Upload
krishna-kadam
View
12
Download
0
Tags:
Embed Size (px)
DESCRIPTION
earth
Citation preview
ESTIMATING EARTHWORK
Prof Awad S. Hanna
Estimating EarthworkEarthwork includes:1.Excavation2.Grading: Moving earth to change elevation3.Temporary shoring4.Back fill or fill: Adding earth to raise grade5.Compaction: Increasing density6.Disposal
Prof Awad S. Hanna
Productivity FactorsA. Job conditionsMaterial typeWater level and moisture contentJob sizeLength of haulHaul road condition (accessibility and load restrictions)
Prof Awad S. Hanna
Productivity Factors (cont.)B. Management conditionsEquipment conditions and maintenance practicesSkills of work force and managementPlanning, supervision and coordination of work.
Prof Awad S. Hanna
Job Efficiency Factors for Earthmoving Operations
Prof Awad S. Hanna
Sheet1
Management Conditions*
Job Conditions**ExcellentGoodFairPoor
Excellent0.840.810.760.70
Good0.780.750.710.65
Fair0.720.690.650.60
Poor0.630.610.570.52
Sheet2
Sheet3
Units of MeasureCubic Yard (bank, loose, or compacted)
Prof Awad S. Hanna
Sheet1
Bank (BCY):Materials in its natural state before disturbance (in-place, in-situ)
Loose (LCY):Material that has been compacted or disturbed or loaded
Compacted (CCY):Material after compaction
Sheet2
Sheet3
1.01.250.901.0 CUBIC YARD IN NATURAL CONDITION (IN-PLACE YARD)1.25 CUBIC YARD AFTER DIGGING (LOOSE YARDS)0.90 CUBIC YARD AFTER COMPACTED (COMPACTED YARDS)In placeCompactedLoose
Prof Awad S. Hanna
VolumeBank: VBBank cubic yards (BCY)Density B Lb /BCY
Loose: VlLoose cubic yards (LCY)Density L Lb/LCY
Compacted: VcCompacted cubic yards (CCY)Density C LB/CCY
Prof Awad S. Hanna
Swell:A soil increase in volume when it is excavated.Swell (%) = ( - 1) x 100
Load factor =
Bank Volume = Loose volume x Load factorLoose densityBank densityBank densityLoose density
Prof Awad S. Hanna
Shrinkage:A soil decreases in volume when it is compactedShrinkage (%) = (1 - ) x 100
Shrinkage factor = 1 - ShrinkageCompacted volume= Bank volume x Shrinkage factorBank densityCompacted density
Prof Awad S. Hanna
Approximate Material CharacteristicsExact values will vary with grain size, moisture content, compaction, etc. Test to determine exact values for specific soils.
Prof Awad S. Hanna
Sheet1
MaterialLoose (lb/cy)Bank (lb/cy)Swell (%)Load Factor
Clay, dry2,1002,650260.79
Clay, wet2,7003,575320.76
Clay and gravel, dry2,4002,800170.85
Clay and gravel, wet2,6003,100170.85
Earth, dry2,2152,850290.78
Earth, moist2,4103,080280.78
Earth, wet2,7503,380230.81
Gravel, wet2,7803,140130.88
Gravel, dry3,0903,620170.85
Sand, dry2,6002,920120.89
Sand, wet3,1003,520130.88
Sand and gravel, dry2,9003,250120.89
Sand and gravel, wet3,4003,750100.91
Sheet2
Sheet3
Typical Soil Volume Conversion Factors
Prof Awad S. Hanna
Sheet1
MaterialLoose (lb/cy)Bank (lb/cy)Swell (%)Load Factor
Clay, dry2,1002,650260.79
Clay, wet2,7003,575320.76
Clay and gravel, dry2,4002,800170.85
Clay and gravel, wet2,6003,100170.85
Earth, dry2,2152,850290.78
Earth, moist2,4103,080280.78
Earth, wet2,7503,380230.81
Gravel, wet2,7803,140130.88
Gravel, dry3,0903,620170.85
Sand, dry2,6002,920120.89
Sand, wet3,1003,520130.88
Sand and gravel, dry2,9003,250120.89
Sand and gravel, wet3,4003,750100.91
InitialConvrted to:
Soil TypeSoil ConditionBankLooseCompacted
ClayBank1.001.270.90
Loose0.791.000.71
Compacted1.111.411.00
Common earthBank1.001.250.90
Loose0.801.000.72
Compacted1.111.391.00
Rock (blasted)Bank1.001.501.30
Loose0.671.000.87
Compacted0.771.151.00
SandBank1.001.120.95
Loose0.891.000.85
Compacted1.051.181.00
Sheet2
Sheet3
Estimating Earth work for Trenches and FoundationAngle of Repose2-0or more
Prof Awad S. Hanna
Approximate Angle of ReposeFor Sloping Sides of ExcavationOriginalGround LineSolid Rock, Slate or Cemented Sand and Gravel(90 Deg.)Compacted Angular Gravels1/2:1 (63 Deg.)Recommended Slope for Average Soils1:1 (45 Deg.)Compacted Sharp Sand1 1/2 :1 (33 Deg.)Well Rounded Loose Sand2:1 (26 Deg.)
Prof Awad S. Hanna
Calculating Earthwork Quantities1.End Area Method2.Contour Line/ Grid Method
Prof Awad S. Hanna
1. End Area MethodUsed in sites where length is much greater than width
Prof Awad S. Hanna
CALCULATING EARTHWORK QUANTITIES1. End Area Method
a.Take cross-sections at regular intervals, typically, 100 intervals.
b.Calculate the cross-section end areas
c.The volume of earthwork between sections is obtained by taking the average of the end areas at each station in square feet multiplied by the distance between sections in feet and dividing by 27 to obtain the volume in cubic yards.
Prof Awad S. Hanna
Project Site Showing 100 StationsFillCut8082848688808486888278ABCDEFABCDEF100'100'100'100'100'500'300'
Prof Awad S. Hanna
80787682807884828086848886908878.580.382.384.286.288.2Sec. A- ASec. B- BSec. C- CSec. D- DSec. E- ESec. F- FProject Cross Sections
Prof Awad S. Hanna
Cross-Section @ A- A807978777679.578.576.7Section A- AArea == 173.7193 x 1.82Area == 53.5107 x 1.02
Prof Awad S. Hanna
Cross-Section @ B- B828180797881.880.376.7Section B- BArea == 189.0210 x 1.82Area == 67.590 x 1.52
Prof Awad S. Hanna
Table 1. Cumulative Earthwork Quantities
Prof Awad S. Hanna
Section
Emb (CCY)
Exc. (BCY)
Exc. x B/C (CCY)
Net Exc. (CCY)
Cum Exc (CCY)
A-B
672
224
254
- 418
- 418
B-C
567
441
499
- 68
- 486
C-D
215
791
896
681
195
D-E
0
1031
1167
1167
1362
E-F
0
1222
1384
1384
2746
2. Contour Line/ Grid MethodUsed for parking lots and site levelingGrid size from 10x10 to 50x50the greater the terrain variance the smaller the grid
Prof Awad S. Hanna
2. CONTOUR LINE/GRID CELL METHOD(cont.)Step lDetermine by visual study of the site drawing if the net total will be an import (more fill required than cut) an export (less fill required than cut) or a blend (cut and fill about equal)
Step 2Determine the pattern of calculation points or grid size.
Step 3 Determine elevations at each calculation location, the corners of each grid.
Step 4 Calculate the cubic yards of cut or fill required in each grid cell.
Step 5Add the individual Grid Cell quantities together to arrive at the total cut, total fill volume and the import or volume export yardage required for the job.
Prof Awad S. Hanna
ABCDEF87.688.689.490.491.693.2GHJKLM87.488.289.590.691.692.7NOPQRS87.287.789.090.491.392.087.688.589.390.391.595.094.393.593.1ABCDEFG30088899091929394No ScaleNotes:1. Bring the entire site to elevation 90.2. All grids are 50x 50 = 2500 sq. ft.3. Present contours
Prof Awad S. Hanna
PurposeGrade the entire site to grade 90
Quick and DirtyAssume one gridExisting90.50Proposed90.00Cut 0.50Total Cost = = 833CY150 x 300 x 0.5027300'150'NeedFillNeedCut90'90'91'90.5'
Prof Awad S. Hanna
Average elevation== 88.08change= 90-88.08= 1.92cut== 177.77 CYand so on.If we choose the grid size to be 50x5087.6+88.5+87.6+88.6487.688.687.687.6
Prof Awad S. Hanna
Prof Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. Hanna7Prof Awad S. HannaProf Awad S. Hanna6Prof Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. Hanna2Prof Awad S. Hanna3Prof Awad S. Hanna4Prof Awad S. Hanna5Prof Awad S. HannaProf Awad S. HannaProf Awad S. HannaProf Awad S. Hanna9Prof Awad S. HannaProf Awad S. HannaProf Awad S. Hanna