Feasibility Study for Regional Industrial Wastewater Treatment and Reuse Facility, Mont Belvieu, Texas

Public Meeting #3Date: Wednesday, November 9, 2016

Trinity BayTabbsBay

Page 2: Feasibility Study for Regional Industrial Wastewater Treatment and

2

Agenda• Introductions

• Feasibility Study Report Summary

• Cost Estimate

• Path Forward

Page 3: Feasibility Study for Regional Industrial Wastewater Treatment and

3

Feasibility Study Report Sections

Cedar Bayou

Page 4: Feasibility Study for Regional Industrial Wastewater Treatment and

FS Report Outline

• Executive Summary

• Section 1: Introduction

• Section 2: Regional Conditions

• Section 3: Wastewater Treatment Facilities and Requirements

• Section 4: Basis of Design

• References

• Appendices

Report Posted at: http://www.gcwda.com/news-events/grant-reports/

4

Page 5: Feasibility Study for Regional Industrial Wastewater Treatment and

Project Team (Section 1)

5

PARTICIPATING MEMBERS

Future ParticipantsFuture Participants

Page 6: Feasibility Study for Regional Industrial Wastewater Treatment and

Project Study Area (Section 1)

6

Page 7: Feasibility Study for Regional Industrial Wastewater Treatment and

Regional Conditions (Section 2)

7

Page 8: Feasibility Study for Regional Industrial Wastewater Treatment and

Regional Conditions (Section 2)

8

Page 9: Feasibility Study for Regional Industrial Wastewater Treatment and

Regional Conditions (Section 2)

• Regionalization Drivers

9

Population Trends

Industrial and Domestic

Wastewater Treatment Capacity

Industrial, Commercial, Residential

Growth

Region H Water

Demands

Page 10: Feasibility Study for Regional Industrial Wastewater Treatment and

Infrastructure Needs & Requirements (Section 3)

• Key Drivers among Participating Members

10

Predictable Water Supply

Sources

City of Mont Belvieu WW

Flow Increases

Industrial WW Flow

Increases

Alternative Water Source for Industry

Industries can focus on Core

Business

Page 11: Feasibility Study for Regional Industrial Wastewater Treatment and

Possible Site Selection Evaluation Criteria (Section 2)

11

Hypothetical IWWTR Plant Site A B C D E

Environmental Factors

Topography

Avoidance of salt dome

Avoidance of the 100-year flood plain

Proximity of tidal receiving waters to locate treated wastewater outfall

Anthropogenic Factors

Parcel size

High priority to sites west of S.H. 146

Avoidance of existing subsurface and surface utilities

Collection and distribution line alignment that minimizes impact to residential land owners

Proximity to each parcel of participating members

Roadway access

Availability of easements

Land parcels within city limits or ETJ of Mont Belvieu

Page 12: Feasibility Study for Regional Industrial Wastewater Treatment and

Regional Industrial Wastewater Treatment and Reuse Facility (Section 3)

12

City of Mt. BelvieuDomestic Sewage

Industrial User 1

Industrial User 2

Industrial User 3

Industrial User 4

Future Other

LAND

ACQUISITION

Reuse/PolishingFacilityRegional POTW

B E N E F I C I A L W A T E R R E U S E D I S T R I B U T I O N L I N E

WA

ST

EW

AT

ER

CO

LL

EC

TIO

N

Storage/StormwaterRetention Facility

Disposal & Discharge

Page 13: Feasibility Study for Regional Industrial Wastewater Treatment and

13

Basis of Design

Cedar Bayou

Page 14: Feasibility Study for Regional Industrial Wastewater Treatment and

Basis of Design for WW Treatment Volume & Water Reuse Demand (Section 4)

• Basis of design 5 MGD of non-potable reuse water

• Future expansion is a function of wastewater influent flow rates and customer demand

14

Dischargers Providing

Wastewater Influent

Reuse Water

Purchasers

Wastewater Quantities Discharged toProposed IWWTR Facility (MGD) Requested Reuse

Water Quantity (MGD)

2016 Estimated Influent Flow

Future Flow Estimate(including Storm Water)

Dry Weather

Flow

Max. Avg. Daily Flow 2025 2050

UBO2075 2025 2050

UBO2075

5 4 5.6 17.9 19.2 23.7 29.0 11.6 13.8 18.0

Page 15: Feasibility Study for Regional Industrial Wastewater Treatment and

Ambient Water Quality from CWA (Section 4)

• Preliminary targets for desired quality of reuse water

• TDS and hardness drive RO treatment process and O&M

15

Parameter Average Concentration

Chloride 20Sulfate 10TDS 110Total Hardness 54

Page 16: Feasibility Study for Regional Industrial Wastewater Treatment and

Schematic Site Layout - ~ 40 acres (Section 4)

16

Page 17: Feasibility Study for Regional Industrial Wastewater Treatment and

Basis of Design: Conveyance, Distribution and Effluent Discharge Lines (Section 4)

17

• Force Main Participating

members - pump to force main

Wastewater conveyance system – ~5.2 miles

• Reuse water -pumped to participating members

• Wastewater effluent outfall pipeline –~4.2 miles

SH 146

Recommended WW Outfall

Page 18: Feasibility Study for Regional Industrial Wastewater Treatment and

18

ROM Cost Estimate

Cedar Bayou

Page 19: Feasibility Study for Regional Industrial Wastewater Treatment and

• Wastewater Treatment Cost (-30% to +50%) Wastewater conveyance system Not included – OSSF and City of Mont Belvieu

sewer system Outfall line to the Cedar Bayou tidal zone Site improvements Wastewater treatment units Land purchase Engineering, Construction and project

management Contingency

• Total Estimated Cost ~ Approx. $60,600,000

19

Class 4 Cost Estimate for Regional IWWTR System (Section 4)

Page 20: Feasibility Study for Regional Industrial Wastewater Treatment and

• Water Reuse Treatment and Distribution Cost (-30% to +50%) Reuse water distribution line Reuse water treatment units Site improvements Land purchase Engineering, Construction and project

management Contingency

• Total Estimated Cost ~ Approx. $21,300,000

20

Class 4 Cost Estimate for Regional IWWTR System (Section 4)

Page 21: Feasibility Study for Regional Industrial Wastewater Treatment and

Class 4 Cost Estimate for Regional IWWTR System (Section 4)

21

Item Description Estimated Cost

Wastewater Treatment Cost $60,600,000Reuse Water System $21,300,000Total Estimated Cost $81,900,000Annual Operation and Maintenance Cost $5,000,000

Page 22: Feasibility Study for Regional Industrial Wastewater Treatment and

22

Path Forward

Cedar Bayou

Page 23: Feasibility Study for Regional Industrial Wastewater Treatment and

Preliminary Project Implementation Schedule

23

A B C D E F G H I J K L A B C D E F G H I J K L

Planning and Conceptual Design 150

Property and ROW Acquisition 180

Front End Engineering and Design (FEED) 240

Permits 360

Secure Funding 150

Detailed Design 300

Bidding and Procurement 270

Construction and Commissioning 360

Acitivity NameYear 1Duration

(days)Year 2

Page 24: Feasibility Study for Regional Industrial Wastewater Treatment and

Preliminary Project Implementation Schedule

24

A B C D E F G H I J K L A B C D E F G H I J K L

Planning and Conceptual Design 150

Property and ROW Acquisition 180

Front End Engineering and Design (FEED) 240

Permits 360

Secure Funding 150

Detailed Design 300

Bidding and Procurement 270

Construction and Commissioning 360

Year 4Acitivity Name Duration

(days)Year 3

Page 25: Feasibility Study for Regional Industrial Wastewater Treatment and

25

Lori [email protected]

Keith Ganze, PE 713-871-7163 [email protected]

Mel Vargas [email protected]

www.gcwda.comwww.parsons.com