Upload
truongdiep
View
226
Download
2
Embed Size (px)
Citation preview
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 1
TABLE OF CONTENTS
CHAPTER 1. INTRODUCTION ................................................................................. 7
1.1 PROJECT BACKGROUND .................................................................................. 7
1.2 OBJECTIVE OF THE PROJECT ......................................................................... 8
1.3 SCOPE OF THE PROJECT.................................................................................. 9
1.4 SCOPE OF INCEPTION REPORT ..................................................................... 10
1.5 TIME FRAME .................................................................................................... 11
1.6 AGREEMENT .................................................................................................... 11
1.7 EFFECTIVE DATE OF COMMENCEMENT OF SERVICES ............................ 11
1.8 QUALITY ASSURANCE PLAN ......................................................................... 12
1.9 WORK PLAN AND DELIVERABLES ................................................................ 12
1.10 POSSIBLE CONSTRAINTS ............................................................................... 12
1.11 STRUCTURE OF THE REPORT ....................................................................... 13
CHAPTER 2. PROJECT APPRECIATION ............................................................... 14
2.1 SITE VISITS ...................................................................................................... 14
2.2 LOCATION MAP ............................................................................................... 14
2.3 PROJECT DESCRIPTION ................................................................................. 15
2.4 ABOUT THE PROJECT CORRIOR ................................................................... 18
2.5 TERRAIN ........................................................................................................... 20
2.6 LAND USE ......................................................................................................... 21
2.7 BUILT – UP AREAS .......................................................................................... 22
2.8 CARRIAGEWAY AND SHOULDER WIDTH ..................................................... 23
2.9 EMBANKMENT HEIGHT ................................................................................. 25
2.10 HORIZONTAL ALIGNMENT ............................................................................ 26
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 2
2.11 VERTICAL ALIGNMENT .................................................................................. 30
2.12 JUNCTIONS ...................................................................................................... 31
2.13 PAVEMENT CONDITION ................................................................................. 31
2.14 ROW DETAILS .................................................................................................. 36
2.15 SOIL AND SUBSOIL ......................................................................................... 37
2.16 UTILITIES ALONG THE PROJECT HIGHWAY............................................... 38
2.17 SOCIO RELIGIOUS STRUCTURE AND BUILDINGS ...................................... 38
2.18 BRIDGES AND CROSS DRAINAGE STRUCTURES ........................................ 38
2.19 RESURFACING PROGRAM .............................................................................. 42
CHAPTER 3. APPROACH & METHODOLOGY ...................................................... 44
3.1 GENERAL .......................................................................................................... 44
3.2 OBJECTIVE OF THE STUDY ........................................................................... 44
3.3 APPROACH AND METHODOLOGY ................................................................. 44
3.4 QUALITY ASSURANCE SYSTEM FOR CONSULTANCY ASSIGNMENT ....... 46
3.5 REVIEW OF DATA AND DOCUMENTS ........................................................... 47
3.6 SOCIAL ANALYSIS ........................................................................................... 48
3.7 TRAFFIC SURVEYS .......................................................................................... 48
3.8 ENGINEERING SURVEYS & INVESTIGATIONS............................................ 55
3.9 DETAILED DESIGN OF ROAD AND PAVEMENTS, STRUCTURES .............. 67
3.10 ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT ................................ 73
3.11 ESTIMATION OF QUANTITIES AND PROJECT COSTS ................................ 78
3.12 VIABILITY AND FINANCING OPTIONS ......................................................... 78
CHAPTER 4. TASK ASSIGNMENT AND MANNING SCHEDULE ........................ 81
4.1 INTRODUCTION ............................................................................................... 81
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 3
4.2 TEAM COMPOSITION ...................................................................................... 81
4.3 TASK ASSIGNMENTS ...................................................................................... 81
4.4 TIME SCHEDULE FOR KEY PERSONNEL ..................................................... 90
4.5 PROJECT DURATION & DELIVERABLES ...................................................... 90
4.6 MOBILIZATION ................................................................................................ 91
CHAPTER 5. WORK PROGRAMME ....................................................................... 92
5.1 GENERAL .......................................................................................................... 92
CHAPTER 6. PROFORMA FOR DATA COLLECTION ........................................... 94
CHAPTER 7. DESIGN STANDARDS AND PROPOSED CROSS-SECTIONS ......... 95
7.1 INDICATIVE DESIGN STANDARDS FOR DIVIDED CARRIAGEWAY: .......... 95
7.2 DESIGN STANDARDS ...................................................................................... 95
7.3 TYPICAL CROSS-SECTIONS .......................................................................... 101
CHAPTER 8. KEY PLAN AND LINEAR PLAN ..................................................... 103
CHAPTER 9. DEVELOPMENT PLANS ................................................................ 104
9.1 GENERAL ........................................................................................................ 104
9.2 EXISTING DEVELOPMENT PLANS AND WORK IN PROGRESS: ............... 104
CHAPTER 10. QUALITY ASSURANCE PLAN (QAP) ............................................. 110
10.1 OBJECTIVES OF QAP .................................................................................... 110
10.2 QUALITY ASSURANCE (QA) .......................................................................... 110
CHAPTER 11. DRAFT DESIGN STANDARDS ....................................................... 112
CHAPTER 12. LAND ACQUISITION PLAN ........................................................... 118
12.1 LAND ACQUISITION PLAN ........................................................................... 118
CHAPTER 13. SUMMARY AND CONCLUSIONS .................................................. 119
13.1 SUMMARY ....................................................................................................... 119
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 4
13.2 CONCLUSIONS / NEXT STEP ........................................................................ 119
Tables
Table 2.1 Summary of Existing and Design Chainage ................................................ 18
Table 2.1 Location of major villages/population centres enroute. ............................... 22
Table 2.2 Details of Carriageway and Shoulder .......................................................... 25
Table 2.3 Horizontal Curve details for the alignment ................................................. 26
Table 2.4 Major Intersections ...................................................................................... 31
Table 2.5 Pavement Condition along the alignment ................................................... 32
Table 2.6 Existing Right of Way along the Alignment ................................................ 36
Table 2.7 Summary of Existing Bridges and Culverts ................................................ 38
Table 2.8 Major Bridge ................................................................................................. 39
Table 2.9 Minor Bridge ................................................................................................ 40
Table 2.10 Details of Resurfacing Section and length of BBD Survey ......................... 42
Table 3.1 Traffic surveys and Durations ..................................................................... 48
Table 3.2 Traffic Survey Locations for TVC, OD and Axle Load Surveys .................. 49
Table 3.3 Turning Movement Count Survey Locations ............................................... 50
Table 4.1 Team Composition ........................................................................................ 81
Table 4.2 Manning Schedule ........................................................................................ 90
Table 4.3 Project Deliverables...................................................................................... 90
Table 5.1 Work Programme ......................................................................................... 92
Figures
Figure 2.1 Location Map ................................................................................................ 14
Figure 2.2 Key Plan showing the alignment ................................................................. 15
Figure 2.3 Alignment of Wainganga River and bridge over Godavari river ................ 16
Figure 2.4 Key plan showing important locations around the Project Corridor .......... 17
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 5
Figure 2.5 The profile of the terrain along the project corridor .................................... 21
Figure 2.6 Cross Section for existing 4 Lane ................................................................. 24
Figure 2.7 Cross Section for existing 2 Lane ................................................................. 24
Figure 2.8 Cross Section for existing Intermediate Lane. ............................................ 24
Figure 7.1 The typical cross-section of new 4-lane with paved shoulder.................... 102
Figure 7.2 The typical cross-section of new 2-lane with paved shoulder.................... 102
Figure 8.1 Location Map .............................................................................................. 103
Abbreviations
AADT Annual Average Daily Traffic
AASHTO American Association of State Highway and Transportation Officials
ADB Asian Development Bank
ADT Average Daily Traffic
BBD Benkelman Beam Deflection
BIS Bureau of Indian Standard
BOQ Bill of Quantities
BOT Built, Operate and Transport
CA Concession Agreement
CBR California Bearing Ratio
DBFOT Design, Build, Finance, Operate and Transfer
DPR Detailed Project Report
DTM Digital Terrain Model
EIA Environment Impact Assessment
EL Electrical Lines
FSR Feasibility Study Report
GAD General Arrangement Drawing
GFC Good for Construction
Govt. Government
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 6
GSB Granular Sub Base
IRC Indian Road Congress
IRC-SP Indian Road Congress – Special Publication
IE/IC Independent Engineer / Independent Consultant
LA Land Acquisition
MORT&H Ministry of Road Transport & Highway
IAHE Indian Academy of Highway Engineers
NH National Highway
PWD Public Work Department
MSH Major State Highway
OD Origin – Destination
OFC Optical Fiber Cable
PUP Passenger Underpass
QAP Quality Assurance Plan
RFP Request for Proposal
ROB Road over Bridge
ROW Right of Way
RUB Road under Bridge
SMA Stone Mastic Asphalt
SPT Standard Penetration Test
TOR Terms of Reference
VDF Vehicle Damage Factor
VUP Vehicular Underpass
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 7
CHAPTER 1. INTRODUCTION
1.1 PROJECT BACKGROUND
Indian Academy of Highway Engineers (IAHE), a premium organization under the aegis
of Ministry of Road Transport & Highways (MORTH) has undertaken formulation of
Detailed Project Reports (DPR) under Phase I in the states of Maharashtra, Karnataka,
Gujarat, Chhattisgarh and Rajasthan. In the state of Maharashtra, Nagpur – Sakoli-
Gadchiroli – Chamorshi – Ashti – Nagepalli - Sironcha forms an important highway for
movement of goods from Nagpur southwards as also is the main artery serving the
relatively underdeveloped areas of Gadchiroli district. This highway recently upgraded
as NH 353 C, from Sakoli to Sironcha, is an amalgamation of erstwhile State Highway
(SH) 11 and State Highway (SH) 9. The project length of 204 kms which runs entirely in
Gadchiroli district is currently of the specification of a Major District Road (MDR).It is
anticipated that in view of a major bridge under construction on Godavari River near
Sironcha, likely to be completed by the year 2016, movement of goods and associated
vehicular traffic from Vidharba, Raipur to Telangana and southern Chattisgarh will be
greatly facilitated. As such the vehicular traffic along this highway now declared as
national highway is likely to increase appreciably. Currently the existing highway is a
SH specification and the proposal is to upgrade this to NH specifications. The existing
road till recently was an MDR and the alignment passes through low lying areas of river
Wainganga as also large tracts of Reserved forest. A number of major bridges exist on
the highway which were constructed in late eighties. There is substantial scope for
Upgradation in the status of bridges as also the alignment for an all-weather road.
It is appreciated that over a horizon of next 20-30 years, this road will serve a critical
purpose of linking Vidharba and parts of northern Chattisgarh to Telangana and
southern parts of Chattisgarh which are mineral rich, thus contributing substantially
towards development of the local economy. Further a number of remote villages are also
being provided connectivity under the PMGSY and the take-off points emanate from this
highway.
With a view to upgrade and rehabilitate the existing highway where necessary, Indian
Academy of Highway Engineers (IAHE) has envisioned preparation of the DPR. M/S
Infra Support Engineering Consultants Pvt. Ltd (ISECPL) have been assigned the task
of preparation of the DPR with main objectives as follows.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 8
Upgradation of existing highway to two lane /four lane with paved shoulders.
Financial analysis and cost estimate for the project.
Preparation of contract documents for EPC and PPP mode.
Traffic study and location of toll plazas.
Obtain MOEF clearance as also submit draft notifications for land acquisition as
per NHAI or State Act.
1.2 OBJECTIVE OF THE PROJECT
The main objective of the consultancy service is to establish the technical,
economical, and financial viability of the project and prepare detailed project
reports for rehabilitation and upgrading of the existing road to 2/4 lane
configuration.
The viability of the project shall be established taking into account the
requirements with regard to rehabilitation, upgrading and improvement based
on highway design, pavement design, provision of service roads wherever
necessary, type of intersections, rehabilitation and widening of existing and/or
construction of new bridges and structures, road safety features, quantities of
various items of works and cost estimates and economic analysis.
The Detailed Project Report would inter-alia include detailed highway design,
design of pavement and overlay with options for flexible or rigid pavements,
design of bridges and cross drainage structures and grade separated structures,
design of service roads, quantities of various items, detailed working drawings,
detailed cost estimates, economic and financial viability analyses, environmental
and social feasibility, social and environmental action plans as appropriate and
documents required for tendering the project on commercial basis for
international / local competitive bidding.
To incorporate aspects of value engineering, quality audit and safety audit in
design and implementation.
Along with Feasibility Report, clearly bring out through financial analysis the
preferred mode of implementation on which the Civil Works for the stretches are
to be taken up. Also provide cost estimates and tender documents along with
feasibility report/ Detailed Project Report.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 9
1.3 SCOPE OF THE PROJECT
General Scope of Services shall cover but be not limited to the following major tasks:
i. Review of all available reports and published information about the project road
and the project influence area;
ii. Environmental and social impact assessment, including such as related to
cultural properties, natural habitants, involuntary resettlement etc.
iii. Public consultation, including consultation with Communities located along the
road, NGOs working in the area, other stake-holders and relevant Govt.
departments at all the different stages of assignment (such as inception stage,
feasibility stage, preliminary design stage and once final designs are concretized).
iv. Detailed reconnaissance;
v. Identification of possible improvements in the existing alignment and bypassing
congested locations with alternatives, evaluation of different alternatives
comparison on techno-economic and other considerations and recommendations
regarding most appropriate option;
vi. Traffic studies including traffic surveys and Axle load survey and demand
forecasting for next thirty years;
vii. Inventory and condition surveys for road;
viii. Inventory and condition surveys for bridges, cross-drainage structures, other
Structures, river Bank training/Protection works and drainage provisions;
ix. Detailed topographic surveys using Total Stations and GPS;
x. Pavement investigations;
xi. Sub-grade characteristics and strength: investigation of required sub-grade and
sub-soil characteristics and strength for road and embankment design and sub
soil investigation;
xii. Identification of sources of construction materials;
xiii. Detailed design of road, its x-sections, horizontal and vertical alignment and
design of embankment of height more than 6m and also in poor soil conditions
and where density consideration require, even lesser height embankment.
xiv. Detailed design of structures preparation of GAD and construction drawings,
cross-drainage and underpasses etc.
xv. Identification of the type and the design of intersections;
xvi. Design of complete drainage system and disposal point for storm water
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 10
xvii. Value analysis / value engineering and project costing;
xviii. Economic and financial analyses;
xix. Contract packaging and implementation schedule.
xx. Strip plan indicating the scheme for carriageway widening, location of all
existing utility services (both over- and underground) and the scheme for their
relocation, trees to be felled, transplanted and planted and land acquisition
requirements including schedule for LA: reports documents and drawings
arrangement of estimates for cutting/ transplanting of trees and shifting of
utilities from the concerned department;
xxi. To find out financial viability of project for implementation and suggest the
preferred mode on which the project is to be taken up.
xxii. Preparation of detailed project report, cost estimate, approved for construction
drawings, rate analysis, detailed bill of quantities, bid documents for execution of
civil works through budgeting resources.
xxiii. Design of toll plaza and identification of their numbers and location and office
cum residential complex including working drawings
xxiv. Design of weighing stations, parking areas and rest areas.
xxv. Any other user oriented facility enroute toll facility.
xxvi. Tie-in of on-going/sanctioned works of MORT&H/ NHAI/ other agencies.
xxvii. Preparation of social plans for the project affected people as per policy of the
lending agencies/ Govt. of India R & R Policy.
1.4 SCOPE OF INCEPTION REPORT
The inception report shall cover the following major aspects:
i. Project appreciation;
ii. Detailed methodology to meet the requirements of the TOR finalized in
consultation with the IAHE officers; including scheduling of various sub
activities to be carried out for completion of various stages of the work; stating
clearly their approach & methodology for project preparation after due inspection
of the entire project stretch and collection/ collation of necessary information;
iii. Task Assignment and Manning Schedule;
iv. Work programme;
v. Proforma for data collection;
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 11
vi. Design standards and proposed cross-sections;
vii. Key plan and Linear Plan;
viii. Development plans being implemented and / or proposed for implementation in
the near future by the local bodies and the possible impact of such development
plans on the overall scheme for field work and design for the study;
ix. Quality Assurance Plan (QAP) finalized in consultation with IAHE;
x. Draft design standards.
The requirements, if any, for the construction of bypasses should be identified on the
basis of data derived from reconnaissance and traffic studies. The available alignment
options should be worked out on the basis of available maps. The most appropriate
alignment option for bypasses should be identified on the basis of site conditions and
techno-economic considerations. Inception Report should include the details regarding
these aspects concerning the construction of bypasses for approval by IAHE.
1.5 TIME FRAME
The schedule for completion of the assignment is 12 months.
1.6 AGREEMENT
The letter of Acceptance (LOA) dated 15.04.2015 was received through mail. The
agreement for the services was signed on 13-05-2015, which is deemed as the effective
date for the contract agreement.
1.7 EFFECTIVE DATE OF COMMENCEMENT OF SERVICES
At Maharashtra Project Site Office:
Contact Persons : Col. Krishna Swamy, Team Leader
Address : Infra Support Engineering Consultants Pvt. Ltd.,
1st Floor, C/o Shri K B Lokhande, Plot No- 221 A, Dongre
Layout Shradhanand Peth, Nagpur – 440 010
Telephone & Fax : +91 9845288018
E-mail : [email protected]
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 12
At Bangalore Head Office:
Contact Persons : Mr. Rathnakar Reddy K B
Address : Infra Support Engineering Consultants Pvt. Ltd.,
# 934, 3rd Cross, HRBR Layout 1st Block
Kalyananagar, Bangalore 560043, India
Telephone & Fax : +91 80 25421364
E-mail : [email protected]
All field work, analysis of primary and secondary data will be carried out from the Site
office, whereas the designs will be carried out at the Bangalore office. Close liaison will
be maintained with the IAHE office in Delhi
1.8 QUALITY ASSURANCE PLAN
The Quality Assurance Plan, is been submitted to IAHE in separate volume along with
this Report for its comments.
1.9 WORK PLAN AND DELIVERABLES
The Consultant has mobilized experienced personnel for project appreciation and to
carry out necessary surveys and investigations at site from 24 May 2015. The team
composition deployed for this project with their name and respective roles is indicated in
Chapter 5 of this report.
The Consultant has prepared the Work Program in line with the scope and service
mentioned in the scope of work and this is provided in Chapter 5 of this report. The
work program shows the activities, deliverables and their duration.
1.10 POSSIBLE CONSTRAINTS
As far as possible, the widening work shall be planned within the existing Right of Way
(ROW). The existing profile of the roadway shall be maintained to avoid any new land
acquisitions and to retain existing bridges. This would also have minimal environmental
disturbances.
We foresee that there are number of constraints that would influence the design of the
project road. Those constraints are:
• Preferring to be within the ROW in case of sharp curves and other improvements.
• To retain any existing Bridge/structures.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 13
• To obviate passing through Forests and towns etc.
• To initiate a separate study for river training work, river course change &
management and geological, geophysical characteristics of the region.
• Any foreseen hindrance expected for carrying out the design or deviation from
Standard designs for easy implementation.
Therefore, a design philosophy is to be prepared listing out the constraints where IRC
guidelines can be compromised. Design philosophy would be the guiding line to achieve
the objective of this project which is complying with IRC norms within the threshold of
developed criteria wherever possible.
However, even after ascertaining the various pros and cons of each individual
problems/deviation from standards, the final decision from the client would help the
consultants to finalize the design philosophy. We would look forward for such a
discussion with the client (IAHE) at an early date.
1.11 STRUCTURE OF THE REPORT
The Inception Report has been structured into thirteen chapters as follows:
Chapter 1. Introduction
Chapter 2. Project Appreciation
Chapter 3. Approach & Methodology
Chapter 4. Review of Available Data and Design
Chapter 5. Task Assignment and Manning Schedule
Chapter 6. Work Programme
Chapter 7. Proforma for Data Collection
Chapter 8. Design Standards and Proposed Cross-Sections
Chapter 9. Key Plan and Linear Plan
Chapter 10. Development Plans Statutory and Municipal Bodies
Chapter 11. Quality Assurance Plan (QAP)
Chapter 12. Draft Design Standards
Chapter 13. Summary and Conclusions
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 14
CHAPTER 2. PROJECT APPRECIATION
2.1 SITE VISITS
The site was visited by the team leader and some supporting staff from 08th April 2015
to 10th April 2015 to collect relevant information and data from the site. Discussions
were carried out with local PWD officials to get know about the project corridor, recent
developments other information about the corridor.
2.2 LOCATION MAP
A location map of the project road is given in Figure 2.1.
Figure 2.1 Location Map
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 15
2.3 PROJECT DESCRIPTION
The project alignment, renamed as NH353 C, commences from Sakoli in Nagpur district
and terminates at Sironcha over a length of 318.00 kms. Sakoli with start Chainage as
0+000, terminates at Sironcha with Chainage as 318+000. Towns of Gadchiroli @ Ch:
113+650, Chamorshi @ Ch: 147+000, Ashti @ Ch: 179+000, Allapalli @ Ch: 224+700 are
located enroute. There are 11 major bridges along the alignment. A sketch indicating the
complete alignment as well as the key plan is shown below in Figure 2.2. Wainganga is
a major river in this area which runs almost parallel to the project alignment. During
rainy season the river is prone to flooding leading to inundation in certain parts of the
highway. Figure 2.3 shows the alignment of Wainganga River along the project corridor.
Figure 2.4 shows the major traffic originating places around the corridor.
Figure 2.2 Key Plan showing the alignment
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 16
Figure 2.3 Alignment of Wainganga River and bridge over Godavari river
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 17
Figure 2.4 Key plan showing important locations around the Project Corridor
Project Road Gadchiroli to Sironcha
AH-43/NH-7 Hyderabad to Nagpur
AH-46 Nagpur to Raipur
NH-43 Raipur to Vishakapatnam (AH-45)
NH-221 Jagdalpur to Vijayawada
NH-16 Nizamabad to Jagdalpur
NH-202 NH-16 (Bhopalpatnam) to Hyderabad
MSH-9 Nagpur to Sironcha via Chandrapur
MSH-7 MSH-7 (Tekadi) to Durg
MSH-5 AH-46 (Rajnandgaon) to NH-221 (Errabore)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 18
This project alignment, from Gadchiroli to Sironcha is an amalgamation of erstwhile
State Highway - 11 (66.550 Km) and State Highway - 9 (138.000 Km). The Summary of
Proposed Chainage and existing Chainage are given in Table 2.1.
Table 2.1 Summary of Existing and Proposed Chainage
2.4 ABOUT THE PROJECT CORRIDOR
Start and End of the Project Corridor
The project alignment, commences from Sakoli in Nagpur district and terminates at
Sironcha over a length of 318.0kms. Sakoli with start Chainage as 0+000, terminates at
Sironcha with Chainage as 318+000. Presently, state highway kilometer markings are
at the site and the project corridor appears to start at km 172+650 as per kilometer
markings (MSH 11). MSH 11 Chainage has been compared with the NH 353 C
Chainage and Chainage at the starting point ,i.e. Proposed Chainage of NH 353 C for
the present project is 113+650 Km at Indira Square Junction in Gadchiroli.
The road traverses through Gadchiroli district of Maharashtra via Gadchiroli,
Chamorshi, Ashti and Allepalli and reaches end point at Sironcha at Chainage 318+200
Km.
Proposed Chainage (NH-353C) Length (Kms)
Existing Chainage Length (Kms) State Highway
Start End Start End
113+650 115+200 1+550 172+650 174+200 1+550 MSH 11
115+200 179+000 63+800 174+200 238+000 63+800 MSH 11
179+000 318+000 138+900 213+500 352+400 138+900 MSH 09
Starting Point (Indira Square) @ Ch: 113+650 (Design Chainage)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 19
Chamorshi Town @ Ch: 147+000 (Design Chainage)
Allapalli Aheri Road Junction @ Ch: 224+700 (Design Chainage)
Ashti Chowk @ Ch: 179+000 (Design Chainage)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 20
2.5 TERRAIN
The complete alignment generally passes through a rolling terrain. The portion of the
highway from Gadchiroli up to Ashti passes through relatively less dense forest area
with sparsely populated villages on both sides. Beyond Ashti, the terrain gradually
changes to deep forest cover with decreasing habitation. Beyond Allapalli up to Sironcha
the road passes through dense forest interspersed with sharp bends at number of places.
Table 2.1 Details of Forest Area.
Sl. No.
Segment details Segment Length in
Km
Forest Area Length in
Km
Protected Forest Area Length in
Km
No Forest Area Length
in Km
1 Gadchiroli to Chamorshi 34.35 3.0 31.35
2 Chamorshi to Ashti 32.7 11.4 21.3
3 Ashti to Allapalli 45.0 24.9 20.1
4 Allapalli to Sironcha 92.5 71.7 1.7 19.1
Total Length 204.55 111 1.7 91.85
End Point, Sironcha @ Ch: 318+200 (Design Chainage)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 21
Figure 2.5 The profile of the terrain along the project corridor
2.6 LAND USE
The largest proportion of land abutting the alignment is forest land followed by
agricultural and then built-up areas. The forest area starts typically from km 179+000
and continues till the end of the project.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 22
2.7 BUILT – UP AREAS
As mentioned earlier, Chamorshi, Ashti, Allepalli and Sironcha are major settlements
along the alignment. These towns are presently midsize towns but are likely to grow in
size subsequent to Upgradation of the highway. It is anticipated that both passenger
and goods traffic is likely to increase substantially and the existing alignment is likely
to create substantial bottlenecks in negotiating the built up areas. As such it is felt that
some of the towns would need a bypass to facilitate smooth flow of traffic. Whereas the
town of Allepalli has already been bypassed by re-alignment of SH-9, it is proposed to
examine feasibility of provision of bypasses in towns of Gadchiroli, Chamorshi and
Ashti. At Gadchiroli a proposal for bypass has been prepared by the Maharashtra Govt
PWD department in the year 2012. The alignment would be scrutinized and modified to
meet design requirements. At Chamorshi a fresh alignment for bypass is proposed.
A detailed list of built up areas along the existing corridor is given in the Table 2.2
below.
Table 2.2 Location of major villages/population centers enroute.
Proposed Chainage (NH-353C) Existing Chainage (MSH) Village
Start End Start End
113+650 114+000 172+650 173+000 Gadchiroli
130+000 131+000 189+000 190+000 Darshni
136+000 137+000 195+000 196+000 Kunghada
138+000 139+000 197+000 198+000 Talodhi
143+000 144+000 202+000 203+000 Kurud
146+000 147+000 205+000 206+000 Deoli
147+000 148+000 206+000 207+000 Chamorshi
151+000 152+000 210+000 211+000 Sonapur
157+000 158+000 216+000 217+000 Jamgiri
161+000 162+000 220+000 221+000 Adyal
163+000 164+000 222+000 223+000 Chittaranjanpur
164+000 165+000 223+000 224+000 Yenapur
171+000 172+000 230+000 231+000 Konsair
173+000 174+000 232+000 233+000 Umri
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 23
Proposed Chainage (NH-353C) Existing Chainage (MSH) Village
177+000 178+000 236+000 237+000 Ankhoda
179+000 180+200 238+000 239+200 Ashti
180+200 180+700 213+500 214+000 Ashti Chowk
191+700 192+700 225+000 226+000 Chaudampalli
201+700 202+700 235+000 236+000 Lagam
202+700 203+700 236+000 237+000 Chutugunta
204+700 205+700 238+000 239+000 Shantigram
207+700 208+700 241+000 242+000 Bori
212+700 213+700 246+000 247+000 Subhashnagar
214+700 215+700 248+000 249+000 Khamancheru
223+700 224+700 257+000 258+000 Nagepalli
224+700 225+700 258+000 259+000 Alapalli
235+700 236+700 269+000 270+000 Mosam
240+700 241+700 274+000 275+000 Nandigaon
241+700 242+700 275+000 276+000 Timram
242+700 243+700 276+000 277+000 Guddigudam
244+700 245+700 278+000 279+000 Nimalgudam
248+700 249+700 282+000 283+000 Golakarje
263+700 264+700 297+000 298+000 Gundera
276+700 277+700 310+000 311+000 Umanur
296+700 297+700 330+000 331+000 Bamani
299+700 300+700 333+000 334+000 Garkapetha
306+700 307+700 340+000 341+000 Rangayapalli
308+700 309+700 342+000 343+000 Amaravati
315+700 316+700 349+000 350+000 Karaspalli
317+700 318+200 351+000 351+500 Sironcha
2.8 CARRIAGEWAY AND SHOULDER WIDTH
The project highway is a four lane divided carriageway facility at the starting point from
Ch: 113+650 to 115+200 for about 1.50 Km. Then the carriageway reduces to Two lane
configuration from Ch: 115+200 to 179+000Km for a length of 63.80 Km. Subsequently
the alignment traverses through forest area where the carriageway width reduces to
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 24
intermediate lane standard till end of the project. The pattern of existing carriageway
for two lane and four lane is shown below in Figure 2.6 to Figure 2.8 in the form of cross-
sections.
Figure 2.6 Cross Section for existing 4 Lane
Figure 2.7 Cross Section for existing 2 Lane
Figure 2.8 Cross Section for existing Intermediate Lane.
The detail of existing width of carriageway along the project length is shown below in
Table 2.3. It is noticed that more than three fourth of the project length consists of
intermediate width configuration.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 25
Table 2.3 Details of Carriageway and Shoulder
Proposed Chainage (NH-353C) Length (Kms)
Existing Chainage Length (Kms)
Road Condition
Width (m)
Start End Start End
113+650 115+200 1+550 172+650 174+200 1+550 4 Lane 7.0 + 1.2 + 7.0
115+200 179+000 63+800 174+200 238+000 63+800 2 Lane 7.0
179+000 318+000 138+900 213+500 352+400 138+900 Intermediate Lane 5.5
2.9 EMBANKMENT HEIGHT
The embankment height of the carriageway varies between 1-2 meters along the
complete length of the project. The project is generally devoid of any high embankments
except for certain approaches to major bridges. The height varies between being at
ground level in some built up stretches to about 5m in the approaches of some of the
major bridges. Simple earthen slopes have been commonly used with chute drains at
30m spacing. In the portion of the project between Chamorshi and Gadchiroli, it has
been observed that the road gets submerged during monsoon season owing to overflow of
water from river Wainganga. The HFL recorded data would be examined and suitable
corrective measures would be suggested.
Embankment profile at chainage 322+000 Embankment profile at chainage 317+000
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 26
2.10 HORIZONTAL ALIGNMENT
The highway basically follows the alignment of MDR upgraded from ODR over the
years. Most of the places the alignment is over steep curves and sharp bends which
would need improvement as per the geometric requirement of NH Two lane/Four lane
specifications. The details of sharp curves which require improvement is shown below.
In accordance with provisions of clause 2.2 of IRC SP: 73-2007, the existing alignment
would be examined and realignment suggested where essential.
Table 2.4 Horizontal Curve details for the alignment
Embankment profile at chainage 256+000 Embankment profile at chainage 26+000
At grade profile at chainage 280+000Embankment profile at chainage 177+000
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 27
Sl. No.
Chainage Design Speed
1 113+785 80
2 114+091 80
3 115+882 100
4 116+336 100
5 116+731 65
6 117+347 65
7 117+563 65
8 118+257 100
9 118+874 100
10 119+557 100
11 120+423 100
12 120+909 100
13 121+730 100
14 122+229 100
15 122+753 65
16 123+025 65
17 123+307 100
18 124+078 80
19 124+586 100
20 125+984 80
21 126+493 100
22 126+990 100
23 128+380 80
24 128+858 65
25 129+181 65
26 129+469 50
27 129+741 100
28 130+400 100
29 131+065 65
30 131+409 100
Sl. No.
ChainageDesign Speed
31 132+135 100
32 133+230 100
33 133+630 100
34 134+609 100
35 134+987 100
36 135+770 100
37 136+499 100
38 137+290 100
39 137+752 100
40 138+170 50
41 139+161 100
42 140+052 100
43 140+406 100
44 141+118 80
45 142+912 100
46 144+501 80
47 144+889 80
48 145+952 65
49 146+137 100
50 146+345 80
51 147+840 100
52 148+020 50
53 148+118 11
54 148+913 100
55 150+044 50
56 150+441 50
57 151+158 100
58 152+291 100
59 153+142 50
60 153+862 100
Sl. No.
Chainage Design Speed
61 154+425 80
62 155+658 80
63 156+271 80
64 157+560 100
65 158+621 100
66 159+823 80
67 160+535 50
68 161+809 100
69 162+898 100
70 164+232 80
71 165+189 50
72 166+437 100
73 166+716 80
74 167+568 100
75 168+181 100
76 168+711 100
77 169+444 100
78 171+245 80
79 172+286 80
80 173+557 100
81 175+226 100
82 175+759 100
83 176+197 100
84 177+276 100
85 178+306 80
86 179+097 80
87 180+403 80
88 180+620 0
89 182+302 80
90 184+271 50
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 28
Sl. No.
Chainage Design Speed
91 185+278 100
92 186+136 100
93 186+782 50
94 187+493 65
95 188+898 100
96 189+594 80
97 189+951 80
98 190+432 100
99 191+758 65
100 192+015 50
101 192+369 50
102 192+682 65
103 193+470 100
104 194+562 80
105 194+815 80
106 195+446 65
107 196+067 40
108 196+522 100
109 197+836 100
110 198+548 65
111 199+117 65
112 199+884 80
113 200+702 100
114 201+601 50
115 201+958 65
116 203+200 100
117 203+411 100
118 203+855 100
119 204+618 100
120 205+540 100
Sl. No.
ChainageDesign Speed
121 206+303 100
122 206+723 100
123 207+539 100
124 208+610 100
125 208+905 100
126 209+612 100
127 211+242 100
128 211+664 50
129 211+893 80
130 212+420 80
131 213+026 100
132 214+289 80
133 215+514 65
134 216+375 50
135 217+170 80
136 218+017 100
137 218+957 40
138 220+178 65
139 221+077 50
140 221+428 80
141 221+917 65
142 222+497 65
143 222+692 65
144 222+938 50
145 223+400 100
146 223+741 80
147 224+186 65
148 224+958 80
149 225+366 100
150 226+248 100
Sl. No.
Chainage Design Speed
151 226+909 80
152 227+336 50
153 229+400 100
154 230+304 100
155 231+991 100
156 233+141 100
157 233+534 100
158 233+887 100
159 234+681 100
160 234+949 100
161 235+598 80
162 235+966 100
163 236+235 80
164 237+537 50
165 237+935 50
166 238+865 65
167 239+284 100
168 239+611 50
169 240+150 50
170 240+442 50
171 241+761 50
172 241+880 50
173 242+061 100
174 242+263 100
175 245+530 50
176 245+712 50
177 246+019 50
178 246+625 100
179 247+620 100
180 249+038 65
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 29
Sl. No.
Chainage Design Speed
181 249+381 100
182 249+665 100
183 250+439 80
184 250+829 100
185 251+473 100
186 252+848 100
187 253+264 65
188 253+492 65
189 253+887 100
190 254+160 50
191 254+392 65
192 254+949 80
193 255+200 80
194 257+168 80
195 257+739 100
196 258+655 80
197 259+287 65
198 260+409 65
199 260+754 65
200 260+920 65
201 261+240 50
202 261+361 50
203 261+957 100
204 263+819 100
205 264+551 100
206 265+100 100
207 265+470 65
208 265+691 65
209 265+830 50
210 267+009 100
Sl. No.
ChainageDesign Speed
211 267+781 80
212 268+277 80
213 268+589 80
214 269+289 100
215 270+376 100
216 270+971 80
217 272+462 100
218 273+111 100
219 273+449 80
220 274+290 100
221 275+050 100
222 276+492 80
223 276+866 50
224 276+957 29
225 277+969 100
226 278+387 100
227 279+117 50
228 279+331 50
229 279+553 80
230 279+782 80
231 280+820 80
232 281+169 80
233 282+065 40
234 282+231 50
235 282+382 35
236 282+740 40
237 282+884 35
238 282+950 35
239 283+132 40
240 283+825 40
Sl. No.
Chainage Design Speed
241 283+760 40
242 283+594 50
243 283+736 50
244 283+940 35
245 284+117 35
246 284+555 35
247 284+862 50
248 285+049 40
249 285+143 40
250 285+404 35
251 285+797 50
252 286+058 50
253 286+267 35
254 286+427 35
255 286+617 40
256 286+840 50
257 287+203 50
258 287+403 35
259 287+617 50
260 288+136 40
261 288+600 40
262 288+881 35
263 290+163 53
264 290+294 53
265 290+794 40
266 291+592 53
267 291+827 50
268 291+977 35
269 292+685 40
270 293+235 53
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 30
Sl. No.
Chainage Design Speed
271 293+709 40
272 294+076 50
273 294+646 50
274 295+124 53
275 295+637 50
276 295+746 50
277 296+016 50
278 296+299 53
279 296+426 35
280 296+515 40
281 297+018 53
282 297+631 35
283 297+979 53
284 298+473 50
285 298+651 35
286 299+116 40
287 299+284 50
288 299+531 50
289 299+636 35
290 299+735 50
291 299+847 35
292 300+026 35
293 300+396 50
294 300+543 40
Sl. No.
ChainageDesign Speed
295 300+669 40
296 300+885 53
297 301+200 50
298 301+392 35
299 301+524 35
300 301+692 53
301 301+911 35
302 302+258 75
303 302+643 50
304 303+493 40
305 303+861 50
306 304+065 40
307 304+402 50
308 304+621 40
309 304+986 40
310 305+153 35
311 305+619 50
312 305+721 53
313 305+918 50
314 306+113 40
315 306+412 100
316 306+831 35
317 307+577 40
318 308+998 100
Sl. No.
Chainage Design Speed
319 309+774 50
320 310+136 35
321 310+522 100
322 311+280 100
323 311+463 50
324 311+667 50
325 312+273 35
326 312+887 53
327 313+322 40
328 314+267 35
329 314+773 35
330 315+556 35
331 316+092 35
332 316+673 53
333 317+548 40
334 317+773 53
335 318+780 100
336 319+357 100
337 320+121 100
338 320+739 24
339 320+819 29
340 321+355 100
2.11 VERTICAL ALIGNMENT
The vertical geometry did not appear to be a significant issue. The vertical profile rarely
rises in except at the locations of the structures. On the other hand maintaining the
minimum gradient for drainage may be often inconvenient. It may be pointed out that
the vertical profile appears to conform to Stopping Sight Distance and not the
Intermediate sight distances.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 31
2.12 JUNCTIONS
Few roads intersect the project highway. All intersections are at grade and some of them
are major intersection with state highways or MDR crossing the project alignment and
minor intersections with village road intersecting the project alignment.
Table 2.5 Major Intersections
Sl.No. Location Intersection
Type
Cross Road
Surface Type
1 Starting Point of the Project, Gadchiroli at Ch:113+650
Km (Dhanora – Mul Road, MSH 07) + BT
2 Chamorshi at Ch: 148+100 Km (Mul - Chandrapur Road,
MDR) T BT
3 Ashti at Ch: 180+600 Km (Gadchiroli – Ashti Road
(MSH 11) and Gondpipari – Sironcha Road (MSH 09)) X BT
4 Bypass Alignment for Allapalli at Ch: 225+000 Km
(Aheri Road, MDR) + BT
5 Allapalli – Sironcha Road and Jimalgatta Road Junction
at Ch: 268+900 Km Y BT
6 Allepalli – Sironcha Road and NH 16 Road Junction at
Ch: 316+600 Km T BT
Chamorshi at Ch: 148+100 Km (Mul - Chandrapur Road, MDR)
Starting Point of the Project, Gadchiroli at Ch: 113+650 Km (Dhanora – Mul Road, MSH 07)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 32
`
2.13 PAVEMENT CONDITION
The carriage way width of the roads has two specifications of 7.0 mtrs and 5.5 meters
with 1-1.5 meters of earthen shoulders on either side. Visual inspection of the road
showed a generally good surface condition. Works related to resurfacing have been
carried out recently as also in certain places around Chamorshi they are still in
progress. Approximate 20-30 % of the highway bears damaged riding surface. The
details on above are given in Table 2.6.
Table 2.6 Pavement Condition along the alignment
Proposed Chainage (NH-353C) Length
(Kms) Existing Chainage Length
(Kms) Pavement Condition
Start End Start End
113+650 147+000 33+350 172+650 206+000 33+350 Good
147+000 161+000 14+000 206+000 220+000 221+400 Fair
161+000 177+000 16+000 221+400 236+000 16+000 Fair
177+000 180+200 3+200 236+000 239+200 3+200 Good
180+200 196+700 16+500 213+500 230+000 16+500 Good
196+700 197+700 1+000 230+000 231+000 1+000 Fair
197+700 216+700 19+000 231+000 250+000 19+000 Poor
216+700 240+700 24+000 250+000 274+000 24+000 Good
240+700 242+700 2+000 274+000 276+000 2+000 Poor
242+700 251+700 9+000 276+000 285+000 9+000 Good
251+700 253+700 2+000 285+000 287+000 2+000 Poor
Allapalli – Sironcha Road and Jimalgatta Road Junction at Ch: 268+900 Km
Bypass Alignment for Allapalli at Ch: 225+000 Km (Aheri Road, MDR)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 33
Proposed Chainage (NH-353C)
Length (Kms)
Existing Chainage Length (Kms)
Pavement Condition
253+700 256+700 3+000 287+000 290+000 3+000 Good
256+700 260+700 4+000 290+000 294+000 4+000 Poor
260+700 279+700 19+000 294+000 313+000 19+000 Good
279+700 283+700 4+000 313+000 317+000 4+000 Good
(Ghat Section)
283+700 284+700 1+000 317+000 318+000 1+000 Good
284+700 288+700 4+000 318+000 322+000 4+000 Fair
288+700 293+700 5+000 322+000 327+000 5+000 Good
293+700 295+700 2+000 327+000 329+000 2+000 Fair
295+700 318+200 22+500 329+000 351+500 22+500 Good
4 Lane Section from Ch: 113+650 to 115+200), Good Condition of Pavement
2 Lane Section from Ch: 147+000 to 161+000), Recent Overlay
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 34
2 Lane Section from Ch: 161+000 to 177+000), raveling on road surface
2 Lane Section from Ch: 177+000 to 196+000), Good Condition of the Road
Intermediate Lane Section from Ch: 197+000 to 216+000 and Ch: 256+000 to 261+000), Extensive Raveling of the Pavement
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 35
Intermediate Lane Section from Ch: 217+000 to 241+000 and Ch: 243+000 to 252+000 and Ch: 261+000 to 280+000), Good Condition of the Pavement
Intermediate Lane Section from Ch: 241+000 to 243+000 and Ch: 252+000 to 254+000), Extensive Cracking & Raveling, and Settlement of the Pavement
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 36
2.14 ROW DETAILS
Major portion of the highway is aligned through the forest areas. Initial recce of the
alignment has shown existence of a number of ROW pillars marked on either side at
approx. 50 mtrs interval. As could be ascertained from local PWD authorities, approx 12
to 13 mtrs on either side of the existing centre line land has been acquired. Thus the
existing right of way (ROW) extends to 24 -25 mtrs. In some portions it extends even up
to 27-28 mtrs. On either side of the earthen shoulders there is a presence of a number of
trees within the ROW. Most of the places only earthen drain was noticed .Also in some
portions OFC could be noticed laid on the outer edge of the ROW. Details of existing
ROW along the project alignment is indicated below.
Table 2.7 Existing Right of Way along the Alignment
Proposed Chainage (NH-353C) Length (Kms)
Existing Chainage Length (Kms)
Existing RoW Start End Start End
113+650 147+000 33+350 172+650 206+000 33+350 24.0
147+000 161+000 14+000 206+000 220+000 14+000 24.0
161+000 177+000 16+000 220+000 236+000 16+000 24.0
177+000 180+200 3+200 236+000 239+200 3+200 24.0
180+200 196+700 16+500 213+500 230+000 16+500 24.0
196+700 197+700 1+000 230+000 231+000 1+000 24.0
Intermediate Lane Section from Ch: 254+000 to 257+000 and Ch: 280+000 to 285+000 and Ch: 296+000 to 318+200), Good Condition of the Pavement
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 37
Proposed Chainage (NH-353C) Length (Kms)
Existing Chainage Length (Kms)
Existing RoW
197+700 216+700 19+000 231+000 250+000 19+000 24.0
216+700 240+700 24+000 250+000 274+000 24+000 24.0
240+700 242+700 2+000 274+000 276+000 2+000 24.0
242+700 251+700 9+000 276+000 285+000 9+000 24.0
251+700 253+700 2+000 285+000 287+000 2+000 24.0
253+700 256+700 3+000 287+000 290+000 3+000 24.0
256+700 260+700 4+000 290+000 294+000 4+000 24.0
260+700 279+700 19+000 294+000 313+000 19+000 24.0
279+700 283+700 4+000 313+000 317+000 4+000 24.0
283+700 284+700 1+000 317+000 318+000 1+000 24.0
284+700 288+700 4+000 318+000 322+000 4+000 24.0
288+700 293+700 5+000 322+000 327+000 5+000 24.0
293+700 295+700 2+000 327+000 329+000 2+000 24.0
295+700 318+200 22+500 329+000 351+500 22+500 24.0
2.15 SOIL AND SUBSOIL
The soil characteristics seem to be fairly uniform along the stretch. Major portion of
project road is agricultural. Sand content appears to be appreciable. The soil appears to
be of non-expansive nature and may be clayey silt. It was reported that the top 20-25m
Boundary Stones @ Forest Location at chainage 29+000
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 38
strata has soil after which rocky strata starts. Inspection of wells showed water at
roughly 5m from the natural ground.
Tube well borings are usually taken over 25m in the area. The river beds are generally
sandy and used for quarrying.
2.16 UTILITIES ALONG THE PROJECT HIGHWAY
OFC cable was noticed in certain places running on the outer edge of the ROW. HT line
crossings were noticed at two to three places. It is proposed to examine provision of
additional utilities e.g. bus bays, passenger facilities, toll plazas where required and
other passenger amenities.
2.17 SOCIO RELIGIOUS STRUCTURE AND BUILDINGS
The roadway is flanked on the sides by important social activity centers such as schools,
colleges, and places of worship etc. While widening, the alignment may have to be
shifted to avoid impacting these structures.
2.18 BRIDGES AND CROSS DRAINAGE STRUCTURES
The inventory data for the existing cross drainage structures, culverts and bridges were
carried out. The project road has 6 Major bridge, 41 Minor bridges, 276 Culverts, 2
Canal works and the summary of the same is given below in Table 2.8.
Table 2.8 Summary of Existing Bridges and Culverts
Length Vented/Non - Vented/
Causeway/ Canal works Culverts Bridges
Pipe Slab Box Total Minor Major Total
2 (Causeway works) 263 3 8 274 41 6 47
2.18.1 Major Bridges
There are 6 major bridges in this project. Details of location span arrangements etc. of
the existing major bridges are tabulated in Table 2.9 below. The bridges would be
examined for strength of slabs, carriageway width and recorded HFL. Effort will be
made to retain existing bridges to the extent feasible.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 39
Table 2.9 Major Bridge
Sl No Proposed
Chainage (NH-353C)
Existing Chainage (MSH)
Span Arrangement (m) Total Width
(m)
Section : Gadchiroli to Ashti
1 117+350 182+900 7 X 7.5 8.2
2 140+500 199+500 17 X 7.0 7.5
Section : Ashti to Allepalli
3 211+700 244+916 17 X 6.2 7.5
Section : Allepalli to Sironcha
4 236+700 258+400 5 X 9.0 8
5 245+300 272+940 3 X 13.0 8.5
6 246+900 320+200 8 X 5.8 7.5
Major Bridge @ Ch: 182+900 Km Major Bridge @ Ch: 199+500 Km
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 40
2.18.2 Minor Bridges
There are 41 minor bridges in the existing project road. Details of the existing minor
bridges are tabulated in Table 2.10 given below.
Table 2.10 Minor Bridge
Sl No Proposed Chainage (NH-
353C) Existing Chainage
(MSH) Span Arrangement
(m) Total Width
(m)
Section : Gadchiroli to Ashti
1. 131+200 187/350 6 X 4.5 8.0
2. 135+100 189/570 4 X 8.5 8.0
3. 136+100 195/00 3 X 3.2 8.2
Major Bridge @ Ch: 244+916 Km Major Bridge @ Ch: 258+400 Km
Major Bridge @ Ch: 272+940 Km Major Bridge @ Ch: 320+200 Km
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 41
Sl No Proposed Chainage (NH-
353C) Existing Chainage
(MSH) Span Arrangement
(m) Total Width
(m)
4. 139+100 198/100 3 X 6 7.5
5. 148+700 207/700 2 X 5 8.2
6. 153+200 212/200 4 x 5.2 8.0
7. 164+900 223/900 4 x 6.5 7.9
8. 178+200 237/200 3 x 6 7.8
Section : Ashti to Allepalli
9. 193+450 222/650 5 x 9.0 7.8
10. 211+700 245/850 3 x 6.2 8.0
11. 220+700 254/300 4 x 4 7.6
12. 222+350 256/350 5 x 5.3 8.2
Section : Allepalli to Sironcha
13. 225+300 261/450 3 x 4 7.6
14. 228+300 262/630 3 x 6 8.0
15. 231+600 264/880 2 x 4.5 8.0
16. 232+900 266/070 2 x 8.0 8.3
17. 235+900 269/070 3 x 7.5 7.0
18. 241+500 273/300 2 x 3.5 8.2
19. 248+700 274/620 3 x 6.0 6.5
20. 251+700 278/450 2 x 4.8 8.0
21. 253+300 280/050 2 x 5.8 8.0
22. 256+900 281/900 3 x 5.0 8.2
23. 257+900 285/850 2 x 5.2 8.0
24. 260+100 286/650 2 x 3.5 7.9
25. 260+700 290/100 2 x 7.2 6.8
26. 261+500 291/000 2 x 4.5 7.0
27. 263+390 293/250 2 x 8.0 7.5
28. 264+700 293/800 2 x 6.0 7.0
29. 266+900 294/750 3 x 5.5 7.8
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 42
Sl No Proposed Chainage (NH-
353C) Existing Chainage
(MSH) Span Arrangement
(m) Total Width
(m)
30. 269+100 296/420 2 x 5.4 7.3
31. 272+260 297/990 3 x 3.7 6.2
32. 278+420 300/150 3 x 3.5 7.8
33. 279+725 303/450 5 x 4.2 7.4
34. 284+850 305/600 4 x 5.0 8.0
35. 285+370 310/360 3 x 4.5 7.6
36. 286+850 311/750 5 x 5.0 6.0
37. 289+560 313/050 2 x 6.5 8.5
38. 290+860 318/200 4 x 8.6 8.5
39. 293+850 318/770 2 x 4.0 8.0
40. 297+470 322/450 9 x 2.5 8.2
41. 300+330 326/220 6 x 4.0 8.3
2.19 RESURFACING PROGRAM
It is noticed that almost 30 % of the existing pavement is damaged and would require
reconstruction. As highlighted above the portion of the alignment from Chamorshi to
Gadchiroli is passing through low lying areas and are prone to flooding and would
require raising of embankment. A number of portions of the existing road is displaying
signs of distress and would require reconstruction. Final assessment will be made after
the BBD survey and pavement examination, the Chainages where the pavement is in
near satisfactory condition and resurfacing could suffice is shown below.
Table 2.11 Details of Resurfacing Section
Proposed Chainage (NH-353C) Length (Kms)
Existing Chainage (MSH) Length (Kms) Start End Start End
113+650 147+000 33+350 172+650 206+000 33+350
177+000 180+200 3+200 236+000 239+200 3+200
180+200 196+700 16+500 213+500 230+000 16+500
216+700 240+700 24+000 250+000 274+000 24+000
242+700 251+700 9+000 276+000 285+000 9+000
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 43
Proposed Chainage (NH-353C) Length (Kms)
Existing Chainage (MSH) Length (Kms)
253+700 256+700 3+000 287+000 290+000 3+000
260+700 279+700 19+000 294+000 313+000 19+000
279+700 283+700 4+000 313+000 317+000 4+000
283+700 284+700 1+000 317+000 318+000 1+000
288+700 293+700 5+000 322+000 327+000 5+000
295+700 318+200 22+500 329+000 351+500 22+500
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 44
CHAPTER 3. APPROACH & METHODOLOGY
3.1 GENERAL
The Consultant’s approach to the project will be in accordance with the “Description of
Services” given in the Contract Document, understanding of the project objectives and
further discussions with the Client during the progress of the project study.
3.2 OBJECTIVE OF THE STUDY
Based on the objectives and scope of the consultancy services, an appropriate
methodology has been developed to address the requirements, especially with regard to
various intermediate targets and completion period, manning schedule and interaction
with client as indicated in the terms of reference (TOR). A work plan has been prepared
on the basis of the methodology developed. A competent team of suitably qualified key
professionals and other supporting staff as per the requirements of TOR is selected for
carrying out the services.
The scope of services includes both independent and inter-dependent activities. Hence
we propose a TASK APPROACH to carry out the entire work comprehensively and
accurately to the complete satisfaction of the client & fulfillment of ToR. The whole work
will be divided into different tasks and the detailed methodology for each task is given
below.
3.3 APPROACH AND METHODOLOGY
The main objective of the consultancy service is to establish the technical, economical,
and financial viability of the project and prepare detailed project reports for
rehabilitation and upgrading of the existing road to 2/4 lane configuration
The assignment includes highway design, pavement design for flexible/ rigid pavements,
design of bridges and cross drainage structures and grade separated structures, design
of service roads, quantities of various items, detailed working drawings, detailed cost
estimates, economic and financial viability analyses, environmental and social
feasibility, social and environmental action plans as appropriate and documents
required for tendering the project on commercial basis for international / local
competitive bidding.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 45
The Methodology for Services, Surveying and Data Collection will be carried out to cover
all the scope of work as detailed in the ToR. A schematic diagram is prepared to cover
the important activities of the assignment which is self-explanatory and is shown in the
figure below.
The widening/improvement work to 2/4 laning will be explored to fit within the existing
right of way avoiding land acquisition, except for locations having inadequate width and
where provisions of short bypasses, service roads, alignment corrections, improvement of
intersections are considered necessary and practicable and cost effective. However
DPR Preparation
1. Site Inspection &. Meeting with
IAHE Officials 2. Design Standards &
QAP
3. Traffic surveys and
demand
assessment
4. Topographic Surveys &
Utility survey
5. Road inventory & pavement
Surveys
6. Structural Inventory &
Geotechnical
Surveys7 Social & Environmental
Surveys
8. Alignment design & pavement
Design
9. Structural Designs
(Bridge/RoB/Culverts)
10. Design of way side
amenties
11. Costing, Economic &
Financial
Analysis
12. Submission of Feasibility
& DPR
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 46
bypass proposals will also be considered, wherever in urban areas, improvement to 2/4
lane of the existing road is not possible. The land acquisition details as per revenue
records/maps and as required in ToR will also be furnished.
Consultants have in-house latest computers/laptops loaded with software for the design
of Alignment, Roadway, Bridges, steel structures, geotechnical analysis.
Consultants also have NABL accredited in-house material testing laboratory to ensure
that the material are tested with proper procedures and consistency in results which
will help in accurate design of pavement, embankment and structures
3.4 QUALITY ASSURANCE SYSTEM FOR CONSULTANCY ASSIGNMENT
It is of great importance to maintain consistency in design, careful preparation of
drawings and infallible design work of any projects by the consultants. The quality of
this work is a vital ingredient in the successful completion of design work and
implementation of the project both for the new highways and for upgrading and
maintaining the existing roads
Our company is an ISO 9001:2008 certified company, our edge in terms of delivering
high quality products requires effective quality assurance mechanisms. For this we have
developed and are applying a quality assurance system, which is compliant with ISO
9001:2008. Our quality assurance systems may be divided into three phases:
1) Pre-implementation phase
2) Implementation
3) Quality assurance of outputs
At the pre-implementation phase the Team Leader will focus on: (a) ensuring that there
is a clear understanding of the ToR and the expectations of the client of the required
work and outputs, and (b) that the team members identified for the assignment are fully
qualified to undertake the assignment. The company will develop the Quality Assurance
Plan (QAP) for all field studies including topographic surveys, traffic surveys,
engineering surveys and investigations and documentation activities. The detailed QAP
will be discussed and finalized with the concerned NH officials immediately upon the
award of the Contract. The same shall be submitted within the stipulated time and
strictly adhered to. The QAP will become a guide to both consultants and the client in
executing the assignment as well as monitoring the activities.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 47
3.5 REVIEW OF DATA AND DOCUMENTS
The Consultants will collect the available data and information relevant for the Study.
The data and documents of major interest will include, but not be limited to, the
following:
(i) Climate;
(ii) Road inventory;
(iii) Road condition, year of original construction, year and type of major
maintenance/rehabilitation works;
(iv) Condition of bridges and cross-drainage structures;
(v) Sub-surface and geo-technical data for existing bridges;
(vi) Hydrological data, drawings and details of existing bridges;
(vii) Existing geological maps, catchment area maps, contour plans etc. for the project
area;
(viii) Condition of existing river bank / protection works, if any.
Completion ofProject 16
Economic &Financial Analysis 14 15 ICB
DocumentBOQ & CostEstimate 12 13 Environmental
& R R Study & ReportDetailedDrawings 10 11 Quality Audit
PavementDesign 8 9 Bridge & Other Structural Design
TrafficReport 6 7 Highway Design
Investigation& Surveys 4 5 Processing, Testing & Reports
Project Setup 2 3 Standardisation, Setting up Quality System & Quality Control
1 Start of Project
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 48
(ix) Details of sanctioned / on-going works on the stretch sanctioned by MoRT&H /
other agencies for Tie-in purposes
(x) Survey and evaluation of locally available construction materials;
(xi) Historical data on classified traffic volume (preferably for 5 years or more);
(xii) Origin-destination and commodity movement characteristics; if available;
(xiii) Speed and delay characteristics; if available;
(xiv) Commodity-wise traffic volume; if available;
(xv) Accident statistics; and,
(xvi) Vehicle loading behavior (axle load spectrum), if available.
(xvii) Type and location of existing utility services (e.g. Fibre Optical Cable, O/H and
U/G Electric, Telephone line, Water mains, Sewer, Trees etc.)
(xviii) Environmental setting and social baseline of the project.
3.6 SOCIAL ANALYSIS
The social analysis study will be carried out in accordance with the MORT&H/ World
Bank/ ADB Guidelines. The social analysis report will, among other things, provide a
socio-economic profile of the project area and address in particular, indigenous people,
communicable disease particularly HIV/AIDS poverty alleviation, gender, local
population, industry, agriculture, employment, health, education, health, child labour,
land acquisition and resettlement .
3.7 TRAFFIC SURVEYS
All traffic surveys and studies will be completed and incorporated in feasibility studies.
The type of traffic surveys and the minimum number of survey stations will be as under.
Table 3.1 Traffic surveys and Durations
Sl. No Type of traffic survey Number of Survey
Stations Survey Extent and Duration
1 Traffic volume Counts
(TVC) 3
Carried out for 7 days (continuous,
direction-wise)
2 Turning Movement
Counts (TMC)
All Major
Intersections
Conducted from morning and evening
on a week day (8 am to 8 pm)
3 Origin and
Destination Survey Minimum 2
Carry out 1-day (24 hour, both
directions) O-D and Commodity
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 49
Sl. No Type of traffic survey Number of Survey
Stations Survey Extent and Duration
Movement Surveys
4 Axle Loading
Characteristics 2
Carried out at suitable location(s) in
the project road stretch on a random
sample basis normally for trucks only
(both empty and loaded trucks) for 2
normal days - (24 hours) at special
count station
5 Speed-Delay
Characteristics Project Road Section
Carry out appropriate field studies
such as moving car survey to
determine running speed and journey
speed
6 Pedestrian/ animal
cross traffic count
All major
inhabitations along
the highway
All major inhabitations along the
highway
Table 3.2 shows the locations of surveys on the proposed corridor For TVC, OD and Axle
Load Surveys. Table 3.3 shows the locations of surveys on the proposed corridor For
TMC Surveys.
Table 3.2 Traffic Survey Locations for TVC, OD and Axle Load Surveys
Link No. Name of
Link
Location
Name TVC OD
Axle
Load Remarks
NH353C-01 Gadchiroli -
Ashti
Jaynagar
Village
(MSH 11)
Yes Yes Yes
On MSH-11, about 5.0 Km
From Chamorshi Towards
Ashti
NH353C-02 Ashti -
Allepalli
Ashti (MSH
09) Yes Yes Yes
On MSH-09, about 1.0 Km
From Ashti Towards Allepalli
NH353C-03 Allepalli -
Sironcha
Karaspalli
(MSH 11) Yes
On MSH-09, about 9.0 Km
From Sironcha Towards
Allepalli
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 50
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 51
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 52
Motorized Traffic Non-Motorized Traffic
Passenger Car Animal Drawn Vehicle (ADV)
Utility Vehicle (Jeep, Van etc) Hand Cart
Bus Mini Bus Other Non-Motorized Vehicle
Standard Bus
LCV LCV – Passenger
LCV – Freight
Truck
MCV - 2 Axle Rigid Chassis
HCV - 3 Axle Rigid Chassis
MAV - Semi Articulated
MAV - Articulated
All results will be presented in tabular and graphical form. The survey data will be
analyzed to bring out the hourly and daily variations. The traffic volume count per day
will be averaged to show a weekly Average Daily Traffic (ADT) by vehicle type. The
Annual Average Daily Traffic (AADT) will be worked out by applying seasonal factors.
The consultants will compile the relevant traffic volume data from secondary sources
also. The salient features of traffic volume characteristics will be brought out and
variations if any, from the traffic census carried out by the State PWD will be suitably
explained.
Origin-Destination (O-D) and Commodity Movements Surveys
The Consultants will carry out 1-day (24 hour, both directions) O-D and Commodity
Movement Surveys at locations finalized in consultation with IAHE. These will be
essentially required around congested towns to delineate through traffic. The road side
interviews will be on random sample basis and cover all four-wheeled vehicles. The
locations of the O-D survey and Commodity Movement surveys will normally be same as
for the classified traffic count stations.
The location of origin and destination zones will be determined in relation to each
individual station and the possibility of traffic diversion to the Project Road from/to
other road routes including bypasses.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 53
The trip matrices will be worked out for each vehicle type information on weight for
trucks would be summed up by commodity type and the results tabulated, giving total
weight and average weight per truck for the various commodity types. The sample size
for each vehicle type will be indicated on the table and also in the graphical
representations.
The data derived from surveys will also be analyzed to bring out the lead and load
characteristics and desire line diagrams. The data analysis would also bring out the
requirement for the construction of bypasses. The distribution of lead and load obtained
from the surveys will be compared with those derived from the axle load studies. The
commodity movement data will be taken into consideration while making the traffic
demand estimates.
Turning Movement Surveys
The turning movement surveys for estimation of peak hour traffic for the design of
major and minor intersections will be carried out for the Study. The details regarding
composition and directional movement of traffic will be furnished.
The methodology for the surveys will be as per IRC: SP: 41-1994. The details including
location and duration of surveys will be finalized in consultation with IAHE officials.
The data derived from the survey will be analyzed to identify requirements of suitable
remedial measures, such as construction of underpasses, fly-overs, interchanges, grade-
separated intersections along the project road alignment. Intersections with high traffic
volume requiring special treatments either presently or in future will be identified.
Axle Load Surveys
Axle load surveys in both directions will be carried out at suitable location(s) in the
project road stretch on a random sample basis normally for trucks only (both empty and
loaded trucks) for 2 normal days - (24 hours) at special count stations to be finalized in
consultation with IAHE. However, a few buses may be weighed in order to get an idea
about their loading behavior. While selecting the location(s) of axle load survey
station(s), the locations of existing bridges with load restrictions, if any, should be taken
into account and such sites should be avoided.
The axle load surveys will be done using axle load pads or other sophisticated
instruments. The location(s) of count station(s) and the survey methodology including
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 54
the data formats and the instrument type to be used will be finalized before taking up
the axle load surveys.
The axle load data should be collected axle configuration-wise. The number of equivalent
standard axles per truck will be calculated on the basis of results obtained. The results
of the survey would bring out the VDF for each truck type (axle configuration, if the
calculated VDF is found to be below the national average, then national average will be
used. Furthermore, the data from axle load surveys are analyzed to bring out the Gross
Vehicle Weight (GVW) and Single Axle Load (SAL) Distributions by truck type (axle
configuration).
Speed-Delay Surveys
The Consultants will carry out appropriate field studies such as moving car survey to
determine running speed and journey speed. The data would be analyzed to identify
sections with typical traffic flow problems and congestion. The objective of the survey is
to recommend suitable measures for segregation of local traffic, smooth flow of through
traffic and traffic safety. These measures would include the provision of bypasses,
under-passes, fly-overs, interchanges, grade-separated intersections and service roads.
Traffic Demand Estimates
The consultants will make traffic demand estimates and establish possible traffic
growth rates in respect of all categories of vehicles, taking into account the past trends,
annual population and real per capita growth rate, elasticity of transport demand in
relation to income and estimated annual production increase. The other aspects
including socio-economic development plans and the land use patterns of the region
having impact on the traffic growth, the projections of vehicle manufacturing industry in
the country, development plans for the other modes of transport, O-D and commodity
movement behavior are also be taken into account while working out the traffic demand
estimates.
The values of elasticity of transport demand will be based on the prevailing practices in
the country. The Consultants will give complete background including references for
selecting the value of transport demand elasticity.
It is envisaged that the 2/4-laning of the project road sections would be completed and
opened to traffic after 3 years. The traffic demand estimates will be done for a further
period of 30 years from completion of two/four lane. The demand estimates will be done
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 55
assuming three scenarios, namely, optimistic, pessimistic and most likely traffic growth.
The growth factors will be worked out for five-yearly intervals.
Traffic projections would be based on sound and proven forecasting techniques. The
traffic projections would also bring out the possible impact of implementation of any
competing facility in the near future. The demand estimates should also take into
account the freight and passenger traffic along the major corridors that may
interconnect with the project. Impact of toll charges on the traffic estimates should be
estimated.
The methodology for traffic demand estimates described in the preceding paragraphs is
for normal traffic only. In addition to the estimates for normal traffic, the Consultants
will work out the estimates for generated, induced and diverted traffic. The traffic
forecasts will also be made for both diverted and generated traffic. Overall traffic
forecast thus made will form the basis for the design of each pavement type and other
facilities/ ancillary works.
3.8 ENGINEERING SURVEYS & INVESTIGATIONS
B.1 Reconnaissance and Alignment
B.2 Topographic Surveys
B.3 Road and Pavement Investigations
B.4 Investigations for Bridges and Structure
B.5 Material Investigations
B.1 Reconnaissance and Alignment
The Consultants would make an in-depth study of the available land width (ROW)
topographic maps, satellite imageries and air photographs of the project area, geological
maps, catchment area maps, contour plans, flood flow data and seismological data. And
other available relevant information collected by them concerning the existing
alignment. Would make efforts for minimizing land acquisition.
The detailed ground reconnaissance may be taken up immediately after the study of
maps and other data.
The data derived from the reconnaissance surveys are utilized for planning and
programming the detailed surveys and investigations. All field studies including the
traffic surveys should be taken up on the basis of information derived from the
reconnaissance surveys.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 56
The data and information obtained from the reconnaissance surveys will be documented.
The data obtained from the reconnaissance surveys should form the core of the database
which would be supplemented and augmented using the data obtained from detailed
field studies and investigations.
B.2 Topographic Surveys
The basic objective of the topographic survey would be to capture the essential ground
features along the alignment in order to consider improvements and for working out
improvements, rehabilitation and upgrading costs. The detailed topographic surveys will
be taken up after the completion of reconnaissance surveys.
The detailed field surveys will be carried out using Total stations. The data from the
topographic surveys will be available in (x, y, z) format for use in a sophisticated digital
terrain model (DTM).
The detailed field surveys would essentially include the following activities
Topographic Surveys along the Existing Right of Way (ROW): Running a
continuous open Traverse along the existing road and realignments, wherever
required, and fixation of all cardinal points such as horizontal intersection points
(HIP’s), centre points and transit points etc. and properly referencing the same
with a pair of reference pillars fixed on either side of the centre-line at safe places
within the ROW.
The detailed field surveys would essentially include the topographic surveys
along the proposed location of bridge and alignment of approach road.
The detailed topographic surveys should be carried out along the approach roads
alignment and location of bridge approved by IAHE.
Collection of details for all features such as structures (bridges, culverts etc.)
utilities, existing roads, electric and telephone installations (both O/H as well as
underground), huts, buildings, fencing and trees (with girth greater than
0.3metre) oil and gas lines etc. falling within the extent of survey.
The width of survey corridor will generally be as given under
The width of the survey corridor should take into account the layout of the
existing alignment including the extent of embankment and cut slopes and the
general ground profile. While carrying out the field surveys, the widening scheme
(i.e. right, left or symmetrical to the centre line of the existing carriageway)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 57
should be taken into consideration so that the topographic surveys cover
sufficient width beyond the centre line of the proposed divided carriageway.
In case the reconnaissance survey reveals the need for bypassing the congested
locations, the traverse lines would be run along the possible alignments in order
to identify and select the most suitable alignment for the bypass. The detailed
topographic surveys should be carried out along the bypass alignment approved
by IAHE. At locations where grade separated intersections could be the obvious
choice, the survey area will be suitably increased. Field notes of the survey
should be maintained which would also provide information about traffic, soil,
drainage etc.
The width of the surveyed corridor will be widened appropriately where
developments and / or encroachments have resulted in a requirement for
adjustment in the alignment, or where it is felt that the existing alignment can
be improved upon through minor adjustments.
Where existing roads cross the alignments, the survey will extend a minimum of
100 m either side of the road centre line and will be of sufficient width to allow
improvements, including at grade intersection to be designed.
The surveyed alignment shall be transferred on to the ground as under
Reference Pillar and Bench Mark / Reference pillar of size 15 cm X 15 cm X 45cm
shall be cast in RCC of grade M 15 with a nail fixed in the centre of the top
surface. The reference pillar shall be embedded in concrete up to a depth of 30cm
with CC M10 (5 cm wide all around). The balance 15 cm above ground shall be
painted yellow. The spacing shall be 250m apart, incase Bench Mark Pillar
coincides with Reference Pillar, only one of the two need be provided.
Establishing Bench marks at site connected to GTS Bench marks at an interval
of 250 meters on Bench mark pillar made of RCC as mentioned above with RL
and BM No. marked on it with red paint.
Boundary Pillars- Wherever there is a proposal of realignment of the existing
Highway and/or construction of New Bypasses, Consultant will fix boundary
pillars along the proposed alignment on the extreme boundary on either side of
the project Highway at 50 m interval.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 58
Longitudinal and Cross-Sections
The topographic surveys for longitudinal and cross-sections shall cover the following:
Longitudinal section levels along final centre line at every 25 m interval, at the
locations of curve points, small streams and intersections and at the locations of
change in elevation.
Cross sections at every 50 m interval in full extent of survey covering sufficient
number of spot levels on existing carriageway and adjacent ground for profile
correction course and earth work calculations. Cross sections shall be taken at
closer interval at curves.
Longitudinal section for cross roads for length adequate for design and quantity
estimation purposes.
Longitudinal and cross sections for major and minor streams shall cover Cross
section of the channel at the site of proposed crossing and few cross sections at
suitable distance both upstream and downstream, bed level up to top of banks
and ground levels to a sufficient distance beyond the edges of channel, nature of
existing surface soil in bed, banks & approaches, longitudinal section of channel
showing site of bridge etc. These shall be as per recommendations contained in
IRC Special Publication No. 13 (Guidelines for the Design of Small Bridges and
Culverts) and provisions of IRC:5 (“Standard Specifications & Code of Practice
for Road Bridges, Section 1 – General Features of Design”).
Details of utility Services and Other Physical Features
The Consultants will collect details of all important physical features along the
alignment. These features affect the project proposals and should normally
include buildings and structures, monuments, burial grounds, cremation
grounds, places of worship, railway lines, stream / river / canal, water mains,
severs, gas/oil pipes, crossings, trees, plantations, utility services such as electric,
and telephone lines (O/H & U/G) and poles, optical fiber cables (OFC) etc. The
survey would cover the entire right-of-way of the road on the adequate allowance
for possible shifting of the central lines at some of the intersections locations.
The information collected during reconnaissance and field surveys will be shown
on a strip plan so that the proposed improvements can be appreciated and the
extent of land acquisition with L.A schedule, utility removals of each type etc.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 59
assessed and suitable actions can be initiated. Separate strip plan for each of the
services involved shall be prepared for submission to the concerned agency.
B.3 Road and Pavement Investigations
The Consultants will carry out detailed field studies in respect of road and pavement.
The data collected through road inventory and pavement investigations should be
sufficient to meet the input requirements of HDM-IV.
Road Inventory Surveys:
Detailed road inventory surveys will be carried out to collect details of all existing road
and pavement features along the existing road sections. The inventory data will include
the following.
Terrain (flat, rolling, mountainous);
Land-use (agricultural, commercial, forest, residential etc ) @ every kilometer;
Carriageway width, surfacing type @ every 500m and every change of feature
whichever is earlier;
Shoulder surfacing type and width @ every 500m and every change of feature
whichever is earlier;
Sub-grade / local soil type (textural classification) @ every 500m and every
change of feature whichever is earlier;
Horizontal curve; vertical curve
Road intersection type and details, at every occurrence;
Retaining structures and details, at every occurrence;
Location of water bodies (lakes and reservoirs), at every occurrence;
Height of embankment or depth of cut @ every 200m and every change of feature
whichever is earlier.
Land width i.e. ROW
Culverts, bridges and other structures (type, size, span arrangement and
location)
Roadside arboriculture
Existing utility services on either side within ROW.
General drainage conditions
Design speed of existing road
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 60
The data should be collected in sufficient detail. The data should be compiled and
presented in tabular as well as graphical form. The inventory data would be stored in
computer files using simple utility packages, such as EXCEL.
Pavement Condition:
The data concerning the pavement composition may be already available with the PWD.
However, the consultants will make trial pits to ascertain the pavement composition.
For each test pit, the following information shall be recorded:
Test pit reference (Identification number, location):
Pavement composition (material type and thickness); and
Subgrade type (textural classification) and condition (dry, wet)
Road and Pavement Condition Surveys
The objective of the road and pavement condition surveys are to identify defects and
sections with similar characteristics. All defects are systematically referenced, recorded
and quantified for the purpose of determining the mode of rehabilitation.
The pavement condition surveys are carried out using visual means. Supplemented by
actual measurements and in accordance with the widely accepted methodology
(AASHTO, IRC, OECD, TRL and World Bank Publications) adapted to meet the study
requirements. The measurement of rut depth would be made using standard straight
edges.
The shoulder and embankment conditions will be evaluated by visual means and the
existence of distress modes (cuts, erosion marks, failure, drops) and extent (none,
moderate, frequent and very frequent) of such distress manifestations would be
recorded.
For sections with severe distresses, additional investigations as appropriate will be
carried out to determine the cause of such distresses.
Pavement Roughness
The roughness surveys will be carried out using Bump Integrator or similar instrument.
The methodology for the surveys will be as per the widely used standard practices. The
calibration of the instrument will be done as per the procedure given in the World
Bank’s Technical Publications and duly got authenticated by established
laboratory/institution acceptable to the client.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 61
The surveys will be carried out along the outer wheel paths. The surveys will cover a
minimum of two runs along the wheel paths for each directions.
The results of the survey shall be expressed in terms of BI and IRI and shall be
presented in tabular and graphical forms. The processed data shall be analysed using
the cumulative difference approach to identify road segments homogenous with respect
to surface roughness.
Pavement Structural Strength
The Consultants will carry out structural strength surveys for existing pavements using
Benkelman Beam Deflection technique in accordance with the CGRA procedure given in
IRC: 81-1997 (“Guidelines for Strengthening of Flexible Road Pavements Using
Benkelman Beam Deflection Technique”).
It is suggested that the deflection surveys may be carried out as per the scheme given
below:
Mainline testing; and,
Control section testing.
The deflection tests for the mainline shall be carried out at every 500 m along the road
sections covered under the study. The control section testing shall involve carrying out
deflection testing for each 100 m long homogenous road segment along the road sections.
The selection of homogenous segment will be based on the data derived from pavement
condition surveys. The total length of such homogenous segments will not be less than
100 m per kilometer. The deflection measurements for the control section testing should
be at an interval of not more than 10 m.
Test pits are taken at every 500 m and also along each homogeneous road segment to
obtain pavement composition details (pavement course, material type and thickness) so
as to be able to study if a correlation exists between deflection and composition. If so, the
relationship are to be used while working out the overlay thickness for the existing
pavement.
Benkelman Beam Deflection surveys may not be carried out for severely distressed
sections of the road warranting reconstruction. The Consultants, immediately upon the
award of the contract, will have to submit to IAHE the scheme describing the testing
schedule including the interval. The testing scheme will be supported by data from
detailed reconnaissance surveys.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 62
Subgrade Characteristics and Strength
Based on the data derived from condition (surface condition, roughness) and structural
strength surveys, the project road section should be divided into segments homogenous
with respect to pavement condition and strength. The delineation of segments
homogenous with respect to roughness and strength should be done using the
cumulative difference approach (AASHTO, 1993).
The data on soil classification and mechanical characteristics for soils along the existing
alignments may already be available with the PWD. The testing scheme is, therefore,
proposed as given under:
For the widening (2/4 Laning) of existing road within the ROW, the
Consultants have to test at least three sub-grade soil samples for each
homogenous road segment or three samples for each soil type
encountered, whichever is more.
For the roads along new alignments, the test pits for sub grade soil shall
be @ 5km or for each soil type, whichever is more. A minimum of three
samples should be tested corresponding to each homogenous segment.
The testing for subgrade soil shall include:
i. In-situ density and moisture content at each test pit
ii. Field CBR using DCP at each test pit
iii. Characterization (grain size and Atterberg limits) at each test pit and,
iv. Laboratory moisture-density characteristics (modified AASHTO
compaction);
v. Laboratory CBR (unsoaked and 4-day soak compacted at three energy
levels) and swell.
For problematic soils, the testing will be more rigorous. The characteristics with regard
to permeability and consolidation will also be determined for these soils. The frequency
of sampling and testing of these soils will be finalized in consultation with the IAHE
officers after the problematic soil types are identified along the road sections. The
laboratory for testing of material should be got approved from IAHE before start of
work.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 63
B.4 Investigation for Bridges and Structures
Inventory of Bridges, Culverts and Structures
The Consultants will carry out inventory of all the structures (bridges, viaducts,
ROBs/RUB and other grade separated structures, culverts, etc.) along the road under
the project. The inventory for the bridges, viaducts and ROBs will include the
parameters required as per the guidelines of IRC-SP: 35. The inventory of culverts will
be presented in a tabular form covering relevant physical and hydraulic parameters.
Hydraulic and Hydrological Investigations
The hydrological and hydraulic studies are to be carried out in accordance with IRC SP:
13 (“Guidelines for the Design of Small Bridges and Culverts”) and IRC: 5 (“Standard
Specifications & Code of Practice for Road Bridges, Section I General Feature of
Design”). These investigations will be carried out for all existing drainage structures
along the road sections under the study.
The consultant will also collect information on observed maximum depth of scour. In
respect of major bridges, history of hydraulic functioning of existing bridge, if any, under
flood situation, general direction of river course through structure, afflux, extent and
magnitude of flood, effect of backwater, if any, aggradation/degradation of bed, evidence
of scour etc. will be used to augment the available hydrological data. The presence of
flood control/irrigation structures, if affecting the hydraulic characteristics like causing
obliquity, concentration of flow, scour, silting of bed, change in flow levels, bed levels etc.
will be studied and considered in design of bridges. The details of any future planned
work that may affect the river hydraulics will be studied and considered.
The Consultants will make a desk study of available data on topography (topographic
maps, stereoscopic aerial photography), storm duration, rainfall statistics, top soil
characteristics, vegetation cover etc. so as to assess the catchment areas and hydraulic
parameters for all existing and proposed drainage provisions. The findings of the desk
study would be further supplemented and augmented by a reconnaissance along the
area. All important hydrological features will be noted during this field reconnaissance.
The Consultants will collect information on high flood level (HFL), low water levels
(LWL), high tide level (HTL), low tide level (LTL) where applicable, discharge velocity
etc. from available past records, local inquiries and visible signs, if any, on the
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 64
structural components and embankments. Local inquiries will also be made with regard
to the road sections getting overtopped during heavy rains.
Condition Surveys for Bridges, Culverts and Structures
1. The team will thoroughly inspect the existing structures and shall prepare a
report about their condition including all the parameters given in the Inspection
pro-forma of IRC-SP; 35. The condition and structural assessment survey of the
bridges / culverts / structures shall be carried out by senior experts of the
Consultants.
2. For the bridges identified to be in a distressed condition based upon the visual
condition survey, supplementary testing shall be carried out as per IRC-SP: 35
and IRC-SP: 40. Selection of tests may be made based on the specific requirement
of the structure.
3. The assessment of the load carrying capacity or rating of existing bridges shall be
carried out under one or more of the following scenarios:
i. When the design live load is less than that of the statutory commercial
vehicle plying or likely to ply on bridge;
ii. If during the condition assessment survey and supplementary testing the
bridge is found to indicate distress of serious nature leading to doubt
about structural and / or functional adequacy, and
iii. Design live load is not known nor are the records and drawings available.
4. The evaluation of the load carrying capacity of the bridge shall be carried out as
per IRC-SP: 37 (“Guidelines for Evaluation of Load Carrying Capacity of
Bridges”). The analytical and correlation method shall be used for the evaluation
of the load carrying capacity as far as possible. When it is not possible to
determine the load carrying capacity of the bridge using analytical and
correlation method, the same shall be carried out using load testing. The
consultant has to exhaust all other methods of evaluation of strength of bridges
before recommending to take up load testing of bridges. Road closure for testing
if unavoidable shall be arranged by IAHE for limited duration say 12 hrs or so.
5. The team shall carryout necessary surveys and investigations to establish the
remaining service life of each retainable bridge or structure with and without the
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 65
proposed strengthening and rehabilitation according to acceptable international
practice in this regard.
Geo-technical Investigations and Sub-Soil Exploration
We shall carry out geo-technical investigations and sub-surface explorations for the
proposed Bridges along high embankments and any other location as necessary for
proper design of the works and conduct all relevant laboratory and field tests on soil and
rock samples.
The deviation(s), if any, by the Consultants from the scheme presented above should be
got approved from IAHE.
However, where a study of geo-technical reports and information available from
adjacent crossings over the same waterway indicates that subsurface variability is such
that boring at the suggested spacing will be insufficient to adequately define the
conditions for design purposes, the we shall review and finalize the bore hole locations in
consultation with the IAHE officers.
Geotechnical Investigations and Sub soil Exploration will be carried out to determine
the nature and properties of existing strata in bed, banks and approaches with trial pits
and bore hole sections showing the levels, nature and properties of various strata to a
sufficient depth below the level suitable for foundations, safe intensity of pressure on the
foundation strata, proneness of site to artesian conditions, seismic disturbance and
other engineering properties of soil etc. Geotechnical investigation and Sub-soil
Exploration will be done as per IRC 78-.
The scheme for the borings locations and the depth of boring will be prepared by the
Consultants and submitted to IAHE for approval. These may be finalized in consultation
with IAHE.
The sub-soil exploration and testing should be carried out through the Geotechnical
Consultants empanelled by MORT&H. The soil testing reports shall be in the format
prescribed in relevant IRC Codes.
For the approach road pavement, bore holes at each major change in pavement condition
or in deflection readings or at 2 km intervals whichever is less shall be carried out to a
depth of at least 2 m below embankment base or to rock level and are to be fully logged.
Appropriate tests to be carried out on samples collected from these bore holes to
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 66
determine the suitability of various materials for use in widening of embankments or in
parts of new pavement structure.
B.5 Material Investigation
The Consultants have to identify sources (including use of fly-ash/ slag), quarry sites
and borrow areas, undertake field and laboratory testing of the materials to determine
their suitability for various components of the work and establish quality and quantity
of various construction materials and recommend their use on the basis of techno-
economic principles. The Consultants will prepare mass haul diagram for haulage
purposes giving quarry charts indicating the location of selected borrow areas, quarries
and the respective estimated quantities.
“As per MORTH circular No. RW /NH-33044/53/2013-S&R(R) dated 20th November,
2013, alternative pavement materials and technologies for road construction shall be
assessed and compared in the design stage. The alternative resulting in substantial
reduction in GHG emission and with least life cycle cost shall be recommended for
implementation.
Technical and economic feasibility of using industrial byproducts, recyclable and waste
materials shall be assessed depending on their availability in the concerned region.
It is to be ensured that no material shall be used from the right-of-way except by way of
leveling the ground as required from the construction point of view, or for landscaping
and planting of trees etc. or from the cutting of existing ground for obtaining the
required formation levels.
Environmental restrictions, if any, and feasibility of availability of these sites to
prospective civil works contractors, should be duly taken into account while selecting
new quarry locations.
We will make suitable recommendations regarding borrow and quarry areas after the
exploitation of materials for construction of works.
The Material Investigation aspect will include preparation and testing of bituminous
mixes for various layers and concrete mixes of different design mix grades using suitable
materials (binders, aggregates, sand filler etc.) as identified during Material
Investigation to conform to latest MORT&H specification.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 67
3.9 DETAILED DESIGN OF ROAD AND PAVEMENTS, STRUCTURES
C.1 General
C.2 Design Standards
C.3 Geometric Design of Highway
C.4 Pavement Designs
C.5 Design of Embankments
C.6 Design of Bridges and Structures
C.7 Design of Drainage System
C.8 Traffic Safety Features, Road Furniture, Road Markings and Road Signs
C.9 Arboriculture and Landscaping
C.10 Toll Plazas
C.11 Weighing Station, Parking Areas and Rest Areas
C.12 Miscellaneous Works
C.1 General
The Consultants are to carryout detailed designs and prepare working drawings for the
following.
High speed highway complete in all respects with service roads at appropriate
locations;
Design of pavement for the additional lanes and overlay for the existing road,
paved shoulders, medians, verges;
Bridges, viaduct/subways and other grade separated structures including
ROBs/RUBs etc.;
At-grade and grade-separated intersections, interchanges (if required);
ROB for railway crossings as per the requirement and the standards of the
Indian Railways; and,
Prepare alignment plans, longitudinal sections and cross-sections @ 50m
intervals;
Designs for road furniture and road safety/ traffic control features;
Designs and drawings for service road/ under passes/ overpass / cattle passes tree
planting/fencing at locations where necessary / required
Toll plazas
Short bypasses at congested locations
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 68
Drainage design showing location of turnouts, out falling structures, separate
drawings sheet for each 5 km. stretch.
Bridges and structures rehabilitation plan with design and drawings
Traffic amenities (Parking Areas, Weighing Station and Rest Areas, etc.).
Design of pavement for approach road
Design of river bank protection / training works Innovative type of structures
with minimum joints, aesthetically, pleasing and appropriate to the topography
of the region shall be designed wherever feasible.
C.2 Design Standards
The Consultants will evolve Design Standards and material specifications for the Study
primarily based on IRC publications, MoRT&H Circulars and relevant recommendations
of the international standards for approval by IAHE.
The Design Standards evolved for the project have to cover all aspects of detailed design
including the design of geometric elements, pavement design, bridges and structures,
traffic safety and materials.
C.3 Geometric Design of Highway
Based on the data collected from reconnaissance and topographic surveys, the sections
with geometric deficiencies, if any, should be identified and suitable measures for
improvement should be suggested for implementation.
The data on accident statistics should be compiled and reported showing accident type
and frequency so that black spots are identified along the project road section. The
possible causes (such as poor geometric features, pavement condition etc.) of accidents
should be investigated into and suitable cost-effective remedial measures suggested for
implementation.
The detailed design for geometric elements will have to cover, but not be limited to the
following major aspects:
horizontal alignment;
longitudinal profile;
Cross-sectional elements, including refuge lane (50m) at every 2kms.
junctions, intersections and interchanges;
bypasses; and,
Service roads as and when require i.e. built up area.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 69
The alignment design has to be verified for available sight distances as per the standard
norms. The provision of appropriate markings and signs has to be made wherever the
existing site conditions do not permit the adherence to the sight distance requirements
as per the standard norms.
We will make detailed analysis of traffic flow and level of service for the existing road
and workout the traffic flow capacity for the improved project road. The analysis would
clearly establish the widening (2/4-laning) requirements with respect to the different
horizon periods taking into account special problems such as road segments with
isolated steep gradients.
In the case of closely spaced cross roads the we will examine different options such as,
providing grade separated structure for some of them with a view to reduce number of
at-grade crossings, services roads connecting the cross-roads and closing access from
some of the intersections and prepare and furnish appropriate proposals for this purpose
keeping in view the cost of improvement, impact on traffic movement and accessibility to
cross roads. The detailed drawings and cost estimate should include the provisions for
realignments of the existing cross roads to allow such arrangements. We will also design
and prepare other details in respect of the parallel service roads in urbanized locations
and other locations to cater to the local traffic, their effect of the viability of the project
on commercial basis if service roads are constructed as part of the project and the
implications of not providing the service roads.
The team shall prepare complete road and pavement design including drainage for new
bypass option identified around congested town enroute.
C.4 Pavement Design
The detailed design of pavement shall involve:
Strengthening of existing road pavement and design of the new pavement if any,
if the findings of the traffic studies and life-cycle costing analysis confirm the
requirement for widening of the road beyond 2 lane undivided carriageway
standard;;
Pavement design for bypasses; and,
Design of shoulders.
The design of pavement will be based on IRC publications. The design alternatives will
include both rigid and flexible design options. It is learnt that Flyash is available at
Chandrapur in sufficient quantities. Possibility of use of Flyash based PPC cement will
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 70
also be explored. Also, use of Flyash for DLC after due testing will be examined. The
most appropriate design, option would be established on life-cycle costing and techno-
economic consideration.
As regards the design of overlays for the existing 2-lane pavement, the strengthening
requirement will take into account the strength of the existing pavement vis-à-vis the
remaining life. The overlay thickness requirements will be worked out for each road
segment homogenous with respect to condition, strength and sub-grade characteristics.
The rehabilitation provisions will also include the provision of regulating layer. For
existing pavement with acceptable levels of cracking, provision of a crack inhibiting
layer will also be included.
Latest techniques of pavement strengthening like provision of geo-synthetics and
cold/hot pavement recycling would be duly considered for achieving economy.
The paved shoulders would be designed as integral part of the pavement for the main
carriageway. The design requirements for the carriageway pavement has to, therefore,
be applicable for the design of shoulder pavements. The design of granular shoulder will
take into account the drainage considerations besides the structural requirements.
The pavement design task would also cover working out the maintenance and
strengthening requirements and periodicity and timing of such treatments.
C.5 Design of Embankments
The embankments design would provide for maximum utilization of locally available
materials consistent with economy. Use of fly ash wherever available with in economical
leads will be considered. In accordance with Government instructions, use of fly ash
within 100 km from Thermal Power Stations is mandatory.
The team shall also carry out detailed analysis and design for all embankments of
height greater than 6 m based on relevant IRC publications.
The design of embankments would include the requirements for protection works and
traffic safety features.
C.6 Design of Bridges and Structures
The Consultant shall prepare General Arrangement Drawing (GAD) and Alignment
Plan showing the salient features of the bridges and structures proposed to be
constructed / reconstructed along the road sections covered under the Study. These
salient features such as alignment, overall length, span arrangement, cross section, deck
level, founding level, type of bridge components (superstructure, substructure,
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 71
foundations, bearings, expansion joint, return walls etc.) shall be finalized based upon
hydraulic and geo-technical studies, cost effectiveness and ease of construction. The
GAD shall be supplemented by Preliminary designs. In respect of span arrangement and
type of bridge a few alternatives with cost-benefit implications should be submitted to
enable IAHE to approve the best alternative. After approval of alignment and GAD the
team shall prepare detailed design as per IRC codes /guidelines and working drawings
for all components of bridges and structures.
GAD for bridges/structures across irrigation/water way channels shall be got approved
from the concerned Irrigation/Water way Authorities where essential. Subsequent to
approval of GAD and alignment plan by IAHE. We shall prepare detailed design as per
IRC codes/guidelines for all components of the bridges and structures.
Subsequent to the approval of the GAD and Alignment Plan by IAHE, the Consultant
shall prepare detailed design as per IRC and working drawings for all components of the
bridges and structures. The Consultant shall furnish the design and working drawings
for suitable protection works and/or river training works wherever required.
Dismantling/ reconstruction of existing structures shall be avoided as far as possible
except where considered essential in view of their poor structural conditions/ inadequacy
of the provisions etc.
The existing structures having inadequate carriageway width shall be
widened/reconstructed in pat or fully as per the latest MoRT&H guidelines. The
Consultant shall furnish the detailed design and working drawings for carrying out the
above improvements.
Suitable repair / rehabilitation measures shall be suggested in respect of the existing
structures as per IRC-SP: 40 along with their specifications, drawings and cost estimate
in the form of a report. The rehabilitation or reconstruction of the structures shall be
suggested based on broad guidelines for rehabilitation and strengthening of existing
bridges contained in IRC-SP:35 and IRC-SP:40.
Subsequent to the approval of the GAD and the alignment plan by IAHE, detailed
design shall also be carried out for the proposed underpasses, overpasses and
interchanges.
The Consultants shall also carry out the design and make suitable recommendations for
protection works for bridges and drainage structures.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 72
In case land available is not adequate for embankment slope, suitable design for RCC
retaining wall shall be furnished. However, RES wall may also be considered depending
upon techno-economic suitability to be approved by IAHE.
C.7 Design of Drainage System
The requirement of roadside drainage system and the integration of the same with
proposed cross-drainage system shall be worked out for the entire length of the project
road section.
In addition to the roadside drainage system, the Consultants shall design the special
drainage provisions for sections with super-elevated carriageways, high embankments
and for road segments passing through cuts. The drainage provisions shall also be
worked out for road segments passing through urban areas.
The designed drainage system should show locations of turnouts/outfall points with
details of outfall structures fitting into natural contours. A separate drawing sheet
covering every 5 km. stretch of road shall be prepared.
C.8 Traffic Safety Features, Road Furniture, Road Markings and Road Signs
The Consultants shall design suitable traffic safety features and road furniture
including traffic signals, signs, markings, overhead sign boards, crash barriers,
delineators etc. The locations of these features shall be given in the reports and also
shown in the drawings.
C.9 Arboriculture and Landscaping
The Consultants shall work out appropriate plan for planting of trees (specifying type of
plantation), horticulture, floriculture on the surplus land of the right-of way with a view
to beautify the highway and making the environment along the highway pleasing. The
existing trees / plants shall be retained to the extent possible. The Transplantation of
trees shall also be proposed wherever feasible.
C.10 Toll Plaza complex & HTMS
The Consultants shall identify the possible toll plaza location(s) based on the data and
information derived from the traffic studies and a study of the existing physical features
including the availability of land. The location of the plaza should keep in view that the
project road is to be developed as a partially access controlled highway facility and it is
required to collect toll on rational basis from as much of the vehicular traffic as possible
consistent with economy of collection and operations. The location of the toll plaza
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 73
should be finalized in consultation with IAHE. Toll Plaza shall be designed as per IRC
84.
C.11 Weighing Station, Parking Areas and Rest Areas
The consultant shall select suitable sites for weighing stations, parking areas and rest
areas and prepare suitable separate designs in this regard. The common facilities like
petrol pump, first-aid medical facilities, police office, restaurant, vehicle parking etc.
should be included in the general layout for planning. For petrol pump, the guidelines
issued by OISD of Ministry of Petroleum shall be followed. The facilities should be
planned to be at approximately 50 km interval. At least each facility (1 no.) is foreseen
to be provided for this project stretch. Weighing stations can be located near toll plazas
so that overloaded vehicles can be easily identified and suitably penalized and unloaded
before being allowed to proceed further. The type of weighing system suitable for the
project shall be brought out in the report giving merits of each type of the state-of-the
art and basis of recommendations for the chosen system.
C.12 Miscellaneous works
The Consultants shall make suitable designs and layout for miscellaneous works
including rest areas, bus bays, vehicle parking areas, telecommunication facilities etc.
wherever appropriate.
The Consultants shall prepare detailed plan for the traffic management and safety
during the construction period.
3.10 ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT
D.1 Environmental Impact Assessment
D.2 Social Assessment
D.3 Reporting Requirements of EIA
D.4 Reporting requirements of RAP
The consultant shall under take the detailed environmental and social impact
assessment in accordance with the standard set by the Government of India for projects
proposed to be funded by MORT&H/ NHAI. In respect of projects proposed to be funded
by ADB loan assistance, Environmental Assessment Requirements, Environmental
Guidelines for selected infrastructure projects, 1993 of Asian Development Bank shall
be followed. Similarly, for projects proposed to be funded by World Bank loan assistance,
World Bank Guidelines shall be followed.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 74
D.1 Environmental Impact Assessment
Environment impact assessment or initial environment examination be carried out in
accordance with ADB’s Environmental Assessment Requirements of ADB
1998guidelines for selected infrastructure projects 1993 as amended from time to time
/World Bank Guidelines / Government of India Guidelines, as applicable.
1. The consultant should carry out the preliminary environmental screening to
assess the direct and induced impacts due to the project.
2. The consultant shall ensure to document baseline conditions relevant to the
project with the objective to establish the benchmarks.
3. The consultant shall assess the potential significant impacts and identify the
mitigation measures to address these impacts adequately.
4. The consultant shall do the analysis of alternatives incorporating environmental
concerns. This should include with and without scenario and modification
incorporated in the proposed project due to environment considerations.
5. The consultant shall give special attention to the environmental enhancement
measures in the project for the following:
(a) Cultural property enhancement along the highways
(b) Bus bays and bus shelters including a review of their location,
(c) Highway side landscape and enhancement of the road junctions,
(d) Enhancement of highway side water bodies, and
(e) Redevelopment of the borrow areas located on public land.
6. The consultant shall prepare the bill-of-quantities (BOQ) and technical
specifications for all items of work in such a way that these may be readily
integrated to the construction contracts.
7. The consultant shall establish a suitable monitoring network with regard to air,
water and noise pollution. The consultant will also provide additional inputs in
the areas of performance indicators and monitoring mechanisms for
environmental components during construction and operational phase of the
project.
8. The consultant shall provide the cost of mitigation measures and ensure that
environmental related staffing, training and institutional requirements are
budgeted in project cost.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 75
9. The consultant shall prepare the application forms and obtain forestry and
environmental clearances from the respective authorities including the SPCBs
and the MOEF on behalf of IAHE/ MORT&H. The consultants will make
presentation, if required, in defending the project to the MOEF Infrastructure
Committee.
10. The consultant shall identify and plan for plantation and Transplantation of the
suitable trees along the existing highway in accordance with IRC guidelines.
11. The consultant shall assist in providing appropriate input in preparation of
relevant environment and social sections of BPIP.
D.2 Social Assessment
The consultant would conduct base line socio-economic and census survey to assess the
impacts on the people, properties and loss of livelihood. The socioeconomic survey will
establish the benchmark for monitoring of R&R activities. A social assessment is
conducted for the entire project to identify mechanisms to improve project designs to
meet the needs of different stakeholders. A summary of stakeholder’s discussions, issue
raised and how the project design was developed to meet stakeholders need would be
prepared.
The consultant shall prepare Land Acquisition Plan and assist IAHE/ MORT&H in
acquisition of land under various Acts.
The consultant would prepare Resettlement and Rehabilitation Plan –assess feasibility
and effectiveness of income restoration strategies and suitability and availability to
relocation sites. The resettlement plan which accounts for land acquisition and
resettlement impacts would be based on a 25% socio-economic survey and 100 % census
survey of project affected people which provides the complete assessment of the number
of affected households and persons, including common property resources. All untitled
occupants are recorded at the initial stages and identify cards will be issued to ensure
there is no further influx of people in to the project area. All consultations with affected
persons (to include list of participants) should be fully documented and records made
available to IAHE.
Assessment on the impact of the project on the poor and vulnerable groups
along the project road corridor.
Based on the identified impacts, developing entitlement matrix for the project
affected people.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 76
Assessment on social issues such as indigenous people, gender, HIV/AIDS,
laborers including child labor.
Implementation budgets, sources and timing of funding and schedule of tasks.
Responsibility of tasks, institutional arrangements and personnel for delivering
entitlement and plans to build institutional capacity.
Internal and external Monitoring plans, key monitoring indicators and
grievance redress mechanism.
Incorporating any other suggestions of the ADB/ World Bank/MORT&H /
IAHE, till the acceptance of the reports by the ADB/ World Bank/ MORT&H
/IAHE, as applicable.
D.3 Reporting Requirements of EIA
The consultant would prepare the stand-alone reports as per the requirement of the
ADB/World Bank / MORT&H/IAHE, as applicable, with contents as per the following:
Executive Summary
Description of the Project
Identification and categorization of the potential impacts (during pre-
construction, construction and operation periods).
Analysis of alternatives (this would include correlation amongst the finally
selected alternative alignment/routing and designs with the avoidance and
environmental management solutions).
The public consultation process.
Policy, legal and administrative framework. This would include mechanisms at
the states and national level for operational policies. This would also include a
description of the organizational and implementation mechanism recommended
for this project.
Typical plan or specific designs for all additional environmental items as
described in the scope of work.
Incorporating any other as per the suggestions of the ADB/ World Bank /
MORT&H/ IAHE, till the acceptance of the reports by the ADB/ World Bank /
MORT&H/ IAHE, as applicable.
EMP Reports for Contract Package based on uniform methodology and
processes. The consultant will also ensure that the EMP has all the elements
for it to be a legal document. The EMP reports would include the following:
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 77
Brief description of the project, purpose of the EMP, commitments on
incorporating environmental considerations in the design, construction
and operations phases of the project and institutional arrangements for
implementing the EMP.
A detailed EMP for construction and operational phases with recourse to
the mitigation measures for all adverse impacts.
Detailed plans for highway-side tree plantation (as part of the
compensatory afforestation component).
Environmental enhancement measures would be incorporated.
Enhancement measures would include items described in the scope of
work and shall be complete with plans, designs, BOQ and technical
specifications.
Environmental monitoring plans during and after construction including
scaling and measurement techniques for the performance indicators
selected for monitoring.
The EMP should be amendable to be included in the contract documents
for the works.
Incorporating any other as per the suggestions of the ADB/ World Bank
MORT&H/ IAHE, till the acceptance of the reports by the ADB/ World
Bank / MORT&H/ IAHE as applicable.
D.4 Reporting requirements of RAP
Analysis on the resettlement plan be conducted based on ADBs Hand Book on
Resettlement, A Guide to Good practice 1998 as amended time to time/ World Bank
Guidelines / Government of India Guidelines, as applicable.
Executive Summary
Description of Project
Objectives of the project.
The need for Resettlement in the Project and evaluation of measures to
minimize resettlement.
Description and results of public consultation and plans for continued
participation of PAPs.
Definition of PAPs and the eligibility criteria.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 78
Census and survey results-number affected, how are they affected and what
impacts will they experience.
Legal and entitlement policy framework-support principles for different
categories of impact.
Arrangements for monitoring and evaluation (internal and external)
Implementation schedule for resettlement which is linked to the civil works
contract
A matrix of scheduled activities linked to land acquisition procedures to
indicate clearly what steps and actions will be taken at different stages and the
time frame
The payment of compensation and resettlement during the acquisition process
An itemized budget (replacement value for all assets) and unit costs for
different assets.
3.11 ESTIMATION OF QUANTITIES AND PROJECT COSTS
The Consultants shall prepare detailed estimates for quantities (considering designs
and mass haul diagram) and project cost for the entire project (civil packages wise),
including the cost of environmental and social safeguards proposed based on MoRT&H’s
Standard Data Book and market rate for the inputs. The estimation of quantities shall
be based on detailed design of various components of the projects. The estimation of
quantities and costs would have to be worked out separately for civil work Package as
defined in this TOR.
The Consultants shall make detailed analysis for computing the unit rates for the
different items of works. The unit rate analysis shall duly take into account the various
inputs and their basic rates, suggested location of plants and respective lead distances
for mechanized construction. The unit rate for each item of works shall be worked out in
terms of manpower, machinery and materials.
The project cost estimates so prepared for MORT&H/ IAHE / ADB/ WB projects are to be
checked against rates for similar on-going works in India under MORT&H/ World Bank
/ ADB financed road sector projects.
3.12 VIABILITY AND FINANCING OPTIONS
The Project Road would be divided into the traffic homogenous links based on the
findings of the traffic studies. The homogenous links of the Project Road would be
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 79
further subdivided into sections based on physical features of road and pavement, sub-
grade and drainage characteristics etc. The economic and commercial analysis shall be
carried out separately for each traffic homogenous link as well as for the Project Road.
The values of input parameters and the rationale for their selection for the economic and
commercial analyses shall be clearly brought out and got approved by IAHE.
For models to be used for the economic and the commercial analyses, the calibration
methodology and the basic parameters adapted to the local conditions shall be clearly
brought out and got approved by MORT&H/ IAHE.
The economic and commercial analyses should bring out the priority of the different
homogenous links in terms of project implementation.
Economic Analysis
The Consultants shall carry out economic analysis for the project. The analysis should
be for each of the sections covered under this TOR. The benefit and cost streams should
be worked out for the project using HDM-IV or other internationally recognized life-
cycle costing model.
The economic analysis shall cover but be not limited to be following aspects:
i. Assess the capacity of existing roads and the effects of capacity
constraints on vehicle operating costs (VOC);
ii. Calculate VOCs for the existing road situation and those for the project;
iii. Quantify all economic benefits, including those from reduced congestion,
travel distance, road maintenance cost savings and reduced incidence of
road accidents; and,
iv. Estimate the economic internal rate of return (EIRR) for the project over a
30-year period. In calculating the EIRRs, identify the tradable and non-
tradable components of projects costs and the border price value of the
tradable components.
v. Saving in time value.
Economic Internal Rate of Return (EIRR) and Net Present Value (NPV), “with” and
“without time and accident savings” should be worked out based on these cost-benefit
stream. Furthermore, sensitivity of EIRR and NPV worked out for the different
scenarios as given under:
Scenario – I Base Costs and Base Benefits
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 80
Scenario - II Base Costs plus 15% and Base Benefits
Scenario - III Base Costs and Base Benefits minus 15%
Scenario - IV Base Costs plus 15% and Base Benefits minus 15%
The sensitivity scenarios given above are only indicative. The Consultants shall select
the sensitivity scenarios taking into account possible construction delays, construction
costs overrun, traffic volume, revenue shortfalls, operating costs, exchange rate
variations, convertibility of foreign exchange, interest rate volatility, non-compliance or
default by contractors, political risks and force majeure.
The economic analysis shall take into account all on-going and future road and transport
infrastructure projects and future development plans in the project area.
Financial Analysis
It is envisaged that the project stretch should be implemented on EPC/BOT basis,
therefore, the Consultant shall study the financial viability of the project under a
commercial format and under different user fee scenarios and funding options. The
Consultants shall submit and finalize in consultation with the IAHE officers the format
for the analysis and the primary parameters and scenarios that should be taken into
account while carrying out the commercial analysis. The financial model so developed
shall be the property of IAHE.
The Financial analysis for the project should cover financial internal rate of return,
projected income statements, balance sheets and fund flow statements and should bring
out all relevant assumptions. The sensitivity analysis should be carried out for a number
of probabilistic scenarios.
The financial analysis should cover identification, assessment, and mitigating measures
for all risks associated with the project. The analysis shall cover, but be not limited to,
risks related to construction delays, construction costs over run, traffic volume, revenue
shortfalls, operating costs, exchange rate variations, convertibility of foreign exchange,
interest rate volatility, non-compliance or default by contractors, political risks and force
majeure.
The consultant shall suggest positive ways of enhancing the project Viability and
furnish different financial models for implementing on BOT format.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 81
CHAPTER 4. TASK ASSIGNMENT AND MANNING
SCHEDULE
4.1 INTRODUCTION
This Chapter gives details about the team composition, mobilization, work program and
deliverables.
4.2 TEAM COMPOSITION
The multi-disciplinary team proposed for the execution of the Project is detailed in Table
4.1 below.
Table 4.1 Team Composition Sl. No Professional Proposed Position
Key Staff
1 COL. KRISHNA SWAMY Team Leader Cum Senior Highway Engineer
2 RATHNAKARA REDDY K B Highway cum Pavement Engineer
3 BASAVARAJ C Sr. Bridge Engineer
4 SRINIVAS B N Traffic – cum – Safety Expert
5 DR.NAGAKUMAR Material cum Geo Technical Engineer
6 HEMADRAYYA HIREMATH Senior Survey Engineer
7 KRISHNA K Environmental Specialist
8 JOSEPH. M. KATTATHARA Quantity Surveyor cum Document Expert
4.3 TASK ASSIGNMENTS
Task Assignment for Key Personnel is given below:
4.3.1 Team Leader cum Senior Highway Engineer:
Overall in charge of the project. Reviewing all designs and calculations, cost estimates.
Coordinating with clients, attending meetings. Presentation to stakeholders.
Responsible for Investigation of subgrade soils, design of flexible/ rigid pavement and
recommending most economical pavement designs. Preparation of Reports:
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 82
• Finalization of methodology in consultation with the Client immediately upon the
award of the services.
• Quality Assurance Plan (QAP) covering all field, design and documentation
activities and implementation of the same.
• Design standards for the project.
• Finalization of data formats and requirements for field investigations;
• Scheduling of all field, design and documentation activities;
• Collection and compilation of data and development of data bank;
• Geometric design of alignment and design of pavements;
• Preparation of reports, documents and drawings;
• Directions to the multi-disciplinary Team of the Consultants regarding the
overall project objective and improvement/ upgrading requirements in order to
achieve the objectives; and,
• Time schedule and management of Team’s resources.
(b) The Team Leader shall be responsible for all technical presentations concerning
the various facets of the study and shall maintain close communication with IAHE.
Team Leader shall maintain a diary to record all major events and discussions
concerning the study and also the resources mobilized by the Consultants. Team Leader
shall be the Consultants Authorized Representative and shall interact with IAHE on
behalf of the Consultants appointed for the Study. Team Leader shall be full-time on the
job and shall be available for technical discussions and presentations as requested by
the Client from time to time.
4.3.2 Highway cum Pavement Engineer:
(a) Highway cum Pavement Engineer shall be responsible for all field, design
concerning strengthening of existing carriageway and design of new carriageway. The
major tasks shall include but not be limited to the following:
• Assist the Team Leader in execution of the study and preparation of DPR.
• Preparation of Quality Assurance Plan under guidance of Team Leader.
• Prepare design standards for the project.
• Geometric design of alignment.
• To maintain time schedule and management of team resources.
• Evaluation, finalization and adoption of pavement design standard.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 83
• Finalization of data formats and requirements for field studies for pavement
investigations (condition, roughness, strength, sub-grade characterization and
sub-grade strength).
• Collection, Compilation and Development of data bank for materials and
pavements.
• Data analysis and selection of parameters for the design of pavements.
• Identification of available pavement rehabilitation and design options and
selection of the same.
• Life-cycle costing for pavement design (rehabilitation of construction).
• Design of pavements (existing road, additional carriageway, service road, bypass,
intersections, toll plaza);
• Scheduling of all field, design and documentation activities;
• Scheme for pavement rehabilitation/construction;
• Reports, documents and drawings for material and pavement engineering related
features;
• Specifications for pavement materials; and
• Time schedule and management of Material and Pavement Engineering Team’s
resources.
(b) The Highway cum Pavement Engineer shall be responsible for designing of
Highways and in absence of Team Leader to perform his duties.
4.3.3 Senior Bridge Engineer
(a) The Senior Bridge Engineer shall be responsible for all field studies, data
analysis and design concerning bridges, cross-drainage and other structures. The major
tasks for Bridge Engineer shall include but not limited to the following:
• Quality Assurance Plan (QAP) and implementation of the same for all field,
design and documentation activities regarding bridge and structural engineering.
• Evaluation, finalization and adoption of field work and instrumentation for
bridge and structural design;
• Finalization of data formats and requirements for field studies for bridges and
structures.
• Collection, compilation and development of bridges and structure related data
bank;
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 84
• Inventory and condition surveys including residual life analysis.
• Hydrological surveys and data analysis;
• Data analysis and selection of parameters for the design of bridges and
structures;
• Identification of available options and selection of rehabilitation and construction
alternative based on techno-economic considerations;
• Design of bridges, cross-drainage structures and other structures (interchanges,
grade separated intersections and underpasses);
• Scheduling of all field, design and documentation activities;
• Reports, documents and drawings for bridge and structural engineering related
aspects; and,
• Time schedule and management of Bridge and Structural Engineering Team’s
resources.
(b) The Senior Bridge Engineer shall maintain a diary to record all major events
concerning bridge and structural engineering study activities including specific inputs to
the project, field discussions and also the resources (other persons, labour and
instruments) for the Bridge Engineering Team mobilized by the Consultants. The
Bridge Engineer shall be full-time on the project as in the Consultants’ technical
proposal and shall maintain a close liaison with the local agencies (such as State
PWD(s)) concerned with the National Highway Section(s) covered under the TOR and
also the other Government Departments, such as MORT&H.
4.3.4 Traffic – cum – Safety Expert
(a) The Traffic cum Safety Expert shall be responsible for all traffic engineering
related field and design activities. The major tasks shall include but not limited to the
following:
• Quality Assurance Plan (QAP) and implementation of the same for all traffic
engineering field, design and documentation activities;
• Evaluation finalization and adoption of highway capacity standard;
• Finalization of data formats and requirements for field studies for traffic volume
and other characteristics (O-D, speed-delay, axle loading, intersection volume
count etc.)
• Scheduling of all field, design and documentation activities;
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 85
• Collection, compilation and development of Traffic Data Bank;
• Analysis of traffic volume and characteristics data;
• Identification of improvement/upgrading requirements for intersections and for
partial access control.
• Identification of bypass, underpass and over-bridge requirements and input to
their geometric design;
• Type and locations of traffic control (e.g. signal) and safety measures.
• Traffic dispersion scheme at the beginning as well as the terminating points of
the highway section.
• Carriageway widening scheme.
• Design of intersections and interchanges;
• Toll plaza location and layout, toll collection method and use facilities;
• Scheme for traffic management during the construction period.
• Reports, documents and drawings for traffic engineering related features;
• Safety audit report; and,
• Time schedule and management of Traffic Engineering Team’s resources.
• To estimate the economic cost flow pattern during the analysis period of the
project road under both situation viz ‘without project’ and ‘with project’ under
various options such as rigid pavements, flexible pavements etc.,
• To estimate the net economic benefits for the project in terms of saving the
vehicle operating cost, time related cost and accident cost.
• To carry out cost benefit analysis in accordance with IRC:SP:38, IRC:-SP-30 and
to work out economic internal rate of return (EIRR) and economic net present
value (ENPV) for both ‘without’ and ‘with’ travel time cost and accident cost
saving for the project including its various improvement options and
• Finally to carry out sensitivity analysis to the economic-feasibility results for
different scenarios such as:
a. Base cost and base benefits
b. Base cost + 15% base benefits
c. Base cost and base benefits –15%
d. Base cost + 15% and base benefits – 15%
(b) The Traffic Engineer shall maintain a diary to record all major events concerning
traffic engineering study activities including specific inputs to the project, field
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 86
discussions and also the resources (other persons, labour and instruments) for the
Traffic Engineering Team mobilized by the Consultants. The Traffic Engineer shall be
full-time on the project for the time specified in the Consultants’ technical proposal and
shall maintain a close liaison with the local agencies (such as State PWD(s)) concerned
with the National Highway Section(s) covered under the TOR and also the other
Government Departments, such as MORT&H.
4.3.5 Material cum Geo Technical Engineer
(a) The Materials-cum-Geo-technical Engineer shall be responsible for all field data
analysis and design concerning geo-technical engineering aspects. The major tasks for
Materials-cum-Geo-Technical Engineer shall include but not limited to the following:
• Quality Assurance Plan (QAP) and implementation of the same for all field,
design and documentation activities regarding geo-technical engineering.
• Evaluation finalization and adoption of field work and instrumentation for geo-
technical engineering exploration, testing and design;
• Finalization of data formats and requirements for field studies for sub-soil
exploration for bridges, structures and embankments;
• Collection, compilation and development of geo-technical engineering data bank;
• Data analysis and selection of parameters for geo-technical engineering design
(design of embankments, design of foundations for bridges and structures);
• Design of embankments;
• Slope stability analysis;
• Identification of road sections with special problems (poor sub-grade, poor
drainage, erosion, subsidence and stability and design of remedial measures;
• Scheduling of all field, design and documentation activities;
• Reports, documents and drawings for geo-technical engineering related aspects;
and,
• Time schedule and management of Geo-technical Engineering Team’s resources.
(b) The Materials-cum-Geo-technical Engineer shall maintain a diary to record all
major events concerning geo-technical studies activities including specific inputs to the
project, field discussions and also the resources (other persons, labour and instruments)
for the Geo-technical Engineering Team mobilized by the Consultants. He shall be on
the project for the time specified in the Consultants’ technical proposal and shall
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 87
maintain a close liaison with the local agencies (such as State PWD(s)) concerned with
the National Highway Section(s) covered under the TOR and also the other Government
Departments, such as MORT&H.
4.3.6 Senior Survey Engineer
(a) The Senior Survey Engineer shall be responsible for the field surveys and use of
the topographic data for highway design purposes. The major tasks shall include but not
limited to the following:
• Quality Assurance Plan (QAP0 for topographic survey work and implementation
of the same.
• Data formats and methodology.
• Collection, compilation and development of data bank for topographic
information.
• Detailed scheme for field survey work.
• Mobilization of Field Survey Team and management of resources;
• Field survey for the project.
• Interpretation of field survey data.
• Identification of highway sections requiring geometric improvement;
• Identification of available alignment options;
• Relating the field survey data to the national reference, such as GTS.
• Use of computer software for data processing;
• Geometric design of highway alignment using DTM software.
• Data for generating strip plan;
• Horizontal and vertical alignment;
• Strip Plan and Alignment Report, and
• Time schedule for the topographic surveys, data processing and interpretation,
alignment design.
(b) The position is of specialized nature and the experience shall have a thorough
understanding of modern methods of surveying using sophisticated instruments such as,
total stations, EDM, digital levels and GPS and shall have proven expertise in the use of
DTM based highway alignment design software. The candidate shall be conversant with
the methods for validating and referencing system.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 88
(c) The Senior Survey Engineer shall maintain a diary to record all major events
concerning the topographic surveying including specific inputs to the project, field
discussions and also the resources (other survey persons, labour and also surveying
instruments) for the Field Survey Team mobilized by the Consultants. The Senior
Survey Engineer shall be full-time on the project for the time specified in the
Consultants’ technical proposal and shall maintain a close liaison with the local agencies
concerned with the National Highway Section (s) covered under the TOR and also the
Government Departments such as Survey of India.
4.3.7 Environmental Specialist
(a) Environmental cum Rehabilitation and Resettlement Specialist shall be
responsible for all activities related to the Environmental Impact Assessment (EIA),
Environmental Management Plan (EMP) and clearances, if any, for the project in
accordance with the guidelines of Ministry of Environment and Forest Government of
India. The major tasks Environmental Specialist / Engineer shall include but not limited
to the following
• Quality Assurance Plan (QAP) and implementation of the same for all field,
design and documentation activities regarding environmental aspects.
• Evaluation, finalization and adoption of field work and instrumentation for
environmental impact assessment and mitigation works;
• Finalization of data formats and requirements for field studies for environmental
impact studies;
• Collection, compilation and development of environment related data bank;
• Inventory of existing environmental features;
• Field studies;
• EIA study;
• Data analysis and selection of parameters for the design of environmental impact
mitigation measures;
• Identification of available options and selection of rehabilitation and construction
on the basis of environmental impact considerations;
• Environmental Management Plan including monitoring;
• Documentation for clearances as per Ministry of Environment and Forests (MEF)
and multi-lateral/bi-lateral funding agencies;
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 89
• Scheduling of all field, design and documentation activities;
• Reports, documents and drawings related to environmental aspects, and,
• Time schedule and management of Environmental Team’s resources.
• Quality Assurance Plan (QAP) and implementation of the same for all field,
design and documentation activities regarding resettlement and rehabilitation
aspects;
(b) The environmental specialist shall maintain a diary to record all major events
concerning environmental study actives including specific inputs to the project, field
discussions and also the resources (other persons, labour and instruments) for the
environmental team mobilized the consultants. The specialist shall be on the project for
the time specified in the consultant’s technical proposal and shall maintain a close
liaison with the local agencies (such as State PWD and other government departments.
4.3.8 Quantity Surveyor cum Document Expert
a) Quantity surveyor /Documentation Expert shall be responsible for all activities
related to the project. His major tasks shall include but not limited to the following.
• Material cost analysis for the project usage.
• Rate analysis of all items for construction of the project.
• Cost estimation of alternatives.
• Project Report Preparation – preliminary stage.
• Technical Specifications.
• Rate Analysis.
• Cost estimates.
• Bill of Quantities.
• Tender Documents.
• In addition to this he is also responsible for compilation and production of the
following documents.
• QAP
• Inception Report
• Feasibility Report.
• Preliminary Project Report. Draft and Final.
• Detailed Project Report Draft and Final.
• Tender Documentation.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 90
4.4 TIME SCHEDULE FOR KEY PERSONNEL
The manning schedule is given in tabular form in Table 4.2.
Table 4.2 Manning Schedule
4.5 PROJECT DURATION & DELIVERABLES
The effective date of commencement of consultancy Services is from 08.04.2015. The
duration for the entire assignment is 365 days covering various stages of work and
report submission.
Table 4.3 Project Deliverables
Sl.
No. Deliverables No. of Copies
Time Period in days from
date of commencement
1 Monthly Report 3 By 10th day of every month
2
Inception Report
(i) Draft Inception Report
including QAP document
(ii) Inception Report including
QAP document
3
3
21 days
30 days
3
Feasibility Study Report
(i) Draft Feasibility Study
Report including option
study report
(ii) Comment of client
(iii) Final Feasibility Study
4
1
4
120 days
150 days
180 days
1 2 3 4 5 6 7 8 9 10 11 12 Number of Man-months
1 COL. KRISHNA SWAMYTeam Leader Cum Senior Highway Engineer
10
2 RATHNAKARA REDDY K B Highway cum Pavement Engineer 6.5
3 BASAVARAJ C Bridge Engineer 5
4 SRINIVAS B N Traffic Engineer 4.5
5 DR.NAGAKUMAR Material cum Geotechnical Engineer 6.5
6 HEMADRAYYA HIREMATH Senior Survey Engineer 7.5
7 KRISHNA K Environmental Specialist 3.5
8 JOSEPH. M. KATTATHARAQuantity Surveyor / Documentation Expert
6
49.5Site Design office/Part time
MonthsSl No. PositionName
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 91
Sl.
No. Deliverables No. of Copies
Time Period in days from
date of commencement
Report incorporating
compliance of comments of
client
4 Technical Schedules for EPC /
PPP projects 4 240 days
5
Detailed Project Report
(i) Draft DPR
(ii) Comments of client
(iii) Final DPR incorporating
compliance of comments of
client
4
4
6
240 days
270 days
300 days
6
Project clearances from concerned
agencies.
Ex: from MOEF, Railway for
approval of GAD and detail
engineering drawing of
ROB/RUB; Irrigation
Department
Land Acquisition – 3(a), 3(A),
3(D) Notifications
Original letters from
the concerned
agencies and 5
photocopies of each.
3 copies each
365 days
4.6 MOBILIZATION
The Consultant have started functioning from its Office, Nagpur and a team of
engineers have been deployed at site for project appreciation and to carry out following
surveys and investigations at site from 20.05.2015 onwards:
Road Inventory and Condition survey
Bridge Inventory and Condition survey
Pavement and Material Investigation Survey
Topographic Survey
Traffic Survey
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 92
CHAPTER 5. WORK PROGRAMME
5.1 GENERAL
The time schedule of the Project along with work programme of activities have been
given in tabular form in Table 5.1.
Schedule for Submission of Reports and Documents.
Submission Time with effect from Date of Commencement of Consultancy Services (i.e
13.05.2015).
Deadlines as per Agreement:
Table 5.1 Work Programme
Sl.
No. Deliverables No. of Copies
Time Period in days from
date of commencement
1 Monthly Report 3 By 10th day of every month
2
Inception Report
(iii) Draft Inception Report
including QAP document
(iv) Inception Report including
QAP document
3
3
21 days
30 days
3
Feasibility Study Report
(iv) Draft Feasibility Study
Report including option
study report
(v) Comment of client
(vi) Final Feasibility Study
Report incorporating
compliance of comments of
client
4
1
4
120 days
150 days
180 days
4 Technical Schedules for EPC /
PPP projects 4 240 days
5
Detailed Project Report
(iv) Draft DPR
(v) Comments of client
(vi) Final DPR incorporating
compliance of comments of
client
4
4
6
240 days
270 days
300 days
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 93
Sl.
No. Deliverables No. of Copies
Time Period in days from
date of commencement
6
Project clearances from
concerned agencies.
Ex: from MOEF, Railway for
approval of GAD and detail
engineering drawing of
ROB/RUB; Irrigation
Department
Land Acquisition – 3(a), 3(A),
3(D) Notifications
Original letters from
the concerned
agencies and 5
photocopies of each.
3 copies each
365 days
Reports will be submitted in a set of CDs along with required number of hardcopies as
mentioned above.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 94
CHAPTER 6. PROFORMA FOR DATA COLLECTION
The Performa for collection of Primary as well as Secondary data has been given in
Quality Assurance Plan (QAP), which has been submitted to IAHE, already.
On receipt of the comments from IAHE, if any, the FINAL Q.A.P will be submitted and
circulated to all the concerned persons working on this project.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 95
CHAPTER 7. DESIGN STANDARDS AND PROPOSED
CROSS-SECTIONS
7.1 INDICATIVE DESIGN STANDARDS FOR DIVIDED CARRIAGEWAY:
7.1.1 Approach
The aim is to provide maximum safety to the road users, in defining the highway
geometry, carriageway, shoulder widths, embankments and other pertinent components
for an uninterrupted and smooth flow of traffic. The approach adopted in achieving the
safety is as follows:
• Provide appropriate cross traffic facilities without impeding traffic flow;
• Use ROW only and recommend land acquisition where absolutely
essential.
• Minimize impact on roadside settlements and environment;
• Avoid adverse impacts of crowded areas along the stretch of Project road;
• Provide cost-efficient, but readily constructible facility with least
hindrances, namely, land acquisition, resettlement and rehabilitation.
7.1.2 Reference Standards
IRC Standards will be used in general. However, where IRC does not cover any
particular feature or aspect appropriately, AASHTO and other International Standards
will be used for providing additional safety, namely, length of vertical curves in view of
likely modernization of goods trucks in India (height of driver’s eye), super elevation and
radii of curve beyond which no super elevation is needed and extra widening on
horizontal curves for smaller radii. AASHTO Standards for transition curves will be
considered as appropriate.
7.2 DESIGN STANDARDS
The following paragraph presents a summary of applicable design standards and
engineering assessment in terms of:
Highway engineering Specifications and Standards
Geometric design
Intersections
Road embankment and cutting
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 96
Pavement design
Drainage and hydrological studies
Landscaping and plantation
Design of structures
7.2.1 Highway Engineering Specifications and Standards
The main Standard applicable for the design of two-Laning (with paved shoulders) of the
Project Highway shall conform to the Manual of Specifications And Standards for Two-
Laning of highways through Public Private Partnership published by the Indian Road
Congress (IRC: SP: 73-2007) Other Design standards and specifications that would
apply shall be drawn from IRC codes and guidelines and other relevant national and
international standards.
7.2.2 Geometric Design
7.2.2.1 Terrain Classification and Design Speed
The terrain in the project stretch is plain with the general cross slope of the country is
less than 10%. Based on this the recommended Project Highway would be designed for a
design speed, referred as Ruling design speed of 80 kmph in normal situations. A
Minimum design speed of 40 to 65 kmph would be adopted where site conditions are
restrictive and adequate land width is not available.
7.2.2.2 Road Land Width
Nature of land Plain & Rolling Terrain Mountainous & Steep Terrain
Normal (m) Range (m) Normal (m)
Open areas 45 30 - 60 24
Built Up areas 30 30 - 60 20
In order to avoid and limit land acquisition, the land widths will be kept to a minimum
within the above range.
7.2.2.3 Roadway Width
The width of roadway depends on the category of road and the nature of terrain through
which it passes. Though the project stretch of Gadchiroli to Sironcha passes through
both plain and hilly terrain, every effort will be made to maintain uniformity within the
roadway width as far as practicable.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 97
The roadway width of cross-drainage structures in plain and rolling terrain measured
from outside to outside of parapet walls should be equal to the normal roadway width in
that section. In mountainous and hilly terrain, the roadway widths are exclusive of
parapets and side drains. Wherever footpath is provided, the width should not be less
than 1.5m.
On horizontal curves, the roadway width should be increased corresponding to the extra
widening of the carriageway required at the provided curvature.
7.2.2.4 Shoulder Width
A total shoulder width of 2.5m will be proposed. The 2.5m shoulder will compose of 1.5m
paved shoulder of the same composition as that of the main carriageway and 1.0m hard
shoulder composed of granular sub-base material or selected earth fill. The paved
shoulder in addition to providing lateral support to the main carriageway can also acts
as a separate lane for 2-wheeler / cycle traffic on the highway.
7.2.2.5 Pavement / Shoulder camber or cross-fall
The cross-fall in the main pavement and paved shoulder is proposed to be kept as 2.5%
and 3.0% in hard shoulder. However, on hill roads this may not be possible in every
situation, particularly in reaches with a meandering alignment where straight sections
are few and far between. In such cases, discretion may be exercised and instead of
normal camber, the carriageway may be given a uni-directional cross-fall towards the
hill side, with regard to factors such as the direction of super-elevation at the flanking
horizontal curves, ease of drainage, problem of erosion of the down-hill face, etc.
On super-elevated sections, the hard shoulder should have a rollover of 8% maximum at
the outer edge with respect to paved shoulder and a cross-fall varying from 3% to the
maximum super-elevated value on the curve at the inner edge.
7.2.2.6 Horizontal Alignment
The tangent sections, circular curve, transition curve and super elevation are the major
elements of horizontal alignment. A balanced control on the above elements is required
to provide safe and continuous flow of vehicles under the general traffic conditions.
The minimum radii of horizontal curves applicable to the Project Highway are:
Nature of Terrain Desirable Minimum Absolute Minimum
Plain 360m 230m
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 98
Nature of Terrain Desirable Minimum Absolute Minimum
Rolling 230m 155m
Mountainous 90m 60m
Steep 60m 30m
The radii of horizontal curves shall not be less than desirable value except where site
conditions are restrictive and adequate length is not available. In such restrictive
conditions, the radius of curvature shall not be less than the absolute minimum radius.
7.2.2.7 Bypasses & Re-alignments
Bypasses or detours will be provided to segregate the local traffic from the through
traffic. Re-alignments are to be done at many places having sub-standard curves and to
avoid landslide zones in hilly terrain.
Further the examination of the project alignment indicates to the possibility of two
bypasses at Gadchiroli and at Chamorshi. Also there is scope for realignment at
Sironcha as shown in succeeding paragraphs.
7.2.2.8 Vertical Alignment
There are two major elements in vertical geometry of an alignment i.e. longitudinal
gradient and vertical curve. The following gradients for Plain / Rolling terrain conditions
as of Project Highway are given below.
Nature of Terrain Ruling Gradient Limiting Gradient
Plain and Rolling 3.3% 5.0%
Mountainous 5.0% 6.0%
Steep 6.0% 7.0%
7.2.2.9 Sight Distance
Visibility is an important requirement for the safety of travel on roads. The various
sight distances for design speed applicable for Project Highway is given in the table
below.
Speed (km/hr) Stopping Sight
Distance (m)
Intermediate Sight
Distance (m)
Overtaking Sight
Distance (m)
100 180 360 640
80 120 240 470
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 99
Speed (km/hr) Stopping Sight
Distance (m)
Intermediate Sight
Distance (m)
Overtaking Sight
Distance (m)
65 90 180 340
50 60 120 235
40 45 90 165
30 30 60 120
7.2.3 Road Embankment and Cutting
Embankment height generally varies from 1.2 to 3m. High embankment is generally
provided in approach to bridges. At other sections of project road embankment varies
from 1.2m to 2.0m. All high embankments will be designed from stability considerations
and adequate protection works will be provided as per the guidelines given in various
Standards.
7.2.4 Pavement Design
Although, the main highway itself is flexible paved, possibility of provision of rigid
pavements will also be explored in certain areas. “Guidelines for the Design of Plain
Jointed Rigid Pavements for Highways”, will be followed for the design of rigid
pavement while IRC: 37-2001, “Guidelines for the Design of Flexible Pavement” will be
followed for the flexible pavement designs. The IRC-37 allows both (i) full pavement
designs for 15 years and (ii) stage construction. The Consultant will establish
alternative strategies or combination of initial design, strengthening and maintenance
to provide the specified level of pavement performance.
It may be worth mentioning that new version of IRC- 37: 2012 has been published in
July 2012.
7.2.5 Drainage and Hydrological Studies
The drainage will be designed in accordance with IRC: SP: 42 - 1994 “Guidelines on
Road Drainage” and IRC: SP: 50 – 1999 “Guidelines on Urban Drainage”. The selection
on type of drain i.e. open drains (lined or unlined) and covered drains will be made
accordingly.
7.2.6 Landscaping and Plantation
Plantation adjacent to the highway is not very significant. The final design will take
plantation into consideration.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 100
7.2.7 Design of Structures
Structures design should be planned in such a way to optimize the design variance, site
activities and materials as well. Modular design for box structures would save by the
multiple uses of the formwork and thereby would speed up the construction process.
7.2.8 Road Safety Measures
Following IRC Codes / Guidelines will be followed:
• IRC SP 44 – 1994: Highway Safety Code.
• IRC SP 43 – 1994: Guidelines on Low Cost Traffic Management Techniques for Urban
Areas.
• IRC 79 – 1981: Recommended Practice for Road Delineators.
• IRC 70 – 1979: Guidelines on Regulation and Control of Mixed Traffic in Urban Areas.
Among others, the following measures will be considered for ensuring safety: -
• Segregation of traffic;
• Bus-stops, lay-buys for cars and trucks for rest, recuperation and attend
technical problems;
• Appropriate delineators, roadway indicators, hazard / object markers with
reflectors, road markings, traffic signals, barricades, left side refuge, passage in median
for police and fire brigades, and intersection channelization;
7.2.9 Pedestrian and Animal Crossings
Besides the provisions of underpasses for the localities and urban areas, potential
locations for pedestrian and animal crossings will be examined in consultation with
IAHE and State PWD’s.
7.2.10 Road and Traffic Signs:
These include Signage, Road Signs / Hoardings, Road Markings, Traffic Signals and
lighting for interchanges, raised carriageway, long bridges and urban and populated
areas.
(a) Signage
• For the safety and guidance of a driver, proper signage and delineators
are critical. Signage drawings will show guide signs and regulating signs
at appropriate locations. The signs will be of reflector type to be easily
visible in the dark.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 101
• Guide signs at major junctions will be illuminate type and mounted to be
visible; lettering size and location of signposts will be for the design speed
and clear visibility. Reflectors will be used so that lanes are visible at
nighttime and different reflectors for median and lane striping will be
proposed to properly guide opposite traffic, and markings to indicate safe
distance between vehicles at different speeds.
(b) Road Signs
• All road signs shall be in conformity with the provision of IRC SP 32 –
1992 New Traffic Signs and IRC 67 – 1977 Code of Practice for Road
Signs. The signs are Mandatory / Regulatory, Cautionary / Warning and
Informatory.
• The bottom of the housing of a signal face will be 2500mm above footpath
when not suspended over roadway or 5500mm above pavement grade at
CL when suspended over roadway.
(c) Road lighting on Bridges and Urban Areas
• Lighting will be provided in the medians on roads with Central Medians;
on the edge of service roads; on high level masts at major intersections in
Urban Areas.
(d) Road Marking
The road markings will be in conformity with the IRC Standards (latest versions):
• IRC 35-1997 :Code of Practice for Road Markings with Paint;
• IRC 30-1968:Standard Letters and Numerals of Different Heights Use
in Highway Signs and
• IRC 31-1969:Route Marker Signs for State Roads
Hot applied thermoplastic paints will be proposed for better visibility and longer service
life (ref. Art 803-MOST Specifications).
However, all efforts will be made to keep up with new developments by conducting
deliberations and seminars. Frequent reference to codes and manuals are necessary to
be updated with revisions if any.
7.3 TYPICAL CROSS-SECTIONS
Typical cross sections for two laning and four laning with paved shoulders to be adopted
is shown below.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 102
Figure 7.2 The typical cross-section of new 2-lane with paved shoulder
Figure 7.1 The typical cross-section of new 2-lane with paved shoulder
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 103
CHAPTER 8. KEY PLAN AND LINEAR PLAN
A location map of the project road is given in Figure 8.1.
Figure 8.1 Location Map
Google map showing the details of road side improvements, habitations, river crossing
are given in strip map attached with this report.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 104
CHAPTER 9. DEVELOPMENT PLANS
9.1 GENERAL
The RFP document has been studied in detail and scope and the methodology to be
adopted for the said DPR has been enunciated in earlier paragraphs. Apart from this
during site visit on 08 April to 10 April 2015, documents available with National
highway division Nagpur as also offices of Maharashtra PWD offices at Gadchiroli,
Allepalli and Sironcha were examined.
9.2 EXISTING DEVELOPMENT PLANS AND WORK IN PROGRESS:
The Consultant is studying some of these data and development plans which they have
managed to gather during their reconnaissance trip which have helped them to identify
more sources and additional data that need to be collected during various field
investigations.
9.2.1 Proposed Bypass near Ashti
The existing alignment of Gadchiroli to Sironcha section passes through Ashti by
intersecting State Highway 11 with State Highway 09. In order to avoid the delay and
accidents at the junction, it is advised to re align the proposed corridor as shown in
below figure. This re-alignment section will save journey time of vehicles travelling in
this road.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 105
Length of Realignment = 1.700 Km
Length using Existing Route = 2.600 Km
Save in Length = 0.900 Km
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 106
9.2.2 Existing Bypass (Re-Alignment Section) Near Allepalli
As ascertained from the local PWD authorities, the alignment is deviated from entering
into town limits of Nagepalli and traversed through Allepalli and connects to the old
alignment at the junction of Road going to Aheri.
Length of Realignment = 0.800 Km
Length using Existing Route = 2.280 Km
Save in Length = 1.480 Km
Existing alignment Section (From Allepalli via Nagepalli to
Sironcha)
Re-alignment Section (From Allepalli via Nagepalli to
Sironcha)
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 107
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 108
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 109
9.2.5 Proposed Bypass-3 at Sironcha
Yet another bypass has proposal has been discussed with PWD authorities wherein the
project alignment instead of terminating at the proposed end point in town limits of
Sironcha, will provide a direct linkage to NH-16,thereby avoiding passage of heavy
traffic through the town.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 110
CHAPTER 10. QUALITY ASSURANCE PLAN (QAP)
The Quality Assurance Plan (QAP) is the Consultant’s commitment for producing a
quality Feasibility and Detailed Project Report for the Client, IAHE. As a 1st step of the
contract for the consultancy Services, a Quality Assurance Plan (QAP) is being
submitted to IAHE.
10.1 OBJECTIVES OF QAP
Is to set quality standards for performing the entire assignment
Follow the set procedure and flow in collecting data, information
Adhere to standards and codes in performing the designs
Attribute responsibility to project team members
Overall to ensure that the report follows the set and acceptable standards.
10.2 QUALITY ASSURANCE (QA)
It is of great importance to maintain consistency in design, careful preparation of
drawings and infallible design work of any projects by the consultants. The quality of
this work is a vital ingredient in the successful completion of design work and
implementation of the project both for the new highways and for upgrading and
maintaining the existing roads
Our company is an ISO 9001:2008 certified company, our edge in terms of delivering
high quality products requires effective quality assurance mechanisms. For this we have
developed and are applying a quality assurance system, which is compliant with ISO
9001:2008. Our quality assurance systems may be divided into three phases:
4) Pre-implementation phase
5) Implementation
6) Quality assurance of outputs
At the pre-implementation phase the Team Leader will focus on: (a) ensuring that there
is a clear understanding of the ToR and the expectations of the client of the required
work and outputs and (b) that the team members identified for the assignment are fully
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 111
qualified to undertake the assignment. Infra support will detail the Quality Assurance
Plan (QAP) for all field studies including topographic surveys, traffic surveys,
engineering surveys and investigations and documentation activities. The detailed QAP
will be discussed and finalized with the concerned NH officials immediately upon the
award of the Contract. The same shall be submitted within the stipulated time and
strictly adhered to. The QAP will become a guide to both consultants and the client in
executing the assignment as well as monitoring the activities.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 112
CHAPTER 11. DRAFT DESIGN STANDARDS
Geometric Design Standards of Highway (Plain Terrain, as per IRC 73 –1980)
Sl. No Description As per IRC
01. Design Speed (km/h) 100 / 80
02. Land Width (m) Normal : 45m, Range : 30 – 60m
03. Building lines (m) 80m (Overall width between Building Lines)
04.
Roadway width (m)
- For 2-lane carriageway 12.0
- On culverts (up to 6 m Span) Same as for road section
- On bridges (more than 6m span) 7.5
05.
Carriageway width (m)
- for 2 lane carriageway with paved
shoulder
10.0
06.
Shoulder width (m)
- Paved shoulder 1.5
- Hard shoulder 1.00
- Total Width 2.50
07.
Camber (percent)
- Carriageway 2.5
- Paved Shoulder 2.5
- Hard Shoulder 3.0
08.
Sight Distance (m)
- Safe stopping sight distance 180/120 for 100/80 kmph respectively
- Intermediate Sight Distance 360/240 for 100/80 kmph respectively
09. Radius of horizontal curve (m) for which
no super-elevation is required
Min : 395 ; Desirable 1780* for 100 kmph
Min : 255 ; Desirable 1140* for 80 kmph
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 113
Sl. No Description As per IRC
10. Super-elevation (e%)
As per formula
e = V2 / 225R
Where e = super elevation in metre per metre
V = design speed (km/h)
R = radius (m)
Subject to maximum of 5%
11.
General notes on Horizontal Alignment :
i) Long tangent sections exceeding 3 km in length should be avoided;
ii) Broken-back curves should be avoided or at least separated by 10 second travel time
iii) Minimum curve length should be 150 metres for 5 degree deflection angle and increased
at the rate of 30m for 1 deg. decrease thereafter.
iv) Extra widening should be provided for all curves with radius less than 300m
12.
Length of transition curve, Ls (m)
(To be obtained from the maximum of
the three formulas)
a) Ls = (0.0215 V3 ) ⁄ CR
Where, C = 0.5 / 0.516 for 100/80 kmph
V = the design speed in km/h
R = the radius of circular curve in metres
b) Ls = EWB
Where, E= super-elevation provided for the curve
W = Rate of change in super-elevation, normally 1 in
150
B = width of the carriageway
c) Ls= (2.7 V2 ) ⁄ R
Where, V = the design speed in km/h
R= the radius of circular curve in metres
13.
Maximum gradient
i Ruling 1 in 30 (Plain and Rolling Terrain)
-ii Limiting 1 in 20 (Plain and Rolling Terrain)
iii Exceptional 1 in 15 (Plain and Rolling Terrain)
14. Summit & valley curves (m) To be designed for sight distance mentioned at S. No. 9
and minimum length = 0.6V
15. Vertical Profile 1m clearance between HFL and sub-grade
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 114
Sl. No Description As per IRC
16. Minimum gradient for drainage in case
of kerbed pavements and sections in cut
Min : 0.5% for lined drain
Min : 1.0% for unlined drain
17. General notes on Vertical Alignment :
18.
Vertical Clearance for Underpasses (m)
a) ROB
b) Vehicular Underpass
c) Pedestrian / Cattle Underpass
6.25m
5.5m
3.0m
Geometric Design Standards of Highway (Hilly Terrain, IRC 52-1981 & SP – 48-1998)
Sl.No Description As per IRC
01. Design Speed (km/h) 50 / 40
02. Land Width (m) Normal : 24m, Range : 20m
03. Building lines (m) 3-5m setback from road boundary
04.
Roadway width (m)
- for 2 lane carriageway 8.8
- On culverts (up to 6 m Span) Same as for road section
- On bridges (more than 6m span) 7.5
05.
Carriageway width (m)
- for 2 lane carriageway with paved
shoulder 7.5
06.
Shoulder width (m)
- Paved Shoulder 0.0
- Hard Shoulder 0.65
- Total Width 0.65
07.
Camber (percent)
- Carriageway 2.5
- Paved Shoulder 2.5
- Hard Shoulder 3.0
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 115
Sl.No Description As per IRC
08.
Sight Distance (m)
- Safe Distance (m) 60/45 for 50/45 kmph respectively
- Intermediate Sight Distance 120/90 for 50/45 kmph respectively
09. Radius of horizontal curve (m) for which
no super-elevation is required
Min : 100 ; Desirable 450* for 100 kmph
Min : 65 ; Desirable 290* for 80 kmph
10. Super-elevation (e%)
As per formula
e = V2 / 225R
Where e = super elevation in metre per metre
V = design speed (km/h)
R = radius (m)
Subject to maximum of 5%. In critical cases a
maximum value of 7% may be adopted.
11.
General notes on Horizontal Alignment :
i) Reverse curves should be ensured with sufficient length in between for introduction of
requisite transition curves;
ii) Compound curves may be used with a limiting ration of 1.5 : 1;
iii) Minimum curve length should be 150 metres for 5 degree deflection angle and increased
at the rate of 30m for 1 deg. decrease thereafter.
iv) Extra widening should be provided for all curves with radius less than 300m
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 116
Sl.No Description As per IRC
12.
Length of transition curve, Ls (m)
(To be obtained from the maximum of
the three formulas)
a) Ls = (0.0215 V3 ) ⁄ CR
Where C = 0.64 / 0.635 for 50/40 kmph
V = the design speed in km/h
R = the radius of circular curve in metres
b) Ls = eWB
Where e = super-elevation provided for the curve
W = Rate of change in super-elevation, normally 1
in 60
B = width of the carriageway
B & W will also depend on the method of
attainment of super-elevation.
c) Ls= (1.0 V2 ) ⁄ R
Where, V = the design speed in km/h
R= the radius of circular curve in metres
13.
Maximum gradient
i Ruling 1 in 20
-ii Limiting 1 in 16.7
iii Exceptional 1 in 14.3
14. Summit & valley curves (m) To be designed for sight distance mentioned at S.
No. 9 and minimum length = 0.6V
15. Grade Compensation at Curves on Hill
Roads
= (30+R)/R, max : 75/R
where R = Radius of circular curve in m.
No grade compensation is required for gradient
flatter than 4%.
16. General notes on Vertical Alignment :
17. Vertical Profile 1m clearance between HFL and sub-grade
18. Minimum gradient for drainage in case
of kerbed pavements and sections in cut
Min : 0.5% for lined drain
Min : 1.0% for unlined drain
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Final Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 117
Sl.No Description As per IRC
19.
Vertical Clearance for Underpasses (m)
d) ROB
e) Vehicular Underpass
f) Pedestrian / Cattle Underpass
6.25m
5.5m
3.0m
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 118
CHAPTER 12. LAND ACQUISITION PLAN
12.1 LAND ACQUISITION PLAN
The Land Acquisition Plan for the proposed widening of highway and corrected
alignment of the existing highway will be prepared after acquiring the data from
relevant Authority such as the District Collector/BLRO/'Amin'.
The Consultant has initiated the efforts to obtain all land records along the highway.
The acquisition plan will be framed after Strip plan and final Highway horizontal and
vertical profile are finalized and approved by IAHE.
Detailed Project Report for up gradation of Gadichiroli -Sironcha of NH- 353 C in the state of Maharastra to two / four lane with paved shoulder configuration (Package no- NH/IAHE/02)
Revision R0 Draft Inception Report
Infra Support Engineering Consultants Pvt. Ltd in JV with IIIE Ltd 119
CHAPTER 13. SUMMARY AND CONCLUSIONS
13.1 SUMMARY
The consultant has mobilized and initial site visit was carried out in April 2015.
Complete project alignment was visited and due interaction was carried out with local
PWD officials. During the site visit, an assessment of the general terrain, condition of
pavement, type of major/minor bridges etc was carried out. Details of existing Right of
way (ROW) were also obtained from local offices. Initial appreciation of flow of traffic
from neighboring towns of Chandrapur, Nagpur, Ballarshah was carried out.
The information obtained has been tabulated in various preceding chapters. The issue of
realignment and provision of bypasses at Gadchiroli, Chamorshi, Ashti and Sironcha
have been duly explained.
Depending upon the scope and timeframe available a detailed methodology and work-
program has been evolved.
13.2 CONCLUSIONS / NEXT STEP
It will be the endeavor of the consultant to deploy adequate resources for timely
preparation of the DPR. At frequent levels interaction with IAHE officials will be carried
out for obtaining concurrence regarding issues of importance.