Contract and Procurement Management (C&PM) 101 Presented by: Cathy Garcia, C.P.M. Manager Vickie L. Hokenson, C.P.M. Lead Buyer III, Contract Specialist Jeff Fratt, C.P.M. Buyer III February 28, 2012

Contract and Procurement Management (C&PM) 101

  • Upload
    gita

  • View
    45

  • Download
    0

Embed Size (px)

DESCRIPTION

Presented by: Cathy Garcia, C.P.M. Manager Vickie L. Hokenson, C.P.M. Lead Buyer III, Contract Specialist Jeff Fratt, C.P.M. Buyer III. Contract and Procurement Management (C&PM) 101. February 28, 2012. Topics for Discussion. Who and Where Are We Basic Training - PowerPoint PPT Presentation

Citation preview

Page 1: Contract and Procurement Management (C&PM) 101

Contract and Procurement Management (C&PM)

101Presented by:

• Cathy Garcia, C.P.M.Manager

• Vickie L. Hokenson, C.P.M.Lead Buyer III, Contract Specialist

• Jeff Fratt, C.P.M. Buyer IIIFebruary 28, 2012

Page 2: Contract and Procurement Management (C&PM) 101

Topics for Discussion Who and Where Are We Basic Training Procure-to-Pay Life Cycle Requisition Creation (Req-creation) Common Transaction Issues Accessible Technology Initiative (ATI) Bid Thresholds/Competition Sole Brand / Sole Source Disabled Veteran Business Enterprise(DVBE)/Small Business (SB) Prohibited Practices / After the Fact (ATF) Deadlines

Page 3: Contract and Procurement Management (C&PM) 101

Contract & Procurement Management

Who and Where are We

Cathy Garcia, C.P.M. Vickie L. Hokenson, C.P.M.

Manager Lead Buyer III, Contract Specialist

[email protected] [email protected]

619-594-4723 619-594-2796

Romeo Del Rosario James Durante Jeff Fratt, C.P.M.

Buyer I Buyer II Buyer III

[email protected] [email protected] [email protected]

619-594-0928 619-594-4720 619-594-3965

Shawn Hawes Kathi Horton, A.P.P. Michelle Tanner

Buyer II Buyer III, Contract Specialist Administrative Suppor

[email protected] [email protected] [email protected]

619-594-7073 619-594-2445 619-594-0112

Administration Building, Room 116 Office Hours: Monday-Friday 8:00am – 4:30pmMain Line Phone: 619-594-5243 Fax: 619-594-5919 Website: http://bfa.sdsu.edu/prosrvcs/

Page 4: Contract and Procurement Management (C&PM) 101

Basic Training Topics covered in Basic Training Presentation

including but not limited to: Mission/Delegation/Areas of Responsibility/ Fiscal Authorization Hierarchy/Campus Hospitality Policy/Campus Contracts may be downloaded from:

http://bfa.sdsu.edu/~leap/ “What’s New”

Page 5: Contract and Procurement Management (C&PM) 101
Page 6: Contract and Procurement Management (C&PM) 101

The Chronology of a RequisitionReq-Creation

Page 7: Contract and Procurement Management (C&PM) 101

Common Transaction IssuesBuyer Recommendations ~ Items identified that assist in expediting requisition

Requisition Entry Issues Action

Turnaround Time • C&PM normally processes in date order. • Don’t forget time for internal departmental approval.

Line Type • Select correct line type , Capital Asset, Construction Amt, Equip, Goods Supplies, Goods Supplies Amt, IT Capital Asset, IT Equipment, IT Goods Supplies, IT Goods Supplies Amount, IT Services Amount, Services Amount, Services Qty

Item TypeAmount Based vs Quantity Based

• Quantity Based should only be use when you have exact quantities.

• Amount Based is for open orders, services and unknown quantities.

Category Codes/Unit of Measures

• There are 100’s of category codes/unit of measures. Search for the most appropriate code. Do not always use Miscellaneous. Call C&PM if you need help with a “key” word to search

Page 8: Contract and Procurement Management (C&PM) 101

Common Transaction Issues- Continued

Requisition Entry Issues Action

Line Description • Always Start with the fiscal year order is funded - currently: 11/12

• List Part #(Receiving uses to identify product on pack list)

• Ensure full description of goods or services• Do not place supplier name on line (already at Header of req)

• Include Service Term at the end of the line (ie 7/1/2012-6/30/2013) (asset recovery information)

• No acronyms-reference full names

Electronic Waste Recycling Fees

• Create line for EWRF fees (Service Amount Based)

Freight • Do not create line for freight-Terms of PO will allow freight to be paid.(Exception Freight costs are >$500)

Supplier Information • New – enter all information, Name, Address, Phone/Fax, Email, Contact person in “Note to Buyer”

• Update – entered new contacts or change of address/phone in “Note to Buyer”

Page 9: Contract and Procurement Management (C&PM) 101

Common Transaction Issues- Continued

Requisition Entry Issues Action

Account Number/General Ledger Date

• Use appropriate natural account. Buyer will return• Use appropriate GL Date for F/Y (June for future year)

Multiple Accounts charged on same PO

• Use separate lines and not one line with two distributions.

Purchase Order Alterations (POA)

• If adding funds or correcting account # in Note to Buyer add existing PO # and Buyer Name.

Renewal • Add prior year PO# to Note to Buyer and indicate renewal

Attachments • Attach supporting documentation as pdf, word, excel documents, etc. (use browser to upload not markview)

• Ensure quotes are valid (not expired)• Provide justification for use of state funds• Hospitality justification, list of attendees, and agenda• Invoice with requisition –sign “OK TO PAY”

(expedites payment) (After the Fact (ATF) not acceptable)

Page 10: Contract and Procurement Management (C&PM) 101

Common Transaction Issues- Continued

Requisition Entry Issues Action

Receiving • If goods received directly by department (exception) and not through Receiving notify Receiving so that they may enter receipt. (x48339)

Who is authorized to sign agreements?

• C&PM are the authorized agents of the University to sign Agreements/Contracts. If individual represent themselves as the correct agent Supplier is unable to determine otherwise.

Frequently Asked Questions (FAQs)

• See web-site http://bfa.sdsu.edu/prosrvcs/faqs.htm

Page 11: Contract and Procurement Management (C&PM) 101

What is the Accessible Technology Initiative (ATI) ?

ATI is the California State University system’s effort to implement federal and California law requiring access to technology for students, faculty, staff, and visitors to each campus. The initiative is a collaborative effort at each CSU university to provide access to technology in three major areas: Web accessibility, instructional materials accessibility, and technology procurement. A detailed description and list of resources are available at <http://www.calstate.edu/accessibility>.

Section 508 refers to federal guidelines that facilitate procurement of products which meet the accessibility needs of our campus community

Page 12: Contract and Procurement Management (C&PM) 101

Accessible Technology Initiative(ATI)Section 508

All Electronic and Information Technology (E&IT) purchases of hardware, software and IT services over $15,000 must be reviewed and approved by the Compliance Officer for each university division prior to submission to Contract & Procurement Management.

If the product requires electricity, has an interactive screen or display and transfers information, it probably falls under Section 508.

Purchasing an accessible product is often less expensive than providing accommodations (e.g. purchasing a video with caption vs. hiring an interpreter.)

Page 13: Contract and Procurement Management (C&PM) 101

E&IT/ATI Product ExamplesTelecommunication products Computer operating systems

Transaction machines Computers

Information kiosks Multimedia (including videotapes)

World Wide Web sites Electronic office equipment (such as copiers and fax machines)

Software applications Any device or system that is used in the creation, conversion, or duplication of data or information

Page 14: Contract and Procurement Management (C&PM) 101

Procurement Process for Software & Equipment AccessibilitySoftware Acquisition http://access.sdsu.edu Equipment Acquisition Accessibility Evaluation Time: 2-4 weeks Involve Us Early VPAT – Voluntary Product Evaluation Template Websites

http://access.sdsu.edu/procurement.htm

http://www.calstate.edu/Accessibility/EIT_Procurement/VPAT_Guide.html

http://access.sdsu.edu/etiresource.htm

http://access.sdsu.edu/index.htm

Page 15: Contract and Procurement Management (C&PM) 101

Bid Thresholds / Competition“The CSU is committed to a policy of promoting fair and open competition, for the acquisition of goods and services to meet its needs” CSU Administrative Manual

Bid thresholds are set by State civil codes and adapted by the CSU.

Classification of the contract is the first step. Contract for Goods Information Technology Resources (ITR) Goods and Services

Contract Contract for Services

What will the dollar amount of the contract be, including freight, delivery, set up, installation and training, but not sales tax?

Page 16: Contract and Procurement Management (C&PM) 101

Bid Thresholds / Competition

If your project is over $50,000.00, call us

Page 17: Contract and Procurement Management (C&PM) 101

Bid Thresholds / Competition Goods

Goods less than $50K – No competition required Goods greater than $50K but less than $100K – Informal bid

process with advertising in the State Contracts Register (Bidsync)

Goods greater than $50K but less than $100K may be the result of informal quotes from two or more Small Business/Micro Business without advertising.

Goods greater than $100K will be the result of a formal competitive bid.

Page 18: Contract and Procurement Management (C&PM) 101

Bid Thresholds / Competition Information Technology Resources

ALL ITR GREATER THAN $15K REQUIRE ATI COMPLIANCE. ITR services greater than $5K require advertising in the Contracts

Register (BidSync) ITR acquisitions less than $50K – No competition required ITR acquisitions greater than $50K but less than $100K may be the

result of informal quotes from two or more SB/MB without advertising.

ITR acquisitions greater than $50K and less than $500K may be the result of informal quotes including advertising on BidSync.

ITR acquisitions greater than $500K will be the result of a formal competitive bid.

Page 19: Contract and Procurement Management (C&PM) 101

Bid Thresholds / Competition Services

Services less than $50K – No competition required Services greater than $50K but less than $100K may be the

result of informal quotes from two or more Small Business/Micro Businesses without advertising.

Services greater than $50K will be the result of a formal competitive bid.

Exception: Public Works contracts greater than $5K require formal competitive bids.

Page 20: Contract and Procurement Management (C&PM) 101

Sole Brand/Sole Source Used when full and open competition is not possible Each sole brand and sole source shall have a written justification and shall

include the following: The unique performance factors required and why are they required; What other source/brands have been considered and why were they rejected (name

names)

Sole brand and sole source shall not be justified because of: A lack of advanced planning Concerns related to the amount of funds available, cost A contract or purchase made that was not competitively bid with a price of zero or

below market can not be amended/ increased or a new order placed above the bid thresholds using the sole source / sole brand as a justification for not bidding.

Personal preference Vendor performance, local service, maintenance and delivery

Page 21: Contract and Procurement Management (C&PM) 101

Disabled Veteran Business Enterprise (DVBE) / Small Business/Micro Business (SB/MB)

The state established a goal of at least 3% DVBE participation in all contracts, PO’s and PCC purchases.

All competitive bids require DVBE participation. The state established a goal for the use of SB/MB in at least 25% of the

State's overall annual contract dollars All competitive bids must offer a 5% preference to SB/MB

DVBE SB/MB Option:May be used for Goods, ITR, Services and Public Works.

Contract value between $5K and $250K

No advertising required

Must obtain bids from 2 or more DVBE firms or 2 or more SB/MB firms.

Page 22: Contract and Procurement Management (C&PM) 101

Prohibited Practices• Use of SDSU name for personal gain• Use of SDSU name to obtain discounts for personal

use• Conflict of Interest – purchase made from a

company you own or from which you will benefit• Endorsement of products• Use of the CSU name without approval• Restrictive bid specifications• Splitting of orders to avoid bidding• Advance payments (Procurement Credit Card is not

considered an advanced payment)

Page 23: Contract and Procurement Management (C&PM) 101

After the Fact (ATF) What is an After the Fact? Commitment of State Funds or Resources without

an authorized Purchase Order. Risk – Individual may be held personally responsible for payment to the

Supplier. Staff/Faculty/Supplier may not be reimbursed or paid by the University for goods or services. Duplicate shipment of orders.

Ways to avoid an ATF: University Procurement Credit Card, Open Purchase/Service Order, OfficeMax on-line Ordering, Request Rush Purchase Order, Plan Ahead.

Educate Suppliers – It is important that Suppliers understand up front a PO is required prior to shipment of goods or services. Individuals who request goods or services without obtaining a PO in advance send a confusing message to our Suppliers. ATF’s delay payments causing loss of payment discounts to the campus. If you have an urgent need call us for assistance!

Plan Ahead

Page 24: Contract and Procurement Management (C&PM) 101

DeadlinesSUBMISSION DATES FOR THE CURRENT 2011/2012 FISCAL YEAR: http://bfa.sdsu.edu/~leap/ MARCH 1, 2012: Submission of final close requests for goods and service orders charged to the 2011/2012 fiscal year. CPM will continue to receive and process final close requests after the March 1st deadline. Timely submission of your final close requests will free up funds for submissions of any additional 2011/2012 requisitions.

.APRIL 2, 2012: Requisitions requiring bidding which exceed $50,000 for goods and services and requisitions exceeding $600,000 for major capital construction projects charged to the 2011/2012 fiscal year.

MAY 1, 2012: Final access to Oracle for submission and approval of requisitions charged to the 2011/2012 fiscal year for commodities and services less than $50,000 and requisitions for Minor Construction (<$600K) projects with fast track bidding documentation included. All requisitions charged to the 2011/2012 must be approved by 4:30 p.m.

MAY 2, 2012 All requisitions not approved by end of business on May 1st with status of in process, returned or rejected will be cancelled. See below for 2012/2013 submission dates.

JUNE 19, 2012: OfficeMax orders must be placed and posted to your account by June 19,2012 in order to be charged to your 2011/2012 fiscal year budget

JUNE 22, 2012: Procurement Credit Card (PCC) charges must be made by June 21, 2012 and POSTED by June 22, 2012, in order to be charged to your 2011/2012 fiscal year budget.

JUNE 30, 2012 All goods/services for 2011/2012 must be ordered, received, and delivered by this date. Orders for goods or services received after June 30, 2012 must be charged to the appropriate 2012/2013 fiscal year.

SUBMISSION DATES FOR THE FUTURE 2012/2013 FISCAL YEAR: JUNE 4, 2012: Access to the 2012/2013 General Ledger (GL) (01-JUL-2012) will be enabled for submission of requisitions charged to the 2012/2013 fiscal year. Requisitions submitted using the current year GL will be returned to the department for re-submittal using the 01-JUL-2012 GL date. Delivery of goods and services charged to the 2012/2013 FY must be scheduled after July 1, 2012.

JUNE 29, 2012: Access to Oracle for submission and approval of requisitions charged to the 2012/2013 fiscal year will be disabled to allow for the year end closing process.

JULY 6, 2012: Access to Oracle for submission of 2012/2013 requisitions will be enabled.

Page 25: Contract and Procurement Management (C&PM) 101

Are there any questions?