Upload
others
View
5
Download
1
Embed Size (px)
Citation preview
Basement Impact Assessment
at 40 Adam and Eve Mews, London W8 6UJ
for Duffy Associates
Reference: 15872/BIA/Rev1.02
January 2017
1
Control Document
Project
40 Adam and Eve Mews, London W8 6UJ
Document Type
Basement Impact Assessment
Document Reference
15872/BIA
Document Status
Final
Date
January 2017
Prepared by
D V Tedesco MEng, PhD, ChIta
First check by
Eur Ing R B Higginson BSc, PGDip, CEng, MICE, FGS.
Second check by
N J Lambert BSc (Hons), CEnv, FGS, MIEncSc
This is not a valid document for use in the design of the project unless it is titled Final in the document status
box.
Current regulations and good practice were used in the preparation of this report. The recommendations
given in this report must be reviewed by an appropriately qualified person at the time of preparation of the
scheme design to ensure that any recommendations given remain valid in light of changes in regulation and
practice, or additional information obtained regarding the site.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
2
Commission
Soils Limited was commissioned by Duffy Associates to undertake a Basement Impact
Assessment on a building at 40 Adam and Eve Mews, London W8 6UJ. The scope of the
investigation was outlined in the Soils Limited quotation reference Q18099/NJL/1, dated
17th October 2016.
This document comprises the Basement Impact Assessment and incorporates the
results, discussion and conclusions.
Standards
The site works, soil descriptions and geotechnical laboratory testing was undertaken in
accordance with the following standards:
BS EN 1997-1:2004+A1:2013 Eurocode 7. Geotechnical design
BS EN ISO 14688-1:2002+A1:2013 - Geotechnical investigation and testing -
Identification and description
BS EN ISO 14688-2:2004+A1:2013 - Geotechnical investigation and testing -
Principles for a classification
The geotechnical laboratory testing was performed by GEO Site & Testing Services Ltd
(GSTL) in accordance with the methods given in BS 1377:1990 Parts 1 to 8 and their
UKAS accredited test methods.
For the preparation of this report, the relevant BS code of practice was adopted for the
geotechnical laboratory testing technical specifications, in the absence of the relevant
Eurocode specifications (ref: ISO TS 17892).
The chemical analyses were undertaken by QTS Environmental Limited in accordance
with their UKAS and MCERTS accredited test methods or their documented in-house
testing procedures. This investigation did not comprise an environmental audit of the site
or its environs.
Trial hole is a generic term used to describe a method of direct investigation. The term
trial pit, borehole or window sample borehole implies the specific technique used to
produce a trial hole.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
3
Contents
Section 1 Introduction ....................................................................................... 1
1.1 Objective of Investigation ..................................................................................... 1
1.2 Limitations and Disclaimers .................................................................................. 1
Section 2 Site Context ....................................................................................... 2
2.1 Location ................................................................................................................ 2
2.2 Site Details ............................................................................................................ 2
2.3 Proposed Development ........................................................................................ 2
2.4 Topography ........................................................................................................... 3
2.5 Published Geological Data ................................................................................... 3
2.5.1 Taplow Gravel Formation ..................................................................................... 4
2.5.2 London Clay Formation ........................................................................................ 4
2.6 Unpublished Geology ........................................................................................... 4
2.7 Hydrogeology ........................................................................................................ 5
2.8 Hydrology .............................................................................................................. 5
2.9 Unpublished Groundwater Records ..................................................................... 6
2.10 Flood Risk ............................................................................................................. 6
2.11 Underground Infrastructure .................................................................................. 6
Section 3 Screening ............................................................................................ 7
3.1 Introduction ........................................................................................................... 7
3.2 Surface Flow and Flooding Screening Assessment ............................................. 7
3.3 Subterranean (Groundwater) Screening Assessment .......................................... 8
3.4 Stability Screening Assessment ........................................................................... 9
3.5 Summary ............................................................................................................ 11
Section 4 Intrusive Investigation .................................................................... 13
4.1 Ground Conditions .............................................................................................. 13
4.1.1 Made Ground ...................................................................................................... 14
4.1.2 Taplow Gravel Formation ................................................................................... 14
4.1.3 London Clay Formation ...................................................................................... 14
4.1.4 Roots .................................................................................................................. 14
4.1.5 Groundwater ....................................................................................................... 14
Section 5 Discussion of Geotechnical In-Situ and Laboratory Testing ...... 16
5.1 Atterberg Limit Tests .......................................................................................... 16
5.2 Particle Size Distribution Tests ........................................................................... 16
5.3 Sulphate and pH Tests ....................................................................................... 16
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
4
Section 6 Foundation Design .......................................................................... 17
6.1 Allowable Bearing Values ................................................................................... 17
6.2 Subsurface Concrete .......................................................................................... 17
Section 7 Basement Impact Assessment – Land/Slope Stability ................ 18
7.1 Introduction ......................................................................................................... 18
7.1.1 Heave Movements .............................................................................................. 18
7.1.2 Underpin Settlement ........................................................................................... 18
7.2 Ground Movement arising from Basement Excavation ...................................... 18
7.2.1 Short Term Heave .............................................................................................. 19
7.2.2 Long Term Ground Movement ........................................................................... 20
7.2.3 Settlement Due To Workmanship ....................................................................... 21
7.3 Ground Movement Due To Underpin Wall Deflection ........................................ 21
Section 8 Damage Category Assessment ...................................................... 22
8.1 Introduction ......................................................................................................... 22
8.2 Summary of Ground Movements and Evaluation of Relative Deflection ........... 22
8.3 Cumulative Effects .............................................................................................. 23
Section 9 Conclusions and Recommendations ............................................. 24
9.1 General Considerations ...................................................................................... 24
9.2 On the Expected Damage Category ................................................................... 24
List of Figures
Figure 1 – Site Location Map ........................................................................................... 27
Figure 2 – Aerial Photograph ........................................................................................... 28
Figure 3 – Boreholes Locations ....................................................................................... 29
Figure 4 – Scenarios ........................................................................................................ 30
Figure 5 – Undrained Heave ............................................................................................ 31
Figure 6 – Drained Movements ........................................................................................ 32
Figure 7 – Deflection at 18 Adam and Eve Mews ............................................................ 33
Figure 8 – Deflection at 36 Adam and Eve Mews ............................................................ 34
Figure 9 – Deflection at 38 Adam and Eve Mews ............................................................ 35
Figure 10 – Damage Category ......................................................................................... 36
Figure 11 – NFIS, Flooding from Rivers and the Sea ...................................................... 37
Figure 12 – NFIS, Flooding from Reservoirs ................................................................... 38
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
5
Figure 13 – NFIS, Flooding from Surface Water ............................................................. 39
Figure 14 – EA, Groundwater Protection Zones .............................................................. 40
Figure 15 – EA, Flooding from Rivers and the Sea ......................................................... 41
Figure 16 – EA, Flood Warning Areas ............................................................................. 42
Figure 17 – SFRA, Critical Drainage Areas ..................................................................... 43
Figure 18 – SFRA, Flood Area 1 ...................................................................................... 44
Figure 19 – SFRA, Flooding from Surface Water ............................................................ 45
Figure 20 – SFRA, Flooding from Sewers ....................................................................... 46
Figure 21 – SFRA, Flooding from Groundwater .............................................................. 47
List of Tables
Table 3.1 Surface Flow and Flooding Screening ............................................................... 7
Table 3.2 Subterranean (Groundwater) Screening ............................................................ 8
Table 3.3 Stability Screening ........................................................................................... 10
Table 3.4 Surface Flow and Flooding .............................................................................. 12
Table 3.5 Subterranean (Groundwater Flow) ................................................................. 12
Table 3.6 Ground Movement (Land stability) ................................................................... 12
Table 4.1 – Investigatory Depths of Trial-holes ............................................................... 13
Table 4.2 – Ground Conditions ........................................................................................ 14
Table 7.1 – Soil Parameters ............................................................................................ 19
Table 8.1 – Classification Of Visible Damage To Walls ................................................... 22
Table 8.2 - Expected Damage Category ......................................................................... 23
List of Appendices
Field Work
Appendix A.1 Engineers Logs
Geotechnical In-Situ and Laboratory Testing
Appendix B.1 Classification
Appendix B.2 Interpretation
Appendix B.3 Geotechnical In-Situ and Laboratory Results
References
Information Provided by the Client
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
1
Section 1 Introduction
1.1 Objective of Investigation
Soils Limited was commissioned by Duffy Associates to undertake a Basement Impact
Assessment (BIA). The objective of this investigation was to establish the impact and risk
of the proposed basement at 40 Adam and Eve Mews, London W8 6UJ on the local
environment.
The report provides details on the ground and groundwater conditions onsite and
presents calculations to determine the potential impact of the proposed development on
neighbouring properties. In addition, the report provides a qualitative risk assessment of
the potential impacts the proposed development might have on groundwater levels,
surface water flows and flooding.
It is recognised that any Basement Impact Assessment is a live document and that
further detailed assessments will be ongoing, if appropriate, as the design and
construction progresses.
1.2 Limitations and Disclaimers
Soils Limited was commissioned by Duffy Associates to undertake a Basement Impact
Assessment to supply a risk based impact assessment with regard to hydrology,
hydrogeology and land stability.
Soils Limited disclaims any responsibility to the Client and others in respect of any
matters outside the scope of the above.
The report is personal and confidential to the Client and Soils Limited accept no
responsibility of whatever nature to third parties to whom this report, or any part thereof,
is made known. Any such party relies on the report wholly at its own risk.
The Client may not assign the benefit of the report or any part to any third party without
the written consent of Soils Limited.
The ground is a product of continuing natural and artificial processes. As a result, the
ground will exhibit a variety of characteristics that vary from place to place across a site,
and also with time. Whilst a ground investigation will mitigate to a greater or lesser
degree against the resulting risk from variation, the risks cannot be eliminated.
Current regulations and good practice were used in the preparation of this report. An
appropriately qualified person must review the recommendations given in this report at
the time of preparation of the scheme to ensure that any recommendations given remain
valid in light of changes in regulation and practice, or additional information obtained
regarding the site.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
2
Section 2 Site Context
2.1 Location
The site was located at 40 Adam and Eve Mews, London W8 6UJ. The approximate O.S
Land Ranger Grid Reference was TQ 25414 79343. It falls within the boundaries of the
Royal Borough of Kensington and Chelsea.
The site location plan is given in Figure 1.
2.2 Site Details
The site comprised a terraced two storey residential building. Further adjoining
residential properties of similar geometry surrounded the building to the north, east and
south boundaries and were respectively identified as 42, 18 and 38 Adam and Eve
Mews. The main façade, to the west boundary, faced a further building, identified as 36
Adam and Eve Mews which was located at a distance of about 5.80m to the west.
Some wisteria from a very small flowerbed was found creeping up the front façade, while
a few further shrubs were similarly found to the front of the neighbouring buildings. No
other soft landscaping was observed adjacent to the building, but apparently mature
trees were noted within the backyards of the properties to the west, at a distance of more
than 15m.
The property was connected to the public sewer and a public surface drainage system
was found.
The local site topography was generally flat and level. The wider topography gently
sloped down towards the River Thames in a north to south/south-east direction.
Given the information provided by the Client, it was understood that the adjoining
property at 42 Adam and Eve Mews already had a basement. No details were provided
by the Client about the depth to the basement foundations, but it was likely they were
similar to the proposed formation depth for 40 Adam and Eve Mews. Assuming that there
is an existing basement it can be considered that the proposed development will not
provide a relevant increase in the differential foundation depths with the building at 42
Adam and Eve Mews. No further basements were identified at close distance from the
development site.
2.3 Proposed Development
The proposed redevelopment is to comprise the construction of a basement to be used
as media room, playroom and shower. Natural light was provided by means of lightwells
in structural glass located to the front and back of the house but within the footprint of the
building. In order to avoid the ingress of water from the existing sewers, the basement
drainage system related to the presence of the shower must be provided with positively
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
3
pumping devices (PPDs) and anti-flood valves will be fitted to contrast the risk of flooding. The proposed basement will be constructed within the footprint of the existing building, with no increase in the ratio between paved and unpaved areas, as reported on drawings provided by the Client and appended to the report. It must be pointed out that the area of Adam and Eve Mews was almost entirely paved and impermeable. The construction of the proposed basement, therefore, will not result in changes in the amount and quality of surface water flows discharged to the ground, public drainage system, neighbouring properties and water features. The top of the finished basement floor level was proposed at a depth of about 2.90m bgl, while the total maximum depth of the excavation was expected to be at about 3.80m bgl, as reported within the drawings and documents provided by the Client. This depth was used within the calculations. The proposed development is likely to have effects on the wisteria shrub to the front of the building (west boundary). NHBC Standards consider wisteria shrubs as potentially damaging and precautions against the effects of this shrub must be taken. Precautions must be taken independently from the nature of the soils encountered on site. In compiling this report reliance was placed on the structural drawings no. 1321.S01-C, 1618.S02-A, 1618.SO3-C, 1618.SO4-B, 1618.S05-B, 1618.S06 to 1618.S07, 1618.S08-A to 1618.S12-A, all dated December 2016, prepared by Duffy Associates, on temporary works drawings no. 1321.TW01 and 1321.TW02, dated December 2016, and on drawings no. 1321.S01 and 1321.S02, dated 2013, prepared by Duffy Associates, and on the architectural drawings no. 1239 PL010 and 1239 P011, dated October 2016 and prepared by Shape Architecture. All the drawings were provided by the Client. Any change or deviation from the scheme outlined in the drawing could invalidate the recommendations presented within this report. Soils Limited must be notified about any such changes. The proposed development layout as provided by the client are included in Appendix D. 2.4 Topography The local site topography was generally flat and level. The wider topography gently sloped down towards the River Thames on a north to south/south-east direction. No relevant slopes were noted in the area of the proposed development and no reprofiling of the site was required. 2.5 Published Geological Data The 1:50,000 BGS map showed the site to be located on bedrock of the London Clay Formation with overlying superficial geology represented by the Taplow Gravel Formation.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
4
2.5.1 Taplow Gravel Formation
The rivers of the south-east of England, including the River Thames and its
tributaries, have been subject to at least three changes of level since Pleistocene
times. One result has been the formation of a complex series of River Terrace
Gravels. These terraces represent ancient floodplain deposits that became isolated
as the river cut downwards to lower levels. The Taplow Gravel Formation is found
at an elevation that approximates to the present floodplain gravel
The composition of the River Terrace Gravel varies greatly, depending on the
source material available in the river’s catchment. Deposits generally consist of
sands and gravels of roughly bedded flint or chert gravels commonly in a matrix of
silts and clays.
2.5.2 London Clay Formation
The London Clay Formation comprises stiff grey fissured clay, weathering to brown
near surface. Concretions of argillaceous limestone in nodular form (Claystones)
occur throughout the formation. Crystals of gypsum (Selenite) are often found
within the weathered part of the London Clay, and precautions against sulphate
attack to concrete are sometimes required.
The upper boundary member of the London Clay Formation is known as the
Claygate Member and marks the transition between the deep water, predominantly
clay environment and succeeding shallow-water, sand environment of the Bagshot
Formation.
The lower boundary is generally marked by a thin bed of well-rounded flint gravel
and/or a glauconitic horizon. The formation overlies the Harwich Formation or
where the Harwich Formation is absent the Lambeth Group.
In the north London area, the upper part of the London Clay has been disturbed by
periglacial processes and may contain pockets of sand and gravel.
2.6 Unpublished Geology
Published information was taken from boreholes available in a radius of about 300m
from the site.
Soils expressly described as Made Ground were identified within some of the boreholes,
generally observed from ground level to depths ranging from 1.50m to 2.50m bgl. The
Made Ground was variable in lithology and composition, typically comprising drift, clay to
gravel with brick, ash, concrete, rubble, clinker and coal fragments.
Soils of the Taplow Gravel Formation were observed within the boreholes to depths
ranging between 1.50m and 4.50m bgl and typically comprised sand and gravel in
variable proportions with clay and silt.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
5
Soils from London Clay Formation were observed from below the Made Ground and/or
Taplow Gravel Formation to a depth of about 60.00m bgl. A weathered layer was usually
found at the top of the stratum, comprising firm becoming stiff to very stiff and fissured
brown to brown orange to brown grey mottled clay with occasional selenite crystals and
orange brown stained fissures. The soil of the unweathered London Clay comprised stiff
to very stiff and closely fissured dark grey to dark brown silty clay with occasional light
brown to brown fine sand and silt partings and rare fine gypsum.
2.7 Hydrogeology
The Environment Agency has produced an aquifer designation system consistent with
the requirements of the Water Framework Directive. The designations have been set for
superficial and bedrock geology and are based on the importance of aquifers for potable
water supply and their role in supporting water bodies and wetland ecosystems.
The London groundwater model was generally split into three aquifers, the Upper,
Intermediate and Lower Aquifer. The Upper Aquifer was confined to the River Terrace
Deposits, overlying the London Clay Formation, which acts as an aquiclude. The
Intermediate Aquifer was generally associated with granular layers within the Lambeth
Group. The Lower Aquifer was principally associated with the Chalk, but can include the
Thanet Sand Formation.
Information presented by the Environment Agency classifies the Taplow Gravel
Formation as a Secondary ‘A’ aquifer and the London Clay Formation bedrock as
unproductive strata.
The Taplow Gravel Formation comprised permeable layers capable of supporting water
supplies at a local rather than strategic scale, and in some cases forming an important
source of base flow to rivers.
Any water infiltrating the London Clay Formation will generally tend to flow vertically
downwards at a very slow rate. Due to the predominantly cohesive nature of the soils,
the groundwater flow rate is anticipated to be very slow. Published permeability data for
the London Clay Formation indicates the horizontal permeability to generally range
between 10-10 m/s and 10-8 m/s (~5 mm/year to ~5 mm/day), with an even lower vertical
permeability.
2.8 Hydrology
The nearest surface water feature was the Round Pond in Hyde Park, recorded at
~950m to the north-east of the site.
The site was recorded at an elevation of approximately 10m AOD, and the Round Pond
was at approximately 24 m AOD.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
6
According the Lost Rivers of London (Barton, 1992) the site is not affected by any
historic rivers. The nearest historic river to the site is Counter’s Creek, at more than
500m to the west, flowing in a south-easterly direction.
2.9 Unpublished Groundwater Records
Groundwater was generally not reported in the unpublished data. Where observed, it
was found at depths ranging from 55.00m to 60.00m bgl. The regional water table in this
location is about 20m to 30m below ordnance datum (Environment Agency, 2016). It
must be pointed out that the groundwater levels from unpublished geology may describe
conditions that differ from the results of the site investigation.
2.10 Flood Risk
The National Flood Information Service shows the site to be at no risk for flooding from
rivers and the sea and from reservoirs. A high risk of flooding from surface water was
identified.
According to the Environmental Agency, the site did not fall within a Groundwater Source
Protection Zone. The site does not lie within a flood risk zone from rivers or the sea or in
a Flood Warning Area/Flood Alert Area.
The Strategic Flood Risk Assessment (SFRA) for the Royal Borough of Kensington and
Chelsea excluded the site to be located within any of the Critical Drainage Areas (CDAs),
but it falls within the Environmental Agency Flood Risk Zone 1. The SFRA identified the
site to be at moderate risk from surface water and groundwater flooding. A risk of
flooding from sewers was also noted.
The maps related to the mentioned flood risk assessment are presented in Figure 11 to
Figure 21.
2.11 Underground Infrastructure
Underground infrastructures were observed at about 200m to the north-east of the site
and were represented by the High Street Kensington Station.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
7
Section 3 Screening
3.1 Introduction
Soils Limited has adopted a screening process to meet the requirements of the Royal
Borough of Kensington and Chelsea (RBKC) Basement Planning Policy and Final
Basements Supplementary Planning Document (SPD) to identify potential risks to the
ground, groundwater/surface water, land stability, adjacent properties and infrastructure.
The assessment is undertaken in the form of tabulated questions, setting out relevant
considerations for conditions in the borough. Where simple answers may be provided
without further analysis, these are provided.
3.2 Surface Flow and Flooding Screening Assessment
The response to the Surface Flow and Flood Screening Assessment is given in Table
3.1.
Table 3.1 Surface Flow and Flooding Screening
Question Response Action Required
1. Is the site within a Critical Drainage
Area?
No
RBKC SFRA shows the site to be located off the
CDAs
None
2. As part of the proposed site drainage,
will surface water flows (e.g. volume of
rainfall and peak run-off) be materially
changed from the existing route?
No
The area surrounding the site was known to be
predominantly paved and impermeable. The
proposed development will not change the ratio
between paved and unpaved areas and/or the
existing slopes. As a consequence, surface water
flows will not be materially changed from the
existing routes.
None
3. Will the proposed basement
development result in a change in the
proportion of hard surfaced / paved
areas?
No
The proposed basement will be constructed within
the footprint of the existing building and no
changes will be applied to the ratio between paved
and unpaved areas.
None
4. Will the proposed basement
development result in changes to the
profile of the inflows (instantaneous and
long term) of surface water being
received by adjacent properties or
downstream watercourses?
No
No changes in the infiltration rates or infiltration
profiles will take place as the area is fully paved and
impermeable and the proposed basement will be
constructed within the footprint of the existing
building..
None
5. Will the proposed basement result in
changes to the quality of surface water
being received by adjacent properties or
downstream watercourses?
No
No changes are expected because of the proposed
development as it will take place within the
None
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
8
footprint of the existing building and does not
change the status quo of water quality.
6. Is the site in an area known to be at
risk from surface water flooding or is it
at risk from flooding because the
proposed basement is below the static
water level of a nearby surface water
feature?
Yes
The site falls within an area at risk of surface water
flooding.
Dewatering of the
basement to be
provided.
3.3 Subterranean (Groundwater) Screening Assessment
The response to the Subterranean (Groundwater) Screening Assessment is given in
Table 3.2.
Table 3.2 Subterranean (Groundwater) Screening
Question Response Action Required
1a. Is the site located
directly above an
aquifer?
Yes
The Taplow Gravel Formation
was classified as a Secondary
“A” Aquifer. The London Clay
Formation was classified as an
Unproductive Stratum.
Dewatering of the basement premises may be needed.
Groundwater flow should not be adversely affected, as
flow around and below the basement will not be
interrupted, but an assessment of potential cumulative
effects on groundwater levels must be carried out due
to the presence of an existing adjoining basement.
1b. Will the proposed
basement extend
beneath the water table
surface?
No
No groundwater was
encountered to the depth of
3.80m bgl at the time of the site
investigation. Historical data
report groundwater depths of
10.00m to 20.00m bgl
None
2. Is the site in an area of
groundwater flooding
risk?
Yes Premises to be sealed up to prevent groundwater
ingress. Sump and pumps to be provided with
appropriate design and redundancy, considering the
risk for potential electric black-outs during flooding
events. Definition of a maintenance programme
recommended.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
9
Question Response Action Required
3. Is the site within 100
m of a watercourse, well
(used/ disused) or
potential spring line?
No
The closest water feature was
the Round Pond at Hyde Park,
located at about 950m to the
north-east of the site. The
Counter’s Creek, as reported by
Barton’s Lost Rivers of London,
was identified at more than
500m to the west. The River
Thames was located at about
2400m to the south/south-east.
None
4. Will the proposed
basement development
result in a change in the
proportion of hard
surfaced / paved areas?
No
The proposed basement will be
constructed within the footprint
of the existing building. The area
surrounding the site was
identified as a predominantly
paved, impermeable area and no
changes will be caused by the
proposed development.
None
5. As part of the site
drainage, will more
surface water (e.g.
rainfall and run-off) than
at present be discharged
to the ground (e.g. via
soakaways and/or
SUDS)?
No
Soils Limited was not informed
about the proposed site
drainage, but no changes are
expected as the area
surrounding the site was fully
paved and impermeable.
Drainage strategy not in the brief of the present
report.
6. Is the lowest point of
the proposed excavation
(allowing for any
drainage and foundation
space under the
basement floor) close to
or lower than, the mean
water level in any local
pond or spring line?
No
The closest water feature with
an elevation lower than the one
existing on site was the River
Thames, located at more than
700m to the south/south-east
None
3.4 Stability Screening Assessment
The response to the Stability Screening Assessment is given in Table 3.3.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
10
Table 3.3 Stability Screening
Question Response Action Required
1. Does the existing site include slopes,
natural or manmade, greater than about
1 in 8?
No
No relevant slopes were noted.
None
2. Will the proposed re-profiling of
landscaping at the site change slopes at
the property boundary to more than 1
in 8?
No
No reprofiling was part of the
proposed development.
None
3. Does the development neighbour
land, including railway cuttings and the
like, with a slope greater than 1 in 8?
No
No slopes were found in the
neighbouring land.
None
4. Is the site within a wider hillside
setting in which the general slope is
greater than 1 in 8?
No
No relevant slopes in the
surrounding settings.
None
5. Is the London Clay the shallowest
strata at the site?
No
Superficial layers of Taplow Gravel
Formation were both expected and
observed
None
6. Will any trees be felled as part of the
proposed development and / or are any
works proposed within any tree
protection zones where trees are to be
retained?
Yes
A wisteria shrub to the front of the
site will be affected by the proposed
construction.
NHBC Standards classify wisteria
shrubs as potentially damaging.
Precautions must be taken even
if the development should take
place within the granular soils of
the Taplow Formation due to
the potential presence of clayey
lenses and the usual low
thickness of the Taplow Gravel
Formation, directly overlying the
overconsolidated soils of the
London Clay Formation and, in
particular, its weathered upper
layer.
7. Is there a history of seasonal shrink-
swell subsidence in the local area and /
or evidence of such effects at the site?
No
No cracks were noted on the
existing walls and the predominantly
granular nature of the soils of the
Taplow Gravel Formation should
exclude shrink/swell phenomena.
None
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
11
Question Response Action Required
8. Is the site within 100 m of a
watercourse or potential spring line?
No
The closest water feature was the
Round Pond at Hyde Park, located
at about 950m to the north-east of
the site. The Counter’s Creek, as
reported by Barton’s Lost Rivers of
London, was identified at more than
500m to the west. The River
Thames was located at about 2400m
to the south/south-east.
None
9. Is the site within an area of previously
worked ground?
No
The site investigation identified
Made Ground, but no infilled pits
and quarries were noted
None
Investigation regarding the
presence of soil gas not in the
brief of the present report.
10. Is the site within 5m of highway or
pedestrian right of way?
Yes
The proposed development will take
place immediately along Adam and
Eve Mews.
The proposed basement is not
to be extended below Adam and
Eve Mews and therefore it is
suggested that the impact on this
access road is likely to be
minimal. However, the
excavations must be carried out
in order to ensure that traffic
and construction activity does
not harm pedestrian, cycle,
vehicular and road safety.
11. Will the proposed basement
significantly increase the differential
depth of foundations relative to
neighbouring properties?
Yes A basement already exists under
the property at 42 Adam and
Eve Mews, so no Basement
Impact Assessment is required
with regards to this property.
Assessments must be carried out
for the other surrounding
properties, with particular
regards to the propertied at 18,
36and 38 Adam and Eve Mews
12. Is the site over (or within the
exclusion zone of) any tunnels, e.g.
railway lines?
No
No tunnels expected in the area of
interest.
None
3.5 Summary
Based on the screening exercise, further stages of the basement impact assessment are
required. A summary of the basement impact assessment requirements has been
provided in Table 3.4, Table 3.5 and Table 3.6.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
12
Table 3.4 Surface Flow and Flooding
Item Description
6 Dewatering of the basement to be provided.
Table 3.5 Subterranean (Groundwater Flow)
Item Description
1a Dewatering of the basement premises may be needed. Groundwater flow should not
be adversely affected, as flow around and below the basement will not be interrupted,
but an assessment of potential cumulative effects on groundwater levels must be
carried out due to the presence of an existing adjoining basement.
2 Premises to be sealed up to prevent groundwater ingress. Sump and pumps to be
provided with appropriate design and redundancy, considering the risk for potential
electric black-outs during flooding events. Definition of a maintenance programme
recommended.
Table 3.6 Ground Movement (Land stability)
Item Description
6 NHBC Standards classify wisteria shrubs as potentially damaging. Precautions must be
taken even if the development should take place within the granular soils of the
Taplow Formation due to the potential presence of clayey lenses and the usual low
thickness of the Taplow Gravel Formation, directly overlying the overconsolidated
soils of the London Clay Formation and, in particular, its weathered upper layer.
10 The proposed basement is not to be extended below Adam and Eve Mews and
therefore it is suggested that the impact on this access road is likely to be minimal.
However, the excavations must be carried out in order to ensure that traffic and
construction activity does not harm pedestrian, cycle, vehicular and road safety.
11 A basement already exists under the property at 42 Adam and Eve Mews, so no
Basement Impact Assessment is required with regards to this property. Assessments
must be carried out for the other surrounding properties, with particular regards to
the propertied at 18, 36and 38 Adam and Eve Mews
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
13
Section 4 Intrusive Investigation
4.1 Ground Conditions
Two hand held windowless sampler boreholes (WS1 and WS2) were drilled on site, at
locations selected by Soils Limited and agreed with the Client, where access could be
gained and no live services were identified, within the footprint of the proposed
redevelopment.
On 26th October and 14th November 2016 two starter pits were hand dug through the
existing ground floor slab: the intrusive investigation was stopped because asbestos
containing materials were encountered. On both the occasions, the Client was informed
and remedial actions were required in order to carry on with the proposed investigation.
The two proposed boreholes were finally drilled on 12th December 2016. The depth
investigated ranged from 2.00m (WS2) to 2.40m bgl (WS1). It was impossible to reach
greater depths because of the presence of obstructions and of the relative density of the
soils encountered.
Dynamic probing was to be undertaken prior and adjacent to the respective boreholes,
but the available headroom inside the building made it impossible to undertake the tests.
The Client was informed of the risk at the quotation stage.
One standpipe monitoring well was installed within borehole WS1 to a depth of 2.50m
bgl (below ground level) to allow long-term groundwater levels monitoring. Groundwater
readings were then carried out on one occasion, as agreed with the Client.
One trial pits for foundation exposure test was carried out by the Client and the results
provided in Appendix D.
The borehole locations are outlined in Figure 3.
Table 4.1 outlines the depths of each trial-hole.
Table 4.1 – Investigatory Depths of Trial-holes
Trial-hole
(WS)
Final Depth
(m bgl)
Trial-hole
(WS)
Final Depth
(m bgl)
WS1 2.40 WS2 2.00
Ground conditions encountered are presented below; detailed information including logs
are presented in Appendix A:
Made Ground (MG)
Taplow Gravel Formation (TPGR)
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
14
Table 4.2 summarises the ground conditions encountered.
Table 4.2 – Ground Conditions
Stratum Epoch Depth Range (m bgl) Thickness (m) Description
Top Bottom
MG Recent GL 0.80 - 1.00 0.90 Fine to coarse brick and concrete with
ACM (removed by specialised personnel).
TPGR Palaeogene 0.80 – 1.00 2.001 – 2.401 Not proven2 Stiff orange brown slightly gravelly sandy
CLAY to clayey gravelly SAND.
Note: 1 Final depth of trial hole. 2 Base of strata not encountered.
4.1.1 Made Ground
Made Ground was encountered in both of the two trial holes from ground level to a
depth of 1.00 m bgl and comprised fine to coarse brick and concrete with asbestos
containing materials. The materials were removed by a specialist contractor.
4.1.2 Taplow Gravel Formation
Soils described as Taplow Gravel Formation were found in both the two trial holes
directly beneath the Made Ground to the full depths of the investigation and
comprised stiff orange brown slightly gravelly sandy CLAY to clayey gravelly
SAND. Sand was fine to coarse. Gravel within the clayey beds was frequent fine to
medium rounded to sub-rounded and fine to medium angular to sub-angular within
the sandy beds.
4.1.3 London Clay Formation
The soils of the London Clay Formation were not encountered in the test holes.
4.1.4 Roots
No roots were observed at the time of the site investigation. The depth to roots
and/or of desiccation may vary from that found during the investigation. The client
is responsible for establishing the depth to roots and/or of desiccation on a plot by
plot basis prior to the construction of foundations. Supplied site surveys may not
include substantial shrubs or bushes and is also unlikely to have data or any trees,
bushes or shrubs removed prior to or following the site survey.
Where trees are mentioned in the text this means existing trees, substantial bushes
or shrubs, recently removed trees (approximately 20 years to full recovery on
cohesive soils) and those planned as part of the site landscaping).
4.1.5 Groundwater
Groundwater was not encountered at the time of the intrusive investigation.
Equilibrium conditions may only be conclusively established if a series of
observations are made via groundwater monitoring wells. One groundwater
monitoring well was installed into borehole WS1 to the depth of 2.50 m bgl.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
15
One visit was done on site for the monitoring of groundwater on 13th January 2017,
when groundwater levels should be rising towards their annual maximum (i.e.
highest) elevation which typically occurs around March, but the monitoring well was
found dry to its full depth of 2.50m bgl.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
16
Section 5 Discussion of Geotechnical In-Situ and Laboratory Testing
5.1 Atterberg Limit Tests
Atterberg Limit tests were performed on three sample from the Taplow Gravel Formation.
The results were classified in accordance with BRE Digest 240 and NHBC Standards
Chapter 4.2.
The soils of the Taplow Gravel Formation were classified as non-plastic to medium
volume change potential in accordance with both BRE Digest 240 and NHBC Standards
Chapter 4.2.
A full interpretation of the Atterberg Limit tests is outlined in Table B.2.1, Appendix B.2
and the laboratory report in Appendix B.3.
5.2 Particle Size Distribution Tests
Particle Size Distribution (PSD) tests were performed on five samples from the Taplow
Gravel Formation.
PSD classified three samples from the granular beds of the Taplow Gravel Formation as
having no volume change potential in accordance with both BRE Digest 240 and NHBC
Standards Chapter 4.2. The results from grading analysis confirmed that two out of the
five samples tested had a volume change potential in accordance with both BRE Digest
240 and NHBC Standards Chapter 4.2. Note that a cohesive soil is only classified as
having a volume change potential if it is also plastic and an Atterberg Limit test can be
conducted on the strata.
A full interpretation of the PSD tests are outlined in Table B.2.2, Appendix B.2 and the
laboratory report in Appendix B.3.
5.3 Sulphate and pH Tests
One sample was taken from the Made Ground (WS2:0.50m bgl) for water soluble
sulphate (2:1) and pH testing in accordance with Building Research Establishment
Special Digest 1, 2005, ‘Concrete in Aggressive Ground’.
The tests recorded water soluble sulphate at 776mg/l with a pH value of 8.8.
The significance of the sulphate and pH Test results are discussed in Section 6.2 and
the laboratory report in Appendix B.3.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
17
Section 6 Foundation Design
6.1 Allowable Bearing Values
The available headroom within the premises made it impossible to investigate the soils at
and below the expected basement formation level.
The Taplow Gravel Formation usually presents a thickness of a few metres, Therefore it
was expected that the proposed basement foundations will be placed within or
immediately above the soils of the weathered layer of the London Clay Formation.
Considering the data available from the literature, an undrained shear strength (cu) of
about 50kPa has been published for the soils of the London Clay Formation at the top of
the stratum. An angle of shearing resistance (∅’) of about 22º can be considered under
drained conditions.
Assuming a strip foundation, 5.00m x 0.75m in plan, the recommended net allowable
bearing pressure for the London Clay Formation at basement formation level is 110kPa.
Given the removal of about 3.80m of soils above the basement formation level, a gross
bearing pressure of 185kPa can be considered. The evaluation of the expected
settlements was reported in detail in Section 7.
The above bearing pressure values were conservatively assumed due to the
impossibility to carry out the investigation using a larger rig. If greater values for the
bearing capacity are needed, it is strongly recommended to carry out further testing on
the roadside, where more powerful rigs can be conveniently located. However, it is
usually recommended that a maximum bearing capacity of 150kPa should not be
exceeded for the soils of the London Clay Formation at basement formation level.
6.2 Subsurface Concrete
Sulphate concentration measured in 2:1 water/soil extracts fell into Class DS-2 of the
BRE Special Digest 1 2005, ‘Concrete in Aggressive Ground’. Table C2 of the Digest
indicated ACEC (Aggressive Chemical Environment for Concrete) site classifications of
AC-1s. The pH of the soil tested was 8.8. The classification given was determined using
the mobile groundwater case, as groundwater was encountered. The laboratory results
are presented in Appendix B.3.
Concrete to be placed in contact with soil or groundwater must be designed in
accordance with the recommendations of Building Research Establishment Special
Digest 1 2005, ‘Concrete in Aggressive Ground’ taking into account any possible
exposure of potentially pyrite bearing natural ground and the pH of the soils.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
18
Section 7 Basement Impact Assessment – Land/Slope Stability
7.1 Introduction
This section provides calculations to determine ground movements that may result from
the construction of the additional basement level and to assess how these may affect
adjacent structures.
Movements are likely to occur through the following mechanisms:
7.1.1 Heave Movements
The excavation will unload the Taplow Gravel Formation and the London Clay
Formation and will cause a degree of heave during excavation and possibly post
construction, and/or settlement after construction.
7.1.2 Underpin Settlement
Construction of underpins can lead to settlement. With good workmanship, this
would be expected to be limited to 5mm of settlement per underpin ‘lift’. Settlement
may potentially also occur where foundation loads are transferred to deeper,
previously unload, soils.
Underpinning settlement only affects shared foundations, such as foundations to
party walls. This was applied to the Ground Movements Assessment and Damage
Category Assessment for the properties at 18 and 38 Adam and Eve Mews.
Where foundations are not shared, or the properties linked, workmanship will not
affect the adjoining structure. This was applied to the GMA and DCA for the
property at 36 Adam and Eve Mews.
7.2 Ground Movement arising from Basement Excavation
The soils at formation level will be subject to stress relief during excavation, as up to
about 3.80m of overburden is to be removed under the house. This is likely to give rise to
a degree of heave over the short term and potential heave or settlement over the longer
term as structural loads are reapplied.
A ground movement assessment has been undertaken using OASYS Limited PDISP
(Pressure induced DISPlacement analysis) analysis software. PDISP assumes that the
ground behaves as an elastic material under loading, with movements calculated based
on the applied loads and the soil stiffness (Eu and E’) for each stratum input by the user.
PDISP assumes perfectly flexible loaded areas and as such tends to overestimate
movements in the centre of loaded areas and underestimate movements around the
perimeters. Notwithstanding this, the structure has not been modelled as an evenly
loaded flexible raft and loads from underpins around the perimeter have been accounted
for and modelled in the analysis. The calculated movements are therefore, not
considered to be underestimated.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
19
The proposed development gives rise to a net unloading of the underlying strata both
during construction and over the long term. The excavation will unload the soils under
the house by approximately 75kPa, assuming that the ground conditions encountered
during the site investigation are laterally continuous across the extent of the proposed
new basement. These values assume a typical bulk unit weight of 19kN/m3 for the soils
of the Made Ground and a unit weight of 20kN/m3 for the soils of the Taplow Gravel
Formation. The combined effects of both the immediate undrained unloading and the
long-term drained recovery of pore pressures have been analysed.
Considering the results of the site investigation and the absence of information from
dynamic probing, an estimation of the mechanical characteristics of the soils
encountered was carried out using data available from the literature. The stiffness
parameters reported in Table 7.1 were adopted for the soils involved in the analyses.
Table 7.1 – Soil Parameters
Stratum Top of Stratum
(m bgl)
Young’s Modulus (MPa) Poisson’s Ratio
Drained Undrained Drained Undrained
Made Ground1 0.00 5.00 5.00 0.25 0.50
Taplow Gravel Formation1 1.00 12.00 12.00 0.30 -
London Clay Formation2 3.80 40 + 4z 50 + 5z 0.25 0.50
Note: 1 Based upon CIRIA C580, Chapter 5. 2 From CIRIA SP200.
Two critical sections were identified in the neighbouring adjoining properties at 18 and 38
Adam and Eve Mews and one in the detached property at 36 Adam and Eve Mews.
No Ground Movements Assessment and Damage Category Assessment were
developed with regards to the property at 42 Adam and Eve Mews, as the proposed
development will not increase the differential depth between adjacent foundations due to
the presence of an already existing basement.
The critical sections at 18 and 38 Adam and Eve Mews were respectively identified at a
distance of about 8.30m and 8.90m from the outer face of the underpinning and, as
already stated, no basement was present under the adjoining buildings.
The building at 36 Adam and Eve Mews, as already discussed, was detached from the
proposed development and located at the distance of 5.80m from the outer face of the
underpinning.
The mentioned scenarios were reported in Figure 4.
7.2.1 Short Term Heave
Calculated short term heave considered the increase of stiffness after the
unloading of clayey soils and the evaluation of heave. The huge amount of data
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
20
available from the literature allowed the adoption of appropriate values for the
Youngs Modulus under both drained and undrained conditions. In the absence of
similar conditions, Simons and Menzies (2000) suggested to divide the calculated
heave by a factor equal to three in order to take into account the increase in
stiffness along a path of unloading and reloading. Poisson’s Ratio was considered
equal to 0.50 for cohesive soils under undrained conditions.
Maximum short term heave is predicted to be of the order of -4.10mm, occurring
towards the centre of the footprint of the building (negative values indicate an
upwards movement). The movement decreases towards the underpins located
along the boundary lengths of the basement. Heave was noted to occur within
these areas up to a maximum of -2.00mm due to the net increase of surcharged
load. The movement decreases with negligible movement at 6m from the boundary
underpins and towards the front of the property. A contour plot showing the
variation of short term movements across the entire basement footprint is
presented in Figure 5.
Minimum short term heave under the footprint of the detached building at 36 Adam
and Eve Mews predicted to be of the order of -0.10mm, occurring under the wall
facing the proposed development.
7.2.2 Long Term Ground Movement
Long term movements depend on the almost contemporary development of the
increase of heave (negative settlements) in the long term due to the reduction in
stiffness of the soils and the development of (positive) settlements due to the
construction of the basement and the application of the loads from the upper
structure to greater depths. Those movements develop contemporary and cannot
be distinguished, but an evaluation of the long term heave, as developing alone,
was also reported for completeness on the graphs in Figure 7, Figure 8 and Figure
9. It must be pointed out that long term heave and other long term movements
develop contemporary and on the same time scale because of the methods
adopted for the excavation and construction sequences used in the construction of
basements under existing buildings.
In the case of the building at 40 Adam and Eve Mews, the maximum long term
ground movements, therefore, are obtained by adding the long term heave
(estimated to a maximum of -7.60mm) to the settlements induced by the application
of the construction loads and are of the order of 8.10mm, occurring under the front
underpinning foundation. The movement decreases to an average of 5.00mm at
the outer faces of the underpinning movement at 5.0m from the excavation. A
contour plot showing the variation of long term movements across the entire
basement footprint is presented in Figure 6.
Maximum long term ground movements under the footprint of the building at 36
Adam and Eve Mews were calculated to be less than 0.50mm under the wall facing
the proposed development.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
21
7.2.3 Settlement Due To Workmanship
The heave/settlement assessment undertaken within PDISP assumes perfect
workmanship in the underpin construction and does not allow for settlement of the
dry pack between existing footings and the new concrete. With good construction
practice, these would be expected to not exceed 5.00mm (assuming 5.00mm per
underpin lift). This value will be applied to the overall ground movement and
corresponding impact assessment to give a worst case damage category for the
adjacent party wall properties.
Underpinning settlement only affects shared foundations, such as foundations to
party walls. This was applied to the Ground Movements Assessment and Damage
Category Assessment for the properties at 18 and 38 Adam and Eve Mews.
Where foundations are not shared, or the properties linked, workmanship will not
affect the adjoining structure. This was applied to the GMA and DCA for the
property at 36 Adam and Eve Mews.
7.3 Ground Movement Due To Underpin Wall Deflection
The retained height of the underpin wall is to be a maximum of some 3.80m beneath the
ground floor. Assuming 300mm thick concrete underpins for Wall A (east boundary,
scenario at 18 Adam and Eve Mews) and Wall B (south boundary, scenario at 38 Adam
and Eve Mews), the presence of permanent propping at the toe and at the top of the
walls and taking no account of a liner wall for long-term movements, deflections of the
underpins would be expected to be less than 2mm. Calculations were carried out using
the commercial software Wallap for the properties adjoining 40 Adam and Eve Mews. It
is assumed that underpins are propped in the temporary condition as described within
the temporary works drawings in order to prevent lateral movement.
A different configuration was assumed for Wall C (west boundary, scenario at 36 Adam
and Eve Mews), where no permanent propping was considered at the top of the wall due
to the presence of lightwells in structural glass. Wall thickness was therefore increased to
350mm. The property at 36 Adam and Eve Mews was located at a distance of 5.80m
from the underpinning.
Limited information was available from the literature with regards to the propagation of
movements at a distance from the excavation and the wall stem, especially with regards
to horizontal movements. An estimation was then done considering the information
provided by CIRIA C580 in Section 2.5.2, Figure 2.8, and the wall assumed as a
cantilevered secant pile wall. Horizontal movements were estimated to be zero at a
distance of 1.5 times the wall depth, corresponding to 5.70m. As a consequence,
horizontal movements at the distance of 5.80m were considered as equal to zero.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
22
Section 8 Damage Category Assessment
8.1 Introduction
These ground movements were considered for assessing the expected potential damage
category that the construction of a new basement was expected to induce to the
neighbouring properties. The assessment was carried out considering the method
described in CIRIA Special Publication 200 (Burland et al., 2001) and CIRIA C580 (Gaba
et al., 2003), based upon the method proposed by Burland et al. (2001) and taking into
account the works by Burland and Wroth (1974) and Boscardin and Cording (1989).
The general categories of damage entity were summarised in Table 8.1.
Table 8.1 – Classification Of Visible Damage To Walls
Category Description
0 (Negligible) Negligible – hairline cracks
1 (Very slight) Fine cracks that can easily be treated during normal decoration (crack width <1mm)
2 (Slight) Cracks easily filled, redecoration probably required. Some repointing may be required
externally (crack width <5mm)
3 (Moderate) The cracks require some opening up and can be patched by a mason. Recurrent cracks can
be masked by suitable linings. Repointing of external brickwork and possibly a small
amount of brickwork to be replaced (crack width 5 to 15mm or a number of cracks >
3mm).
4 (Severe) Extensive repair work involving breaking-out and replacing sections of walls, especially over
doors and windows (crack width 15mm to 25mm but also depends on number of cracks).
5 (Very severe) This requires a major repair involving partial or complete re-building (crack width usually
>25mm but depends on number of cracks).
The London Boroughs usually indicate that the design and construction methodology
should aim to restrict the damage category to neighbouring properties to not higher than
Category 2 damage (slight damage), as it will only imply the risk of aesthetic damages to
the buildings.
However, the Councils considers that neighbouring residential properties are particularly
sensitive to damage, where relatively minor internal damage to a person’s home can
incur cost and considerable inconvenience to repair and redecorate. The Councils
therefore will expect that a damage not higher than Category 1 (very slight) is achieved.
8.2 Summary of Ground Movements and Evaluation of Relative Deflection
The analysis of the ground movements reported in Section 7 allowed to estimate the
relative vertical and horizontal deflections for all the considered buildings and scenarios,
corresponding to an expected Damage Category of 1 (Very slight) according to the
classification by Burland (2001). The results were summarised in Table 8.2.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
23
Table 8.2 - Expected Damage Category
Critical Section Horizontal
Movement
(mm)
Vertical
Deflection
(mm)
Horizontal
Strain
h (%)
Deflection
Ratio
/L (%)
Damage
Category
18 Adam and Eve Mews 2.00 5.70 0.0241 0.0687 1 (Very slight)
36 Adam and Eve Mews 0.00 2.90 0.0000 0.0500 1 (Very slight)
38 Adam and Eve Mews 2.00 3.50 0.0225 0.0393 1 (Very slight)
The results for the sections at 18 and 38 Adam and Eve Mews, as already explained,
consider the effects of good workmanship to increase the potential damage. No
workmanship error was considered for the section at 36 Adam and Eve Mews, as that
building does not share foundations with the proposed development. It must be pointed
out that generally the evaluation of vertical and horizontal movements is over-
conservative and this induces the evaluation of expected damage categories indicating a
higher risk than the real one.
8.3 Cumulative Effects
The information provided by the Client identified the presence of a basement under the
building at 42 Adam and Eve Mews. Therefore, quantitative calculations were not carried
out as the construction of the proposed basement will not increase the differential depths
between the foundations of the two buildings.
The presence of the basement, however, cannot be excluded for the development of
qualitative evaluations regarding to the construction of a new basement adjoining an
existing one, and the potential effects on the depth of groundwater table.
The proposed development was to take place within the soils of the Taplow gravel
Formation and it did not exclude the possibility for the groundwater to flow around and
below the basement.
The construction of a further basement, therefore, will increase the length of the flow
path and the potential for the increase of the upstream groundwater level exists. This
effect can increase the potential ingress of water within the basement, increasing the risk
already considered in Section 2.10. The design of the sump and pumping system,
therefore, must be carried out considering a higher total volume and flow than the one
obtainable for the construction of an isolated basement. Also, the choice of pump type
must be carried out considering the risk of a long lasting use and the potential for electric
black-outs during flooding events. A malfunctioning of the pumping device must be also
taken into account. In order to reduce the risk of malfunctioning, an adequate
maintenance programme must be prepared and it is strongly recommended to consider
an appropriate system redundancy.
Soils Limited 40 Adam and Eve Mews, London – Basement Impact Assessment
24
Section 9 Conclusions and Recommendations
9.1 General Considerations
The findings of this report are informed by site investigation data and information
regarding construction methods, sequence, loading and allowable bearing capacity
provided by the client. The analysis is undertaken on the assumption of high quality
workmanship.
The analysis is based on site investigation data and published data, particularly within
the Taplow Gravel Formation, the London Clay Formation and regarding to the
groundwater depths. Soils Limited must be notified if different conditions are observed
during the construction phase.
The site investigation could not reach the proposed formation level, which is likely to be
still within the Taplow Gravel Formation or, as conservatively assumed within the report,
at the top of the London Clay Formation.
Due to the shallow investigated depth, because of the obstacles encountered and the
density of the soils of the Taplow Gravel Formation, no groundwater was encountered.
For the development of the calculations, however, it was conservatively assumed to be
at the depth of 2.50m bgl as a moderately conservative scenario and the depth of 1.00m
bgl within the worst-case scenario.
The basement design would take into account the potential of water ingress over the
lifetime of the structure and would include appropriate water proofing design as also the
presence of appropriate water sumps. The basement must also be protected against the
risk of flooding from sewers by applying positive pumping devices.
The proposed development will consider no changes in the proportion between paved
and unpaved areas, as the area of interest was predominantly impermeable. The net
effect on surface water flow or flooding can be, as a consequence, considered as
negligible.
If perched water will be observed at the time of the excavation, precautions must be
taken to allow for a safe and comfortable development. The application of pumps for
allowing the dewatering of the excavation must have a local relevance and interest the
excavation only. No dewatering must be applied to the surrounding areas to avoid
unwanted settlements of the surrounding buildings.
9.2 On the Expected Damage Category
The construction of the basement will generate ground movements due to a variety of
causes including; heave, settlement, underpin construction and underpin wall deflection
during and after excavation. Calculations indicate that these could give rise to a damage
category within ‘Category I’ (Very Slight) for the adjacent properties. The above assumes