Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
DFH Collaboration – visit of Uppsala
University & RFR Solutions
DFH Status Overview
Paul Cruikshank for WP6a
10 December 2019 - CERN
Today’s plan
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 2
DFHX pre-serie (#1)
New concept of DFH - Q3, 2019
CDR - 15/10/2019
Advanced 3D design – on-going
Integration in HL-LHC underground – on-going
Detail Design Review – mid Feb 2020
Production Readiness Review - April 2020
3DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank
4
DFHX Design EvolutionDFH Working Reference up to mid-2019
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank
5
13
kA
18
kA
2 kA
DFHX
CDB
DFHX Design EvolutionNew concept & preliminary layout
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank
Why change concept ?
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 6
Assembly & cold testing of key
components validated before
installation in the underground areas.
SC link + DFH + Current leads
Compact design avoids dis-assembly
for installation and re-assembly in the
tunnel – transport as a system.
12
M
DFH Conceptual Design Review 15 Nov 2019, CERN
PH 10 PH 20 PH
30
DFHx sub-components
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 8
Vacuum
instrumentation
HTS cable
Current leads
& housings
(yellow)
Link cryostat
MgB2 link cable
Vacuum
vessel
Helium
vessel
& MLI
Internal
supports
Thermal
shield
& MLI
External
supports
Assembly
rail & tooling
(not shown)
Rupture disc,
safety valve
(not shown)
Uppsala Collaboration Hardware Deliverables
DFHx cryostat cannot be fully
assembled (welded) without the
MgB2 cable and current leads:
At RFR, assemble & cut welds
or assemble without welding &
demonstrate that parts fit
together.
Final assembly & test at Cern
(Cern responsibility)
+ manu drg
+ QA doc
+ testing
+ PED
+ packaging
+ transport
Milestones – DFHx & DFHm
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 9
Milestones are indicative – need to be confirmed within the Uppsala Collaboration Agreement
Assembly of DFHx #1 will provide feedback for optimization of the series units
Each series DFH is assembled with current leads and SC link, then cold tested before installation in the LHC underground in Long Shutdown 3 (2024-2026).
Dates coherent with WP6a global planning
Technologies Technologies are the same as previous concept, presented in
UU/Cern meetings of June ’18 & April ’19 (Yann & Vittorio)
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 10
Procurement Strategy Manufacturing & qualification strategy same as previous concept,
presented at UU/Cern meetings June ’18, Jan ‘19 (Yann & Vittorio).
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 11
PED Conformity Assessment
According to the CERN safety rules GSI-M4 “The manufacture […] by collaborating institutions, of all new cryogenic equipment shall comply with the applicable CERN Safety Rules, European directives and harmonised standards” implies PED 2014/68/EU.
UU & RFR transform Cern’s specification drawings into manufacturing drawings (with or without changes) and perform the structural analysis according to EN13445.
Concerning deliverables, welding and re-cutting the helium pressure vessel is a solution, but WP6a is open to proposals from UU & RFR (& its NoBo).
Next presentations from J. Fleiter & R. Betemps will highlight the proposed assembly sequence and joining details.
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 12
Key documents
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 13
Tech Spec
(for comments)
Func SpecCollaboration
agreement
Latest drafts to Uppsala next week
Jan 2020
April 2020
Specification
drawings
Thanks for your attention
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 14
Spare slides (from CDR)
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 15
What can Uppsala & industrial partner already do ?
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 16
Follow the design development and provide feedback on solutions
Review factory infrastructure needs for the manufacturing, assembly and testing area Separation from incompatible co-activities, handling, etc.
Seek potential suppliers of long lead items Bellows, Forged material, MLI, others.
Study approach to PED conformity assessment Welder and welding qualification, NDT, NoBo advice, strategy for subassemblies
Review approach to leak testing Work with sub-contractor, train personnel, buy testing equipment, etc
Review approach to cleaning Facilities required, handling, training, etc.
Evaluate if personnel can benefit from a short stay at Cern Techniques: MLI, insulating supports, leak testing, cleaning, clean (HV) assembly,
auto welding & cutting solutions, etc.
Prepare the quality assurance follow-up Establish contact with the Cern QA representative
Prepare the Manufacturing and Test Folder
Manufacturing, qualification and QADesign phase : CERN supply specification drawings acc. ISO-GPS
Procurement
Design, calculation reports, Technical specifications (PED, HL-LHC QA spec., CE certif.)
CERN approval before release
Manufacturing
MIP, welding book, cleaning, inspection procedures.
Manufacturing drawings produced from CERN specification dwg
CERN approval
Manufacturing process Inspection reports (including certifications)
CERN reports approval
Assembly & qualification phase
Assembly procedures / Inspection and qualification plan
CERN assembly approval
Assembly process Inspection reports
QA follow-up
Upload documentation to MTF
Detailed installation and maintenance procedures
CERN approval
Delivery to CERN
Packing and shipping to CERN
17
CERN database MTF for manufactured products
Non exhaustive list of QA requirements for illustration
From Jan ‘19 meeting
Milestones – DFHx #1
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 18
DFH – Manufacture DFHx #1
Test Proto – assemble & cold test DFHxwith current leads, 100m SC link & DFX in standalone configuration in SM18.
String – (re)assemble* & cold test (as above) as cold powering system to HL Triplet String in SM18.
Spare - Operational spare with SC link attached (DFX proto removed).
*will be possible to keep DFH & SC link attached after the ‘Test Proto’.
2020
2021
2022-2023
2024
WP6a global planning
DFHx Design Development
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 19
Today Design phase 1 Design phase 2
CDR
3D model
3D mock-up
Func spec
Interfaces
Integration
Tech* & Interface spec,
Instrumentation PIDs,
Integration studies,
PED calcs* & 3D iteration,
Risk analysis,
Assembly procedure
DDR,
Manu 2D drgs,
Safety file*,
PED report*,
Manu/insp plan,
PRR (with Uppsala).
Coordination P. Cruikshank
Engineering Y. Lecercq
Design R. Betemps
Integration P. Fessia
Transport & handling C. Bertone
MgB2 & HTS splices J. Fleiter
Warm powering M. Martino
Cryogenics S. Claudet
Quench protection F. Rodriguez-Mateos
Safety V. Parma, T. Otto.
Roles:
Priorities:
• Restart DFH technical meetings in
parallel with integration studies.
• Create a planning with above phases.
• Identify resources for PED analysis.
• Produce specification documents.
*Compliance with:
Cern safety rules,
GSI-M-04 (cryo),
PED 2014/68/EU.
Preparing for DFH cryostat manufacture
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 20
Build the relationship with the Uppsala Collaboration Uppsala Uni team – contacts at Fermilab, CDR, regular dialogue via teleconference (TBD)
Uppsala industrial partner – visits to Cern (next one 10th December), visits to Sweden (to plan).
Formalise the Uppsala Collaboration Finalise the Agreement with scope of supply, deliverables and dates (December)
Agree the communication lines between Cern and the Collaboration.
Knowledge exchange with the Uppsalla Collaboration Identify missing competences (if any) and facilitate a dialogue with TE and EN technical groups as required eg best-
practice solutions (CRG, MSC, EN-MME workshop, etc)
Integrate solutions from the University and industrial partner.
Provide opportunities for learning with Cern teams.
Collaboration shall contribute to the DDR.
Collaboration shall play a leading role in the PRR.
Manage & share the evolution of cryostat interfaces Documents and drawings for internal interfaces - current leads & SC link
Documents and drawing for external interfaces - handling, warm powering, cryo, instrumentation.
3D design pre-validated with mock up
DFH Conceptual Design Review 15 Nov 2019, CERNDFH Conceptual Design Review 15 Nov 2019, CERN
DFHx #1 Cryostat manufacturing & assembly
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 22
Assembly of the DFHx #1 cryostat can’t be made without the DSHx link or HTS current leads
Trial assembly of DFHx cryostat (without lip weld execution) shall be performed in industry using rail system.
Cern may provide subcomponents for trial assembly or instrumentation for final integration.
The methodology to ensure PED compliance of the helium pressure vessel must be agreed.
Technology experts responsible for the DFHx assembly works at Cern (splice, welding, instrumentation, testing, etc) can provide advice on technical solutions being implemented in the production of the cryostat.
Assembly validation at Cern provides the go-ahead for DFH series production.
Preparation of infrastructure and resources for the DFHx #1 assembly works at Cern will begin Q3 2020.
Design & Integration - DFHX
DFH - UU & RFR visit - 10th Dec 2019 – P. Cruikshank 23
Integration review, end Jan.
Interfaces OK.
OK for DFH detail design
CDR
DDR PRR