34
10/29/2015 © Sargent & Lundy, L.L.C. 2015 Steam Electric Effluent Limitations Guidelines (ELG) Thank you for joining our presentation! Our phone is currently muted Please check to ensure your volume is turned up Please submit questions via the chat window, participant phones are muted to avoid noise disturbances Today’s presentation will be available for download on S&L’s website www.sargentlundy.com Sargent & Lundy’s detailed summary of the ELG rule is also available for download on our website 1 Sargent & Lundy Webinar

Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

Steam Electric Effluent Limitations Guidelines (ELG)

• Thank you for joining our presentation!• Our phone is currently muted• Please check to ensure your volume is turned up• Please submit questions via the chat window, participant

phones are muted to avoid noise disturbances• Today’s presentation will be available for download on S&L’s

website www.sargentlundy.com• Sargent & Lundy’s detailed summary of the ELG rule is also

available for download on our website

1

Sargent & Lundy Webinar

Page 2: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

Steam Electric Effluent Limitations Guidelines (ELG)

2

Page 3: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

PanelistsKen Snell – manager of environmental regulatory and permitting group

Matthew Heermann – wastewater treatment technology specialist

Ed Wolfington – manager of material handling group and technology specialist

Darrel Packard – manager of civil design group and civil engineering specialist

3

Sargent & Lundy Webinar

PresenterAndy Carstens – director of environmental services

Page 4: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

Today’s presentation will focus on the following:

Agenda

4

Overview of ELG Rule

Compliance Strategies

ApplicabilityRegulated StreamsKey Definitions and ProvisionsImplementation

Technologies Minimizing Wet FGD WastewaterProject Requirements (Schedule, Costs)Other Considerations

Page 5: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

5

Page 6: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

6

§ 423.10 Applicability ( to ) 1982 2015

Page 7: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

7

Today’s discussion is limited to standards for:

“Existing” coal-fired plants >50MW

Page 8: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 8

Surface Water or POTW

Cooling Tower Blowdown

Once-Through Cooling Water

Coal Pile Runoff

Ash Pond

Metal Cleaning Wastewaters

Low Volume Wastes (LVW)

CCR Leachate

ELG Rule Overview

Regulated Waste Streams (1982)

Wet FGDBoiler

Air Heater

ESP

Fly Ash Transport Water

Bottom Ash Transport Water

FGD Wastewater

Drains

Boiler Blowdown

Streams w/No ELG Limit

Page 9: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

CCR Leachate

9

Surface Water or POTW

Cooling Tower Blowdown

Once-Through Cooling Water

Coal Pile Runoff

Ash Pond

Metal Cleaning Wastewaters

Low Volume Wastes (LVW)

CCR Leachate

ELG Rule Overview

Regulated Waste Streams (2015)

Wet FGDBoiler

Air Heater

ESP

Fly Ash Transport Water

Bottom Ash Transport Water

FGD Wastewater

Drains

Boiler Blowdown

Streams w/No ELG Limit

FGD Wastewater

Activated Carbon

Baghouse

Flue Gas Mercury Control

Page 10: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

10

Standards for Existing Units >50MW

Stream Existing Unit Standards (>50MW) Technology BasisFly Ash Transport Water Zero-Discharge Dry Ash Handling

FGMC Wastewater Zero-Discharge Dry Ash Handling

Bottom Ash Transport Water Zero-Discharge Dry Ash Handling

or 100% Recycle

FGD Wastewater

As – Daily Max < 11 ug/L, 30-day Avg < 8 ug/L

Hg – Daily Max < 788 ng/L, 30-day Avg < 356 ng/L

Se – Daily Max < 23 ug/L, 30-day Avg < 12 ug/L

N – Daily Max < 17 mg/L, 30-day Avg < 4.4 mg/L

Physical / Chemical and

Biological Treatment

Combustion Residual Leachate Same as current Low-Volume Waste Standards Impoundment

Page 11: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

11

Definition of Transport Water

ANDTransport Water

Used to convey fly, bottom, or economizer ash

Contacts fly, bottom, or economizer ash

Cyclone boiler cooling water to slag tanks overflows to separate outfall. Does contact bottom ash, but is not used to convey the ash. This is not transport water because it does not satisfy both criteria.

Example:

Page 12: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

12

Anti-Circumvention Provisions

Fly Ash Transport Water

Bottom Ash Transport Water

Flue Gas Mercury Control

Wet Wet FGD

FGD Wastewater

Any Plant Process that Discharges

Not Allowed

Allowed

Page 13: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

13

Anti-Circumvention Provisions

Low Volume Waste

Wet Wet FGD

FGD Wastewater

< 4 ug/L

< 178 ng/L

< 6 ug/L

< 2.2 mg/L

< 8 ug/L

< 356 ng/L

< 12 ug/L

< 4.4 mg/L

< DL

< 89 ng/L

< 3 ug/L

< 1.1 mg/L

As

Hg

Se

N

No Dilution

Diluted Stream

Any 1 below DL

*DL – Detectable Limit

AllowedNot

Allowed

Page 14: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

ELG Rule Overview

14

Implementation through NPDES Permits

• ASAP considers time, other plant changes, optimization (FGD only)• ASAP date can be different for different streams• If FGD wastewater evaporated, ASAP date is not applicable

Page 15: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

Today’s presentation will focus on the following:

Complying with ELG

15

Overview of ELG Rule

Compliance Strategies

ApplicabilityRegulated StreamsKey Definitions and ProvisionsImplementation

Technologies Minimizing Wet FGD WastewaterProject Requirements (Schedule, Costs)Other Considerations

Page 16: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 16

Complying with ELG

Planning for Compliance

Page 17: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 17

Surface Water or POTW

Ash Pond

Complying with ELG

Biggest Impacts to Coal-Fired Units

Wet FGDBoiler

Air Heater

ESP

Fly Ash Transport Water

Bottom Ash Transport Water

FGD Wastewater

Page 18: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 19

Complying with ELG

Technologies – General Format for Following Slides

Other Information• Other Relevant Information

Simplified Process Flow Diagrams

Example schedules from recent projects (note: schedules vary for each project, schedules

shown represent a single example)

Example cost estimates from recent projects (note: costs vary for each project, costs shown

represent a single example)

Page 19: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 20

Complying with ELG

Bottom Ash – Dry Belt Conveyor

Example cost for single 400 MW

Total Installed Cost ~$18 Million

Other Information• Need sufficient room under boiler• Longer outage required for installation• Cooling air recovers some heat back to the

boiler

Page 20: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 21

Complying with ELG

Bottom Ash – Submerged Scraper Conveyor

Example cost for single 450 MW unit

Total Installed Cost ~$13 Million

Other Information• Need sufficient room under boiler• Longer outage required for installation

Page 21: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 22

Complying with ELG

Bottom Ash – Remote Submerged Scraper Conveyor

Example cost for single 450 MW unit

Total Installed Cost ~$18 million

Other Information• Flexibility with location• Minimal outage time required• Larger, higher capital than under-boiler SSC

Page 22: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 23

Complying with ELG

Bottom Ash – Self-supporting Concrete Basins

Other Information• Minimal outage time required• Larger footprint required

Example cost for single 450 MW unit

Total Installed Cost ~$17 million

Page 23: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 24

Complying with ELG

Strategies to Minimize FGD Wastewater

• Dry Sorbent Injection

• Alternate FGD Liners

• Produce less wall-board grade byproduct

• Burn lower chloride fuels

• Reverse Osmosis

Page 24: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 25

Complying with ELG

FGD Wastewater – Physical / Chemical Treatment

Other Information• Established technology• Can meet Hg and As limits• Must be used with biological for Se and N

limits

Example cost for two 550 MW units

Total Installed Cost ~$10 million

Page 25: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 26

Complying with ELG

FGD Wastewater – Biological Treatment

Other Information• Only a few in operation• Few suppliers available

Example cost for two 550 MW units

Total Installed Cost ~$19 million

Page 26: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 27

Complying with ELG

FGD Wastewater – Brine Concentration / Evaporation

Other Information• High capital - materials• High O&M• Demonstrated on Wet FGD wastewater in a

few applications

Example cost for single 950 MW unit

Total Installed Cost ~$70 million

Page 27: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 28

Complying with ELG

FGD Wastewater – Waste Fixation and Stabilization

Example Cost for Two 450 MW Units

Total Installed Cost ~$35 million

Other Information• May still achieve “zero discharge”• Requires testing to determine “recipe” for

chemically fixated and structurally stable product

Page 28: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 29

Complying with ELG

Developing Technologies

Spray Dryer Evaporation

Forward Osmosis

Zero Valent Iron

Page 29: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 30

Surface Water or POTW

Ash Pond

Metal Cleaning Wastewaters

Low Volume Wastes (LVW)

Complying with ELG

Impacts of Coal Combustion Residual (CCR) Rule

Drains

Boiler Blowdown

Streams w/No ELG Limit

CCR ponds can be used as long as they cease receiving transport water by the compliance date

“Legacy wastewater” can be discharged, but CCR material within causes CCR rule to be applicable

If pond closure required due to CCR, streams routed to ponds must be recycled, re-routed, and / or treated

Page 30: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 31

Complying with ELG

Compliance Planning

Page 31: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

Complying with ELG

32

Compliance Planning

Technology Implementation ~18 to 24 months

Begin compliance planning now

Page 32: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015 33

Additional Questions ?

Selected Sargent & Lundy  Services to Support Compliance Planning through ImplementationWater Balance Preparation 

Wastewater Flow and Characterization  Compliance Planning and Economic Modeling 

Equipment Design Basis, Specification Preparation, and Procurement Support  Detailed Design for Balance‐of‐Plant Integration 

Project Management and Oversight  Permit Application Preparation and Support (NPDES, Section 401/404, State Permits, etc.) 

CCR Fugitive Dust Plan Preparation  Impoundment Safety Hazard Analyses

Groundwater Monitoring Plans and Well Installation Support  CCR Impoundment Location Assessments

CCR Impoundment Safety and Hazard Potential Assessments  CCR Impoundment Inspection Plans CCR Closure and Post‐Closure Plans 

Page 33: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

Thanks for AttendingIf you have any further questions about this topic or other environmental support, please contact:

Andy Carstens – Director of Environmental Services

Ken Snell – Manager of Permitting and Licensing

34

(312) [email protected]

(312) [email protected]

Page 34: Steam Electric Effluent Limitations Guidelines (ELG) · Today’s presentation will focus on the following: Complying with ELG 15 Overview of ELG Rule Compliance Strategies Applicability

10/29/2015 © Sargent & Lundy, L.L.C. 2015

The information provided by Sargent & Lundy ("S&L") in this presentation is intended to provide general information on a particular topic and is not intended to be asubstitute for a discussion, consultation, or advice with an appropriate professional. There are no express or implied representations or warranties related to the informationpresented or contained in any presentation materials, nor is there any guarantee that the information is error-free, or that it meets any sort of performance or qualitycriteria. In no event shall S&L be held liable to any party for any direct, indirect, implied, punitive, special, incidental or other consequential damages arising directly orindirectly from any use of this information and material, which is provided as is. S&L, it affiliates, officers, and employees, shall not be liable for any decision made or actiontaken in reliance on the information provided. The materials provided are owned by S&L and may only be used for personal or internal use, and may not be copied,redistributed, or otherwise provided to third parties without the express written authorization of S&L