Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
ELG 4126 – DGDSustainable Electrical Power Systems
Winter 2015
DGD Introduction
• TA: Viktar Tatsiankou (PhD student)
• e-mail: [email protected]
• Objectives of the DGD:– to teach students the economics of the distributed
energy generation
– to assist students with the background information for case studies
– to learn!
• The DGD is worth 15% of the course
• There will be 2 or 3 quizzes based on the DGD material, unannounced!
DGD - ELG 4126 2January 26, 2015
Review from last DGD
• Distributed resources– Distributed generation
– Grid resources
– Demand-side resources
• Electric utility rate structure
– Standard residential rates
– Residential time-of-use (TOU) rates
– Demand charges
– Demand charges with a ratchet adjustment
– Load factor
– Real-time pricing
DGD - ELG 4126 3January 26, 2015
Distributed generation
• Generation of electric power by a variety of small-scale producers (up to 50 MW) located close to the point of use
• Examples:
– Wind turbines
– Solar farms
– Fuel cells
– Mini-hydro
DGD - ELG 4126 4January 26, 2015
Standard residential rates
• Example of standard residential electric rate
• This is an inverted block rate structure (designed to discourage excessive consumption)
DGD - ELG 4126 5
Power is measured in W or J/sEnergy is measured in J or W·s
1 J = 2.78 x 10-7 kW·h1 kW·h = 3.60 x 106 J
Table 1. Example of the standard residential rates
January 26, 2015
Residential time-of-use rates
• Example of residential time-of-use (TOU) rates
• Implemented to shift the customers loads away from the daily energy peak
• A solar installation generation well coincides with the summer energy demand peak
DGD - ELG 4126 6
Table 2. Example of the time of use rates
January 26, 2015
Demand charges
• Usually applies to industrial or commercial entities
• Based on the highest (typically monthly) power drawn (averaged over a 15 min period)
• For example, if the peak power draw is 100 kW over 15 min in June, demand charges are $900 for that month.
DGD - ELG 4126 7
Table 3. Example of the demand charges
January 26, 2015
Demand charges with a ratchet adjustment
• Problem with demand charges
– Monetary significant for one month of the year
– No sufficient for the utility to pay for the peaking power plant they had to build to supply the load
• Solution is to implement a ratchet adjustment into the demand charges
• Benefits
– Huge penalties for customers who add a few kWh to their load right at their annual peak
– Gives incentive for customers to reduce their annual peak energy demand
DGD - ELG 4126 8January 26, 2015
Load factor
• Ratio of a customer’s average power demand to its peak demand
• Useful way for utilities to characterize the cost of providing power to the customer
• For example, a customer with a hourly peak demand of 200 kW that uses 876,000 kWh/yr would have a load factor for 50%.
1 year = 365 days x 24 hr = 8760 hr/yr
Average power = 876,000 kWh/yr / 8760 hr/yr = 100 kW
DGD - ELG 4126 9January 26, 2015
Real-time pricing (RTP)
• Time-of-use (TOU) rates are crude mechanisms that attempt to capture the true cost of utility service.
• TOU rates use large time blocks and have only two seasons
• RTP on other hand offers pricing schemes as:
– one-day-ahead
– hour-by-hour
– real-time pricing
• RTP allows utilities to charge customers the true cost of energy generation and distribution.
DGD - ELG 4126 10January 26, 2015
Energy Economics – DGD 2
DGD - ELG 4126
Outline for today’s DGD
• Energy economics– Simple payback period
– Initial rate of return
– Net present value
– Internal rate of return
– Net present value and internal rate of return with fuel escalation
– Annualizing the investment
– Levelized bus-bar costs
DGD - ELG 4126 12January 26, 2015
Simple payback period
• The simplest way to evaluate the economic value of a project.
• For example, an energy-efficient air conditioner that costs an extra $1000 and saves $200/year in electricity, would have a simple payback of 5 years.
• But what if the air conditioner malfunctions in 3 years?
• Rarely used because it does not include any information about the longevity of a project.
DGD - ELG 4126 13January 26, 2015
Initial (simple) rate of return
• The initial rate of return is the inverse of the simple payback period.
• For example, if an efficiency investment with a 20% initial rate of return, which sounds very good, lasts only 5 years, then just as the device finally pays for itself, it dies and the investor has earned nothing.
• Usually used as a “minimum threshold” indicator.
DGD - ELG 4126 14January 26, 2015
Net present value (NPV) 1
• In general, $1 today is not the same as $1 in 10 years. Why?
• So if an investment P earns an interest i, after one year, you will have F = P + i×P or P×(1+i). Analogously, after two years, you will have F = P×(1+i) 2 and so on F = P×(1+i) n .
• Typically, in the context of energy economics an interest irefers to a discount rate d.
• It can be thought of as the interest rate that you could have earned if you would have invested the money into an alternative investment.
DGD - ELG 4126 15January 26, 2015
NPV 2
• Typically, an energy efficiency investment results in a stream of annual cash flows A, for n years, at some discount rate d.
• What is the present worth P of an energy efficiency investment based on this information?
DGD - ELG 4126 16January 26, 2015
NPV 3
• For example, say you save $100/yr by installing the energy efficient lighting in your home. In 10 years this is equivalent to $1000, future worth. The question is “What is the present worth of this investment?” with discount d.
• If d = 1%, P = $100/yr × 9.47 yr = $947
• If d = 30%, P = $100/yr × 3.09 yr = $309
• So if d = 30%, would it make sense to spend $500 on installing the energy efficient lighting?
DGD - ELG 4126 17January 26, 2015
Example 1
Two 100-hp electric motors are being considered—call them
“good” and “premium.” The good motor draws 79 kW and costs
$2400; the premium motor draws 77.5 kW and costs $2900. The
motors run 1600 hours per year with electricity costing
$0.08/kWh. Over a 20-year life, find the net present value of the
cheaper alternative when a discount rate of 10% is assumed.
We know that
• d = 10%
• n = 20 years
• A = Power consumption × Operation hrs × Electricity cost
DGD - ELG 4126 18January 26, 2015
Example 1 (Solution)
The annual electricity cost for the two motors is
A(good) = 79 kW × 1600 hr/yr × $0.08/kWh = $10,112/yr
A(premium) = 77.5 kW× 1600 hr/yr × $0.08/kWh = $9920/yr
The present value factor for these 20-year cash flows with a 10%
discount rate is
The present value of the two motors, including first cost and
annual costs, is therefore
P(good) = $2400 + 8.5136 yr × $10,112/yr = $88,489
P(premium) = $2900 + 8.5136 yr × $9920/yr = $87,354
DGD - ELG 4126 19January 26, 2015
Example 1 (Solution)
The premium motor is the better investment with a net present
value of
NPV = $88,489 − $87,354 = $1,135
or alternative solution is:
DGD - ELG 4126 20January 26, 2015
Internal rate of return (IRR) 1
• IRR is the discount rate d which makes the NPV equal to zero
• IRR is the most persuasive measure of the value of an energy-efficiency project
DGD - ELG 4126 21January 26, 2015
Internal rate of return (IRR) 2
DGD - ELG 4126 22January 26, 2015
Table 1. Present value functions to help estimate the IRR
Internal rate of return (IRR) 3
DGD - ELG 4126 23January 26, 2015
Internal rate of return (IRR) 4
DGD - ELG 4126 24January 26, 2015
Table 1. Present value functions to help estimate the IRR
NPV and IRR with fuel escalation 1
• We must take into the account the rising cost of fuel.
• Add the 1+e term to the PVF function as shown, where e is the fuel escalation rate.
• $1 of fuel today, costs $1×(1+e) in 1 year, costs $1×(1+e)×(1+e) in year 2, costs $1×(1+e)n in year n.
DGD - ELG 4126 25January 26, 2015
NPV and IRR with fuel escalation 2
DGD - ELG 4126 26January 26, 2015
Example 1
The premium motor in Example 1 costs an extra $500 and
saves $192/yr at today’s price of electricity. If electricity
rises at an annual rate of 5%, find the net present value
of the premium motor if the best alternative
investment earns 10%.
Solution:
The equivalent discount rate with fuel escalation is
DGD - ELG 4126 27January 26, 2015
Example 1 (Solution)
The present value function for 20 years of escalating
savings is
The net present value is
Without fuel escalation, the net present value of the
premium motor was only $1135 (from Example 1).
DGD - ELG 4126 28January 26, 2015
Annualizing the investment
• In most cases the extra capital required for an energy-efficiency project must be borrowed.
DGD - ELG 4126 29January 26, 2015
Example 2
A 3-kW photovoltaic system, which operates with a
capacity factor (CF) of 0.25, costs $10,000 to install.
There are no annual costs associated with the system
other than the payments on a 6%, 20-year loan. Find the
cost of electricity generated by the system (¢/kWh).
Solution:
The capital recovery factor in this case is 0.0872/yr.
DGD - ELG 4126 30January 26, 2015
Example 2 (Solution)
DGD - ELG 4126 31January 26, 2015
Table 2. Capital recovery factors as a function of interest rate and load
Example 2 (Solution)
The annual payments for the loan are
The actual energy generated by the PV systems is
The cost PV electricity is
DGD - ELG 4126 32January 26, 2015
Levelized bus-bar costs 1
• There are two key components to the cost of electricity for a power plant:
– Up-front fixed cost to build the power plant
– Assortment of costs incurred in the future
• Operation and maintenance (O&M)
• Fuel escalation
• The ratio of the equivalent annual cost ($/yr) to the annual electricity generated (kWh/yr) is called the levelized, bus-bar cost of power:
DGD - ELG 4126 33January 26, 2015
Levelized bus-bar costs 2
• Converts all of the costs into a series of equal annual amounts.
DGD - ELG 4126 34January 26, 2015
Levelized bus-bar costs 3
• Converts all of the costs into a series of equal annual amounts.
DGD - ELG 4126 35January 26, 2015
Levelized bus-bar costs 4
DGD - ELG 4126 36January 26, 2015
Levelized bus-bar costs 5
DGD - ELG 4126 37January 26, 2015
+
= Levelized Bus-Bar Cost
Example 3
A microturbine has the following characteristics:
– Plant cost = $850/kW
– Heat rate = 12,500 Btu/kWh
– Capacity factor = 0.70
– Initial fuel cost = $4.00/106 Btu
– Variable O&M cost = $0.002/kWh
– Fixed charge rate = 0.12/yr
– Owner discount rate = 0.10/yr
– Annual cost escalation rate = 0.06/yr
Find its levelized ($/kWh) cost of electricity over a 20-
year lifetime.
DGD - ELG 4126 38January 26, 2015
Example 4 (Solution)
The levelized fixed cost is
The initial annual cost for fuel and O&M is
This needs to be levelized to account for inflation. The
inflation adjusted discount rate d would be
DGD - ELG 4126 39January 26, 2015
Example 4 (Solution)
The levelizing factor for annual costs is
The levelized annual cost is therefore
This needs to be levelized to account for inflation. The
The levelized fixed plus annual cost is
DGD - ELG 4126 40January 26, 2015
Questions
DGD - ELG 4126