The Township Center Project - 2020
Daily Diary 07-17-2020 Page 1
SUBJECT: DAILY DIARY July 17, 2020
WEATHER: 80’s degrees, sunny.
WORK DAY = 30.
E. P. DOYLE: On-Site Tony all day.
ENGINEERING SOLUTIONS TEAM: Ed on-site on and off.
PREMIUM CONCRETE: Dustin + 2. on-site today.
WALKER: Jose +1 on-site today.
WATER PROOFING: 1 on-site today.
Activities Today:
• Premium worked on punch-list items today.
• Walker on-site to establish the final sub-base finish grade for the basement.
• Water proofer on-site to work on the elevator and the northeast corner.
Activities Monday:
• Concrete for the remaining basement walls is scheduled for Monday.
Critical Path:
• Status of Com Ed Truck and potential bracing?
• Construction and delivery of the pre-cast floor planks.
Pending Items:
• How to backfill the NE corner of the building?
Please advise if there are questions or if I missed anything.
Thank you. Notes by Ed Kalina. / Please advise if there are any further thoughts or questions.
The Township Center Project - 2020
Daily Diary 07-17-2020 Page 2
Premium starting the day.
Premium starting the Day.
The Township Center Project - 2020
Daily Diary 07-17-2020 Page 3
The Outside Basement Walls.
Installing the Insulation.