment plant has recently been

    spread widely. This technology has been applied in specialty chemical plant, food industry,

    pharmaceuticals, and many others. An applied thermophilic MBR system in a specialty

    chemical plant could handle wastewater with COD loading up to 180,000 ppm and has an

    average COD removal of 90%.

    7. Oxidation Ditch

    Oxidation ditch is a modified activated sludge biological treatment that utilizes long solid

    retention time to remove biodegradable organics. Typical oxidation ditch consists of a

    single or multichannel configuration within ring, oval, or horseshoe-shaped basin. The

    wastewater within the basin is circulated by the work of surface aerators. The circulating

    wastewater helps to mix the oxygen with the wastewater which could foster microbial

    growth and ensures contact of microorganisms with the incoming wastewater. A scheme of

    oxidation ditch system is shown in Figure 4.6.

    Oxidation ditch system operates at ambient temperature and pressure. The wastewater that

    enters the ditch is aerated and circulated at about 0.25 0.35 m/s to maintain the solids in

    suspension. The RAS recycle ratio is from 75 150% and the OTE ranges from 2.5 3.5

    lb/Hp-hour. Required BOD loading that enters the system rates vary, from less than 160

    ppm to more than 40,000 ppm (US Environmental Protection Agency, 2000).

  • 20

    Figure 4.6 Oxidation ditch system

    (Source: US Environmental Protection Agency, 2000)

    The main advantage of oxidation ditch is the ability to achieve removal performance with

    low operational requirements as well as operating and maintenance costs. There is also

    added measure of reliability and performance over other biological processes owing to a

    constant water level and continuous discharge which lowers the overflow rate. Oxidation

    ditch system also has long hydraulic retention time and complete mixing, which minimize

    the impact of shock load or hydraulic surge. In addition, it produces less sludge than other

    biological treatment processes due to the extended biological activity during the activated

    sludge process. The last, the operation of oxidation ditch is more energy efficient and

    result in reduced energy cost compared to other biological treatment processes.

    Contrary to the advantages, oxidation ditch system has disadvantages such as is high

    suspended solids concentration in the effluent and requirement of larger land area than

    other biological treatment processes. This can prove costly, limiting the feasibility of

    oxidation ditch in urban, suburban, or other areas where land acquisition costs are

    relatively high.

    In summary, information about commercially available single method is given in Table 4.4

    Table 4.4 Summary of single wastewater treatment method

    Method Organic loading Operating condition COD removal Scale

    WAO Up to 150,000 ppm

    COD

    T: 150320oC P: 11 217 atm

    55 75%

    Industry

    Ozone Oxidation >100,000 ppm COD T&P: ambient 60 92%

    Fenton Oxidation Up to 300,000 ppm

    COD

    T: 20 80oC ; P: atm pH: 3.5

    90%

    PACT

    BOD/COD: 0.4 0.6

    T & P: ambient

    98.5 99%

    MBR 89 97%

    Thermophilic MBR Up to 98.5%

    Oxidation ditch T: 40 75oC Up to 97%

  • 21

    Reference plants of each method along with the vendors are listed in Table 4.5.

    Table 4.5 Reference plants and vendors of single methods

    Method Reference plants Vendors

    WAO 1. Atofina Italias methyl methacrylate plant, Rhoo, Italy

    2. BASF ethylene facility, Port Arthur, Texas 3. Tosco refinery 4. Municipal treatment plant of The Passaic

    Valley, New Jersey

    5. Ontario Hydros Bruce Spent Solvent

    Siemens (1 4)

    Kenox (5)

    Ozone Oxidation 1. Wastewater treatment plant city of Kalundborg, Denmark (20% municipal and 80%

    pharmaceuticalsinsulin production plant, 1200 m3/h) (ITT)

    2. Municipal wastewater treatment plant in Regensdorf, Switzerland (900 m3/h) (Xylem)

    3. Hospital Waldbrohi wastewater treatment, Germany (648 m3/h) (Xylem)

    ITT (1)

    Xylem (2 3)

    Fenton Oxidation 1. Specialty chemical maufacturer, Louisiana (40 GPM wastewater with 400 - 600 mg/l phenol

    compound and 4000 - 5000 mg/L COD)

    2. Refinery Plant, Southeast US (15 GPM scrubber blowndown system containing COD,

    phenols, and organic compounds)

    3. Emergency treatment of phenol contaminated wastewater at chemical plant, Alabama

    4. Aircraft Painting Stripping and Maintenace Facility, Midwest US (wastewater containing

    toxic compounds e.g. methylene chloride,

    pentachlorophenol, nitrophenols)

    5. Wood treating facility (wastewater containing phenols, naphtols, and cresols)

    US Peroxide

    MBR 1. Syral, Groupe Tereos, Nestle, France (250 v/h) (Degremont Industry)

    2. Groupe SCA, Laakirchen, Austria (2,500 m3/h) (Degremont Industry)

    3. PetroChina Company Ltd. (1600 m3/h ) (Degremont Industry)

    4. Gebt Lang Papier GmbH Ettringen paper mill (396 m3/h) (Xylem)

    5. SCA Graphic Laakirchen AG, Austria paper mill (826.5 m3/h) (Xylem)

    Degremont industry (1 3)

    Xylem (4 5)

    Thermophilic

    MBR

    1. Sartomer Specialty Chemicals 2. Alpharma Pharmaceuticals 3. Glaxo Pharmaceuticals 4. K&K Foods 5. Specialty Food Chemicals 6. Ferro Specialty Chemicals 7. Groundwater remediation 8. Sartomer Specialty Chemicals 9. Wolverhampton Chemicals

    BioConversion

    Solutions

  • 22

    Table 4.5 Reference plants and vendors of single methods (contd.)

    Method Reference plants Vendors

    PACT

    Siemens

    Oxidation ditch 1. Central water reclamation facility, Florida (capacity of 22.4 MGD)

    2. Municipal wastewater treatment of Santa Rosa Country, Florida (capacity of 3 MGD)

    Westech Engineering

    Xylem

    S & N Airoflo

    4.2.1.2 Combined method

    Although there are many commercial single wastewater treatment methods, it is known

    that none of the said single methods is able to treat the wastewater to meet the discharge

    requirement to Hemmaraj. All of the contaminants are still over the limit of Hemarajs

    wastewater discharge requirement. Moreover, some of the streams are not feasible to be

    combined and treated in a single method because contaminants in a certain stream can

    inhibit the treatment. Therefore, a combination of single method is needed in order to meet

    the discharge requirement.

    The idea of single method combination is to combine the chemical and biological

    treatment. The highly polluted water (HPW) will be treated by both methods: chemical

    treatment first and followed by biological treatment. The chemical treatment is needed to

    reduce BOD/COD ratio of HPW, so that the ratio meets the requirement to enter biological

    treatment. The low polluted water (LPW) is directly sent to biological treatment due to its

    BOD/COD ratio that has met the requirement of biological treatment. Below are detailed

  • 23

    descriptions of wastewater treatment method combination that could possibly treat the

    HPW and LPW.

    1. Wet Air Oxidation Powdered Activated Carbon Wet Air Regeneration

    Combination of wet air oxidation, powdered activated carbon, and wet air regeneration is

    called TAR. In this method, the wet air oxidation system acts as a chemical treatment

    which treats the highly polluted water at the beginning. The effluent leaving the WAO

    system is then enters the PACT to be treated by biological means and activated carbon

    along with the LPW. The mixture of WAOs effluent and LPW that has been treated will

    leave the PACT system and enter the sand filter for final treatment before being discharged

    to Hemaraj.

    In our case, the HPW wastewater with flow rate of 45.7m3/h will first enter the wet air

    oxidation system. Here, the organic contaminant which is represented by COD will be

    oxidized and converted into carbon dioxide, water, and organic acid. In the other hand, the

    organic nitrogen contaminant will be converted into ammoniac, nitrate, or elemental

    nitrogen, carbon dioxide, and organic acid.

    If we consider a 65% removal of organic contaminant by the WAO, (similar to WAO

    performance in POSM Plant of Repsol Tarragona, Spain) the HPWs COD concentration

    will be reduced to 50,827 ppm. Along with the LPW, this WAO effluent is sent to the

    PACT. However, due to the acidic pH of LPW, the LPW stream needs to be neutralized

    first until reach a certain pH. The neutralized LPW which flow rate is 10.38m3/h and COD

    concentration of 19,373 ppm is then combined with the WAOs effluent and routed to the

    PACT system.

    If we consider the PACTs maximum performance of COD and organic nitrogen

    contaminant removal are 83%, the COD concentration in the PACT effluent will be 360

    ppm and TKN concentration will be 36 ppm. This concentration has actually met the

    discharge specification of Hemmaraj. However, to ensure that the amount of suspended

    solid has already met the discharge requirement as well, this PACT effluent is routed to the

    sand filter to reduce the remaining suspended solid. After being treated by the sand filter,

    the wastewater is ready to discharge to Hemmaraj.

    As the fresh activated carbon cost that is used in PACT system has a large contribution in

    the overall cost of the method, this activated carbon needs to be regenerated. Regeneration

    of activated carbon is done by the WAR. The sludge containing activated carbon and

    biomass leaving the PACT system will be separated from the liquid effluent and enter the

    WAR to be burnt by air. After being treated in the WAR, the regenerated activated carbon

    will be sent back to the PACT system. It is also important to note that the amount of

    activated carbon is usually lost approximately 10% of the initial mass in the WAR system.

    Therefore, a 10% addition of fresh activated carbon is needed to the PACT system.

    Summarized information about the TAR system is listed in Table 4.6.

  • 24

    Table 4.6 Summary of TAR system

    Operating condition Pros & Cons Performance Estimated cost

    WAO T/P: 150

    oC 320oC/11

    217 atm Retention time: 15 120 min

    Flow rate: 1 50 m3/h

    PACT T/P: ambient

    Minimum dissolved

    O2 : 2 ppm

    Flow rate: 0.1 378.5 m

    3/h

    WAR T/P: up to 260

    oC/up to

    75 atm

    Flow rate: > 0.5 m3/h

    Sufficient energy due to the liquid

    Oxidation

    Autothermal operation

    No oxides of nitrogen or sulfur in

    the off-gases

    High operating condition

    Needs special material for the

    WAO reactor

    Needs VOCs treatment

    Large footprint

    COD removal:

    WAO: 75 90% PACT: 83% TKN removal: up to

    83%

    Capital cost: $4,831,396/m

    3/h

    Operating cost: $ 2.6/m

    3

    2. Ozone Oxidation Membrane Bioreactor (MBR)

    The combination of ozone oxidation and membrane bioreactor utilizes ozone oxidation as

    the chemical treatment followed by membrane bioreactor as the biological treatment. As it

    has been mentioned before, ozone is a strong oxidizing agent which can destroy a wide

    range of contaminants. The treated wastewater from ozone oxidation is routed to the

    membrane bioreactor to be treated by biological activity.

    In the given case, if we consider the maximum performance of COD removal in ozone

    oxidation system is 90% (Stacy, 2007), the treated effluent will have COD level of 1452.2

    ppm. The treated effluent from ozone oxidation system will be combined with LPW which

    has been neutralized to a certain level of pH. The combined stream is then routed to the

    MBR system which consists of de-nitrification tank, nitrification tank, and ultrafiltration

    membrane.

    The combined effluent from ozone oxidation system and neutralized LPW will enter the

    MBR system. If we take the maximum COD and TKN removal of MBR system is 97%

    and 98% each (Stacy, 2007), the COD level in the treated effluent of MBR system will be

    333.84 ppm and the TKN level will be 5.9 ppm. Such levels of COD and TKN have

    already met the requirement discharge to Hemmaraj. Therefore, the treated effluent leaving

    ozone oxidation-MBR system can be directly discharge to Hemmaraj. A simple flow

    diagram of this system is shown in Figure 4.7. Summarized information about the

    combination of ozone oxidation and MBR system is listed in Table 4.7.

  • 25

    Figure 4.7 Block diagram of TAR system

    Fresh activated carbon 10%

    HPW

    45.7 m3

    /h

    COD: 145,219 ppm

    N: 295 ppm

    HPW

    COD: 50,827 ppm

    Dewatered ash to

    disposal

    Ash

    Regenerated act.

    carbon

    Sludge

    Wet Air Oxidation (WAO) Powdered Activated Carbon

    (PACT) Sand filter

    Wet Air Regeneration

    (WAR)

    Filter press

    Neutralization

    HPW + LPW

    LPW

    10.38 m3

    /h

    COD: 19,373 ppm

    pH < 1

    LPW

    pH: 6 - 9

    Discharge to Hemmaraj

    56 m3

    /h

    COD: 360 ppm

    TKN: 36 ppm

    Org. + O2 CO

    2 + H

    2O + RCOOH

    *

    Org. N + O2 NH

    3/NO

    3/elemental N + CO

    2 + RCOOH

    Air

    O2

  • 26

    Table 4.7 Summary of ozone oxidation MBR system

    Operating condition Pros & Cons Performance Estimated cost

    Ozone oxidation T/P: ambient

    Flow rate: 1 10,000 m

    3/hr

    O3 dosage: 0.7 1.1 g / g COD eliminated

    T in Catalytic Ozone

    destructor : 30 70oC Catalyst in catalytic

    destructor: palladium,

    manganese, nickel

    oxides)

    MBR T/P: ambient

    TMP: up to 150 kPa

    Standard flux rate: 50

    200 L/m2.hr SRT: 5 30 days

    Very powerful oxidizing agent

    Remove wide range of pollutant

    Environmentally friendly

    Ozone minimizes sludge production

    Small footprint (10 40 % to conventional)

    High operating cost Low energy

    efficiency

    Requires corrosion-resistant material

    due to ozones corrosivity

    COD removal:

    Ozone oxidation: 60 99%

    MBR: 89 - 97% TKN removal: up to

    96 - 98%

    Capital cost: $136,017.6/m

    3/h

    Operating cost: $ 7.62/m

    3

    3. Thermophilic Membrane Bioreactor Chemical Treatment

    The combination of thermophilic MBR and chemical treatment has been recently used in

    industrial waste water treatment. The utilization of thermophilic MBR may be relatively

    new and is believed to have better performance than the existing biological treatment. One

    of hundreds vendor that has been widely trusted to provide this combination of technology

    is BioConversion solution, which gives a commercial name of this wastewater treatment

    combination as Advanced Fluidized Composting.

    Chemical treatment that used in this method is usually utilization of oxidizing agent such

    as hydrogen peroxide (H2O2). The oxidizing agent will oxidize and destroy contaminant in

    the wastewater. The amount of oxidizing agent used depends on the amount of

    contaminant in the wastewater itself.

    Contrary to the previous methods, the applied combination of thermophilic MBR-chemical

    treatment has reversed order between the chemical and biological treatment. The

    wastewater will be routed to the MBR first (biological treatment) and then to the chemical

    treatment. The vendor claimed that this treatment order can be used in almost all kinds of

    wastewater stream, even in wastewater with high COD content. They also claimed that this

    treatment order is done to reduce the operating cost, because routing the HPW alone

    directly to the chemical treatment will consume high amount of chemical.

    If we follow the applied order of thermophilic MBR-chemical treatment, we need to

    combine the HPW and LPW together in the beginning and send them to the thermophilic

    bioreactor system. The combination of HPW and LPW will result wastewater flow rate of

    56 m3/h, COD content of 121,926 ppm, and TKN content of 240 ppm. The treated effluent

    leaving the thermophilic bioreactor is sent to the ultrafiltration membrane to separate

  • 27

    liquid effluent and sludge containing biomass and hardly biodegradable compounds. The

    sludge is routed to the chemical treatment tank. Here, the oxidizing agent (usually H2O2)

    will oxidize the remaining contaminants in the wastewater which are hard to degrade

    biologically. The treated effluent from chemical treatment tank will be routed back to the

    MBR system to reduce more levels of contaminant. Take the maximum performance of

    COD and TKN removals are 99.8% and 75% (similar to the commercial scale of this

    technology that treats pharmaceuticals wastewater with COD level of 200,000 ppm). The

    wastewater effluent leaving this method will have COD level of 244 ppm and TKN level

    of 60 ppm and is ready to discharge to Hemmaraj. A simple block diagram of this method

    is shown in Figure 4.6.

    Due to the very high amount of COD level and low ratio of BOD/COD in our HPW, a

    pilot test should be done before deciding whether the treatment order is reversed

    (biological first followed by chemical treatment) or not. If the pilot scale tests result

    shows that routing the wastewater directly to MBR system is inefficient (take a long time

    to reach the mentioned percentage of performance), then separating entrance for HPW and

    LPW is needed. The HPW is firstly sent to the chemical treatment to lower its COD level

    as well as increasing the BOD/COD ratio. The effluent of chemical treatment is then

    combined with the neutralized LPW and treated in the MBR system. The effluents

    contaminant will have accepted levels to be discharged to Hemmaraj.

    Summarized information about the combination of thermophilic MBR and chemical

    treatment system is listed in Table 4.8.

    Table 4.8 Summary of ozone oxidation MBR system

    Operating condition Pros & Cons Performance Estimated cost

    Thermophilic bioreactor

    T: 45oC 75oC

    Retention time: 20 30 min for readily

    biodegradable

    compounds

    Flow rate: up to 158

    m3/h

    Minimum OTE: 10 15%

    Minimum dissolved

    O2 : 1 ppm

    Ultrafiltration membrane

    T/P: ambient

    Flux range: 40 135 l/m

    2 . h

    TMP: up to 210 kPa

    Chemical treatment tank

    T/P: ambient

    Lower even zero waste sludge

    production

    High loading rate capability

    Smaller footprint (10 - 40% smaller

    than conventional

    technology)

    Autothermal operation

    Achieve equivalent result to WAO

    for most waste

    stream with less cost

    Require operation and maintenance

    which is more

    complicated than

    disposal

    COD removal: Up t0

    99.8%

    TKN removal: up to

    75%

    Capital cost: $56,574/m

    3/h

    Operating cost: $ 4.5/m

    3

  • 28

    4. Fenton Oxidation Oxidation Ditch

    Fenton oxidation has been widely used in wastewater treatment plant due to its powerful

    and selective activity in reducing contaminants in the wastewater. Such high performance

    of Fenton oxidation makes the requirement of biological treatment that follows the Fenton

    oxidation is not too high. A simple yet effective biological treatment is enough to be

    placed after Fenton oxidation system. The choice of biological treatment then falls on

    oxidation ditch which is more energy intensive, produces less sludge, and many other

    excellences than other biological treatments.

    In the combination of Fenton oxidation and oxidation ditch, the HPW is first routed to the

    chemical treatment tank where oxidation reaction of contaminant by Fenton regent occurs.

    If we take the maximum COD removal in Fenton oxidation system is 90% (similar to the

    applied Fenton oxidation system in paper mill wastewater with COD level of 300,000

    ppm), the effluent leaving chemical treatment tank will have COD level of 14,522 ppm. It

    is important to note that oxidation reaction by Fentons reagent is only effective at acidic

    pH (approximately at pH 3.5). Therefore, an acidification of HPW stream is needed before

    this stream is treated in the chemical treatment tank.

    The chemical-treated effluent is then routed to the oxidation ditch to be treated by

    biological treatment. Before entering the oxidation ditch system, this stream is combined

    with the neutralized LPW which pH is around 6 9. The effluent leaving oxidation ditch

    will pass through the clarifier to separate the sludge and the liquid effluent. The sludge

    which contains biomass will be routed back to the oxidation ditch while the liquid effluent

    will be sent to the disinfection system to remove the remaining biomass. The disinfection

    system usually uses chlorine to kill the remaining microbes in the wastewater before being

    discharge to environment. If we take the maximum COD and TKN removal in oxidation

    ditch each is 98.5% and 94%, the final COD and TKN level in the effluent will be 501 and

    17.7 ppm. This level of contaminant in the wastewater is accepted to be discharged at

    Hemmaraj.

    A simple block diagram of Fenton oxidation-oxidation ditch is shown in Figure 4.7.

    Summarized information about the combination of Fenton oxidation and oxidation ditch

    system is listed in Table 4.9.

  • 29

    Table 4.9 Summary of Fenton oxidation oxidation ditch system

    Operating condition Pros & Cons Performance Estimated cost

    Fenton oxidation (H2O2/Fe

    2+)

    T/P: 20oC 80oC /

    atmosphere

    pH around 3.5

    Retention time: 5 10 min

    Flow rate: 15.75 1800 m

    3/h

    Amount of H2O2: 35 50% (w/w)

    Catalyst: Fe salt:

    Fe(NO3)3,

    FeSO4.7H2O,

    FeCl2.4H2O

    H2O2 : Fe = 10 : 1

    Oxidation ditch T/P: ambient

    pH: 6 9 Minimum dissolved

    O2 : 2 4 ppm Circulated wastewater

    velocity: 0.25 0.35 m/s

    HRT: 6 30 hours SRT: 15 30 days

    Very selective oxidizing agent

    Does not require special material

    for the reactor

    Autothermal operation

    Can save energy saving up to 40%

    compared to

    conventional

    biological treatment

    Requires high concentration of

    H2O2 which cost is

    higher than air

    Requires larger land area than

    conventional

    biological treatment

    TSS in effluent is relatively higher

    than other biological

    treatment process

    COD removal:

    Fenton: 90% Oxidation ditch: 95

    98.5% TKN removal: up to

    90 94%

    Capital cost: $55,713.4/m

    3/h

    Operating cost: $ 4.4/m

    3

    4.2.2 Technology for salt stream

    As the salt content in the salt stream may disturb the chemical and biological treatment, the

    salt stream needs to be treated by special treatment. Technologies that have been

    commercially used to treat salt-contained wastewater and become consideration in our

    method selection are described as the following.

    1. Thermal Oxidizer

    Thermal oxidizer is a unit where combustion of contaminants, especially organic content

    in the waste occurs. The combusted organic content will be converted to carbon dioxide,

    water, and ash. The phase of waste that can be combusted in thermal oxidizer could be

    either liquid or solid. Thermal oxidizer has been widely used in industrial waste treatment

    especially to treat high solid-content and highly contaminated waste. By thermal oxidizer,

    almost all contaminants in the waste will be burnt and converted to ash and gases.

    There are two types of thermal oxidizer that have been commercially available. The first

    one is the fluidized bed technology which consists of windbox section where combustion

  • 30

    air is introduced, a bed section where the waste is fluidized along the sand, and a freeboard

    section where combustion is completed. In fluidized bed, waste and auxiliary fuel are

    injected co-currently to the unit. The exhaust gases and ash that are produced from the

    combustion will pass through energy recovery facilities before it is treated in air pollution

    control system. The ash is usually removed in a slurry form by wet scrubbing system and

    some of thermal oxidizer units have a dry ash removal system upstream of the scrubbers.

    The residence time in fluidized bed thermal oxidizer is 5 60 seconds.

    The second type of thermal oxidizer is multiple hearth technology. It is a vertical

    refractory-lined cylinder with a series of horizontal refractory brick hearths and rotating

    center shaft. The multiple hearth is separated into three zones; the top hearth or drying

    zone where water is evaporated, the middle hearth or the combustion zone where volatile

    contaminants are oxidized, and the cooling zone where the ash is cooled by incoming

    combustion air. In multiple hearth, the waste and auxiliary fuel are injected counter

    currently to the system. The residence time in multiple hearth system is 40 60 minutes.

    Schematic figures of fluidized bed and multiple hearth thermal oxidizers are shown in

    Figure 4.8.

    Figure 4.8 Schematic figures of multiple hearth (left) and fluidized bed (right)

    Source:

    The operation of thermal oxidizers can be run autothermally. In general, about 70% of heat

    required by waste incineration come from the waste itself (Dangtran, dkk,200x). The

    remaining 30% of the heat are obtained from auxiliary fuel and/or from the combustion air.

  • 31

    The supplementary heat can also be recuperated from the flue gas to preheat the

    combustion air up to 1250oF to achieve autogenous combustion.

    Although fluidized bed and multiple hearth function are similar, the different in their basic

    design leads to some advantages for the fluidized bed system. Some plants even replaced

    multiple hearth with fluidized bed Manchester Water Pollution Control Facility,

    Manchester, NH, Wyoming Valley in Wilkes Barre, PA, and T.Z. Osborne in Greensboro,

    NC and claimed that the replacement results a better performance. Some of the

    excellences of fluidized bed compared to multiple hearth are lower NOx formation, lower

    CO formation, lower THC formation, easier for control and automation, wider rang in feed

    variability, lower fuel usage, lower maintenance cost, lower power requirement, etc.

    Summarized comparison between fluidized bed and multiple hearth is shown in Table 4.10

  • 32

    Figure 4.6 Block diagram of Ozone oxidation-MBR system

    Concentrate containing biomass & untreated compounds

    LPW

    pH: 6 - 9

    HPW

    45.7 m3

    /h

    COD: 145,219 ppm

    N: 295 ppm

    HPW

    COD: 1452,2 ppm

    N: 260 ppm

    Ozone oxidation De-nitrification tank Nitrification tank Ultrafiltration

    membrane O

    3

    Neutralization

    LPW

    10.38 m3

    /h

    COD: 19,373 ppm

    pH < 1

    Organic N NH4

    +

    NO2

    -

    + NO3

    -

    Discharged to

    Hemmaraj

    56 m3

    /h

    COD: 333.84 ppm

    N: 5.9 ppm

    NO3

    -

    NO2

    -

    NO N2O

    N

    2

    O3

    destructor

    Unreacted O3

    O2

    Sludge

    Acidification

    HPW

    45.7 m3/h

    COD: 145,219 ppm

    N: 295 ppm

    HPW

    COD: 14,522 ppm

    Neutralization

    Clarifier Disinfection

    LPW

    10.38 m3/h

    COD: 19,373 ppm

    pH < 1

    Fenton Oxidation ditch

    LPW

    pH: 6 - 9

    Discharge

    56 m3/h

    COD: 501 ppm

    TKN: 17.7 ppm

    H2O

    2/Fe

    2+

    Figure 4.7 Block diagram of Fenton oxidation-oxidation ditch

  • 33

    Table 4.10. Comparison between fluidized bed and multiple hearth

    Parameters Multiple hearth Fluidized bed

    Flow Counter current Intense back mixing

    Heat transfer Poor High

    Waste detention time - 3 hours 1 5 minutes

    Gas detention time at high

    temperature 1 - 2 seconds 6 8 seconds

    Combustion temperature 1500 1800 oF 1400 1500 oF

    Gas exit temperature 800 1000 oF 1500 1600 oF

    Excess air 75 100% 40%

    Thermal oxidation system can handle a large range of feed flowrate and contaminants as

    well as remove nearly all contaminants in the wastewater. Even so, the application of

    thermal oxidizer also raises cons. This is due to the pollutant gas released which make this

    process is considered as not green process. A summary of strengths and weaknesses of

    thermal oxidation system is shown in Table 4.11.

    Table 4.11 Strengths and weaknesses of thermal oxidation system

    Strength Weakness

    Complete stabilization process destroying all volatile solids and pathogens

    Large volume and mass reduction lowers truck traffic as compared with other biosolids handling alternatives

    Low life cycle cost for medium and large facilities Low potential for onsite or offsite odors Requires small land area and can operate continuously in all

    weather conditions

    Lower auxiliary fuel requirements than other biosolids handling alternatives

    Strictest monitoring and reporting requirement ensure public of proper operation

    Produces recoverable energy that can be used to produce heated air, gas, water, and oil that can be used for heating and

    electricity

    Pre-stabilization process not required

    High initial capital cost Poor public image and acceptance due to

    misinformation and perceptions

    May not be appropriate for non-continuous operation

    Permitting is more complex than for other biosolids alternatives

    Not perceived as green process Ash reuse programs have not been well

    developed

    Emits pollutant gases such as CO, NOx, SOx, and THC (total hydrocarbon, usually exhibits as CH4)

    In the end, technical and economic information of thermal oxidizer system is provided in

    Table 4.12.

  • 34

    Table 4.12 Summary of technical and economic information about thermal oxidation system

    Allowable inlet flow rate

    Main equipment

    Fluidized bed:

    Windbox section where combustion air is introduced Refractory arch where hot air distributed homogenously through the bed Combustion zone where biosolids and fuel is introduced Freeboard which acts a s afterburner to complete combustion of volatile

    hydrocarbon

    Multiple hearth:

    Upper hearth where biosolids water and organic compounds evaporated Middle hearth/combustion zone Lower hearth/cooling zone

    Operating condition

    Fluidized bed:

    Bed area/combustion zone: 1350 1500oF Freeboard: 50 1000F higher than combustion zone Biosolids detention time: - 3 hours Multiple hearth:

    Upper hearth: 800 1000oF Middle hearth: 1500 1700oF Lower hearth: 350 400oF Biosolids detention time: 1 5 min

    Additional equipment

    Heat exchangers Air pollution control system which includes venturi/nozzle scrubber, cooling

    tray, and electrostatic precipitator

    Operating mode Continuous (24 hours, 4 5 days per week)

    Operation & Maintenance

    70% of the heat required by biosolids come from the biosolids: 25% of the flue gas can preheat the combustion ait up to 1250

    oF to achieve autogenous

    combustion

    The remaining 30% of the heat are from auxiliary fuel Autogenous combustion condition: combustion air temperature: 1200oF and

    solid content 25 28%

    Cost

    Capital cost $175,000 - $250,000

    Operating

    cost (per dry

    ton organics)

    $155 - $260 (fluidized bed) $172 - $313 (multiple hearth)

    Applied scale Industry

    Available vendors

    Degremont Technology Hitachi Zosen Industrial Furnace Company Cockerill Maintenance & Ingenierie

    Reference Plants

    Municipal wastewater treatment of Waldwick, New Jersey Pharmaceutical waste Chemical and paper mill waste Petrochemical waste

  • 35

    2. Electrodialysis Reversal

    Electrodialysis is a membrane process for recycling water from electrolyte, including salt

    solution. The electrodialysis system consists of cation and anion exchange membrane,

    dilution and concentration chamber, and also cathode and anode.

    The principle of electrodialysis system is that the dissolved salts which have positive and

    negative charge will migrate through ion-selective semipermeable membranes. This

    phenomenon happens as a result of their attraction to two electrically charged electrodes.

    The anions will pass through the anion-selective membrane but are not able to pass by the

    cation selective membrane, which blocks the anion in the brine stream. Similarly, cations

    move in the opposite direction through cation selective membrane under the negative

    charge and are trapped by anion-selective membrane.

    EDR system is a variation of ED process. EDR uses electrode polarity reversal to

    automatically clean the membrane surface. EDR works the same way as ED, except the

    polarity of the power is reversed two to four times per hour. When the polarity is reversed,

    the source water will dilute and concentrate compartments are also reversed and so are the

    chemical reactions at the electrodes. This polarity reversal will prevent the formation of

    scale on the membrane. A schematic diagram of EDR system and a summary of its

    technical and economic information are shown in Figure 4.9 and Table 4.13.

    Figure 4.9. Schematic diagram of electrodialysis reversal system

    (Source: U.S. Department of the Interion Bureau Reclamation, 2010)

  • 36

    Table 4.13 Summary of technical and economic information of EDR system

    Allowable inlet flow rate 10 25 gallons/day/ft2 membrane area

    Main equipment

    Cation-exchange membrane Anion-exchange membrane Dilution and concentration chamber Cathode and anode

    Operating condition

    pH: 2 11 Pressure: atmosphere Ratio of permeate and feed water flow rate: 85 95%

    Additional equipment

    Raw water pumps Debris screen Slow mix flocculator Clarifier Gravity filters Chlorine disinfection Clearwell storage

    Operating mode Continuous

    Operation & Maintenance

    Reversal frequency: 15 30 minutes Cleaning using 5% hydrochloric acid solution Average membrane life: 12 15 years

    Energy consumption 2.4 kWh/m3 with elect