28
Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS Contents 7.1. Comparison of the Status of BSC Implementation ...................................... 254 7.2. Comparison of the Challenges – The Leaders’ Perspective ......................... 256 7.3. Comparison of Challenges – The Employees’ Perspective .......................... 259 7.4. Comparison of the Challenges – The Facilitators’ Perspective .................... 263 7.5. Common Challenges for BSC Implementation ............................................ 266 7.6. Root Causes of the Challenges to BSC Implementation .............................. 267 7.7. Concerns at Individual and Organisational Levels ....................................... 270 7.8. Differentiating Key Success Factors ............................................................ 270 7.9. BSC Implementation Challenges in the Context of PSU ............................. 275 7.10. Summary of Factors Driving Employee Buy-in for BSC............................. 278 7.11. Enabling Factors for Enhanced Employees Performance ............................ 279 7.12. Summary....................................................................................................... 280

Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

Chapter Seven

CROSS CASE ANALYSIS:

DISCUSSIONS AND FINDINGS

Contents

7.1. Comparison of the Status of BSC Implementation ...................................... 254

7.2. Comparison of the Challenges – The Leaders’ Perspective ......................... 256

7.3. Comparison of Challenges – The Employees’ Perspective .......................... 259

7.4. Comparison of the Challenges – The Facilitators’ Perspective .................... 263

7.5. Common Challenges for BSC Implementation ............................................ 266

7.6. Root Causes of the Challenges to BSC Implementation .............................. 267

7.7. Concerns at Individual and Organisational Levels ....................................... 270

7.8. Differentiating Key Success Factors ............................................................ 270

7.9. BSC Implementation Challenges in the Context of PSU ............................. 275

7.10. Summary of Factors Driving Employee Buy-in for BSC ............................. 278

7.11. Enabling Factors for Enhanced Employees Performance ............................ 279

7.12. Summary ....................................................................................................... 280

Page 2: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

254

Chapter Seven

CROSS CASE ANALYSIS:

DISCUSSIONS AND FINDINGS

This chapter compiles the findings of the cases studies in Chapters 4, 5, and 6 and makes a

comparative analysis of the challenges from the perspectives of employees, leaders and

facilitators. The analysis examines the context of each case and the determinants that

impact the process of BSC implementation. Further investigation highlights the factors that

are not too evident, but are the root causes of these concerns. These factors are discussed at

both individual and organisational levels.

Since the study was carried out in a PSU, the challenges and success factors specific to the

PSU context are highlighted. The analysis reveals the necessary attributes in a facilitator,

drivers of employee buy-in and the factors that motivate employees to commit their efforts,

all of which result in successful implementation.

7.1. Comparison of the Status of BSC Implementation

Comparative study of all the six cases shows that BSC implementation could be termed as

successful (as defined and discussed in Chapter 2) in two departments- ECR-ISD and

WCR-EMD. Implementation in WCR, Aviation and E&P may be termed to have been

partially successful. ECR may require still more efforts to institutionalise BSC.

The case of E&P was of particular interest as the planning was done in line with BSC, but

implementation and reviews were independent of BSC. The leader’ ability to engage his

team exceeded BSC requirements. The team achieved SBU objectives. This case

underlined the importance of leadership. Table 7.1 gives a comparative representation of

the BSC implementation in all cases.

Page 3: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

255

Table 7.1

Comparison of the Status of BSC Implementation

SN STATUS E&P AVT ECR WCR ECR-

ISD

WCR-

EMD

I Pre-Implementation Stage : BSC Awareness and Buy-in

1 Awareness about the BSC

Concept

2 Leaders Buy-in

3 Employee Buy-in

II BSC Implementation Stage: BSC Designing, Cascading, Aligning and Reviewing

1 Designing Strategy Map &

BSC Template

2 Cascading

3 Alignment with Vision &

Strategy

4 BSC Review

III Post BSC Implementation – Sustenance Stage

1 Adapting BSC to Modified

Strategy

2 Integrating BSC as an

Ongoing Management

Process

A number of factors, including the context of each case, impacted the degree of success of

BSC implementation. The teams that successfully implemented BSC and experienced

transformation were both small in size and had team heads who were able to maintain close

relations with all their team members. The facilitators’ provided appropriate and timely

support and motivation to these teams. On the other hand, in spite of its small sized team,

E&P did not get satisfactory support from its facilitator.

In all the teams, the head took the ownership of implementation upon him. The leaders also

took the initiative to educate their team members as well as to institutionalise the processes

P P N S S S

S S N P S S

P P N P S S

S P P S S S

N P N P S S

P S P P S P

P P P S S N

P P N P S N

P P S S S S

Page 4: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

256

that were necessary for BSC implementation. They ensured proper cascading of BSC and

engaged the employees in the strategic pursuits. Employees in these teams described

several positive transformations that were the outcomes of BSC implementation.

7.2. Comparison of the Challenges – The Leaders’ Perspective

The concerns of the senior and middle management were broadly classified in seven main

categories with a total of 33 sub-categories of challenges as shown in Table 7.2. These

were separated out from the 222 codes giving leaders perspective on challenges, success

factors and outcomes of BSC implementation. While some challenges were common, some

others were specific to the case.

Table 7.2

Comparison of the Challenges from the Leaders’ Perspective

Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

I Developing an Appropriate SBU/ Department Business / Support Strategy

1 Understanding Macro

Business Scenario

2 Identifying Strategic

Objectives

3 Identifying Strategic

Competencies

4 Business Foresight

5 Resource Availability

II Translating Strategy into Actionable Objectives & Strategy Implementation

6 Understanding and

Designing Scorecards

7 Competence and

Commitment of the BSC

Facilitator

8 Involvement and Support of

BSC Facilitator

M M M L L M

H L M M M M

H L H M M M

H L M M M N

H N L L L N

H H N N N N

H H N N N N

L L L L L N

Page 5: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

257

Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

9 Dissemination and Cascading

of Scorecards

10 Bringing Alignment to

Become Strategy Focused

11 Strategic Networking

III Structural Inadequacies of BSC

12 Validating Causal

Relationships

13 Finding BSC Framework Not

Enough for Achieving

Objectives

IV Inspiring and Engaging the Leaders and Employees in the Pursuit of Business

Results

14 Personal Involvement –

Leaders’ Own Buy-In for

Strategy and BSC

15 Managing Employee Buy-In

16 Instilling Hope and

Optimism

17 Appealing to Intrinsic

Motivation

18 Developing and Nurturing

Relationships

19 Developing Positive Work

Environment

20 Institutionalising Work

Systems

21 Employee Placements

22 Transfers

23 Objectivity in Performance

Reviews

H M M H M H

M L H H H H

M M M M L M

H M M L H N

M H H L M N

L M M M M M

H L L L L M

L H M M H H

H H H M M M

H M M M M H

H N N N N H

L L H L L N

M M M M N N

H M M M M N

H M M N N N

Page 6: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

258

Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

24 Coaching and Mentoring

Leaders and Employees

25 Ensuring Value Based

Management

26 Political Interferences

V Developing Internal Business Capabilities

27 Proactive Learning Initiatives

linked with Strategy to Build

People Competencies

28 Adopting New Technologies

Proactively

VI BSC Reviews

29 Ongoing Parallel Reviews

30 Avoiding BSC Format for

Reviews

VII Change Management

31 Structures and Policies

32 Being a PSU

33 Managing Resistance to

Change

High Challenge Moderate Challenge Low Challenge No Challenge

Though the leaders in each case faced different sets of challenges that were specific to their

contexts, a few sets of challenges were common across the SBUs. E&P was at the

inception stage and leaders faced the challenges of understanding the complexities of their

business and identifying the high leverage areas and developing strong business alliances.

This was not the case with the other SBUs and teams. But they differed in the manner by

which they interacted with their employees and got them engaged in the strategic pursuit.

N H M L

M L M M L H

M M M M L L

H L M M M M

M N H H N N

M M M M M N

H H M H N N

H L H M H N

L M H H H N

M H H H H N

H H H H N N

Page 7: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

259

In the case of E&P and Aviation, obtaining facilitator’s support was a challenge whereas

the refineries did not face this problem. Refineries acknowledged that the facilitators took

the initiative to obtain employee buy-in and extended support during the implementation

process.

BSC reviews were conducted only in the refineries and their implementation teams. The

leaders admitted that ensuring that the reviews were consistent and qualitatively sound was

a challenge and needed considerable patience and understanding. Further, BSC

implementation necessitated changes in work routines and, though not very obvious, there

was resistance to change. Managing and overcoming the resistance was a challenge.

Smaller teams managed and resolved these issues better.

A common challenge faced by nearly all the leaders was motivation. It was necessary to

address concerns of employees who were dissatisfied with their performance ratings and

felt that they were not being fairly treated. Addressing this issue sympathetically and

motivating them to work for the team was a difficult task for the leaders.

Another commonly quoted challenge was interdepartmental conflicts and alignment of

support functions. These issues were rooted in an organisational culture that did not

recognise interdependency. This cultural aspect was a big barrier to alignment. Technically,

although the scorecards and processes were shown as aligned, they were practically

ineffective.

7.3. Comparison of Challenges – The Employees’ Perspective

The inputs received from the several in-depth interviews, group interviews and focused

group discussions led to total 204 codes with many overlaps considering all six cases.

While collating the findings, all the challenges were grouped in 6 major categories with a

total of 36 sub-categories as tabulated in Table 7.3.

Page 8: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

260

Table 7.3

Comparison of the Challenges from the Employees’ Perspective

Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

I Understanding of the BSC Concept , Strategy Maps and BSC Template

1

Understanding BSC

perspectives - Putting

Thoughts in the BSC

Format

2 Identification of

Strategic Objectives

3 Quantifying Intangibles

4 Forced Irrelevant

Objectives & Targets

II Leaders’ Competence, Commitment and Involvement

5 Technical Expertise at

Senior Positions

6

Leaders’ Engagement

Levels-(Discussing

Vision, Strategy and

Initiatives with

Employees)

7 Supervisor Prioritising

on Personal Goals

8

Faith in Leadership –

(Perception of Leaders’

Accountability and

Transparency )

9

Leaders’ Seriousness

About Using BSC –

BSC Just a Formality

III Facilitators’ Competence, Commitment and Involvement

10 Facilitators’

Competence

11

Facilitators’

Commitment and

Support

H M M M M M

H H H M M M

L N N M M M

L

L

L

N

N

N

N

N

H

N

N

L

N

N

N

N

N

N

L N H N N M

L H L N N M

H N N N N N

H H L M H H

H N N N N H

Page 9: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

261

Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

12

Facilitators’ Knowledge

of Business

Complexities

IV Overall Alignment

13 Alignment of the

Organisation Structure

14

Alignment of Support

Functions / Other

Functions

15

Alignment of Policies:

Employee Performance

Management System

(EPMS)

16

Alignment of Training

& Development

Initiatives

17 Alignment of Budget

and Resources

18 Alignment of Rewards

and Incentives

V Review Related Challenges

19 Data and Information

Availability

20 Time Constraints

21 IT or BSC Software

22

Representation of

Operational

Complexities

23

Comprehensive

Representation of all

Work Done

24 Consistent Performance

Feedback

VI Cultural and Other Organisation Specific Challenges

25 Communication

H L L N L M

L N M M M M

N M M M M M

N M M M M M

N L H H L N

N M M M M M

L

L

L

L

L

L

L

N

M

M

M

M

M

M

M

M

M

M

M

M

M

M

M

M

N L H L N L

L H H H H H

H H H M H H

L H H H H H

Page 10: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

262

Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

26 Information Sharing

27 Decision Making

28 Conflict Resolutions

29 Work Systems

30 Employee Morale

31

Dissemination of BSC

to Non-management

Staff

32 Perception about

Organisational Care

33

Perception about Top

Management

Sponsorship

34 Perception about

Supervisor Dominance

35 Ownership and

Responsibility

36 Role Clarity

High Challenge Moderate Challenge Low Challenge No Challenge

Employees in E&P and Aviation observed that the non-availability of support from the

BSC facilitator was a challenge. This problem was not faced by the employees in other

SBUs. As a result, awareness and understanding of the concepts was relatively less in E&P

and Aviation. In EMD and the refineries, the challenge Understanding of the BSC Concept ,

Strategy Maps and BSC Template was felt mostly by the employees who had risen through

the ranks. These employees were usually of an age that was higher than the team average.

Their capability and motivation for learning was also low.

The existing work culture was also a deterrent. Slow decision making, lack of proper

communications and coordination posed a challenge. The first line of supervisors faced

N H M L

N

N

H

H

H

H

H

H

H

N

H

H

L N N L M

L N N N M

L L H N M

M

M

M

L L M M

N L M M M

M

M

M

H L H M M M

N N N N M M

N H N M M M

N H N H M M

Page 11: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

263

challenges of engaging the non-managerial staff (who were unionised workmen). They

refused ownership and accountability and very few of them worked sincerely. Thus, the

major common challenges were:

1- Understanding and designing of the scorecards

2- Quantifying intangibles

3- Alignment among functions and teams

4- Aligning the EPMS based on bell curve with BSC

5- Aligning rewards and incentives strictly with BSC

6- Conflict resolution

7- Non-involvement of workmen (unionised staff i.e. labour and clerical staff) in BSC

implementation process.

7.4. Comparison of the Challenges – The Facilitators’ Perspective

The study of inputs provided by the 6 facilitators from BSC team and four scorecard

managers resulted in 102 codes which referred to the challenges, outcomes and

methodology of BSC implementation. The comparative study indicated that the

competence, commitment and support extended by the facilitator plays a significant role in

the successful implementation of BSC. However, unless the initiative is taken by the

respective leaders, the facilitator can’t really do much. The onus of implementation lies

with the leaders.

Table 7.4 shows the challenges from the perspective of facilitators for different SBUs and

teams. Challenges pertaining to the structure, role clarity and absence of suitable BSC

software were some of the challenges experienced by all the facilitators.

Page 12: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

264

Table 7.4

Comparison of the Challenges from the BSC Facilitators’ Perspective

SN Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

I Team Structure and Size

1 Size of the Team

2 Work Load

3 Location of the Team

4 Reporting of the BSC Team

5 Hierarchical Issues

II Role Clarity of BSC Team

6 Accountabilities of the BSC

Team

7 Role and Accountabilities of

Scorecard Managers

III Competency Development

8 Training of Scorecard

Managers

9 Training of Facilitators on

BSC Concept and

Implementation

10 Competencies to Conduct

Training and Workshops

11 Knowledge of Business

Complexities

IV Commitment and Ownership

12 Commitment of BSC

Facilitator

H

L

H

L

H

H

H

H

H

H

H

H

H H H H M M

H H L H L N

M M M M M M

N H H H H H

L M M M M H

L

L

L

L

L

N

L

N

L

N

L

N

L L L L M M

M M M M M M

H H N N N N

Page 13: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

265

SN Challenging Factors E&P AVTN ECR WCR ECR-

ISD

WCR-

EMD

13 Commitment of SBU Heads

14 Leaders’ and Employee Buy-

in

V Cultural Factors

15 Communications

16 Enforcement of Decisions

17 Culture of Appeasing the

Boss

18 Willingness for the Change

VI BSC Review

19 Reviewing Abilities of the

Leaders

20 BSC Software for

Information Collation

21 Time and Data Constraints

VII Employee Transfers

22 Integrating New Incumbents

into BSC

23 Change in Leadership

Approach to BSC

High Challenge Moderate Challenge Low Challenge No Challenge

Challenges that were quoted by almost all the facilitators were:

1- In relation to their work load and the locations they had to cover, their team did not have

sufficient numbers.

N H M L

N N N M M M

L L N L M H

N L M M M M

L L L N L M

L H H H H H

L L N N

L L L N N

M H

H

L L M M L N

H L M N N M

N N N M M H

N N H N N H

Page 14: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

266

2- Hierarchy was a hurdle, especially when they were required to coach or guide officers

and managers who were much senior to them. It was more difficult in situations where

the leaders showed a lack of interest and initiative.

3- Another major concern was that the role and accountabilities of the scorecard managers

were not clearly defined and implemented.

4- Although SBU heads and leaders talked good about BSC in meetings, no one really

seemed to take the ownership for successful implementation of BSC. SBU heads

expected BSC facilitators to take initiative for implementation. BSC team did take

initiative but felt that their role was restricted to creating awareness, explaining the

concepts and offering implementation support and guidance. In the opinion of the

facilitators, the process owners - in this case, the SBU heads - were responsible for

implementation and its outcomes.

5- Facilitators expressed that not having a BSC software was a major constraint. It would

have made real time data and information available to top management and all

concerned. This limitation significantly impacted the quality of BSC reviews.

7.5. Common Challenges for BSC Implementation

Closer examination of the challenges highlighted by the top leadership team, functional and

team heads, the employees and implementation facilitators show several similarities in the

major themes of challenges. Figure 7.1 depicts these groups of common challenges.

Page 15: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

267

Figure 7.1

Common Themes for Challenges to BSC Implementation

7.6. Root Causes of the Challenges to BSC Implementation

A deeper examination of organisation’s history and culture as well as some psychological

factors provides an understanding of the factors that were at the root of these challenges

(yet not too evident). A summary of these hidden cultural and structural factors is given in

Table 7.5.

Understanding and

Designing of BSC

Cascading and

Diffusion of BSC

BSC Reviews /

BSC Software

Competence of Employees,

Leaders and Facilitators

Transfers

BSC Not Applicable to

Unionised Staff

Commitment, Initiative

and Ownership for BSC

Implementation

Overall Alignment

EPMS Synchronisation

PSU Constraints Common

Challenges

Page 16: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

268

Table 7.5

Underlying Issues to BSC Implementation Challenges

SN ISSUES IMPACT ON IMPLEMENTATION OF STRATEGY

AND BSC

1 Resistance to Change -

From Complacency to

Dynamism

Oil PSUs enjoyed a monopoly status for several decades.

The Government controlled the pricing of final products

through a system of cross subsidies and oil bonds to the

PSUs to compensate for the losses. There was no

competition. With changes in the business scenario and

Government policies, oil PSUs are now faced with

competition. Implementing BSC demanded customer focus,

strategic thinking, and sustained efforts to improve internal

processes and developing new capabilities. It was a change

for the organisation and there was (mostly passive)

resistance to change.

2 Strategy Team at Loss

with BSC

The Corporate Strategy and Planning (CSP) considered their

role to be limited to bringing out the strategy documents.

They felt they would not have to follow up on the

implementation process and left the implementation to the

SBU heads. From the beginning, the facilitator team did the

follow-up. Gradually the team of facilitators limited its role

to awareness about BSC and assisting in designing and

cascading of scorecards. For reasons unknown, there was no

scorecard for the strategy team. The strategy and BSC teams

worked independent of each other and reported to different

functional directors without any coordination between them.

3 Individual Successes

over Team Successes

Promotions were the only way by which the employees

considered themselves to be growing in the organisation.

The prevailing culture encouraged employees to work for

their personal advancement. This resulted in organisational

objectives becoming of secondary importance.

4 Conflicts, Blames

Indecisiveness, Lack of

Ownership and Initiative

There was a lack of collaboration and coordination among

SBUs, functions and teams. The impression that one could

get was that they worked in separate silos. There was no

system to resolve the inevitable conflicts. Whenever

interdependency matters came up the tendency was for

people to blame each other. The BSC team got the teams

and SBUs together and developed SLAs between SBUs and

departments. However, people showed the tendency to

return to the old way of working. More often than not, it

gave the impression that the teams were not ready to take

the initiative and work towards getting things done. They

Page 17: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

269

SN ISSUES IMPACT ON IMPLEMENTATION OF STRATEGY

AND BSC

seemed to want to limit their ownership and accountability

to the minimum possible.

BSC and SLAs brought in clear accountabilities and

required them to take initiative. In the given culture, there

was resistance to this arrangement. Nevertheless, some

people demonstrated higher level of commitment and

accepted accountability and took initiative.

5 Discrepancy Between

What is Said in Meetings

and What Actually Got

Done

It was also generally accepted that what was talked about in

the meetings was not necessarily to be implemented. There

was also the tendency to question the wisdom of the

decisions taken in the meeting. The meetings had limited

credibility. Only those issues that were pursued by the office

of chairman and directors were considered important and

were attended to.

6 Short Tenures of

Directors and Chairman

The short tenure of leaders in the top management team was

also a challenge. Typically, they have two to four year

tenure in these positions. The initiatives taken by them

might not get completed during their tenure. Their

successors might see matters differently and introduce new

ideas. Thus, there is always an element of uncertainty about

what the organisation will be like after three years.

7 EPMS Incoherent with

BSC

The existing EPMS incorporated strict government

guidelines on moderation of individual performance scores.

This often conflicted with the BSC system which calls for

scoring the employee performance against the achievement

of predefined objectives and rewarding appropriately. If the

performance ratings were going to be moderated anyway,

employees lose faith in BSC.

8 Employee Grievance

Handling

EPMS seemed to be the single biggest cause of

dissatisfaction among employees. It created an all pervasive

sense of injustice by the organisation. The organisation did

not have a mechanism or system for addressing such issues.

There were grievance handling cells but these were

ineffective. It led to employees not fully getting engaged

with organisational goals, but staying focused on their

personal goals.

Page 18: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

270

7.7. Concerns at Individual and Organisational Levels

The set of concerns as discussed above, are rooted in both micro- and macro- levels. At the

organisational level, they usually pertain to organisational culture, structure and systems;

and at the individual level, the challenges are on account of factors pertaining to

employees’ beliefs, values, and other such psychosomatic reasons. Table 7.6 depicts these

factors at individual and organisational levels.

Table 7.6

BSC Implementation Concerns at the Root of Individual

And Organisational Level Challenges

ROOT CAUSE FOR CHALLENGES

INDIVIDUAL LEVEL ORGANISATIONAL LEVEL

1 Mental Models 1

Leadership lacking in Ownership,

Initiative and Commitment 2 Previous Conditionings

3 Beliefs 2

Culture Lacking in Values, Justice,

Camaraderie and Discipline 4 Values

5 Resilience 3 Managerial Executive Abilities

6 Emphasis on Personal Gains

7 Ego and Professional Rivalry

4

Organisation Structure and

Systems, particularly the Employee

Performance Management System 8 Nature of Passing the Buck

7.8. Differentiating Key Success Factors

A comparative study of all the six cases showed that every case had some degree of

success. Some benefits were definitely experienced. Even though all the objectives could

not have been achieved, some important BSC objectives were certainly fulfilled. The two

teams - ECR-ISD and WCR-EMD - had registered better success by achieving the

maximum number of objectives. These teams also experienced significant transformations.

ECR–ISD not only successfully implemented BSC, it even exceeded the targets it had set

for itself. The following differentiating key success factors were seen with reference to

these two cases of successful implementation:

Page 19: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

271

1. Leaders’ Conviction: The head of ECR–ISD department fully believed in the concept

of BSC and was sure about the benefits of implementation. He took the initiative to

make his team understand and implement BSC. He sought the support of the facilitator

to organise workshops and implementation support whenever needed. Therefore, the

complete ownership of ensuring BSC implementation was taken by the team head.

2. Facilitator Support: The interest and commitment of the team was a motivation for the

facilitator who devoted time and energy to help make the implementation a success in

these teams.

3. Awareness, Understanding and Buy-in for BSC Implementation: The ISD team was

small and young (average age less than thirty five years). The ISD team members

believed in their leader and accepted BSC after initial cynicism. They remained focused

on the objective throughout the implementation period.

An interesting phenomenon to note here is that team profile of EMD was exactly

opposite. It had high average age and team members were not so well qualified. Still

EMD achieved substantial success in BSC implementation. The common factor here

was ‘employee buy-in’. The team head and facilitator could convince the team members

on the expected beneficial outcomes. The facilitator inculcated the understanding of

BSC in a simple and lucrative manner. Once convinced, employees took interest in

learning and at times simply followed the path showed by the team head.

4. Ownership and the Initiative of the Team: The team set itself stretch targets and came

up with innovative ideas. The notion that they were working for excellence generated

enthusiasm and commitment. A sense of purpose and meaning got into their work.

5. Budget and Resource Availability: The team justified all resource requirements with

sufficient data. For this reason, they did not face problems of budget sanctions and

purchase approvals. They also managed their budgets efficiently to implement their

initiatives and fulfil training needs.

6. Training and Capacity Building: With BSC framework in place, it became easy to

justify and arrange the necessary training and development for the team. The

Page 20: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

272

employees agreed that all team members were given the opportunity to upgrade their

domain skills and knowledge. This was a sentiment shared by all teams.

7. Operational and Strategic Reviews: ISD team held review meetings over breakfast

to discuss performance status against agreed targets every Monday. The monthly and

quarterly BSC reviews assessed if the team was meeting strategic objectives.

Similarly, the EMD team had weekly department meeting for operational reviews and

quarterly reviews of strategy implementation. Thus, there was a balance of operational

and strategic reviews. The process of data collection and compilation was made simple

by instituting systems and easy to use excel templates.

8. Performance Feedback to Employees: During the BSC reviews, team members

could themselves assess their performance and make a comparative analysis of

individual performances. The team leader regularly discussed areas which each team

member needed to develop.

9. Personal Relationship with the Team Heads: Personal relationships were important.

Often, the team leader’s relationship with his team was necessary to overcome

dissatisfaction and de-motivation over the perceived injustices in performance

appraisals.

10. Collective Accountability: All members participated in the review meetings. The

meetings were informal, yet focused on specific agenda. The discussions were more on

issues and targets and not on personal achievements.

11. Value-Based-Management: In both E&P and ISD, the team leader had a humane

approach. They encouraged everyone to participate in the discussions, valued their

ideas and treated them with respect. In return, team members respected and trusted

him. There was stress free environment and people could focus on achieving

performance objectives.

The importance of the commitment and competence of facilitator is obvious from the fact

that in all cases of success, this was the common feature. In the case of E&P, the SBU head

was highly committed to strategy implementation but they could not really do well with

BSC implementation because of the unavailability of support from BSC facilitators.

Page 21: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

273

Similarly, Aviation SBU could have performed better in implementation had there been

continuous support from facilitator as the buy-in of leaders and employees was already

there.

The case of ECR shows, how in the absence of a committed and agile leadership, BSC

implementation could move forward. WCR’s experience emphasises the importance of the

approach of leadership to the situation.

The key success factors can be depicted as shown in Figure 7.2.

Figure 7.2

Key Success Factors for BSC Implementation

The most important factor that emerges in BSC implementation is strategy– focus and

engaged employees. BSC implementation was eventually successful only when the leaders

could get their employees engaged and remain strategy– focused. This is evident from the

cases of ECR-ISD and WCR-EMD. The leaders in these cases adhered strictly to the

implementation procedure. This approach automatically resulted in changes in the ways

they worked. Attention was given to reviews, performance feedback, training and

development etc. which helped in keeping the employees engaged. The leadership style and

values defined the manner in which such things were done.

Value Based

Management

Relationship

Bonds

Collective

Accountability

Regular

Performance

Feedback

BSC Reviews

Capacity

Building

Resource

Availability

BSC Buy-In

Leaders’

Conviction

Facilitators’

Support

BSC Buy-In &

Understanding

Success

Factors

Page 22: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

These differentiating success factors can be further classified at three different levels, i.e.

organisational, leadership and individual as shown in Figure 7.

observed in the cases of successful implementation of BSC.

Key Success Factors at Organ

Thus, this comparative

competent BSC implementation facilitators (BSC Team), committed and agile leadership,

strategy– focused and engaged employees, and the importance of ‘values’ that are held by

individuals and the organ

Organizational

•Culture of Ownership & Accountability

•Capability Building of Employees & Organization (LO)

•Consistent Strategic & Operational Reviews

•Policies and Systems Aligned with Strategy

•Aligned Structure

•Quality of Manpower

•Availability of Budget and Resources

274

These differentiating success factors can be further classified at three different levels, i.e.

adership and individual as shown in Figure 7.3

observed in the cases of successful implementation of BSC.

Figure-7.3

Key Success Factors at Organisational, Leadership and Individual Levels

comparative study brings out the importance and impact of committed and

competent BSC implementation facilitators (BSC Team), committed and agile leadership,

focused and engaged employees, and the importance of ‘values’ that are held by

individuals and the organisation in ensuring successful implementation of BSC.

Organization (LO)

Aligned Structure

Leadership

•Is Committed

•Is Strategy Focused

•Is Business Savvy Decisions

•Is Resourceful

•Is Noble, Wise & Just

•Enables Team Camaraderie

•Empowers Employees

•Develops and Nurtures Relationships

•Gives Performance feedback & Coaches Employees

Individual

•Values -work, Discipline & Gratitude

•Synchronization b/w Personal & Organizational Aspirations

•Awareness and Focus on Vision, Strategy and His Team’s Goals

•Considers his Job Meaningful and Valuable

•Updates Requisite Skills & Competencies

•Ownership & Collective Accountability

•Initiatives & Innovative Thinking

These differentiating success factors can be further classified at three different levels, i.e.

3. These factors were

tional, Leadership and Individual Levels

the importance and impact of committed and

competent BSC implementation facilitators (BSC Team), committed and agile leadership,

focused and engaged employees, and the importance of ‘values’ that are held by

suring successful implementation of BSC.

Individual

- Honesty, Hard work, Discipline & Gratitude

Synchronization b/w Personal & Organizational Aspirations

Awareness and Focus on Vision, Strategy and His Team’s Goals

Considers his Job Meaningful and Valuable

Updates Requisite Skills & Competencies

Ownership & Collective Accountability

Initiatives & Innovative Thinking

Page 23: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

275

7.9. BSC Implementation Challenges in the Context of PSU

As discussed in the literature review, the context of PSUs differs widely from private sector

organisations. The PSU culture is unique to PSU and the study found that it poses

enormous challenges to BSC implementation. This was evident from the interviews of

directors, leaders and employees. Although the interviews would begin with a denial of

problems, the challenges and issues would surface during discussions. Top management

was not free from political pressures and interference. For example, UPCL was bound by

government guidelines in the selection and allocation of work to vendors. There were also

instances when work had to be given to contractors who demanded work based on their

influence in the ministry.

UPCL management has to abide by the targets set by the ministry. There was no scope for

questioning. Under pressure to show performance, managements resorted to shortcuts

regardless of the operational risks.

The directors felt that managing the employee performance management system was a

challenge in itself. There was a conflict between performance rating based on the

individual scorecard and the bell-curve which was the norm in PSUs. They were of the

opinion that the two must be synchronised.

Some PSU specific constraints that were evident in this study are being discussed here:

1. DPE guidelines required the assessment of employee performance to fit on a bell-curve.

Moreover, PRP was disbursed according to the employee’s position on the bell-curve.

While the organisation followed BSC, the ratings were further modified by a moderation

committee in order to ensure the employee performance fits on the bell-curve. This

conflicted with the BSC philosophy of performance assessment. The resulting

dissatisfaction in employees becomes an impediment to BSC implementation.

2. Immediate monetary rewards were not given to employees and PRP was generally

viewed as not being fair. There were other rewards schemes such as ‘Outstanding

Achievement’ and ‘UP-Icon’ etc. All these schemes were operated from the corporate

Page 24: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

276

level. It was not easy for the team heads or even the SBU heads to devise ways to

immediately reward outstanding performance.

3. Senior managers did not have the flexibility to hire and retain talent or fire

underperformers. PSU rules did not allow such discretionary hiring and firing. Hiring

employees at middle and senior levels was not common even though DPE guidelines

give increased flexibility and power to CPSEs.1 Senior management is now allowed to

create and abolish positions, and appoint personnel at all levels except to the board. The

PSUs, however, have yet to put this provision to day-to-day use.

4. The team heads did not have a say in the composition of their teams. Besides, employee

transfers were an essential feature of the organisation. The employees were usually

transferred after three to four years. Though the objective behind these transfers is

laudable and helps in overall development of employees, it also has certain demerits.

When an employee knows that he has limited tenure in each assignment, he tends to

prioritise on objectives that yield personal results in the short term. Long term objectives

are often ignored.

There is also the tendency to blame the work of the predecessors, and undo some of

their good initiatives that may be in practice. New incumbents to a position tend to ask

for a change in the existing scorecards. The process of educating the new incumbents,

getting their buy-in had to be done all over again.

5. Being a PSU, bureaucracy and politics play influential roles in its working. Referring to

the governmental constraints. There is a need to develop a culture of discipline and

professionalism.

6. Job Security is taken for granted in PSUs and government services in India. Thus, while

there is not much incentive to work hard, there is also no deterrent to sluggish working.

It is not uncommon to devote their attention to personal matters during working hours

with the full knowledge that they will not be taken to task.

1 Chapter -7. Delegation of Enhanced Financial Powers to CPSEs. PUBLIC ENTERPRISES

SURVEY 2009-2010, Vol. – 1,

www.dpe.nic.in/sites/upload_files/dpe/files/sur0708/vol1ch8.pdf

Page 25: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

277

7. Systems and procedures are in place, but they are person driven. Accordingly,

performance depended a lot on the values and motives of the leaders as well as the

employees. A culture of discipline and professionalism is required to ensure that the

systems are followed and work gets done efficiently.

8. Government guidelines mandate that other government agencies/ organisations must be

given preference in awarding contracts as vendors. Delays in execution by such vendors

were the norm and could not be attributed to the vendors. It was a challenge to get such

vendors/ contractors aligned to the strategy of UPCL.

9. Sometimes the actions of the vigilance department, even if they are in the organisation’s

interest, block initiative and put the employees in defensive state of mind. One team

leader had advised his team to be very cautious in their actions and not do anything that

might invite scrutiny. Getting caught in vigilance cases has demoralising effect. But

another leader highlighted the positive side. It was true that there are constraints. But

oversight agencies like the vigilance departments actually strengthen the system.

Figure 7.4 shows these PSU specific constraints.

Figure 7.4

BSC Implementation Challenges in the PSU Context

EPMS –Bell Curve

Synchronisation

Constraints of

Financial Rewards

Transfers

Vigilance Phobia

Discipline &

Professionalism

Bureaucracy

Political Interferences

Personal Agendas over

Organisational Objectives

PSU

Constraints

Page 26: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

278

To summarise, it can be said that the culture of the PSU places constraints and pose a big

challenge to BSC implementation that essentially requires a performance oriented dynamic

culture. The structure, systems and the culture in PSUs need an overhaul before a

reasonable degree of success can be achieved.

7.10. Summary of Factors Driving Employee Buy-in for BSC

Employee buy-in for the success of BSC implementation is essential and cannot be

overemphasised. The study also examined the motivating factors that enabled the buy-in.

1. Supervisor’s Commitment to Implement BSC: A committed supervisor invariably

educated his subordinates on BSC concept. He would make his expectations clear about

implementation and work on educating his subordinates on the concepts and benefits of

BSC. Such efforts usually led to the employee’s buy-in. With a majority having

accepted the need for implementation, the sceptics would have no option but to fall in

line. Conversely, employees cannot be expected to achieve anything significant without

a committed supervisor.

2. Employee’s Desire to Bring in Positive Changes in Work Environment: Employees

felt that applying BSC could actually bring about positive changes in their work

environment. The BSC tool gave clarity to their role and responsibilities and empowered

them to work towards a common organisational goal.

3. Expectation of a Fair and Objective Assessment of Performance: BSC was regarded

as a useful tool for fair and objective assessment of employee performance against

predefined targets. The employees hoped that BSC would eliminate bias and the other

shortcomings of the existing EPMS.

4. Employees Inspired by the BSC Facilitator: The facilitator presented the ‘big picture’

of the organisation and showed how individual roles and performance influenced the

organisation’s growth and survival. To make employees feel that they were an important

part of the organisation was considered the facilitator’s biggest achievement.

5. Benefits that Accrued from BSC Implementation: The benefits of successful

implementation were shared with others in the organisation. This encouraged other

Page 27: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

279

leaders and employees and strengthened their commitment to work for success in their

areas.

7.11. Enabling Factors for Enhanced Employees Performance

The factors that enabled and motivated employees to give their best performance were:

1. Team Members and Working Environment: A cohesive team, good interpersonal

relations and amicable work environment encouraged the employees and enabled them

to give their best performance.

2. Work Systems and Resource Availability: Clearly defined systems facilitated smooth

functioning without conflict of interest. Timely availability and adequate resources

facilitated the implementation process as the employees could focus on their work

without worrying about issues over which they had no control.

3. Personal Rapport with Supervisor / SBU head: Good working relationships in an

atmosphere of mutual respect give a sense of security and belonging. Better the

relationship, the better the sense of connectedness.

4. Meaningfulness of the Work: The feeling that they added value gave the employees a

sense of pride.

5. Career Progression: Many employees were open in their admission that they were

motivated by the prospect of promotions and the resulting financial gain.

6. Empowerment: The employees were empowered to prioritise and given the freedom in

their methods to achieve targets. This also made them accountable for their own

performances which became a motivating factor.

7. Personal ‘Values’: A majority of the employees mentioned that, notwithstanding good

working environment and systems, it was their personal values that drives them to

continue giving their best performance to the organisation they work for.

8. Fair and Just Treatment by the Organisation: Employees feel motivated to work for

an organisation if they perceive it to be ‘just and fair’ in its treatment of the employees.

They expected their performance to be appreciated and valued. Justice, fairness, respect,

Page 28: Chapter Seven CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGSshodhganga.inflibnet.ac.in/bitstream/10603/16130/17/17... · 2015. 12. 4. · CROSS CASE ANALYSIS: DISCUSSIONS AND FINDINGS

280

transparency and accountability are qualities that the employees expect in the

organisation.

9. Organisation that Cares: Employee responses show that they are motivated to work in

an organisation that ‘cared’ for its people. ‘Care’ is understood as coaching/ guidance

from the boss and seniors, getting the required training to perform better, and

development for professional capability and personal growth, employee and family

friendly policies, and organisational support by way of medical, housing and other

entertainment and welfare related policies. Employees also expect a genuine concern of

the supervisor to resolve problematic issues, and their support and encouragement. They

want to feel important, respected and empowered.

10. Feeling of Security: An important organisational attribute which motivates the

employees is able leadership. Employees felt that a capable leadership will take into

consideration that employees are important stakeholders and thus it is a business

imperative that their interests are not compromised. Growth in business, market

recognition and improvement in other business indicators are important motivating

factors.

7.12. Summary

Comparative case analyses in this chapter indicate that there are only a few challenges that

vary when looked at from different perspectives of top management, leaders facilitators

and employees. Leadership, culture, capabilities of the employees, leaders and facilitators

and their engagement are pivotal to successful BSC implementation. The context of the

organisation, in this case the PSU context, also impacts BSC implementation. The root

causes for most of these challenges can be traced to the individual human values, beliefs

and behaviour. At organisational level, they are rooted in culture, leadership and

managerial executive abilities. The challenges and the success factors discussed in this

chapter are the basis of the hypothesis discussed in the following chapter.