Electrical System Studies for Large Projects Executed at Multiple Engineering Centres

  • Upload
    gtgreat

  • View
    38

  • Download
    0

Embed Size (px)

DESCRIPTION

Electrical System Studies for Large Projects Executed at Multiple Engineering Centres

Citation preview

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    2009 Bechtel Corporation. All rights reserved.

    INTRODUCTION

    Electrical system studies are carried out toverify that major electrical equipment isadequately rated, determine the conditions

    for satisfactory and reliable operation, and

    highlight any operational restrictions required

    for safe operation.

    The various units within the Jamnagar Export

    Refinery Project (JERP) were engineered at

    Bechtel engineering centres (London, Houston,

    Frederick, Toronto, and New Delhi), the Bechtel/

    Reliance Industries Limited joint venture (JV)

    office in Mumbai, and the sites of non-Bechtel

    engineering contractors. The core Electrical

    group based in Bechtels London office (the

    London core group) was tasked with preparing

    a combined model of the electrical system and

    with conducting the system studies.

    The system studies for this project presented

    unique challenges because of the sheer size of the

    captive power generation (with a new 800 MW

    power plant operating in parallel with an existing

    400 MW power plant), the Jamnagar plants

    extensive power distribution network, and the

    engineering work distributed amongst various

    Bechtel engineering centres and non-Bechtel

    engineering contractors around the world.

    System studies are normally conducted o

    selected set of study cases, and their res

    are used to determine the system behavi

    under all operating conditions. For this proj

    it was difficult to select the cases to simulate

    study because of the large number of possoperating configurations for such a comp

    industrial electrical network. The system stu

    themselves were a challenge because so m

    study cases (particularly transient stabi

    analysis studies) had to be evaluated.

    This paper presents an overview of system st

    execution on the complex electrical network

    the JERP, along with a brief report on the vari

    studies conducted as part of this project.

    OVERVIEW OF THE JERP

    Reliance Industries operates the JamnaDomestic Tariff Area (DTA) oil refinand petrochemical complex located in Guja

    India. The complex processes 650,000 bar

    per stream day (650 kbpsd) of crude

    and produces liquefied petroleum gas (LP

    naphtha; gasoline; kerosene; diesel; sulph

    coke; polypropylene; and numerous arom

    products, including paraxylene, orthoxyle

    Issue Date: December 2009

    AbstractElectrical system studies are carried out to verify that major electrical equipment is adequarated, determine the conditions for satisfactory and reliable operation, and highlight any operational restrictirequired for safe operation.

    The system studies for the Jamnagar Export Refinery Project (JERP) presented unique challenges becausthe sheer size of the captive power generation (with a new 800 MW power plant operating in parallel withexisting 400 MW power plant), the plants extensive power distribution network, and the engineering wdistributed amongst various Bechtel engineering centres and non-Bechtel engineering contractors around world. The large number of system study cases (particularly transient stability analysis studies) to be evalua

    also made the task challenging.This paper presents an overview of system study execution on the complex JERP electrical network, along wa brief report on the various studies conducted as part of this project.

    Keywordsanalysis, electrical system studies, Electrical Transient Analysis Program (ETAP), JamnaExport Refinery Project (JERP)

    ELECTRICAL SYSTEM STUDIES FOR

    LARGE PROJECTS EXECUTED AT

    MULTIPLE ENGINEERING CENTRES

    Rajesh NarayanAthiyarath

    [email protected]

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    Bechtel Technology Journal2

    and benzene. The original project, which

    Bechtel designed and constructed, was the

    worlds largest grassroots single-stream

    refinery. The complex includes a captive power

    plant (CPP) designed to produce 400 MW of

    power (backed up by a 132 kV grid supply) to

    meet the refinerys power demands.

    The JERP comprises a new export-oriented

    refinery located in a special economic zone

    (SEZ) adjacent to the DTA site. The project aimsto almost double the capacity of the Jamnagar

    refinery to more than 1,200 kbpsd; add crude

    distillation, associated secondary conversion

    facilities, and an 800 MW CPP; and modify the

    existing refinery to ensure the efficient operation

    of both it and the new refinery.

    On completion of the JERP, the Jamnagar

    complex will be the worlds largest refinery,

    surpassing Venezuelas 940 kbpsd Paraguana

    refining complex.

    ENGINEERING THE JERP

    The JERP required approximately 6 millionengineering jobhours within a short andchallenging project schedule. Hence, project

    engineering was split up amongst the various

    Bechtel offices, headed by the London core

    group (Figure 1). The key task of conducting

    overall system studies on the JERP and DTA

    electrical networks was handed over to the

    London core group.

    POWER GENERATION AND DISTRIBUTION

    Asimplified depiction of the JERP powergeneration and distribution system isportrayed in Figure 2.

    JERP Power System

    As the JERP power source, the CPP consists of six

    125 MW, 14.5 kV gas turbine generators (GTGs),

    with space allocated for three future GTGs. The

    GTGs are connected to the 220 kV switchyard

    bus via their dedicated 14.5/231 kV, 161 MVA

    step-up transformers. Eight 220/34.5 kV, 174 MVA

    refinery service transformers (RSTs) connectedto the 220 kV switchyard feed the JERP plant

    substations through 33 kV switchboards in two

    main receiving stations (MRS-1 and MRS-2). Two

    11 kV, 25 MW steam turbine generators (STGs)

    are connected to the switchboards in MRS-1

    via 11/34.5 kV, 38 MVA step-up transformers.

    Finally, a pair of 220/132 kV, 107 MVA auto-

    transformers are provided as the interconnecting

    The key task of

    conducting overall

    system studies on

    the JERP and DTA

    electrical networks

    was handed over

    to the London

    core group.

    ABBREVIATIONS, ACRONYMS, AND TERMS

    AVR automatic voltage regulator

    BSAP Bechtel standard applicationprogram (a software applicationthat Bechtel has determinedto be suitable for use tosupport functional processescorporate-wide)

    CPP captive power plant

    DTA Domestic Tariff Area

    DWI discipline work instruction

    EDMS electrical distributionmanagement system

    EMS energy management system

    ETAP Electrical Transient AnalysisProgram (a BSAP)

    FEED front-end engineeringand design

    GTG gas turbine generator

    HVDC high-voltage direct current

    ICT interconnecting transformer

    IEC International ElectrotechnicalCommission

    IEEE Institute of Electrical andElectronics Engineers

    IHD individual harmonic distortion

    JERP Jamnagar Export Refinery Project

    JV joint venture

    LMS load management system

    LPG liquefied petroleum gas

    LV low voltage

    MRS main receiving station

    MV medium voltage

    OLTC on-load tap changer

    PC personal computer

    RST refinery service transformer

    SEZ special economic zone

    STG steam turbine generator

    THD total harmonic distortion

    VSD variable-speed drive

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    December 2009 Volume 2, Number 1

    transformers (ICTs) between the JERP and DTA

    electrical systems.

    The JERP electrical system incorporates an energy

    management system (EMS) that comprises an

    electrical distribution management system

    (EDMS) to control and monitor the electrical

    network and a load management system (LMS) to

    carry out load shedding, if required, within the

    JERP and DTA electrical networks.

    DTA Power System

    The DTA CPP consists of nine 28 MW GTGsand six 25 MW STGs that feed the five

    33 kV switchboards, from which power is further

    distributed to the DTA plant substations.

    ELECTRICAL SYSTEM STUDIES

    System studies is the generic term for awide range of simulations conducted on

    System studies

    is the generic ter

    for a wide range

    of simulations

    conducted on

    a model of an

    electrical system

    under various

    operating

    conditions

    encountered or

    anticipated

    during operation

    of the network.

    BECHTEL HOUSTON/SHANGHAI

    CFP, Crude &

    Alkylation Units

    BECHTEL FREDERICK

    Captive Power

    Plant (CPP)

    JAMNAGAR

    ENGINEERINGOFFICE (JEC)JAMNAGAR (SITE)

    Merox, ATU, SWS, PRU Units

    FCC/VGO Units (Balance)

    DTA Revamp

    BECHTEL NEW DELHI

    Captive Power

    Plant (CPP)

    THIRDPARTY ANDLICENSOR OFFICES

    Coker (FWHouston)

    Sulphur & TGTU

    (BVPIKansas City)Sulphur Granulation

    Hydrogen (LindeMunich)Acid Regeneration

    (MECSSt. Louis)

    BECHTELRELIANCE JVMUMBAI

    Offsites & Utilities

    CFP, Crude & Alkylation

    Units (Balance)

    BECHTEL LONDON

    DTA Expansion Group

    DTA Revamp FEED

    FCC Group

    FCC/VGO Units

    BANTREL TORONTO

    Aromatics Unit

    CNHT/KHT Units

    BECHTELLONDON

    COREFUNCTIONS

    Interconnection

    to DTA

    Four Sets 33 kV

    Main Receiving Switchgear

    6.6 kV/415 V Distribution

    Network for Each Unit

    220 kV Switchgear

    (1 Breaker Scheme)

    Two 25 MW STGs

    Captive Power Plant

    (Six 125 MW GTGs)

    Figure 1. Project Execution Locations

    Figure 2. JERP Power System Generation and Distribution

    ATU amine treating unit

    CFP clean fuel plant

    CNHT cracked naphtha hydrotreater

    CPP captive power plant

    DTA Domestic Tariff Area

    FCC uid catalytic cracker

    FEED front-end engineering and design

    FW Foster Wheeler

    JEC Jamnagar Engineering O fce

    KHT kerosene hydrotreater

    Merox (mercaptan oxidation process)

    PRU propylene recovery unit

    SWS sour water stripper

    TGTU tail ga s treatmen t unit

    VGO vacuum gas oil

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    Bechtel Technology Journal4

    a model of an electrical system under various

    operating conditions encountered or anticipated

    during operation of the network. System

    studies analyse the behaviour of the electrical

    network components under various steady-state,

    dynamic, and transient conditions, and the

    results are used to predict the networks

    behaviour under actual operating conditions.

    System studies are conducted at different

    stages of a project. The results of system studiesperformed during the front-end engineering and

    design (FEED) and detailed engineering stages

    enable proper selection of equipment ratings,

    identification of the electrical system loading

    and operational modes for maximum reliability

    and safety, and selection of the control modes for

    major equipment. These early system studies can

    also assess the ability of the electrical network to

    meet present and future system energy demands.

    System studies conducted after the power

    system network is operational generally study

    the feasibility or effects of system expansion,

    check conformance with any changes in codes

    and standards, or analyse system behaviour

    to identify the underlying causes of a network

    disturbance or equipment failure.

    In the case of the JERP, the electrical system is

    planned to operate in parallel with the existing

    DTA electrical system and the grid supply from

    the local electricity utility. The JERP electrical

    system also has to be adequate for the addition

    of future units and high-voltage direct current

    (HVDC) links to the local electricity utility supply.

    Hence, this combination of large-scale greenfield

    project/major expansion of an existing networkbecomes a special case for system studies.

    The sheer size of the JERP and DTA electrical

    networks (with a combined power generation

    of 1.2 GW), the extensive power distribution

    network within the JERP and DTA plants, and

    the crucial need to ensure reliability of the power

    supply under all operating conditions make

    it important to conduct reliable and accurate

    system studies. Further, the study results

    can help in the design of a reliable electrical

    system suitable for the projects present and

    future requirements.

    Three key elements are at the heart of a proper

    system study:

    A dependable and versatile system study

    software program

    A reliable model of the electrical network

    Selection of studies to be conducted and

    study cases to be simulated

    ELECTRICAL SYSTEM STUDY

    SOFTWARE PROGRAMS

    System studies entail the analysis of theinteractions amongst the various componentsof the electrical network to determine the power

    flows between elements and the voltage profile

    at the various buses in the network. Many

    mathematical computations are required to

    analyse even a small network, precluding the use

    of manual calculation techniques to conduct anybut the most rudimentary system studies.

    These circumstances have led to an effort

    since the late 1920s to devise computational

    aids for network analysis. From about 1929 to

    the 1960s, special analogue computers in the

    form of alternating current network analysers

    were used for system studies. These network

    analysers contained scaled-down versions of the

    network components, such as power sources,

    cables, transmission lines, and loads, that were

    interconnected using flexible cords to represent

    the system being modelled. Although limited in

    scope and complexity, the network analysers were

    used to study power flows and voltage profiles

    under steady-state and transient conditions.

    The next stage in the evolution of system study

    software programs was the use from the late

    1940s of digital computers to conduct system

    studies. These programs were initially limited

    in scope due to the programming methods

    used (punched-card calculators). However, the

    availability of large-scale digital computers

    from the mid-1950s gave a boost to the use

    of computer programs for system studies.

    Although these programs originally required

    mainframe computing power and specialised

    programming techniques, the growth in the

    computing power of desktop PCs and laptops

    has seen these programs become an essential

    tool for the electrical engineer. Current system

    study programs offer flexible and easy-to-use

    techniques for system modelling, analysis,

    and presentation.

    One of the more commonly used system study

    software programs is Operation Technology,

    Inc.s (OTIs) Electrical Transient Analysis

    Program (ETAP), which has been qualifiedas a Bechtel standard application program

    (BSAP). The offline simulation modules of

    ETAP 6.0.0, the most current release at the time

    of project execution, were used to conduct the

    JERP power system studies.

    The sheer size of

    the JERP and DTA

    electrical networks,

    the extensive

    power distribution

    network within

    the JERP and DTA

    plants, and the

    crucial need to

    ensure reliability

    of the power

    supply under

    all operating

    conditions make

    it important to

    conduct reliable

    and accurate

    system studies.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    December 2009 Volume 2, Number 1

    MODEL OF THE JERP ELECTRICAL NETWORK

    The various Bechtel and third-partyengineering centres prepared models of theelectrical networks for the individual JERP units.

    The London core group integrated these various

    submodels into a composite model of the overall

    plant electrical network.

    It was necessary to ensure that all the engineering

    centres used uniform modelling principles to

    prepare the individual models, to speed the

    process of integrating them. The London core

    group issued specific discipline work instructions

    (DWIs) to the engineering centres and held a

    series of conferences to explain the modelling

    principles to be followed to ensure uniformity.

    These work instructions covered key points such

    as model structure, division of responsibility

    for preparing and using the model, key data

    required, instructions for dealing with cases of

    incomplete/missing data related to network or

    equipment required for the model, and use of

    library data (accompanied by a common librarydatabase to be used to populate the model).

    The major items modelled were the GTGs/STGs

    along with their control systems (governors,

    exciters, and power system stabilisers), plant

    loads, and interconnecting power cables. The

    modelling of certain complex portions of the

    GTG control system required software such

    as Simulink, a specialised program used to

    model and simulate dynamic control systems.

    OTI constructed the models, which were later

    integrated with the overall model.

    ELECTRICAL SYSTEM STUDIES AND

    STUDY CASES

    Awide range of system studies can beconducted on electrical networks to studythe behaviour of the system under steady-state

    conditions as well as conditions in which it is

    subjected to disturbances in normal operation

    (e.g., step loading or load sharing amongst

    generators) or unplanned events (e.g., electrical

    fault, generators tripping). Because it is not

    possible to analyse every expected operating

    condition, it is very important to select the studycases whose results can be used to predict the

    system behaviour under all operating conditions.

    As a result, the studies are usually conducted on

    the most onerous conditions expected during the

    refinery operation.

    The following system studies were carried out

    to analyse the behaviour of the JERP and DTA

    electrical networks. In line with the specification

    requirement for the JERP, the engineering centres

    used International Electrotechnical Commission

    (IEC) standards as the basis for evaluating the

    results of all studies except harmonic analysis.

    Load Flow Analysis

    Once the refinery is commissioned and fully

    operational, the electrical system is expected to

    operate in a stable condition. Load flow analysis

    is a steady-state analysis that calculates the active

    and reactive power flows through each elementof the network and the voltage profile at the

    networks various buses. A balanced load flow

    analysis is adequate because the vast majority

    of loads in the refinery are inherently balanced

    (e.g., three-phase motors).

    Load flow analyses help identify any abnormal

    system conditions during steady-state operation

    that can be harmful for the system in the long

    run. They also provide the initial basis for other

    detailed analyses such as motor starting and

    transient stability. It is also to be noted that the

    results of the load flow analysis affect theseother analyses. For example, an electrical system

    operating under steady-state conditions is more

    likely to satisfactorily survive a transient event

    such as the step-loading or tripping of one of

    the operating generators if its initial operating

    conditions are favourable (e.g., voltages within

    limits, sufficient margin in the loading of various

    network elements).

    Some of the main parameters examined in a

    load flow analysis are presence of overvoltage

    or undervoltage at any point in the electrical

    network, overloading of any network element,and very low system power factor.

    To study system behaviour at the JERP under all

    expected operating conditions, the London core

    group carried out load flow analyses under these

    three sets of conditions:

    Normal system configuration, i.e., with

    redundant power feeds, where available,

    to various plant switchboards that simulate

    the normal operating condition of the

    electrical network

    Loss of redundant power feed, i.e., with single

    power feed to the various plant switchboards

    (This condition of single-ended operation

    can occur in the electrical network under a

    contingency like loss of plant transformers.)

    No-load conditions (This study case

    was selected to assist in identifying any

    dangerous overvoltage that may occur

    when the network is operating under

    no-load or lightly loaded conditions [e.g.,

    plant startup conditions]).

    It is

    very important

    to select the

    study cases

    whose results

    can be used

    to predict the

    system behaviou

    under all operatin

    conditions.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    Bechtel Technology Journal6

    The results of these analyses revealed some

    instances in which the bus voltages exceeded

    the acceptable limits. The London core group

    recommended that the tap settings of the

    upstream transformers associated with these

    switchboard buses be changed to bring the

    voltages within the specified limits. The core

    group also highlighted cases of potential

    overloading of transformers under loss of

    redundant power feed (second case) forobservation during actual plant operation.

    Short Circuit Analysis

    A short circuit condition imposes the most

    onerous short-time duty on the system electrical

    equipment. This fault condition arises as a result

    of insulation failure in the equipment or wrong

    operation of the equipment (e.g., closing onto an

    existing fault or closing circuit breakers when the

    associated earth switch is closed), leading to the

    flow of uncontrolled high currents and severely

    unbalanced conditions in the electrical system.

    The four main types of short circuits are:

    Three-phase short circuit with or without

    earthing (This is usually the most severe

    short circuit condition.)

    Line-to-earth (single-phase-to-earth) fault

    (In certain circumstances, the short circuit

    current for a line-to-earth fault can exceed

    the three-phase short circuit current.)

    Line-to-line (phase-to-phase) fault

    Double line-to-earth fault

    The electrical equipment has to be rated

    for the short circuit level of the system, which

    basically requires all of the following conditions

    to be met:

    The electrical equipment must be able to

    withstand the short circuit current until

    the protective equipment (relays) detects

    the fault and it is cleared by opening circuit

    breakers (i.e., thermal withstand short

    circuit current). The IEC standards specify a

    standard withstand duration of 1 second or

    3 seconds. The JERP used switchgear rated

    for 1-second withstand time.

    The circuit breakers must be suitable to

    interrupt the flow of the short circuit current

    (i.e., breaking duty).

    The circuit breakers must be suitable to close

    onto an existing fault (i.e., making duty).

    Additionally, the protective system of the

    network has to be set to enable reliable detection

    of any short circuit condition (minimum and

    maximum short circuit conditions).

    The calculation of the short circuit current

    for these conditions is made more complex

    by the behaviour of the short circuit current

    immediately after the fault. Depending on

    the network characteristics, behaviour of the

    generators in the network, and the exact instant

    of the fault, the short circuit current may contain

    significant amounts of transient alternating

    and direct current components, which decay to

    zero over time, depending on the characteristicsof the network and the rotating machines. It

    is very difficult to account for the effects of

    these phenomena through manual calculation

    methods. This is particularly true because the

    presence of a large direct current component in

    the short circuit current imposes a very stringent

    breaking duty on the circuit breakers, since a

    natural current zero may not be achieved.

    The results of the short circuit analysis calculated

    the following various components of the short

    circuit current at each bus:

    ipPeak current in the first cycle after theshort circuit

    IdcDirect current component at the instant

    the circuit breaker opened

    Ib sym and Ib asymSymmetrical and

    asymmetrical root mean square currents at

    the instant the circuit breaker opened

    IthThermal withstand short circuit current

    for 1-second rating

    These results were cross-checked with the

    equipment ratings to verify that the equipment

    short-time ratings were suitable for the shortlevel of the system.

    Stability Analysis

    It is relevant to note the concept of stability as

    defined in standards such as Standard 399 of

    The Institute of Electrical and Electronics

    Engineers, Incorporated (IEEE). [1] IEEE 399

    states that a system (containing two or more

    synchronous machines) is stable, under a

    specified set of conditions, if, when subjected

    to one or more bounded disturbances (less

    than infinite magnitude), the resulting system

    response(s) are bounded.

    System stability requirements can be generally

    categorised into steady-state stability, dynamic

    stability, and transient stability. [2]

    Steady-State Stability Analysis

    Steady-state stability is the ability of the system

    to remain stable under slow changes in system

    loading. The power transfer between two

    synchronous machines (generator G and motor

    A short circuit

    condition imposes

    the most onerous

    short-time duty

    on the

    system electrical

    equipment.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple

    December 2009 Volume 2, Number 1

    Mrefer to Figure 3) with internal voltages of

    EGand EM, respectively, and a phase angle of

    between them is represented in Equation 1: [1]

    (1)

    The maximum power that can be transferred

    occurs when = 90 degrees, per Equation 2:

    (2)

    For particular values of EG and EM, the

    machines lose synchronism with each other if

    the steady-state limit of Pmax is exceeded. The

    steady-state stability study determines the

    maximum value of machine loading that is

    possible without losing synchronism as the

    system loading is increased gradually.

    Dynamic Stability Analysis

    A steady-state scenario never exists in actual

    operation, however. Rather, the state of the

    electrical system can be considered dynamic,

    whereby small, random changes in the system

    load constantly occur, followed by actions of the

    generator governor, exciter, and power system

    stabiliser to adjust the output of the machine and

    match the load requirement. The system can be

    considered stable if the responses to these small,

    random disturbances are bounded and damped

    to an acceptable limit within a reasonable time.

    The dynamic stability analysis of any system

    is only practical through specialised computer

    programs such as ETAP.

    Transient Stability Analysis

    Transient stability is the ability of the system to

    withstand sudden changes in generation, load,

    or system characteristics (e.g., short circuits,

    tripping of generators, switching in large

    bulk loads) without a prolonged loss of

    synchronism. [1] Traditionally, transient stability

    analysis focused on the ability of the system

    to remain in synchronism immediately after

    the occurrence of the transient event (i.e.,

    the first swing of the machines, generally

    within 1 second of the event). Also, the

    traditional transient stability analysis ignored

    the action of the machine governor, exciter,

    and automatic voltage regulator (AVR) because

    they were slow-acting compared with the

    duration of the analysis.

    This approach to transient stability analysis

    has been modified in recent times since the

    advent of governors, exciters, and AVRs basedon fast-acting control systems. It has also been

    seen that different sections of an interconnected

    network may respond at different times to a

    transient event that sometimes may be outside

    the traditional 1 second window for transient

    analysis. Also, the behaviour of different sections

    of the network may be different for the same

    transient event. Hence, to verify whether system

    stability is retained, the transient stability

    analysis needs to be carried out for a longer

    duration (preferably over a range of transient

    events having varying severities and durations).This kind of analysis was not possible in earlier

    years due to the high complexity of modelling

    and limited computing power, but today such

    an analysis can be performed because of the

    availability of practically unlimited computing

    power on desktop and laptop computers,

    coupled with specialised computer programs

    such as ETAP. Hence, the dividing line between

    dynamic stability analysis and transient stability

    analysis has been virtually eliminated.

    A range of stability analyses was carried out

    on the JERP refinery system. They covered the

    operation of the JERP electrical network while

    in a standalone condition as well as in parallel

    operation with the DTA electrical network. The

    stability analyses can be broadly classified into

    the following categories.

    Transient and Extended Dynamic

    Stability Analysis

    Fault withstand study: This study entailed

    simulation of single-phase and three-phase

    faults at various locations in the electrical

    network. It analysed the behaviour of the

    power system in the pre-fault stage, during

    the fault, and after the fault was cleared bythe systems protective devices.

    Load throw-off study: A load throw-off

    condition can cause the machines to over

    speed. Temporary overvoltage conditions

    can also occur in the system. Hence, the

    behaviour of the electrical system was

    studied for all probable cases of load throw-

    off in which a substantial portion of the

    operating load was suddenly tripped.

    Stability analyse

    carried out

    on the JERP

    refinery system

    covered the

    operation of

    the JERP electric

    network in

    standalone condit

    as well as in

    parallel operatio

    with the DTA

    electrical networ

    G

    EG

    EM

    jX M

    Figure 3. Power Transfer Between Machines

    sinM=E GE

    PX

    M=

    E GE

    P Xmax

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multipl

    Bechtel Technology Journal8

    Load sharing on tripping of tie circuit

    breaker between JERP and DTA electrical

    systems: The behaviours of the JERP and

    DTA electrical systems were studied on

    disconnection of the JERPDTA tie line.

    This study was carried out for various

    combinations of operating GTGs/STGs in

    the JERP and DTA electrical systems (i.e.,

    various power flow scenarios between JERP

    and DTA systems). When system stabilitycould not be achieved by load sharing

    amongst the operating GTGs/STGs in each

    individual network, load shedding was

    simulated to try to achieve a stable system.

    Contingency Analysis

    Load sharing on tripping of JERP/DTA

    GTG: The behaviour of the power system

    was studied when one or more of the

    operating GTGs/STGs tripped, causing a

    loss of generation. This study was carried

    out for various combinations of operating

    GTGs/STGs in the JERP and DTA electricalsystems. When system stability could not

    be achieved by load sharing amongst the

    remaining operating GTGs/STGs, load

    shedding was simulated to try to achieve

    a stable system.

    Operational Analysis

    Step-load addition study:A sudden addition

    of load on operating machines can cause loss

    of stability. A step-load addition scenario can

    occur in a variety of ways in an electrical

    system, the most probable being loss of one

    of the operating machines, which can cause

    a sudden increase in the load demand on the

    other operating GTGs/STGs. The behaviour

    of the system was studied for all probable

    scenarios of step-load addition.

    The results of these stability analyses helped

    define the limits of safe operation of the

    power system under various generation/

    load scenarios.

    Motor-Starting Study

    At the instant of starting, synchronous and

    induction motors draw a starting current that is

    several times the full-load current of the motor.

    In the absence of assisted starting, this starting

    current is typically between 600% and 720% of

    the normal full-load current. This high current

    causes a voltage drop in the upstream electrical

    network, as well as in the motor feeder cable.

    The effects of this voltage drop include:

    The combined voltage drop in the supply

    network and the motor cable reduces the

    voltage available at the motor terminals

    during the starting period. Because the motor

    torque is directly proportional to the square

    of the applied voltage, excessive voltage

    drops can mean that insufficient torque is

    available to accelerate the motor in the face

    of the load torque requirement, leading to

    very long starting times or a failure to start.

    The voltage drop at the switchboard buses

    can affect the other operating loads, mainlyin the form of nuisance tripping of other

    loads on the network (e.g., voltage-sensitive

    loads or contactor-fed loads where the

    control voltage for the contactor is derived

    from the switchgear bus). There can also be

    cases in which the reduction in the terminal

    voltage for the operating motors causes the

    motor-torque curve to shift downwards.

    This reduction in the motor torque can cause

    the running motors to stall.

    For the other operating loads, a reduction

    in the motor terminal voltages causes the

    current drawn by the motors to increase

    as they strive to produce the power the

    process demands of them. This condition

    exacerbates the voltage problem because the

    increased current gives rise to an increased

    voltage drop in the system.

    Depending on the size of the motor being started

    and the generating capacity available, motor

    starting can impose a very high short-term

    demand on the operating generators.

    Studying motor starting can help identify these

    voltage-drop-related problems at the designstage. Usually, the worst-case motor-starting

    scenario is the starting of the highest-rated motor

    (or the highest-rated standby motor) at each

    voltage level with the operating load of the

    plant as the standing load. However, other

    worst-case scenarios may require evaluation in

    certain situations:

    Motors with an unusually long supply cable

    circuit

    Motors fed from a weak power supply (e.g.,

    starting on emergency power supplied from

    a diesel generator set of limited rating) Simultaneous starting of a group of motors

    In the event of an unfavourable outcome from

    the motor starting study, various improvement

    measures are available, including:

    Specifying that motors be designed with

    a lower value of starting current, which is

    particularly feasible for the larger medium-

    voltage (MV) motors

    The results

    of stability

    analyses help

    define the limits of

    safe operation of

    the power system

    under various

    generation/load

    scenarios.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multipl

    December 2009 Volume 2, Number 1

    Specifying lower impedance for the upstream

    transformer after verifying the suitability

    through a short circuit analysis

    Starting the largest motors in the network

    with a reduced standing load

    Using larger cable sizes for the motor feeder

    to improve the motor terminal voltage

    Providing assisted starting, if required, for

    the larger HV/MV motors instead of direct

    on-line starting

    Using motor unit transformers to feed power

    to large MV motors, which ensures that the

    effect of the voltage drop on the rest of the

    electrical system is reduced

    Increasing upstream bus voltage temporarily

    (e.g., through on-load tap changers [OLTCs])

    before starting large motors

    Various motor starting scenarios were modelled

    for the JERP, and the results indicated that the

    motors could be started satisfactorily.

    Transformer Energisation Studies

    The inrush phenomenon in transformers can

    inflict a very severe, albeit short-term, effect

    on the voltage profile at the refinerys various

    switchboard buses. The inrush current taken

    by the transformers is due to the behaviour of

    the magnetic circuit. The constant flux linkage

    theorem states that the magnetic flux in an

    inductive circuit cannot change suddenly. Hence,

    the magnetic flux immediately after energisation

    (t = 0+) should be equal to the magnetic flux

    immediately before energisation (t= 0).

    When a transformer is switched on, the

    magnetic flux immediately after energisation

    depends on the following factors that are

    essentially random:

    The point on the sine wave voltage

    waveform where the transformer is switched

    on, which decides the amount and direction

    of the flux requirement

    The amount and direction of the remnant

    flux, which depends on the point on the

    sine wave voltage waveform where the

    transformer was last switched off

    As explained by the constant flux linkage

    theorem, the magnetic flux after energisation

    retains a sinusoidal shape that is biased by the

    flux requirement at the point of energisation

    and the remnant flux. Depending on the design

    of the transformer, this condition can cause the

    flux requirement to be well above the knee-point

    voltage on the transformer magnetising curve,

    leading to very high excitation currents that may

    reach large multiples of the full-load current

    of the transformer. The inrush current decays

    substantially within a few cycles.

    Although modern protection systems are well-

    equipped with algorithms to distinguish the

    transformer inrush current from the short circuit,

    the inrush current still causes a severe voltage

    dip at the other switchboards in the network.

    This voltage dip can cause nuisance tripping of

    other network loads.

    The London core group studied various probable

    transformer energisation scenarios (including

    group energisation of transformers) to confirm

    that the network voltages recover without

    tripping system operating loads.

    Because ETAP could not directly model

    transformer behaviour under inrush conditions,

    the impact of the transformer inrush current

    was simulated by switching a series of low

    power-factor loads in and out at intervals of

    5 milliseconds. The load values were selectedas exponentially decreasing to simulate the

    inrush current decay. To ensure accurate

    modelling, the inrush current data was based on

    transformer manufacturers data supplemented

    by the measurements recorded during site

    testing and commissioning.

    The results of the transformer energisation

    studies established the network conditions

    under which the JERP transformers can be safely

    energised. This finding was crucial because in

    certain scenarios, the JERP main transformers

    were to be energised from the DTA electrical

    system and any disruption to the DTA operating

    loads could lead to tripping of the DTA refinery.

    Harmonic Analysis

    The amount of periodic waveform distortion

    present in the power supply is one of the most

    important criteria for measuring power quality.

    Periodic waveform distortion is characterised by

    the presence of harmonics and interharmonics

    in the power supply.

    Harmonics are sinusoidal voltages and currents

    with frequencies that are integral multiplesof the fundamental frequency of the system.

    Interharmonics are sinusoidal voltages and

    currents with frequencies that are non-integral

    multiples of the fundamental frequency of

    the system.

    For the JERP:

    f1= fundamental frequency = 50 Hz

    fharmonic= nxf1(n= 2, 3, 4, ) (3)

    finterharmonic= mxf1(m> 0 and non-integral) (4)

    The results of

    the transformer

    energisation

    studies

    established the

    network condition

    under which the

    JERP transformer

    can be safely

    energised.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple- Bechtel Technology Journal10

    Periodic waveform distortion is caused by non-

    linear loads, which are loads that do not draw a

    sinusoidal current when excited by a sinusoidal

    voltage. The non-linear loads act as sources

    of harmonic currents in the power system,

    which cause a voltage distortion at the various

    buses because of the harmonic voltage drops

    across the impedances of the network. Hence,

    the quantum of voltage distortion depends on

    the harmonic currents injected into the systemand the impedance of the system (the voltage

    distortion in a weak system, characterised by a

    high system impedance, is higher).

    The presence of excessive harmonics can lead to

    premature aging of electrical insulation due to

    dielectric thermal or voltage stress in equipment

    such as motors, cables, and transformers. Other

    possible effects of harmonics include reduced

    power factors, incorrect operation of protection

    systems, interference with communication

    networks, and occurrence of series and parallel

    resonant conditions that can lead to excessivecurrents and voltages in the system. Hence, it

    is important to carry out a harmonic analysis

    wherever the non-linear load forms a significant

    portion of the total load.

    The JERP electrical network includes a large

    number of harmonic-generating loads, mainly

    22 kW and 37 kW low-voltage (LV) variable-speed

    drives (VSDs) that act as sources of harmonic

    currents. The London core group carried out a

    harmonic analysis of the JERP electrical network

    to verify that the voltage distortion at the

    networks various switchboards caused by these

    harmonic-generating loads is within the limits

    specified in Table 11-1 of IEEE 519 (Table 1).

    All harmonic-generating process loads were

    modelled in the ETAP model used for harmonic

    analysis. The power sources in the JERP network

    (GTGs and STGs) were assumed to have no

    harmonic distortion. As a worst-case scenario,

    the harmonic analysis was carried out with

    the minimum generation configuration under

    normal operating conditions because this

    configuration corresponds to the maximum

    system impedance.

    The results of the harmonic analysis highlighted

    the switchboards whose power quality needs to

    be monitored further during plant operation.The London core group recommended that any

    corrective action (such as adding harmonic filters)

    to reduce the harmonics at these JERP plant

    switchboards be undertaken after measuring the

    actual harmonic levels at the various 6.6 kV/415 V

    switchboards when the plant is operating.

    CONCLUSIONS

    The results of the system studies of the JERPelectrical network verified the adequacy ofthe ratings for the systems major equipment.The results also helped determine the conditions

    for satisfactory and reliable system operation

    and highlighted any operational restrictions

    required for safe operation.

    LESSONS LEARNT

    Conducting electrical system studies ona complex project such as the JERP andworking with execution centres and non-Bechtel

    engineering contractors located across the globe

    have highlighted three major areas, discussedbelow, where existing Bechtel project procedures

    can be improved or fine-tuned to increase

    operating efficiency.

    Distributing Work

    The work distribution amongst the execution

    centres, non-Bechtel engineering contractors,

    and the London core group for carrying out

    ETAP modelling must be clearly defined

    through proper DWIs. Amongst other things,

    the instructions should include the structure of

    the model, the extent of modelling required, the

    data required to be populated in the model, themethodology of populating the data, the use of

    assumptions and approximations, the common

    library to be used to populate the standard data

    in the model, and the tests that must be carried

    out to ensure that sections of the model meet

    all requirements before they are transferred to

    the London core group for integration into the

    overall model.

    Table 1. Harmoni c Limits as Define d by IEE E 519

    Rated

    Bus Voltage

    Individual

    Harmonic

    Distortion

    (IHD), %

    Total

    Harmonic

    Distortion

    (THD), %

    69 kV and less 3 5

    Greater than 69 kV

    up to 161 kV1.5 2.5

    161 kV and greater 1 1.5

    For shorter periods, during startups or unusual conditions,

    these limits may be exceeded by 50%.

    Conducting

    system studies on

    a complex project

    such as the JERP

    has highlighted

    areas where

    existing Bechtel

    procedures

    can be improved

    or fine-tuned.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple- December 2009 Volume 2, Number 1

    Handling Model Revisions

    Proper work procedures for handling ETAP

    model revisions need to be furnished to the

    execution centres/non-Bechtel engineering

    contractors so that the London core group

    can integrate the revised models or revised

    sections of same into the overall model without

    causing rework or loss of data.

    Identifying Study CasesTo increase engineering efficiency, it is essential

    to optimise the types of studies to be conducted

    on a project and the number of cases to be

    analysed for each study. At the same time,

    it is essential to ensure that the number

    and types of study cases allow the engineer

    to determine system behaviour under all

    operating conditions.

    This opportunity is particularly valuable because

    the projects that Bechtel is bound to take up

    (in the role of engineering contractor or as a

    project management consultant or member ofa project management team) are more likely

    to be of the scale of the JERP, and it is highly

    likely that the engineering work for such

    projects will be divided amongst various

    execution centres.

    ACKNOWLEDGMENTS

    The author wishes to express his gratitude to

    R.H. Buckle (chief engineer), R.D. Hibbett (lead

    electrical engineerJERP), and David Hulme

    (project engineering manager) for their support

    and guidance during execution of the JERP

    system studies. The author also wishes to

    thank V. Shanbhag, B.S. Venkateswar, and

    M.A. Mujawar from Reliance Industries for

    their support and encouragement.

    TRADEMARKS

    ETAP is a registered trademark of Operation

    Technology, Inc.

    IEEE is a registered trademark of The Institute

    of Electrical and Electronics Engineers,Incorporated.

    Merox is a trademark owned by UOP LLC,

    a Honeywell Company.

    Simulink is a registered trademark of The

    MathWorks, Inc.

    REFERENCES

    [1] IEEE 399-1997, IEEE Recommended Practicefor Industrial and Commercial Power SystemsAnalysis, The Institute of Electrical andElectronics Engineers, Inc., 1998, pp. 79,209214, access via http://standards.ieee.org/colorbooks/sampler/Brownbook.pdf.

    [2] D.P. Kothari and I.J. Nagrath, Power SystemEngineering, 2nd Edition, Tata McGraw-HillPublishing Company Ltd., 2008, Chapter 12,pp. 558560, access via http://highered.mcgraw-hill.com/sites/0070647917/information_center_view0/.

    ADDITIONAL READING

    Additional information sources used to develop

    this paper include:

    P.M. Anderson and A.A. Fouad, PowerSystem Control and Stability, 2nd Edition,IEEE Press Series on Power Engineering,

    John Wiley & Sons, Inc., 2003, pp. 510,access via http://www.amazon.com/Power-System-Control-Stability-Engineering/

    dp/0471238627#noop. Systems, Controls, Embedded Systems, Energy,

    and Machines, The Electrical EngineeringHandbook, 3rd Edition, Richard C. Dorf, ed.,Chapter 5, 2006, CRC Press/Taylor & FrancisGroup, LLC, Boca Raton, FL, pp. 5-1 5-3,access via http://www.amazon.com/Controls-Embedded-Machines-Electrical-Engineering/dp/0849373476.

    BIOGRAPHY

    Rajesh Narayan Athiyarathis a senior electrical engineer

    in Bechtels OG&C GlobalBusiness Unit. He has 16 yearsof experience in engineeringoil and gas, petrochemical,and GTG power plant projectsworldwide. During his 3 yearswith Bechtel OG&C (London),Rajesh has contributed to

    system studies and relay coordination studieson the JERP and to FEED for the Ruwais refineryexpansion project. He has also acted as theresponsible engineer for the energy managementsystem and load shedding system on the JERP.

    Rajesh received a performance award for his work onthe JERP system studies.

    Rajesh holds a BE from Mumbai University, India,and is a chartered electrical engineer (CEng,member of Institution of Engineer ing and Technology[MIET], UK). He is a Six Sigma Yellow Belt.

  • 5/19/2018 Electrical System Studies for Large Projects Executed at Multiple Engineering Cen...

    http:///reader/full/electrical-system-studies-for-large-projects-executed-at-multiple- Bechtel Technology Journal12