38
Environmental Monitoring Report 4 th Quarterly Report May 2016 VIE: Power Transmission Investment Program - Tranche 1 220 kV Phu My 2 Industrial Zone Substation Prepared by Southern Power Projects Management Board (SPPMB) for National Power Transmission Corporation and the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Environmental Monitoring Report - Asian Development · PDF fileEnvironmental Monitoring Report 4th Quarterly Report May 2016 VIE: Power Transmission Investment Program - Tranche 1

Embed Size (px)

Citation preview

Environmental Monitoring Report 4th Quarterly Report May 2016

VIE: Power Transmission Investment Program -

Tranche 1

220 kV Phu My 2 Industrial Zone Substation

Prepared by Southern Power Projects Management Board (SPPMB) for National Power

Transmission Corporation and the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

NATIONAL POWER TRANSMISSION CORPORATION

SOUTHERN VIETNAM POWER PROJECT MANAGEMENT BOARD

POWER TRANSMISSION INVESTMENT PROGRAM – TRANCHE 1

SUB-PROJECT: 220KV PHU MY 2 INDUSTRIAL ZONE SUBSTATION

LOAN 2848-VIE

QUARTERLY MONITORING REPORT

FOR

ENVIRONMENTAL SAFEGUARD - No.8

(Operation phase, October – December 2015)

January, 2016

i

Content

List of Table ....................................................................................................................... ii

List of Figure ...................................................................................................................... ii

Abbreviations ....................................................................................................................... iii

1. Introduction .................................................................................................................................................. 1

1.1. Project background ............................................................................................ 1

1.2. Subproject description ....................................................................................... 1

1.3. Organization in Operation Phase ....................................................................... 5

2. Environmental Management and Monitoring Framework ..................................................................... 6

2.1. Applicable Policies and Regulations .................................................................. 6

2.2. Environmental Management Organizational Structure....................................... 7

2.3. Operation Phase ................................................................................................ 8

2.3.1. Potential Impacts Identified during the IEE Preparation ....................................................................... 8 2.3.2. Environmental Mitigations and Compensation Measures Proposed in

the IEE 11

2.3.3. Monitoring Framework .......................................................................................................... 13

3. Monitoring Result ......................................................................................................................... 14

3.1. Compliance with ADB loan covenants and applicable

government laws, regulations and requirements ............................ 14

3.2. Environmental Monitoring Program ................................................ 17

3.3. Environment compliance at the substation............................... 18

3.4. Effectiveness of mitigation measures ....................................... 21

ii

List of Table

Table 1: Scope of the substation .................................................................................................. 3

Table 2: Scope of 220kV connection line .................................................................................... 5

Table 3: Application Laws and Regulations ............................................................................... 6

Table 4: environmental procedures requirement ...................................................................... 7

Table 5: Potential environmental issues during the operation

phase............................................................................................................................................. 9

Table 6: Mitigation measures in operation phase ...................................... 11

Table 7: Monitoring framework in operation phase ................................... 13

Table 8: Compliance with the ADB loan covenants related to

environmental safeguard ............................................................................................... 14

Table 9: Compliance with Vietnam regulations on environmental

protection............................................................................................................................... 16

Table 10: Monitoring programme............................................................................... 17

Table 11: Summary of environmental compliance activities ................ 18

Table 12: Mitigation compliance and effectiveness ................................. 21

List of Figure

Figure 1: Location Map of 220kV Phu My 2 IZ Substation ..................................................... 2

Figure 2: Diagram of Phu My 2 IZ Substation .......................................................................... 2

Figure 3: Diagram of Operation management ........................................................................... 5

Figure 4: Diagram of safeguards monitoring and management .............................................. 8

iii

Abbreviations

ADB Asian Development Bank

CHS Community Health and safety

EA Executing Agency

EMP Environmental Management Plan

EPC Environment Protection Commitment

IA Implementing Agency

IEE Initial Environmental Examination

IZ Industrial Zone

NPT National Power Transmission Corporation

PDMP Power Development Master Plan

SPPMB Southern Power Project Management Board

ROW Right of Way

1

1. Introduction

1.1. Project background

1. The Power Transmission Investment Program (“Investment Program”) is an

integral part of the National Power Development Master Plan VII (“PDMP VII”) and comprises of:

- Transmission Network Expansion Component to expand and upgrade 500 kV

and 220 kV transmission lines and associated substations throughout Viet Nam;

- Operational Improvement Component for strengthening operational effectiveness

and efficiency of the National Power Transmission Corporation (“NPT”); and

- Project Implementation Support Component for detailed technical design,

construction supervision, safeguard compliance, and preparing subsequent

projects of the Investment Program.

2. The Asian Development Bank (ADB) provides financing for the development the

subprojects of Power transmission investment program - tranche 1, which includes the

subproject of the 220 kV Phu My 2 Industrial Zone. The subproject includes following

components:

(i) Construction of the 220kV substation and access road;

(ii) Construction of the 220kV transmission line with a total length of 1,707 m;

(iii) Construction and installation of two parallel 110kV transmission line with a

length of 831 m and 912 m.

3. The National Power Transmission Corporation (NPT) of Viet Nam is the

executing agency (EA) while the Southern Power Project Management Board

(SPPMB) is the implementing agency (IA) of the sub-project.

4. The construction works started in August 2013 and completed in December

2014. The substation is called as “Tan Thanh substation” and handovered to the

Power Transmission Company No. 4 for management and operation.

5. This quarterly report will describe the implementation of the EMP and compliance

issues with the environmental and social management programs in during operation

phase between October and December of 2015.

1.2. Subproject description

6. The subproject is located in Tan Phuoc commune, Tan Thanh district, Ba Ria –

Vung Tau province. The location map of Subproject is presented in Figure 1 and the

diagram of Subproject is illustrated in Figure 2.

2

Figure 1: Location Map of 220kV Phu My 2 IZ Substation

Figure 2: Diagram of Phu My 2 IZ Substation

3

7. The subproject includes 220kV Tan Thanh substation, 220kV and 110kV

connection lines as follows:

Tan Thanh substation: The substation is located in an area of 55,013m2 with

voltage level of 220/110/22kV and capacity of 2x250MVA. Scope of the substation is

presented in Table 1.

Table 1: Scope of the substation

Item Content Specification Quantity I Control part and Auxiliary Facilities 1 Centre control house (including

director room, technical staff room, control center room, information room, battery room)

384m2

2 Fire-house (electrical motor pump Q = 150m3/h, H=60m, 2 units; Jockey motor pump Q=5,3m3/h, H=80m, 1 unit)

24m2

3 Fire water tank 150m3 4 Supply system water (domestic water

tank, water tower, well deep 35m, process water house)

4m3

5 Water drainage system 6 Vocational house

II Substation Part 1 Power Transformer - Type: Outdoor, three

phase, 50Hz, autotransformer

- Capacity: 250/250MVA - Voltage:

225+8x1.25%/115/23kV

2

2 220kV switchgear - SF6 circuit breaker – 220kV - Type: outdoor

- Voltage: 245kV - Frequency: 50Hz

7

- Disconnector – 220kV - Type: outdoor - Voltage: 245kV - Frequency: 50Hz

32

- Current transformer - Type: Single phase, oil-immersed transformer

- Voltage: 245kV - Frequency: 50Hz

18

- Capacitive voltage transformer - Type: Single phase, oil-immersed transformer

- Voltage: 245kV - Frequency: 50Hz

18

4

- Lightning arrester and lightning strike counter

- Type: ZnO, outdoor, single phase

- Voltage: Ur = 192 kV - Frequency: 50Hz

12

3 110kV switchgear - SF6 circuit breaker - Type: outdoor

- Voltage: 123kV - Frequency: 50Hz

11

- Disconnector - Type: outdoor, single-phase and three-phase

- Voltage: 123kV - Frequency: 50Hz

52

- Current transformer - Type: Single phase, oil-immersed transformer

- Voltage: 123kV - Frequency: 50Hz

33

- Capacitive voltage transformer - Type: Single phase, oil-immersed transformer

- Voltage: 123kV - Frequency: 50Hz

36

- Lightning arrester and lightning strike counter

- Type: ZnO, outdoor, single phase

- Voltage: Ur = 96 kV - Frequency: 50Hz

12

4 22kV switchgears - Circuit breaker - Voltage: 24kV

- Frequency: 50Hz 2

- Disconnector - Voltage: 24kV - Frequency: 50Hz

2

Current transformer - Voltage: 24kV 12 - Inductive voltage transformer - Type: Single phase

- Voltage: 24kV - Frequency: 50Hz

6

- Lightning arrester and lightning strike counter

- Type: ZnO, outdoor, single phase

- Voltage: Ur = 30 kV - Frequency: 50Hz

6

Connection lines:

- The 220kV connection line has 4 circuits with 1,808 m long from N242-66ĐN to 220kV gate tower of the 220kV Phu My 2.

- The 110kV connection line has 4 circuits with total length of 1,637m including:

+ Part 1 with 778m from 110kV gate tower of the 220kV Phu My 2 to tower T15/8

of the 110kV Phu My - Thi Vai and Posco and

+ Part 2 with 859m from 110kV gate tower of the 220kV Phu My 2 to tower T15/8

of the 110kV Phu My - Thi Vai and Posco.

5

The scope of connection line is presented in Table 2.

Table 2: Scope of 220kV connection line

Item Connection line

Length (m) Circuit

s

Tower

Quantity Coding

1 220kV connection line

1,808 4 8

N242-66ĐN, N242-66V, Đ242-72, N242-66C, N242-57C-XP, N222-43B

2 110kV connection line part 1

831 4 5

N122-29B, N142-48C+XP, N142-48ĐN, Đ142-52A

3 110kV connection line part 2

912 4 5

N122-29B, N142-48C+XP, N142-48ĐN, Đ142-52A

1.3. Organization in Operation Phase

8. The substation is under control of Western (Mien Dong) Power Transmission

No.1 belonging to Power transmission Company No.4.

9. The substation has 12 officers and staff in which 1 staff is in charge of safety and

environmental works. The operation management diagram is presented in Figure 3.

Figure 3: Diagram of Operation management

Power transmission Company No.4 No.07, National Highway 52, Truong Tho

Ward, Thu Duc district, Ho Chi Minh

Western (Mien Dong) Power Transmission No.1

No. 18, Road 2A, Bien Hoa Industrial

Zone, Dong Nai province

Units under Power

transmission Company No.4

220 kV Tan Thanh Substation (12 Staff)

Ong Trinh hamlet, Tan Phuc commune, Tan

Thanh district, Ba Ria - Vung Tau province

Administration

unit

Operation unit

(including 1 safety and

environmental staff)

Security unit

Units under Western Power

Transmission No.1

6

2. Environmental Management and Monitoring Framework

2.1. Applicable Policies and Regulations

10. The substation shall comply with ADB safeguard requirements, Vietnam laws

and regulations including Vietnam’s obligations under international law.

11. The Table 3 presents the Laws and regulations have been complied with during

the operation phase.

Table 3: Application Laws and Regulations

Item Laws/Regulations Remark

I ADB Requirements

1 Safeguard Policy Statement – SPS 2009

II Vietnam Laws and regulations

1 Environmental protection Law 2014

2 Decree No. 19/2015/ND-CP of the Government detailing

the implementation of a number of articles of the law on

environmental protection.

dated 14

February 2015

3 Decree No: 38/2015/NĐ-CP of the Government on

management of waste and discarded materials.

dated 24 April

2015

4 The Decree 59/2007/NĐ-CP by the Government on solid

waste management

dated 09 April

2007

5 Circular No 36/2015/TT-BTNMT regarding hazard waste

management

dated 30 June

2015

12. The Table 4 presents the requirement during operation phase of the subproject.

7

Table 4: environmental procedures requirement

Item Requirement Regulations

I ADB Requirements

1 Prepare quarterly

environmental monitoring

reports in Operation phase

until 30 June 2016

The letter MFF 0066-VIE: Power Transmission

Investment Program Loan 2848-VIE (tranche 1)

and Loan 2959 (Tranche 2) – Quarterly

Environmental Monitoring Reports issued by

ADB dated 9 October 2015.

II Vietnam requirements

1 Apply mitigation measures

in the operation phase

subproject’s ECP

2 Hazardous waste

management

Circular No 36/2015/TT-BTNMT dated 30 June

2015 regarding hazardous waste management

2.2. Environmental Management Organizational Structure

13. Safeguard monitoring plan is implemented by both project owner (SPPMB) and

operation agency (Power transmission Company No. 4).

SPPMB’s staff: The SPPMB’s staff for environment regularly visits site and monitors the safeguard compliance of the substation during operation phase.

National Safeguard Consultant for Environment: The consultant undertake

the following specific tasks:

- Environmental Safeguard Policy Compliance Monitoring: i) Monitor

environmental safeguard policy compliance of subprojects during operation

phase; ii) Identify, monitor and report on issues related to environmental

compliance; iii) Assist SPPMB in the preparation of quarterly and completion

monitoring reports.

- Guidance and Advisory Services: i) Identify and resolve environmental issues

including complaints through the Grievance Redress Mechanism; ii) Provide

guidance and advice on environmental safeguard compliance issues; iii) Advice

on improvements for environmental safeguard compliance.

- Capacity Building Services: i) On the job training on environmental management,

occupational health and safety, community health and safety awareness; ii)

Ensure ongoing learning and development on environmental compliance,

8

management and health and safety; iii) Supervise the performance of assigned

staff on environmental management and provide clear guidance and direction in

strengthening the performance.

The Operation Agency (Power transmission Company No.4/ Western 1 (Mien

Dong) Power Transmission/220kV Tan Thanh Substation)

The operation agency assigned to environmental works are as follows:

- The safety department under power transmission Company No.4 and technical

department under Western 1 (Mien Dong) Power Transmission has general

responsibility on safety and environmental issues of all substations and

connection lines,

- The Tan Thanh Substation mobilized 1 staff for management of safety and

environmental issues.

The Figure 3 shows the safeguards management organization.

Figure 4: Diagram of safeguards monitoring and management

2.3. Operation Phase

2.3.1. Potential Impacts Identified during the IEE Preparation

14. Some environmental issues that may occur during operation phase, are

presented in Table 5.

National

Safeguard

Consultant

for

Environment

SPPMB

(Vice Director)

Compensation

Department (Environmental Staff)

Power transmission Company No.4/

Western 1 (Mien Dong) Power Transmission

No.1

Safety/Technical

Departments

(Environmental Staff)

220kV Tan Thanh Substation

(Safety and Environmental

Staff)

9

Table 5: Potential environmental issues during the operation

phase

Item Environmental

Impacts

Impact

1

Occupational

Health and

Safety

The occupational health and safety issues

inherent to the operation of transmission

line and substation include hazards due to

exposure to live power lines and high

voltage systems, working in heights and

risks of accidents, and potential exposure

to electromagnetic fields (EMF). Accidents

that may occur include electrocution, fires,

and explosion.

Exposure to Live Power Lines and High

Voltage Systems. Workers may come in contact

with live power lines during the maintenance

of the facilities and electrocution from

direct contact with high-voltage electricity

is a hazard directly related to power

transmission lines and facilities.1

Working in High Elevation. Accidents may

happen when working in high elevation.

However, a worker safety plan may be

implemented to reduce risks that include

testing of structural integrity prior to

proceeding with the work and the use of fall

protection measures.

Worker Exposure to Electromagnetic Fields

(EMF). Electric utility workers have higher

exposure to EMF than the general public

because of working in close proximity to

electric power lines. The occupational EMF

exposure should be minimized through the

implementation of an EMF safety program2

2 Community Electrocution: The community may also be

1 International Finance Corporation (IFC), Environmental, Health, and Safety Guidelines –

Electric Power Transmission and Distribution. 30 April 2007. 2 People’s Committee of Tan Thanh District

10

Health and

Safety

exposed to electrocution hazards as a result

of direct contact with high voltage

electricity or from contact with tools,

vehicles, or other devices that come in

contact with high-voltage electricity.

Exposure to EMF: The transmission frequency

commonly used in transmission systems ranges

from 50–60Hz which is considered as

extremely low frequency3, with impacts

becoming low with distance. The electric

fields become shielded by trees, buildings,

and other materials that conduct

electricity. In general, the electric fields

are strongest close to the source and

diminish with distance.

3

Management of

Hazardous

Waste

Chemicals that are commonly handled in the

transmission lines and substation are

mineral oil in transformers and other

electrical components and liquid petroleum

fuel. There are also potential hazardous

materials and oil spills associated with the

operation of equipment and

retrofitting/maintenance works.

Storage facilities of liquid petroleum fuels

for the generator sets and for vehicles and

other equipment are potential sources of

accidental spills. Oil leak or accidental

spills of hazardous materials could give

rise to contamination of soil and water.

4

Emergency

preparedness

at substation

There are several risks that could occur

with the operation of the transmission line

and substation. Among these are the

likelihood of cable being damaged, corrosion

of the towers over time which could

compromise its structural integrity,

potential fire events, explosion of

equipment, and being hit by lightning.

3 People’s Committee of Tan Thanh District

11

5

Management

and Control

of Vegetation

at

Transmission

Line

One of the regular programs to maintain the

integrity of the transmission line is the

trimming of tall trees and vegetation along

the ROW. This is being done to maintain the

necessary conductor clearance of the line.

In addition, the presence of vegetation

along the ROW provides habitat for birds.

With reduced vegetation growth along the

ROW, the risk of bird collision on the

transmission line will be prevented.

2.3.2. Environmental Mitigations and Compensation Measures

Proposed in the IEE

15. Proposed mitigation measures for the operation phase are

presented in Table 6. The effectiveness of these measures will

be the focus of future monitoring.

Table 6: Mitigation measures in operation phase

Item Negative Impact Propose mitigation measures

1

Trimming of

trees and

bushes for

maintenance of

ROW

- Burning to clear and control vegetation

along ROW will be prohibited.

- Local villagers living along routes of the TL will be invited to participate under

contract to manually cut vegetation along

ROW

- Plantation trees and crops higher than 3 m will not be allowed

- ROW checking and maintenance of ROW will be conducted every month.

- Conduct training on environmental

performance monitoring with workers and

community representatives

2

Health and

safety; injury

to workers

- Conduct training/seminar on occupational

health and safety

- Periodic health and safety training and

practice drills

- Preparation of an Emergency Preparedness

and Response Plan

- Restricting access to electrical equipment by workers only trained and certified to

work on electrical equipment

- Provision of PPE for workers, safety

measures, personal safety devices, and

12

other precautions

3 Working in

heights

- Testing of structural integrity prior to proceeding with the work

- Use of fall protection measures 4

Worker exposure

to EMF

- Identification of potential exposure

levels in the work area including surveys

of exposure levels and establishment of

safety zones

- Limit access to properly trained workers and those equipped with appropriate PPE

when entering safety zones.

- Utilization of personal monitors during

work activities

- Posting of safety signages and warning

signs.

5

Community

Health and

Safety

- Provision of signs, barriers, and

gates/posts surrounding transmission

towers particularly in built-up areas

- Signboards (Danger Warning Signs) need to be put on every tower as well as on the

conductors where crossing community

centers, roads and rivers.

- Grounding of conducting objects such as

fences or other metallic structures near

power lines.

- Conduct orientation seminar on community

health and safety programs

6

Hazardous Waste

Management

- Provision of secondary spill containment

for fuel storage facilities, areas around

substation transformers, and at

maintenance yard (See Annex 6 - pictures).

- Direct discharges contaminated with oil

from spill bunds into oil-water

separators.

- Implementation of approved disposal

options for all waste transformer oil,

equipment maintenance, residually

contaminated soils, and scrap metal.

7

Management and

Control of

Vegetation at

Transmission

line

- Access already existing roads or tracks to reach the transmission lines

- Inform locals in advance through the

village heads on the schedule of

maintenance and trimming works

- Avoid encroachment into rice or crop land of villagers.

- Do not allow the use of herbicides and

pesticides to control vegetation growth.

13

2.3.3. Monitoring Framework

16. Monitoring frameworks in operation phase is presented in

the Table 8.

Table 7: Monitoring framework in operation phase

Parameter

Location and Method

of Monitoring

Activities Monitorin

g Frequency

Responsibility

Trees and

vegetation

control

Along the

ROW

Inspect the

status of tree

and vegetation

growth that may

damage or

threaten the

integrity of the

lines.

Monthly SPPMB

Health and

safety;

injury to

workers and

villagers

Towers and

tower bases

Inspect integrity

of the towers in

order to maintain

and ensure good

condition.

Inspect Warning

Signs/Boards if

placed well on

towers and on the

line where the

connection lines

cross the gas

pipeline, roads,

and drainage

canals.

Monthly SPPMB

Substation

transformer

insulating

and cooling

oil leaks

that may

contaminate

water

courses or

soil.

Substation

site

Inspection of

leaks on

transformer,

cleanout, and

disposal of any

spilled

insulating and

cooling oils.

Weekly/Mo

nthly SPPMB

14

3. Monitoring Result

3.1. Compliance with ADB loan covenants and applicable

government laws, regulations and requirements

17. The subproject compliance with the ADB safeguard

requirements is presented in the Table 8.

Table 8: Compliance with the ADB loan covenants related to

environmental safeguard

Item Requirement Project compliance Remark

I. Preparation Phase

1 The sub-project

belongs to category B

based on project

impacts and risks. An

initial environmental

examination

(IEE) shall be

The sub-project’s IEE report was

prepared

Submitted

ADB in

November

2011

2 Inclusion of the

safeguard

requirements in

bidding documents

The provisions and

appendixes of the

bidding documents

included the

safeguard

The

Contractor

prepared a

EMPs for

bidding

3 Incorporated the

relevant provisions

from the EMP into the

Works contract

The provisions and

appendixes of the

civil works contract

included the

safeguard

4 Engaged a consultants

to support

environmental

safeguard

implementation and

A national safeguard

specialist for

environment was

mobilized in

November 2013

5 Available a budget

for all such

environmental and

social measures

A budget was

allocated for

environmental

protection

6 A written notice of

any unanticipated

environmental risk

There was no

environmental risk

during construction

phase

15

7 Applicable laws and

regulations relating

to environment,

health and safety

All related laws

and regulations

were applied during

preparation and

construction phases

8 Disclosure the final

environmental

assessment, EMP

SPPMB already

disclosed the final

environmental

assessment report

and EMP to affected

people and

stakeholders of the

project area and at

construction sites.

These documents were

published in August

2013 at Tan Phuoc

II Construction Phase

1 Periodic monitoring

report

The SPPMB prepared

and submitted the

following monitoring

report:

- Quarterly internal

monitoring report

No.1 in March,

No.2 in June, No.3

in September, No.

4 in December

2014, No.5 in

March 2015, No.6

in June 2015 ;

- Semi-annual report

No.1 in June 2014

III Operation Phase

1 Prepare quarterly

environmental

monitoring reports

The SPPMB prepared

and submitted

monitoring report

No.7 in October 2015

16

18. The subproject compliance with the Vietnam regulations on

environmental protection is presented in the Table 9.

Table 9: Compliance with Vietnam regulations on environmental

protection

Item Requirement Project compliance Remark

I. Preparation Phase

1 Preparation EPC The subproject’s EPC prepared in March

2008.

Tan Thanh

district People

Committee

issued approval

letter No

418/UBND-TNMT

dated April 08,

2008

II. Construction Phase

1 Implementation of

the mitigation

measures in the

EPC

Mitigation measures

were undertaken by

the Contractor in

construction phase

III Operation Phase

1 Implementation of

the mitigation

measures in the

EPC for the

operation phase

Mitigation measures

are being undertaken

by the operation

agency (Refer to

Table 11).

2 Hazardous waste

management

The profile of

hazardous wastes

generated are being

reviewed by Ba Ria – Vung Tau Natural

Resources and

Environmental

Department. The types

and quantities of

hazardous waste

generated are

presented in the

Annex 5 - Hazardous

documents issued by

Baria-Vung Tau

Natural Resources and

Environment

Department.

17

3.2. Environmental Monitoring Program

19. The environmental monitoring program undertaken by the

SPPMB and operation agency during operation phase is presented

in Table 10. The environmental monitoring is consistent with

the proposed programme in the IEE of this subproject.

Table 10: Monitoring programme

Environmental issues

Monitoring

Location Activities

Monitoring Frequency

Operation agency (Power

transmission

N0.4/Mien Dong

1/ substation)

SPPMB

Trees and

vegetation

control

Along

the ROW

Inspect the

status of tree

and vegetation

growth that may

damage or

threaten the

integrity of the

lines.

Monthly Monthl

y

Health and

safety;

injury to

workers

and

villagers

Towers

and

tower

bases

- Inspect integrity of the

towers in order

to maintain and

ensure good

condition.

- Inspect Warning

Signs/Boards if

placed well on

towers and on

the line where

the connection

lines cross the

gas pipeline,

roads, and

drainage canals.

Daily Monthl

y

Substation

transforme

r

insulating

and

cooling

oil leaks

Substati

on site

Inspection of

leaks on

transformer,

cleanout, and

disposal of any

spilled

insulating and

cooling oils.

Daily Monthl

y

18

3.3. Environment compliance at the substation

20. The Table 11 shows the implemented mitigation measures on

safety and environment during operation phase.

Table 11: Summary of environmental compliance activities

Location/Time

Negative Impact

Implemented mitigation measures

Implementation Agency

ROW of the

220kV and

110kV

connection

lines

Trimming of

trees - No trimming of tree

Mien Dong 1

Power

Transmission/T

an Thanh

substation

- Connection lines;

- Substation

Health and

safety;

injury to

workers

- Conducted training

courses on occupational

health and safety for

all the substation’s staff at Colleague of Ho

Chi Minh Trade Union,

Lot 7- Thanh Da block,

27 ward, Binh Thanh

district, Ho Chi Minh

city

- Quarterly health and

safety training and

practice drills at the

substation;

- Prepared an Emergency

Preparedness and

Response Plan issued by

Power transmission N0.4

at No. 004564/KH-PTC4

dated 08 June 2015 and

Mien Dong 1 Power

Transmission at No.

3298/KH-TTĐMĐ1-KT dated

22 June 2015

- Restricted areas access

including battery room,

transformer areas, 110kW

and 220kV switchgear

areas to electrical

equipment by workers

only trained and

certified to work on

electrical equipment

- Provision of PPE for

workers, safety

- Power transmission

Company No.4;

- Mien Dong 1

Power

Transmission;

- Tan Thanh

substation

19

measures, personal

safety devices, and

other precautions

- Prepared fire prevention plan and approved by Ba

Ria – Vung Tau fire

department

- Connection lines;

- Substation

Working in

heights

- Survey the working site

and prepare working

method, safety plan,

- Register for electric

cut off, and handover as

regulations,

- Testing of structural

integrity prior to

proceeding with the

work,

- Use of fall protection

measures such as safety

belt, falling prevention

measure.

- Mien Dong 1

Power

Transmission;

- Tan Thanh

substation

- Connection lines;

- Substation

Worker

exposure to

EMF

- Undertake identification

of potential exposure

levels in the work area

and prepared map of

exposure levels area and

safety zones (Refer to

the Annex 3 - map of

exposure levels and

safety zones and Annex 4

- Monitoring Result of

Electric Field).

- Limit access to properly trained workers and

those equipped with

appropriate PPE when

entering safety zones.

- Posting of safety

signages and warning

signs (Refer to the

Annex 6 - Pictures).

- Power transmission

Company No.4;

- Mien Dong 1

Power

Transmission;

- Tan Thanh

substation

- Connection lines;

- Outside the

substation

Community

Health and

Safety

Regularly check land

subsidence of

transmission towers

Regularly maintained

drainage system.

Provided signs, barriers,

and gates/posts

- Mien Dong 1

Power

Transmission;

- Tan Thanh

substation

20

surrounding transmission

towers particularly

- Put Signboards (Danger

Warning Signs) on every

tower (Refer to the

Annex 6 – Pictures). - Grounding of conducting

objects such as fences

or other metallic

structures near power

lines.

- The substation

Hazardous

Waste

Management

- The documents related to hazardous waste

management reviewed by

Ba Ria – Vung Tau

Natural Resources and

Environment 13-11-2015

(Refer annex 5 -

Hazardous documents

issued by Baria-Vung Tau

Natural Resources and

Environment Department).

- Provided secondary spill containment for fuel

storage facilities,

areas around substation

transformers, and at

maintenance yard.

- Domestic waste is being

collected and treated by

Tan Thanh urban services

Joint Stock Company

- Power transmission

Company No.4;

- Mien Dong 1

Power

Transmission;

- Tan Thanh

substation

- Connection lines

Management

and Control

of

Vegetation

at

Transmission

line

- Reached to the

transmission lines by

already existing roads

- Informed to community

the schedule of

maintenance and trimming

works

- No encroachment into

rice or crop land of

villagers.

- No use of herbicides and pesticides to control

vegetation growth.

- Mien Dong 1

Power

Transmission;

- Tan Thanh

substation

21

3.4. Effectiveness of mitigation measures

21. Mitigation compliance and effectiveness can be described in

qualitative terms or be evaluated based on a ranking system.

Table 12 presents an analysis of the effectiveness of the

mitigation measures.

Table 12: Mitigation compliance and effectiveness

Mitigation Measures

Compliance Effectiveness

Rating Reason Rating Reason

Trimming of

trees

2 Regularly

inspection,

No trees need to

be cut off

2 No negative

impact to

subproject

operation

Health and

safety; injury

to workers

2 Provided

necessary first-

aid kits for

workers

2 No negative

impact to

worker

Working in

heights

2 Provided

protective

equipment

2 No negative

impact to

worker

Worker

exposure to

EMF

2 Identified and

prepared map of

exposure levels

(refer the annex

3 - Map of

exposure levels

and Safety

Zones).

2 No negative

impact to

worker

Community

Health and

Safety

2 Implemented

measures to

protect community

health and safety

2 No complaint

from local

people

Hazardous

Waste

Management

2 Hazardous waste

documents

reviewed by

functional agency

2 completed the

hazardous

waste

documents

Management and

Control of

Vegetation at

Transmission

line

2 Implemented

measures to

control

vegetation

2 No complaint

from local

people

Note:

1. Very Good 2. Good 3. Fair

4. Poor 5. Very Poor

22

ANNEX 1 - List of Fire Protection Equipments

Item Equipments Unit Quantity

1 CO2 fire extinguisher, 5kg Unit 20

2 CO2 fire extinguisher, 30kg Unit 6

3 Foam fire extinguisher, 5 kg Unit 9

4 Shovel Unit 17

5 Bamboo ladder, 5m Unit 3

6 A aluminum ladder, 3m Unit 1

7 Insulated ladder, 8m Unit 1

8 Bucket, 10-15litter Unit 4

9 Fire regulations Unit 2

10 Fire equipment frame Unit 19

11 Cask, 200 litter Unit 17

12 Black sand m3 8.5

13 Water tank for fire and fighting prevention Unit 2

14 Fire and fighting diagram Unit 1

15 Command statement board Unit 4

23

ANNEX 2: List of labour safety equipment

Item Equipment Specification Unit Quantity

1

All kind of

warning

signs

Size and content comply

with Decision No.

1559EVN-KTAT of ENV

dated 21 October 1999

Unit 30

2

Voltage

tester

110kV

Working voltage: 66kVAC

to 132kVAC

Working frequency: 50Hz

Unit

1

3

Voltage

tester 6-

35kV

Working voltage: 12kVAC

36kVAC Working

frequency: 50Hz

Unit

1

4 Insulating

stick 110kV

Material: Fiberglass

Working voltage: up to

10kVVAC;

Total length: 3,6¸3,7m;

Diameter: 32mm ±5%

Unit

1

5 Pole

grounding

Material: fiberglass

Working voltage: up to

110kV Ac.

Total length: 2,4m -

2,6m;

Diameter: 32mm± 5%;

Weigh: ≤5 kG

Unit

1

6 Insulating

gloves

Material: rubber;

Voltage: 15KV Pair 4

7 Insulation

boots

Material: rubber;

Voltage: 15KV Pair 2

9 Protective

goggles

100% eye protected,

prevent dust

Unit 4

10 Gas mask Material: rubber Unit 2

11 Face mask Unit 20

12 Safety belt

Unit 4

13 Protective

clothing Set 14

14 Protective

shoes size from 38 to 42 Pair 14

15 Safety hat

Material: HDPE,

Standard: TCVN 6407-

1998, TCVN 6407-1998

Unit

14

16 Caves rain

coat Length: 1,2 m

Unit 14

17 caves

gloves 100% cotton Pair 10

24

Item Equipment Specification Unit Quantity

18 Low voltage

tester

Voltage from 12V to

250V AC-DC

Insulation: 1000V

Unit 14

19 Safety

fence Set 2

20

Grease-

resistant

rubber

gloves

Length: 30 cm

Pair 2

21

Grease-

resistant

rubber

boots

Length: over 30 cm

Pair

2

22 Rainy boots

Pair 5

23 Insulated

mat

Material: rubber

Electrical insulation:

>=40kV,

Thick: >=5mm,

Size: >=0.8x1m

Unit 1

25

ANNEX 3: Map of exposure levels and Safety Zones

231

231-2

231-1

231-15

231-3

231-35

212-2

212-25

212-24

232-3

232-38

232-35

232-1

232-15

232-2 271-2

271-7

271-76

271-75

231-38

212-1

212-14

212-15

271-1

271-15

233-2

233-1

233-15

272-2

272-1

272-15

273-2

273-1

273-15

274-2

274-1

274-15

275-2

275-1

275-15

276-2

276-1

276-15

233-3

233-38

233-35

C22

C21

TUC21

TUC22

CS2AT1

CSC22

CSC21

272-7

272-76

272-75

273-7

273-76

273-75

274-7

274-76

274-75

275-7

275-76

275-75

276-7

276-76

276-75

CS2AT3

441-3

441-35

441-38

441

CS1AT1 CS4AT1TU4AT1

AT1

CSTD41

TD41

Ð?N T? AC

CS2AT2

442-3

442-35

442-38

442

CS1AT2 CS4AT2TU4AT2

CSTD42

TD42

Ð?N T? AC

Ð?N PHÍA 22kVT? I T? DÙNG TÝ ÕNG LAI

AT3

171-75

171-76

171-7

171

171-2

171-15

171-1

172-75

172-76

172-7

172-2

172-15

172-1

173-75

173-76

173-7

173-2

173-15

173-1

174-75

174-76

174-7

174-2

174-15

174-1

175-75

175-76

175-7

175-2

175-15

175-1

176-75

176-76

176-7

176-2

176-15

176-1

177-75

177-76

177-7

177-2

177-15

177-1

178-75

178-76

178-7

178-2

178-15

178-1

112-2

112-25

112-24

112-1

112-14

112-15CSC12

CSC11

131-35

131-38

131-3

131-2

131-15

131-1

132-35

132-38

132-3

132-2

132-15

132-1

133-35

133-38

133-3

133-2

133-15

133-1

AT2

C11

C12

TUC12

TUC11

TI 231 TI 212 TI 232 TI 271 TI 272 TI 273 TI 274 TI 275 TI 276TI 233

TI 171 TI 172 TI 173 TI 174 TI 175 TI 176 TI 177 TI 178 TI 112 TI 131 TI 132 TI 133

212 232 271 233 272 273 274 275 276

172 173 174 175 176 177 178 112 131 132 133

26

ANNEX 4: Monitoring Result of Electric Field

Power Transmission No.1 and Tan Thanh substation undertaken

monitoring of electric field on 04 December 2015. The monitoring

results are as follow:

Item Location Result

1 Operation zone 0.269 (Kv/m)

2 Security house area 0.750(Kv/m)

3 Vocational house area 0.325(Kv/m)

4 Disconnector zone 220kV (from 231

to 271)

11.50(Kv/m)

5 Disconnector zone 220kV (from 273

to 276)

11.16(Kv/m)

6 Disconnector zone 110kV (from 171

to 178)

4.41(Kv/m)

7 Disconnector zone 110kV (from 112

to 132)

4.67(Kv/m)

8 AT1 transformer zone 4.48(Kv/m)

9 AT2 transformer zone 4.46 (Kv/m)

27

28

ANNEX 5: Hazardous documents issued by Baria-Vung Tau Natural Resources and Environment Department

Baria – Vung Tau Natural Resources and Environment Department

issued a Registration of Hazardous Waste Generators for

discharge sources of 220kV Tan Thanh substation (CS1) and 500kV

Phu My substation (CS2) under management of Western (Mien Dong)

Power Transmission No.1 dated 13 November 2015 with Code of

QLCTNH:77.000372T. Types and quantity of hazardous waste are as

follow:

Item Name of Wastes

Status (state) of normal

existence

Quantity (Kg/year)

HW Code

1 Waste paint residues, paint and

varnish containing organic

solvents or other hazardous

components

Solid/Liquid 5 08 01 01

2 Waste print cartridge containing

hazardous constituents

Solid 4 08 02 04

3 Waste fluorescent and other

activated glass

Solid 6 16 01 06

4 Waste equipment, electronic

components or electrical

equipment (other than the types

referred to in code16 01 06 16 01

07 16 01 12) with electronic

components (except for the

electrical board not containing

details of hazardous components

exceeding HW threshold)

Solid 80 16 01 13

5 Waste mineral-based inorganic

chlorinated insulating and

heating oil

Liquid 100 17 03 03

6 Waste rigid metal packaging

including pressure containing

vessels ensured empty completely

Solid 30 18 01 02

7 Waste absorbents, filtering

materials (including oil

filtering materials not mentioned

in other codes), cloth,

protective fabric contaminated

with hazardous constituents

Solid 200 18 02 01

8 Waste batteries and lead

accumulators

Solid 70 19 06 01

Total 494 kg

29

30

31

32

ANNEX 6: Pictures

Hazardous waste storage house and secondary spill containment

with label and warning signs

33

Secondary spill containment with label and warning signs at

towers

Health and safety training and practice drills at the substation

Fire prevention system