Microsoft - Cheyenne Board of Public Utilities Biogas CHP Demonstration Project Presented By: Sean James - Microsoft Ryan Smith - BOPU Todd Lovell - Jacobs E.B. Jensen - Jacobs

Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Embed Size (px)

Citation preview

Page 1: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Microsoft - Cheyenne

Board of Public Utilities

Biogas CHP

Demonstration Project Presented By:

Sean James - Microsoft

Ryan Smith - BOPU

Todd Lovell - Jacobs

E.B. Jensen - Jacobs

Page 2: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Sean James

• Microsoft - Advanced Data Center Development Group

• Sr. Research Program Manager

Sean James is responsible for research and developing new datacenter technology for Microsoft’s Global Foundation Services (GFS) group. GFS provides the foundational cloud infrastructure for over 200 Microsoft online and cloud services for consumers and businesses worldwide. Sean drives new datacenter technology for Microsoft’s next generation data centers including the evaluation, development, and testing.

Sean joined Microsoft in 2007 to manage one of Microsoft’s data centers. Later, he joined the construction team and oversaw the design and building of new Microsoft data centers.

Prior to joining Microsoft, Sean worked in data center management overseeing the day-to-day maintenance and repair operations for both IT hardware and critical infrastructure, such as backup generators and electrical switchgear. Prior to joining Microsoft, Sean served in the US Navy Submarine Fleet as an electrician.

o

Page 3: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Ryan Smith

• Cheyenne - Board of Public Utilities (BOPU)

• Plant Supervisor Operations & Maintenance

• Ryan Smith has been in wastewater treatment for 7 years,

the last 5 with the BOPU in his current position.

Page 4: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Todd Lovell

• Jacobs Project Management Company

• Senior Projects Manager

• Mr. Lovell has 30 years of diverse project management

experience, 6 years with Jacobs, the last 4 working in

alternative energy solutions, including multiple CHP business

projects and numerous gas to energy projects utilizing fuel

cell technologies.

Page 5: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

E.B. Jensen, P.E., CEM

• Jacobs Engineering

• Director - Power & Energy

• Mr. Jensen has been with Jacobs for over 11 years and

has been in the CHP business for over 25 years. He has

been involved in numerous biogas gas to energy projects

and projects involving fuel cells - both simple cycle and

ones in CHP configurations.

Page 6: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Project Background

• The rising demand for online services is

driving the need to identify and

development new sources of energy

• In May 2012, Microsoft made a commitment

to make our operations carbon neutral;

including datacenters

• In addition to renewable project investments

and internal carbon tax, we were looking for

innovative sources of clean energy

Sean James

Page 7: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Project Background

• Based on the benefits of waste to energy projects, we invited proposals from various sewer utilities.

• Cheyenne LEADS and Western Research Institute coordinated the winning proposal.

• The team included:

• City of Cheyenne

• Cheyenne Board of Public Utilities

• Cheyenne Light Fuel & Power

• FuelCell Energy

• The University of Wyoming

• Wyoming Business Council

Sean James

Page 8: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Project Background

• Microsoft provided matching funds to the Wyoming Business

Counsel grant of $1.5M to fund infrastructure upgrades to the

BOPU site

• In addition, Microsoft provided a server container and purchased a

300kW fuel cell from FuelCell Energy

• FuelCell Energy also contributed $700k in-kind

Sean James

Page 9: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Why BOPU participated

• BOPU was interested in the project because:

• It gave the facility the opportunity to implement a new CHP

technology that would not have been achieved with public

only funds.

• By installing such a system with sophisticated monitoring

systems, the plant would be able to better monitor and

analyze the plants operational behaviors.

• Through the fuel cell plant power and thermal outputs, it was

expected the Wastewater treatment plant would see a

decrease in utility electric and natural gas consumption.

Ryan Smith

Page 10: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Wastewater Treatment Plant

• The Wastewater treatment plant has been in operations

since 1975 and is designed for a daily wastewater inlet

capacity of 10.5 million gallons per day.

• The plant consumes on average 360642.74 kWhrs of

electricity per month.

• The plant consumes on average 494.22 decatherms of

natural gas on a monthly basis primarily for use in sludge

heating.

Ryan Smith

Page 11: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

The Project Management

• The project execution approach was thru an EPC

arrangement with Fuel Cell Energy performing as both

equipment supplier and turnkey EPC provider.

• Jacobs performed as Microsoft's PM/CM provider and

Owner's Engineer.

• As PM - Jacobs assisted MS with the receipt and

distribution of public funds from Wyoming Business

Council/City of Cheyenne.

Todd Lovell

Page 12: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

The Project Management

• Jacobs PM, acting as the MS representative, also provided the PM/CM services :

• Subject Matter Expertise

• Infrastructure & System Design Review as Owner’s Engineer

• Quality Assurance (Owners Rep) - Design & Construction

• Coordination of stakeholders • BOPU

• Microsoft

• LEADS

• City of Cheyenne

• WRI

• UWO

• FCE

• EPC Team

• Project financial tracking

Todd Lovell

Page 13: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

The Project Configuration

• Fuel Cell – DFC 300

• Waste Heat Recovery – Sludge Heater

• Natural Gas &/or ADG

• Electric Islanding Capability for ITPAC

Page 14: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Anaerobic

Digester (1°)

Flare

Sludge

Heater

Raw

ADG

Raw

Sludge

Cool

Glycol

Natural

Gas

Digested

Sludge

Sludge

HTX

Hot

Glycol

From Fuel Cell

To Fuel Cell

RS

NG1 HG

CG

DS

ADG1

ADG2

ADG3

ADG4

C1

C2 C3

C4

Flare

Exhaust

Heater

Exhaust

Ex2

Ex1

Air

Air

A1

A2

Schematic of Digester Components

Pump

To Further

Processing

From Dry

Creek Plant

CADG3

Compressor

To ADG Clean-up

CADG4

From Clean ADG

From Clean ADG

ADGmix

Anaerobic

Digester (2°)

1DSO

TWAS

TWAS

Page 15: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Fuel

Cell Inverter

Load

Leveler

ITPAC

Dry Creek

Plant

Schematic of Electricity “Flow”

ADG

Clean-Up

Glycol

Heater

Parasitic

Load

E1 E2 E3

E4

E5

E6

E7

E8

Base

Load

E9 Measure E6.

Calculate E7, E8, E9.

Page 16: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Schematic of Electricity “Flow”

System / Location

Device Name/

Calculation

EM1 FuelCell Parasitic Load BOP_KW

EM2 Tie Breaker Output to Grid TB_KW

EM3 Tie Breaker Output to Grid BOPU Grid

EM4 Total CCB Load Load_Leveler

EM5 CCB Customer Loads CCB_KW

EM6 IT PAC Total Load Main_PM1

EM7 Server Load 1 Load1_PM3

EM8 Server Load 2 Load2_PM3

EC1 Fuel Cell Module DC Power Output

Calc=DC amps*DC

volts

EC2 FuelCell NET AC Output Calc=EM3+EM4

EC3 Load Leveler Consumption Calc=EM4-EM5

EC4 HRU and DG Cleanup Skid Load Calc=EM5-EM6

EC5 IT PAC Parasitics Calc=EM6-EM7-EM8

EC6 Inverter Losses Calc=EC1-EC2-EM1

Page 17: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project
Page 18: Cheyenne Board of Public Utilities Biogas CHP Demonstration Project

Test Data - thru Sept 2014

• Project is still in construction (HRU & ADG) – Operations to

date on Fuel Cell with natural gas.

• The operational testing of the fuel cell has enabled the

Wastewater treatment plant to gain a better understanding

of how the operations of high power consuming equipment

can impact the overall electric power demand for the entire

facility.

• Thru the testing to date, the peak load reduction has been

identified thru a modification to the plant operator's

methodology for equipment sequencing.