27
Prof Awad S. Hanna

Earth work

Embed Size (px)

DESCRIPTION

earth

Citation preview

  • ESTIMATING EARTHWORK

    Prof Awad S. Hanna

  • Estimating EarthworkEarthwork includes:1.Excavation2.Grading: Moving earth to change elevation3.Temporary shoring4.Back fill or fill: Adding earth to raise grade5.Compaction: Increasing density6.Disposal

    Prof Awad S. Hanna

  • Productivity FactorsA. Job conditionsMaterial typeWater level and moisture contentJob sizeLength of haulHaul road condition (accessibility and load restrictions)

    Prof Awad S. Hanna

  • Productivity Factors (cont.)B. Management conditionsEquipment conditions and maintenance practicesSkills of work force and managementPlanning, supervision and coordination of work.

    Prof Awad S. Hanna

  • Job Efficiency Factors for Earthmoving Operations

    Prof Awad S. Hanna

    Sheet1

    Management Conditions*

    Job Conditions**ExcellentGoodFairPoor

    Excellent0.840.810.760.70

    Good0.780.750.710.65

    Fair0.720.690.650.60

    Poor0.630.610.570.52

    Sheet2

    Sheet3

  • Units of MeasureCubic Yard (bank, loose, or compacted)

    Prof Awad S. Hanna

    Sheet1

    Bank (BCY):Materials in its natural state before disturbance (in-place, in-situ)

    Loose (LCY):Material that has been compacted or disturbed or loaded

    Compacted (CCY):Material after compaction

    Sheet2

    Sheet3

  • 1.01.250.901.0 CUBIC YARD IN NATURAL CONDITION (IN-PLACE YARD)1.25 CUBIC YARD AFTER DIGGING (LOOSE YARDS)0.90 CUBIC YARD AFTER COMPACTED (COMPACTED YARDS)In placeCompactedLoose

    Prof Awad S. Hanna

  • VolumeBank: VBBank cubic yards (BCY)Density B Lb /BCY

    Loose: VlLoose cubic yards (LCY)Density L Lb/LCY

    Compacted: VcCompacted cubic yards (CCY)Density C LB/CCY

    Prof Awad S. Hanna

  • Swell:A soil increase in volume when it is excavated.Swell (%) = ( - 1) x 100

    Load factor =

    Bank Volume = Loose volume x Load factorLoose densityBank densityBank densityLoose density

    Prof Awad S. Hanna

  • Shrinkage:A soil decreases in volume when it is compactedShrinkage (%) = (1 - ) x 100

    Shrinkage factor = 1 - ShrinkageCompacted volume= Bank volume x Shrinkage factorBank densityCompacted density

    Prof Awad S. Hanna

  • Approximate Material CharacteristicsExact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils.

    Prof Awad S. Hanna

    Sheet1

    MaterialLoose (lb/cy)Bank (lb/cy)Swell (%)Load Factor

    Clay, dry2,1002,650260.79

    Clay, wet2,7003,575320.76

    Clay and gravel, dry2,4002,800170.85

    Clay and gravel, wet2,6003,100170.85

    Earth, dry2,2152,850290.78

    Earth, moist2,4103,080280.78

    Earth, wet2,7503,380230.81

    Gravel, wet2,7803,140130.88

    Gravel, dry3,0903,620170.85

    Sand, dry2,6002,920120.89

    Sand, wet3,1003,520130.88

    Sand and gravel, dry2,9003,250120.89

    Sand and gravel, wet3,4003,750100.91

    Sheet2

    Sheet3

  • Typical Soil Volume Conversion Factors

    Prof Awad S. Hanna

    Sheet1

    MaterialLoose (lb/cy)Bank (lb/cy)Swell (%)Load Factor

    Clay, dry2,1002,650260.79

    Clay, wet2,7003,575320.76

    Clay and gravel, dry2,4002,800170.85

    Clay and gravel, wet2,6003,100170.85

    Earth, dry2,2152,850290.78

    Earth, moist2,4103,080280.78

    Earth, wet2,7503,380230.81

    Gravel, wet2,7803,140130.88

    Gravel, dry3,0903,620170.85

    Sand, dry2,6002,920120.89

    Sand, wet3,1003,520130.88

    Sand and gravel, dry2,9003,250120.89

    Sand and gravel, wet3,4003,750100.91

    InitialConvrted to:

    Soil TypeSoil ConditionBankLooseCompacted

    ClayBank1.001.270.90

    Loose0.791.000.71

    Compacted1.111.411.00

    Common earthBank1.001.250.90

    Loose0.801.000.72

    Compacted1.111.391.00

    Rock (blasted)Bank1.001.501.30

    Loose0.671.000.87

    Compacted0.771.151.00

    SandBank1.001.120.95

    Loose0.891.000.85

    Compacted1.051.181.00

    Sheet2

    Sheet3

  • Estimating Earth work for Trenches and FoundationAngle of Repose2-0or more

    Prof Awad S. Hanna

  • Approximate Angle of ReposeFor Sloping Sides of ExcavationOriginalGround LineSolid Rock, Slate or Cemented Sand and Gravel(90 Deg.)Compacted Angular Gravels1/2:1 (63 Deg.)Recommended Slope for Average Soils1:1 (45 Deg.)Compacted Sharp Sand1 1/2 :1 (33 Deg.)Well Rounded Loose Sand2:1 (26 Deg.)

    Prof Awad S. Hanna

  • Calculating Earthwork Quantities1.End Area Method2.Contour Line/ Grid Method

    Prof Awad S. Hanna

  • 1. End Area MethodUsed in sites where length is much greater than width

    Prof Awad S. Hanna

  • CALCULATING EARTHWORK QUANTITIES1. End Area Method

    a.Take cross-sections at regular intervals, typically, 100 intervals.

    b.Calculate the cross-section end areas

    c.The volume of earthwork between sections is obtained by taking the average of the end areas at each station in square feet multiplied by the distance between sections in feet and dividing by 27 to obtain the volume in cubic yards.

    Prof Awad S. Hanna

  • Project Site Showing 100 StationsFillCut8082848688808486888278ABCDEFABCDEF100'100'100'100'100'500'300'

    Prof Awad S. Hanna

  • 80787682807884828086848886908878.580.382.384.286.288.2Sec. A- ASec. B- BSec. C- CSec. D- DSec. E- ESec. F- FProject Cross Sections

    Prof Awad S. Hanna

  • Cross-Section @ A- A807978777679.578.576.7Section A- AArea == 173.7193 x 1.82Area == 53.5107 x 1.02

    Prof Awad S. Hanna

  • Cross-Section @ B- B828180797881.880.376.7Section B- BArea == 189.0210 x 1.82Area == 67.590 x 1.52

    Prof Awad S. Hanna

  • Table 1. Cumulative Earthwork Quantities

    Prof Awad S. Hanna

    Section

    Emb (CCY)

    Exc. (BCY)

    Exc. x B/C (CCY)

    Net Exc. (CCY)

    Cum Exc (CCY)

    A-B

    672

    224

    254

    - 418

    - 418

    B-C

    567

    441

    499

    - 68

    - 486

    C-D

    215

    791

    896

    681

    195

    D-E

    0

    1031

    1167

    1167

    1362

    E-F

    0

    1222

    1384

    1384

    2746

  • 2. Contour Line/ Grid MethodUsed for parking lots and site levelingGrid size from 10x10 to 50x50the greater the terrain variance the smaller the grid

    Prof Awad S. Hanna

  • 2. CONTOUR LINE/GRID CELL METHOD(cont.)Step lDetermine by visual study of the site drawing if the net total will be an import (more fill required than cut) an export (less fill required than cut) or a blend (cut and fill about equal)

    Step 2Determine the pattern of calculation points or grid size.

    Step 3 Determine elevations at each calculation location, the corners of each grid.

    Step 4 Calculate the cubic yards of cut or fill required in each grid cell.

    Step 5Add the individual Grid Cell quantities together to arrive at the total cut, total fill volume and the import or volume export yardage required for the job.

    Prof Awad S. Hanna

  • ABCDEF87.688.689.490.491.693.2GHJKLM87.488.289.590.691.692.7NOPQRS87.287.789.090.491.392.087.688.589.390.391.595.094.393.593.1ABCDEFG30088899091929394No ScaleNotes:1. Bring the entire site to elevation 90.2. All grids are 50x 50 = 2500 sq. ft.3. Present contours

    Prof Awad S. Hanna

  • PurposeGrade the entire site to grade 90

    Quick and DirtyAssume one gridExisting90.50Proposed90.00Cut 0.50Total Cost = = 833CY150 x 300 x 0.5027300'150'NeedFillNeedCut90'90'91'90.5'

    Prof Awad S. Hanna

  • Average elevation== 88.08change= 90-88.08= 1.92cut== 177.77 CYand so on.If we choose the grid size to be 50x5087.6+88.5+87.6+88.6487.688.687.687.6

    Prof Awad S. Hanna

    Prof Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. Hanna7Prof Awad S. HannaProf Awad S. Hanna6Prof Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. Hanna2Prof Awad S. Hanna3Prof Awad S. Hanna4Prof Awad S. Hanna5Prof Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. Hanna9Prof Awad S. HannaProf Awad S. HannaProf Awad S. Hanna