DVR2000E Training--SECT #2 (Hardware Install)

Embed Size (px)

Citation preview

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    1/13

    DVR

    2000E / DVR

    2000ECHardware Installation

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    2/13

    2

    DVR2000E/EC Hardware Installation- IOM Reference -

    This section will discuss the installation of the

    DVR2000E/EC hardware. This is discussedin detail in the DVR2000E Installation,

    Operation, and Maintenance (IOM) Manual(GPN019 03/06), Pages 26 36.

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    3/13

    3

    DVR2000E/EC Hardware Installation- Mounting -

    The DVR2000E Installation, Operation, andMaintenance (IOM) Manual(GPN019 03/06),

    Pages 26 - 28 provides you the information

    necessary to mount the DVR2000E/EC

    voltage regulator. Please refer to this

    information for:

    Size evaluation,

    A cutout template, and

    Drilling dimensions.

    Ref: IOM, Page 26

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    4/13

    4

    DVR2000E/EC Hardware Installation- Connections -

    The DVR2000E Installation, Operation, andMaintenance (IOM) Manual(GPN019 03/06),

    Pages 29-32 provides you the information

    necessary to connect the DVR2000E/EC

    voltage regulator to your generator. Please

    refer to this information for detailed

    instructions and definitions of each terminal.

    Ref: IOM, Page 26

    NOTE: Be sure that the DVR2000E/ECis hard-wired to earthwith no smaller than 12 AWG copper wire attached to the

    ground terminal on the rear of the unit case.

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    5/13

    5

    Three Phase Sensing

    DVR2000E/EC Hardware Installation- Typical Connection Diagram -

    Ref: IOM, Page 33

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    6/13

    6

    DVR2000E/EC Hardware Installation- Typical Connection Diagram -

    Single Phase Sensing

    Ref: IOM, Page 34

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    7/13

    7

    DVR2000E/EC Hardware Installation- Electrical Connection Notes -

    1. In order to parallel with the DVR2000E/EC, a

    current transformer (CT) MUST be installed in

    the B-phase of the generator and connected to

    the CT1 and CT2 inputs of the regulator.

    2. If installing a CT, always confirm that the dot-

    side is towards the generator as shown in theconnection diagrams.

    Ref: IOM, Page 33

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    8/13

    8

    DVR2000E/EC Hardware Installation- Electrical Connection Notes (Contd) -

    3. To disable the droop circuit (Parallel Control),you MUST SHORT Terminals 52L and 52M.

    This will be necessary to run the generator as

    a stand-alone unit.

    4. To disable the VAR/PF Control(available on

    DVR2000EConly), you MUST SHORT

    Terminals 52J and 52K. This will be necessary

    to run the generator as a stand-alone unit if

    using a DVR2000EC regulator.

    Ref: IOM, Page 33

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    9/13

    9

    DVR2000E/EC Hardware Installation- Typical Cross-Current Connections -

    Connection of (2) Generators

    Ref: IOM, Page 36

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    10/13

    10

    DVR2000E/EC Hardware Installation- Typical Cross-Current Connections -

    Connection of (3+) Generators

    Ref: IOM, Page 36

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    11/13

    11

    DVR2000E/EC Hardware Installation- Electrical Connection Notes (Contd) -

    5. The suggested 0.1 Ohm resistor shown for the

    cross-current (reactive differential) connections

    may need to vary. This burden resistorshould

    have a value approximately (10) times thecross current loop resistance for proper

    differential operation. The volt-ampere (VA)

    capacity of the paralleling current transformersshould be considered after sizing the burden

    resistor.

    Ref: IOM, Page 32

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    12/13

    12

    DVR2000E/EC Hardware Installation- Install Protective Cover -

    NOTE: It is highly recommended that the protective cover be installed on the DVR2000E /

    DVR2000ECwhenever power is applied to the DVR2000E / DVR2000ECas the heat sinks

    on the rear-side of the DVR2000E / DVR2000ECare live when power is applied.

    Ref: IOM, Page 27

  • 7/30/2019 DVR2000E Training--SECT #2 (Hardware Install)

    13/13

    DVR2000E/EC Hardware Installation- End of Section -

    QUESTIONS?