60
Environmental Monitoring Report This report has been submitted to ADB by the Project Management Unit (OIIAWMIP), Bhubaneswar and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 38411-043 October 2016 Period: January 2016 June 2016 IND: Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)- Project 2 Subproject: Machhagaon Submitted by: Project Management Unit (OIIAWMIP), Bhubaneswar

Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Environmental Monitoring Report

This report has been submitted to ADB by the Project Management Unit (OIIAWMIP), Bhubaneswar and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 38411-043 October 2016 Period: January 2016 – June 2016

IND: Orissa Integrated Irrigated Agriculture and Water Management Investment Program (OIIAWMIP)- Project 2 Subproject: Machhagaon

Submitted by:

Project Management Unit (OIIAWMIP), Bhubaneswar

Page 2: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY
Page 3: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  Consulting Services for “Institutional Strengthening and Project Management” 

Environmental Monitoring Report    December   1 

 

Department of Water Resources (DoWR)

Project Management Unit (PMU)

Orissa Integrated Irrigated Agriculture and

Water Management Investment Programme (OIIAWMIP) – Project - 2

(ADB Loan No. 3265-IND)

SEMI- ANNUAL ENVIRONMENTAL MONITORING REPORT

(Environmental Mitigation Measures Compliance Status & Monitoring of Select Parameters of Civil Works Packages in Project -2 under)

Machhagaon Subproject

(January 2016 to June 2016)

August 2016

assisted by

Institutional Strengthening and Project Management Consultants (ISPMC)

  

Hydrosult, Division of SNC- Lavalin Inc

Page 4: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon Sub Project  August   2 

 

CONTENTS

 

No  CONTENT  Pg.No 

  List of Abbreviations   

  EXECUTIVE SUMMARY  i to iv 

1.0  INTRODUCTION   1   .    Project Background   1   .    Objective  1   .    Project Profile  1 

2.0  IMPLEMENTATION STATUS AND EVALUATION  6 

3.0  ENVIRONMENTAL MONITORING PROCEDURE REVIEW  6 

4.0  ENVIRONMENTAL COMPLIANCES   6   . .  Compliance Status with National / State / Local statutory    Authorities  6 

  . .  Compliances Status on EMP Implementation – Machhagaon Subproject   9 

   . .   Machhagaon Subproject  9    . . .   Environmental Monitoring   10    . . .   Plantation  14    . . .   Consultation / Focus Group Discussions   14    . . .   Grievance Mechanism  15 

5.0  INSTITUTIONAL ARRANGEMENTS   15 

6.0  COMPLIANCES STATUS OF PREVIOUS EMR–  MACHHAGAON SUBPROJECT 

18 

7.0  COMPLIANCES WITH LOAN COVENANTS   18 

8.0  CONCLUSIONS   20 

  List of Tables   

  List of Annexure   

  Photographs   

 

 

 

Page 5: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon Sub Project  August   3 

 

List of Tables

 

Table 1  Showing Sub Project Status as on 30 June  2016 

Table 2  Details of Tree cutting for Machhagaon subproject 

Table 3  Quarry material details for Machhagaon subproject  – contract package wise 

Table 4  Details of Borrow Earth Approvals for Machhagaon Subproject  ‐ Contract package wise 

Table 5  Details of Labour Licences  for Machhagaon subproject – contract package wise 

Table 6  Details of Insurances  for Machhagaon Subproject – contract package wise 

Table 7  Compliance Status with EMP for Machhagaon Subproject ‐ Contract Package wise 

Table 8  Details of Environmental Monitoring 

Table 9  Average Noise Level in (dB) in different subprojects 

Table 10  Showing the status of plantation in Machhagaon subproject 

Table 11  Compliance Status from the Previous EMR Contract wise – Machhagaon Subproject  

Table 12  Compliances on Loan Covenants 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 6: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon Sub Project  August   4 

 

List of Annexes 

Environmental Mitigation Measures Compliances Status & Monitoring of Select Parameters at Subproject Level and By Civil Work Package wise) 

Annex. No  Details 

Machhagaon Subproject 

Annex 1   Letter to DEIAA for exemption of Environmental Clearance for borrow earth – Cuttack District 

Annex 1 a  Letter to DEIAA for exemption of Environmental Clearance for borrow earth – Jagatsinghpur District 

Annex 2  Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW‐NCB – MAC‐01 

Annex 3  Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW‐NCB –MAC‐02  

Annex 4  Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW‐NCB –MAC‐03 

Annex 5  Compliance Status of Environmental Mitigation Measures adopted by Civil Works Contractors for CW‐NCB –MAC‐05 

Annex 6  Surface Water Quality Monitoring Results ‐ 2016 

Annex 7  Silt Quality Monitoring Results ‐ 2016 

Annex 8  Noise  Quality Monitoring Results – 2016‐ MAC ‐01  

Annex 8a  Noise  Quality Monitoring Results – 2016‐ MAC ‐02  

Annex 8b  Noise  Quality Monitoring Results – 2016‐ MAC ‐03  

Annex 8c  Noise  Quality Monitoring Results – 2016‐ MAC ‐05  

Annex 9   FGD / Consultation‐ List of Participants at Hajipur Village 

Annex 9a  FGD / Consultation‐ List of Participants at Pandia Village 

 

 

 

 

 

 

Page 7: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon Sub Project  August   5 

 

List of Abbreviations 

$ US. Dollar % Percentage ADB Asian Development Bank A.E Assistant Engineer BOQ’s Bill of Quantities C Centigrade CAD Command Area Development CFE Consent for Establishment CFO Consent for Operation CO Community Organisers CTA Component Technical Assistance CW Civil Works DDR Due Diligence Report DEIAA District Environment Impact Assessment Authority D.S.L Dead Storage Level DG Diesel Generator DoWR Department of Water Resources Dy.SIO Deputy Sub project Implementation Officer EARF Environmental Assessment and Review Framework E.E Executive Engineer EMP Environmental Management Plan EMR Environmental Monitoring Report ERM Extension, Renovation and Modernization FB Foot Bridge ha / Ha Hectares HMP Hot Mix plant HR Head Regulator HSD High Speed Diesel IA Implementing Agency IEE Initial Environmental Examination IS Indian Standard ISPM Institutional Strengthening and Project Management ISPMC Institutional Strengthening and Project Management Consultants IWRM Integrated Water Resources Management J.E Junior Engineer KM/ km/ Km Kilo meters Km

2 Square Kilometers

l Litres LHR Left Head Regulator m Meters M

3 Cubic Metre

MFF Multi-tranche Financing Facility Mg Milli grams MCM Million cubic meters mm Millimetres NCB National Competitive Bidding NGO Non Governmental Organisation NR Not Required NTU Nephelometric Turbidity Unit NWP National Water Policy OIIAWMIP Orissa Integrated Irrigated Agriculture and Water Management Investment Program PD Project Director PIM Participatory Irrigation Management PMU Project Management Unit PP Pani Panchayat PPME Project Planning and Monitoring Evaluation PPSU Pani Panchayat Support Unit PPTA Project Planning and Technical Assistance RD Reduced Distance ROW Right of Way Sec Seconds SIO’s Sub- Project Implementation Officers SST Support Service Team VRB Village Road Bridge WALMI Water and Land Management Institute WMM Wet Mix Macadam WUAs Water Users Association

 

 

Page 8: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon Sub Project  August   6 

 

PREFACE 

 

This Environmental Monitoring Report  (EMR)  for  the Machhagaon Subproject presents  the salient features demonstrating the compliance status of environmental mitigation measures, environmental monitoring  of  selected  parameters  for  the  civil  work  contractors.  It  is  in    compliance with  Loan Covenants of Project  ‐2 of  the OIIAWMIP  for  the period  January 2016(Date of commencement) to end of June 2016. The report has been prepared for the PMU with guidance support and assistance of Institutional Strengthening and Project Management Consultants (ISPMC). 

This  report  represents  Compliance  with  Environmental  Safeguard  Policy  of  ADB  which  includes preparation  of  Initial  Environmental  Examinations  (IEE)  reports  ‐prepared  for  Project  ‐2, Environmental Monitoring Plans  (EMP) preparations and  implementation monitoring with periodic monitoring  reports.  The  report  preparation,  field  activities  for  data  acquisition  was  planned  and undertaken with PMU/SIOs supported by ISPMC.  

This document has been prepared using  all  available  subproject  chronological  and  current data  / information, with necessary  compilations  for presentation; and analysis  as deemed practicable  to comply with Loan Agreement Schedule 5, Paras 5, 10,11 and 14  item    for the OIIAWMIP project –which  requires  PMU  to  submit  progress  report  on  the  EMP  implementation  as  part  of  ADB’s Safeguards Policy Statement (2009).  

 

August  2016  

ISPMC 

 

 

 

 

 

 

 

 

 

Page 9: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

Environmental Monitoring Report – Macchagaon subproject   August    i 

 

EXECUTIVE SUMMARY i. “Orissa  Integrated  Irrigated  Agriculture  and  Water  Management  Investment  Program” (OIIAWMIP)  is  a  multitranche  financing  facility  (MFF)  project  with  Asian  Development  Bank (ADB)  assistance.  Department  of  Water  Resources  (DoWR)  had  completed  Project‐1 implementation  and  Project  ‐2  is  under  progress.  Project  2  of  the MFF  implementation  has commenced and will be closed in September 2018.  It will modernize irrigation infrastructure of 4 major( Machhagaon, Pattamundai, HLC Range  ‐1 and MCII) and 3 medium( Ramial, Kanjhari and Kansbahal) subprojects and 750 minor lift irrigation (MLI) schemes in selected river basin of Odisha. It will also strengthen 169 WUAs in improved land and water management for increase agricultural  production,  and  restore  saline  embankments  in  12  segments  covering  about  57 kilometres.   

ii. The  Executing Agency  (EA)  is  the Department  of Water  Resources  and  the  Implementing Agency  (IA)  is  Project  Management  Unit  (PMU).  PMU  /  Subproject  Implementation  Officers (SIOs)    undertake  civil  works  through  Contractors  selected  through  National  Competitive Bidding (NCB). 

iii. The  “Orissa  Integrated  Irrigated Agriculture  and Water Management  Investment  Program (OIIAWMIP) under Project‐ 2  includes    Irrigation sub‐projects   and Saline Embankments which are  classified  as  “Category  B”  according  to  the  Environment  Policy  (2009)  of  the  Asian Development Bank (ADB). An environmental assessment and review framework (EARF) was also prepared  to guide  the environmental assessment of  the subprojects. An  Initial Environmental Examination  (IEE)  reports  were  prepared  for  the  proposed  sub‐projects.  Environmental Management Plan (EMP) is part of the IEE. EMP implementation responsibility mostly lies with the Contractors.   

iv. Under Project  ‐2, 6  sub‐projects out of 7subprojects  commenced  civil works  {three major subprojects (Machhagaon, Pattamundai and HLC Range‐1); three medium (Ramail, Kanjhari and Kansbahal)}  and  10  saline  embankments  out  of  12  have  commenced  civil  works,  the implementation  of  EMP  was  Contractors  responsibility.  EMP  is  part  of  civil  work  contract packages executed by Contractors, but not   with the civil works carried out by Pani Panchayat (for  irrigation subprojects only). The semi – annual Environmental Monitoring Report (EMR)  is prepared for each subproject, the present EMR report pertains to the Machhagaon subproject. 

v. The  Machhagaon  sub  project  was  divided  into  12  contract  packages  and  one  sub‐minor package  implemented  by  Pani  Panchayat.  , Out  of  the  13  contract  packages  (including  sub‐minors) during  this period  4  contract packages  (CW‐ NCB‐ MAC‐01, CW‐ NCB‐ MAC‐02, CW‐ NCB‐  MAC‐03,  and    CW‐  NCB‐  MAC‐05)    have  commenced  civil  works  after  signing  the agreement.   While   Contract package CW‐ NCB‐ MAC‐01 agreement completed on 25 January 2016;  CW‐ NCB‐ MAC‐02 was done on 9 February 2016, CW‐ NCB‐ MAC‐03 contract signed on 9 February 2016 and CW‐ NCB‐ MAC‐05 contract package agreement done on 15 February 2016,  while the rest of 8 contract packages and sub‐minors are yet to be awarded 

vi. The objective of this report is to assess:(i) compliances of the project with the requirements of ADB’s  environmental  safeguards  contained  in ADB’s  Environment  Policy,  (ii)  the  status  of obtaining statutory clearances by the Contractors as per the national environmental laws, Govt. 

Page 10: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    ii 

 

of  India and  (iii)  status of  implementation of mitigating measures  suggested  in  the EMP  and difficulties encountered during the stages of  implementation. The report findings also assist  in formulation of corrective actions by PMU that may  improve EMP  implementation adjustments and in suggesting mechanism for effective supervision during  Project‐2 implementation 

vii.   Monitoring and reporting on EMP  issues was going well there was no change  in the scope of work from the approved contract package.  

viii. The  SIO  staff  and  contractor  representatives  at  site  were  explained  by  ISPMC, Environment  Specialist  on  the  environmental  safeguard  requirements  and  the  required measures    that are needed at  site  along with necessary on  job –  training  /  sub project  level trainings  (on  national  environmental  law  requirements,  environmental  safeguards requirements of ADB, contractual clauses for EMP implementation. PMU with the help of ISPM consultants are also monitoring overall project progress and evaluating project benefits, social and environmental impacts.  

ix. As part of capacity building program few persons (SIO staff and Contractors) were trained in the  EMP  implementation,  environmental  safeguards  and  an  environmental  Check  list  was introduced to the Contractors through PMU for effective monitoring.  

x. The environmental monitoring  report preparation  for  the  implementation period  i.e.  from the date of agreement/ commencement   to end of   June 2016  is   based on the monthly EMP checklist  submitted  by  Contractors  through  SIO  staff,  feedback  obtained  from  SIO  staff especially  Junior engineers  inputs during day  to day  field  activities,  random  field  checking of work  sites  and  verification  and  validation  of  information  submitted  by  the  Contractors  and feedback from villagers through consultations by ISPMC Environment specialist form the  basis for preparation of the report.  

xi. the   Machhagaon sub project doesn’t require any environmental clearances from the State Pollution  Control  Board  or  Ministry  of  Environment  &  Forests  since  this    subproject  is  an   existing one, no new  canals were  formed    and only    strengthening of  existing  systems were taken up. The canals are not  located  in the  forest areas nor  located  in the Coastal Regulation Zone, no clearance were needed. 

xii. The  Contractors  have  not  established  any  plants  under  the  sub  project.  Materials  are purchased from the vendors only.  

xiii.  Overall  the  EMP  implementation  was  satisfactory  in  two  contract  packages  and partially  satisfactory  in  two  contract  packages  due  to  initial  delays  in  documentation  / environmental monitoring and testing.   

xiv. As  per  the  environmental  assessment  and  review  framework  prepared  for  the project,  it states that DoWR wants the surface and ground water quality monitoring to assess the source of  impacts of upstream urbanization and  industrialization and to check the  level of deterioration  due  to  increased  application  of  fertilizers  and  pesticides.  The  suggested monitoring parameters  to  the contractor have a dual objective  to generate  the data base  for water  quality  of  WRD  and  to  assess  the  impacts  of  construction  by  the  Contractors  by 

Page 11: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    iii 

 

monitoring turbidity. Silt analysis was also incorporated to ensure quality of silt before disposal. The generated environmental data will be utilised for Integrated Water Resource Management Planning.  The  SIO  &  Contractors  are  responsible  for  the  environmental  monitoring  and  the analysis would be carried out by the accredited laboratories. 

xv. The environmental monitoring  i.e.  testing of  surface water,  silt and noise was  carried out during  the  implementation  period..  The  surface  water  quality  also  shows    slightly  higher turbidity  levels than the CPCB  limits acceptable  limits, as the river water not used for drinking also,  slight  change  in  turbidity  levels,  which  is  a  temporary  impact.  The  silt  analysis  results shows  the soils are acidic  in nature and soils are not polluted due  to construction. The noise levels are also with the residential limits as there is limited work activity undergoing at present; however  equipment  placed  away  from  habitations  and  the  noise  levels  are  within  the prescribed noise levels of three wheels vehicles.  

xvi.  Consultations Focus groups discussions were carried out in two villages (Hajipur and  Pandia  villages)  to  obtain  feedback  from  the  villagers  for  taking  opinion  on  EMP implementation.  The  Consultation  revealed  during  EMP  implementation,  the  Villagers  are satisfied with the implementation of EMP measures in the subproject but had some suggestions for undertaking works of sub minors at the earliest.  

xvii. In the subproject, SIO has not received any grievances and no grievances were noted during consultations also.  

xviii. A compliance review indicates full compliance with Loan Covenants. Table 13 shows the environmental safeguards assurances and the status of compliances. 

Conclusions  

xix. Overall,  EMP  implementation  is  rated  generally  “Satisfactory”  in  two  contract packages  and  “Partially  satisfactory”  in  two  contract  packages.    Consultations  reveal beneficiaries  (local  communities)  are  generally  happy  with  the  construction  program.  No adverse environmental impacts were observed and no grievances noted. The subprojects after under  taking  renovation  of  the  canals  coupled  with  integrated  agricultural  activities  shall increase economic benefits in the sub project area. 

xx. Awareness  and  Capacity  development  at  PMU/SIOs  commenced  early  in  the  project  and included training on ADB environment policy and its implementation.  Orientation programs on Environmental  safeguards  implementation was  conducted during  January  and  February 2016 which  involves  staff  and  Contractors  of  Machhagaon  subproject  also.  Topics  included  ADB safeguards, environmental laws, contract clauses, and reporting needs 

xxi. Subsequently subproject level orientation program was conducted on 21 June 2015 at  Balia  rest  shed  to  overcome  the  shorting  comings;  around  17  persons  including  the Environment Specialist was present. The key participants were SIO & Contractors staff. 

xxii. EMP  implementation  timelines  have  been  met  in  general.    However,  EMP implementation  by  Contractors  is  rated  satisfactory  in  two  contract  packages  and  partially satisfactory in two contract packages, with only minor initial delays noted by some contractors, 

Page 12: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    iv 

 

mainly  due  to  understanding  of  the  guidelines,  contractual  constraints  and  experience  of contractor’s staff.   

xxiii. Contractor’s  responsiveness  is  increasing  and  aided  in  EMP  successful implementation as a Monthly Environmental Check was introduced to monitor all subprojects.  

xxiv. The  Contractors  had  recently  drilled  some  tubewells,  so  SIO  had  requested contractors  to  undertake  ground  water  quality  test  as  per  IS:  10,500  immediately  and  the results shall be presented in the next environmental monitoring report. 

xxv. The surface water quality also shows slightly higher  turbidity  levels  than  the CPCB limits, the river water not used  for drinking also and hence  impact of surface water observed due to construction is negligible. However SIO will undertake surface water testing form canals after release of water into the canal and also assess the impact of construction. 

xxvi. SIO will   undertake soil monitoring by collecting samples adjacent  to canals as per the  suggested  frequency of    IEE  immediately,  and  the  results  shall be  submitted  in  the next environmental monitoring report 

xxvii. The silt analysis results shows the soils are acidic in nature and soils are not polluted due  to  construction  and desilted material used  for  filling  the  low  lying  areas within Right of Way, hence no impact observed because of construction.  

xxviii. The  noise  levels  for  all  the  contract  packages  are  within  the  residential  limits  of CPCB; however equipment placed away  from habitations and  the noise  levels are within  the prescribed noise levels of three wheels vehicles. 

xxix. Contractors provided safety gear/equipment which was not utilized adequately by labour because of discomfort, as observed and informed during monitoring visits, hence there is scope  for  improvement  on  the  Contractors  side  to  ensure  and  encourage  the  labour  for  a regular use. 

xxx. Integrated Borrow area management   approach by SIO’s  (borrow area  test  for soil classification,  OMC  and  MDD  tests  along  with  agreement  with  the  landowners,  obtaining Environmental  Clearance  from DEIAA/ DEAC) will  ensure  easy  Contractors  compliances,  as  a result  this will improve the borrow area management. 

xxxi. AIDS  awareness  program  conducted  and  the  contractor  shall  ensure  that  they conduct periodically. 

xxxii. The EMR data acquisitions may be archived as  information and baseline  for use  in future  DOWR  environmental  program  management  options  and  as  anticipated  policy enforcement changes evolve over time. 

Page 13: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

Environmental Monitoring Report – Macchagaon subproject   August    1 

 

1.0 INTRODUCTION 

1.1 Project Background  

1. “Orissa  Integrated  Irrigated  Agriculture  and  Water  Management  Investment  Program” (OIIAWMIP) is a multitranche financing facility (MFF) project with Asian Development Bank (ADB) assistance.  It  aims  to  enhance  the  productivity  and  sustainability  of  the  existing  irrigation schemes  in  the  four  northern  river  basins  and  a  part  of  Mahanadi  delta.  This  will  involve renovating irrigation infrastructure, installing participatory irrigation management (PIM) systems with  Pani  Panchayats  (PP)  /  water  users  associations  (WUAs),  and  empowering  WUAs  as  a cohesive  platform  for  irrigation  operation  and  maintenance  (O  &  M)  and  agriculture development. The OIIAWMIP will also strengthen  the  institutional basis  for PIM and  integrated water  resource management  (IWRM) with management  reforms and capacity strengthening of the relevant institutions. 

2. Department  of  Water  Resources  (DoWR)  had  completed  Project‐1  implementation  and Project ‐2 are under progress. Project 2 of the MFF implementation has commenced and will be closed  in September 2018.    It will modernize  irrigation  infrastructure of 4 major( Machhagaon, Pattamundai,  HLC  Range  ‐1  and  MCII)  and  3  medium(  Ramial,  Kanjhari  and  Kansbahal) subprojects and 750 minor  lift  irrigation  (MLI) schemes  in selected  river basin of Odisha.  It will also  strengthen  169 WUAs  in  improved  land  and water management  for  increase  agricultural production, and restore saline embankments in 12 segments covering about 57 kilometers.   

3. The  Executing Agency  (EA)  is  the Department  of Water  Resources  and  the  Implementing Agency  (IA)  is  Project  Management  Unit  (PMU).  PMU  /  SIOs  undertake  civil  works  through Contractors selected through National Competitive Bidding (NCB). 

4.  The  “Orissa  Integrated  Irrigated Agriculture and Water Management  Investment Program (OIIAWMIP) under Project‐ 2 includes  Irrigation sub‐projects  and Saline Embankments which are classified as “Category B” according to the Environment Policy (2009) of the Asian Development Bank  (ADB). An environmental assessment and  review  framework  (EARF) was also prepared  to guide  the  environmental  assessment  of  the  subprojects. An  Initial  Environmental  Examination (IEE)  reports  were  prepared  for  the  proposed  sub‐projects.  Environmental  Management  Plan (EMP) is part of the IEE. EMP implementation responsibility mostly lies with the Contractors.   

1.2 Objective 

5. The objective of this report is to assess: (i) compliances of the project with the requirements of  ADB’s  environmental  safeguards  contained  in  ADB’s  Environment  Policy,  (ii)  the  status  of obtaining statutory clearances by the contractor as per the national environmental laws, Govt. of India  and  (iii)  status  of  implementation  of  mitigating  measures  suggested  in  the  EMP  and difficulties encountered during  the  stages of  implementation. The  report  findings also assist  in formulation of corrective actions by PMU  that may  improve EMP  implementation adjustments and in suggesting mechanism for effective supervision during Project ‐2 implementation.  

1.3 Project Profile 

6. Under  Project  ‐2,  there  are  6    sub‐projects   out of  7  subprojects  commenced  civil works (three major subprojects Machhagaon, Pattamundai and HLC Range‐1);  three medium  (Ramial, 

Page 14: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    2 

 

Kanjhari and Kansbahal) and 10 saline embankments out of 12 have commenced civil works, the implementation  of  EMP  was  Contractors  responsibility.  EMP  is  part  of  civil  work  contract packages executed by Contractors, but not  with the civil works carried out by Pani Panchayat.  

7. In  the present  report, EMP  implementation status of Machhagaon subproject  is presented since  January 2016( Commencement of  award of Contracts)  to  end of  June 2016  The  Table 1  Shows  the  project  components  contract  package  wise,  starting  date  of  implementation, Scheduled date of  completion etc., along with physical progress  for   each  contract package  in Machhagaon sub project under Tranche ‐1. 

8. The  Machhagaon  sub  project  was  divided  into  12  contract  packages  and  one  sub‐minor package  implemented  by  Pani  Panchayat.  ,  Out  of  the  13  contract  packages  (including  sub‐minors) during the period 4 contract packages (CW‐ NCB‐ MAC‐01, CW‐ NCB‐ MAC‐02, CW‐ NCB‐ MAC‐03,  and    CW‐ NCB‐ MAC‐05)    have  commenced  civil works  after  the  agreement.   While  Contract package CW‐ NCB‐ MAC‐01 agreement completed on 25 January 2016;  CW‐ NCB‐ MAC‐02 was done on 9 February 2016, CW‐ NCB‐ MAC‐03 contract signed on 9 February 2016 and CW‐ NCB‐  MAC‐05  contract  package  agreement  done  on  15  February  2016.    While  the  rest  of  8 contract  packages  and  sub‐minors  are  yet  to  be  awarded. 

Page 15: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    3 

 

Table 1 Showing   Machhagaon Sub Project Status as on 30 June  2016 

Contract Package 

Sub –Project Title/ Components/ Contractor 

Date of Agreement 

Contract Commence

ment date 

Date of Completio

Duration as per 

Contract 

Earth work progress in 

Concrete work 

progress in %  

Slope Protectio

n Works progress 

in % 

Financial progress in 

CW‐NCB‐MAC ‐01 

REM  of  Machhagaon  main  canal including  lining  (  0.0  km  to  14.60 km)  and  renovation  and construction  of  associated structures Contractor: Ajit. Ku. Swain 

25‐01‐2016  25‐01‐2016  24‐01‐2016 24 

Months 45.91  20.69  0  29.29 

CW‐NCB‐MAC‐02 

REM  of  Machhagaon  main  canal including lining ( 14.60 km to 29.20 km)  and  renovation  and construction  of  associated structures Contractor: Ajit. Ku. Swain 

09.02.2016  09.02.2016  08.02.2016 24 

Months  49.34  14.054  0  26.60 

CW‐NCB‐MAC ‐03 

REM  of  Machhagaon  main  canal including  lining  (  29.20  km  to 52.425  km)  and  renovation  and construction  of  associated structures Contractor: Ajit. Ku. Swain 

09.02.2016  09.02.2016  08.02.2018 24 

Months  0  6.09  0  8.95 

CW‐NCB‐MAC‐04 

REM of Distributaries No 2, 19, and Bhagalpur  Distributaries  canals  of Machhagaon  Canal  including structures,  selective  lining  and repair to canal embankment roads.  

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

CW‐NCB‐ REM  of  Distributaries  No.  7  and  15‐02‐2016  15‐02‐2016  14‐02‐2016  24  74.54  9.26  0  31.14 

Page 16: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    4 

 

Contract Package 

Sub –Project Title/ Components/ Contractor 

Date of Agreement 

Contract Commence

ment date 

Date of Completio

Duration as per 

Contract 

Earth work progress in 

Concrete work 

progress in %  

Slope Protectio

n Works progress 

in % 

Financial progress in 

MAC ‐05  19A  of  Machhagaon  Canal including  structures,  selective lining  and  repair  to  canal embankment roads.  Contractor: Karunakar Routray 

Months 

CW‐NCB‐MAC‐06 

REM  of    Distributaries  No.  8,  10 and  10H    of  Machhagaon  Canal including  structures,  selective lining  and  repair  to  canal embankment 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

CW‐NCB‐MAC ‐07 

REM  of    Distributaries  No. 16,13,13C,15,15A    of Machhagaon Canal  including  structures, selective  lining and  repair  to  canal embankment roads. 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

CW‐NCB‐MAC‐08 

REM  of  minor  canals  of Machhagaon  canal  system including  structures,  selective lining  and  repair  to  canal embankment roads. 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

CW‐NCB‐MAC ‐09 

REM  of  minor  canals  of Machhagaon  canal  system including  structures,  selective lining  and  repair  to  canal embankment roads. 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

CW‐NCB‐ REM  of  minor  canals  of  Agreement  ‐  ‐  ‐  ‐  ‐  ‐  ‐ 

Page 17: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    5 

 

Contract Package 

Sub –Project Title/ Components/ Contractor 

Date of Agreement 

Contract Commence

ment date 

Date of Completio

Duration as per 

Contract 

Earth work progress in 

Concrete work 

progress in %  

Slope Protectio

n Works progress 

in % 

Financial progress in 

MAC‐10  Machhagaon  canal  system including  structures,  selective lining  and  repair  to  canal embankment roads. 

not done 

CW‐NCB‐MAC ‐11 

REM  of  minor  canals  of Machhagaon  canal  system including  structures,  selective lining  and  repair  to  canal embankment roads. 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

CW‐NCB‐MAC‐12 

REM  of  minor  canals  of Machhagaon  canal  system including  structures,  selective lining  and  repair  to  canal embankment roads. 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

Various (347) 

(construc

tion of Sub‐

minors of Machhag

aon 

Construction  of  Sub‐minor  canals and  associated  structures  of  Machhagaon system. 

Agreement not done 

‐  ‐  ‐  ‐  ‐  ‐  ‐ 

Page 18: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    6 

 

2.0 IMPLEMENTATION STATUS AND EVALUATION 9. In the In Machhagaon Subproject civil works award of contract for 4 contract packages took place during January & February   2016   and while other contract packages are yet to awarded. While  sub  minors  works  implemented  by  Pani  Panchayat  are  also  yet  to  commence. Implementation  of  Environmental  Management  Plans  is  part  of  Contractors  agreement  for Contract packages but not for works implemented by Pani Panchayat.  Monitoring and reporting on  EMP  issues was  going well  there was  no  change  in  the  scope of work  from  the  approved contract package.  

3.0 ENVIRONMENTAL MONITORING PROCEDURE REVIEW 10. To  comply  with  the  Environmental  Management  Plan  (EMP)  recommendations  and Environmental Statutory requirements as per the Initial Environment Examination (IEE) report of the project and loan covenants.  Environment Specialist  was assisting and advising the PMU, had reviewed the situation of the EMP  implementation along with SIO staff of the ongoing contract packages in the subproject and  environmental monitoring reports  are being prepared as part of Environmental  monitoring    for  the  sub–projects  under  Projects  ‐2  which  were  under  implementation (construction stage) after award of contracts.  

11. The SIO staff and contractor  representatives at site were explained   on the environmental safeguard requirements and the required measures  that are needed at site along with necessary on  job  –  training  /  sub  project  level  trainings  (on  national  environmental  law  requirements, environmental  safeguards  requirements  of  ADB,  contractual  clauses  for  EMP  implementation. PMU  with  the  help  of  ISPM  consultants  are  also  monitoring  overall  project  progress  and evaluating  project  benefits,  social  and  environmental  impacts.  As  part  of  capacity  building program  few  persons  (SIO  staff  and  Contractors)  were  trained  in  the  EMP  implementation, environmental  safeguards  and  an  environmental Check  list was  introduced  to  the Contractors through PMU.  

12. The environmental monitoring  report preparation  for  the  implementation period  i.e.  from the date of agreement  to end of  June 2016 is  based on the monthly EMP checklist submitted by Contractors through SIO staff, feedback obtained from SIO staff especially Junior engineers inputs during  day  to  day  field  activities,  random  field  checking  of  work  sites  and  verification  and validation  of  information  submitted  by  the  Contractors  and  PP  consultations  by  ISPMC Environment specialist form the  basis for preparation of the report.  

4.0 ENVIRONMENTAL COMPLIANCES  13. The  environmental  compliances  are  in  accordance  with  the  statutory  requirements  of National,  State  level  authorities,  as  per  ADB  safeguard  requirements  and  EMP  requirements which were made part of Contractors agreements.  The Status of compliances is described below: 

4.1. Compliance Status with National / State / Local statutory Authorities 

14. The  Initial  Environmental  Examination  (IEE) documents have  identified  the  Environmental Regulations and Legislations applicable to the project and the clearances/NOCs to be obtained at various  stages  of  construction.  The  EMPs  detail  out  the  mitigation  measures  for  potential 

Page 19: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    7 

 

negative  impacts.   However,  the   Machhagaon  sub project doesn’t  require  any environmental clearances from the State Pollution Control Board or Ministry of Environment & Forests since all the  subprojects were    existing  one,  no  new  canals  were  formed    and  only    strengthening  of existing systems were taken up. The canals are not located in the forest areas nor located in the Coastal Regulation Zone, no clearance were needed. 

A. Tree Cutting Permission 

15. In the  IEE document  identified there are trees that are present within the existing ROW of embankments out of which some trees might require felling, to the possible extent tree cutting shall be avoided but if any tree needs to be removed shall be done with State Forest Department Permission.  The details of tree cutting are provided in Table 2 below: 

Table 2    Details of Tree cutting for Machhagaon subproject – Contract Package wise 

Contract Package 

Contractor  No. of trees identified as Per 

IEE 

No. of Trees 

identified to be Cut as per site conditions 

No of trees felled or cut 

Details & Status of 

Forest Dept. Permission 

CW‐NCB‐MAC ‐01 

Ajit. Ku. Swain  No. not identified  NR  Nil  NR 

CW‐NCB‐MAC‐02 

Ajit. Ku. Swain  No. not identified  NR  Nil  NR 

CW‐NCB‐MAC‐03 

Ajit. Ku. Swain  No. not identified  60  Nil  SIO writing to DFO for tree cutting permission 

CW‐NCB‐MAC‐05 

Karunakar Routray 

No. not identified  NR  Nil  Nil 

( Note: NR – not required) 

B. Consent From State Pollution Control Boards: 

16. The Contractor doesn’t require any specific environmental clearances from the Odisha State Pollution Control Board since they have not established any crusher/ HMP/ WMM plant etc. The contractors are purchasing the materials (aggregates) from the vendors only details provided  in Table 3; they haven’t taken any quarry on lease nor were undertaking any blasting operations. 

Table 3   Quarry material details for Machhagaon subproject – Contract package wise 

Contract Package 

Contractor  Stone products  Sand  Morrum / other products 

CW‐NCB‐MAC ‐01 

Ajit. Ku. Swain  Purchased form vendor* 

Purchased form 

vendor** 

NR 

CW‐NCB‐MAC‐02 

Ajit. Ku. Swain  Purchased form vendor*  

Purchased form 

vendor** 

NR 

CW‐NCB‐ Ajit. Ku. Swain  Purchased form  Purchased  NR 

Page 20: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    8 

 

Contract Package 

Contractor  Stone products  Sand  Morrum / other products 

MAC‐03  vendor *  form vendor** 

CW‐NCB‐MAC‐05 

Karunakar Routray  Purchased form vendor* 

Purchased form 

vendor** 

NR 

( Note : NR‐ not required; *‐ Vendors details submitted by Contractor; **‐ Vendor details yet to be submitted by Contractor) 

17.  No HSD was stored at the camp; the contractor was purchasing HSD from the vendor only. Vehicle  fitness  and  Pollution  under  Control  certificates  were  requested  for  effective implementation of works and vehicles were sent to nearby garages for repair work if required. 

C. Environmental Clearance for Borrow Earth 

18. The details of borrow earth approvals subproject wise are provided under Table 4 below. 

Table 4    Details of Borrow Earth Approvals for Machhagaon Subproject – Contract package wise 

 

Contract Package  Contractor  No. of Borrow earth Patches 

approved by SIO 

Details & Status of  Environmental Clearance 

from DEIAA 

CW‐NCB‐MAC ‐01  Ajit. Ku. Swain  15 CW‐NCB‐MAC‐02  Ajit. Ku. Swain  20 

CW‐NCB‐MAC‐03 Ajit. Ku. Swain  Earth work 

not commenced 

CW‐NCB‐MAC‐05  Karunakar Routray  5 

E.E has written to Chairman DEIAA  of Cuttack and Jagatsinghpur districts for exemption enclosed as Annexure‐1 & 1a 

D. Status of Labour Licence 

19. The details of Labour licenses subproject wise are provided under Table5 below. 

Table 5    Details of Labour Licences  for Machhagaon subproject – Contract package wise 

 

Contract Package  Sub –Project Title/ Components/ Contractor 

Labour Licence Obtained (Yes / N0) 

CW‐NCB‐MAC ‐01  Ajit. Ku. Swain  YES (Provided) 

CW‐NCB‐MAC‐02  Ajit. Ku. Swain  YES (Provided) CW‐NCB‐MAC‐03  Ajit. Ku. Swain  YES (Provided) CW‐NCB‐MAC‐05  Karunakar Routray  YES (Provided) 

 (Note: Details of Labour license available with SIO) 

Page 21: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    9 

 

E. Details of Insurance 

20. The details of insurances undertaken subproject wise is provided in Table 6 below. 

Table 6    Details of Insurances for Machhagaon Subproject – Contract package wise 

Contract Package  Contractor   All Risk Insurance Obtained (Yes / N0)  

Employee Compensation 

Obtained (Yes / N0)  

Accident Insurance Obtained (Yes / N0)  

CW‐NCB‐MAC ‐01 Ajit. Ku. Swain  YES 

Provided* YES 

Provided* Contractor Requested 

CW‐NCB‐MAC‐02 Ajit. Ku. Swain  YES 

Provided* YES 

Provided* Contractor Requested 

CW‐NCB‐MAC‐03 Ajit. Ku. Swain  YES 

Provided* YES 

Provided* Contractor Requested 

CW‐NCB‐MAC‐05 Karunakar Routray  YES 

Provided* YES 

Provided* YES 

Provided*  

 4.2. Compliances Status on EMP Implementation ­  Machhagaon Subproject  

4.2.1 Machhagaon Subproject  21. The Machhagaon Subproject is covering  12 contract packages and one sub minor package.   Out of the 12 contract packages only 4 contract packages have been awarded during this period. The status of EMP implementation against different environmental components for each contract package is shown in Annexure 2 to 5.  

22. Overall  the  EMP  implementation  is  rated  generally  satisfactory  with  only  minor  delays (testing of surface water, ground water and silt/ soil) noted by some contractors, mainly due to understanding of the guidelines, contractual constraints and experience of the contractors & SIO  staff.   

23. EMP  implementation  quality  in  each  contract  packages  is  rated  on  a  3‐point  scale  (i.e. satisfactory,  partially  satisfactory  and  unsatisfactory).  Ratings  are  assigned  considering  the degree  of  contractors  compliance  with  EMP  condition  as  determined  by  reports,  periodic monitoring by  SIO with  ISPMC  assistance. The definitions  adopted  for  assessment of  the  EMP implementation  quality  ratings  are:  (i)  “Satisfactory”  (S)  ‐  when  overall  compliant  with  EMP; “Partially  Satisfactory”  (PS)  mostly  compliant  with  EMP;  and  “Un‐Satisfactory”  (NS)–  when inadequately compliant with EMP”.  

24. The EMP  implementation rating  is shown  in Table7. EMP  implementation out of 4 contract packages,  it  is generally satisfactory  in     contract packages ( CW‐ NCB‐ MAC  ‐03 and   CW‐ NCB‐ MAC ‐05) and Partially Satisfactory  in  contract packages(CW‐ NCB‐ MAC ‐01 and CW‐ NCB‐ MAC ‐02).  

 

Table 7   Compliance Status with EMP for Machhagaon Subproject‐ Contract package wise 

Page 22: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    10 

 

S.No  Contract Package  EMP status (Yes/ 

No/ NR) 

Rating  (Satisfactory/ Partially 

Satisfactory/ Unsatisfactory) 

Observations / Remarks 

1 CW‐NCB‐MAC ‐01  Yes  Partially Satisfactory   • Mostly EMP complied.  

 2 

CW‐NCB‐MAC‐02  Yes  Partially Satisfactory   • Mostly EMP complied.   

3 CW‐NCB‐MAC ‐03 

Yes  Satisfactory   • Overall EMP complied.   

4 CW‐NCB‐MAC ‐05 

Yes  Satisfactory   • Overall EMP complied.   

4.2.1.1 Environmental Monitoring    25. During the design phase sub‐project wise  IEE’s were prepared  incorporating EMP, to make  EMP  more  effective  WRD  had  incorporated  Environmental    testing  and  monitoring  (Surface water,  ground  water  and  silt  analysis)  as  part  of  environmental  budget.  As  part  of  technical specification  of  Contractors  BOQ  Contractors  shall  adhere  to  the  mitigation  measures  as stipulated  in  the  IEE  document.  As  per  the  environmental  assessment  and  review  framework prepared  for  the  project,  it  states  that  DoWR  wants  the  surface  and  ground  water  quality monitoring to assess the source of impacts of upstream urbanization and industrialization and to check  the  level  of  deterioration  due  to  increased  application  of  fertilizers  and  pesticides.  The suggested monitoring parameters  to  the contractor have a dual objective  to generate  the data base  for water quality of WRD and to assess the  impacts of construction by the Contractors by monitoring turbidity. Silt analysis was also  incorporated to ensure quality of silt before disposal. The generated environmental data will be utilised  for  Integrated Water Resource Management Planning.  The    SIO  &  contractors  are  responsible  for  the  environmental  monitoring  and  the analysis would be carried out by the approved laboratories.  

26. The details of provisions under EMP  as per IEE is detailed in Table 8 which also provides the number of locations against the proposed is also indicated. The analysis of the data is as follows: 

Table 8   Details of Environmental Monitoring  

Environmental Parameter

Suggested No. of

locations as per IEE

Frequency and period of monitoring as Per IEE

No. of Locations Env. Monitoring

Carried out

Remarks

Surface water 6 1 SIO requested to undertake after release

of water in the canal Ground water 6 Nil Contractor was

requested Soil 6 Nil SIO requested to

undertake immediately Silt 6 4 -

Noise Monitoring Nil

Twice in a year before construction

and after construction

4 Contractor requested to continue

 

Page 23: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    11 

 

4.2.1.1.1 Ground Water Quality Monitoring 27. The project  ‐2 do not have a provision of providing  tube wells  in  the   on  the sides of  the canals. However in the subproject contractors had drilled some tube wells under three  contract package  for providing drinking water  to his  labour.   The details of  tube well  locations  for each contract package is as (Contract package MAC‐01 : 2 (Athanga and Astasambhu villages); Contract Package – MAC‐02  : 2  ( Kahaliapur and Satpura villages); and Contract package – MAC‐05  : 1  in Rambhadeipur village. 

28. The Contractors of three contract packaged have drilled tube wells during March / April to meet the water requirements of the labour, hence he was requested by SIO to undertake water quality testing from a accredited  laboratories    immediately,   the results shall be  included  in the next monitoring report.  

4.2.1.1.2 Surface Water Quality Monitoring 29. As per  the  Initial Environment Examination Report prepared  for  the  subproject  there  is  a provision for testing the surface water in 6  locations. The environmental testing budget was not part of contractor’s responsibility; however SIO had carried out testing  from Head Regulator of Machhagaon canal at Jobra.  

30. The  surface water was not available during  the period  (January  to mid    July 2016) as  the canal was closed for civil works. So the SIO could not undertake water testing immediately after agreement however after  capacity building  SIO had  carried out  testing during  June 2016  from Head Regulator which will act as a baseline for the future. However the SIO will undertake testing after release of water in to the canals as per the suggested frequency. 

31. The details of surface water quality analysis results are provided in Annexure 6 and the hard copies of test results are available with SIO for reference.  

32. The pH of the waters range  is 8.52   which  is slightly higher than permissible  limit of 6.5 to 8.5. While the turbidity of the waters is 2.6 NTU acceptable limit of 1 NTU for drinking water  but  within the permissible limit of drinking water standards of 5 NTU, which means there is no impact of construction on the activity.  

33. The  sample  was tested for limited general parameters  like  aluminium, barium, Chlorides, Fluorides,  Iron  and  Nitrates  ,  sulphates  etc  and  total  Hardness  were  tested    all  the  results conform with the CPCB limits.   

34. The  sample  was  tested  for  toxic  substances  like  cyanide,  lead,  mercury,  arsenic  and chromium  all  results  confirm within CPCB  limits  and pesticide  residues were  also  found  to be absent 

35.   The  Dissolved  Oxygen  content  is  5.2  mg  /l  as  compared  to  the  inland  surface  quality standard  IS:  2296‐1982 CLASS C  i.e.  4 mg/l,    BOD  is    2.8   mg  /l    as  compared  to  3 mg/l  and Chemical Oxygen Demand  ranges from 16  mg/l.  The report also show the presence of total Coli forms in the samples.  

Page 24: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    12 

 

36. The water quality monitoring  report  results shows  the water quality  is better  than Class C and Class E waters,  so  there would not be any  impact on water being used  for  irrigation. The water quality is not impacted, hence no impact from construction observed. 

4.2.1.1.3 Soil Quality Monitoring 37. In  the  study  area,  Mahanadi  basin  is  broadly  divided  into  four  main  regions  namely  the northern plateau, the Eastern Ghats, the coastal plain and the erosion plains of central table land. The Machhagaon canal falls in coastal plain. The main soil found in the study area are alluvial and laterite soil. The alluvial soil is generally found in Cuttack district. The texture of this soil is sandy loam, silty loam; clay loam and heavy loam and it is very fertile in nature while the laterite soil is generally hard, infertile and acidic in nature. 

38. There  is a close  linkage between geomorphic elements and soils. Soils on the dune regions are  deep,  sandy  and well  drained.  Those  in  the  intervening  depressions  are water  saturated, clayey and  salt enriched. The soils on  the  levees are silty and well drained. The clay mineral  is dominantly  illitic.  The pH  of  the  soils  is  about  6.5  at  the  surface  and  increases  upto  8.0 with depth. The soils are saline as indicated by electrical conductivity, which increases with depth from 1.72  to  5.0  ds/m.  The  cation  exchange  capacity  of  the  soils  ranges  from  16.8  to  21.6  mill equivalent/100 g soil. Exchangeable Mg and Na dominate the exchange complex and this causes low  permeability.  The  organic  carbon  content  is  medium  in  the  surface  soil  due  to  slower decomposition of organic matter in anaerobic environment. The soils are reported to be medium to low in available P and medium to rich in available K. It follows from the observations recorded above  that  soil varies  from  sandy  loam of  light greyish  to  light yellowish grey  colour  to  clayey loam  of  light  greyish  to  deep  greyish  colour.  The  soils  in  the  valley  flats  remain  under  aquic moisture  regime  due  to  shallow  ground  water  level  and  poor  drainage  condition,  but  the situation is different on the dune region. 

39. However the soil samples adjacent to the canal embankment were to be tested as per the EMP provisions of the IEE however the SIO was not aware hence he was requested to undertake immediately. 

4.2.1.1.4 Silt Quality Monitoring 40. Desiltation of canals are proposed now out of 12 contract packages only 4 packages are  in force. Though  IEE reports suggested for testing of 6 silt samples  in the subproject. However SIO has undertaken  testing of  silt  in 4  locations during  the period  covering one  sample  from each contract package. 

41. The  silt  sample  from  contract package MAC  ‐01 was  collected  from RD 0.060 km of main canal; for MAC‐02 it was collected from RD 25.41 km of main canal; for MAC‐03 it was RD 29.30 km of main canal and for Contract package MAC‐05 it was from  RD 0.010 Km of Disty. No‐7.  All the samples were tested during 23 June 2016. 

42. The details of   silt quality report carried out  in different  locations  is shown  in Annexure   7, and the copies of test results of acrredited laboratory are available with SIO staff. 

Page 25: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    13 

 

43.   During 2016  the results of silt analysis shows, the pH of the samples are varying from 5.88 to 6.57 4   which shows they are neutral and electrical conductivity is varying from 36 to 63 . The organic carbon ranging  from 0.8 to 0.92 %. The potassium content ranging from 0.021 to 0.024 mg/100g   which means  low  to medium content   and phosphorous content varying  from 0.1  to 0.16 mg/ 100g, this also indicates  low medium content of the silt. The silt was tested from heavy metals as well as pesticide residue the silt does have any pesticide residue nor heavy metals at present .Hence no impact observed in the surrounding environment because of silt disposal. 

4.2.1.1.5 Noise Quality Monitoring 44. The ambient air quality standards  in  respect of noise  in the project area  for each contract package under Machhagaon were monitored on a hourly basis for each contract package which are under implementation during 24 April 2016. To ascertain the need for mitigative measures to be  adopted  by  Contractors  during  construction  period  i.e.    Noise  emanating  from  vehicular movements,  blowing  of  horns,  and  operation  of  construction  equipment  like  concrete  mixer, movement of construction equipments and sound producing  instruments   etc., were measured for    a  day  during  day  and  night.  The  noise monitoring  reports  for  each  contract  package  are enclosed as Annexure 8, 8a, 8b, 8b and 8c. The average noise  levels  in the different subprojects under Machhagaon Subproject are mentioned below in the Table 9. 

Table 9  Average Noise Level in (dB) in different subprojects 

No  Contract Package  Average Noise Level in (dB) 

1 CW‐NCB‐MAC ‐01 

 51.9  dBA  during  day  and 44.36 during night 

2 CW‐NCB‐MAC‐02 

50.2  dBA  during  day  and 43.06 during night 

3 CW‐NCB‐MAC‐03 

49.0  dBA  during  day  and 43.1 during night 

4 CW‐NCB‐MAC‐05 

48.4  dBA  during  day  and 43.2 during night 

 

45. In general the existing noise levels are within  the residential category / area limits  and also within  the  three wheelers vehicle noise  limits prescribed by CPCB. However,  the present work locations are away from the residential areas where the noise levels get diluted hence no impact of  noise  anticipated,  in  addition  contractors  were  also  instructed  to  do  maintenance  of  the vehicle  and  equipments  which  will  also  reduce  the  noise  levels  further.    So  Contractor  was instructed  to  adhere  to  the  ambient  air  quality  standards  specified  under  the  rules  and  shall undertake measures for abatement of noise including use of silencer for the vehicle if necessary and sending equipments for maintenance regularly.  

4.2.1.2 Plantation Details 

46. The  IEE  has  identified  that  there  are  some  trees  within  the  existing  right  of  way  of  the embankments, which might get affected due to construction and also to enhance the aesthetics of  the area a provision  for plantation has been  indicated  for  in  the  IEE  report. The BOQ of  the contract packages doesn’t’ have a provision for plantation. However at present no trees were cut 

Page 26: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    14 

 

and  no  plantation  was  carried  out  in  the  subproject  areas,  however  if  required  as  part  of compensatory  plantation  the  DoWR  shall  request  State  Forest  Department  in  undertaking plantation where ever surplus ROW is available after completion of civil works 

Table 10   showing the Status of Plantation in the  Machhagaon subproject 

Contract Package No. of Plants proposed in Contract Packages

Plantation carried out till date

CW‐NCB‐MAC ‐01  Nil Nil

CW‐NCB‐MAC‐02  Nil Nil

CW‐NCB‐MAC‐03  Nil Nil

CW‐NCB‐MAC‐05  Nil Nil

4.2.1.3  Consultation( Focus Group Discussion) with Villagers    47. The public consultations were conducted  in  two villages  (Hajipur and Pandia villages)  that are located in the Machhagaon subproject.  

Hajipur Village

48. The FGD/ consultation was in the Village Hajipur, Birdi Block of Jagatrsinghpur District.   The Consultation  was  carried  out  on  10  August  2016  with  the  help  of  DowR  staff,  the  list  of participants  enclosed  as  Annexure  9.  The  PP/  WUA/villagers  expressed  happiness  over undertaking  civil works  after  a  long  time where  their  canals were damaged  and not  receiving good water supply. The  village falls in PP.No 3 ( at present PPs not active)  it receives water from Main canal and Hajipur minor A & B canals. 

The  feedback  on  environmental issues  related  to  construction was taken. The  feedback obtained was good and no environmental  issues like dust, irregular borrowing etc in their village. Over all there were no environmental  problem  associated with the execution of work and the farmers  are happy with  the works in  the  main  canal  however  they expressed  unhappiness  in  not undertaking  works  in  minor  and subminors as they are dependent on them for good water supply.  They suggested there is a need for undertaking packing and  lining  in many portions of the Hajipur minor   as rodents had made holes  leading  to breach of  the  embankment.    They  even  suggested   during maintenance only   scattered works undertaken by SIO  that are not sufficient. They even suggested release of early water  to  facilitate  the kharif  crop  cultivation. Some have  suggested  the outlet positions  in  the subminor  are  not  proper  which  may  be  rectified.  All  the  issues  were  brought  to  notice  of  Executive Engineer and they will ensure to address while taking up works in minor and subminors 

49.  The overall  feedback got  is  that there are no environmental  issues which are observed as part of the construction activity. Villagers expressed satisfaction for the works completed. 

Page 27: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    15 

 

Pandia Village

50. The FGD/ consultation was in the Village Pandia, Birdi Block of Jagatrsinghpur District.   The Consultation  was  carried  out  on  10  August  2016  with  the  help  of  DowR  staff,  the  list  of participants  enclosed  as  Annexure  9a.  The  PP/  WUA/villagers  expressed  happiness  over undertaking  civil works  after  a  long  time where  their  canals were damaged  and not  receiving good water supply.  

51. The  feedback  on  environmental  issues  related  to  construction  was  taken.  The  feedback obtained  was  good  and  no environmental  issues  like  dust, irregular  borrowing  etc  in  their village.  Over  all  there  were  no environmental  problem  associated with  the  execution  of work.  The  PP have expressed some suggestions for minor  and  sub‐minors:      survey  of the  sub‐minors  shall  be  undertaken to  ensure    proper  embankment height and    to   maintain proper bed levels. Even   PP expressed they have lot of   problem  in  the  subminors which need  to be addressed at  the earliest  to ensure proper supply of water in to their fields.   

52. The  villagers  said  they  are  undertaking  only  Kharif  cultivation  at  present  and  no  rabi  in general. They are cultivating Paddy and the yield  is around 17 to 18 quintal and they are using organic  and  inorganic  fertilisers,  they use around 75 kgs of  fertilisers  for one acre at different stages.  

53.  The overall  feedback got  is  that there are no environmental  issues which are observed as part of the construction activity. Villagers expressed satisfaction for the works completed. 

4.2.1.4 Grievance Mechanism 

54. The  subproject  is  part  of  Project  ‐2  of  investment  program  (OIIAWMIP)  which  has established a Grievance Redress Mechanism (GRM).  In addition, there is an arrangement at the district level which provides a grievance mechanism whereby a grievance cell was located at the Collector’s office.   The subproject, SIO has not received any grievances and no grievances were noted during consultations (details of consultations provided in section 4.2.1.3).   

1.2  INSTITUTIONAL ARRANGEMENTS  55. The following are the key agencies involved in the implementation of the EMP: 

56. DoWR  is the Executing Agency for OIIAWMIP. A Project Management Unit (PMU) has been established within the CAD&PIM Directorate with a Project Director of the rank of Chief Engineer operating under  the overall guidance of Additional Secretary cum Director CAD  ‐ PIM with  the 

Page 28: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    16 

 

overall responsibility of program implementation. Chief Engineer cum Project Director, PMU will exercise the powers vested by the OPWD code for execution of all civil works. 

57. At the field level Sub‐project Implementation Offices (SIO) have been formed to implement the program. For Major irrigation sub‐projects the concerned Superintending Engineer is the Sub‐project manager and the concerned Executive Engineer  is the Sub‐project manager for Medium irrigation Sub‐projects. The Sub‐Project Manager, who is a Superintending Engineer (SE) for major irrigation  systems  and  an  EE  for  medium  schemes,  will  manage  the  Technical  Cell  as  well  as monitor and guide the CAD and PP Support Cells for effective integration and coordination of the sub‐project activities, under the support and guidance of PMU, EIC (P&D), and ISPM Consultants provided through regular PMU‐SIO meetings.  

58. DoWR for effective  implementation of Project‐2 sub‐projects under OIIAWMIP proposes to create  one  Circle,  four  Divisions,  12  Sub‐Divisions  under  the  Chief  Engineer  –  cum  –  Project Director, PMU. 

Circle:   One Superintending Engineer S.E will be  in charge of circle office. He will be responsible for the   managing the Technical Cell as well as monitor and guide the CAD and PP Support Cells for effective integration and coordination of the sub‐project activities.  

Division: Under each division one Executive Engineer  (E.E) will be  in charge of  the division  for, processing  tender  and  bid  documents  executing  the  works,  check  measurement  etc.  He  will ensure the quality of the ongoing works etc.  

Sub‐Division: Under each  sub‐division Assistant Engineer  / Asst. Executive Engineer  shall be  in charge of the sub‐division office. He will be supported by field functionaries like Junior Engineer and  other  field  for  execution,  check  measurement,      monitoring  the  works  and  ensuring  the quality of the work. 

59. The  Junior  Engineer  at  the  field  level  will  be  responsible  for  day  to  day  environmental monitoring and the overall supervision and responsibility of EMP implementation will be with the concerned SIO ( S.E for Major sub project and E.E for medium sub project). 

Institutional Strengthening and Project Management Consultants (ISPMC)  

60. The  ISPMC  will  have  an  Environment  Specialist,  Resettlement  Specialist  and  Indigenous group Specialist who will support  the PMU  in advising and monitoring  the EMP measures with help  of  SIO  Staff  and  WUAs.  The  ISPMC  will  assist  in  reviewing  all  the  contractors’  monthly environmental reports submitted by Contractors through SIO in consultation with PMU.  They will assist the PMU in preparing environmental monitoring reports and other reports like preparation of IEEs, RP and social assessment reports. 

Responsible for carrying out monitoring measures  

61. As per  the  “ Environmental Assessment  and Review  Frame work  (EARF) prepared  for  the project  it  states  that  “PMU  will  be  responsible    to  undertake  (i)  environmental  screening  at subproject identification stage; (ii) preparation of IEEs/EIAs at subproject appraisal stage; and (iii) environmental management and mitigation during  subproject  implementation and operational 

Page 29: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    17 

 

stage. At appraisal,  IEEs /EIAs will be done with the engagement of consulting firms who would be guided by the project environmental specialist.  

62. Environmental  management  and  mitigation  will  be  undertaken  by  the  construction contractors  during  construction  phase  under  the  supervision  of  the  designated  staff  in  the subproject  management  offices  (SIOs)  and  monitored  by  PMU  environmental  cell.    The consultants  mobilized  for  institutional  strengthening  and  project  management  will  also  be entrusted  to provide necessary capacity development of  the DOWR engineers and SIO  (S.E  for major  sub  project  and  E.E  for  medium  subproject)    in  terms  of  environmental  planning  and management”. 

63. . The PMU  / SIO of DoWR assisted by  the WUAs, and  the  Institutional Strengthening and Project Management Consultants  (ISPMC) will be guiding  the  implementation of  the EMP. The SIO (S.E for major sub project and E.E for medium subproject). The field level Junior Engineer shall be responsible for monitoring the EMP activities of the Contractors on a day to day basis. The SIO staff  and  WUAs  with  the  help  of  ISPMC,  Environment  Specialist  will  monitor  the  EMP implementation of the Contractor.  

64. While  the  implementation  of  sub‐minors  shall  be  on WUAs  and monitored  by  SIO.    Pani Panchayat  Support  Unit  (PPSU)  is  the  state  level  apex  agency  who  is  responsible  for strengthening the PP activities.  PPSU ‐ Environmental Monitoring Specialist be made responsible for the monitoring of WUAs along with SIO staff and these will work under the overall guidance of ISPMC. 

65. The  Environmental  Framework  prepared  for  the  Project  ‐2  states  “Environmental management  and  mitigation  will  be  undertaken  by  the  construction  contractors  during construction  phase.  The  PMU  and  SIOs  as  well  as  contractors  were  guided  by  the  ISPMC Environmental Specialist in implementation of the EMPs and associated monitoring and reporting activities.  

66.  Systematic monitoring of the EMP was  facilitated by a check  list developed specifically  for SIO‐ J.Es and contractors. The format was part of the IEE report and subsequently during January & February 2016 orientation program the format was explained.  

67. The SIO staff and contractors representatives at site were explained   on the environmental aspects and the required safeguards measures   that are needed at site along with necessary on job  –  training  /  sub  project  level  trainings  (on  national  environmental  law  requirements, environmental safeguards requirements of ADB, contractual clauses for EMP implementation). 

Capacity Building 

68. During  January  2016  and  February  2016  Capacity  building  on  EMP  implementation  was carried out by PMU with the help of  ISPMC Consultants.   So far 88 persons (Senior DoWR staff, SIO  staff  and  Contractors  also)  were  trained  (which  includes  staff  and  Contractors  from Machhagaon  Subproject  also)  SIO  staff  and  Contractor  representatives  in  the  EMP implementation and as a result Contractor compliances had improved to a greater extent.  

Page 30: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    18 

 

69. The orientation program on Environmental Safeguards for Machhagaon subproject was held on  21st  June  2016  at  Balia  rest  shed,  Jagatsingpur  District  to  bring  awareness  on  EMP implementation  to  SIO  field  staff  and  contractor  representatives.  There  were  17  number  of participants including the speaker. One Junior Engineer for each contract package was identified who  will  act  as  an  Environmental  Co‐ordinator  for  monitoring  the  field  level  EMP implementation. This mechanism had helped in timely EMP compliances but with some delays.  

6.0 COMPLIANCES STATUS OF PREVIOUS EMP REPORT ‐ SUB PROJECT WISE 70.  For the Machhagaon Subproject  i.e. two saline embankment subprojects contract package wise  status  of  compliances  with  reference  to  the  previous  Environmental  Monitoring  Report (EMR)  is  stated  in  Table  11.    As  this  is  the  first  Environmental  Monitoring  Report  for  the subprojects so there are no previous compliances reported pending.    

Table 11 Compliance Status from the Previous EMR Contract wise – Machhagaon Subproject  

S.No  Contract Package  Issue from the Previous Environmental Monitoring Report 

Actions  Taken by SIO staff 

1  CW‐NCB‐MAC ‐01  • Nil  • Nil 

2  CW‐NCB‐MAC‐02  • Nil  • Nil 

3  CW‐NCB‐MAC‐03  • Nil  • Nil 

4  CW‐NCB‐MAC‐05  • Nil  • Nil 

7.0 COMPLIANCES WITH LOAN COVENANTS  71. OIIAWMIP  Project  ‐2  loan  agreement    Schedules  5  stipulates  certain  condition  for safeguarding “Environment” which  includes safeguards related provisions  in bidding documents and  works  contracts  and  Safeguards  monitoring  and  reporting  requirements.  A  compliance review  indicates  full  compliance  with  Loan  Covenants.  Table  12  shows  the  environmental safeguards assurances and the status of compliances. 

Table 12 Compliances on Loan Covenants 

S.No  Loan Covenants  Status   Environment   5  The Borrower shall ensure or cause the State to ensure 

that  the  preparation  ,  design,  construction, implementation,  operation,  and  decommissioning  of the  project,  each  subproject  and  all  Project  facilities comply with  

 

a)  all applicable laws and regulations of the Borrower and the State relating to environment, health and safety 

Complied 

b)  the Environmental Safeguards  Complied c)  the EARF  Compiled d)  all  measures  and  requirements  set  forth  in  the 

respective  IEE  and  EMP    and  any  corrective  or preventive actions set forth  in a Safeguards Monitoring Report. 

Complied  

Page 31: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    19 

 

  Safeguards – Related Provisions in Bidding Documents and Works Contracts 

 

10  The Borrower shall ensure or cause the State to ensure, that  all  bidding  documents  and  contracts  for  Works contain provisions that require Contractors to : 

 

a)  comply with  the measures  and  requirements  relevant to the contractor set forth in the IEE/ EIA, the EMP, the RP and the  IPP( to the extent they concern  impacts on affected  people  during  construction),  and  any corrective or preventive actions set out in a Safeguards Monitoring Report; 

Complied 

b)  make  available budget  for  all  such  environmental  and social measures; 

Complied 

c)   Provide  the  State  with  a  written  notice  of  any unanticipated  environmental,  resettlement  or indigenous  peoples  risks  or  impacts  that  arise  during construction,  implementation  or  operation  of  the Project  that were not  considered  in  the  IEE,  the EMP, the RP or the IPP 

No Change in the situation as reported in IEE & EMP 

d)  Adequately  record the conditions of  roads, agricultural land  and  other  infrastructure  prior  to  starting  to transport materials and construction; and 

Complied 

e)  Fully reinstate pathways, other local infrastructure , and agricultural  land  to  at    least    their  pre  –project conditions upon the completion of construction 

Complied – SIO ensuring Contractors do regular 

maintenance of roads as required   Safeguards Monitoring and Reporting   

11.  The  Borrower  shall,  or  cause  the  State  to,  do  the following: 

 

a)  submit semi‐annual   Safeguards Monitoring Reports  to ADB  and  disclose  relevant  information  from  such reports to affected persons promptly upon submission 

Complied 

b)  If any unanticipated environmental and / or social risks and  impacts arise during construction,  implementation or operation of the Project that were not considered in the  IEE,  the  EMP,  the  RP  or  the  IPP,  promptly  inform ADB  of  the  occurrence  of  such  risks  or  impacts,  with detailed  description  of  the  event  and  proposed corrective action plan; and 

No change in the Scenario 

c)  report  any  actual  or  potential  breach  of  compliance with  the  measures  and  requirements  set  forth  in  the EMP, the RP or the IPP promptly after becoming aware of the breach 

No change in the scenario 

  Labour Standards   14  The  Borrower  and  State  shall  ensure  that  Works  

Contracts under the Project follow all applicable labour laws  of  the  Borrower  and  the  State  and  that  these further  include  provisions  to  the  effect  that Contractors: 

Complied 

Page 32: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    20 

 

a)  carryout HIV/ AIDS awareness programs for  labour and disseminate  information  at  worksites  on  risks  of sexually transmitted diseases and HIV / AIDS as part of health and safety measures  for those employed during construction; and  

Complied – AIDS awareness at PMU level conducted during 18 June 2016 and collaboration with 

Odisha AIDS Control Society undertaken and subproject level 

AIDS campaign for labours undertaken at four places  on 2 

July 2016  b)  follow and implement all statutory provisions on labour 

(  including  not  employing  or  suing  children  as  labour, equal  pay  for  equal  work),  health,  safety,  welfare, sanitation, and working conditions. Such contracts shall also  include  clauses  for  termination  in  case  of  any breach of the state provisions by the Contractors 

Complied 

8.0 CONCLUSIONS  72. Overall, EMP implementation is rated generally “Satisfactory” in two contract packages and two “Partially satisfactory”.   Consultations reveal beneficiaries (local communities) are generally happy with the construction program. No adverse environmental impacts were observed and no grievances  noted.  The  subprojects,  after  restoration  of  the  canals    shall  increase  economic benefits in the sub project area. 

73. Awareness  and  Capacity  development  at  PMU/SIOs  commenced  early  in  the  project  and included training on ADB environment policy and  its  implementation.   Orientation programs on Environmental  safeguards  implementation  was  conducted  during  January  and  February  2016 which  involves  staff  and  Contractors  of  Machhagaon  subproject  also.  Topics  included  ADB safeguards, environmental laws, contract clauses, and reporting needs 

74. Subsequently subproject level orientation program was conducted on 21 June 2015 at Balia restshed  to  overcome  the  shorting  comings;  around  17  persons  including  the  Environment Specialist was present. The key participants were SIO & Contractors staff. 

75. EMP  implementation  timelines have been met  in general.   However, EMP  implementation by  Contractors  is  rated  satisfactory  in  two  contract  packages  and  partially  satisfactory  in  two contract  packages,  with  only  minor  initial  delays  noted  by  some  contractors,  mainly  due  to understanding of the guidelines, contractual constraints and experience of contractor’s staff.   

76. Contractor’s responsiveness  is  increasing and aided  in EMP successful  implementation as a Monthly Environmental Check was introduced to monitor all subprojects.  

77. The Contractors had  recently drilled  some  tubewells,  so SIO had  requested  contractors  to undertake  ground  water  quality  test  as  per  IS:  10,500  immediately  and  the  results  shall  be presented in the next environmental monitoring report. 

78. The surface water quality also shows slightly higher turbidity levels than the CPCB limits, the river  water  not  used  for  drinking  also  and  hence  impact  of  surface  water  observed  due  to construction  is negligible. However  SIO will  undertake  surface water  testing  form  canals  after release of water into the canal and also assess the impact of construction. 

79. SIO  will    undertake  soil  monitoring  by  collecting  samples  adjacent  to  canals  as  per  the suggested  frequency  of    IEE  immediately,  and  the  results  shall  be  submitted  in  the  next environmental monitoring report 

Page 33: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    21 

 

80. The silt analysis results shows the soils are acidic in nature and soils are not polluted due to construction and desilted material used for filling the low lying areas within Right of Way, hence no impact observed because of construction.  

81. The  noise  levels  for  all  the  contract  packages  are  within  the  residential  limits  of  CPCB; however equipment placed away from habitations and the noise levels are within the prescribed noise levels of three wheels vehicles. 

82. Contractors provided  safety  gear/equipment which was not utilized  adequately by  labour because of discomfort, as observed and  informed during monitoring visits, hence there  is scope for improvement on the Contractors side to ensure and encourage the labour for a regular use. 

83. Integrated  Borrow  area  management    approach  by  SIO’s  (borrow  area  test  for  soil classification,  OMC  and  MDD  tests  along  with  agreement  with  the  landowners,  obtaining Environmental  Clearance  from  DEIAA/  DEAC)  will  ensure  easy  Contractors  compliances,  as  a result  this will improve the borrow area management. 

84. AIDS  awareness  program  conducted  and  the  contractor  shall  ensure  that  they  conduct periodically. 

85. The EMR data acquisitions may be archived as  information and baseline  for use  in  future DOWR  environmental  program  management  options  and  as  anticipated  policy  enforcement changes evolve over time. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 34: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    22 

 

 

 

 

 

 

 

ANNEXURES  

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 35: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    23 

 

Annexure 1 Letter to DEIAA for Exemption of Environmental Clearance for Borrow Earth ( Cuttack District) 

 

 

Page 36: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    24 

 

Annexure 1a Letter to DEIAA for Exemption of Environmental Clearance for Borrow Earth ( Jagatsinghpur District) 

 

 

Page 37: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    25 

 

Annexure 2  

 Status of Environmental Mitigation Measures adopted by Contractor for CW‐NCB‐MAC‐01 

Name of the Sub‐project  :  REM of Machhagaon main canal including lining (0.0km to 14.60 km ) and renovation and construction of associated structures 

Name of the Contract Package  : CW‐NCB‐ MAC‐01 Implementation Period  :  25 January 2016 ( commencement date) to 30 June 2016  Physical Works Progress  : Earth Work: 45.91l %   Concrete work: 20.69 %  Physical works carried out during the period:  29.29%  

S.

No.

Environmental

Components / Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

1 Camp Yes • Temporary Transit Labour Camps established in

rented accommodation at Athanga during February

to June 2016.

• The camp is used for supervisory staff and some

labour.

• Some of the outside labour from Keonjhar district

were working apart from local labour (Athanga

village)

• No grievances observed as per SIO

2 Borrow Areas Yes   • Earth procurement is the responsibility of

Contractor. He has procuring earth from private land

and necessary royalty being deducted by the SIO

staff. ( Earth work : 69,317.92 cum total quantity)

• During this working season no earth work was in

progress. Borrowing earth was as per the land

owner’s convenience.

• The SIO had approved 15 patches of borrow area but

No-objection letters from 7 landowners ( Basturi – 2;

Athanga -1; Mahura -2; Birbati -2) were submitted

to SIO. The contractor was requested for the balance

No-objection letters.

• As per SIO there are no grievance noticed however

contractor had to adopt integrated borrow area

management

3 Transporting

Construction Materials

and Haul Road

Management

Yes   • The contractor has avoided the agricultural land for

transportation of materials the contractor used

existing village kachha roads and there are no

damages as per SIO staff

4 Quarries

(Sand and stone metal

from quarry)

Yes   • The contractor has not operated any quarry of his

own under the project. He has obtained aggregates

from the vendors.

• SIO had deducted necessary royalty from the

Contractors (Sand- 500.57 cum and Stone products

– 1873.69 cum so far.

Page 38: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    26 

 

S.

No.

Environmental

Components / Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

5 Soil Erosion & Siltation Yes   • The Construction activity was restricted to non-

monsoon period only.

• Minor rain cuts ( RD 5to 6km; 9 to 10 km) were

observed which would be taken up during next

season

• Provision for slope protection works like turfing is

also proposed

6 Disposal of Silt,

dismantle materials,

debris and equipment

Yes   • Dismantled material /the debris is used in filling the

low lying areas with in the ROW.

7 Impact on land use

pattern of the area

Yes   • Most of the material was stored along the sides of

the canal not in any nearby agricultural lands hence

there is no change in land use as per SIO staff.

8 Blockage of natural

drainage patterns

Yes   • Most of the material was stored along the sides of

the embankment not in any nearby agricultural lands

hence there is no change in land use as per SIO staff.

9 Temporary closure of

irrigation schemes

Yes   • No natural drainage was blocked; Contractor was

requested to clear excess construction materials

present near the sluice sites.

10 Work Sites & protection

of public and workers

health and safety and

appointment of Safety

Officer

Yes   • The villagers were informed construction works and

the consultation carried out is presented in the below

sections.

• The Contractor had provided necessary protective

gears like helmets, hand gloves and boots to the

labourers during construction period, however

limited labour work in progress as most of the work

carried out by machines, even there was resistance to

wear continuously as per SIO. However the

contractor had to motivate the labour in using the

gadgets regularly.

11 Environmental Testing

and Monitoring (

Ground/ Surface Water,

Silt and Soil)

Yes   • SIO had carried out Environmental testing (Surface

water : 1 location, , Noise – 1 location and silt a- 1

location were tested during June 2016.

• The SIO was supposed to conduct baseline after

agreement however they have undertaken during

June 2016.

• SIO and Contractor shall continue environmental

testing as per IEE.

12 Dust generation Yes   • The canals are away from the habitations. However

the Contractor had made dust suppression measures

such as sprinkling of water wherever necessary.

13 Noise from Vehicles,

Plants and Equipments

Yes   • The camp site and equipment sites were located

away from the habitations.

• Average noise levels recorded is 51.9 dBA during

day time and 44.36 dBA during night time decibels,

which are with in the CPCB residential standards.

However, Contractor was requested to undertake

Page 39: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    27 

 

S.

No.

Environmental

Components / Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

proper maintenance of the Construction equipment

to reduce the noise levels.

• The contractor had maintained the vehicles properly

by sending it to regular maintenance.

14 Water Pollution from

Fuel and Lubricants

Yes   • At Present water sample from Jobra testing

undertaken during work period however after

release of canal water surface water testing as per the

suggested frequency shall be done by SIO to assess

impact of the work.

• The contractor had taken adequate care. He was

sending vehicles for the repair to the nearby

mechanics. If any minor repairs he has to do, he has

ensured the area doesn’t contaminate.

15 Contamination of soil by

fuel and lubricants

Yes   • The contractor had taken adequate care. He was

sending vehicles for the repair to the nearby

mechanics. If any minor repairs he has to do, he has

ensured the area doesn’t contaminate.

16 Interference with

existing road network

and traffic, blockage of

access ways. Restriction

on movements of

communities

Yes   • The contractor had made proper safety arrangements

with the local available materials etc., and as well as

informing the community, time to time, wherever

necessary.

17 Emission from

Construction Vehicles,

Equipment and

Machineries

Yes   • Necessary regular and routine maintenance practices

were undertaken for equipments as per the vendor’s

manuals.

• The contractor had maintained the vehicles properly

by sending it to regular maintenance.

18 Flora and Fauna

Protection, tree cutting if

any, including

impairment of fisheries/

aquatic ecology & other

beneficial uses

Yes   • Construction workers were not damaging any flora

or fauna during their work and most of the labour

were not staying near the work site. They are from

the adjoining villages who work and go.

• The Contractor had installed signed boards like no

bird hunting etc.

19 Impact from other

Projects in the area

NR • The environmental pollution like dust emissions,

damage to some sub-minors and improper borrowing

of the earth are also noticed in the environs of the

project because of other ongoing project woks like

construction of road works and pipeline works; these

are also contributing to the change in environmental

conditions of the environs of this project.

 

 

 

Page 40: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    28 

 

Annexure 3 

 Status of Environmental Mitigation Measures adopted by Contractor for CW‐NCB‐MAC ‐02 

Name of the Sub‐project  :  Restoration of Machhgaon main canal including lining (14.60km to  29.20 km) and renovation and construction of associated structures 

Name of the Contract Package  : CW‐NCB‐ MAC‐02 Implementation Period   : 9 February 2016( Date of commencement) to 30 June 2016  Physical Works Progress  :  Earth  work 49.34   Concrete work: ‐14.054‐%  Physical works carried out during the period:  26.60  

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

1 Camp

Yes

• Temporary Transit Labour Camps established in rented

accommodation at Dhanipur during February to June 2016.

• The camp is used for supervisory staff and some labour.

• Some of the outside labour from Keonjhar district were

working apart from local labour ( Blia and Tarikunda,

village)

• No grievances observed as per SIO

2 Borrow Areas Yes • Earth procurement is the responsibility of Contractor. He

has procuring earth from private land and necessary royalty

being deducted by the SIO staff. ( Earth work : 72,189.41

cum total quantity)

• During this working season no earth work was in progress.

Borrowing earth was as per the land owner’s convenience.

• SIO had approved 20 patches of land for borrow earth.

No-objection letters from --7 landowners ( Jayasolo -2;

Balia -2;Biridi -2; Pandia -1) were submitted to SIO by the

contractor.

• SIO had requested contractor for submitting the balance

NOC

• As per SIO there are no grievance noticed however

contractor had to adopt integrated borrow area

management

3 Transporting

Construction

Materials and Haul

Road Management

Yes . • The contractor has avoided the agricultural land for

transportation of materials the contractor used existing

village kachha roads and there are no damages as per SIO

staff

4 Quarries

(Sand and stone

metal from quarry)

Yes • The contractor has not operated any quarry of his own

under the project. He has obtained aggregates from the

vendors.

• SIO had deducted necessary royalty from the Contractors

(Sand – 429.24cum and Stone products – 684.28 cum so

Page 41: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    29 

 

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

far.

5 Soil Erosion &

Siltation

Yes • The Construction activity was restricted to non-monsoon

period only.

• Minor rain cuts(RD 15 to 20km on the left bank) were

observed which would be taken up during next season

• Provision for slope protection works like turfing is also

proposed

6 Disposal of Silt,

dismantle

materials, debris

and equipment

Yes • Dismantled material /the debris is used in filling the low

lying areas with in the ROW.

7 Impact on land use

pattern of the area

Yes • Most of the material was stored along the sides of the canal

not in any nearby agricultural lands hence there is no

change in land use as per SIO staff.

8 Blockage of natural

drainage patterns

Yes • Most of the material was stored along the sides of the

embankment not in any nearby agricultural lands hence

there is no change in land use as per SIO staff.

9 Temporary closure

of irrigation

schemes

Yes • No natural drainage was blocked; Contractor was requested

to clear excess construction materials present near the

sluice sites.

10 Work Sites &

protection of public

and workers health

and safety and

appointment of

Safety Officer

Yes • The villagers were informed construction works and the

consultation carried out is presented in the below sections.

• The Contractor had provided necessary protective gears

like helmets, hand gloves and boots to the labourers during

construction period., however limited labour work in

progress as most of the work carried out by machines, even

there was resistance to wear continuously as per SIO.

However Contractor was requested to motivate the labour

for using regularly.

11 Environmental

Testing and

Monitoring (

Ground/ Surface

Water, Silt and

Soil)

Yes • SIO had carried out Environmental testing (Surface water :

1 location, , Noise – 1 location and silt - 1 location were

tested during June 2016.

• The SIO was supposed to conduct baseline after agreement

however they have undertaken during June 2016.

• SIO and Contractors shall undertake environmental testing

as per the IEE regularly.

12 Dust generation Yes • The canals are away from the habitations. However the

Contractor had made dust suppression measures such as

sprinkling of water wherever necessary.

13 Noise from

Vehicles, Plants

and Equipments

Yes • The camp site and equipment sites were located away

from the habitations.

• Average noise levels recorded is 50.2 dBA during day time

and 43.6 dBA during night time decibels, which are with in

Page 42: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    30 

 

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

the CPCB residential standards. However, Contractor was

requested to undertake proper maintenance of the

Construction equipment to reduce the noise levels.

• The contractor had maintained the vehicles properly by

sending it to regular maintenance.

14 Water Pollution

from Fuel and

Lubricants

Yes • At Present water sample from Jobra testing undertaken

during work period however after release of canal water

surface water testing as per the suggested frequency shall

be done by SIO to assess impact of the work.

• The contractor had taken adequate care. He was sending

vehicles for the repair to the nearby mechanics. If any

minor repairs he has to do, he has ensured the area doesn’t

contaminate.

15 Contamination of

soil by fuel and

lubricants

Yes • The contractor had taken adequate care. He was sending

vehicles for the repair to the nearby mechanics. If any

minor repairs he has to do, he has ensured the area doesn’t

contaminate.

16 Interference with

existing road

network and traffic,

blockage of access

ways. Restriction

on movements of

communities

Yes • The contractor had made proper safety arrangements with

the local available materials etc., and as well as informing

the community, time to time, wherever necessary.

17 Emission from

Construction

Vehicles,

Equipment and

Machineries

Yes • Necessary regular and routine maintenance practices were

undertaken for equipments as per the vendor’s manuals.

• The contractor had maintained the vehicles properly by

sending it to regular maintenance.

18 Flora and Fauna

Protection, tree

cutting if any,

including

impairment of

fisheries/ aquatic

ecology & other

beneficial uses

Yes • Construction workers were not damaging any flora or

fauna during their work and most of the labour were not

staying near the work site. They are from the adjoining

villages who work and go.

• The Contractor had installed signed boards like no bird

hunting etc.

19 Impact from other

Projects in the area

NR • The environmental pollution like dust emissions, damage to

some sub-minors and improper borrowing of the earth are

also noticed in the environs of the project because of other

ongoing project woks like construction of road works and

pipeline works; these are also contributing to the change in

environmental conditions of the environs of this project.

 

 

Page 43: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    31 

 

Annexure 4 

 Status of Environmental Mitigation Measures adopted by Contractor for CW‐NCB‐MAC ‐03 

Name of the Sub‐project  :  Restoration of Machhgaon main canal including lining (  29.20 km to 52.425) and renovation and construction of associated structures 

Name of the Contract Package  : CW‐NCB‐ MAC‐03 Implementation Period   : 9 February 2016( Date of commencement) to 30 June 2016  Physical Works Progress  :  Earth  work : 0 %   Concrete work: 6.09 %  Physical works carried out during the period:  8.95%  

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

1 Camp

Yes

• Temporary Transit Labour Camps established in rented

accommodation at Ichhapur during February to June

2016.

• Some supervisory staff and out side labour were staying

the camp

• Labour from Keonjhar and Sundergarh were working

apart from local labour( Ichhapur and Balikuda villagers

were working

• No grievances observed as per SIO

2 Borrow Areas Yes • Earth procurement is the responsibility of Contractor.

During this period only concrete work has commenced

earth work is yet to commence.

• Contractor was requested to identify the land owners

who are willing to give earth for obtaining necessary

permissions.

3 Transporting

Construction

Materials and Haul

Road Management

Yes . • The contractor has avoided the agricultural land for

transportation of materials the contractor used existing

village kachha roads and there are no damages as per

SIO staff

4 Quarries

(Sand and stone

metal from quarry)

Yes • The contractor has not operated any quarry of his own

under the project. He has obtained aggregates from the

vendors.

• SIO had deducted necessary royalty from the

Contractors (Sand- 391.98 cum Stone products 747.69

cum;

5 Soil Erosion &

Siltation

Yes • The Construction activity was restricted to non-

monsoon period only.

• Minor rain cuts were observed which would be taken up

during next season

• Provision for slope protection works like turfing is also

proposed

Page 44: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    32 

 

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

6 Disposal of Silt,

dismantle

materials, debris

and equipment

Yes • Dismantled material /the debris is used in filling the low

lying areas with in the ROW.

7 Impact on land use

pattern of the area

Yes • Most of the material was stored along the sides of the

canal not in any nearby agricultural lands hence there is

no change in land use as per SIO staff.

8 Blockage of natural

drainage patterns

Yes • Most of the material was stored along the sides of the

embankment not in any nearby agricultural lands hence

there is no change in land use as per SIO staff.

9 Temporary closure

of irrigation

schemes

Yes • No natural drainage was blocked; Contractor was

requested to clear excess construction materials present

near the sluice sites.

10 Work Sites &

protection of public

and workers health

and safety and

appointment of

Safety Officer

Yes • The villagers were informed construction works and the

consultation carried out is presented in the below

sections.

• The Contractor had provided necessary protective gears

like helmets, hand gloves and boots to the labourers

during construction period., however limited labour

work in progress as most of the work carried out by

machines, even there was resistance to wear

continuously as per SIO.

11 Environmental

Testing and

Monitoring (

Ground/ Surface

Water, Silt and

Soil)

Yes • SIO had carried out Environmental testing (Surface

water : 1 location, , Noise – 1 location and silt - 1

location were tested during June 2016.

• The SIO was supposed to conduct baseline after

agreement however they have undertaken during June

2016.

• SIO and Contractors shall undertake environmental

testing as per frequency suggested in the IEE.

12 Dust generation Yes • The canals are away from the habitations. However the

Contractor had made dust suppression measures such as

sprinkling of water wherever necessary.

13 Noise from

Vehicles, Plants

and Equipments

Yes • The camp site and equipment sites were located away

from the habitations.

• Average noise levels recorded is 49.0 dBA during day

time and 43.1 dBA during night time decibels, which are

with in the CPCB residential standards. However,

Contractor was requested to undertake proper

maintenance of the Construction equipment to reduce

the noise levels.

• The contractor had maintained the vehicles properly by

sending it to regular maintenance.

14 Water Pollution

from Fuel and

Yes • At Present water sample from Jobra testing undertaken

during work period however after release of canal water

surface water testing as per the suggested frequency

Page 45: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    33 

 

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

Lubricants shall be done by SIO to assess impact of the work.

• The contractor had taken adequate care. He was sending

vehicles for the repair to the nearby mechanics. If any

minor repairs he has to do, he has ensured the area

doesn’t contaminate.

15 Contamination of

soil by fuel and

lubricants

Yes • The contractor had taken adequate care. He was sending

vehicles for the repair to the nearby mechanics. If any

minor repairs he has to do, he has ensured the area

doesn’t contaminate.

16 Interference with

existing road

network and traffic,

blockage of access

ways. Restriction

on movements of

communities

Yes • The contractor had made proper safety arrangements

with the local available materials etc., and as well as

informing the community, time to time, wherever

necessary.

17 Emission from

Construction

Vehicles,

Equipment and

Machineries

Yes • Necessary regular and routine maintenance practices

were undertaken for equipments as per the vendor’s

manuals.

• The contractor had maintained the vehicles properly by

sending it to regular maintenance.

18 Flora and Fauna

Protection, tree

cutting if any,

including

impairment of

fisheries/ aquatic

ecology & other

beneficial uses

Yes • Construction workers were not damaging any flora or

fauna during their work and most of the labour were not

staying near the work site. They are from the adjoining

villages who work and go.

• There are around 60 trees which are hindrance to

movement of construction vehicles hence SIO was

requested to write to the forest department for obtaining

forest tree cutting permission.

• The Contractor had installed signed boards like no bird

hunting etc.

19 Impact from other

Projects in the area

NR • The environmental pollution like dust emissions, damage

to some sub-minors and improper borrowing of the earth

are also noticed in the environs of the project because of

other ongoing project woks like construction of road

works and pipeline works; these are also contributing to

the change in environmental conditions of the environs of

this project.

 

 

 

 

Page 46: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    34 

 

Annexure 5 

 Status of Environmental Mitigation Measures adopted by Contractor for CW‐NCB‐MAC ‐05 

Name of the Sub‐project  :  Restoration of Distributaries no. 7 and 19A of  Machhgaon main canal  including structures, selective lining and repair to canal embankment road 

Name of the Contract Package  : CW‐NCB‐ MAC‐05 Implementation Period   : 15 February 2016( Date of commencement) to 30 June 2016  Physical Works Progress  :  Earth  work : 74.54%Concrete work: 9.26%  Physical works carried out during the period:  31.14%  

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

1 Camp

Yes

• Temporary Transit Labour Camps established in rented

accommodation at Rambhaidepur village during

February to June 2016.

• Some supervisory staff and outside labour were staying

the camp

• Labour from Keonjhar and Jajpur Districts were

working apart from local labour(Kospa, Rambhadeipur,

Kulamundilo, Mandasahi, Rohia, Kendal, Tartanga,

Titigoan, Kuntapada, and Erasama villages were

working during this period

• No grievances observed as per SIO

2 Borrow Areas Yes • Earth procurement is the responsibility of Contractor.

He has procuring earth from private land and necessary

royalty being deducted by the SIO staff. ( Earth work :

53,644.48 cum total quantity)

• During this working season no earth work was in

progress. Borrowing earth was as per the land owner’s

convenience.

• No-objection letters were collected 5 landowners and

which are available with SIO staff

• As per SIO there are no grievance noticed.

3 Transporting

Construction

Materials and Haul

Road Management

Yes . • The contractor has avoided the agricultural land for

transportation of materials the contractor used existing

village kachha roads and there are no damages as per

SIO staff

4 Quarries

(Sand and stone

metal from quarry)

Yes • The contractor has not operated any quarry of his own

under the project. He has obtained aggregates from the

vendors.

• SIO had deducted necessary royalty from the

Contractors (Sand- 133.55 cum Stone products 262.62

cum so far.

Page 47: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    35 

 

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

5 Soil Erosion &

Siltation

Yes • The Construction activity was restricted to non-

monsoon period only.

• Minor rain cuts( Disty 19A-RD 2 to 4km; 6 to 7km; and

12.5 to 15km) were observed which would be taken up

during next season

• Provision for slope protection works like turfing is also

proposed

6 Disposal of Silt,

dismantle

materials, debris

and equipment

Yes • Dismantled material /the debris is used in filling the low

lying areas with in the ROW.

7 Impact on land use

pattern of the area

Yes • Most of the material was stored along the sides of the

canal not in any nearby agricultural lands hence there is

no change in land use as per SIO staff.

8 Blockage of natural

drainage patterns

Yes • Most of the material was stored along the sides of the

embankment not in any nearby agricultural lands hence

there is no change in land use as per SIO staff.

9 Temporary closure

of irrigation

schemes

Yes • No natural drainage was blocked; Contractor was

requested to clear excess construction materials present

near the sluice sites.

10 Work Sites &

protection of public

and workers health

and safety and

appointment of

Safety Officer

Yes • The villagers were informed construction works and the

consultation carried out is presented in the below

sections.

• The Contractor had provided necessary protective gears

like helmets, hand gloves and boots to the labourers

during construction period., however limited labour

work in progress as most of the work carried out by

machines, even there was resistance to wear

continuously as per SIO. However, the contractor was

requested to motivate the labour in using PPE regularly.

11 Environmental

Testing and

Monitoring (

Ground/ Surface

Water, Silt and

Soil)

Yes • SIO had carried out Environmental testing (Surface

water : 1 location, , Noise – 1 location and silt - 1

location were tested during June 2016.

• The SIO was supposed to conduct baseline after

agreement however they have undertaken during June

2016

• SIO and Contractor were requested to undertake

environmental testing as per suggested frequency in the

IEE.

12 Dust generation Yes • The canals are away from the habitations. However the

Contractor had made dust suppression measures such as

sprinkling of water wherever necessary.

13 Noise from

Vehicles, Plants

and Equipments

Yes • The camp site and equipment sites were located away

from the habitations.

• Average noise levels recorded is 48.4 dBA during day

Page 48: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    36 

 

S.

No.

Environmental

Components /

Issues

Compliances

by the

Contractor

Status on Mitigation measures by the Contractor

Yes No /

NR

time and 43.2 dBA during night time decibels, which are

with in the CPCB residential standards. However,

Contractor was requested to undertake proper

maintenance of the Construction equipment to reduce

the noise levels.

• The contractor had maintained the vehicles properly by

sending it to regular maintenance.

14 Water Pollution

from Fuel and

Lubricants

Yes • At Present water sample from Jobra testing undertaken

during work period however after release of canal water

surface water testing as per the suggested frequency

shall be done by SIO to assess impact of the work.

• The contractor had taken adequate care. He was sending

vehicles for the repair to the nearby mechanics. If any

minor repairs he has to do, he has ensured the area

doesn’t contaminate.

15 Contamination of

soil by fuel and

lubricants

Yes • The contractor had taken adequate care. He was sending

vehicles for the repair to the nearby mechanics. If any

minor repairs he has to do, he has ensured the area

doesn’t contaminate.

16 Interference with

existing road

network and traffic,

blockage of access

ways. Restriction

on movements of

communities

Yes • The contractor had made proper safety arrangements

with the local available materials etc., and as well as

informing the community, time to time, wherever

necessary.

17 Emission from

Construction

Vehicles,

Equipment and

Machineries

Yes • Necessary regular and routine maintenance practices

were undertaken for equipments as per the vendor’s

manuals.

• The contractor had maintained the vehicles properly by

sending it to regular maintenance.

18 Flora and Fauna

Protection, tree

cutting if any,

including

impairment of

fisheries/ aquatic

ecology & other

beneficial uses

Yes • Construction workers were not damaging any flora or

fauna during their work and most of the labour were not

staying near the work site. They are from the adjoining

villages who work and go.

• The Contractor had installed signed boards like no bird

hunting etc.

19 Impact from other

Projects in the area

NR • The environmental pollution like dust emissions, damage

to some sub-minors and improper borrowing of the earth

are also noticed in the environs of the project because of

other ongoing project woks like construction of road

works and pipeline works; these are also contributing to

the change in environmental conditions of the environs of

this project.

Page 49: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    37 

 

Annexure  6 Surface Water Quality Monitoring Report – 2016 

Machagaon

Machagon Canal

Division/ near HR

1 2 3 4 5 9

Date of Sample collection dd/mm/yy 23/06/2016

1 Physical Parameter

i Colour Hazen 5 15

ii Odour Unobjectionable Unobjectionable

iii pH Value 6.5-8.5 6.5-8.5 8.52

iv Taste Agreeable Agreeable

v Turbidity NTU Max 1 Max 5 2.6

vi Total Dissolved solids mg/l Max 500 Max 2000 117

vii Total Suspended solids mg/l Max 500 Max 2000

2

i Alluminium as Al mg/l Max 0.03 Max 0.2 0.1

ii Ammonia (as total ammonia-N) mg/l 0.5 No relaxation

iii Anionic detergents (as MBAS) mg/l Max 0.2 Max 1 <0.2

iv Barium ( as Ba) mg/l Max 0.7 No relaxation <1.0

v Boron as B mg/l Max. 0.5 1 ND

vi Calcium as Ca mg/l Max 75 200

vii Chloramine as cl2 mg/l 4 No relaxation

viii Chloride (as Cl) mg/l Max 250 Max 1000 9.52

ix Copper (as Cu) mg/l Max 0.05 Max 1.5 0.15

x Fluoride (as F) mg/l Max 1.0 Max 1.5 1.1

xi Free residual chlorine mg/l Min 0.2 1

xii Iron (as Fe) mg/l Max 0.3 Max 1 0.04

xiii Magnesium as Mg mg/l 30 100

xiv Manganese as Mn mg/l 0.1 0.3 0.1

xv Mineral oil mg/l 0.5 No relaxation

xvi Nitrate (as No3) mg/l Max 45 Max 45 0.28

xvii Phenoloic compounds (as

C6H5HO)

mg/l Max 0.001 Max 0.002 <0.002

xviii Selinium (as Se) mg/l Max 0.01 Max 0.01

xix Silver as Ag mg/l 0.1 No relaxation

xx Sulphate (as So4) mg/l Max 200 Max 400 1.32

xxi Sulphide as H2S mg/l 0.005 No relaxation

xxii Total Alkalinity as calcium

carbonate

mg/l 200 600

xxiii Total Hardness as TH mg/l 40

xxiv Total Hardness (as CaCO3) mg/l Max 200 Max 600 17.63

xxv Magnesium hardness as

CaCO3

mg/l 2.8

xxvi Zinc (as Zn) mg/l Max 5.0 Max 15 0.28

xxvii Silica mg/l

xxviii Phosphate mg/l

xxix Percentage of Sodium 2.2

xxx Residual Sodium Carbonate as

RSC

meq/l 0.41

xxxi Free Amonia as N ND

3

i Cadmium (as Cd) mg/l Max 0.003 No relaxation

ii Cyanide (as CN) mg/l Max 0.05 Max 0.05 <0.02

iii Lead (as Pb) mg/l Max 0.05 Max 0.05 <0.1

iv Mercury (as Hg) mg/l Max 0.001 Max 0.001 ND

v Molybodenum as Mo mg/l 0.07 No relaxation

vi Nickle as Ni mg/l Max 0.02 No relaxation

vii Polychlorinated

biphenyles

mg/l Max 0.0005 No relaxation

viii Polynuclear aromatic

hydrocarbons

mg/l Max 0.001 No relaxation

ix Arsenic (as As) mg/l Max 0.01 0.05 <0.05

x Total chromium as Cr mg/l Max 0.05 No relaxation <0.05

4 Pesticide Residues

i DDT (o,p and p,p isomer of

DDT,DDE and DDD)

1 Absent

ii Endosulfans(alpha,beta,sulphat

e)

0.4 Absent

iii Monocrotophos 1 Absent

iv Phorate 2 Absent

v Carbofuram Absent

5 Bacteriological

i Total Coliform as TC MPN/100ml 21

ii Total Colonies CFU/ml

6 Others

i Electrical Conductivty 159.8

ii Sodium Absorption ratio 0.4 0.2

iii Dissolved Oxygen 5.2

iv Chemical Oxygen Demand 16

v Biological Oxygen Demand 2.8

Sl

No

Test Parameter Unit Acceptable

Limit Unit

Surface Water Quality Monitoring Report- 2016

Permisible

Limit Unit

General

Parameters concerning Toxic Substances

 

Page 50: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    38 

 

Annexure  7  ‐Silt Quality Monitoring Report‐ 2016 

S.No Parameters Units of

Measurem

ent

PACKAGE1

S1

PACKAGE2

S2

PACKAGE3

S3

PACKAGE4

S4

1 2 3 S1 S2 S3 S4

Date of Sample

Collection

23/06/16 23/06/16 23/06/16 23/06/16

1 pH of 5% Solution µs/cm 6.25 5.88 6.03 6.572 E C of 5% Solution % 47.74 63 36.09 543 Organic Carbon as C mg/kg 0.85 0.88 0.92 0.84 Phosphorus as P mg/kg 0.023 0.021 0.026 0.0245 Potassium as K mg/kg 0.16 0.12 0.12 0.16 Sulphur as S mg/kg 0.018 0.014 0.014 0.027 Calcium as Ca mg/kg 8.2 7 6.3 7.88 Magnisium as Mg mg/kg 2.8 1.2 1.4 0.929 Flouride mg/kg 0.08 0.1 0.04 0.0810 Iron as Fe 2 2 1 4 2 1 1 811 Chloride PPM12 Total Soluble Sulphate

as So4%

13 Phosphates PPM14

a Lead as Pb mg/kg 0.012 0.016 0.011 0.011b Chromium as Cr mg/kg 0.022 0.026 0.028 0.022c Nickel as Ni mg/kg ND ND ND NDd Cadmium as Cd mg/kg ND ND ND NDe Mercury as Hg mg/kg ND ND ND NDf Arsenic as As mg/kg ND ND ND ND

15

a Boron as B mg/kg 0.008 0.006 0.01 0.008b Copper as Cu mg/kg 0.012 0.012 0.014 0.013d Manganese as Mn mg/kg 0.13 0.11 0.1 0.06e Molybdenium as Mo mg/kg 0.04 0.02 0.02 0.02f Zinc as Zn mg/kg 0.14 0.16 0.18 0.2

16

a DDE-o.p mg/kg

b DDE-p.p mg/kg

c DDD-o.p mg/kgd DDT-p.p mg/kg ABSENT ABSENT ABSENT ABSENT

e DDT-o.p mg/kg

f DDT-p.p mg/kg

g Endosulphan 1 mg/kg ABSENT ABSENT ABSENT ABSENT

h Endosulphan-II mg/kg

i Endosulphan Sulphate mg/kg

j Monocrotophos mg/kg ABSENT ABSENT ABSENT ABSENT

k Carbofuran mg/kg ABSENT ABSENT ABSENT ABSENT

l Phorate mg/kg ABSENT ABSENT ABSENT ABSENT

Micronutrients

Pesticides

Heavy Metals

Silt Quality Monitoring Report - 2016

 

 

Page 51: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    39 

 

Annexure  8‐ Noise Quality Monitoring Report – 2016‐ MAC‐01 

 

Page 52: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    40 

 

Annexure  8‐ Noise Quality Monitoring Report – 2016‐ MAC‐02 

 

Page 53: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    41 

 

Annexure  8‐ Noise Quality Monitoring Report – 2016‐ MAC‐03 

 

Page 54: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    42 

 

Annexure  8‐ Noise Quality Monitoring Report – 2016‐ MAC‐05 

 

Page 55: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    43 

 

Annexure  9 – FGD/ Consultation‐ List of Participants at  Hajipur Village 

 

 

 

 

 

 

 

 

 

 

 

 

Page 56: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    44 

 

Annexure  9a – FGD/ Consultation‐ List of Participants at  Pandia Village 

 

 

 

 

 

 

 

 

Page 57: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    45 

 

 

 

 

 

 

 

 

PHOTOGRAPHS  

 

 

 

 

 

 

 

 

 

 

 

 

Page 58: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    46 

 

Photo Plate:1‐ Machhagaon Sub Project  

   RD 4.7km of MAC‐01 main canal – VRB work in progress‐ ADB 

visit Interaction of ADB staff, SIO and Contractors at 

Machhagaon Subproject 

   RD 6.40km of MAC‐01 main canal with Safety arrangement – ADB Visiit 

Review of EMP compliances by ADB Env. Spl in Machhagaon Subproject 

Meeting with PP at jagatsingpur circuit house – during ADB visiit 

Environmental Orientation Program on  2nd July at Balia Reset shed 

Page 59: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    47 

 

  

RD 3.00km in MAC‐01 benching work in Progress  RD 4.00km of Disty 19A – Embakment work in Progress  

  

 Water sprinkling in progress 0.000 Km to 10.000 Km Disty 19A‐ MAC ‐05 

Borrow Area – Madhusudanpur for MAC ‐05 

 

 

MAC‐05 Disty 7 usage of PPE   Focus Group Discussion at Pandia Village 

 

Page 60: Environmental Monitoring Report€¦ · Environmental Monitoring Report – Machhagaon Sub Project August r s x 2 CONTENTS No CONTENT Pg.No List of Abbreviations EXECUTIVE SUMMARY

Orissa Integrated Irrigated Agriculture and Water Management Investment Program  

 

Environmental Monitoring Report – Machhagaon sub project  August    48 

 

   

AIDS  Awareness  Campaign  at  Athanga  Village  – MAC‐01 contract package 

AIDS  Awareness  Campaign  at  Balia  Village  – MAC‐2 contract package 

   AIDS  Awareness  Campaign  at  Ichhapur  Village  – MAC‐03 contract package 

AIDS Awareness Campaign at Ichhapur Village – MAC‐05 contract package Virabarapatna