7/25/2019 Curs Testare fdgfd 2015666 g gh hhg http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 1/106 1 Testing Course explaining the ISTQB Certified Tester Foundation Level Syllabus

Curs Testare fdgfd 2015666 g gh hhg

Embed Size (px)

Citation preview

Page 1: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 1/106

1

Testing Course

explaining the

ISTQB Certified Tester Foundation Level Syllabus

Page 2: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 2/106

2

(…the common answer is :) To find bugs! 

...but consider also:

•To reduce the impact of the failures at the client‘s site (live defects) andensure that they will not affect costs & profitability

•To decrease the rate of failures (increase the product‘s reliability) 

•To improve the quality of the product

•To ensure requirements are implemented fully & correctly

•To validate that the product is fit for its intended purpose

•To verify that required standards and legal requirements are met•To maintain the company reputation

Testing provides the product’s measure of quality! 

Can we test everything? Exhaustive testing is possible?

-No, sorry …time & resources make it impractical !…but, instead: -We must understand the risk to the client‘s business of the software not

functioning correctly

•We must manage and reduce risk, carry out a Risk Analysis of the

application

•Prioritise tests to focus them (time & resources) on the main areas of risk

1.1.1 Why is testing necessary – Why do we test?

Page 3: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 3/106

3

The main goals of testing:

• Find defects

• Assess the level of quality of the software product and providing related

information to the stakeholders

• Prevent defects

• Reduce risk of operational incidents• Increase the product quality

Different viewpoints and objectives:

• Unit & integration test – find as many defects as possible

• Acceptance testing – confirm that the system works as specified and that thequality is good enough

• Testing metrics gathering – provide information to the project manager about

the product quality and the risks involved

• Design tests early and review requirements – help prevent defects

1.1.1 Why is testing necessary - Testing goals and objectives 

Page 4: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 4/106

4

 A programmer (or analyst) can make an error  (mistake), which produces a defect (fault, bug) in the program‘s code. If such a defect in the code is executed, the

system will fail to do what it should do (or it will do something it should not do),

causing a failure.

Error  (mistake) = a human action that produces an incorrect result

Defect (bug) = a flaw that can cause the component or system to fail to perform itsrequired function

Failure = deviation of the component or system from its expected delivery, service

or result

 Anomaly = any condition that deviates from expectations based on requirements

specifications, design documents, user documentation, standards or someone‘s

perceptions or expectations

Defect masking = An occurrence in which one defect prevents the detection of

another.

1.1.2 Why is testing necessary - Testing Glossary

Page 5: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 5/106

5

Defects are caused by human errors!

Why? Because of:

•Time pressure - the more pressure we are under the more likely we are to

make mistakes

•Code complexity or new technology

•Too many system interactions

•Poor training

•Poor communication

•Requirements not clearly defined, changed & not properly documented

•We make wrong assumptions about missing bits of information!

1.1.2 Why is testing necessary – Causes of the errors

Page 6: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 6/106

6

(Boris Beizer)

• Requirements (incorrect, logic, completeness, verifiability, documentation, changes)

• Features and functionality (correctness, missing case, domain and boundary,

messages, exception mishandled)

• Structural (control flow, sequence, data processing)

• Data (definition, structure, access, handling)

• Implementation and Coding

• Integration (internal and external interfaces)

• System (architecture, performance, recovery, partitioning, environment)• Test definition and execution (test design, test execution, documentation, reporting)

(Cem Kaner (b1))

• User interface (functionality, communication, missing, performance, output)

• Error handling (prevention, detection, recovery)

• Boundary (numeric, loops)

• Calculation (wrong constants, wrong operation order, over & underflow)• Initialization (data item, string, loop control)

• Control flow (stop, crash, loop, if-then-else,…) 

• Data handling (data type, parameter list, values)

• Race & Load conditions (event sequence, no resources)

• Source and version control (old bug reappear)

• Testing (fail to notice, fail to test, fail to report)

1.1.2 Why is testing necessary - Causes of software defects -

Defects taxonomy

Page 7: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 7/106

7

Testers do cooperate with:

 Analysts – to review the specifications for completeness and correctness,

ensure that they are testable

• Designers – to improve interfaces testability and usability

• Programmers – to review the code and assess structural flaws

• Project manager – to estimate, plan, develop test cases, perform tests and

report bugs, to assess the quality and risks

• Quality assurance staff – to provide defect metrics• Interactions with these project roles are very complex.

1.1.3 Why is testing necessary - The role of testing in the

software life cycle

Page 8: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 8/106

8

1.1.4 Why is testing necessary – What is quality?

Quality (ISO) = The totality of the characteristics of an entity that bear on its

ability to satisfy stated or implied needs

Testing means not only to Verify (the thing is done right)… but also to Validate (the right thing is done)!

Software quality includes: reliability, usability, efficiency, maintainability and

portability.

RELIABILITY: The ability of the software product to perform its required

functions under stated conditions for a specified period of time, or for a

specified number of operations.

USABILITY: The capability of the software to be understood, learned, used and

attractive to the user when used under specified conditions.

EFFICIENCY: The capability of the software product to provide appropriate

performance, relative to the amount of resources used under stated conditions.MAINTAINABILITY: The ease with which a software product can be modified

to correct defects, modified to meet new requirements, modified to make future

maintenance easier, or adapted to a changed environment.

PORTABILITY:The ease with which the software product can be transferred

from one hardware or software environment to another.

Page 9: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 9/106

9

Testing does not inject Quality into

the product, but will measure the

level of the Quality of the product.

Quality can be measured for:

• progress

• variance (planned versus actual)

1.1.4 Why is testing necessary - Testing and quality

Measuring product quality:

•Functional compliance - functional software requirements testing

•Non functional requirements:

•Security

•Performance: efficiency, responsiveness, concurrency, faulttolerance, scalability

•User friendly: accessibility, attractiveness, compatibility,

discoverability, ease of use, localizability

•Manageability: reliability, installability, maintainability, operability,

portability, recoverability, supportability, interoperability

•Test coverage criteria•Defect count or defect trend criteria

Page 10: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 10/106

10

The five basic criteria often used to decide when to stop testing are:

• Previously defined coverage goals have been met

• The defect discovery rate has dropped below a previously defined threshold

• The cost of finding the "next" defect exceeds the expected loss from that defect

• The project team reaches consensus that it is appropriate to release the product• The manager decides to deliver the product

 All these criteria are risk based.

It is important not depending on only one stopping criterion.

Software Reliability Engineering can help also to determine when to stop testing,by taking into consideration aspects like failure intensity.

1.1.5 Why is testing necessary - How much testing is enough?

Page 11: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 11/106

11

Testing = the process concerned with planning the necessary static and dynamic

activities, preparation and evaluation of software products and related deliverables,

in order to:

• determine that they satisfy specified requirements• demonstrate that they are fit for the intended use

• detect defects, help and motivate the developers to fix them

• measure, assess and improve the quality of the software product 

Testing should be performed throughout the whole software life cycle

There are two basic types of testing: execution and non-execution based

Other definitions:

•(IEEE) Testing = the process of analyzing a software item to detect the differencesbetween existing and required conditions and to evaluate its features

•(Myers (b3)) Testing = the process of executing a program with the intent of finding

errors

•(Craig & Jaskiel (b5)) Testing = a concurrent lifecycle process of engineering, using

and maintaining test-ware in order to measure and improve the quality of the

software being tested

1.2 What is testing - Definition of testing 

Page 12: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 12/106

12

• Testing shows presence of defects, but cannot prove that there are no more

defects; testing can only reduce the probability of undiscovered defects

• Complete, exhaustive testing is impossible; good strategy and risk management

must be used

• Pareto rule (defect clustering): usually 20% of the modules contain 80% of the

bugs

• Early testing: testing activities should start as soon as possible (including here

planning, design, reviews)

• Pesticide paradox: if the same set of tests are repeated over again, no new bugs

will be found; the test cases should be reviewed, modified and new test cases

developed

• Context dependence: test design and execution is context dependent (desktop,

web applications, real-time, …) 

• Verification and Validation: discovering defects cannot help a product that is not fit

to the users needs

1.3 General testing principles 

Page 13: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 13/106

13

-Test Planning & Test control

-Test Analysis & Design

-Test Implementation &

Execution

-Evaluating exit criteria &

Reporting

-Test Closure activities

1.4.1 Fundamental test process – phases 

Page 14: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 14/106

14

Planning

1. Determine scope

• Study project documents, used software life-cycle specifications, product desired

quality attributes

• Clarify test process expectations

2. Determine risks

• Choose quality risk analysis method (e.g. FMEA) 

• Document the list of risks, probability, impact, priority, identify mitigation actions

3. Estimate testing effort, determine costs, develop schedule

• Define necessary roles

• Decompose test project into phases and tasks (WBS)• Schedule tasks, assign resources, set-up dependencies

4. Refine plan

• Select test strategy (how to do it, what test types at which test levels)

• Select metrics to be used for defect tracking, coverage, monitoring

• Define entry and exit criteria

Control• Measure and analyze results

• Monitor testing progress, coverage, exit criteria

•  Assign or reallocate resources, update the test plan schedule

• Initiate corrective actions

• Make decisions 

1.4.1 Fundamental test process – planning & control 

Page 15: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 15/106

15

• Reviewing the test basis (such as requirements, architecture, design,interfaces).

• Identifying test conditions or test requirements and required test data

based on analysis of test items and the specification.

• Designing the tests:

• Choose test techniques

• Identify test scenarios, pre-conditions, expected results, post-conditions

• Identify possible test Oracles  

• Evaluating testability of the requirements and system.

• Designing the test environment set-up and identifying any required

infrastructure and tools.

(see Lee Copeland (b2))

1.4.2 Fundamental test process – analysis & design 

Page 16: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 16/106

16

• The expected result (test outcome) must be defined at the test analysis stage

• Who will decide that (expected result = actual result), when the test will be

executed? The Test Oracle!

Test Oracle = A source to determine expected result, a principle or mechanism to

recognize a problem. The Test Oracle can be:

•  an existing system (the old version…) 

•  a document (specification, user manual)

•  a competent client representative… but never the source code itself  !

Oracles in use = Simplification of Risk : do not assess ‗pass - fail‘, but instead

‗problem - no problem‘ 

Problem: Oracles and Automation - Our ability to automate testing is

fundamentally constrained by our ability to create and use oracles;

Possible issues:

• false alarms

• missed bugs 

1.4.2 Fundamental test process – what is a test Oracle? 

Page 17: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 17/106

17

1.4.3 Fundamental test process – implementation & execution 

Test implementation:

• Develop and prioritize test cases, create test data, test harnesses and automation scripts

• Create test suites from the test cases

• Check test environmentTest execution:

• Execute (manually or automatically) the test cases (suites)

• Use Test Oracles to determine if test passed or failed

• Login the outcome of tests execution

• Report incidents (bugs) and try to discover if they are caused by the test data, test

procedure or they are defect failures• Expand test activities as necessary, according to the testing mission

(see Rex Black (b4))

Page 18: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 18/106

18

1.4.3 Fundamental test process – prioritizing the Test Cases 

Why prioritize the Test Cases?

•It is not possible to test everything, we must do our best in the time available

•Testing must be Risk based, assuring that the errors, that will get through to the

client‘s production system, will have the smallest possible impact and frequency

of occurrence

•This means we must prioritise and focus testing on the priorities

What to watch?

•Severity of possible defects

•Probability of possible defects

•Visibility of possible defects•Client Requirement importance

•Business or technical criticality of a feature

•Frequency of changes applied to a module

•Scenarios complexity

Page 19: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 19/106

19

1.4.4 Fundamental test process – evaluating exit criteria and

reporting 

Evaluate exit criteria:• Check test logs against exit criteria specified in test mission definition

• Assess if more tests are needed

• Check if testing mission should be changed

Test reporting:• Write the test summary report for the stakeholders use

The test summary report should include:

• Test Cases execution coverage (% executed )

• Test Cases Pass / Fail %

• Active bugs, sorted according to their severity

(see Rex Black (b4) & RUP- Test discipline(s5))

Page 20: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 20/106

20

1.4.5 Fundamental test process – test closure 

• Verify if test deliverables have been delivered

• Check and close the remaining active bug reports

• Archiving the test-ware and environment

• Handover of the test environment

• Analyze the identified test process problems (lessons learned)

• Implement action plan based improvements 

(see Rex Black (b4))

Page 21: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 21/106

21

1.5 The psychology of testing 

Testing is regarded as a ‗destructive‘ activity

(we run tests to make the software fail…) 

A good tester:

•Should always have a critical approach

•Must keep attention to detail

•Must have analytical skills

•Should have good verbal and written

communication skills

•Must analyse incomplete facts

•Must work with incomplete facts

•Must learn quickly about the product being

tested

•Should be able to quickly prioritise

•Should be a planned, organised kind ofperson

 Also, he must have a good knowledge about:

•The customer‘s business workflows 

•The product architecture and interfaces

•The software project process•Testing techniques and practices

Rex Black’s

Top 10 professional errors

•Fall in Love with a Tool

•Write Bad Bug Reports

•Fail to Define the Mission•Ignore a Key Stakeholder

•Deliver Bad News Badly

•Take Sole Responsibility for Quality

•Be an Un-appointed Process Cop

•Fail to Fire Someone who Needs Firing

•Forget You‘re Providing a Service•Ignore Bad Expectations

(see also Brian Marick‘s article)

Page 22: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 22/106

22

1.5 The psychology of testing 

“”The best tester isn’t the one who finds the most bugs, the best tester is the one

who gets the most bugs fixed”  (Cem Kaner)

“Selling” bugs (see Cem Kaner (c1) 

•  Motivate the programmer

•  Demonstrate the bug effects

•  Overcome objections

•  Increase the defect description coverage (indicate detailed preconditions,

behavior)•  Analyze the failure

•  Produce a clear, short, unambiguous bug report

•  Advocate error costs

Levels of Independence of the Testing Team:

Low – Developers write and execute their own tests

Medium – Tests are written and executed by another developer

High – Tests written and executed by an independent testing team (internal or

external)

Page 23: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 23/106

23

2.1.1 The V testing model

Page 24: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 24/106

24

2.1.1 The V testing model – Verification & Validation

Verification = Confirmation by examination and through the provision of

objective evidence that specified requirements have been fulfilled.

Validation = Confirmation by examination and through provision of objectiveevidence that the requirements for a specific intended use or application have

been fulfilled.

Verification is the dominant activity in the Unit, Integration, System testing levels

Validation is a mandatory activity in the Acceptance testing level

Page 25: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 25/106

25

2.1.1 The W testing model – dynamic testing

Page 26: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 26/106

26

2.1.1 The W testing model – static testing

Page 27: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 27/106

27

2.1.2 Software development models - Waterfall

Page 28: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 28/106

28

2.1.2 Software development models - Waterfall

Waterfall weaknesses 

· Linear: any attempt to go back two or more phases to correct a problem or

deficiency results in major increases in cost and schedule

· Integration problems usually surface too late. Previously undetected errors

or design deficiencies will emerge, adding risk with little time to recover

· Users can't see quality until the end. They can't appreciate quality if the

finished product can't be seen· Deliverables are created for each phase and are considered frozen. If the

deliverable of a phase changes, which often happens, the project will suffer

schedule problems

The entire software product is being worked on at one time. There is no way to

partition the system for delivery of pieces of the system

Page 29: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 29/106

29

2.1.2 Software development models - Rapid Prototype Model 

Page 30: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 30/106

30

2.1.2 Software development models - Rapid Prototype Model 

Rapid Prototype Model weaknesses 

· In the rush to create a working prototype, overall software quality or

long-term maintainability may be overlooked

· Tendency for difficult problems to be pushed to the future, causing the

initial promise of the prototype to not be met by subsequent products

· Developers may fall into a code-and-fix cycle, leading to expensive,

unplanned prototype iterations

· Customers become frustrated without the knowledge of the exact

number of iterations that will be necessary

· Users may have a tendency to add to the list of items to be

prototyped until the scope of the project far exceeds the feasibility study

Page 31: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 31/106

31

2.1.2 Software development models - Incremental Model 

Page 32: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 32/106

32

2.1.2 Software development models - Incremental Model 

Incremental Model weaknesses 

· Definition of a complete, fully functional system must be done early in

the life cycle to allow for the definition of the increments

· The model does not allow for iterations within each increment

· Because some modules will be completed long before others, well-defined interfaces are required

· Requires good planning and design: Management must take care to

distribute the work; the technical staff must watch dependencies

Page 33: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 33/106

33

2.1.2 Software development models - Spiral Model 

Page 34: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 34/106

34

2.1.2 Software development models - Spiral Model 

Spiral Model weaknesses 

· The model is complex, and developers, managers, and customers may find it

too complicated to use

· Considerable risk assessment expertise is required

· Hard to define objective, verifiable milestones that indicate readiness toproceed through the next iteration

· May be expensive - time spent planning, resetting objectives, doing risk

analysis, and prototyping may be excessive

Page 35: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 35/106

35

2.1.2 Software development models - Rational Unified Process 

Page 36: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 36/106

36

2.1.3 Software development models – Testing life cycle 

• For each software activity, there must be a corresponding testing activity

• The objectives of the testing are specific to that ―tested‖ activity 

• Plan, analysis and design of a testing activity should be done during the

corresponding development activity

• Review and inspection must be considered as part of testing activities

Page 37: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 37/106

37

2.2.1 Test levels – Component testing 

 

Target: single software modules, components that are separately testable

   Access to the code being tested is mandatory, usually involves the programmer

  May consist of:

o  Functional tests

Non-functional tests (stress test)o 

Structural tests (statement coverage, branch coverage)

  Test cases follow the low level specification of the module

 

Can be automated (test driven software development):

Develop first test code

o  Then, write the code to be tested

o  Execute until pass

  Also named Unit testing

Page 38: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 38/106

38

2.2.2 Test levels – Integration testing 

 

Target: the interfaces between components and interfaces with other parts ofthe system

We focus on the data exchanged, not on the tested functionalities.

 

Product software architecture understanding is critical

  May consist of: 

o  Functional tests

o  Non-functional tests (ex: performance test)

Component integration testing (after component testing)

System integration testing (after system testing)

  Test strategy may be bottom-up, top-down or big-bang

Page 39: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 39/106

39

2.2.2 Test levels – Component Integration testing 

Component integration testing (done after Component testing) :

•Linking a few components to check that they communicate correctly

•Iteratively linking more components together

•Verify that data is exchanged between the components as required

•Increase the number of components, create & test subsystems and finally thecomplete system

Drivers and Stubs should be used when necessary:

•driver: A software component or test tool that replaces a component that takes

care of the control and/or the calling of a component or system.

•stub: A skeletal or special-purpose implementation of a software component, used

to develop or test a component that calls or is otherwise dependent on it. It replaces

a called component.

Page 40: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 40/106

40

2.2.2 Test levels – System Integration testing 

System integration testing (done after System or Acceptance testing) :

Testing the integration of systems and packages; testing interfaces to external

organizations

We check the data exchanged between our system and other external systems.

 Additional difficulties:

•Multiple Platforms

•Communications between platforms

•Management of the environments

 Approaches to access the external systems:

•Testing in a test environment

•Testing in a ‗clone‘ of a production environment 

•Testing in a real production environment

Page 41: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 41/106

41

2.2.3 Test levels – System testing 

System testing = The process of testing an integrated system to verify that it meets

specified requirements

  Target: the whole product (system) as defined in the scope document

 

Environment issues are critical

  May consist of:

o  Functional tests, based on the requirement specifications

Non-functional tests (ex: load tests)

o  Structural tests (ex: web page links, or menu item coverage)

  Black box testing techniques may be used (ex: business rule decision table)

  Test strategy may be risk based

 

Test coverage is monitored

2 2 4

Page 42: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 42/106

42

2.2.4 Test levels – Acceptance testing 

Acceptance Testing = Formal testing with respect to user needs, requirements,

and business processes conducted to determine whether or not a system satisfies

the acceptance criteria and to enable the user, customers or other authorized entity

to determine whether or not to accept the system

The main goals:

•establish confidence in the system

•is the product good enough to be delivered to the client?

The main focus is not to find defects, but to assess the readiness for deployment•It is not necessary the final testing level; a final system integration testing session

can be executed after the acceptance tests

•May be executed also after component testing (component usability acceptance)

•Usually involves client representatives

•Typical forms:•User acceptance: business aware users verify the main features

•Operational acceptance testing: backup-restore, security, maintenance

• Alpha and Beta testing: performed by customers or potential users

•Alpha : at the developer‘s site 

•Beta : at the customer‘s site 

2 3 1 T t t F ti l t ti

Page 43: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 43/106

43

2.3.1 Test types – Functional testing 

Target: Test the functionalities (features) of a product

 Specification based:

uses Test Cases, derived from the specifications (Use Cases)

business process based, using business scenarios

 Focused on checking the system against the specifications

 

Can be performed at all test levels

 Considers the external behavior of the system

 Black box design techniques will be used

 

Security testing is part of functional testing, related to the detection of threats

2 3 2 T t t N F ti l t ti

Page 44: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 44/106

44

2.3.2 Test types – Non-Functional testing 

Non functional testing = testing the attributes of a component or system that do

not relate to functionality, e.g. reliability, efficiency, usability, maintainability andportability

Targeted to test the product quality attributes:

  Performance testing

 

Load testing (how much load can be handled by the system?) 

Stress testing (evaluate system behavior at limits and out of limits)

  Usability testing

  Reliability testing

 

Portability testing

  Maintainability testing

2 3 2 T t t N F ti l t ti U bilit

Page 45: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 45/106

45

2.3.2 Test types – Non-Functional testing - Usability 

Usability testing = used to determine the extent to which the software product is

understood, easy to learn, easy to operate and attractive to the users under

specified conditions

•People selected from the potential users may be involved to study how they

use the system

• A quick and focused beta-test may be a cheap way of doing Usabilitytesting

•There is no simple way to examine how people will use the system

•Easy to understood is not the same as easy to learn or as easy to use or as

easy to operate

2 3 2 T t t N F ti l t ti I t l bilit

Page 46: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 46/106

46

2.3.2 Test types – Non-Functional testing - Instalability 

Instalability testing = The process of testing the installability of a softwareproduct‖

•Does the installation work?

•How easy is to install the system?

•Does installation affect other software?

•Does the environment affect the product?

•Does it uninstall correctly?

2.3.2 Test types – Non-Functional testing – Load, Stress,

Page 47: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 47/106

47

yp g , ,

Performance, Volume testing 

Load Test = A test type concerned with measuring the behavior of a component

or system with increasing load, e.g. number of parallel users and/or numbers of

transactions to determine what load can be handled by the component or system

Stress Test = Testing conducted to evaluate a system or component at or

beyond the limits of its specified requirements.

Performance Test = The process of testing to determine the performance of a

software product

Volume Test = Testing where the system is subjected to large volumes of data

2 3 3 Test types Structural testing

Page 48: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 48/106

48

2.3.3 Test types – Structural testing 

  Targeted to test:

internal structure (component)o  architecture (system)

Uses only white box design techniques

  Can be performed at all test levels

  Used also to help measure the coverage (% of items being covered by tests)

 

Tool support is critical

2 3 4 Test types Confirmation & regression testing

Page 49: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 49/106

49

2.3.4 Test types – Confirmation & regression testing 

Confirmation testing = Re-testing of a module or product, to confirm that the

previously detected defect was fixed

  Implies the use of a bug tracking tool

 

Confirmation testing is not the same as the ―debugging‖ (debugging is a

development activity, not a testing activity)

Regression testing = Re-testing of a previously tested program following

modification to ensure that defects have not been introduced or uncovered as a

result of the changes made. It is performed when the software or its environment

is changed

 

Can be performed at all test levels 

Can be automated (because of cost and schedule reasons)

2 4 Maintenance testing

Page 50: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 50/106

50

2.4 Maintenance testing 

Maintenance testing = Testing the changes to an operational system or the

impact of a changed environment to an operational system

Done on an existing operational system, triggered by modification, retirement or

migration of the software

Include:

•Release based changes•Corrective changes

•Database upgrades

Regression testing is also involved

Impact analysis = determining how the existing system may be affected bychanges (used to help decide how much regression testing to do)

3 1 Reviews and the testing process

Page 51: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 51/106

51

3.1 Reviews and the testing process 

Static Testing = testing of a component or system at specification or

implementation level without execution of that software, e.g. reviews (manual) or

static code analysis (automated)

Reviews

Why review?

•To identify errors as soon as possible in the development lifecycle

•Reviews offer the chance to find omissions and errors in the software

specifications

The target of a review is a software deliverable:

 

Specification

  Use case

 

Design  Code

  Test case

  Manual

3 1 Reviews and the testing process

Page 52: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 52/106

52

3.1 Reviews and the testing process 

When to review?

• As soon as an software artifact is produced, before it is used as the basis for the

next step in development

Benefits include:

 

Early defect detection

  Reduced testing costs and time

  Can find omissions

Risks:

•If misused they can lead to project team members frictions

•The errors & omissions found should be regarded as a positive issue

•The author should not take the errors & omissions personally

•No follow up to is made to ensure correction has been made

•Witch-hunts used when things are going wrong

3 2 1 Phases of a formal review

Page 53: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 53/106

53

3.2.1 Phases of a formal review 

Formal review phases:

•Planning: define scope, select participants, allocate roles, define entry &

exit criteria

•Kick-off: distribute documents, explain objectives, process, check entry

criteria

•Individual preparation: each of participants studies the documents, takesnotes, issues questions and comments

•Review meeting: meeting participants discuss and log defects, make

recommendations

•Rework: fixing defects (by the author)

•Follow-up: verify again, gather metrics, check exit criteria

3 2 2 Roles in a formal review

Page 54: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 54/106

54

3.2.2 Roles in a formal review 

The formal reviews can use the following predefined roles:

  Manager: schedules the review, monitor entry and exit criteria

 

Moderator: distributes the documents, leads the discussion, mediates

various conflicting opinions

   Author: owner of the deliverable to be reviewed

  Reviewer: technical domain experts, identify and note findings

 

Scribe: records and documents the discussions during the meeting

3 2 3 Types of review

Page 55: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 55/106

55

3.2.3 Types of review 

Informal review

• A peer or team lead reviews a software

deliverable

•Without applying a formal process•Documentation of the review is optional

•Quick way of finding omissions and defects

• Amplitude and depth of the review depends

on the reviewer

•Main purpose: inexpensive way to get

some benefit

Walkthrough

•The author of the deliverable leads the

review activity, others participate

•Preparation of the reviewers is optional

•Scenario based

•The sessions are open-ended•Can be informal but also formal

•Main purposes: learning, gaining

understanding, defect finding

Technical Review

•Formal Defect detection process

•Main meeting is prepared

•Team includes peers and technical domainexperts

•May vary in practice from quite informal to very

formal

•Led by a moderator, which is not the author

•Checklists may be used, reports can be prepared

•Main purposes: discuss, make decisions,

evaluate alternatives, find defects, solve technicalproblems and check conformance to

specifications and standards.

Inspection

Formal process, based on checklists, entry and

exit criteriaDedicated, precise roles

Led by the moderator

Metrics may be used in the assessment

Reports, list-of-findings are mandatory

Follow-up process

Main purpose: find defects

3 2 4 Success factors for reviews

Page 56: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 56/106

56

3.2.4 Success factors for reviews 

  Clear objective is set

   Appropriate experts are involved

 

Identify issues, not fix them on-the-spot   Adequate psychological handling (author is not punished for the found

defects)

 

Level of formalism is adapted to the concrete situation

  Minimal preparation and training

  Management encourages learning, process improvement

  Time-boxing is used to determine time allocated to each part of thedocument to be reviewed

  Use of effective checklists 

3 3 Static analysis by tools

Page 57: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 57/106

57

3.3 Static analysis by tools 

•Performed without executing the examined software, but assisted by tools

•The approach may be data flow or control flow based

•Benefits:

• early defects detection

• early warnings about unwanted code complexity

• detects missing links

• improved maintainability of code and design

• Typical defects discovered:

• reference to an un-initialized variable

• never used variables

• unreachable code

• programming standards violations

• security vulnerabilities

4. Test design techniques - glossary

Page 58: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 58/106

58

4. Test design techniques glossary 

  Test condition = item, event, attribute of a module or system that could

be verified (ex: feature, structure element, transaction, quality attribute)

  Test data = data that affects or is affected by the execution of the

specific module

 

Test case [IEEE] = a set of input values, execution preconditions,

expected results and execution post-conditions, developed for a particularobjective or test condition, such as to exercise a particular program path or

to verify compliance with a specific requirement

 

Test case specification [IEEE] = a document specifying a set of test

cases for a test condition

 

Test procedure (suite) specification = a document specifying asequence of actions for the execution of a series of test cases

4.1 Test design – test development process

Page 59: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 59/106

59

4.1 Test design   test development process 

1.  Identify test conditions:

Inputs:

•Field – level•Group – level

Capability related:

•Trigger conditions

•Constraints or limits

•Interfaces to other products

•Validation of inputs at the followinglevels of aggregation:

•Field / action / message

•Record / row / window

•File / table / screen

•Database

•Product states

•Behavior rules

 Architectural design related:

•Invocation paths

•Communication paths

•Internal data conditions

•Design states•Exceptions

2. Develop test cases

· Use cases are used as input

· Test cases will cover all possible paths of the

execution graph flow

· Test data should be specified if necessary

· Priorities of Test cases should be assigned

· Traceability matrix (Use cases x Test cases)

should be maintained

3. Develop test procedures

· Group test cases into execution schedules

· Factors to be considered:

a. Prioritization

b. Logical dependencies

c. Regression tests

· Traceability from test condition to the

specifications (requirements) is a must

· Risk analysis is a best practice

4.2 Test design – categories of test design techniques

Page 60: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 60/106

60

4.2 Test design   categories of test design techniques 

Black box: no internal structure knowledge will be used

White box: based on the analysis of the internal structure

Static: without running, exercised on specific project artifacts

Each black box or white box test technique has:

• A method (how to do it)

• A test case design approach (how to create test cases using the approach)

• A measurement technique – coverage % (except the black box Syntax testing)

Other taxonomy:

  Specification based: test cases are built from the specifications of the module

  Structure based: information about the module is constructed (design, code) is

used to derive the test cases

 

Experience based: tester‘s knowledge about the specific domain, about thelikely defects, is used

4.3.1 Black box techniques – equivalence partitioning 

Page 61: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 61/106

61

3 ac bo tec ques equ a e ce pa t t o g

  To minimize testing, partition input (output) values into groups of equivalent

values (equivalent from the test outcome perspective)

 

Select a value from each equivalence class as a representative valueIf an input is a continuous range of values, then there is typically one class of valid

values and two classes of invalid values, one below the valid class and one

above it.

Example: Rule for hiring a person is second its age:

0 – 15 = do not hire

16 – 17 = part time

18 – 54 = full time

55 -- 99 = do not hire

Which are the valid equivalence classes? And the invalid ones?

Give examples of representative values!

(other examples) 

(see Lee Copeland b2 chap.3, Cem Kaner c1, Paul Jorgensen b7 chap.2.2,6.3)

4.3.1 Black box techniques – all-pairs testing

Page 62: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 62/106

62

q p g

In practice, there are situations when a great number of combinations must be

tested. For example: A Web site must operate correctly with different browsers—

Internet Explorer 5.0, 5.5, and 6.0, Netscape 6.0, 6.1, and 7.0, Mozilla 1.1, and

Opera 7; using different plug-ins—RealPlayer, MediaPlayer, or none; running on

different client operating systems—Windows 95, 98, ME, NT, 2000, and XP;

receiving pages from different servers—IIS, Apache, and WebLogic; running on

different server operating systems—Windows NT, 2000, and Linux.

•Test environment combinations: 

•8 browsers

•3 plug-ins

•6 client operating systems

•3 servers

•3 server OS

•1,296 combinations !

• All-pairs testing is the solution : tests a significant subset of variables pairs.

4.3.2 Black box techniques – boundary value analysis 

Page 63: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 63/106

63

q y y

Boundaries = edges of the equivalence classes.

Boundary values = values at the edge and nearest to the edge

The steps for using boundary values:

•First, identify the equivalence classes.

•Second, identify the boundaries of each equivalence class.

•Third, create test cases for each boundary value by choosing one point on the

boundary, one point just below the boundary, and one point just above theboundary. "Below" and "above" are relative terms and depend on the data

value's units

•For the previous example:

•boundary values are {-1,0,1}, {14,15,16},{15,16,17},{16,17,18}{17,18,19},

{54,55,56},{98, 99, 100}

Or, omitting duplicate values:

{-1,0,1,14,15,16,17,18,19,54,55,56,98,99,100}

(other examples) 

(see Lee Copeland b2 chap.4, Paul Jorgensen b7 chap5)

4.3.3 Black box techniques – decision tables 

Page 64: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 64/106

64

q

 

Conditions represent various input conditions

   Actions are the actions taken depending on the various combinations of input

conditions

  Each of the rules defines a unique combination of conditions that result in the

execution of the actions associated with that rule   Actions do not depend on the condition evaluation order, but only on their

values.

 

 Actions do not depend on any previous input conditions or system state.

(see Lee Copeland b2 chap 5, Paul Jorgensen b7 chap 7)

4.3.3 Black box techniques – decision tables - example

Page 65: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 65/106

65

q p

a, b, c are they the edges of a triangle?

(however, some additional test cases are needed)

4.3.4 Black box techniques – state transition tables

Page 66: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 66/106

66

q

 Allow the tester to interpret the system in term of:

 

States

 

Transition between states

 

Events that trigger transitions

 

 Actions resulting from the transitions

 

Transition table used:

(see Lee Copeland b2, chap 7)

4.3.4 Black box techniques – state transition tables - example

Page 67: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 67/106

67

Ticket buy - web application

Exercise: Fill-in the transition table!

4.3.5 Black box techniques – requirements based testing

Page 68: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 68/106

68

Best practices:

•Validate requirements (what) against objectives (why)

• Apply use cases against requirements

•Perform ambiguity reviews

•Involve domain experts in requirements reviews

•Create cause-effect diagrams

•Check logical consistency of test scenarios

•Validate test scenarios with domain experts and users

•Walk through scenarios comparing with design documents•Walk through scenarios comparing with code

4.3.5 Black box techniques – scenario testing

Page 69: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 69/106

69

Good scenario attributes:

•Is based on a real story

•Is motivating for the tester

•Is credible

•Involves an enough complex use of environment and data

•Is easy to evaluate ( no need for external oracle)

How to create good test scenarios:

•Write down real-life stories

•List possible users, analyze their interests and objectives

•Consider also inexperienced or ostile users

•List system benefits and create paths to access those features

•Watch users using old versions of the system or an analog system

•Study complaints about other analog systems

4.3.5 Black box techniques – use case testing

Page 70: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 70/106

70

Generating the Test Cases from the Use Cases

Steps:

1. Identify the use-case

scenarios.

2. For each scenario, identify one

or more test cases.3. For each test case, identify the

conditions that will cause it to

execute.

4. Complete the test case by

adding data values.

(see example) 

Most common test case mistakes:

1. Making cases too long

2. Incomplete, incorrect, or incoherent setup

3. Leaving out a step

4. Naming fields that changed or no longer exist5. Unclear whether tester or system does action

6. Unclear what is a pass or fail result

7. Failure to clean up

4.3.5 Black box techniques – Syntax testing

Page 71: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 71/106

71

Syntax testing = uses a model of the formally-defined syntax of the inputs to a

Component

The syntax is represented as a number of rules each of which defines the

possible means of production of a symbol in terms of sequences of, iterations

of, or selections between other symbols.

Here is a representation of the syntax for the floating point number, float inBackus Naur Form (BNF) :

float = int "e" int.

int = ["+"|"-"] nat.

nat = {dig}.

dig = "0"|"1"|"2"|"3"|"4"|"5"|"6"|"7"|"8"|"9".

Syntax testing is the only black box technique without a coverage metric

assigned.

4.4 White box techniques – Control flow 

Page 72: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 72/106

72

Modules of code are converted to graphs, the paths through the graphs are analyzed, and

test cases are created from that analysis. There are different levels of coverage.

Process Blocks

 A process block is a sequence

of program statements that

execute sequentially.

No entry into the block is

permitted except at thebeginning. No exit from the

block is permitted except at

the end. Once the block is

initiated, every statement

within it will be executed

sequentially.

Decision Point

 A decision point is a point in the

module at which the control

flow can change. Most decision

points are binary and are

implemented by if-then-else

statements. Multi-way decision

points are implemented by

case statements. They are

represented by a bubble with

one entry and multiple exits.

Junction Point

 A junction point is a point at

which control flows join

together

Example:

(see Lee Copeland b2, chap.10)

4.4.1 White box techniques – statement coverage

Page 73: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 73/106

73

Statement coverage = Executed statements / Total executable statements

Example:

a;  

if (b) {  

c;  

 }  

d ;  

In case b  is TRUE, executing the code will result in 100% statement coverage

4.4.1 White box techniques – statement coverage - exercise

Page 74: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 74/106

74

Given the code:

a;

if (x) {

b;

if (y) {

c;

}else {

d;

}

}

else {

e;

}

How many test cases are needed to get 100% statement coverage?

x T T F F

y T F T F

a a a a

b b

c

d

e e

4.4.2 White box techniques – branch & decision coverage - glossary

Page 75: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 75/106

75

Branch = a conditional transfer of control from a statement to any other statement

OR

= an unconditional transfer of control from a statement to any otherstatement except the next statement;

Branch coverage = executed branches / total branches

Decision coverage = executed decisions outcomes / total decisions

For components with one entry point 100% Branch Coverage is equivalent to

100% Decision Coverage

4.4.2 White box techniques – branch & decision coverage - example

Page 76: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 76/106

76

Decisions = B2, B3, B5 each with 2 outcomes = 3 * 2 = 6

Branches = (how many arrows?) = 10

Q1. What are the decision and branch coverage for (B1  B2 

B9) ?

Q2. But for (B1->B2->B3->B4->B8->B2->B3->B5->B6->B8->B2-

>B3->B5->B7) ? 

 Answers: 1. 1/6, 2/10 2. 5/6, 9/10

4.4.2 White box techniques – LCSAJ coverage

Page 77: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 77/106

77

LCSAJ = Linear Code Sequence and Jump

Defined by a triple, conventionally identified by line numbers in a source

code listing:

•the start of the linear code sequence•the end of the linear code sequence

•the target line to which control flow is transferred

LCSAJ coverage = executed LCSAJ sequences / total nr. of LCSAJ seq.

4.4.3 White box techniques – data flow coverage

Page 78: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 78/106

78

Just as one would not feel confident about a program without executing every

statement in it as part of some test, one should not feel confident about a program

without having seen the effect of using the value produced by each and everycomputation.

Data flow coverages:

• All defs = Number of exercised definition-use pairs / Number of variable definitions

• All c(omputation)-uses = Number of exercised definition- c-use pairs / Number of

definition- c-use pairs

• All p(redicate)-uses = Number of exercised definition- p-use pairs / Number of

definition- p-use pairs

• All uses = Number of exercised definition- use pairs / Number of definition- use pairs

•Branch condition = Boolean operand values executed / Total Boolean operandvalues

•Branch condition combination = Boolean operand values combinations executed /

Total Boolean operand values combinations

(see Lee Copeland b2, chap.11)

4.5 Exploratory testing

Page 79: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 79/106

79

  Exploratory testing = Concurrent test design, test execution, test logging

and learning, based on a quick test charter containing objectives, and executed

within delimited time-intervals  Uses structured approach to error guessing, based on experience,

available defect data, domain expertise

  On-the-fly design of tests that attack these potential errors

  Skill, intuition and previous experience is vital

  Test strategy is built around:

•The project environment

•Quality criteria defined for the project

•Elements of the product

•Risk factors

4.6 Choosing test techniques

Page 80: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 80/106

80

Factors used to choose:

  Product or system type

  Standards

  Product‘s requirements 

   Available documentation

  Determined risks

  Schedule constraints

  Cost constraints

  Used software development life cycle model

  Tester‘s skills and (domain) experience 

(see some exercises …) 

5.1.1 Test organization & independence

Page 81: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 81/106

81

Options : independent team or not?

Pluses:

  Testers are not influenced by the other project members

  Can act as ‗the customer‘s voice‘ 

  More objectivity in evaluating the product quality issues

Minuses:

  Risk of isolation from the development team

  Communication issues

· Developers can loose the ‗quality ownership‘ attribute

5.1.2 Tasks of the test leader

Page 82: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 82/106

82

•Plan, estimates test effort, collaborates with project manager

•Elaborates the test strategy

•Initiate test specification, implementation, execution

•Set-up configuration management of test environment & deliverables

•Monitors and controls the execution of tests

•Chooses suitable test metrics

•Decides if and to what degree to automate the tests

•Select tools

•Schedule tests

•Prepare summary test reports

•Evaluate test measurements

5.1.2 Tasks of the tester

Page 83: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 83/106

83

Test Analyst 

 

Identify test objectives (targets)

 

Review product requirements andsoftware specifications

  Review test plans and test cases

  Verifies requirements to test cases

traceability

  Define test scenario details

  Compares test results with test

oracle

 

 Assesses test risks

 

Gather test measures

Test Designer  

  Define test approach (procedure)

 

Structure test implementation

  Elaborates test case lists and

writes main test cases

 

 Assesses testability

Define testing environment details

Tester  

  Define test approach (procedure)

 

Write test cases

  Review test cases (peer review)

  Implement and execute tests

Record defects, prepare defect reports

5.2.1-5.2.2-5.2.3 – Test planning

Page 84: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 84/106

84

Test plan = A document describing the scope, approach, resources and schedule of

intended test activities

It identifies amongst others test items, the features to be tested, the testing tasks, who

will do each task, degree of tester independence, the test environment, the test designtechniques and test measurement techniques to be used, and the rationale for their

choice, and any risks requiring contingency planning.

It is a record of the test planning process

IEEE 829: Test plan contents:

•Test plan identifier

•Introduction

•Test items

•Features to be tested

•Features not to be tested

• Approach•Item pass / fail criteria

•Suspension criteria & resumption

criteria

•Test deliverables

•Testing tasks

•Environment

•Responsibilities

•Staffing and training needs

•Schedules•Risks and contingencies

• Approvals

5.2.1-5.2.2-5.2.3 – Test planning Determine scope

Page 85: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 85/106

85

  Determine scopeo

  Study project documents, used

software life-cycle specifications, product

desired quality attributeso  Identify and communicate with other

stakeholderso  Clarify test process expectations

 

Determine riskso  Choose quality risk analysis method

(e.g. FMEA)

Document the list of risks,probability, impact, priority, identify

mitigation actions

 

Estimate testing effort, determine costs,

develop scheduleo  Define necessary roles

Decompose test project into phasesand tasks (WBS)o  Schedule tasks, assign resources,

set-up dependencieso  Develop a budget

o  Obtain commitment for the plan

from the stakeholders 

  Refine plano  Define roles detailed

responsibilities

Select test strategy, test levels:Test strategy issues (alternatives):

  Preventive approach

  Reactive approach

  Risk-based

  Model (standard) based

  Choosing testing techniques (white

and/or black box)

o  Select metrics to be used for defect

tracking, coverage, monitoring

Define entry and exit criteria•

 

Exit criteria:

  Coverage measures

  Defect density or trend measures

  Cost

  Residual risk estimation

  Time or market based

5.2.4 – Test estimation

Page 86: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 86/106

86

Two approaches:

• based on metrics (historical data)

• made by domain experts

Testing effort depends on:

• product characteristics (complexity, specification)

• development process (team skills, tools, time factors)

• defects discovered and rework involved

• failure risk of the product (likelihood, impact)

Time for confirmation testing and regression testing must be

considered too

5.2.5 – Test strategies

Page 87: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 87/106

87

Test approach (test strategy) = The chosen approaches and decisions made that follow from the

test project's and test team's goal or mission.

The mission is typically effective and efficient testing, and the strategies are the general policies,

rules, and principles that support this mission. Test tactics are the specific policies, techniques,

processes, and the way testing is done.

One way to classify test approaches or strategies is based on the point in time at which the bulk of

the test design work is begun:

•Preventative approaches, where tests are designed as early as possible.

•Reactive approaches, where test design comes after the software or system has been produced.

5.3 – Test progress monitoring, reporting & control

Page 88: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 88/106

88

Monitoring - Test metrics used:

•Test cases (% passed/ % failed)

•Defects (found, fixed/found, density,

trends)

•Test Coverage (% executed Test cases)

Reporting:

•Defects remaining

•Coverage metrics

•Identified risks

Control: identify and implement

corrective actions for:•Testing process

•Other software life-cycle activities

Possible corrective actions:

• Assign extra resource

•Re-allocate resource

• Adjust the test schedule

• Arrange for extra test

environments

•Refine the completion criteria

5.4 – Configuration management

Page 89: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 89/106

89

IEEE definition of Configuration Management:

 A discipline applying technical and administrative direction and surveillance to:

•identify and document the functional and physical characteristics of a

configuration item,•control changes to those characteristics,

•record and report change processing and implementation status, and

•verify compliance with specified requirements

Configuration Management:

•identifies the current configuration (hardware, software) in the life cycle of

the system, together with any changes that are in course of being

implemented.

•provides traceability of changes through the lifecycle of the system.

•permits the reconstruction of a system whenever necessary

Only persistent objects must be subject to Configuration Management,

therefore, the data processed by a system cannot be placed under

Configuration Management.

•Related to Version Control and Change Control

5.4 – Configuration management

Page 90: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 90/106

90

Configuration Management activities:

Configuration identification = selecting the configuration items for a system

and recording their functional and physical characteristics in technicaldocumentation

Configuration control = evaluation, co-ordination, approval or disapproval, and

implementation of changes to configuration items after formal establishment of

their configuration identification

Status accounting = recording and reporting of information needed to manage

a configuration effectively, including:

•a listing of the approved configuration identification,

•the status of proposed changes to the configuration, and

•the implementation status of the approved changes

Configuration auditing = The function to check that the software product

matches the configuration items identified previously

5.4 – Configuration management

Page 91: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 91/106

91

In Testing, Configuration Management must:

•Identify all test-ware items

•Establish and maintain the integrity of the testing deliverables

(test plans, test cases, documentation) through the project life

cycle

•Set and maintain the version of these items

•Track the changes of these items

•Relate test-ware items to other software development items in

order to maintain traceability•Reference clearly all necessary documents in the test plans

and test cases

5.5 – Risk & Testing 

Page 92: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 92/106

92

Risk = a factor that could result in future negative consequences,

expressed as likelihood and impact

  Project risks (supplier related, organizational, technical)

  Product risks (defects delivered, poor quality attributes (reliability,

usability, performance)

The risks identified can be used to:

  Define the test strategy and techniques to be used

  Define the extent and depth of testing

  Prioritize test cases and procedures (find important defects early)

  Determine if review or training activities could help

5.6 – Incident management

Page 93: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 93/106

93

Incident = any significant, unplanned event that occurs during testing thatrequires subsequent investigation and / or correction

•The system does not function as expected

• Actual results differ from expected results

•Required features are missing

Incident reports can be raised against:

•documents placed under review process

•product‘s defects related to functional & non-functional requirements

•documentation anomalies (manuals, on-line help)

•test-ware defects (errors in test cases or test procedures)

The incident reports raised against products defects are named also bug

reports.

5.6 – Incident management

Page 94: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 94/106

94

Recommended Bug report format 

•Defect ID

•Component name and Build version

•Reported by and Date

•Error type

•Severity

•Priority

•Summary and detailed description

• Attached documents

(Exercise)

Bug statuses

Issued – just been reported

Opened – programmer is working to solve-it

Fixed – programmer thinks that‘s repaired 

Not solved – tester retested but the bug is

not solved

Deferred – programmer or PM decided topostpone the decision

Not-a-bug – programmer or tester

discovered that it is not a defect

Closed – bug is solved and verified

6.1.1 – Test tool classification

Page 95: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 95/106

95

• Management of testing:

•Test management

•Requirements management

•Bug tracking

•Configuration management

• Static testing:

•Review support

•Static analysis

•Modeling

• Test specification:

•Test design

•Test data preparation

• Test execution:

•Record and play

•Unit test framework

•Result comparators

•Coverage measurement

•Security

• Performance and monitoring:

•Dynamic analysis

•Load and stress testing

•Monitoring

• Specific application areas

• Other tools

6.1.2 – Tool support - Management of testing

Page 96: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 96/106

96

•Test management:

•Manage testing activities

•Manage test-ware traceability

•Test result reporting

•Test metrics tools

•Requirements management:

•Checking

•Traceability

•Coverage

•Bug tracking

•Configuration management 

•Individual support:

•Version and change control

•Builder

•Project related

•Department or company related

6.1.3 – Tool support - Static testing

Page 97: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 97/106

97

•Review support:

•Process support

•Communications support

•Team support

•Static analysis:

•Coding standards

•WEB site structure

•Metrics

•Modeling:

•SQL database management

6.1.4 – Tool support – Test specification

Page 98: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 98/106

98

•Test design:

•From requirements•From design models

•Test stubs and driver generators

•Test data preparation

Page 99: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 99/106

6.1.6 – Tool support – Performance and monitoring

Page 100: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 100/106

100

•Dynamic analysis:

•Time dependencies•Memory leaks

•Load testing

•Stress testing

•Monitoring

6.2.1 – Tool support – benefits

Page 101: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 101/106

101

•Repetitive work is reduced (e.g. running regression tests, re-entering the

same test data, and checking against coding standards).

•Greater consistency and repeatability (e.g. tests executed by a tool, and

tests derived from requirements).

•Objective assessment (e.g. static measures, coverage and system

behavior).

•Ease of access to information about tests or testing (e.g. statistics andgraphs about test progress, incident rates and performance).

6.2.1 – Tool support – risks

Page 102: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 102/106

102

•Unrealistic expectations for the tool (including functionality and ease of

use).

•Underestimating the time, cost and effort for the initial introduction of a tool

(including training and external expertise).

•Underestimating the time and effort needed to achieve significant and

continuing benefits from the tool (including the need for changes in the

testing process and continuous improvement of the way the tool is used).

•Underestimating the effort required to maintain the test assets generated by

the tool.

•Over-reliance on the tool (replacement for test design or where manual

testing would be better).

•Lack of a dedicated test automation specialist

•Lack of good understanding and experience with the issues of test

automation

•Lack of stakeholders commitment for the implementation of a such tool

6.2.2 – Tool support – special considerations

Page 103: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 103/106

103

•Test execution tools:

•Significant implementation effort•Record and play tools are instable when changes occur

•Technical expertise is mandatory

•Performance testing tools:

•Expertise in design and results interpretation are mandatory

•Static analysis tools:

•Lots of warnings generated

•Build management sensitive

•Test management tools:

•Interfacing with other tools (Windows Office, at least) is critical

6.2.2 – Tool support – testing in Visual Studio Team System 

Page 104: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 104/106

104

•Developer:

•use Test Driven

Development methods

•manage Unit Testing

•analyze code coverage

•use code static analysis

•use code profiler to handle

performance issues•Tester:

•manage test cases

•manage test suites

•manage manual testing

•manage bug tracking

•record / play WEB tests

•run load tests

•report test results

6.2.2 – Introducing a tool into an organization 

Page 105: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 105/106

105

•Tool selection process:

•Identify requirements•Identify constraints

•Check available tools on the market (feature evaluation)

•Evaluate short list (feature comparison):

•Demos

•Quick pilots

•Select a tool

ISTQB Foundation Exam guidelines

• 40 multiple (4) choice questions  K1: The candidates will recognize, remember

Page 106: Curs Testare fdgfd 2015666 g gh hhg

7/25/2019 Curs Testare fdgfd 2015666 g gh hhg

http://slidepdf.com/reader/full/curs-testare-fdgfd-2015666-g-gh-hhg 106/106

p ( ) q

• 1 hour exam 

• Score > 60% (25 or more) to pass

• 50% K1, 30% K2, 20% K3 

•Chapter 1 - 7 questions

•Chapter 2 – 6 questions

•Chapter 3 – 3 questions

•Chapter 4 – 12 questions

•Chapter 5 – 8 questions

•Chapter 6 – 4 questions

g ,

and recall a term or concept.

K2: The candidates can select the reasons or

explanations for statements related to the topic.

They can summarize, compare, classify and

give examples for concepts of testing.

K3: The candidates can select the correct

application of a concept or techniques and/or

apply it to a given context.

Example: (see others…) 

Which statement regarding testing is correct?

a) Testing is planning, specifying and executing a program with the aim of

finding defects

b) Testing is the process of correcting defects identified in a developed

program

c) Testing is to localize analyze and correct the direct defect cause