Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
0
Consultation
Reference: CER/17/335 Date Published: 12/12/2017 Closing Date: 26/01/2018
An Coimisiún um Rialáil Fóntas
Commission for Regulation of Utilities
Reporting and Incentives
under Price Review 4 Consultation
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
i
Executive Summary In December 2015, CRU set the price controls for the electricity networks Price
Review 4 (PR4) period for EirGrid as Transmission System Operator (TSO), and for
ESB Networks (ESBN) as Transmission Asset Owner (TAO) and Distribution System
Operator (DSO)/Distribution Asset Owner (DAO). In the Decision, CRU also
committed to update the reporting and incentive arrangements. The PR4 period runs
from 2016 to 2020.
Monitoring and reporting give visibility to what each company is delivering, and
improve accountability. Incentive mechanisms go a step further by attaching
additional rewards or penalties to specific reported measures of performance. Data
generated through reporting and incentives helps to inform the more detailed cost
assessments and forecasts involved in future price reviews, and ongoing regulatory
scrutiny. They are, therefore, important instruments through which CRU seeks to
protect the interests of customers.
This document sets out and seeks views on proposals for improving reporting and
incentives arrangements. These proposals will improve outcomes for electricity
customers and market participants during the PR4 period, and create a robust
platform for the continuing development of reporting and incentives for PR5 and
beyond.
Views are invited on these proposals by 26 January 2018.
Transmission
EirGrid as TSO is responsible for operating the power system in real-time, and
planning transmission network development. It also contracts with generation and
demand customers for connection to and use of the transmission system. ESBN as
TAO is responsible for maintaining the transmission network, and undertaking
transmission investment at the request of the TSO.
Under PR4, allowed revenues of €1,974m for the period were provided on behalf of
customers to fund the activities of the TSO and TAO. This was set to support total
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
ii
new investment of €1,024m1, and operating costs of €810m.
Reporting and monitoring (Proposals 1-3)
CRU is proposing the following changes to strengthen monitoring and reporting of how
these allowances are spent, and what levels of performance they deliver for
customers:
Re-set the requirements for the Annual Performance Report (APR) to produce
a new, consolidated TSO/TAO report containing a wider range of performance
measures, more information with which to understand the context for
performance, and be presented in more accessible and reader-friendly format;
Require the publication of a companion document of comparable readability to
inform stakeholders how network investment needs are being identified, and
how options to meet those needs are being developed, evaluated and
delivered;
A more formal process for the TSO or TAO (or CRU) to use monitoring
information to trigger an adjustment to capital expenditure allowances, if new
information reveals the existing allowances to be materially too high or low.
Incentives (Proposals 4-10)
The total amount at stake through incentives was set at 4% of operating costs for the
TSO, and 5% of operating costs for the TAO in PR3. CRU is proposed to retain these
overall incentive “pots” for the remainder of PR4, and refocus them in the following
ways:
Retain the existing TSO performance incentives around System Minutes Lost
and System Frequency, updated for recent data on actual performance;
A new incentive mechanism for performance on investment planning and
delivery, to replace the narrower PR3 focus on individual project milestones
on the portfolio of “live” projects being progressed by the TSO;
1 All values are in real 2014 prices unless otherwise stated.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
iii
Augment the existing TAO incentive on managing outages, to provide greater
flexibility for the TSO and TAO to work together to re-schedule outages at
short notice if the wider market benefits outweigh the additional costs;
A new incentive mechanism relating to the quality of stakeholder engagement;
A new incentive to reward the TSO for delivering exceptional outcomes
against key strategic objectives; and
A new formalised process for developing and reporting on innovation projects,
including the option for the TSO to submit applications for additional funding
where the business case is sufficiently strong.
The TSO’s incentive is symmetrical and is 4% of the TSO’s internal Opex,
which means the TSO can earn a maximum reward/penalty of €9.32m
The TAO’s incentive is symmetrical and is 5% of the TAO’s Opex, which
means the TAO can earn a maximum reward/penalty of €15.03m
This constitutes a combination of updating existing, proven incentive mechanisms for
new data on achievable levels of performance, and introducing new incentive
mechanisms to focus better on the TSO and TAO behaviours that in CRU’s view make
the biggest difference for consumers and market participants.
Distribution
ESBN as DSO/DAO operates the distribution system in real-time, and plans
extensions and reinforcements to the distribution network. It also manages the
allocation of rights to connect to and make use of the distribution system.
Under PR4, allowed revenues of €4,126m for the period were provided on behalf of
customers to fund the activities of the DSO/DAO. This was set to support total new
investment of €1,337m, and operating costs of €1,362m.
Reporting and monitoring (Proposal 11)
CRU is proposing the following changes to strengthen monitoring and reporting of how
allowances are spent by the DSO, and what levels of performance they deliver for
customers
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
iv
Consistent with the proposals for Transmission, to re-set the requirements for
the Annual Performance Report (APR) to produce a report containing a wider
range of performance measures, more information with which to understand
the context for performance, and presented in more accessible and reader-
friendly format.
Incentives
The total amount at stake through incentives was set at 4% of annual allowed
revenues in PR3. CRU is proposed to retain this overall incentive “pot” for PR4, with
this total concentrated over the remaining three years of the PR4 period. CRU is
refocusing the suite of incentive mechanisms in the following ways:
Retain the PR3 DSO incentives around unplanned Customer Minutes Lost
and Customer Interruptions, updated for new information on achievable
performance – and using a more accurate, standardised method of adjusting
for storm events;
Retaining the PR3 incentives around customer service and traditional
metering, updated for new information on achievable performance;
A new incentive mechanism linked to the DSO’s delivery of smart metering
services to Suppliers by Q4 2020 under its revised plan to support the
National Smart Metering Programme;
A new incentive mechanism relating to the quality of stakeholder engagement;
A new incentive to make available, or claw back, funding based on the DSO’s
performance in delivering sustained improvements in supply continuity for
6,000 of Ireland’s worst-served customers; and
A new formalised process for developing and reporting on innovation projects
pursuant to the Strategic Innovation Fund, with access to a significant
proportion of the Fund contingent on implementing a strong innovation
strategy.
The DSO’s incentive is asymmetrical and is based on the DSO’s total
revenue, which means the DSO can earn a maximum reward €147.52m or a
penalty of €178.46m.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
v
Public/ Customer Impact Statement
The electricity transmission and distribution systems deliver vital services for
customers. The Commission for Regulation of Utilities (CRU) ensures these services
are delivered efficiently and securely. The CRU does this by monitoring and
incentivising the behaviour of the Transmission System Operator (TSO), the
Transmission Asset Owner (TAO) and the Distribution System Operator (DSO).
The CRU’s overarching objective in proposing new mechanisms in this paper is to
ensure that incentives are targeted on the TSO and TAO behaviours that can make
the most positive difference to network users and consumers.
The impacts of the proposals on monitoring and reporting set out in this document are
informational. They afford energy customers and the wider public with more and
better information on what is being delivered in return for the revenue allowances
being provided on their behalf. Further, the information generated through these
reforms should over time lead to improvements in the CRU’s ability to make regulatory
decisions that protect the interests of customers.
The impacts of the proposals on incentives for the TSO, TAO and DSO are financial
and quality-of-service related:
First, the proposed incentives will have a direct impact on transmission and
distribution tariffs over the period 2019 to 2021. This is because the rewards
or penalties earned under the incentive schemes will impact tariffs the year
after the performance is measured. Transmission and distribution charges
are one of the inputs to each customer’s electricity bill. Where the network
companies outperform these incentives, to the benefit of consumers, they will
receive a financial reward that will be paid for through consumer network
charges. Where a weak performance will result in financial penalties to the
network companies that will put downward pressure on consumer’s network
charges.
Second, the incentives will impact on the quality of services provided by the
TSO, TAO and DSO/DAO. Companies will only be rewarded if they deliver
outputs that customers and the market value, e.g. higher than expected
supply quality, or strong stakeholder engagement. Collectively, the impact is
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
vi
to ensure that the prices customers pay are more closely aligned to the quality
of services they receive.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
vii
Table of Contents
1. Introduction ........................................................................................................ 1
1.1 Commission for Regulation of Utilities ........................................................................... 1
1.2 Background ................................................................................................................... 1
1.3 Purpose of this proposed decision ................................................................................. 2
1.4 Related documents ....................................................................................................... 2
1.5 Structure of this document ............................................................................................ 2
1.6 Responding to the CRU .................................................................................................. 3
2. Context ............................................................................................................... 4
2.1 Industry structure ......................................................................................................... 4
2.2 The role of reporting and incentives .............................................................................. 4
2.3 PR3 reporting and incentives ......................................................................................... 5
2.4 CRU’s objectives for PR4 ................................................................................................ 7
3. Transmission – reporting .................................................................................. 9
3.1 Output-based reporting ................................................................................................. 9
3.2 Capex monitoring ........................................................................................................ 12
3.3 Capex adjustment process ........................................................................................... 14
3.4 Consultation question ................................................................................................. 15
4. Transmission – incentives .............................................................................. 17
4.1 System performance – TSO .......................................................................................... 17
4.2 Investment Planning and Delivery (IPD) – TSO .............................................................. 19
4.3 Project delivery – TAO ................................................................................................. 21
4.4 Outage management ................................................................................................... 23
4.5 Stakeholder engagement ............................................................................................. 25
4.6 Delivering against strategic objectives ......................................................................... 27
4.7 Innovation .................................................................................................................. 29
4.8 Consultation question ................................................................................................. 31
5. Distribution – reporting ................................................................................... 32
5.1 Output measures ........................................................................................................ 32
5.2 Consultation question ................................................................................................. 34
6. Distribution – incentives ................................................................................. 36
6.1 Unplanned outages ..................................................................................................... 36
6.2 Worst-served customers .............................................................................................. 38
6.3 Customer service ......................................................................................................... 40
6.4 Metering – traditional ................................................................................................. 42
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
viii
6.5 Metering – smart ........................................................................................................ 44
6.6 Stakeholder engagement ............................................................................................. 46
6.7 Strategic and innovative thinking ................................................................................. 47
6.8 Consultation question ................................................................................................. 51
7. Incentives as a package .................................................................................. 53
7.1 TSO incentive package ................................................................................................. 53
7.2 TAO incentive package ................................................................................................ 55
7.3 DSO/DAO incentive package ........................................................................................ 58
7.4 Consultation question ................................................................................................. 63
Annex 1: International review ................................................................................................ 64
Annex 2: Draft Annual Reporting Principles ............................................................................ 66
Annex 3: TSO incentives......................................................................................................... 68
Annex 4: DSO incentives ........................................................................................................ 71
Annex 5: Questions for consultation ....................................................................................... 73
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
ix
Glossary of terms and abbreviations
Abbreviation or Term Definition or Meaning
PR3 The third electricity price control set by CRU, spanning the period January 2010 to December 2015
PR4 The fourth electricity price control set by CRU, spanning the period January 2016 to December 2020
TSO Transmission System Operator – EirGrid
TAO Transmission Asset Owner – ESB Networks
DSO Distribution System Operation – ESB Networks
DAO Distribution Asset Owner – ESBN Networks
APR Annual Performance Report
CI Customer Interruptions - the average number of interruptions per customer connected in the year (CI) – Distribution System
CML Customer Minutes Lost - the average number of minutes without supply per customer connected in the year (CML) – Distribution System
SML System Minutes Lost (SML) – Transmission System
SF System Frequency (SF) – Transmission System
WSC Worst Served Customer
SIF Strategic Innovation Fund
PIP Project Implementation Plan
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
1
1. Introduction
1.1 Commission for Regulation of Utilities
The Commission for Regulation of Utilities (CRU) is Ireland’s independent energy and
water regulator. Our Mission is to regulate Water Energy and energy safety in the
public interest.
Further information on the CRU’s role and relevant legislation can be found on the
CRU’s website at www.cru.ie.
1.2 Background
CRU is responsible for the economic regulation of the system operators and asset
owners for electricity transmission and distribution.
Price controls, which limit the revenues that the relevant licensees can recover from
electricity consumers, are set every 5-years. CRU also has powers to require
licensees to submit or publish reporting information, and to set incentive schemes
(with associated financial or reputational rewards or penalties) for specified areas of
activity.
In December 2015, CRU set its price controls for the Price Review 4 (PR4) period for
EirGird as Transmission System Operator (TSO), and for ESB Networks (ESBN) as
Transmission Asset Owner (TAO) and Distribution System Operator
(DSO)/Distribution Asset Owner (DAO). In the Decision, CRU also committed to
update the reporting and incentive arrangements.
It should be made clear from the outset that the PR4 incentives for the TSO and TAO
were not turned off during 2016 and 2017 (unlike for the DSO/DAO). Performance
against the System Minutes Lost (SML) and System Frequency (SF) incentives will
therefore still be measured for the TSO for 2016 and 2017, using the targets set out in
this consultation. Any new incentives introduced in this consultation will only take
effect from 2018.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
2
1.3 Purpose of this Consultation
The purpose of this document is to set out and seek views on proposals for the
reporting and incentives arrangements to apply for the remainder of the PR4 period.
The objective is twofold. First, to improve outcomes for electricity customers and
market participants during the PR4 period. Second, to create a robust platform for the
continuing development of reporting and incentives for PR5 and beyond.
1.4 Related documents
Further background relevant to this consultation document can be found in the
following documents:
CER/15/295 Decision on DSO Distribution Revenue for 2016 to 2020
Decision Paper
CER/15/296 Decision on TSO and TAO Transmission Revenue for 2016 to 2020
Decision Paper
CER/10/206 Decision on TSO and TAO transmission revenue for 2011 to 2015
Decision Paper
CER/10/198 Decision on DSO distribution revenue for 2011 to 2015
Decision Paper
1.5 Structure of this document
The first half of this document sets out proposals relating to Transmission. This
covers EirGrid as TSO, and ESB Networks as TAO. Proposed changes to the
reporting framework are set out in Section 3 and the proposed incentive framework
is described in Section 4. Sections 5 and 6 follow the same structure, for Distribution
– and only relate to ESB Networks.
For each area covered, we describe the issue being addressed and the action we
propose to take. We then summarise the supporting reasoning. In developing these
proposals, CRU has analysed performance under the PR3 framework, reviewed
practice in other relevant jurisdictions, and engaged with EirGrid and ESB Networks.
Specific questions for consultation can be found at the end of Sections 3-6. A
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
3
complete list of questions can also be found at Appendix 5. A summary of how CRU
has identified and used relevant experience from other jurisdictions is set on in
Appendix 1.
1.6 Responding to the CRU
This consultation document is for the attention of all stakeholders who have an interest
in understanding how EirGrid and ESBN’s performance is monitored and reported on,
and how revenues should flex to reflect levels of performance in certain specified
areas of activity.
The CRU welcomes comments on this consultation to be submitted via email by
Friday, 26 January, close of business, to [email protected].
All responses will be published on the CRU’s website unless marked as confidential.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
4
2. Context
In this section, we describe the industry structure, the role of reporting and incentives
in the economic regulation of networks, and how it had been given effect during the
PR3 period.
2.1 Industry structure
The PR4 Decision covers two companies, and three distinct roles. In summary, the
different roles and responsibilities are:
Transmission System Operator (TSO) – EirGrid: The physical operation of
the transmission system in real-time, including the procurement of system
services; the planning of extensions and reinforcements to the transmission
network, and associated interactions with the TAO; the offering of rights to
connect to and make use of the transmission system.
Transmission Asset Owner (TAO) – ESB Networks: The owner of the
transmission network, and the party who builds additional transmission
infrastructure or replaces assets at their end of life at the direction of the TSO,
and maintains the existing network.
Distribution System Operator and Asset Owner (DSO/DAO) – ESB
Networks: Responsible for the physical operation of the distribution system;
the planning and delivery of extensions, renewal and reinforcement of the
distribution network; maintenance, repair and supply restoration of the existing
network; the offering of rights to connect to and make use of the distribution
system.
2.2 The role of reporting and incentives
The key task for the economic regulation of regulated monopolies such as EirGrid and
ESBN is to align the interests of the regulated businesses more closely to the long-
term interests of customers. There are a variety of methods used by regulators to
pursue this objective.
The Price Review process determines how much revenue each licensee is permitted
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
5
to recover for a 5-year period. The allowances are set to enable each licensee to
recover efficient operating and capital costs, including a reasonable return on capital.
Companies can earn additional returns (for a limited time) by “beating” the cost
forecasts used in setting the allowance. Cost saving are then shared with customers
through lower charges.
Reporting requirements complement the “core” incentive to minimise costs in the
short-term. By giving visibility to what each company is delivering, there is less
potential for companies to boost short-term returns by reducing quality, or storing up
problems for the future by deferring necessary investment or maintenance. Incentive
mechanisms go a step further by attaching additional rewards or penalties to specific
reported measures of performance.
There are also wider informational benefits to use of reporting and incentives. They
increase understanding by network users and other stakeholders on how EirGrid and
ESBN are performing – which in turn improves accountability. Data generated through
reporting and incentives also helps to inform the more detailed cost assessments and
forecasts involved in future price review.
2.3 PR3 reporting and incentives
Under PR3, the TSO, TAO and DSO/DAO were subject to a range of financial
incentives, which resulted in reward or payment during the price review period. The
PR3 incentives have been the starting point for the PR4 incentive packages presented
in this consultation. Future behaviour and incentive targets have been calibrated with
historical performance to ensure continued improvement in service provision for
consumers.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
6
Table 1 TSO and TAO incentives and performance under PR3
Incentive Description and PR3 performance
TSO – EirGrid
Transmission System Performance
- System Minutes Lost2 Measure of minutes lost per year (planned and unplanned). <1.5 minutes per year target met in all year of PR3.
- System Frequency Measure (percentage) of network frequency, between the limits of 49.9 Hz and 50.1 Hz. Frequency target (96%) met in all years of PR3.
Transmission System Development
- TSO Project Milestones Incentive for successful completion of project milestones for pre-defined projects. The TSO received positive payments every year under this incentive during PR3.
- Delivery of Enhanced Network Capacity
Demonstration of benefits of network solutions, using cost-benefit analysis to quantify benefits delivered in previous periods.
TAO – ESBN
Transmissions System Development
- Issue PIP Incentive for successful completion of project milestones for pre-defined projects. The TAO received positive payments under this incentive during PR3.
- Scheduled outages Incentive linked to difference between planned and actual outage days (where subject to TAO control). The incentive resulted in payments to the TAO each year under PR3.
- Construction and Energisation Incentive linked to spend against agreed PR3 budget submission. Full incentive payment received each year in PR3.
2 “System Minute Lost is a measure of the energy not supplied for a disturbance. The metric takes account of the load lost (MW), duration of disconnection (Minutes) and peak system demand (MW), to allow for historical comparison. For example, if 300 MW were lost for 10 minutes and the system peak was 3000 MW, this would represent one System Minute. System Minutes = (Load MW x Duration mins) / (System Peak MW) = (300 x 10) / 3000 = 1” – Source - All-Island Transmission System Performance Report 2015
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
7
Table 2 DSO/DAO incentives and performance under PR3
Incentive Description and PR3 performance
Continuity of supply Customer Minutes Lost (CML) – duration of interruptions Customer Interruptions (CI) – frequency of interruptions. Target met in 2 of the 5 years in PR3.
Overall customer satisfaction survey3
Measure of customer perception of ESBN services (measured through a customer survey). 74% target met every year in PR3 (average performance of 81.6%).
Customer satisfaction Measure of speed of telephone response, abandonment rate, mystery caller, call back survey and call referral rate. Overall target rate of 85.3%, met every year in PR3.
Metering Meter reading targets: 98% of meters should have 1 reading per year, and 99% of meters will not have back to back block estimates. Targets met in all but 1 year in PR3.
Worst served Customer €10m fund available to improve services to customers experiencing large number of interruptions.
2.4 CRU’s objectives for PR4
As part of the PR4 final decisions (2015) for the TSO, TAO and DSO/DAO PR4, the
CRU committed to consult on the incentive packages for PR4 (see Section 1.4 for
document links). At the time, we commented that a number of existing incentives,
applicable during PR3, remained relevant for PR4. In addition, we identified areas
where significant review was required before the full incentive packages could be
introduced.
For the DSO/DAO (Ref CER/15/295), we committed to consider:
Incentives relating to continuity of supply,
An incentive to improve service of the DSO’s ‘worst served customers’,
Incentives relating to the quality of service provided by the DSO customer call
centre and an overall customer satisfaction incentive,
Incentives to reduce the level of electrical losses on the distribution system,
3 More Commonly known as the RedC survey
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
8
An incentive relating to the DSO’s meter reading for non-quarterly-hour
metered customers,
An incentive relating to the connection of renewable generation,
Other items for which there are no financial rewards/penalties, but which do
nevertheless encourage the DSO to maintain or improve its performance,
The introduction of a Strategic Innovation Fund for the DSO.
For the TSO and TAO (Ref CER/15/296), we committed to:
Carry out a review of the incentive mechanism that currently applies to the
TSO and TAO in relation to service delivery and targets,
Put in place strategic incentives separately to incentives focused on
operational and service level targets,
Consult on the objectives against which the incentives would be assessed
and the details of the mechanism itself (noting that objectives should be time
limited, clearly measureable, and be a strategic objective related to the TSO’s
role in the transition of the system to one with a large penetration of
renewable energy).
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
9
3. Transmission – reporting
In this section we set out and invite views on proposals for reporting that will apply to
EirGrid as TSO and ESBN as TAO, for the period 2018 to 2020. In developing these
proposals, the CRU is also seeking to put in place arrangements that can endure,
subject to review and refinement as part of the PR5 process.
3.1 Output-based reporting
Objective
CRU’s objective in revising the framework of reporting for Transmission is to increase
transparency for all stakeholders on what is being delivered over time by the TSO and
TAO in return for the revenues made available through the Price Review. Further, to
ensure that relevant information is easy to access and interpret – and capable of
adapting over time to continue to ensure reporting on the full range of ways in which
actions by the TSO and TAO impact stakeholders.
Without a robust framework for reporting, there is a risk that consumers, stakeholders
and CRU cannot easily discern how the TSO and TAO are performing – and hence
are less able to hold the TSO and TAO to account, or understand the levels of
performance that it is reasonable to expect the TSO and TAO to deliver. This could,
over time, constrain the quality of regulatory decision-making on behalf of consumers.
Proposal 1
CRU is proposing a new reporting framework for Transmission with two component
parts, which together – along with changes to capex monitoring – represent a material
change to current arrangements. The two component parts are described in turn
below.
a. A consolidated TSO/TAO Annual Performance Report (APR)
We propose to facilitate a consolidated APR covering all aspects of Transmission.
This would replace the current arrangements under which reports are produced and
published separately by the TSO and by the TAO.
b. Updated rules on the format and content of the APR
We proposed to re-state the required format and content of the APR, to make it more
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
10
useful and accessible to stakeholders. This will be given effect by CRU setting new
principles for the APR4, and for the TSO and TAO to undertake a review of changes
needed to meet the new principles. The finding of these reviews would be considered
for approval by CRU, and then reflected in the APRs for 2017 (expected to be
published in mid-2018).
The updated principles proposed by CRU are designed to ensure that the APR is
updated to make its content more comprehensive and relevant, and to make its format
easier for stakeholder to access the information. Draft principles are set out below,
with further detail provided in Annex 2.
Reasoning
CRU has come forward with this model based on analysis of how the current
arrangements perform, and might be expected to continue to perform, against the
objective above, and taking into account background research into how output-based
reporting is given effect in other relevant jurisdictions.
The key documents in the current framework are the APR prepared by the TSO, and
the APR prepared by the TAO. Collectively, these documents should provide a broad,
accessible summary of performance. But in practice, there are weaknesses and
limitations:
The two documents are prepared separately, and do not reference each
other. It is not “joined up” for a stakeholder who might be interested in
understanding performance of the transmission sector overall. It should also
be noted that the TSO report is prepared as a joint document with SONI to
provide an all-island view, with separate sections for EirGrid and SONI.
The TSO document is not particularly visible or easy-to-access on its website,
and has a “look-and-feel” consistent with a regulatory submission. This
contrasts with other documentation, such as the EirGrid Annual Report –
which are much more accessible and engaging for the reader.
4 Pursuant to Condition 18 of the TSO licence and Condition 11 of the TAO licence.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
11
While the TSO report is relatively lengthy at around 75 pages (including
appendices), of which over 30 pages relate directly to EirGrid’s performance
as TSO, the information contained is relatively superficial and uninformative
from the perspective of a reader wanting to understand whether the TSO was
performing well or not. Two examples from the 2016 Report:
o First, the section on grid development is a bullet-point list of fourteen
capital projects which were reported as being completed in 2016.
There is no information on whether these projects were completed on
time or to budget, what impacts these delivered projects have on
market participants or consumers in terms of supply reliability or the
ability to participate in the market, or why these projects represent an
efficient response to an identified need. Hence, only a very narrow
perspective on performance is provided.
o Second, the section on connection reports that 5 new demand
connection offers and 1 new generation connection have been
executed in 2016, and that there has been a “significant increase” in
the work done to modify connection offers. It also reported that 0 new
demand connections, and 3 new generation connections comprising
154 MW of capacity have been energised. It is difficult to see what a
reader could infer about the quality of TSOs performance in respect of
connection from this information, even if the reported information was
compared to reports from previous years.
The limitations in the reporting of TSO’s delivery of new connections
represents a significant gap, whereas better reporting could improve
accountability and the strength of “reputational” incentives on the TSO to meet
the needs of prospective network users.
The choice of formatting and language, and the extent to which information
and data are provided to help understand the broader context for
performance, is not fit for the purpose of helping a reader understand and
access information easily. This applies to the reports prepared by the TSO
and by the TAO.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
12
3.2 Capex monitoring
Objective
CRU’s primary objective in revising the framework of capex monitoring is to increase
its own capacity to understand the processes that result in transmission investment,
and hence better protect customers from the risks and costs of inefficient investment.
Regulatory reporting is a core function of any regulatory price review process. It
allows regulators to monitor the progress of regulated companies during the price
review, in reconciliation at the end of the review, and as a key input to the next review.
Effective reporting helps to overcome the asymmetric information problem inherent in
monopoly regulated network industries – including by helping networks users and
other stakeholders better understand, and engage with, plans for how the network is
being developed.
Proposal 2
CRU proposes a new approach to capex monitoring which has three component parts,
which collectively will support a broader and more accessible view on how the TSO
and TAO, collectively, plan and deliver investment in transmission infrastructure:
a. Broadening the range of reported activities
We propose to increase the scope of reporting to include all elements of the
investment planning and delivery process. Reporting currently focusses on progress
against milestones for the ‘live’ list of transmission projects. We propose to extend the
scope of reporting to also include how the need for investment is assessed and
quantified, and how options are identified and evaluated – and the optimal option
identified.
b. From quarterly to annual
We propose to change the frequency of submissions on capex progress from the TSO
and TAO to CRU. Currently, data is submitted to CRU quarterly. We propose to
move to an annual submission of data and supporting commentary, across the
broader range of activities identified in point a. above.
c. An annual Investment Planning and Delivery Report (IPDR)
We propose to oblige the TSO and TAO to produce, jointly, a consolidated summary
report on investment planning and delivery for external stakeholders. This will, in
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
13
effect, be a companion document to the new, consolidated APR. Currently, summary
information derived from the data submitted to CRU is not routinely published.
Reasoning
The key reasoning for the proposed changes to capex reporting and monitoring can
be summarised as follows:
Quarterly, project-level data is unnecessarily detailed. There is a risk that
provision of such frequent, detailed data blurs or dilutes the primary
accountability of the TSO and TAO for investment planning and delivery
decisions. There are also the administrative resources involved for the TSO,
TAO and CRU in processing but not routinely using these data. This has both
an absolute cost and an opportunity cost, i.e. resources could be deployed in
other regulatory activities with potentially greater benefits for consumers.
While the focus of the current arrangements could be view as too detailed, it
could also be challenged as too narrow. There is little formal reporting to the
CRU on why the specific mix of transmission project represents the right set
of projects – including how the precise need for enhancing transmission
capabilities has been identified, and on how different options for meeting
those needs have been identified and evaluated. Arguably, it is this
information that is more relevant and useful to understanding whether the
transmission network is being developed economically and efficiently.
There is evidence in other jurisdictions of arrangements that provide much
greater transparency on needs and options working effectively in practice5.
Both as a mechanism for enabling stakeholders to engage actively in the
investment planning process, and as a means of supporting better informed
decision-making. The rules for investment planning in Australia’s National
Electricity Market (NEM), and the manner in which the active consideration of
alternative, non-network solutions is supported, is a case in point.
5 A summary of our analysis of other jurisdictions is provided in Annex 1
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
14
3.3 Capex adjustment process
Objective
CRU’s objective in tightening up the mechanism for adjusting capex allowances during
a price review period is to provide flexibility in response to significant new information,
and hence avoid delays to necessary investment – but without diluting the incentives
on the TSO and TAO to manage costs efficiently.
The nature of PR4, and all regulatory price controls, is that investment funding is
provided in expectation of what will be required. Market developments may however
result in the efficient level of investment being very different to what was expected. An
adjustment mechanism is intended to address the situation where the differences are
so large as to risk delaying necessary investment, or placing unreasonable financial
demands on the TSO or TAO (or on consumers, e.g. if capex allowances were set
much higher than was later seen to be needed).
Proposal 3
CRU proposes to introduce a formal mechanism through which an application to re-set
allowances can be triggered in specified circumstances. The mechanism has the
following features (with the dates and parameters in parentheses being for illustration,
with views invited):
Either the TSO, TAO or CRU may trigger the process, on or before [31st
March] in any given year.
The process may only be triggered if there has been a material change in
circumstances (relative to when the capex allowance was originally set) such
that either: (a) the total capex allowance for the 5-year PR period is likely to
be breached by more than [10%] in the next calendar year; or (b) there is a
high likelihood that the total capex allowance will be underspent by more than
[20%] by the end of the 5-year PR period.
The event triggering the process will be either: (a) a submission to CRU by
the TSO or TAO setting out in detail the nature of the material change, and its
net impact on the level of capex and opex over the remainder of the PR
period; or (b) a determination by the CRU requesting a submission by the
TSO or TAO, and citing the nature of the material change to be costed.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
15
CRU will consult on the application, and may subsequently issue a decision to
modify the allowances for capex and opex used for the purposes of setting
tariffs.
This proposed process replaces the current scope for ad hoc adjustments to be
considered and made.
Reasoning
The key reasoning for the proposed changes to the capex adjustment process can be
summarised as follows:
It is appropriate to have some flexibility to revisit allowances in the light of
significant new information, and this should allow for the fact that the new
information might reveal the allowances to be significantly higher or lower
than expected. Without such flexibility there is a risk that efficient and
necessary investment cannot be made, or that current consumers are making
payments “on account” for assets that are not going to be built. Further, a
degree of formality of how this process will operate increases regulatory
certainty, and provides a more transparent and regime for stakeholders. For
example, by affording stakeholders an opportunity to be consulted on the
need for, and value of, adjustments to capex allowances.
But there should be a “high bar” to trigger such a mechanism, to avoid diluting
the incentives on the TSO and TAO to manage their costs efficiently under the
allowances that have been set. Further, if the allowances are to be re-
opened, then the impacts should be considered broadly – recognising that
material changes in capex drivers could have direct and indirect impacts on
the overall capex programme, and might also impact on opex6.
3.4 Consultation question
6 For example, a change in circumstances that means that replacement capex needs to be accelerated could also have a reducing impact on maintenance costs over the period. If such second-order impacts were not recognised, then the adjustment to allowances could be too high (or low).
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
16
1. Do you have any comments on Proposals 1-3 and CRU’s supporting
reasoning, including but not limited to the following aspects:
a. The objective of a more comprehensive, user-friendly joint TSO/TAO
performance report, and how best to meet it; and
b. The rationale for a companion summary report each year on investment
planning and delivery.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
17
4. Transmission – incentives
In this section we set out and invite views on proposals for incentive mechanisms
applying to EirGrid as TSO and ESBN as TAO, for the PR4 period.7 In developing
these proposals, the CRU is also seeking to put in place arrangements that can
endure, subject to review, refinement and updating as part of the PR5 process.
The CRU’s overarching objective in proposing these mechanisms is to ensure that
incentives are targeted on the TSO and TAO behaviours that can make the most
positive difference to network users and consumers. Further, that the performance
targets against which the TSO and TAO are incentivised are based on the most
appropriate and up-to-date data.
The proposals have also been calibrated such that, in aggregate, the financial
exposure for the TSO and TAO is consistent with the PR4 Decision. For the TSO, this
translates to 4% of internal opex; for the TAO this translates to 5% of allowed opex.
4.1 System performance – TSO
Objective
CRU’s objective in putting in place an incentive mechanism for system performance is
to give the TSO an appropriate financial stake in maintaining appropriately high
standards of system performance. It reflects that customers and market participants
place a high value on supply reliability and quality, and that the actions of the TSO can
be a significant influencing factor on outcomes.
Proposal 4
CRU proposes to retain the PR3 structure of incentives, with target levels of
performance for System Minutes Lost (SML) and System Frequency (SF), updated for
new information. We also propose to retain the share (40%) of the total TSO incentive
7 The PR4 incentives for the TSO and TAO were not turned off during 2016 and 2017 (unlike for the DSO/DAO). Performance against the SML and System Frequency incentives will therefore still be measured for the TSO for 2016 and 2017, using the targets set out in this consultation. Any new incentives introduced in this consultation will only take effect from 2018.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
18
pot allocated to system performance.
The mechanism is proposed to have the following features:
As for PR3, an annual reward of up to 0.8% of TSO internal opex per
incentive.
As for PR3, an annual penalty of up to 0.8% of TSO internal opex per
incentive.
Targets for SML and SF based on average actual performance over the past
five years. See Annex 2.
Retention of the same structure of caps, collars and dead-bands around the
target levels of performance as adopted in PR3.
Reasoning
The key reasoning for the proposal can be summarised as follows:
System Minutes Lost and System Frequency are well-recognised, robust
ways of measuring the reliability and quality of supply delivered by an
electricity transmission system. The metrics are proximate to outcomes that
users of the transmission system place a high value on. The use of standard
metrics also allows the TSO’s performance to be understood over time, and
relative to other jurisdictions.
The structure of incentives used in PR3 has proven to be workable in practice,
and consistent with delivering high levels of performance, and trend
improvements. The value of the incentive pot for PR3 appears to be
reasonable and proportionate, relative to other potential uses for incentives.
The symmetric nature of the scheme means that strong performance is
rewarded and poor performance is penalised, and increments in performance
are valued at the same rate.
Updating of the target levels of performance to make use of recent data
means that the benefits of past performance improvements by the TSO are
shared with network users. Without this recalibration of targets, there would
be the potential for windfall gains (or losses) for the TSO.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
19
The CRU is also considering whether an improvement factor should also be
built in. Existing performance levels are very high, and the scope for further
performance improvements might be marginal. However, the principle of
continuing improvement should also be recognised in setting incentives. CRU
will revisit this aspect of the incentive design in the light of consultation
responses, and following further engagement with the TSO.
4.2 Investment Planning and Delivery – TSO
Objective
CRU’s objective in putting in place an incentive mechanism for investment planning
and delivery is to improve transparency over the efficiency with which these key
processes are undertaken. Further, to give the TSO a proportionate financial stake in
maintaining consistently high standards in what these processes deliver. It reflects the
fact that the TSO has significant discretion over investment planning and delivery, and
these decisions ultimately (and cumulatively) have a significant impact on network
performance and customers bills’.
Proposal 5
CRU proposes to replace the structure of incentives used during PR3, while retaining
the share (60%) of the incentive pot allocated to TSO behaviour associated with the
delivery of investment and provision of network capacity. The new mechanism will
have the following features:
An annual “balanced scorecard” assessment of the efficiency and rigour of the
TSO processes for (i) identifying the need for additional network capacity, (ii)
identifying and evaluating different technical and commercial options for
meeting identified needs, and (iii) supporting the delivery of investment
projects to increase or maintain network transfer capabilities.
The assessment will be undertaken by an independent auditor with
appropriate technical and commercial expertise. The auditor will be funded by
the TSO, but will report to both the TSO and CRU – using a framework and
criteria approved by CRU, following consultation with the TSO and other
stakeholders.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
20
A grading of “strong”, “adequate” or “weak” determined by CRU on the basis
of the auditor’s report and any other evidence considered relevant by CRU.
A reward for “strong” performance of 2.4% of TSO annual internal opex for
2018, 2019 and 2020; A reward for “adequate” performance equal to the
reasonable cost of the audit; A penalty for “weak” performance of 2.4% of
TSO internal opex8.
The mechanism described above will replace the PR3 “Project Milestones” incentive
and “Delivery of Enhanced Network Capacity” incentive mechanisms, with effect from
2018.
Reasoning
The key reasoning for the proposal can be summarised as follows:
Analysis undertaken by CRU’s independent consultants as part of the PR4
process raised significant concerns about the structure of incentives used
during PR3, and questioned whether there was a disjoint between rewards
under the scheme and a broader assessment of the timeliness and efficiency
with which necessary transmission investment was being planned and
delivered.
While the TSO did not necessarily accept this analysis, it is the case that the
PR3 scheme is partial in nature – by focusing only on whether milestones for
the currently “live” list of transmission projects are being met. This approach
does not incentivise, for example, the analysis of the need for investment, or
the choice of option to meet that need. By implication, this means that the
TSO could be rewarded under the scheme even if the “wrong” mix of projects
was being delivered. The focus on project milestones is not sufficiently
proximate to the outcomes that matter, i.e. a transmission network that is
optimised to meet the needs of current and prospective network users, at
efficient cost to customers.
8 Less the reasonable cost of the audit.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
21
Analysis undertaken by CRU’s PR4 consultants also highlighted concerns
about the practicalities of the Project Milestones and Delivery of Enhanced
Network Capacity incentives. For example, the rolling nature of the list of
projects against which progress was assessed – and the role of the TSO in
formulating this list. In effect, there was a concern that the TSO could be
perceived to be “setting its own exam”.
CRU recognises that while the proposals address the concern about the
current incentive mechanism being too partial in scope, it does introduce more
subjectivity into the assessment of the TSO’s performance. The use of an
independent auditor working to a “scorecard” that is developed following
consultation between the TSO, CRU and other stakeholders is designed to
mitigate this concern. CRU considers that the key elements of (i) identifying
need, and (ii) developing and evaluating options, are amenable to objective
assessment through choice of an appropriate set of KPIs.
CRU is open to considering a more granular scoring scheme than
“strong/weak/adequate”, and would welcome views on this aspect of the
incentive scheme. A wider range of outcomes for the TSO might enable
performance to be rewarded or penalised more accurately. But, it might also
introduce more subjectivity in the mapping of evidence to one side or another
of a performance boundary.
4.3 Project delivery – TAO
Objective
CRU’s objective in putting in place an incentive mechanism for project delivery by the
TAO is to give the TAO a proportionate financial stake in the efficient and timely
implementation of the TSO’s investment plans. While the role of the TAO is narrower
than the TSO’s in the sense that it does generate the investment plans, the TAO’s
efficiency and timeliness in delivery can have significant impacts for market
participants and customers.
Proposal 6
CRU is considering one of the following two approaches.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
22
The first option is to incorporate the assessment of TAO project delivery into the
“balanced scorecard” approach for investment planning and delivery outlined in
Section 4.2 above. This would have the following characteristics:
The performance of the TAO and timely and efficient delivery of projects
would be audited annually against pre-defined criteria – and a report
submitted to CRU.
The report would form the basis for an overall TAO assessment by CRU of
“strong”, “adequate” or “weak”.
“Strong” performance would translate to a reward equivalent to 4.1% of
annual allowed opex for 2018, 2019 and 2020. This retains the maximum
upside of the corresponding project milestones incentive mechanisms from
PR3; “Weak” performance would translate to a penalty equivalent to 4.1% of
allowed opex.9 This retains the maximum downside of the corresponding
project milestones incentive mechanisms from PR3; “Adequate” perform
would translate to an award equivalent to the reasonable cost of the audit.
The second option is to retain the PR3 approach, which links rewards or penalties to
(i) the timeliness with which the TAO issues each required Project Initiation Plan (PIP),
and (ii) the extent to which the TSO carries out the works it is scheduled to carry out in
the construction and energisation of new transmission infrastructure.
Reasoning
The key reasoning for the proposal can be summarised as follows:
The role of the TAO within the framework of investment planning and delivery
is much narrower that the TSO, and has less discretion. In broad terms,
responsibility for investment planning sits with the TSO, and the TAO’s role is
to build the projects defined by the TSO as necessary. Hence, incentives
linked to meeting milestones or planned expenditure on individual projects
might continue to be appropriate.
9 Less the reasonable cost of the audit.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
23
However, the move to an audit-based approach to support a broader, less
mechanistic approach to assessing performance – which could on balance be
more accurate. While meeting milestones and expenditure plans for identified
projects will continue to be relevant (and significant) in a TAO “scorecard”, the
audit approach does allow for other relevant metrics or evidence to be
considered also.
One specific concern about the PR3 arrangements is the extent to which the
mechanism creates sufficiently strong incentives on the TAO to facilitate new
connections. CRU recognises that many factors can influence the date at
which a new generation project is able to connect and participate in the
wholesale market, only some of which are within the control of the TSO or
TAO. However, it is important to use incentives effectively as a means of
rewarding (or penalising) the TSO that make a difference to the number and
type of generators able to participate in the wholesale market (and contribute
to wider policy goals, e.g. relating to renewables) at any given time.
The CRU is open to considering a more granular scoring scheme that
“strong/weak/adequate”, and would welcome views on this aspect of the
incentive scheme. A wider range of outcomes for the TSO might enable
performance to be rewarded or penalised more accurately. But, it might also
introduce more subjectivity in the mapping of evidence to one side or another
of a performance boundary.
4.4 Outage management
Objective
CRU’s objective in putting in place an incentive mechanism for the management of
outages by the TAO is to give the TAO a proportionate financial stake to minimise the
total net costs associated with the agreed outage plan, having regard to its own costs
and costs imposed by outages on the TSO and market participants. It reflects that at
times there can be a tension between the least cost outage plan for the TAO, and the
least cost outage plan for the system as a whole (and, by extension, consumers).
Proposal 7
CRU proposes to retain the core mechanism that has been in place during PR3, while
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
24
also introducing greater scope for flexibility where short-term changes in outage plans
can be agreed between the TSO and TAO. The two components of the proposed
incentives are:
A mechanism to reward the TAO for meeting the 3-weekly outage plans
published on the TSO website. This is, in effect, the continuation of the
mechanism that has been in place during PR3:
o A baseline level of outage days consistent with each 3-weekly outage
plan;
o Three performance bands relative to this baselined level
o If actual outage days are not more than 5% higher than the baseline,
then the full incentive payment is received
o If actual outages days is between 5% of 10% over the baseline level,
then a partial incentive payment is received
o If actual outage days total is more than 10% over the baseline level,
then no incentive payment is received.
A “use-it-or-lose it” allowance to fund, by agreement with the TSO, actions to
reduce the duration or timing of planned outages at short-notice. This is a
new feature:
o The option for the TSO to request at short notice a variation to the 3-
weekly outage plan to reduce the duration and/or amend the start date
o An incentive payment for the TAO equal to the reasonable costs
incurred by the TAO in meeting the request plus an uplift of [25%], for
each request accepted and met.
Collectively, these two mechanisms will account for 17% of the total TAO
incentive pot, equal to 0.85% of annual allowed opex (consistent with PR3).
The appropriate allocation between the two elements will be determined in
light of consultation responses, and further engagement with the TSO and
TAO.
Reasoning
The key reasoning for the proposal can be summarised as follows:
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
25
The joint management of outages by the TSO and TAO is an important
process that has potentially significant impacts on market participants and
consumers. Efficient design and delivery can help minimise network
maintenance costs, constraint costs and supply interruption risks. Hence, in
principle it is an appropriate activity to incentivise.
The focus on incentivising the TAO to meet the rolling plans agreed with the
TSO remain relevant and useful, recognising the risks associated with the
TAO only being rewarded if it beat the target for outage days.
By adding flexibility for the TSO and TAO to work together to agree short-term
variations to the outage plan which are both value-creating for the market and
can be accommodated by the TAO at reasonable cost, CRU considers that it
is increasing opportunities for beneficial outcome for customers. Further, it is
reasonable to permit the TAO to retain a share of the realised benefits
through the proposed “cost uplift”.
It should be noted that the framework also places an obligation on the TSO to
make efficient choices on when to request a variation, and whether to take up
the offer made by the TAO. The value-for-money of this arrangement will be
monitored over time, and will be a factor in determining whether this type of
scheme continues beyond PR4.
4.5 Stakeholder engagement
Objective
CRU’s objective in putting in place an incentive mechanism for stakeholder
engagement by the TSO is to enable the potential benefits of effective stakeholder
engagement to be realised in practice. It reflects that innovation in how stakeholders
are communicated with, and how their input is used to improve how network services
meet the needs of stakeholders has significant potential value, but is inherently difficult
to quantify. Hence, without an incentive mechanism there is a risk of “under-
investment” in stakeholder engagement.
Proposal 8
The stakeholder engagement incentive will be common across the DSO, TSO and
TAO. This will give CRU the option to compare methods, engagement, and outcomes
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
26
between network companies. The CRU will place an obligation on the network
companies to put in place a stakeholder engagement strategy, to be reported on
annually. The annual report should include submission of evidence to demonstrate
effective and successful engagement.
The annual stakeholder engagement submission will be assessed by CRU. To ensure
a balanced assessment of consumer needs and engagement, the CRU may
complement its own evaluation with input from input from other parties, e.g. a
stakeholder panel or panel of independent experts. Through this process, CRU will
assess merits of the stakeholder engagement strategy, the delivery of the strategy
over the preceding year, and the implementation of methods to improve stakeholder
engagement in future.
The stakeholder engagement incentive will be reputational in year 1 (2018), with no
financial reward or penalty associated with performance. The results of the CRU
assessment may include insights from the stakeholder engagement panel, will be
published.
Following the first assessment year, the CRU will consider whether a financial
incentive should be introduced for the stakeholder engagement incentive. Any
financial value attached to this incentive will be re-distributed from the other DSO
incentives, therefore maintaining the total incentive value at risk/reward under PR4.
Reasoning
The key reasoning for the proposal can be summarised as follows:
The intention of the new stakeholder incentive is to provide a clear framework
for the CRU to assess the measures taken by the TSO, and the other network
companies, to understand and address the needs of stakeholders – in an
environment in which the energy sector, and hence what different
stakeholders might need, is in a process of transformation.
A consistent assessment approach across network companies will give both
the CRU and the network companies the opportunity to learn from industry
good practice and continually improve engagement methods. It also provides
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
27
a platform for the network companies to demonstrate their efforts and success
in these areas.
Stakeholder engagement benchmarking is an approach that Ofgem has
developed as part of the RIIO package of price control incentives (specifically
the Stakeholder Engagement (and Consumer Vulnerability) Incentive).10
Ofgem employ a panel to advise on DNO performance, based on a set of pre-
defined objectives. The limited number of network companies in Ireland
reduces the competitive pressure compared to GB. The consistent
application of the CRU’s stakeholder engagement incentive across all network
companies will go some way to address this.
The “reputation only” status in year 1 will provide an environment in which the
assessment framework can be developed and tested collaboratively with the
network companies, and stakeholders before any revenue is put “at risk”. The
expectation, however, is that the quality of stakeholder engagement will be
subject to financial incentives at some point. In a period of rapid energy
sector change, it is important that the TSO, TAO and DSO/DAO prioritise how
they communicate to, and work with, stakeholders.
4.6 Delivering against strategic objectives
Objective
CRU’s objective in putting in place a strategic incentive is to create a mechanism to
allow the TSO to retain a share of the value to the market (and, by extension
customers) if the TSO outperforms what might reasonably be expected in specified,
strategically important areas. There areas relate, in various ways, to the ability of
different parties to participate in the markets for energy, capacity and system services.
Proposal 9
The mechanism is calibrated around a total value of €5m, spread evenly across each
10 Information on Ofgem’s website: https://www.ofgem.gov.uk/publications-and-updates/direction-issuing-stakeholder-engagement-and-consumer-vulnerability-incentive-guidance-riio-ed1
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
28
of the years 2017 to 2020 – as per the PR4 Decision. It will have the following
features:
The TSO will make an annual application to CRU, supported by evidence.
The evidence will set out how (and to what extent) its actions in the calendar
year have accelerated the following:
o The implementation and efficient operation of ISEM,
o The allocation of non-firm access rights to new generation,
o The upgrading of access right from non-firm to firm,
o The participation on the demand-side in the provision of services,
o The dynamic adjustment of permitted transfer capabilities in
circumstances that would otherwise cause constraints,
o The ability to accommodate an increasing proportion of non-
synchronous generation within the total generation mix.
If in the view of the CRU the evidence is consistent with the accelerated
delivery of high-value outcomes for the market and consumers, then the
incentive payment for that calendar year will be provided for in the CRU’s
setting of transmission tariffs.
If in the view of the CRU the evidence is reflective of performance that could
have reasonably been expected, given the TSO pre-existing obligations and
revenue allowances, then the incentive payment for that calendar year will not
be provided in the setting of tariffs.
The CRU reserves the right to consult prior to forming a view, based on the
evidence submitted by the TSO.
Reasoning
The key reasoning for the proposal can be summarised as follows:
The power system that that TSO is operating, and the market arrangements
which sit alongside that power system, are in a period of rapid change. The
TSO has a key role to facilitate and manage this process change, and in
some areas actively leading it. Further, it is difficult to define specific KPIs
that will accurate and comprehensively capture the quality of the TSO’s
performance in this regard. However, the value at stake for the market and
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
29
for consumers is significant. Hence, some form of incentive mechanism
appears to be appropriate.
Further, any incentive payment should be matched by demonstrable evidence
of delivering outcomes consistent with strong performance, in the areas that
matter to the market and consumers. In addition, the outcomes consistent
with such “performance bonuses” should be clearly over and above what
might reasonably have been expected under business-as-usual.
The proposed approach, based on an evidence-based assessment against
identified strategic objectives with a maximum incentive payment of €5m in
total, is in CRU’s view a reasonable and proportionate incentive for the TSO
to respond to.
4.7 Innovation
Objective
CRU’s objective in putting in place a more formal process is to track the use by the
TSO of innovation projects to help support and accelerate progress against the
strategic objectives. This process will also be a vehicle to consider the case for
additional funding for innovation projects, over and above the sums already provided
or adequately incentivised for under PR4.
Proposal 10
CRU propose a common approach across transmission and distribution to monitor,
and where appropriate incentivise, innovation by the TSO and DSO. It is based on
annual reporting on initiatives being progressed pursuant to an innovation strategy,
complemented by a layer of assessment by the CRU, where a case for incremental
funding is being made – or where assessment of the value-for-money of funded
projects is appropriate. In the context of the TSO, this translates to the following:
Annual submission: A report to the CRU on how available funding for
innovation has been used, with evidence on (i) projects being initiated, (ii)
projects that are in progress, and (iii) projects that have completed. In this
context, the CRU will expect evidence proportionate to the level of funding in
respect of:
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
30
o Systems and process that ensure that projects are sufficiently
innovative – and do not, for example, reflect business-as-usual
activities or projects to capture internal cost-savings through the
deployment of proven technology (which the TSO already has
incentives to deliver)
o How partnerships and external input are being used to shape
innovation projects and deliver of innovation projects
o How learnings are being transitioned into BAU activities, or the
specification of further innovation projects.
Potential for additional funding: The scope for the TSO to include, in its
report on innovation performance, a business case for additional funding for
new projects. This must include rationale for why the project is innovative, the
nature of the potential benefits at stake, and a description of how the project
will be managed, reported on and evaluated. If the application is accepted by
CRU, then reporting on progress will be folded into the proposed annual
process.
Reasoning
The key reasoning for the proposal can be summarised as follows:
There are existing provisions under PR4 for the TSO to progress innovation
projects. While the funding is set at a relatively low level currently, it is still
important to have a degree of transparency over how this funding is being
used. The proposed approach is proportionate to this objective, and
consistent with the approach being proposed for the DSO.
The proposed approach also has the ability to flex if additional funding for
innovation is made available, either through the annual reporting process and
the submission of a business case by the TSO, or through the PR5 process.
The ability to increase the funding made available to the TSO ensures that
initiatives can be progressed quickly if a strong case can be made. But also
that there are sufficient safeguards in place when initiating new projects and
tracking progress over time to provide comfort for consumers that value-for-
money is being safeguarded.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
31
4.8 Consultation question
2. Do you have any comments on Proposals 4-11 and CRU’s supporting
reasoning, including but not limited to the following aspects:
a. The mix of new and retained incentive mechanisms, and how they relate
to the key areas of TSO and TAO behaviour for market participants and
consumers
b. The proposed change in the approach to setting incentives for
investment planning and delivery, based on assessment against a
broader range of criteria and evidence than under the existing
mechanism
c. The choice of key strategic objectives and associated outputs for the
TSO to be rewarded for exceptional performance.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
32
5. Distribution – reporting
In this section we set out and invite views on proposals for reporting applying to ESB
Networks as DSO/DAO, for the period 2018 to 2020. In developing these proposals,
CRU is also seeking to put in place arrangements that can endure, subject to review
and refinement as part of the PR5 process.
5.1 Output measures
Objective
CRU’s objective in revising the framework of reporting for Distribution is to increase
transparency for all stakeholders on what is being delivered over time by the
DSO/DAO in return for the revenues being made available. Further, to ensure that
relevant information is easy to access and interpret – and capable of adapting over
time to continue to ensure reporting on the full range of ways in which actions by the
DSO/DAO impact on stakeholders.
Without a robust framework for reporting, there is a risk that consumers, stakeholders
and CRU cannot easily discern how the DSO/DAO is performing – and hence are less
able to hold it to account, or understand the levels of performance that it is reasonable
to expect. This could, over time, constrain the quality of regulatory decision-making on
behalf of consumers.
Proposal 11
CRU proposes a new reporting framework for Distribution based on improving the
completeness, usefulness and accessibility of the existing Annual Performance Report
(APR). This approach will be applied consistently across both transmission and
distribution. The proposal as it applies to the DSO can be summarised as:
To re-state the required format and content of the APR, to make it more useful
and accessible for stakeholders. This will be given effect by CRU setting new
principles for the APR11, and for the DSO/DAO to undertake a review of
11 Pursuant to Condition 13 and 17of the DSO licence.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
33
changes needed to meet the new principles. The finding of this review would
be considered for approval by CRU, and then reflected in the APRs for 2017
(published in mid-2018).
The updated principles proposed by CRU are designed to ensure that the
APR is updated to make its content more comprehensive and relevant, and to
make its format easier for stakeholder to access the information. Draft
principles are set out in Annex 2.
Reasoning
CRU has come forward with this model based on analysis of how the current
arrangements perform, and might be expected to continue to perform, against the
objective above, and background research into how output-based reporting is given
effect in other relevant jurisdictions.
The key document in the current framework is the APR prepared by DSO pursuant to
Condition 13 and 17 of its licence. This document should provide a broad, accessible
summary of performance. But in practice, there are weaknesses and limitations:
The document has the “look and feel” of a regulatory submission or
compliance document, rather than a document that might meet the needs of a
stakeholder seeking a clear, concise and comprehensive review of the
performance of the DSO in context.
Some aspects of DSO performance are reported in disproportionate detail,
while other areas where the performance of the DSO has significant impacts
on the market or consumers are reported in a relatively superficial manner.
While the CRU recognises that this reflects in part the historic development of
KPIs in different areas of activity, it also considers that the case for an update
to improve the completeness and usefulness of the APR is strong.
Some observations on the accessibility and usefulness of the DSO’s APR in
its current form:
o Relative to the TSO, the document itself is much easier to find on the
ESB Networks website. A section on Performance Reports is visible
on the landing page of the ESB Networks library, and this takes the
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
34
reader to an archive of all past reports starting with the most recent.
Although at the time of writing, the 2016 report was not present.
o Relative to the TSO, the document also provides more information for
the reader to understand performance in context, e.g. over time.
o However, as with the TSO, the reporting on how much network
investment has been undertaken, and why, is limited. There is a bullet
list of completed large projects, with limited commentary plus some
data tables on volume and value of investment in different areas. It is
difficult for the reader to understand whether this constitutes good
performance, or not, why these projects were needed, what benefits
they delivered, why they represented the most appropriate mix of
projects, and whether they were delivered on time and to budget.
o A significant proportion of the report is taken up with data tables in
respect of 44 individual Service Level Agreements (SLAs) relating in
various way to the quality and timeliness of metering-related services
provided to the market. While this is relevant information, it lacks
context, e.g. on whether performance overall is improving or not.
Volumes of activity under each SLA are also not reported.
o There are number of areas of activity that are not included in the APR,
which might reasonably be expected to be included: innovation;
engagement with stakeholders; worst-served customers; progress on
the National Smart Metering Programme (NSMP).
The choice of formatting and language, and the extent to which information
and data are provided to help understand the broader context for
performance, can be improved for the purpose of helping a reader understand
and access information easily. This applies to the reports prepared by the
DSO, TSO and by the TAO.
5.2 Consultation question
3. Do you have any comments on Proposals 11 and CRU’s supporting reasoning,
including but not limited to the following aspect:
a. The objective of a more comprehensive, user-friendly DSO performance
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
35
report, and which particular aspects of DSO behavior or performance
are under or poorly-reported on currently in the APR.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
36
6. Distribution – incentives
In this section we set out and invite views on proposals for incentive mechanisms
applying to ESBN as DSO/DAO, for the period 2018 to 2020. In developing these
proposals, the CRU is also seeking to put in place arrangements that can endure,
subject to review, refinement and updating as part of the PR5 process.
The CRU’s overarching objective in proposing these mechanisms is to ensure that the
performance targets against which the DSO is incentivised are based on the most
appropriate and up-to-date data. Further, that incentives are targeted on the DSO
behaviours that matter most to network users and ultimately consumers. The
proposals have also been calibrated such that, in aggregate, the financial exposure for
the DSO/DAO is consistent with the PR4 Decision.
6.1 Unplanned outages
Objective
CRU’s objective in putting in place an incentive mechanism for unplanned outages is
to give the DSO/DAO an appropriate financial stake in maintaining appropriately high
standards of supply reliability. It reflects the high value of supply reliability to
consumers, and that behaviours of the DSO/DAO can be a significant influencing
factor on reliability outcomes.
Proposal 12
CRU propose to retain the core mechanism that has been in place during PR3,
updated for new information on the levels of performance achievable by the DSO. We
seek views on whether, and how, exclusions for unplanned outages associated with
extreme weather should be given effect. The key features of CRU’s proposal are:
Target levels for Customer Interruptions (CI) and Customer Minutes Lost
(CML), will be based on the target performance for 2015. See Annex 4 for
further details.
Deviations around these performance targets at the same levels as used in
the PR3 scheme, with the same broad structure of caps and collars.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
37
The adoption of an alternative method of excluding the effects of storm events
for the purposes of measuring supply continuity.
To exclude planned outages from the incentive mechanism, and reposition
this element of the DSO’s performance as being subject to a reporting-based
“reputational” incentive.
Reasoning
The key reasoning for the proposal can be summarised as follows:
Unplanned interruptions in supply can impose significant costs and
inconvenience on customers, and it is appropriate for (a) high standards to be
set for the DSO, and (b) the DSO to have a proportionate financial stake in
outcomes, both positive and negative. Further, the structure of incentive in
place during PR3 has delivered improvements over time, and is in line with
international good practice in its design and use of metrics.
The use of the most recent performance data to recalibrate the scheme
ensures that targets continue to be reasonable, but challenging – based on
actual data on what level of performance can, on average, deliver.
The proposed changes to the rules around how supply interruptions during
storm events are treated seeks to address two points.
o First, by more accurately identifying and excluding supply interruptions
associated with storms we can more accurately incentivise the DSO’s
performance in “normal” conditions. This is not to say that measures to
increase the resilience of supply during storms is unimportant. But by
not excluding storm events, out-turn performance in any given year
would be unduly influenced by whether or not there were storms – a
situation that the DSO has no control over. This effect could easily
“swamp” other effects, potentially diluting or removing the incentive
properties of the scheme.
o Second, by adopting a methodology which aligns to practice in other
jurisdictions, it makes the DSO’s performance easier to benchmark
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
38
against other DSOs over time. This will improve the information
available to CRU is setting targets in the future.
The proposal to focus the financial incentives solely on unplanned
interruptions, and to reposition the DSO’s performance on planned outages as
a “reputational” incentive is driven by the following: First, the costs and
inconvenience imposed by planned outages (where customers are notified in
advance) are lower than for unplanned outages, hence there is a case for
giving unplanned outages a lower weighting in any given incentive scheme12.
Second, the reputational stake for the DSO in managing planned outages
efficiently and meeting its targets is high – hence the addition of a financial
element might well have a limited additional impact on actual outcomes.
Third, there are other areas of DSO performance where the use of financial
incentives might be expected to a more direct impact on outcomes, e.g.
Worst-Served Customers.
6.2 Worst-served customers
Objective
CRU’s objective in putting in place an incentive mechanism for worst-served
customers is to improve outcomes for those households and business who would
otherwise have a sustained and materially lower standard of supply reliability. It
reflects a desire to introduce a greater degree of social fairness into the outcomes that
would otherwise prevail if investments to improve supply reliability were chosen on the
basis of narrow economic cost-benefit alone.
Proposal 13
The Worst-Served Customer (WSC) incentive under PR4 will introduce a mechanistic
assessment of ESBN’s progress to address worst-served customers. The incentive
mechanism was proposed by ESBN.
As part of the PR4 settlement, ESBN was awarded capex to fund a continuity
12 The comparable scheme in place in Australia’s National Electricity Market, for example, places a weighting of zero on planned outages, i.e. only unplanned outages are subject to financial incentives.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
39
improvement programme during PR4. €1.4m of this funding is associated with
improving supplies to the DSO’s worst served customers. The allowance under PR4
is designed to improve supply for 2,000 customers. ESBN has indicated that an
increase in funding to €6.7m for its WSC programme would be sufficient to expand its
programme to benefit 6,000 customers. We propose that this funding is increased.
Alongside the programme funding, CRU proposes to introduce an incentive to ensure
ESBN faces strong financial incentives to deliver against the programme. The WSC
incentive will be symmetrical with a dead-band set at 70-80% (which equates to 70-
80% of the target volume of 6000 customers receiving a 20% improvement in
reliability). The total downside penalty for ESBN will be aligned with the total value of
the funding available for the WSC programme. Where success falls below 70%, the
value of the incentive will reduce on a straight-line basis such that zero success
means the incentive penalty is equal to the initial funding awarded (i.e. ESBN receive
no funding).
The symmetrical nature of the incentive means that should ESBN successfully deliver
reliability improvements to more than the target volume of customers, i.e. greater than
80% success rate, they will receive an incentive reward. The incentive rate per
customer will be symmetrical for under and over performance. This provides a strong
incentive for ESBN to exceed the customer volume target, and overachieve against
the incentive. The upside will be capped at €6.7m, the total value of the fund.13
Reasoning
Under PR3, CRU made a fund of €10m available to ESBN to improve the service to
worst served customers. The fund was not included in the DSO revenue and
therefore spend was subject to approval by CRU. Only a fraction of the fund was
applied for during PR3.
The risk/reward mechanisms introduced for the remainder of PR4, provides a stronger
incentive for ESBN to work to improve services for worst-served customers. The
13 This means that if ESBN exceeds the 6000 customer target, improving reliability by greater than 20% for 9000 customers, ESBN will receive the full incentive upside of €6.7m.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
40
incentive is set such that the full value of the fund is available to ESBN where the
customer target is met. Equally, the symmetrical nature means that ESBN can lose all
funding where action does not result in an appropriate increase in service levels for
worst-served customers.
A key element of the incentive is that it is calibrated such that value of capital
programme funding should reduce to zero where no action is taken by ESBN (i.e. the
total penalty should equal the cost of the programme). In addition to this core
principle, we have considered the following incentive options:
- Symmetrical or asymmetrical incentive: Should the incentive provide both
penalty and reward for ESBN? An upside incentive reward could be introduced
through a financial reward where ESBN delivers an improved service to more
than the targeted volume of customers (where “success” is defined as a 20%
improvement in a targeted customers’ network reliability being seen over the
three years subsequent to intervention).
- Dead-bands around a target performance: Should there be a level of
success which results in no reward or payment through the WSC incentive, i.e.
where ESBN receives full funding but no additional incentive payment or
reward? This acknowledges that success for some customers may be harder
to achieve than others.
6.3 Customer service
Objective
CRU’s objective in putting in place an incentive mechanism for customer service is to
give the DSO/DAO an appropriate financial stake in maintaining appropriately high
standards of service. It reflects that customers and market participants rely on the
quality of services provided by the DSO/DAO, and they do not have the option of
choosing an alternative service provider in response to poor service quality.
Proposal 14
For PR4, the CRU will maintain the PR3 incentives, specifically the overall customer
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
41
satisfaction survey14 and Customer Satisfaction metrics (Networks Customer Contact
Centre metrics). Combined, these incentives provide a comprehensive assessment of
ESBN customer’s perceptions of services regarding planned and unplanned outages,
connection and voltage complaints (through the overall customer satisfaction survey)
and direct engagement with customers through the customer call centre. These
incentives remain fit for purpose for PR4.
The DSO incentives were not in force for the first two years of PR4 (2016 and 2017).
The incentive value caps have therefore been re-distributed to the remaining years of
PR4 so that the overall value at risk/reward for the DSO is maintained. The overall
incentive package for the DSO is explained in Section 7.3.
For Customer Satisfaction, the CRU proposes to maintain the incentive cap at +0.25%
and -1.00% of annual Allowed Revenue. This provides a strong incentive to meet the
PR4 targets. The Customer Satisfaction performance targets for the remainder of
PR4 are set out in Table 3. The target performance levels have been recalibrated,
based on PR3 outturn performance (taking the average performance during PR3 as
the target for PR4). This reflects ESBN’s actual outperformance against the Customer
Satisfaction incentive for PR3.15
Table 3 Customer Satisfaction – Incentive components and performance targets
Weight 2016 2017 2018 2019 2020
Speed of Telephone Response 25% - - 88% 88% 88%
Call Abandonment Rate 25% - - 4% 4% 4%
Customer Call-Back survey results 20% - - 83% 83% 83%
Mystery Caller survey results 15% - - 88% 88% 88%
First Contact/Call Referral 15% - - 10% 10% 10%
ESATRAT16 (Performance target) 100% - - 90% 90% 90%
Reward/Penalty per % point from Target)
- - - €0.72m €0.72m €0.72m
For the overall customer satisfaction survey, the total revenue at risk/reward for PR4
14 More Commonly known as the RedC survey 15 Based on ESBN’s submission to CRU. 16 As defined in CER/06/107
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
42
will be aligned to PR3 (equal to +/-€1.6m, €2009). During PR3, ESBN exceeded the
74% overall customer satisfaction survey target significantly in all years (PR3 annual
results ranged from 80.1%-83.8%). The overall customer satisfaction survey target for
17PR4 has been increased to reflect the strong performance against this incentive in
PR3 (the PR4 target is based on the average performance during PR3).18 This higher
target will ensure continued performance improvements in the DSOs approach to
customer engagement. Setting the target at 81% still provides a strong incentive for
ESBN to outperform the target and receive the full revenue reward available during the
remaining years of PR4.
Table 4 Overall customer satisfaction survey – PR4 incentive Performance targets
2016 2017 2018 2019 2020
PR4 target - - 81% 81% 81%
Reward/Penalty per % point from Target)19
- - €0.72m €0.72m €0.72m
Reasoning
The customer service incentives are core elements of the DSO incentive package.
The DSO has a central responsibility to its customers and should therefore take every
effort to continue to improve customer services. Performance targets under PR3 were
easily achieved under both of the customer services incentives. This results in
payments to ESBN. To ensure a continued improvement in performance, the
incentive targets for PR4 are more stretching, based on average performance
observed during PR3. The total value of the incentives are unchanged, providing
ESBN with a strong incentive to continue to deliver customer service through the
remainder of PR4.
6.4 Metering – traditional
17 the payment to be made to or by the DSO (in €) per 1 percentage point deviation between actual
and target performance 18 Based on ESBN’s submission to CRU. 19 the payment to be made to or by the DSO (in €) per 1 percentage point deviation between actual
and target performance
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
43
Objective
CRU’s objective in putting in place an incentive mechanism for metering is to give the
DSO/DAO an appropriate financial stake in providing customers and market
participants with a regular supply of accurate metering data on which to bill. It reflects
that inaccurate billing imposes costs and inconvenience on suppliers and customers,
and that the DSO/DAO is the monopoly provider of metering data.
Proposal 15
For PR4 the existing traditional metering incentive will remain for the DSO. There are
Service Level Agreements (SLA) in place for PR3 which were subject to financial
incentives. These included:
98% of meters should have 1 reading (DSO or customer) per year
99% of meters will not have back to back block estimates.
The PR3 incentive rate for both incentives will be maintained for PR4. This will be set
at €0.1m per 0.1% deviation from the target (with a 0.2% dead-band, whereby no
incentive payments are made, for the first metering incentive only). The total value
(cap and collar) of the metering incentive will also be retained at +/-€1m (2009).
The PR4 incentive targets for the DSO will be aligned with those in place for PR3.
The targets under PR3 were stretching for ESBN and we consider these appropriate
for PR4.
The DSO incentives were not in force for the first two years of PR4 (2016 and 2017).
The incentive value caps have therefore been re-distributed to the remaining years of
PR4 so that the overall value at risk/reward for the DSO is maintained. The overall
incentive package for the DSO is explained in Section 7.3.
Reasoning
The traditional metering incentives are core elements of the DSO incentive package.
They drive network company behavior that is desirable for consumers, and for the
CRU. The implementation of the National Smart Metering Policy will change metering
policy in the medium-term, and will be incentivise separately, as explained in Section
6.5. In the short-term, and for the remainder of PR4, the traditional metering incentive
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
44
remain applicable for ESBN.
6.5 Metering – smart
Objective
CRU’s objective in putting in place an incentive mechanism for smart metering is to
give the DSO/DAO an appropriate financial stake in delivering its part of the revised
plan for the National Smart Metering Programme (NSMP). It reflects that customers
and market participants are reliant on DSO/DAO’s delivery before the benefits of smart
metering can be realised in full.
Proposal 16
CRU proposes a new incentive mechanism linked to the DSO’s delivery of smart
metering services to market participants, and by extension consumers. The proposed
mechanism is similar in design to the proposed incentive for unplanned outages, in
that it will reward or penalise ESBN based on whether or not it meets target outcomes.
The outcomes are calibrated to the revised delivery plan that the DSO has notified to
the CRU.
The key features are:
A target profile of “smart meter delivery days” for 2019 and 2020.
A “delivery day” being equal to the provision of the requisite level of smart
metering services to one meter for one day.
The “requisite level of smart metering services” being characterised in two
distinct ways in the period to the end 2020. First, in the preparatory phase of
smart meters being installed but not operational, the presence of an installed
“smart ready” meter will equate to “delivery”. Second, in the phase when the
functionality has been switched on to retrieve data from smart meters and
make it available to the relevant Supplier and customer, then the requirement
for “delivery” will increase commensurately.
The target profiles being set are consistent with (a) 250,000 meters being
installed over the course of 2019 and 2020, and (b) that stock of meters
operating with phase 1 functionality by Q4 2020.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
45
A 50% weighting being attached to each of (a) and (b) in the financial
incentive to deliver.
The scheme parameters set such that if (a) and (b) are met (within a
reasonable range of tolerance), then the financial outcome for the DSO is
equivalent to earning its regulated cost of capital on the assumed capex for
this phase. Further, for the impact of non-delivery against these metrics being
capped at a level consistent with the DSO earning its regulated cost of debt
on the assumed capex for this phase.
The option for the DSO to apply for a “grace period” of no more than six
months, if for reasons outside the control of the DSO the delivery of (a) and/or
(b) have been delayed. If the application is accepted by the CRU, then
delivery within the “grace period” would be deemed to be delivery on time.
An option for the DSO to earn an enhanced rate of return if the stock of
meters installed and operating with phase 1 functionality by Q4 2020 is
greater than 250,000.
Reasoning
A key reasoning for the proposal can be summarised as follows:
The DSO’s preparations for the delivery of its component of the NSMP have
been ongoing for a number of years, and have been funded by customers.
Further, the revised plan for delivery has been developed in large part by the
DSO, in consultation with CRU and other stakeholders. Hence, it is
reasonable to assume that the delivery plan should be capable of being
adhered to.
There are substantial benefits at stake for consumers and for market
participants through delivery of the NSMP, and significant costs for market
participants in managing their own readiness. The relatively high value
associated with the proposed incentive is, in the view of CRU, proportionate.
The proposed mechanism is focused on the measurable delivery of outputs
that impact directly on customers and market participants. CRU consider that
an output-based mechanism is more appropriate than, for example, a regime
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
46
based on the DSO’s progress against interim milestones – in seeking to
promote clear accountability, and to drive efficiency in delivery by the DSO.
The option for the DSO to apply for a “grace period” reflects that not all factors
influencing delivery are within the control of the DSO, e.g. there will be a role
for Suppliers to enable the rollout of smart-ready meters and in being ready to
operate phase 1 functionality themselves. Hence a degree of flexibility might
be appropriate, if there are mitigating factors.
6.6 Stakeholder engagement
Objective
CRU’s objective in putting in place an incentive mechanism for stakeholder
engagement by the DSO/DAO is to enable the potential benefits of effective
stakeholder engagement to be realised in practice. It reflects that innovation in how
stakeholders are communicated with, and how their input is used to improve how
network services meet the needs of stakeholders has significant potential value, but is
inherently difficult to quantify. Hence, without an incentive mechanism there is a risk
of “under-investment” in stakeholder engagement.
Proposal 17
The stakeholder engagement incentive will be common across the DSO, TSO and
TAO. This will give CRU the option to compare methods, engagement, and outcomes
between network companies. The CRU will place an obligation on the network
companies to put in place a stakeholder engagement strategy, to be reported on
annually. The annual report should include submission of evidence to demonstrate
effective and successful engagement.
The annual stakeholder engagement submission will be assessed by CRU. To ensure
a balanced assessment of consumer needs and engagement, the CRU propose to
appoint a stakeholder engagement panel to assist with the evaluation. The panel
would advise the CRU on the merits of the stakeholder engagement strategy, the
delivery of the strategy over the preceding year, and the implementation of methods to
improve stakeholder engagement in future.
The stakeholder engagement incentive will be reputational in year 1, with no financial
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
47
reward or penalty associated with performance. The results of the CRU assessment,
which will include insights from the stakeholder engagement panel, will be published.
Following the first assessment year, the CRU will consider whether a financial
incentive should be introduced for the stakeholder engagement incentive. Any
financial value attached to this incentive will be re-distributed from the other DSO
incentives, therefore maintaining the total incentive value at risk/reward under PR4.
Reasoning
Stakeholder engagement is currently a core activity for the DSO. Stakeholder
engagement across the industry is however disjointed. The distinction in roles
between network companies can be unclear, and this can be exacerbated by
inconsistent communication and engagement strategies.
The intention of the new stakeholder incentive is to provide a clear framework for the
CRU to assess the measure taken by ESBN, and the other network companies, to
understand and address the needs of customers. A consistent assessment approach
across network companies will give both the CRU and the network companies the
opportunity to learn from industry good practice and continually improve engagement
methods. It also provides a platform for the network companies to demonstrate their
efforts and success in these areas.
Stakeholder engagement benchmarking is an approach that Ofgem has developed as
part of the RIIO package of price control incentives (specifically the Stakeholder
Engagement (and Consumer Vulnerably) Incentive). Ofgem employ a panel to advise
on DNO performance, based on a set of pre-defined objectives. The limited number of
network companies in Ireland reduces the competitive pressure compared to GB. The
consistent application of the CRU’s stakeholder engagement incentive across all
network companies will go some way to address this.
6.7 Strategic and innovative thinking
Objective
CRU’s objective in putting in place an incentive mechanism for strategic and
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
48
innovative thinking by the DSO/DAO is to encourage and reward the DSO/DAO for
actively, and imaginatively, tackling the sizeable challenges associated with the
transition to a low carbon energy system – including the accommodation of distributed
and micro-generation, storage and more active management of demand. It reflects
that the DSO/DAO has an important role in articulating the variety of commercial and
technical challenges, and working with market participants, the TSO, the TAO and
other stakeholders to develop and test practical, workable solutions.
As indicated by the CRU in the PR4 decision, the innovation will be funded through
PR4 via the Strategic Innovation Fund (SIF) – providing funding for research,
development, demonstration and adoption of innovative technology, as well as
operating and commercial arrangements.
The value of the SIF for PR4 is set at €100m. The size of the fund reflects the scale of
challenge in the short-term (i.e. to 2020), and the significance of the consumer benefit
from the successful delivery of innovation.
Proposal 18
Funding under the SIF will take place under a clear submission and assessment
framework. An annual assessment will be completed by CRU to determine the quality
of the process to identify innovation20, the efficiency in the delivery of innovative
projects and the way that projects learnings or outcomes have been used by ESBN.
This three stage assessment will be as follows:
1. The quality of the ESBN processes that generate, prioritise and specify
projects: For example, are the projects identified consistent with the aims of
the strategy? Is the innovation clearly separable to Business-as-usual? Is the
mix of projects balanced and complete relative to the stated aims of the
strategy? How is internal and external data and evidence used to generate
potential projects?
2. The efficiency of delivery: Have the projects in the pipeline been delivered
20 Innovation areas may also be identified by CRU and proposed to ESBN for assessment. Under this approach, ESBN would need to consider the merits of innovation in these areas, and include their assessment as part of the annual reporting process.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
49
efficiently, or are on track to deliver in future (noting that some projects will take
some time to implement)? Are there appropriate management controls in
place? Is the input of partners or other external parties being managed well?
Are the projects being well communicated?
3. Use of learning/outcomes: How effectively/efficiently has ESBN captured and
made use of the learnings from innovation? What are the internal processes to
make this happen? What are the examples, and what have the impacts been
(across all types of findings, including when projects did not deliver the desired
outcomes)?
This evidence should be submitted to the CRU on an annual basis. It will be used by
the CRU to inform a balanced scorecard assessment, resulting in a score of
strong/adequate/weak for the year.
To support the innovation submission, the CRU expect to see economic and
assurance methods applied by ESBN to demonstrate standard of performance. For
example the use of Cost-Benefit Analysis (CBA), where appropriate, to demonstrate
welfare benefits; collaboration with third parties to demonstrate validation of
innovation; and the option to include third party assurance of the process to
demonstrate efficiency in delivery. The score over the remainder of PR4 will then
determine ESBN’s revenue reward through the SIF.
Evidence on learnings/outcomes will be contingent on where individual projects have
got to in their lifecycle. The purpose of this framework is to assess, with evidence, the
quality of what could reasonably have been expected to be present during any
particular 12-month period.
In evaluating the SIF allowances for the PR4 period the CRU will take into account the
consumer value delivered and retained. The evaluation of ESBN’s innovation
activities, and the link between this evaluation and the SIF, is designed to be broad-
based. In CRU’s view, this means that all innovation projects being delivered and
learned from during PR4 should be within scope. This includes projects where the
original funding pre-dates PR4, such as the PR3-funded Electric Vehicle R&D Pilot.
For PR4, SIF allowances for 2018, 2019 and 2020 will be assessed, with a total value
of €60m. The value under assessment will be structured as follows:
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
50
A “strong” score across the assessment areas, for all years in PR4 would
result in the full allowance (€20m per year for 3 years)
An “adequate” score would result in a €5m being held back each year
A “weak” performance would result in €15m being held back each year.
Reasoning
There is already some innovation underway as part of PR4, and earlier price review
periods. Innovation is currently funded through the main Price Review revenue
allowances. The SIF was introduced to respond to the step-change in innovation
spend that is required to keep pace with industry and technology change. The nature
of innovation spending, and in particular the risk and uncertainty inherent in investing
in untested projects or trials, calls for a process that recognises these risks and
possible rewards. Without a dedicated and clear investment route, there is a risk that
socially beneficial innovation investment is not progressed to the detriment of
consumers.
The Electric Vehicle R&D Pilot received funding of €25m under PR3 and the pilot
concluded in PR4. As outlined in CRU/17/283 ESBN is due to submit a final report on
the Pilot and a plan for the assets (in terms of preparation for sale and maintenance in
the interim). As this was a significant innovation investment by the DUoS customer this
will provide the CRU with valuable insight into the ESBN’s approach to such project’s
and the likelihood of strong performance in current and future innovation projects,
hence it will be a valuable input into the evaluation. It is also noted that as the SIF is
intended to deliver on-going and long-term benefits to consumers a key aspect of the
assessment will be how well ESBN maintains and extracts value from learnings and
physical assets acquired during an innovation project – such as the Electric Vehicle
R&D Pilot.
The SIF design provides a clear framework for innovation investment for ESBN. The
assessment and reward will be aligned with outcomes that are valuable for consumers
– i.e. socially beneficial projects that are demonstrably not business-as-usual activities
for the DSO (and therefore funded elsewhere in the Price Review). It will reward
ESBN for innovative projects that are supported and validated by third parties, further
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
51
reinforcing the wider value of innovation. The size of the fund, and costs to ESBN of
sub-standard performance, will provide a strong financial incentive to drive these
behaviours.
The SIF design builds on successful innovation stimuli in GB and across Europe. The
principles of collaboration, third party validation and auditing performance are
embedded in Ofgem’s network innovation framework and stakeholder engagement
incentives.
Through setting the SIF objectives, both the CRU and ESBN will have the opportunity
to identify innovation areas that are deemed valuable to consumers. Where these
areas are identified by CRU, ESBN will need to consider the evidence and benefits
assessment. Based on a current assessment of areas of potential benefit of
innovation, the CRU considers the following candidates 21for inclusion in the SIF:
Facilitating the participation of distribution connected generation in System
Services.
Facilitating the participation of Demand Side Units in System Services.
Increasing the number of sites that can participate in Demand Side Units
unrestricted.
Maximising the value to be recovered from the Electric Vehicle R&D Pilot.
6.8 Consultation question
4. Do you have any comments on Proposals 12-18 and CRU’s supporting
reasoning, including but not limited to the following aspects:
a. The mix of new and retained incentive mechanisms, and how they relate
to the key areas of DSO behaviour for market participants and
consumers
b. The proposed change to move performance against planned outages to
a reporting-based reputational incentive, and not focused on financial
21 this is a non-exhaustive list.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
52
incentives instead focused on improving outcomes for worst-served
customers
c. The case for the proposed new incentive on stakeholder engagement,
and types of engagement (and associated outcomes) it should seek to
encourage
d. The form and strength of incentive for the proposed new incentive
mechanism on smart metering delivery by the DSO.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
53
7. Incentives as a package
In this section we set out and invite views on how the component parts of our
incentives proposals combine financially as a package, for each of the TSO, TAO and
DSO.
For each network company, we present the total revenue at risk, i.e. the maximum
cost to the network company of poor performance, and the total revenue reward, i.e.
the maximum additional revenue that can be earned for out-performance.
7.1 TSO incentive package
The incentive package for the TSO includes elements of the PR3 incentive package
that are still relevant and will continue into PR4, and new incentives around
Investment Planning and Delivery, and Stakeholder engagement.
For PR4, the total value of the incentive revenue at risk/reward will be the same as for
PR3. For the TSO, this total incentive value is capped at +/-4% of annual internal
opex, around €2m per year with a total PR4 pot of under €10m (real 2014). This
operational incentive cap excludes the strategic incentive for the TSO, a €5m incentive
introduced for PR4 and explained in Section 4.6.
The total incentive revenue at risk/reward for the TSO over PR4 is shown in Table 5.22
For the TSO, the incentive cap is symmetrically applied over PR4. The values
presented in both tables are based on the published PR4 ex-ante opex allowances for
the TSO. These are indicative only. The actual incentive payments will be calculated
by CRU annually during PR4, and calculated in nominal terms.
22 The opex profile for the TSO shown in these tables is taken from the following CRU decision (Section 12.1): https://www.cru.ie/wp-content/uploads/2015/07/CER15296-Decision-on-TSO-and-TAO-Transmission-Revenue-for-2016-to-2020-1.pdf
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
54
Table 5 TSO incentive revenue at risk/reward for PR4
Incentives for the TSO (€m, 2014) 2016 2017 2018 2019 2020 Total
PR4 internal opex 46.70 47.80 47.20 45.50 45.80 233.00
System Minutes Lost 0.37 0.38 0.38 0.36 0.37 1.86
System Frequency 0.37 0.38 0.38 0.36 0.37 1.86
TSO Project Milestones 0.65 0.67 - - - 1.32
Delivery of Enhanced Network Capacity 0.47 0.48 - - - 0.95
Investment Planning and Delivery (NEW)23
- - 1.13 1.09 1.10 3.32
Stakeholder engagement (NEW)24 - - - - - TBD
Total 1.87 1.91 1.89 1.82 1.83 9.32
Percentage of internal opex 4.00% 4.00% 4.00% 4.00% 4.00% 4.00%
Explanation of the TSO incentives for PR4
This section of the consultation explains the rationale for the value of each incentive
for the TSO during PR4.
Transmission System Performance – System Minutes Lost and System
Frequency
The value and methodology for the PR4 System Performance incentives will
remain unchanged from PR3.
The incentive risk and reward will remain capped as +/-0.80% of the TSO’s
annual internal opex for System Minutes Lost and for System Frequency (with
a total of 1.60% for the System Performance incentives).
For the TSO, the operational incentives were not turned off for the TSO in
2016 and 2017 (unlike for the DSO where incentive revenue for 2016 and
2017 is re-distributed to the remainder of the PR4 period).
Transmission System Development
23 For further information on this incentive, please see Proposal 5 in section 4.2 24 For further information on this incentive, please see Proposal 8 in section 4.5
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
55
Under PR3, the TSO was subject to a ‘Project Milestone’ incentive and an
incentive on the ‘Delivery of Enhanced Network Capacity’. Together, these
incentives were capped at 1.40% and 1.00% of internal opex respectively.
For 2016 and 2017, these incentives will remain in place for the TSO.
Starting in 2018, these incentives will be replaced by the single ‘Investment
Planning and Delivery’ (IPD) incentive.
The total incentive cap on the Transmission System Development incentive is
unchanged between PR3 and PR4 at 2.40% of annual internal opex.
Over the whole of the PR4 period, the value of the TSO incentive risk/reward
cap for Transmission System Development will be unchanged (at 2.40% of
internal opex).
Stakeholder engagement incentive – new incentive for PR4
The stakeholder engagement incentive will be a new incentive common
across the TSO, TAO and DSO/DAO.
For 2018, the stakeholder engagement incentive will be reputational for all
parties.
From 2019, the incentive value will be set by the CRU based on a review of
the success of performance in 2018.
The revenue at risk/reward for the stakeholder engagement incentive for the
TSO will be re-distributed from the value available under the Transmission
System Performance, SML and SF, incentive.
The total incentive package value under PR4 for the TSO will be unchanged
to the proposal in this consultation.
7.2 TAO incentive package
The incentive package for the TAO includes elements of the PR3 incentive package
that are still relevant and will continue into PR4, and new incentives around
Investment Delivery, and Stakeholder engagement.
For PR4, the total value of the incentive revenue at risk/reward will be the same as for
PR3. For the TAO, the incentive package is capped at +/-5% of annual opex, around
€3m per year with a total PR4 pot of under €15m.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
56
The total incentive revenue at risk/reward for the TAO over PR4 is shown in Table 6.25
For the TAO, the incentive cap is symmetrically applied over PR4. The values
presented are based on the published PR4 ex-ante opex allowances for the TAO.
These are indicative only. The actual incentive payments will be calculated by CRU
annually during PR4, and calculated in nominal terms.
Table 6 TAO incentive revenue at risk/reward for PR426
Incentives for the TAO (€m, 2014) 2016 2017 2018 2019 2020 Total
PR4 opex 54.10 58.50 60.50 62.70 64.80 300.60
Issue PIP 0.22 0.23 - - - 0.45
Scheduled outages 0.46 0.50 0.51 0.53 0.55 2.56
Construction and Energisation 2.03 2.19 - - - 4.22
Investment Delivery (ID) (NEW)27 - - 2.51 2.60 2.69 7.80
Stakeholder engagement (NEW)28 - - - - - TBD
Total 2.71 2.93 3.03 3.14 3.24 15.03
Percentage of TAO allowed opex 5.00% 5.00% 5.00% 5.00% 5.00% 5.00%
Explanation of the TAO incentives for PR4
There were three Transmission System Development incentives for the TAO in
operation during PR3. These three incentives will continue to operate in PR4 for 2016
and 2017. The incentive around outage scheduling will remain in place for the whole
of PR4. The alterations to the remaining incentives are explained below.
Incentive around Issuing the PIP
For PR3, the PIP incentive was capped at +/-0.4% of TAO annual opex. This
incentive will remain in place, with the same capped value for the TAO for
2016 and 2017.
25 The opex profile for the TAO shown in these tables is taken from the following CRU decision (Section 12.2): https://www.cru.ie/wp-content/uploads/2015/07/CER15296-Decision-on-TSO-and-TAO-Transmission-Revenue-for-2016-to-2020-1.pdf 26 This table is presented assuming that the CRU consultation concludes that the PIP and Construction and Energisation incentives for the TAO are re-formatted to form the new Investment Delivery incentive (option 2 as described in Section 4.3). 27 For further information on this incentive, please see Proposal 6 in section 4.3 28 For further information on this incentive, please see Proposal 8 in section 4.5
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
57
From 2018 onwards, CRU has set out 2 possible incentive options: the first
option would remove the PIP incentive, replacing it with the Investment
Delivery incentive explained below; the second option would retain the PIP
incentive in its current form and value. Both options are explained in Section
4.3.
Construction and Energisation incentive
The TAO incentive around Construction and Energisation was capped at +/-
3.75% of annual opex for PR3. This incentive will remain in place, with the
same capped value, for the TAO for 2016 and 2017.
From 2018 onwards, CRU has set out 2 possible incentive options: the first
option would remove the Construction and Energisation incentive, replacing it
with the Investment Delivery incentive explained below; the second option
would retain the Construction and Energisation incentive in its current form
and value. Both options are explained in Section 4.3.
The Investment Delivery incentive – new incentive for PR4
This new incentive will come into force in 2018 and run to the end or PR4 in
2020.
The total value of the incentive will be 4.15% of the TAO opex for years 2018,
2019 and 2020.
For 2018, 2019 and 2020, the revenue at risk/reward has been redistributed
from the PIP incentive and the Construction and Energisation incentive as
explained above.
The reward for the TAO under the Investment Delivery incentive will be
symmetrical, so that the incentive is capped at +/-4.15% depending on the
outcome of the incentive assessment (as explained in Section 4.3.
In addition to these Transmission System Development incentives, the TAO will also
be subject to a new Stakeholder Engagement incentive (aligned with the incentive
introduced for the TSO and DSO).
Stakeholder Engagement incentive – new incentive for PR4
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
58
For 2018, the Stakeholder Engagement incentive will be reputational for all
parties.
From 2019, the Stakeholder Engagement incentive value will be set by the
CRU based on a review of the success of performance in 2018.
The revenue at risk/reward for the stakeholder engagement incentive for the
TAO will be re-distributed from the value available under the Investment
Delivery incentive.
The introduction of the Stakeholder Engagement incentive will maintain the
total TAO incentive value under PR4, as set out in this consultation.
7.3 DSO/DAO incentive package
The incentive package for the DSO includes elements of the PR3 incentive package
that are still relevant and will continue into PR4, and new incentives introduced from
2018 for the remainder of PR4. In addition to these operational incentives, the DSO
also has access to the Strategic Innovation Fund in PR4.
For PR4, the total value of the incentive revenue at risk/reward will be the same as for
PR3 – this is calculated as 4% of DSO Allowed Revenues (on an annual basis and
across the whole PR4 period). To maintain this cap for the PR4 operational incentives
(excluding the SIF), the distribution of revenue available/at risk across each incentive
has been adjusted for PR4 as set out in this consultation.
For the DSO, the operational incentives for the first 2 years of PR3 have been turned
off. To maintain the strength of the incentives (i.e. the total size of the incentive
risk/reward value over the whole of PR4), the annual value of the remaining incentives
for 2018, 2019 and 2020 has been increased.
The total value of revenue at risk for the DSO is shown in
Table 7. The total possible incentive reward for the DSO is shown in
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
59
Table 8.
The figures presented in both table are based on the published PR4 Allowed
Revenues. These are indicative only. The actual incentive payments will be
calculated by CRU annually during PR4, and calculated in nominal terms.
Table 7 DSO incentive revenue at risk for PR4
Incentives for the DSO (€m, 2014) 2016 2017 2018 2019 2020 Total
PR4 Allowed Revenue 737.07 817.12 835.83 857.72 883.23 4130.97
Continuity – Customer Interruptions - - 15.27 15.52 15.81 46.60
Continuity – Customer Minutes Lost - - 15.27 15.52 15.81 46.60
Overall Customer Satisfaction Survey29 - - 2.72 2.72 2.72 8.16
Customer Satisfaction - - 13.54 13.76 14.01 41.31
Metering – 1 read/year - - 0.85 0.85 0.85 2.55
Metering – Estimated reads - - 0.85 0.85 0.85 2.55
Smart Metering (NEW) - - 4.00 4.00 16.00 24.00
Stakeholder engagement (NEW) - - - - - 0.00
Worst served customer (NEW) - - 2.23 2.23 2.23 6.70
Total 0.00 0.00 54.74 55.45 68.28 178.46
Percentage of DSO allowed revenues 0.00% 0.00% 6.55% 6.46% 7.73% 4.32%
For the DSO, the revenue reward is lower than the revenue at risk for PR4. This is
because the value of the customer satisfaction incentive cap is asymmetrical
(+0.25%/-1.00%) – this is unchanged from PR330. This means that the DSO can earn
a maximum of €10.33m on this incentive (customer satisfaction), however the amount
the DSO can lose is €41.31m. This explains the difference between the total revenue
at risk €178.46m (Table 7) and total revenue for reward €147.52m (Table 8)
The total incentive cap or the DSO is set at 4.00% of annual Allowed Revenues31.
29 More commonly known as the RedC survey 30 This is unchanged since CER/06/107 31 As per CER/06/107
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
60
These caps are calculated annually by the CRU in nominal terms and taking into
account adjustments made between years of the PR period. This explains why the
total cap, presented in Table 7 does not equal 4.00%.
Table 8 DSO incentive revenue reward for PR4
Incentives for the DSO (€m, 2014) 2016 2017 2018 2019 2020 Total
PR4 Allowed Revenue 737.07 817.12 835.83 857.72 883.23 4130.97
Continuity – Customer Interruptions - - 19.21 19.52 19.88 58.62
Continuity – Customer Minutes Lost - - 19.21 19.52 19.88 58.62
Overall customer satisfaction survey - - 2.72 2.72 2.72 8.16
Customer Satisfaction - - 3.38 3.44 3.50 10.33
Metering – 1 read/year - - 0.85 0.85 0.85 2.55
Metering – Estimated reads - - 0.85 0.85 0.85 2.55
Smart Metering (NEW) - - - - - 0.00
Stakeholder engagement (NEW) - - - - - 0.00
Worst served customer (NEW) - - 2.23 2.23 2.23 6.70
Total 0.00 0.00 48.46 49.14 49.93 147.52
Percentage of DSO allowed revenues 0.00% 0.00% 5.80% 5.73% 5.65% 3.57%
Explanation of the DSO incentives for PR4
This section explains the rationale for each incentive value decision for PR4.
Continuity of Supply – Customer Interruptions (CI) and Customer Minutes Lost
(CML)
The CI and CML incentives will be retained for PR4. The cap on revenue at
risk for each incentives has been reduced from 1.50% of annual Allowed
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
61
Revenues under PR3, to 1.13% under PR4.32 This reflects the reduced scope
of the CI incentive, which now will only apply to unplanned interruptions.
The revenue reward available to the DSO for good performance against the
CI and CML incentive is higher that the revenue at risk, at 1.42% of annual
Allowed Revenue. This increase is applied to ensure that the total revenue
reward during PR4 remains the same as during PR3 (4.00% of Allowed
Revenue across the whole PR period).
Overall customer satisfaction survey33
The overall customer satisfaction survey incentive was capped at +/-€1.6m
per year for PR3 (real €2009). For PR4, we will maintain this annual value.
As the incentive for 2016 and 2017 was turned off for the DSO, the 2016 and
2017 value has been re-distributed to the remaining years of PR4 to maintain
the overall strength of the incentive.
This results in an annual incentive value for 2018, 2019 and 2020 of +/-
€2.72m with a total PR4 value of +/-€8.16m (this is equivalent to €1.63m per
year for 5 years in real €2014 prices).
The risk/reward incentive cap for overall customer satisfaction survey is
symmetrical over PR4.
Customer Satisfaction (Network Customer Contact Centre metrics)
The Customer Satisfaction incentive is unchanged from PR3. The annual
upside is capped at 0.25% of Allowed Revenue and the annual downside is
capped at -1.00%.
Aligned with the other DSO incentives, the Customer Satisfaction incentive
risk/reward value from 2016 and 2017 will be re-distributed to 2018, 2019 and
2020. This will ensure the DSO has strong incentives for the remainder of
32 This is the equivalent annual percentage if the incentive was applied to all 5 years under PR4. As the PR4 incentive values for 2016 and 2017 for the DSO have been re-distributed to the remainder of PR4, the incentive value for 2018, 2019 and 2020 is higher than this. Over the whole of PR4, the revenue at risk/reward for the CML and CI incentive is 1.13%/1.42% of allowed revenue respectively. 33 Commonly known as the RedC survey incentive
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
62
PR4, but maintains the total Customer Satisfaction incentive value for PR4 as
a whole.
Metering incentives – ‘At least 1 read per year’ and ‘Estimated reads’
The PR3 metering incentives will be maintained for PR4. For PR3 the
incentive risk/reward value was capped at +/-€0.50m per year for each
metering incentives (with a total value of +/-€1m in real €2009 prices).
For PR4, these values have been uplifted to €2014 prices and re-distributed
so that the total incentive value is available for 2018, 2019 and 2020. This will
ensure the DSO has strong incentives for the remainder of PR4, but maintains
the total Metering incentives value for PR4 as a whole.
Smart metering incentive (NSMP “Smart delivery days”) – new incentive for PR4
The NSMP incentive is a new DSO incentive for PR4 and will come into force
from 2018.
The incentive is designed to reward the successful delivery of the smart
metering programme plan, as defined by smart delivery days as explained in
Section 6.5)
Under PR4 and the revised NSMP delivery plan, the DSO has been awarded
capex to match the deployment. Poor delivery against the plan will result in a
revenue reduction from the DSO through the Smart meter incentive.
The NSMP incentive revenue profile for the remainder of PR4 is set at €4m in
2018 and 2019 and €16m in 2020. This is equivalent to around 0.6% of the
DSO total Allowed Revenue over the whole of PR4.
As funding for the NSMP roll-out has been provided through the PR4
settlement, the NSMP incentive is downside only (effectively reducing the
funding allowance where the delivery targets are not met).
Stakeholder Engagement incentive – new incentive for PR4
The Stakeholder Engagement incentive is a new reputational incentive for
PR4.
The incentive value will be reputational in the first year, as the framework
process for assessment is developed between the DSO and CRU.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
63
For 2019 and 2020 the CRU propose to introduce a financial incentive for
performance under the stakeholder engagement incentive.
The value for this new incentive will be symmetrical, with the same value at
risk for poor performance as for reward for strong performance, and will be
determined following review of performance under the first year of the
incentive.
The revenue at risk/reward for the Stakeholder Engagement incentive for the
DSO will be re-distributed from the value available under the Continuity of
Supply (CI and CML) incentive.
Worst Served Customer incentive – new incentive for PR4
The Worst Served Customer incentive is also a new incentive that will start in
2018.
This incentive will be capped at +/-€6.7m over the remainder of PR4.
The incentive reward is payable on the quantified reduction in the number of
Worst Served Customers by the DSO.
The incentive will apply where network reliability is improved by 20% per
customer for worst served customer over a three year period. The incentive
will be based on a payment of +/-€1,595 per customer around a dead band of
70-80%. This means that the DSO would be penalised per customer if less
than 70% of targeted customer receive this improvement, and would earn the
incentive if more than 80% of customers receive this improvement. The
maximum incentive reward allows ESBN outperform the incentive, which is
based on a target customer volume of 6000 customers.34
7.4 Consultation question
5. Do you have any comments on how CRU’s proposals combine as packages of
incentives for the TSO, TAO and DSO/DAO including reasoning or evidence for
34 If EBSN improves reliability for 9000 customers, the full €6.7m upside will be achieved.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
64
alternatives or variants that might better meet CRU’s objectives?
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
65
Annex 1: International review
The CRU engaged consultants to review regulatory reporting and incentive
mechanisms in operation in other jurisdictions. This international review of best
practice provides evidence of successful methods and approaches employed by other
National Regulatory Authorities, in Europe and internationally. This international
review has been used to inform and develop the proposals set out in this consultation.
The assessment took each of the consultation areas in turn, to establish where
appropriate benchmarks were available, a description of the mechanisms in place, and
to identify key contacts within relevant organisations. Key jurisdictions for review
included GB, with a focus on Ofgem’s implementation of the RIIO regulatory
framework, and the east coast of Australia. Regulatory mechanisms in other
European jurisdictions were also used as evidence as relevant, mainly focusing on
other European Member States.
The desktop research was complimented with bilateral discussions with National
Regulatory Authorities in Europe and Australia, to provide first-hand evidence of the
practicality and merits of mechanisms employed.
Jurisdiction Key characteristics Reason for selection
GB Long-term, liberalised market
Mature, stable regulatory framework
Incentive-based network regulation
3 Transmission Owners, 14 Distribution
Network Owners, 1 System Operator – no state-owned companies
Similar market structure and challenges to Ireland – e.g. evolving energy mix, development of smart networks, distributed generation and smart meter roll-out
Recent fundamental review of framework for network regulation
Large range of different incentive mechanisms introduced (with a focus on innovation and stakeholder engagement)
Australia
(East coast)
More recently liberalised market than GB
New regulatory framework adopted in 2005
Incentive-based network regulation
8 Transmission Owners (including interconnector operators), 13 Distribution Network Owners, 1 system operator (not-for-profit, with national transmission planning function) – some state-owned companies
Actively managed, and well-documented reform programme
Combination of state-owned and private companies
Active approach to network planning and needs case assessment
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
66
Others Varied, based on characteristics of
relevant European Member States
As relevant, to provide wider context and specific examples of best practice
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
67
Annex 2: Draft Annual Reporting Principles
This annex sets out a draft set of principles to inform the development by the TSO,
TAO and DSO/DAO of revised, more useful friendly annual performance reports.
Purpose
The APR shall be a clear, accessible and non-technical document summarising
performance during the relevant year in each relevant area of performance.
Format
It shall be short in length, and visually appealing. It shall contain no appendices and
annexes, but may provide links to other relevant material for a reader seeking more
detailed information in a particular area. It shall make effective and proportionate use
of tables, charts and diagrams – and supporting commentary – such that a non-
technical reader can easily discern:
Levels of performance
Key behaviours of the licensee
Context of past performance.
It shall be easy to compare and reconcile to past APRs prepared under this
framework.
Scope
It shall order the material in a complete set of logical sections derived from an analysis
of the different ways in performance impacts on customers, market participants or
other stakeholders. For example:
Maintaining reliable supplies of electricity
Meeting new demands for connection
Servicing customers and the market
Optimising the network
Utilising innovation
Engaging with stakeholders
Safety
Managing environmental footprint.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
68
Ongoing improvement
The usefulness of the performance report shall be review annually, including
on the basis of feedback from stakeholders. Improvements, such as new
metrics for measuring performance, shall be developed and introduced
promptly.
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
69
Annex 3: TSO incentives
This annex provides a summary of EirGrid’s performance of under the ‘System
Minutes Lost’ (SML) and ‘Frequency’ incentive. The historical performance during
PR3 has been used to establish the target rates, dead-bands and upper and lower
bounds for the SML and Frequency incentives under PR4, included in this proposal.
The dead-band for PR4 will be reduced to reflect recent performance under the SML
incentive. The dead-band will be set at 0.6-2.1 SML per year.
Table A1 PR4 Customer Minutes Lost incentive targets for the TSO
Incentive 2011 2012 2013 2014 2015 PR3
average PR4 rate
Actual performance 0.183 0.372 0.357 2.881 0.049 0.768
Dead-band 1.5-3.0 1.5-3.0 1.5-3.0 1.5-3.0 1.5-3.0 1.5-3.0 0.6-2.1
Upper Bound 3.5 3.5 3.5 3.5 3.5 3.5 2.5
Lower bound 1.0 1.0 1.0 1.0 1.0 1.0 0.0
The incentive rate for the CML incentive will be the same for PR3 and PR4:
Plus €66,000 per 0.1 minute below dead-band
Minus €66,000 per 0.1 minute above the dead-band
The PR4 dead-band is positioned to allow EirGrid to earn the full capped incentive rate
for the CML incentive each year during PR4 (equal to 0.8% of internal opex).
The Frequency target for PR4 will be set at 99%, measured as the proportion of time
per year when the Frequency is between the limits of 49.9Hz and 50.1Hz.
Table A2 PR4 Frequency incentive targets for the TSO
Incentive 2011 2012 2013 2014 2015 PR3
average PR4 rate
Actual performance 99.6% 99.3% 99.3% 99.2% 99.4% 99.4%
Target 96.0% 96.0% 96.0% 96.0% 96.0% 96.0% 99.0%
Upper Bound 98.0% 98.0% 98.0% 98.0% 98.0% 98.0% 100%
Lower bound 94.0% 94.0% 94.0% 94.0% 94.0% 94.0% 98.0%
The incentive rate for the CI incentive for PR3 were set at:
Plus €33,000 per 0.2% above the target
Minus €33,000 per 0.2% below the target
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
70
For PR4, the rate will be adjusted to allow EirGrid to earn the same upside and
downside under PR4 as under PR3:
Plus €33,000 per 0.1% above the target
Minus €33,000 per 0.1% below the target
EirGrid’s historical performance under the SML and CI incentives are shown in the
Figures below.
Figure 1 PR2 and PR3 SML incentive performance
Figure 2 PR2 and PR3 Frequency incentive performance
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
SML p
er
year
Deadband Actual performance (SML) Upper and lower bound
Plus €66,000 per 0.1 minute below deadband
Minus €66,000 per 0.1 minute above deadband
Annual incentive capped by upper and lower bounds
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
71
90%
91%
92%
93%
94%
95%
96%
97%
98%
99%
100%
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Fre
quency
within
49.9
Hz
to 5
0.1
Hz
Actual performance PR3 target performance PR3 Upper and lower bounds
Minus €33,000 per 0.2% below target
Plus €33,000 per 0.2% above target
Annual incentive capped by upper and lower bounds
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
72
Annex 4: DSO incentives
This annex provides a summary of ESBN’s performance of under the Customer
Minutes Lost (CML) and Customer Interruptions (CI) incentive (based on ESBN’s
published Annual performance reports for PR3). The historical performance during
PR3 has been used to establish the target rates, dead-bands and upper and lower
bounds for the CML and CI incentives under PR4, included in this proposal.
The CML target for PR4 will be based on the target performance for 2015. This
results in a rate of 68.00 for PR4. During PR3, actual CML performance was worse
than the target, in 2013, 2014 and 2015. It is appropriate to use the 2015 target value
to set the CML target for PR4. The CML target under PR4 will be based on unplanned
outages only, therefore no target is set for the planned outage rate (the planned
outage performance will be assessed through a reputational incentive).
Adjusted actual performance (for CML and CI) includes ESBN’s performance taking
into account the impact of Maintenance Renewal Programmes.
Table A3 PR4 Customer Minutes Lost35 incentive targets for the DSO
2011* 2012* 2013 2014 2015 PR3
average PR4 rate
Unplanned
CML target - - 76.40 72.20 68.00 72.20 68
CML actual 69.58 59.83 86.72 97.67 82.99 79.36 -
CML actual (adjusted) 69.58 59.83 86.72 97.67 82.99 79.36 -
Planned
CML target - - 55.70 55.80 55.80 55.77 -
CML actual 46.59 45.25 42.13 49.78 73.06 51.36 -
CML actual (adjusted) 24.53 22.64 27.21 30.38 41.25 29.20 - *Planned and unplanned data was not available for 2011 and 2012
The Customer Interruptions incentive target for PR4 is 1.10 for unplanned interruptions, based on
the average of the PR3 performance (using data available to CRU at the time of writing).
35 The average number of minutes without supply per customer connected in the year (CML).
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
73
Table A4 PR4 Customer Interruptions36 incentive targets for the DSO
2011* 2012* 2013 2014 2015 PR3
average PR4 rate
Unplanned
CI target - - 1.13 1.10 1.06 1.10 1.04
CI actual 0.95 0.83 1.14 1.24 1.03 1.04 -
CI actual (adjusted) 0.95 0.83 1.14 1.24 1.03 1.04 -
Planned
CI target - - 0.23 0.23 0.23 0.23 -
CI actual 0.18 0.19 0.17 0.18 0.25 0.19 -
CI actual (adjusted) 0.11 0.10 0.11 0.13 0.15 0.12 - *Planned and unplanned data was not available for 2011 and 2012
36 average number of interruptions per customer connected in the year (CI) and
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
74
Annex 5: Questions for consultation
CRU is inviting stakeholders to submit views and evidence on the following questions:
1. Do you have any comments on Proposals 1-3 and CRU’s supporting
reasoning, including but not limited to the following aspects:
a. The objective of a more comprehensive, user-friendly joint TSO/TAO
performance report, and how best to meet it; and
b. The rationale for a companion summary report each year on investment
planning and delivery.
2. Do you have any comments on Proposals 4-11 and CRU’s supporting
reasoning, including but not limited to the following aspects:
a. The mix of new and retained incentive mechanisms, and how they relate
to the key areas of TSO and TAO behavior for market participants and
consumers;
b. The proposed change in the approach to setting incentives for
investment planning and delivery, based on assessment against a
broader range of criteria and evidence than under the existing
mechanism; and
c. The choice of key strategic objectives and associated outputs for the
TSO to be rewarded for exceptional performance.
3. Do you have any comments on Proposals 11 and CRU’s supporting reasoning,
including but not limited to the following aspect:
a. The objective of a more comprehensive, user-friendly DSO performance
report, and which particular aspects of DSO behavior or performance
are under or poorly-reported on currently in the APR.
4. Do you have any comments on Proposals 12-18 and CRU’s supporting
reasoning, including but not limited to the following aspects:
a. The mix of new and retained incentive mechanisms, and how they relate
to the key areas of DSO behavior for market participants and
consumers;
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities
75
b. The proposed change to move performance against planned outages to
a reporting-based reputational incentives, and focus financial incentives
instead on improving outcomes for worst-served customers.
c. The case for the proposed new incentive on stakeholder engagement,
and types of engagement (and associated outcomes) it should seek to
encourage.
d. The form and strength of incentive for the proposed new incentive
mechanism on smart metering delivery by the DSO.
5. Do you have any comments on how CRU’s proposals combine as packages of
incentives for the TSO, TAO and DSO/DAO including reasoning or evidence for
alternatives or variants that might better meet CRU’s objectives?