Chapter 20 Quality Control

Embed Size (px)

Citation preview

  • 8/9/2019 Chapter 20 Quality Control

    1/174

    Chapter 20 Six Sigma

    Management

  • 8/9/2019 Chapter 20 Quality Control

    2/174

    j Six Sigma (a registered trademark of the Motorola

    Corp.) is the relentless and rigorous pursuit of thereduction of variation in all critical processes toachieve continuous and breakthrough improvementsthat impact the bottom line of the organization andincrease customer satisfaction.

    j It is an organizational initiative designed to createmanufacturing, service and administrative processesthat produce approximately 3.4 defects per million.Opportunities (DPMO).

  • 8/9/2019 Chapter 20 Quality Control

    3/174

    Relationship between the Voice of theCustomer and the Voice of the Process

    j Six Sigma management promotes the idea that thedistribution of output for a process (the Voice of theProcess) should take up no more than half of the

    tolerance allowed by the specification limits (theVoice of the Customer)

    j This assumes that the measurement data is from astable and normal distribution of output whose meancan shift by as much as 1.5 standard deviations over

    time.

  • 8/9/2019 Chapter 20 Quality Control

    4/174

    j The following figure shows the Voice of the Customeras spoken in the language of a nominal value, m, and

    the lower and upper specification limits, LSL andUSL, for a quality characteristic.

    j This assumes Distribution of process output is measurement data

    The process is stable

    The distribution is normal

    The process average is on nominal

    The distance between nominal and either specification limitis 3 times the process standard deviation

    j If these five conditions are met we all the process a3-sigma process.

    j A 3-sigma process will produce 2,700 defects permillion opportunities.

  • 8/9/2019 Chapter 20 Quality Control

    5/174

    LSL USL3-sigma Process

  • 8/9/2019 Chapter 20 Quality Control

    6/174

    An Example of a 3-sigma Process

    j The number of days to complete a month accountingreport is stable and normally distributed with anaverage of 7 days and a standard deviation of 1 day.

    j The lower specification limit is 4 days and the upper

    specification limits is 10 days.

  • 8/9/2019 Chapter 20 Quality Control

    7/174

  • 8/9/2019 Chapter 20 Quality Control

    8/174

    j Next we see a quality characteristic represented bymeasurement data that: Is stable

    Is normally distributed

    Has a process output that can shift by as much as 1.5standard deviations on either side of nominal

    Has a distance between nominal and either specificationlimit of 3 standard deviations of process output.

    j This is a 3-sigma process with a 1.5 sigma shift in themean.

    j This process will generate 66,811 defects per million

    opportunities or 93.33189% of its output between thespecification limits.

  • 8/9/2019 Chapter 20 Quality Control

    9/174

  • 8/9/2019 Chapter 20 Quality Control

    10/174

    Accounting process with process average shifts of 1.5

    standard deviations.

  • 8/9/2019 Chapter 20 Quality Control

    11/174

    j Next we see a scenario where the voice of the

    process takes up only half the distance between thespecification limits. The process mean remains thesame, but the process standard deviation has beenreduced to one half-day

  • 8/9/2019 Chapter 20 Quality Control

    12/174

  • 8/9/2019 Chapter 20 Quality Control

    13/174

    Output for the monthly accounting process with the

    standard deviation reduced to one-half day through process

    improvement activities.

  • 8/9/2019 Chapter 20 Quality Control

    14/174

    j Next we will see the voice of the customer and the

    voice of the process for a quality characteristic that: Is represented by measurement data

    Is stable

    Is normally distributed

    Has a process average that can shift by as much as 1.5

    standard deviations on either side of nominal Has the distance between nominal and either specification

    limit is 6 standard deviations of the process output.

    j This is a process that will generate 3.4 defects permillion opportunities, or 99.99966% of its outputwithin specification limits in the near future.

  • 8/9/2019 Chapter 20 Quality Control

    15/174

  • 8/9/2019 Chapter 20 Quality Control

    16/174

    Six sigma accounting process with a 1.5 sigma shift in

    the mean

  • 8/9/2019 Chapter 20 Quality Control

    17/174

    The DMAIC Model

    j The model that is used to improve a process in SixSigma management is called the DMAIC model. Thisstands for: Define

    Measure

    Analyze

    Improve

    Control

  • 8/9/2019 Chapter 20 Quality Control

    18/174

  • 8/9/2019 Chapter 20 Quality Control

    19/174

    Define Phase

    j The define phase involves: Preparing a business charter (rationale for the project)

    SIPOC Understanding the relationships between

    Suppliers

    Inputs

    Process

    Outputs

    Customers

    Gathering and analyzing voice of the customer data toidentify the critical-to-quality (CTQ) characteristicsimportant to customers

    Developing a project charter (statement of the project)

  • 8/9/2019 Chapter 20 Quality Control

    20/174

    Measure Phase

    j The measure phase involves Developing operational definitions for each CTQ

    characteristic

    Performing studies to determine the validity (repeatabilityand reproducibility) of the measurement procedure for each

    CTQ

    Collecting baseline capabilities for each CTQ

    Determining the process capability for each CTQ

  • 8/9/2019 Chapter 20 Quality Control

    21/174

    Analyze Phase

    j The analyze phase involves Identifying upstream variables (xs) for each CTQ

    Operationally defining each x

    Collecting baseline data for each x

    Performing studies to determine the validity (repeatabilityand reproducibility) of the measurement process for each x

    Establishing baseline capabilities for each x

    Understanding the effect of each x on each CTQ

  • 8/9/2019 Chapter 20 Quality Control

    22/174

    Improve Phase

    j The improve phase involves Designing experiments to understand the relationships

    between the CTQs and the xs

    Determining the optimal levels of critical xs that optimize the

    spread, shape and center of the CTQs

    Developing action plans to implement the optimal level of thexs into the process under study

    Conducting a pilot test of the revised process

  • 8/9/2019 Chapter 20 Quality Control

    23/174

    Control Phase

    j The control phase involves Avoiding potential problems with the revised settings of the

    xs through risk abatement planning and mistake-proofing

    Standardizing successful process revisions in training

    manuals

    Controlling the revised settings of the critical xs

    Turning the revised process over to the process owner forcontinuous improvement using the PDSA cycle

  • 8/9/2019 Chapter 20 Quality Control

    24/174

    Benefits and Costs of Six SigmaManagement

    j A successful six sigma program will yield thefollowing benefits to the management of theorganization Improved process flows

    Improved communication through six sigma terminology (forexample, DPMO and process sigma)

    Reduced cycle times

    Enhanced knowledge and enhanced ability to manage thatknowledge

    Higher levels of customer satisfaction

    Higher levels of employee satisfaction

    Increased Productivity

  • 8/9/2019 Chapter 20 Quality Control

    25/174

    Reduced total defects

    Decreased work-in-progress (WIP)

    Decreased inventory Improved capacity and output

    Increased quality and reliability

    Decreased unit costs

    Increased price flexibility

    Decreased time to market

    Faster delivery time

    Increased liquid capital

  • 8/9/2019 Chapter 20 Quality Control

    26/174

    j Resources required by Six Sigma management

    Training time costs Material costs

    Training manual development costs

    Administrative and operating costs for DMAIC projects

    Infrastructure costs such as the sots of constructing and

    using organizational metric tracking systems Monitoring DMAIC project costs

    Anecdotal evidence strongly indicates that he benefitsof a Six Sigma process far outweigh the costs.

  • 8/9/2019 Chapter 20 Quality Control

    27/174

    Six Sigma Roles and Responsibilities

    j The Senior Executive provides the impetus,direction and alignment necessary for the ultimatesuccess of Six Sigma management.

    j Roles and responsibilities of a senior executive Leads the Executive Committee (EC) Participates in high-level policy management and cross-

    functional project teams.

    Monitors and balances all Six Sigma activities to avoid localoptimization and organizational suboptimization.

    Maintains a long-term view of the organization and acts as aliaison to stakeholders

    Conducts Presidential reviews of Six Sigma dailymanagement and cross functional management projects.

  • 8/9/2019 Chapter 20 Quality Control

    28/174

    j Top management must be totally committed to theprocess.

    j The CEO must allocate substantial resources to SixSigma management.

    j Leadership must be willing to engage all levels of theorganization through organizational metric tracking

    systems and daily management and cross-functionalSix Sigma and DMAIC projects.

    j The CEO must have a burning desire to createrevolutionary change in the enterprise.

  • 8/9/2019 Chapter 20 Quality Control

    29/174

    j Members of the Executive Committee (EC) mustoperate with the same level of commitment as the

    senior executive.j The EC must

    Create an organizational metric tracking systemthat cascades, or deploys, key objectives and keyindicators throughout the organization via policymanagement

    Empower the Policy Deployment Committee(PDC) to deploy key objective throughout theorganization through policy management.

    Manage the organizational Six Sigma projectportfolio toward optimization of the entireorganizations bottom line

  • 8/9/2019 Chapter 20 Quality Control

    30/174

    Use catchball to establish a reasonable andequitable project portfolio for each

    division/department within the organization.

    Improve the Six Sigma process through constantiteration of the PDSA cycle.

    Provide the resources necessary for Six Sigma

    management.

  • 8/9/2019 Chapter 20 Quality Control

    31/174

    j The role and responsibilities of a black belt are: Full time change agent

    Master of the change process rather than a master of theprocess under study

    Supervise green belts working on a Six Sigma project

    Prepare a draft project charter for the Six Sigma projectsunder his/her supervision.

    Work closely with a project team to keep it functioning andprogressing toward a conclusion to its Six Sigma project.

    Communicate with the individual responsible for the financialand political well-being of the team

    Serve as the team leader for Six Sigma projects

    Help team members analyze data and design experiments

  • 8/9/2019 Chapter 20 Quality Control

    32/174

    Provide training in Six Sigma theory, tools and methods

    Help team members prepare for management and

    presidential reviews Recommend Six Sigma teams for six Sigma projects

    Lead and coach green belts leading simpler Six Sigmaprojects

    j A black belt must pass a certification examinationand lead at least two successful Six Sigma projects.

  • 8/9/2019 Chapter 20 Quality Control

    33/174

    j Most green belts serve as team members on SixSigma projects.

    j If a green belt acts as a team leader for simplerprojects he/she: Prepares a draft charter for the Six Sigma project

    Selects the project team members

    Communicates with the champion, black belt and processowner concerning the status of the project

    Facilitates the project members

    Provides training in the basic Six Sigma tools and methods.

    j A green belt must pass a certification examination

    and participate in at least one successful Six Sigmaproject.

  • 8/9/2019 Chapter 20 Quality Control

    34/174

    j A master black belts responsibilities are: To be a proven team leader and technical expert

    To be a teacher and mentor of black belts and green belts Simultaneously supervise several black belts and green

    belts

    To be an ambassador (in conjunction with the seniorexecutive, members of the executive committee, and

    champions) of Six Sigma management To work continuously to improve and innovate the Six Sigma

    management process.

    j A master black belt must complete a certificationexamination and successfully supervise at least twoblack belts in their completion of two successful SixSigma projects each.

  • 8/9/2019 Chapter 20 Quality Control

    35/174

    j A champion is a member of the EC, or at least anindividual who is trusted to report directly to a

    member of the EC.j A champion takes a very active leadership and

    sponsorship role in implementing Six Sigmamanagement, and works closely with the EC, blackbelts and master black belts to:

    Translate key objectives and key indicators from his sectionof the organizational metric tracking system into Six Sigmaprojects as a part of policy management

    Prepares an initial draft of a project charter for each SixSigma project under his auspices

    Assigns green belts and black belts to the Six Sigmaprojects under his auspices

    Removes obstacles to the effective functioning of the SixSigma project teams under his auspices

  • 8/9/2019 Chapter 20 Quality Control

    36/174

    Provides a direct line of communication between a Six sigmaproject team and the EC

    Obtains and manages the resources necessary for a SixSigma project team to meet its project charter

    Conducts management review of each Six Sigma projectteam under his auspices focused by providing direction andguidance on the attainment of its project charter

    A champion must pass a certification examination.

  • 8/9/2019 Chapter 20 Quality Control

    37/174

    j A process owneris the individual who has theultimate authority to change a process.

    j The process owner should be identified for everyproject or task that is entered onto an organizationalmetric tracking system.

    j The process owner:

    Monitors the performance of his/her process through keyindicators

    Empowers the people who work in the process

    Works with all Six Sigma project teams in the area to enablethem to successfully complete their projects

    Manages the process after completion to the Six Sigmaproject to sustain the gains made.

  • 8/9/2019 Chapter 20 Quality Control

    38/174

    Continues to improve and/or innovate the process throughthe application of the PDCA cycle.

    j A process owner should pass the championcertification examination.

  • 8/9/2019 Chapter 20 Quality Control

    39/174

    Six Sigma Terminology

    jj UnitUnit A unit is the item (e.g. product or component,service or service step, or time period) to be studiedwith a Six Sigma project.

    jj

    DefectiveDefective A nonconforming unit is a defective.jj DefectDefect A defect is a nonconformance on one of

    many possible quality characteristics of a unit thatcauses customer dissatisfaction.

    jj Defect OpportunityDefect Opportunity a defect opportunity is themost fundamental area for a defect. There may beseveral opportunities for defects within a defined unit.

  • 8/9/2019 Chapter 20 Quality Control

    40/174

    jj Defects perUnit (DPU)Defects perUnit (DPU) - Defects per unit refers tothe average of all defects for a given number of units,

    that is, the total number of defects for n units dividedby n.

    jj Defects per Opportunity (DPO)Defects per Opportunity (DPO) Defects peropportunity refers to the number of defects divided by

    the number of opportunities.jj Defects per Million Opportunities (DPMO)Defects per Million Opportunities (DPMO) DPMO

    equals DPO multiplied by 1,000,000.

    jj Observed YieldObserved Yield Observed yield is the proportion of

    units within specification divided by the total numberof units.

  • 8/9/2019 Chapter 20 Quality Control

    41/174

    jj Rolled Throughput Yield (RTY)Rolled Throughput Yield (RTY) RTY is theproduct of the observed yield s from each step in a

    process. It is the probability of a unit passing throughall steps of a process and incurring no defects.

    jj Process SigmaProcess Sigma Process sigma is a measure of theprocess performance determined by using DPMO

    and a normal distribution table. Process sigma is ametric that allows for process performancecomparisons across processes, departments,divisions, companies, and countries. In Six Sigmaterminology, the sigma value of a process is a metric

    used to indicate the number of defects per millionopportunities, or how well the process is performingwith respect to customer needs and wants.

  • 8/9/2019 Chapter 20 Quality Control

    42/174

    A Six Sigma Case StudyBackground

    j Paper Organizers International (POI) offers a fullrange of filling, organizing, and paper shufflingservices.

    j POI purchases Metallic Securing Devices (MSDs),

    staplers, hole punchers, folders, three-ring binders,and a full range of related products to serve itscustomers in paper handling needs.

    j The employees, or internal customers, of PaperOrganizers use MSDs to organize piles of paperpending placement into folders or binders.

  • 8/9/2019 Chapter 20 Quality Control

    43/174

    j The purchasing department has noticed anincrease in complaints from employees in thePaper Shuffling Department (PSD) about MSDsbreaking and failing to keep papers together.

    j This creates opportunities for client papers to bemixed together.

    j The Purchasing Department would like to improvethe purchasing process for purchasing MSDs toeliminate complaints from employees in the PaperShuffling Department.

  • 8/9/2019 Chapter 20 Quality Control

    44/174

    Origin of the MSD Six Sigma Project

    Mission Statement:

    j

    Put theR

    ightInformation in the right Place.

    j RIP it!

  • 8/9/2019 Chapter 20 Quality Control

    45/174

    POIs Business Objectives and Indicators with Potential Six Sigma Projects

    President Director of Paper Shuffling Department

    BusinessObjectives

    BusinessIndicators

    Area Objectives Area Indicators Potential SixSigma Projects

    Increase thenumber of orders

    # orders /month(c-chart)

    Increase thenumber of ordersin PSD

    # orders inPSD/month(c-chart)

    New CustomerPromotionsProject

    Increase thenumber of POIservices (filing,organizing, etc)utilized by eachcustomer

    1. Average # ofservices utilizedper customer /quarter2. Standarddeviation ofnumber ofservices utilizedpercustomer/quarter(x-bar and s chart)

    Increase thenumber ofservices utilizedby each customerin PSD

    1. Average # ofservices utilizedper PSDcustomer/quarter2. Standarddeviation ofnumber ofservices utilizedper PSDcustomer/quarter(x-bar and s chart)

    Existing CustomerPromotionsProject

    Minimizeproduction costs

    Productioncosts/month(I and MR chart)

    Minimizeproduction costsin PSD

    Production costsin PSD/month(I&MR chart)

    MSDQualityProject

    Eliminateemployeecomplaints

    # of employeecomplaints/month(c-chart)

    Eliminateemployeecomplaints fromPSD

    # of employeecomplaints fromPSD/month(c-chart)

    Employee MoraleProject

  • 8/9/2019 Chapter 20 Quality Control

    46/174

    Individual and Moving Range Chart of Monthly

    Production Costs in the Paper Shuffling Department

    Su

    group

    Individual

    alue

    Mean=

    C

    =

    C

    =

    MovingRange

    R=

    C

    =

    C

    =

    I and MR Chart for Production C

    Production costs are sta le (no special causes such as pointseyond a control limit or too many runs up and down, etc.) in

    the PSD with an average monthly cost of $ , , and astandard deviation of

    $116,672.128$111,672/1d/R 2 !!

  • 8/9/2019 Chapter 20 Quality Control

    47/174

    Distribution of Monthly Production Costs in the PSD

    Production costs are approximately normally distributed.Team members discovered that PSD management considersmonthly production costs to be very high given the volume ofwork being processed by the department.

    ! "

    #

    "

    Production Costs in PSD

    re

    uency

    istogram of Production Costs in PSD

  • 8/9/2019 Chapter 20 Quality Control

    48/174

    Prioritization of Six Sigma Projects

    j Top management generated four potential SixSigma Projects.

    j The following table is used to estimate theimportance of each potential Six Sigma project on

    POIs business objectives.

  • 8/9/2019 Chapter 20 Quality Control

    49/174

    Business Objectives

    Potential Six Sigma Projects

    NewCustomerPromotionsProject

    ExistingCustomerPromotionsProject

    MSDQualityProject

    EmployeeMoraleProject

    Increasethe numberof orders

    WEIGHT

    S

    .35 3 3 0 0

    Increase

    the numberof POIservicesutilized byeachcustomer

    .10 1 3 0 0

    Minimizeproductioncosts

    .40 0 0 9 3

    Eliminateemployeecomplaints

    .15 0 0 9 9

    Weighted Average of Potential SixSigma Projects

    1.15 1.35 4.95 2.55

  • 8/9/2019 Chapter 20 Quality Control

    50/174

    j The cell values are assigned by top managementand are defined as follows: 0 no relationship, 1

    weak relationship, 3 moderate relationship, and9 strong relationship.

    j The Finance Department developed theimportance weights for each business objective tomaximize the impact of Six Sigma projects on the

    bottom-line of the organization.j Consequently, the most critical project in respect to

    the business objectives is the MSD quality project,see 4.95 in the last row of the table.

    j The Champion and Process Owner of the MSD

    process prepared an initial project charter. Itpresented the business case for the MSD qualityproject to the members of the MSD quality projectteam.

  • 8/9/2019 Chapter 20 Quality Control

    51/174

    j The define phase has three components:

    prepare a business case with a project charter do a SIPOC analysis

    conduct a Voice of the Customer analysis.

    Prepare a Business Case with a Project Charter

    j Preparing a business case with project charterrequires team members to answer the followingpartially redundant questions. The redundancy in

    the questions helps team members distill thecritical elements of the business case.

    Define Phase

  • 8/9/2019 Chapter 20 Quality Control

    52/174

    1. What is the name of the process?

    MSD Purchasing Process. The first step in the supply chain for the MSD processis the process for purchasing MSDs.

    Hence, the first operation to be investigated by MSDquality project team members is the process for

    purchasing MSDs. Team members may study other factors that affect thequality of MSDs such as method of use or shelf life at alater time.

  • 8/9/2019 Chapter 20 Quality Control

    53/174

    2. What is the aim of the process?j The aim of the purchasing process as it relates to this project

    is to purchase MSDs that improve the productivity andmorale of the employees in the Paper Shuffling Department(PSD).

    3. What is the business case (economic rationale) for theproject?

    j Question 3 is answered by addressing the following sub-questions.

    3a. Why do the MSD project at all?j According to a judgment sample of 3 employees and 2

    managers from the PSD, team members determined thatMSDs that cannot withstand 4 or more bends are

    unacceptable because they are unlikely to remain intactthroughout the paper shuffling processes and will not holdpapers tightly; this is called durability.

  • 8/9/2019 Chapter 20 Quality Control

    54/174

    j Defective MSDs create costs for POI, for example: papers from different clients may get mixed together if

    not properly bound requiring additional processing time employees may have to use multiple MSDs for one

    project creating additional material costs

    employees get frustrated and do not perform their jobsefficiently and productively increasing labor costs.

    j Additionally, team members discovered that alarge proportion of the boxes containing MSDsarrive to the PSD with 5 or more broken MSDs;this is called functionality.

  • 8/9/2019 Chapter 20 Quality Control

    55/174

    j This creates additional processing costs for POI,for example

    increased unit costs frustrated and non-productive employees and

    managers.

    j Team members used the same judgment sampleas above and determined that approximately 60%

    of individual MSDs do not meet durability criteriaand 60% of MSD boxes do not meet functionalitycriteria. They used the following surveyquestionnaire and the data matrix.

  • 8/9/2019 Chapter 20 Quality Control

    56/174

    SurveyName: ____________________________1. Please estimate the percentage of MSDs that cannot withstand 4 or more bends. _____

    2. Please estimate the percentage of MSD boxes that contain greater than 5 broken MSDs. _____

    Survey Number ResponseQ1 Response Q2

    1 55 70

    2 50 55

    3 60 65

    4 65 60

    5 70 50

    Average 60 60

  • 8/9/2019 Chapter 20 Quality Control

    57/174

    3b. Why do the MSD project now?

    j The Paper Shuffling Department is experiencingvery high monthly production costs.j Also, internal customers, including managers and

    hourly employees, are submitting an increasednumber of complaints as recorded in the

    Purchasing Departments complaint log for thefiscal year 2000: 14 in the first quarter 18 in the second quarter 32 in the third quarter

    j There are 100 hourly workers in the PaperShuffling Department.

  • 8/9/2019 Chapter 20 Quality Control

    58/174

    3c. What business objectives are supported by the MSDproject?

    j The MSD project is most strongly related to theminimize production costs and eliminate employeecomplaints business objectives.

  • 8/9/2019 Chapter 20 Quality Control

    59/174

    3d. What are the consequences of not doing theproject?

    j The consequences of not doing the project aredecreased profit margins due to higher productioncosts and increased employee complaints due tofrustration with materials.

    3e. What projects have higher or equal priority?j At this time, the MSD quality project has the

    highest priority.

  • 8/9/2019 Chapter 20 Quality Control

    60/174

    4. What is the problem statement? What is the pain?

    j Low quality MSDs create additional production

    costs and employee frustration.

    5. What is the goal (desired state) for this project?

    j The Champion and Process Owner of the MSDprocess initially determined that a 100-foldimprovement in MSD quality (durability andfunctionality) should be the goal for the Six Sigmaproject.

    j They derived the concept of a 100-foldimprovement from Motorolas 1986 statedimprovement rate of 10-fold every 2 years, or a100-fold every 4 years during the kickoff of the SixSigma effort.

  • 8/9/2019 Chapter 20 Quality Control

    61/174

    j Since 100-fold improvement means the DPMO woulddecrease from 600,000 to 6,000, and a DPMO of

    6210 represents a 4-sigma process, team membersdecided to use 4-sigma as the goal for the MSDproject.

  • 8/9/2019 Chapter 20 Quality Control

    62/174

    6. What is the project scope?

    j Question 6 is answered by answering the following

    sub-questions.6a. What are the process boundaries?

    j The starting point for the project is when thePurchasing Department receives purchase ordersfrom the PSD.

    j The stopping point for the project is when the PSDplaces MSDs into inventory.

    6b. What, if anything, is out-of-bounds?

    j The project team cannot change the way

    employees handle or use MSDs.

  • 8/9/2019 Chapter 20 Quality Control

    63/174

    6c. What resources are available for the project?

    j The budget for the MSD project is $30,000.00.

    This includes estimated hourly salaries of projectparticipants.

    j Team members, Brian Mercurio and JeremyPressman, are the only project participants that willincur additional job responsibilities as result of the

    project.j Budget estimates show opportunity cost and

    hard costs. The estimated hard costs ($10,500)and total costs ($26,040) are less than the budgetof $30,000.

  • 8/9/2019 Chapter 20 Quality Control

    64/174

    NAME POSITION EstimatedSalary /Hour

    ExpectedNumber of

    Hours

    Per Week

    ExpectedOpportunityCosts for 21weeks

    Expected

    HardCosts for21 weeks

    (directlaborcosts)

    Howard Gitlow Champion $100 2 $4,200

    Dana Rasis Process Owner $50 2 $2,100

    Bettina Arguelles Black Belt $50 5 $5,250

    Brian Mercurio Team Member $25 10 $0 $5,250

    Jeremy Pressman Team Member $25 10 $0 $5,250

    Lindsey Barton Finance Rep. $45 2 $1,890

    Mary Montano ITRep. $50 2 $2,100

    TOTAL $15,540 $10,500

  • 8/9/2019 Chapter 20 Quality Control

    65/174

    6d. Who can approve expenditures?

    j Only the Process Owner, Dana Rasis, can approve

    expenditures.

    6e. How much can the team spend beyond $30,000.00without seeking additional authority?

    j Nothing.

    6f. What are the obstacles and constraints of theproject?

    j The team must work within a $30,000 budget and

    a 21week time constraint.

  • 8/9/2019 Chapter 20 Quality Control

    66/174

    6g. What time commitment is expected of teammembers?

    j Team members are expected to be present atweekly Friday morning meetings from 8:00 a.m.until 9:00 a.m.

    j Team members are also expected to provideprogress of project tasks at each meeting.

    Completion of project tasks may require additionalhours of work per week.

    6h. What will happen to each team members regularjob while he or she is working on the project?

    j If any, overtime hours will be compensated forteam members and support staff. Note: Theestimated rate for overtime labor is 1.5 timesnormal labor. Overtime labor is not included in thebudget.

  • 8/9/2019 Chapter 20 Quality Control

    67/174

    6i. Is there a Gantt chart for the project?

    j Yes.

    Steps Resp. Week

    1 2 3 4 5 6 7 8 9 10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    Define BA X X X X X X

    Mesure BA X X

    Analyze BA X X X

    Improve BA X X X X X X

    Control BA X X X X

  • 8/9/2019 Chapter 20 Quality Control

    68/174

    7. What are the benefits of the project?

    j The soft benefits of the project include eliminatingcomplaints from the Paper Shuffling Departmentand increasing employee morale.

    j The hard (financial) benefits of the project areminimizing labor costs and material costs. The

    hard cost benefits are estimated from the following:

  • 8/9/2019 Chapter 20 Quality Control

    69/174

    100 employees in the Paper Shuffling Departmentx 40 hours/week/paper shuffling employeex 10% of time devoted to clipping

    @ 400 hours/week devoted to clipping in PSDx $25/hour/paper shuffling employee$10,000/week devoted to clippingx 50 weeks/year$500,000/year devoted to clippingx .60 defective clips (judgment sample estimate of durability of thecurrent system)Broken clips are not selected for use on jobs. This

    makes 0.6 a conservative estimate of the percentage of defective clips inthe current system. Note: This conservative estimate does not includeproblems arising from defective clips not detected until after they havebeen used and have caused failure on the job.$300,000/year on defective clipping for current system

    x .0062 defective clips (durability of the proposed system)Again, broken

    clips are not selected for use on jobs.$3100/year on defective clipping for proposed system

  • 8/9/2019 Chapter 20 Quality Control

    70/174

    j Hence, the annual savings on labor costs fromimproving MSD purchasing process is $296,900

    ($300,000 - $3,100).j The PSD incurs a 10% annual employee turn over.

    j To capitalize on savings in labor costs, thedepartment will now higher 4 new employees

    instead of 10 new employees, for a savings of 6full-time employees ($296,900/$25 11,876 hours;11,876/40 hours per week/50 weeks per year5.938 ~ 6 employees saved).

    Note: Alternatively, the PSD may now serve morecustomers with their current employee base.

  • 8/9/2019 Chapter 20 Quality Control

    71/174

    Material Costs:

    100 employees in the Paper Shuffling Department

    x60 projects/week/paper shuffling employee

    x50 weeks/year

    @ 300,000 projects/year requiring 3,000,000 MSDs (10 clips per project on average)

    x.60 defective clips (judgment sample estimate of current system).

    7,500,000* clips must be used to complete 300,000 projectsx.01/clip

    @ $75,000/year on clips in current system

    x.0062 defective clips (proposed system)

    3,018,000** clips must be used to complete 300,000 projects

    x.01/clip

    @ $30,180/year on clips in proposed system

  • 8/9/2019 Chapter 20 Quality Control

    72/174

    Material Costs:

    Note: * 1/(1-.6) 2.5 clips needed to get a good

    clip. So, 3,000,000 x 2.5 7,500,000Note: ** 1/(1-.0062) 1.006 clips needed to get agood clip. So, 3,000,000 x 1.006 3,018,000.

    j Hence, the annual savings on material costs fromimproving MSD purchasing process is $44,820($75,000 - $30,180).

    j This yields an annual total hard benefit savings of

    $341,720.00.

  • 8/9/2019 Chapter 20 Quality Control

    73/174

    8. What are the roles and responsibilities of team members?

    ProjectName: MSD Purchasing Process

    Role Responsibility Stakeholder SupervisorsSignature

    Signature Date

    Champion Howard Gitlow HG 9/1/2000

    Process Owner Dana Rasis DR 9/1/2000

    Team Leader Bettina Arguelles BA 9/2/2000

    Team Member 1 Bryan Mercurio BM 9/3/2000

    Team Member 2 Jeremy Pressmen JP 9/3/2000

    FinanceRep Lindsey Barton LB 9/4/2000

    ITRep Michelle Montano MM 9/4/2000

  • 8/9/2019 Chapter 20 Quality Control

    74/174

    Do a SIPOC Analysisj The second part of the define phase requires that

    team members perform a SIPOC analysis.j A SIPOC analysis is a simple tool for identifying

    the Suppliers and theirInputs into a Process, thehigh level steps of a process, the Outputs of theprocess, and the Customers segments interestedin the outputs.

    Start

  • 8/9/2019 Chapter 20 Quality Control

    75/174

    Purchasingreceives order from

    Paper ShufflingDepartment

    Purchasing agentcalls vendor

    Does vendorhave MSDin stock?

    Place order withvendor

    Receive order fromvendor

    Store productreceived into

    inventory (newboxes go on bottom

    back of shelf)

    PSD removesproducts from

    inventory

    PSD uses Product

    Stop

    No

    Yes

  • 8/9/2019 Chapter 20 Quality Control

    76/174

  • 8/9/2019 Chapter 20 Quality Control

    77/174

    Team members analyze the Voice of theCustomer data by market segment.

    Next, they use all the raw Voice of the Customerdata points to create affinity diagram.

    Themes, called focus points using numbers linkingcolumns 2 and 3 in column 3 in the following tableare identified.

    Next, team members identify the engineering issueunderlying each focus point, called cognitiveissues.

    Then, team members convert each cognitive issueinto one or more quantitative engineeringvariables, called Critical-To-Quality (CTQ)

    variables. Finally, team members develop technical

    specifications for each CTQ.

  • 8/9/2019 Chapter 20 Quality Control

    78/174

    SelectedMarketSegment

    Raw Voice of the Customerdata

    AffinityDiagramtheme (FocusPoint)

    Engineeringissue(Cognitiveissue) CTQ

    Tech.Spec.

    Paperorganizingmanagers

    My employees are frustratedabout the MSDs. They complain

    that they break too fast 1&2

    Variation indurability (1) Durability Ability towithstandbending

    > 4 bendswithoutbreaking

    My employees are complainingthat the MSDs are not holdingup during the organizingprocess. 1

    Variation incolor(2)

    Color Thenumber ofdifferentMSD colors

    1 color ofMSDs

    The employees arecomplaining that the color of theMSDs change from one day tothe next. It seems to beconfusing them. 2

    Variation infunctionality(3)

    Functionality Thenumber ofbrokenMSDs in abox

    < 5brokenMSDs in abox

    My employees are veryunhappy with the purple andblue MSDs. They would preferonly one color of MSDs be usedconsistently 2

    My employees say that morethan 5 MSDs per box arrivebroken. 3

    Ive heard from numerousemployees that the MSDscoming straight from inventoryare already broken. 3

    . . .

  • 8/9/2019 Chapter 20 Quality Control

    79/174

    SelectedMarketSegment

    Raw Voice of the Customerdata

    AffinityDiagramtheme (FocusPoint)

    Drivingissue(Cognitiveissue) CTQ

    Tech.Spec.

    Hourly

    employees

    "The MSDs are falling apart

    before we are ready to file thepapers in to binders. An MSDshould be able to take at least 4bends." 1

    Variation in

    durability (1)

    Durability Ability to

    withstandbending

    > 4 bends

    withoutbreaking

    "The MSDs aren't helping us todo our work efficiently." 1 & 2

    Variation incolor(2)

    Color Thenumber ofdifferentMSD colors

    1 color ofMSDs

    I would prefer if we only usedone color of MSDs. 2

    Variation infunctionality

    (3)

    Functionality Thenumber of

    brokenMSDs in abox

    < 5broken

    MSDs in abox

    I dont understand why we usedifferent colors of MSDs. 2

    "The MSDs just break whentrying to bend them over thepaper stacks. They should takeat least 4 bends" 1

    It is very frustrating when youopen a brand new box of MSDsand find that more than 5 of theclips are already broken. 3

    It is very time consuming to siftout the broken MSDs from abrand new box coming straightfrom inventory. 3

    . . .

  • 8/9/2019 Chapter 20 Quality Control

    80/174

    Returning to the first part of the define phase, team memberscan now define the projects objectives.

    Project Objective 1: Decrease (direction) the percentage ofMSDs that can not withstand 4 or more bends without breaking(measure) bought by the Purchasing Department (process) to00.62% (goal) by January 1, 2003 (deadline). Go for 4-sigma!

    Project Objective 2: Decrease (direction) the percentage of

    boxes of MSDs with more than 5 broken clips (measure)bought by the Purchasing Department (process) to 00.62%(goal) by January 1, 2003 (deadline). Go for 4-sigma!

    A correlation exists between the project objectives. A brokenMSD cannot withstand 4 or more bends because it is already

    broken. Improving the percentage of functional MSDs per boxwill increase the percentage of MSDs that can withstand 4 ormore bends.

    M Ph

  • 8/9/2019 Chapter 20 Quality Control

    81/174

    The measure phase has three steps: operationally define the CTQs perform a gage R&R study on each CTQ develop a baseline for each CTQ.

    Operationally define the CTQs

    First, team members operationally define durabilityand functionality by: establishing criteria for durability and

    functionality developing a test for each set of criteria

    formulating a decision rule for each criteria.

    Measure Phase

  • 8/9/2019 Chapter 20 Quality Control

    82/174

  • 8/9/2019 Chapter 20 Quality Control

    83/174

    Test for a selected MSD

    1. Select the top-front box of MSDs on the shelf in theinventory room.

    2. Close your eyes, then open the box of MSDs, thenhaphazardly select one intact MSD. No switching isallowed.

    3. Utilize the criteria for the selected MSD4. Count the number of bends until breaking

    Decision for a selected MSD

    If the number of bends is u 4, then MSD is conforming.If the number of bends is < 4, then MSD is defective.

  • 8/9/2019 Chapter 20 Quality Control

    84/174

    Operational Definition for CTQ2: Functionality

    Criteria for a box of MSDs: Count the number ofbroken clips. Aclip is broken if it is in 2 pieces, regardless of the relative sizes ofthe pieces. Clips can be broken only into two pieces.

    Testfor a box of MSDs:1. Select the top-front box of MSDs on the shelf in the inventory

    room.2. Count the number ofbroken clips.

    Decision for a box of MSDsIf the number of MSDs that are broken e 5, then the box of MSDs is

    conforming.If the number of MSDs that are broken > 5, then the box of MSDs is

    defective.

    The same box of MSDs is used for both operational definitions.

  • 8/9/2019 Chapter 20 Quality Control

    85/174

    Perform a gage R&R study on each CTQ.

    Team members conduct an attribute Gage R&R(Repeatability and Reproducibility) study on themeasurement system of each CTQ to determine if it isadequate for the needs of the project.

    The measurement of durability requires a destructivetest, hence, a simple Gage R&R study was not done fordurability at this time.

    In the near future, an operational definition of the testing

    process for durability will be established and testing willbe audited to assure consistency.

  • 8/9/2019 Chapter 20 Quality Control

    86/174

    The measurement system for functionality is studied using thefollowing sampling plan.

    1. A shelf in the storage area contains boxes of MSDs purchasedthroughout the week. There are different types of MSD boxes inthe storage area (different vendors, sizes, etc.).

    2. The Gage R&R study required 2 inspectors to sample the same10 boxes of MSDs twice.

    3. The top 10 boxes on the front of the shelf were selected for the

    Gage R&R study.4. The study is repeated as is deemed necessary by PSDmanagement.

    Two PSD managers have the responsibility of inspecting theMSDs for functionality; they are called Inspector 1 (Tom) and

    Inspector 2 (Jerry). BothT

    om and Jerry counted the number ofdefective MSDs, twice, in random order.

    Box Inspector Count Functionality Box Inspector Count Functionality

  • 8/9/2019 Chapter 20 Quality Control

    87/174

    1 1 1 10

    1 1 2 10

    1 2 1 10

    1 2 2 10

    2 1 1 9

    2 1 2 9

    2 2 1 9

    2 2 2 9

    3 1 1 5

    3 1 2 5

    3 2 1 5

    3 2 2 5

    4 1 1 4

    4 1 2 4

    4 2 1 4

    4 2 2 4

    5 1 1 5

    5 1 2 5

    5 2 1 5

    5 2 2 5

    6 1 1 9

    6 1 2 9

    6 2 1 9

    6 2 2 9

    7 1 1 6

    7 1 2 6

    7 2 1 6

    7 2 2 6

    8 1 1 6

    8 1 2 6

    8 2 1 6

    8 2 2 6

    9 1 1 9

    9 1 2 9

    9 2 1 9

    9 2 2 9

    10 1 1 11

    10 1 2 11

    10 2 1 11

    10 2 2 11

    Date of study:

    Gage name:

    Runchart of Fuctionality by Box Inspector

  • 8/9/2019 Chapter 20 Quality Control

    88/174

    Misc:

    Tolerance:

    Reported by:

    11

    10

    9

    8

    7

    6

    5

    4

    54321Box

    Fuctionality

    1

    2

    1110

    9

    8

    7

    6

    5

    4

    109876Box

    Fuctionality

    Runchart of Fuctionality by Box, Inspector

    A Gage Run chart shows that there is no variation within inspectors orbetween inspectors. All the variation is between the 10 boxes ofMSDs. Hence, the measurement system is acceptable to measurefunctionality.

  • 8/9/2019 Chapter 20 Quality Control

    89/174

    Develop a baseline for each CTQ.

    At the beginning of each hour, one box of MSDs isselected from the storage area.

    The procedure for selecting a box of MSDs is simply to

    select the top-front most box on the shelf.T

    he selectionprocess was not altered during a sampling period of two8-hour shifts.

    Baseline capability data is as follows.

  • 8/9/2019 Chapter 20 Quality Control

    90/174

    Th i ld f d bilit d f ti lit b th 0 375

  • 8/9/2019 Chapter 20 Quality Control

    91/174

    The yield for durability and functionality are both 0.375 asdetermined by the number of tests out of 16 trials shown in theprevious table that met their respective CTQs (i.e., at least 4bends for durability, no more than 5 broken MSDs per box forfunctionality).

    This indicates very poor levels of durability and functionalityfor the MSDs received into the Paper Shuffling department andsupports the initial yield estimates of 40.0%, or 60% defectiveMSDs.

    An individuals and moving range (I-MR) chart for thedurability baseline data indicates that the variability ofdurability is not stable over time, see bottom panel of thefollowing chart.

    An investigation of the range between the eight and ninthMSDs did not reveal any obvious special cause of variationthat could be used to improve the durability of MSDs.

  • 8/9/2019 Chapter 20 Quality Control

    92/174

    15105Subgroup 0

    15

    10

    5

    0

    -5IndividualValue

    Mean 3.875

    UCL 12.21

    LCL -4.458

    10

    5

    0M

    ovingRange

    1

    R=3.133

    UCL=10.24

    LCL=0

    I and MR Chart for Durability

    Note: Use of the I-MR chart assumes approximate normality of the CTQ (durability). Thedurability data is clearly not normally distributed, see dot plot that follows.

  • 8/9/2019 Chapter 20 Quality Control

    93/174

  • 8/9/2019 Chapter 20 Quality Control

    94/174

    Hence, use of the durability I-MR chart is not advisedat this time.

    However, the distribution of durability mayapproximate a Poisson distribution. Consequently, team members constructed a c-chart

    for the count of bends before each MSD breaks,see next slide.

    Note: If the durability were measured using a continuousmeasurement system allowing for fractional number of bends beforebreaking, then a log or similar transformation of the distribution may beappropriate before using an Individuals-Moving Range chartingprocedure.

  • 8/9/2019 Chapter 20 Quality Control

    95/174

    The c chart indicated a possible special cause during Shift 2 - Hour 1 when 12bends was observed for the durability test. Further investigation and notes relatedto the test did not reveal any obvious differences between the MSD tested and theothers, although during the first hour the tester indicated that he may have bent theMSD slower than usual during the test which may have caused less stress andconsequently more bends.

  • 8/9/2019 Chapter 20 Quality Control

    96/174

    A c-chart forfunctionality indicates that is stable overtime.

  • 8/9/2019 Chapter 20 Quality Control

    97/174

    The functionality data appears to be approximately Poissondistributed (due to a Goodness of Fit test). Hence, use ofthe functionality c-chart is acceptable at this time.

    Finally team members estimate the current process

  • 8/9/2019 Chapter 20 Quality Control

    98/174

    Finally, team members estimate the current processperformance for each CTQ in the following table.

    Notice the desired 100-fold improvement shown in the DPMO

    columns (Current = 625,000 and Desired = 6,210). This isconsistent with the goals stated in question 5 of the Define Phaseof the DMAIC model.

    CTQs Yield DPMO Process Sigma

    Current Desired Current Desired Current Desired

    Durability 37.50% 99.38% 625,000 6210 ~1.2 4.0

    Functionality 37.50% 99.38% 625,000 6210 ~1.2 4.0

    Analyze Phase

  • 8/9/2019 Chapter 20 Quality Control

    99/174

    The Analyze phase has five steps:

    1. Develop a more detailed process map (that is, moredetailed than the process map developed in theSIPOC analysis of the Define phase)

    2. Construct operational definitions for each input orprocess variable (called Xs)

    3. Perform a gage R&R study on each X (test theadequacy of the measurement system)

    4. Develop a baseline for each X5. Develop hypotheses between the Xs and Ys. The Ys

    are the output measures used to determine if theCTQs are met.

    First, team members prepare a detailed process mapidentifying and linking the Xs and Ys.

    Analyze Phase

    Start

  • 8/9/2019 Chapter 20 Quality Control

    100/174

    Purchasingreceives order from

    Paper ShufflingDepartment

    Purchasing agentcalls vendor

    Does vendorhave MSDin stock?

    Place order with

    vendor

    Receive order fromvendor

    MSDs placed intoinventory (new boxes

    go on the bottomback of shelf)

    PSD removesbox frominventory

    PSD uses MSDs

    Stop

    No

    Yes

    X1 Vendor (Ibix or Office Optimum)X2 Size (Small or Large)X3 Ridges (With or Without)X4 = Cycle time from order to receipt for MSDsX5 = Discrepancy in count from order placed andorder received

    X6 = Cycle time to place product in inventory

    X7 = Inventory shelf time (in days)

    X8 =Type of usage (Large stack of paper or Smallstack of paper)

    D l ti l d fi iti f h X

  • 8/9/2019 Chapter 20 Quality Control

    101/174

    Develop an operational definition for each X.

    Team members develop an operational definition for each X

    variable identified on the process map. The operationaldefinitions for X1, X2, X3 and X8 relate to individual MSDs andare shown below.

    Criteria: Each X conforms to either one or the other of the options.

    Test: Select MSD.Decision: Determine X1, X2, X3, and X8 options for the selectedMSD.

    X1 Vendor Ibix Office Optimum

    X2 Size Small (stock size) Large (stock size)

    X3 Ridges With ridges Without ridges

    X8 Type of Usage Large stack of paper (# papers is 10 or more)

    Small stack ofpaper(# papers is 9 or

    less)

  • 8/9/2019 Chapter 20 Quality Control

    102/174

    The operational definitions for the procedures used tomeasure X4, X5, X6 and X7 are:

    Criteria: Compute cycle time in days by subtracting theorder date from the date on the bill of lading.

    Test: Select a box of MSDs upon receipt of shipment

    from vendor. Compute the cycle time.Decision: Determine X4 for the selected box of MSDs.

    X4 Cycle time from order toreceipt for MSDs

    In days

  • 8/9/2019 Chapter 20 Quality Control

    103/174

    Criteria: Count the number of boxes of MSD received fora given order. Subtract the number of boxes ordered

    from the number of boxes received for the order understudy.

    Test: Select a particular purchase order for MSDs.

    Decision: Compute the value of X5 in number of boxesfor the selected purchase order.

    X5 Discrepancy in count fromorder placed and orderreceived

    In boxes of MSDs by order

    Criteria: Compute cycle time in days to place a shipment of MSDs in

  • 8/9/2019 Chapter 20 Quality Control

    104/174

    Criteria: Compute cycle time in days to place a shipment of MSDs ininventory by subtracting the date the shipment was received from thedate the order was place in inventory.

    Test: Select a particular purchase order.

    Decision: Compute the value of X6 in days for the selected purchaseorder.

    Criteria: Compute inventory shelf-time in days for a box of MSDs bysubtracting the date the box was placed in inventory from the datethe box was removed from inventory.

    Test: Select a box of MSDs.

    Decision: Compute the value of X7 in days for the selected box ofMSDs.

    X6 Cycle time to place product in inventory In days

    X7 Inventory shelf time In days

  • 8/9/2019 Chapter 20 Quality Control

    105/174

    Conduct Gage R&R studies on Xs.

    Recall, that the purpose of a Gage R&R study is todetermine the adequacy of the measurement system foran X.

    In this case, the measurement systems for all of the Xsare known to be reliable and reproducible, hence, GageR&R studies were not conducted by team members.

    Collect baseline data for each X

  • 8/9/2019 Chapter 20 Quality Control

    106/174

    Collect baseline data for each X.

    Team members gathered baseline data on durability(Y1) and functionality (Y2), and relevant Xs using thefollowing sampling plan:

    For a two-week period the first box of MSDs broughtto the PSD each hour was selected as a sample; thisyielded a sample of 80 boxes of MSDs

    For each sampled box, team members determined thedurability (Y1) and functionality (Y2) measurement.Furthermore, they collected information concerning

    the vendor (X1), size of the MSD (X2), whether or notthe MSD has ridges (X3), and inventory shelf life willbe recorded (X7).

  • 8/9/2019 Chapter 20 Quality Control

    107/174

    Note that Purchasing Department will separately studycycle time from order to receipt of order (X4), discrepancy

    between ordered and received box counts (X5), and cycletime from receipt of order to placement in inventory (X6). These last factors may influence such concerns aschoice of vendor, ordering procedures, and inventorycontrol, but they do not impact durability and functionality.

    Furthermore, the MSDs are not tested after they areused so the type of usage (X8) is not studied here.As was indicated in the Define phase, certain variables(e.g., X4, X5, X6, and X8) can be addressed in subsequentGreen Belt projects.

    The following show the baseline data for the Xs.

    Sample Day Hour X1 X

    2 X3 X7 Durability Function

  • 8/9/2019 Chapter 20 Quality Control

    108/174

    Sample Day Hour X1 X2 X3 X7 Durability Function1 Mon 1 1 0 0 7 2 52 Mon 2 0 1 0 7 2 93 Mon 3 0 0 1 7 10 74 Mon 4 0 1 0 7 1 4

    5 Mon 5 0 0 0 7 7 36 Mon 6 0 1 1 7 2 57 Mon 7 0 1 1 7 1 98 Mon 8 0 0 0 7 7 59 Tue 1 0 1 0 8 2 810 Tue 2 0 1 0 8 1 711 Tue 3 0 1 0 8 1 1312 Tue 4 1 1 1 8 9 513 Tue 5 1 1 0 8 9 9

    14T

    ue 6 1 1 1 8 10 1115 Tue 7 1 1 1 8 10 1116 Tue 8 0 0 1 8 8 917 Wed 1 1 1 1 9 8 1118 Wed 2 1 0 0 9 1 1119 Wed 3 1 1 1 9 10 1120 Wed 4 0 0 0 9 7 1121 Wed 5 1 1 1 9 9 922 Wed 6 0 0 1 9 9 523 Wed 7 1 0 1 9 2 1124 Wed 8 1 0 0 9 1 1025 Thu 1 1 0 1 10 1 1426 Thu 2 0 1 1 10 1 1027 Thu 3 1 1 1 10 8 1328 Thu 4 0 0 1 10 10 1229 Thu 5 0 0 0 10 7 1430 Thu 6 0 1 1 10 3 13

    Sample Day Hour X1 X

    2 X3 X7 Durability Function31 Thu 7 0 0 0 10 9 13

  • 8/9/2019 Chapter 20 Quality Control

    109/174

    31 Thu 7 0 0 0 10 9 1332 Thu 8 1 1 1 10 8 1133 Fri 1 0 1 0 1 2 034 Fri 2 0 1 0 1 2 135 Fri 3 0 1 0 1 1 6

    36 Fri 4 0 1 0 1 3 337 Fri 5 0 1 0 1 2 238 Fri 6 1 1 0 1 10 639 Fri 7 0 0 1 1 10 040 Fri 8 0 1 0 1 2 041 Mon 1 0 1 1 4 3 442 Mon 2 0 1 0 4 3 743 Mon 3 0 1 1 4 3 344 Mon 4 0 0 0 4 10 2

    45 Mon 5 1 1 0 4 8 546 Mon 6 0 1 1 4 3 447 Mon 7 1 0 0 4 1 448 Mon 8 0 0 1 4 10 549 Tue 1 1 1 1 5 11 650 Tue 2 1 0 1 5 3 451 Tue 3 1 1 0 5 10 652 Tue 4 1 0 1 5 3 553 Tue 5 1 0 0 5 2 454 Tue 6 0 0 0 5 9 555 Tue 7 0 0 1 5 9 556 Tue 8 0 1 0 5 3 757 Wed 1 0 0 1 6 9 558 Wed 2 1 1 0 6 9 759 Wed 3 0 0 0 6 9 560 Wed 4 1 0 0 6 2 6

    Sample Day Hour X1 X

    2 X3 X7 Durability Function

  • 8/9/2019 Chapter 20 Quality Control

    110/174

    p y 1 2 3 7 y61 Wed 5 1 0 1 6 2 562 Wed 6 1 1 1 6 10 563 Wed 7 0 1 0 6 1 764 Wed 8 0 1 0 6 2 5

    65 Thu 1 0 0 1 7 10 766 Thu 2 1 1 0 7 9 567 Thu 3 1 0 0 7 1 768 Thu 4 0 1 0 7 2 569 Thu 5 1 0 1 7 1 670 Thu 6 0 1 0 7 1 571 Thu 7 1 0 0 7 1 872 Thu 8 1 1 1 7 10 573 Fri 1 0 1 1 8 3 7

    74 Fri 2 1 1 1 8 9 775 Fri 3 1 0 0 8 1 1376 Fri 4 0 1 1 8 2 877 Fri 5 0 1 1 8 3 978 Fri 6 1 1 1 8 8 1079 Fri 7 1 0 1 8 3 1180 Fri 8 0 0 1 8 10 11

    Legend:X1 = Vendor (0 = Office Optimum and 1 = Ibix)X2 = Size (0 = Small and 1 = Large)X3 =Ridges (0 = Without and 1 = With)X7 = Inventory shelf time, in days

    Collect Baseline Data for Each X

  • 8/9/2019 Chapter 20 Quality Control

    111/174

    Collect Baseline Data for Each X.

    The baseline data revealed that the yield for durabilityis 0.4625 (37/80) and the yield for functionality is0.425 (34/80), see the next table.

    As before, this indicates very poor levels for the CTQsin the Paper Shuffling Department.

    For comparison purposes the judgment samplecarried out by the team during the Define phaseshowed that the yield was approximately 40% (i.e., theteam assumed the failure rate was approximately

    60%) for both durability and functionality.

    Th li ht i d i ld i thi t d b d t

  • 8/9/2019 Chapter 20 Quality Control

    112/174

    The slight increased yields in this study can be due tonatural variation in the process.

    The baseline data also showed that 56.25% of allMSDs are from Office Optimum (X1), 42.50% ofMSDs are small (X2), 50.00% of all MSDs are withoutridges (X3), and the average shelf time for boxes of

    MSDs (X7) is 6.5 days, with a standard deviation of2.5 days, see the next table.

  • 8/9/2019 Chapter 20 Quality Control

    113/174

    Basic statistics on baseline data

    Variable Proportion Mean Standarddeviation

    Y1: Durability 4or morebends/clip

    0.4625 5.213 3.703

    Y2: Functionality 5 or fewer broken/box

    0.4250 7.025 3.438

    X1: Vendor 0=OfficeOptimum1=Ibix

    0.56250.4375

    X2: Size 0=Small1=Large

    0.42500.5750

    X3: Ridges 0=Without

    Ridges1=WithRidges

    0.5000

    0.5000

    X7: Inventory ShelfTime

    Shelf time indays

    6.5000 2.5160

    Develop hypothesis between Xs and Ys.

  • 8/9/2019 Chapter 20 Quality Control

    114/174

    Develop hypothesis between Xs and Ys.

    Team members develop hypotheses [Y=f(X)] about the

    relationships between the Xs and the Ys to identify the Xsthat are critical to improving the center, spread and shapeof the Ys in respect to customer specifications.

    This is accomplished through data mining. Data mining isa method used to analyze passive data; that is, data that is

    collected as a consequence of running a process. In this case, the baseline data is the passive data set thatwill be subject to data mining procedures.

    Dot plots or box plots of durability (Y1) and functionality (Y2)stratified by X1, X2, X3 and X7 can be used to generatesome hypotheses about main effects (i.e., the individual

    effects of each X on Y1 and Y2).

  • 8/9/2019 Chapter 20 Quality Control

    115/174

    Interaction plots can be used to generate hypotheses aboutinteraction effects (i.e., those effects on Y1 orY2 for which

    the influence of one X variable depend on the level or valueof another X variable) if all combinations of levels of Xvariables are studied.

    If all combinations of levels of X variables are not studied,then often interaction effects are not discovered.Frequently, screening designs are utilized to uncoverinteraction effects.

    Team members constructed dot plots from the baselinedata to check if any of the Xs (i.e., main effects) impactdurability (Y1) and functionality (Y2).

    The dot plots for durability an functionality are:

  • 8/9/2019 Chapter 20 Quality Control

    116/174

    Dot plot for durability by X1 (i.e., vendor)

  • 8/9/2019 Chapter 20 Quality Control

    117/174

    Dot plot for durability by X2 (i.e., size)

  • 8/9/2019 Chapter 20 Quality Control

    118/174

    Dot plot for durability by X3 (i.e., ridges)

  • 8/9/2019 Chapter 20 Quality Control

    119/174

    Dot plot for durability by X7 (i.e., shelf life)

  • 8/9/2019 Chapter 20 Quality Control

    120/174

    Dot plot for functionality by X1 (i.e., vendor)

  • 8/9/2019 Chapter 20 Quality Control

    121/174

    Dot plot for functionality by X2 (i.e., size)

  • 8/9/2019 Chapter 20 Quality Control

    122/174

    Dot plot for functionality by X3 (i.e., ridges)

  • 8/9/2019 Chapter 20 Quality Control

    123/174

    Dot plot for functionality by X7 (i.e., shelf life)

  • 8/9/2019 Chapter 20 Quality Control

    124/174

    The dot plots for durability (Y1) indicate:

    1.T

    he values of durability tend to be low or high with a significantgap between 4 and 6 for X1, X2, X3 and X7, and2. The variation in durability is about the same for all levels of X1,

    X2, X3 and X7.

    The dot plots for functionality (Y2) indicate:

    1. The values of functionality tend to be lower when X1 = 0 thanwhen X1 = 1

    2. The variation in functionality is about the same for all levels of X2and X3

    3. The values of functionality tend to be lower for low values of X7.

    Discussion of the Analysis ofDurability.

  • 8/9/2019 Chapter 20 Quality Control

    125/174

    Since there are no clear differences in variation (i.e.,

    spread) of durability for each of the levels of X1, X2, X3and X7, the team wondered if there might bedifferences in the average (i.e., center) for each levelof the individual Xs.

    Team members constructed a main effects plot fordurability to study differences in averages, seefollowing figure.

  • 8/9/2019 Chapter 20 Quality Control

    126/174

    Main effects plot for durability by X1, X2, X3, and X7.

    Develop hypothesis between Xs and Ys.

  • 8/9/2019 Chapter 20 Quality Control

    127/174

    p yp

    The main effects plot for durability indicates that:

    For the range of shelf lives observed there is no clearpattern for the relationship of shelf life (X7) to theaverage Durability.

    On the other hand, it appears that ridges (i.e., X3 = 1)

    has a positive relationship to the average Durability. At first glance it would seem that the better results for

    the average Durability are seen when the vendor Ibixis chosen using small MSDs (i.e., X1 = 1 and X2 = 0),while using large MSDs from Office Optimum

    (i.e., X1 = 0 and X2 = 1) yield worse results.

  • 8/9/2019 Chapter 20 Quality Control

    128/174

    While discussing the dot plots and main effects plot itwas suggested that it is dangerous to make any

    conclusions without knowing if there are interactioneffects.

    An interaction effect is present when the amount ofchange introduced by changing one of the Xs

    depends on the value of another X.

    In that case, it is misleading to choose the best valueof the Xs individually without first considering theinteractions between the Xs.

    Consequently, team members did an interactions plot

  • 8/9/2019 Chapter 20 Quality Control

    129/174

    Consequently, team members did an interactions plotfor X1, X2, and X3.

    X7 was not included in the interactions plot becausethe main effects plot indicated no clear pattern orrelationship with durability (Y1).

    All combinations of levels of the X variables must be

    present to draw an interactions plot.

    This is often not the case with passive data (i.e., noplan was put in place to insure all combinations wereobserved in the data gathering phase).

    Fortunately, although not all combinations wereobserved equally often they were all present.

    Interaction effects plot for durability by X1, X2, and X3

  • 8/9/2019 Chapter 20 Quality Control

    130/174

  • 8/9/2019 Chapter 20 Quality Control

    131/174

    Interestingly, the interaction plot indicates that there isa possible interaction between X1 (i.e., vendor) and

    X2 (i.e., size).

    How is this known?

    When there is no interaction the lines should be

    parallel to each other indicating the amount of changein average Durability when moving from one level ofeach X variable to another level should be the samefor all values of another X variable.

    This plot shows the lines on the graph of X and X

  • 8/9/2019 Chapter 20 Quality Control

    132/174

    This plot shows the lines on the graph of X1 and X2not only are not parallel, but they cross.

    The average Durability is the highest when eitherlarge Ibix MSDs (i.e., X1 = 1 and X2 = 1) or smallOffice Optimum MSDs (i.e., X1 = 0 and X2 = 0) areused.

    This means the choice of vendor may depend on thesize of MSD required.

    The main effects plot suggests that the best results

  • 8/9/2019 Chapter 20 Quality Control

    133/174

    for average Durability would occur when small MSDsfrom Ibix are used, but the interactions plot suggests

    this combination would yield a bad average Durability.

    In order to study all this further the team decides thatduring the Improve phase they will run a full factorialdesign to examine the relationship of X1, X2, and X3

    on Durability (Y1) since the main effects plot indicatespotential patterns.

    Again, there does not appear to be a relationshipbetween Durability (Y1) and X7.

    Discussion of the Analysis of Functionality

  • 8/9/2019 Chapter 20 Quality Control

    134/174

    Discussion of the Analysis ofFunctionality

    Main effects plot for functionality by X1, X2, X3, and X7.

    Interaction effects plot for functionality by X1, X2, and X3

  • 8/9/2019 Chapter 20 Quality Control

    135/174

    The main effects plot indicates that higher values ofh lf lif (X ) i ld hi h l f F ti lit (Y )

  • 8/9/2019 Chapter 20 Quality Control

    136/174

    shelf life (X7) yield higher values for Functionality (Y2).

    The team surmised that the longer a box of MSDs sitsin inventory (i.e., higher values of shelf life), thehigher the count of broken MSDs (i.e., functionalitywill be high).

    From a practical standpoint, the team felt comfortablewith this conclusion.

    They decided the Purchasing Department should puta Six Sigma project in place to investigate whether

    the potential benefit of either a just in time MSDordering process or establishing better inventoryhandling procedures will solve the problem.

    The interaction effects plot indicate a potentialinteraction between the X (i e size) and X (i e

  • 8/9/2019 Chapter 20 Quality Control

    137/174

    interaction between the X2 (i.e., size) and X3 (i.e.,ridges).

    The better results for functionality (i.e., low values)were observed for large MSDs without ridges(i.e., X2 = 1 and X3 = 0). Why this may be the casewould need to be studied further.

    Also, there may be an interaction between X1 (i.e.,vendor) and X2 (i.e., size), but it appears that betterresults are observed whenever Office Optimum isused (i.e., X1 = 0).

    In other words, the average count of broken MSDs islower (i.e., functionality average is lower) wheneverOffice Optimum is the vendor.

    Analyze Phase Summary.

  • 8/9/2019 Chapter 20 Quality Control

    138/174

    The Analyze Phase resulted in the following hypotheses:

    Hypothesis 1: Durability =f(X1=Vendor, X2=Size,X3=Ridges) with a strong interaction effect betweenX1 and X2.

    Hypothesis 2: Functionality =f (X1=Vendor, X2=Size,

    X3 =Ridges, X7=Shelf Life) with the primary driverbeing X7 with some main effect due to X1 and aninteraction effect between X2 and X3.

    X7 is the main driver of the distribution of Functionality(Y2) and is under the control of the employees of POI.

    Hence, team members restructured Hypothesis 2 asfollows:

    Functionality =f(X1=Vendor, X2=Size, X3=Ridges) foreach fixed level of X7 (Shelf Life).

    Improve Phase

  • 8/9/2019 Chapter 20 Quality Control

    139/174

    The improve phase involves:

    Designing experiments to understand the relationshipbetween the Ys and the vital few Xs and major noisevariables

    Generating the actions needed to implement thelevels of the vital few Xs that optimize the shape,spread and center of the distributions of the Ys

    Developing action plans

    Conducting pilot test of the action plans.

    Conduct Experiments.

  • 8/9/2019 Chapter 20 Quality Control

    140/174

    First, team members conducted an experimental

    design to determine the effect of X1 (Vendor), X2(Size), and X3 (Ridges), and their interactions, on theYs with X7 = 0 (no shelf life MSDs are testedimmediately upon arrival to POI before they areplaced in inventory).

    A 23 full factorial design with 2 replications (8 trials)was performed for durability and functionality.

    The factor conditions for Vendor (X1) are Office

  • 8/9/2019 Chapter 20 Quality Control

    141/174

    1

    Optimum (-1) or Ibix (1); the factor conditions for Size

    areSmall (-1) or

    Large (1), and the factorsconditions forRidges (X3) are Without Ridges (-1)

    orWith Ridges (1).

    The experiment was setup in two blocks to increase

    experimental reliability, with the first 8 runs conductedin the morning and the second 8 runs conducted inthe afternoon.

    The runs were randomized within each block

  • 8/9/2019 Chapter 20 Quality Control

    142/174

    The runs were randomized within each block.

    The purpose of the blocks and randomization is tohelp prevent lurking (background) variables that arerelated to time (e.g., time of day and order in whichdata is collected) from confusing the results.

    Additional information can be gathered since 16 trials

    were run, rather than the minimum of 8 trials,especially regarding potential interactions.

    The data from the 23 full factorial design, with 2replications in run order with the first 8 runsconstituting the first replicate, is:

    Std Order Run Order Vendor Size Ridges Durability Functionality

    2 1 Ibix Small Without 1 8

    4 2 Ibix Large Without 9 9

  • 8/9/2019 Chapter 20 Quality Control

    143/174

    4 2 Ibix Large Without 9 9

    3 3 Office Optimum Large Without 1 8

    8 4 Ibix Large With 11 8

    5 5 Office Optimum Small With 10 06 6 Ibix Small With 4 2

    7 7 Office Optimum Large With 4 3

    1 8 Office Optimum Small Without 10 2

    16 9 Ibix Large With 9 3

    10 10 Ibix Small Without 3 0

    12 11 Ibix Large Without 9 0

    14 12 Ibix Small With 3 7

    13 13 Office Optimum Small With 9 6

    11 14 Office Optimum Large Without 2 4

    9 15 Office Optimum Small Without 8 1

    15 16 Office Optimum Large With 2 4

    Pareto Chart of Effects for Durability

  • 8/9/2019 Chapter 20 Quality Control

    144/174

    The major effects (i.e., those that have significance level less than.10, in other words over 90% confidence level) for Durability are theinteraction of Vendor and Size and the main effect due to Ridges.

    Pareto Chart of Effects for Functionality

  • 8/9/2019 Chapter 20 Quality Control

    145/174

    j There are no significant effects due to Vendor, Size,Rid t f F ti lit

  • 8/9/2019 Chapter 20 Quality Control

    146/174

    orRidges present for Functionality.j This indicates that since the effect of Shelf Life was

    held constant in this designed experiment, while itwas shown to affect Functionality in the data mininganalysis, the team can restrict its attention toimproving Functionality by addressing Shelf Life first.

    j As Durability is the only outcome influenced by

    Vendor, Size, orRidges in this designed experiment,further consideration in this study will be restricted toDurability.

    j Another project can address Shelf Life and its effecton Functionality.

    Since interaction effects should be interpreted prior tostudying main effects the team decided to construct

  • 8/9/2019 Chapter 20 Quality Control

    147/174

    studying main effects the team decided to constructan interaction effect plot for Vendor and Size.

    The interaction effect plot between Size and Vendor

  • 8/9/2019 Chapter 20 Quality Control

    148/174

    The interaction effect plot between Size and Vendorindicates that the best results for Durability are

    obtained using small MSDs supplied by OfficeOptimum or large MSDs supplied by Ibix.

    The reasons for this interaction may be due to factorssuch as materials used for each size MSD,

    differences in supplier processes for each size MSD,or other supplier-dependent reasons.

    Team members can ask each vendor why their sizesshow significant differences in average durability if

  • 8/9/2019 Chapter 20 Quality Control

    149/174

    show significant differences in average durability, ifthere is a preference to use only one vendor.

    Otherwise, the Purchasing Department should buysmall MSDs from Office Optimum or large MSDsfrom Ibix to optimize Durability (Y1).

    The only significant main effect not involved within asignificant interaction effect is X3 =Ridges.

    The main effect forRidges on Durability is shownnext.

  • 8/9/2019 Chapter 20 Quality Control

    150/174

    The main effect ofRidges indicates that the averageDurability is about 6 5 5 4 = 1 1 more when an MSD

  • 8/9/2019 Chapter 20 Quality Control

    151/174

    Durability is about 6.5 5.4 1.1 more when an MSDwith Ridges is used rather than an MSD without

    Ridges.

    Therefore, since Ridges is a main effect independentof any interaction effects, then the right selection ofMSDs is to use Office Optimum for small MSDs with

    ridges and Ibix for large MSDs with ridges.

    If the experimental results are used, then the averageDurability for Office Optimums small MSDs withridges is (10 + 9) / 2 = 9.5 while the average

    Durability for Ibixs large MSDs with ridges is (11 + 9)/ 2 = 10.0.

    Both averages are well above the requireddi CTQ f t l t 4

  • 8/9/2019 Chapter 20 Quality Control

    152/174

    corresponding CTQ of at least 4.

    As long as the variation (spread) of results is smallenough so that no individual Durability result is farfrom these averages, then the team is successfulwith respect to Durability.

    The variation in these results can be monitored usingcontrol charts after changing the purchasing processfor selecting MSDs.

    The team members decided to purchase all MSDs

  • 8/9/2019 Chapter 20 Quality Control

    153/174

    The team members decided to purchase all MSDsWith Ridges.

    In addition, the choice of Vendor and Size will be asfollows: (Vendor= Office Optimum) and (Size =Small) or (Vendor= Ibix) and (Size = Large) tomaximize average durability.

    In addition, the team decided to take on anotherproject to reduce Shelf Life to less than 5 days toaddress Functionality.

    The revised flowchart for the Purchasing Departmentincorporating the findings of the Six Sigma project isshown next.

    Start

    Purchasing Department receives an orderfrom the Paper Shuffling Department

  • 8/9/2019 Chapter 20 Quality Control

    154/174

    Purchasing agent calls Ibix to place an order A

    Are large MSDswith ridgesavailable

    Yes

    No

    Place an order for MSDs with IbixPurchasing agent calls Office Optimum

    Are small MSDswith ridgesavailable

    YesPlace an order forMSDs with Office

    Optimum

    Receive order from vendor

    No

    Wait one day and call again

    A

    Store product received into inventory

    PSD removes MSDs from inventory

    PSD uses MSDs

    Stop

    Pilot Test.

  • 8/9/2019 Chapter 20 Quality Control

    155/174

    The team members conducted a pilot test of therevised best practice (flowchart). Data for durabilityfrom the pilot test is:

    HourVendor Size Ridges Durability

    Shift 1 Hour 1 Office Optimum

    Ibix

    Small

    Large

    With

    With

    10

    11Shift 1 Hour 2 Office Optimum

    IbixSmallLarge

    WithWith

    711

    Shift 1 Hour 3 Office OptimumIbix

    SmallLarge

    WithWith

    1011

    Shift 1 Hour 4 Office OptimumIbix

    SmallLarge

    WithWith

    811

    Shift 1 Hour 5 Office Optimum

    Ibix

    Small

    Large

    With

    With

    9

    10

    Shift 1 Hour 6 Office OptimumIbix

    SmallLarge

    WithWith

    99

    Shift 1 Hour 7 Office OptimumIbix

    SmallLarge

    WithWith

    811

    Shift 1 Hour 8 Office OptimumIbix

    SmallLarge

    WithWith

    910

    Shift 2 Hour 1

    Office Optimum Small With 9

  • 8/9/2019 Chapter 20 Quality Control

    156/174

    Office OptimumIbix

    SmallLarge

    WithWith

    911

    Shift 2 Hour 2

    Office OptimumIbix

    SmallLarge

    WithWith

    810

    Shift 2 Hour 3

    Office OptimumIbix

    SmallLarge

    WithWith

    109

    Shift 2 Hour 4

    Office OptimumIbix

    SmallLarge

    WithWith

    79

    Shift 2 Hour 5

    Office OptimumIbix

    SmallLarge

    WithWith

    710

    Shift 2 Hour 6

    Office OptimumIbix

    SmallLarge

    WithWith

    911

    Shift 2 Hour 7

    Office OptimumIbix

    SmallLarge

    WithWith

    109

    Shift 2 Hour 8

    Office OptimumIbix

    SmallLarge

    WithWith

    811

    RTY 32/32=1

    The RTY for durability is 100%.

    Functionality was also tested but not shown here

  • 8/9/2019 Chapter 20 Quality Control

    157/174

    Functionality was also tested, but not shown here,using Shelf Life = 0 days; that is, the MSDs weretested immediately upon arrival to POI before theywere placed in inventory.

    It resulted in a RTY of 75% that is better than thebaseline RTY.

    The effect on Functionality of Shelf Life and inventorycontrol procedures will be investigated in subsequentprojects if management decides these projects shouldbe chartered.

    With all things being equal, large MSDs from Ibixshould have a higher average durability then smallMSDs from Office Optimum.

  • 8/9/2019 Chapter 20 Quality Control

    158/174

    Control Chart for Durability for small MSDs from OfficeOptimum

  • 8/9/2019 Chapter 20 Quality Control

    159/174

    Control Chart for Durability for Large MSDs from Ibix

    I an MR Chart for Large MSDs f

  • 8/9/2019 Chapter 20 Quality Control

    160/174

    Subgrou

    In

    iiual

    alue

    Mean=

    CL=

    LCL=

    Mo

    ingRange

    R=

    CL=

    LCL=

    I an MR Chart for Large MSDs f

    Durability (Y1) is in control, but it is dangerous tocompute any process capability statistics due to the

    ll l i

  • 8/9/2019 Chapter 20 Quality Control

    161/174

    small sample sizes.

    However, estimates for the mean and standarddeviation of Small MSDs from Office Optimum are8.625 and 1.05 (calculated from the data but thecalculation is not shown here), respectively.

    The mean and standard deviation for Large MSDsfrom Ibix are 10.25 and 0.83, respectively.

    Since the CTQ for durability requires the number ofbends to be 4 or more, then this requirement is 4.4

  • 8/9/2019 Chapter 20 Quality Control

    162/174

    qstandard deviations below the mean for Small MSDs

    from Office Optimum and 7.5 standard deviationsbelow the mean for Large MSDs from Ibix.

    Team members all agreed that as long as theprocess for both Small MSDs from Office Optimumwith ridges and Large MSDs from Ibix with ridgesremain in control, then it is extremely unlikely that theMSDs will fail the CTQ for Durability (Y1).

  • 8/9/2019 Chapter 20 Quality Control

    163/174

    Mistake Proof the Revised Process.

    Team members identified and prioritized two

  • 8/9/2019 Chapter 20 Quality Control

    164/174

    Team members identified and prioritized twoproblems while mistake proofing the processimprovements discovered in the improve phase; theywere:

    1. Purchasing agents do not specify with ridges on apurchase order

    2. Purchasing agents do not consider that the choice ofvendor depends on the size of the MSDs beingrequested on the purchase order.

    Team members created solutions that makeboth errors impossible; they are:

  • 8/9/2019 Chapter 20 Quality Control

    165/174

    both errors impossible; they are:

    The purchase-order entry system does not processorder unless with ridges is specified on thepurchase order

    The purchase-order entry system does not processan order unless Office Optimum is the selectedvendor for small MSDs and Ibix is the selected

    vendor for large MSDs.

    Develop a Risk Management Plan.

    Team members use risk management to identify two

  • 8/9/2019 Chapter 20 Quality Control

    166/174

    Team members use risk management to identify tworisk elements, they are:

    1. Failing to train new purchasing agents in the revisedpurchasing process

    2. Office Optimum and Ibix are out of MSDs with ridges.

    Team members assigned risk ratings to both riskelements.

    Risk Elements Risk CategoryLikelihood ofoccurrence

    Impact ofoccurrence

    Riskelementscore

    Failing to train new

    purchasing agents Performance 5 5 25 High

    Vendor out of MSDswith ridges Materials 2 5 10 Medium

    Scale: 1-5 with 5 being the highest.

    Both risk elements must be dealt with in riskabatement plans.

  • 8/9/2019 Chapter 20 Quality Control

    167/174

    The risk abatement plan forfailing to train newpurchasing agents is to document the revisedpurchasing process in training manuals.

    The risk abatement plan forVendor out of MSDs with

    ridges is for POI to request that both Office Optimumand Ibix manufacture only MSDs with ridges due totheir superior durability.

    This is a reasonable and acceptable suggestion toPOI, Office Optimum and Ibix because the coststructures for manufacturing MSDs with and withoutridges are equal, and neither Office Optimum nor Ibixhas other customers requesting MSDs without ridges.

    Office Optimum and Ibix agree to produce only MSDsith id ft i th t i l i d i hi h th

  • 8/9/2019 Chapter 20 Quality Control

    168/174

    with ridges after a six-month trial period in which they

    check incoming purchase orders for requests forMSDs without ridges.

    If the trial period reveals no requests for MSDswithout ridges, then the POI Purchasing Department

    will revise the process and the appropriate ISO 9000documentation to reflect the possibility of purchasingonly MSDs with ridges.

    Additionally, Office Optimum and Ibix thanked POI for

    pointing out to them that average durability is higherfor MSDs with ridges than MSDs without ridges.

    Both vendors claim that they are going to experimentwith possible different ridge patterns to increased bili d d

  • 8/9/2019 Chapter 20 Quality Control

    169/174

    durability and decrease costs.

    Both vendors stated that they anticipate decreasecosts from only producing MSDs with ridges becauseof the lower amortized costs of having only oneproduction line.

    Prepare ISO Documentation.

  • 8/9/2019 Chapter 20 Quality Control

    170/174

    Team members prepare ISO 9000 documentation for

    the revisions to the training manual for the purchasingprocess.

    Develop a Control Plan.

    Thi i thl li f th b f

  • 8/9/2019 Chapter 20 Quality Control

    171/174

    This requires a monthly sampling of the boxes of

    MSDs in inventory. The purpose of the sampling plan is to check if the

    boxes of MSDs being purchased are either smallOffice Optimum MSDs with ridges or large Ibix MSDswith ridges.

    The percentage non-conforming boxes of MSDs willbe plotted on a p-chart. PSD management will usethe p-chart to highlight violations of the new andimproved purchasing process.

    The p-chart will be the basis for continuously turningthe PDSA cycle for the purchasing process.

    Control Plan.

  • 8/9/2019 Chapter 20 Quality Control

    172/174

    Finally, team members checked the business

    indicator from the PSD metric tracking system anddetermined that production costs in the PSDdecreased, probably due to the MSD Six Sigmaproject.

    The MSD project took effect in month 73 as per thenext control chart.

  • 8/9/2019 Chapter 20 Quality Control

    173/174

    Turn over the Process to the Process Owner

  • 8/9/2019 Chapter 20 Quality Control

    174/174

    It is time for the Champion and Black Belt to disbandthe project team, turn the improved process over tothe Purchasing Department, and celebrate theprojects success with team members.