Broward County Project Number5413
Qualifications for Construction Engineering and Inspection Services
CEI Services for Wiles Road from Riverside Drive to Rock Island Road
BROWARD COUNTY
YOUR CEI SOLUTION – YOUR PARTNERS
MEET THE AE TEAM
YOUR CEI SOLUTION – YOUR PARTNERS
Calvin Giordano + Associates, Inc.
Expertise and Manpower
Issue Identification and Resolution
Communication, Coordination & Stakeholder Outreach
I
II
III
Calvin Giordano + Associates, Inc.
Expertise and ManpowerI
Calvin Giordano + Associates, Inc.
Expertise and Manpower I
Roderick Myrick, P.E. Sr. Project Engineer (AE)
Udin Dwarica-Ogeer , Contract Support Specialist (AE)
Arie Saraga, Inspector (SCE)
Mike Latulippe, Senior Inspector (AE)
Eddie Hernandez. P.E., Project Administrator (AE)
Torrance Thomas, Inspector (AE)
Cory Nichols, P.E.Quality Assurance
Quality Control
Marlin Engineering Inc. Survey & Mapping
Universal Engineering Sciences, Inc.
Geotechnical Serivces
Gerard Fleurgin, Senior Inspector (SCE)
Michael Davis, Inspector (SCE)
Christopher Bradbeer, Inspector (RS&H)
Derek Wynne, Landscape Inspector (AE)
Chase Elliott, Inspector (RS&H)
Randy Rosa, P.E., Materials Specialist (AE)
Christina Yero, P.E., LAP Contract Compliance Specialist (AE)
Erica Valencia, Resident Compliance Specialist (AE)
Calvin Giordano + Associates, Inc.
Expertise and Manpower
ManpowerWe have found that the key to successful management of our projects is the assignment of theright personnel with the necessary skills and similar past experience.
Senior Project Engineer:• Roderick Myrick, P.E. (21 years experience) core responsibilities include Overall
Management, Customer Service, and Timely Project DeliveryProject Administrator:• Eddie Hernandez, P.E. (11 years experience) responsibilities – Verify and Monitor
CPM Schedule and Shop Drawings, Coordinate Materials TestingContract Support Specialist:• Udin Dwarica, (25 years experience) responsibilities – Project Documentation,
Organization, Monthly Estimates and Closeout AssistanceSenior Inspector:• Mike Latulippe (25 years experience) responsibilities – Daily Project Oversite,
Materials TestingLAP Specialty Services:• Christina Yero, P.E. (8 years experience) responsibilities – LAP Monthly Invoicing and
Final Settlement with FDOT LAP Office• Erica Valencia (12 years experience) responsibilities –Resident Compliance Specialist• Randy Rosa, P.E. (8 years experience) responsibilities – Materials Specialist
I
Calvin Giordano + Associates, Inc.
Expertise and Manpower
Expertise – Similar ExperienceRecent Projects:
• FDOT Broward Operations; SR-A1A 3R from Mercedes River to Sunrise Blvd; FM 430601-1-52-01: Milling & resurfacing, widening, drainage including French drain, signalization improvements, sidewalk and curb ramp construction
• City of West Palm Beach; Clematis Street Improvements; FDOT LAP Project FM 427652-1-58-01: Pedestrian, safety and landscape improvements including sidewalk construction and milling & resurfacing
• City of West Palm Beach; 15th Street Beautification Project; FDOT LAP Project FM 431652-1-58-01: Scope included signalization and drainage improvements, milling & resurfacing, and bike lane striping
• FDEP; SR 5/Overseas Hrt. Trail @ MM 47 (Knights Key Pedestrian Underpass –FDOT LAP Project FM 428061-1-58-01: ADA ramps, retaining walls, bulkhead wall, sidewalks, railing, pedestrian bridge approach, landscaping, signage, and striping within DOT right-of-way.
• FDEP; SR 5/Overseas Hrt. Trail Spanish Harbor Historical Bridge @ MM 33 FDOT LAP Project FM 422628-1-58-01: Replacement of missing bridge span sections via proprietary pre-fabricated truss and precast concrete beams, existing deck milling and resurfacing, joint/crack cleaning and resealing, aluminum safety railing, navigational lighting, striping and signage.
I
Calvin Giordano + Associates, Inc.
Issue Identification and ResolutionIIPresentation TopicsConsistent with order of categories distributed in short-list announcement
Calvin Giordano + Associates, Inc.
Issue Identification and Resolution
Unique Project Issues:Drainage• 1524 LF of French drain installation – Filter fabric and aggregate• Thirty-eight (38) Inlets, and thirty-one (31) Manholes• Cast-in-place structures – Verifying elevations prior to shop drawing approval
Signalization• Coordination with Broward County and FDOT for acceptance• Seven (7) Mast Arms installed at Riverside Dr. and Leitner/Woodside Dr.• Drilled Shaft – Deep removal of existing foundations
Asphalt• Limits of Milling and Overbuild – Maintaining positive drainage• Paving Operations Challenges – Smoothness and Rideability• Binder Type – PMA called out
Concrete Operations• Gravity Wall Construction per Index 6011• Sidewalk and curb ramps – maintaining pedestrian and driveway access
II
Calvin Giordano + Associates, Inc.
Communication, Coordination & Stakeholder OutreachIII
Calvin Giordano + Associates, Inc.
Communication, Coordination & Stakeholder Outreach
Communication and CoordinationRod Myrick, P.E and Eddie Hernandez, P.E. – CEI Point of Contact (POC)Rod will serve as the Sr. PE/Project Manager. Eddie will be serving as the coordinator of all informationconcerning the project. This ensures that there will be no communication break-downs amongst the teammembers. Key members that we will coordinate with include:• Construction Contractor• Project Manager• Design Team/ Consultant • Broward County Traffic
Communications will include:• Kick-off meeting prior to Pre-Construction Meeting• Pre-Construction Meeting• Weekly or bi-weekly meetings• Weekly updates to County staff• Clarifying or resolving issues in a timely manner• Discrepancies/ disputes • Budget• Compliance
III
Calvin Giordano + Associates, Inc.
Communication, Coordination & Stakeholder Outreach
Stakeholder Outreach• Door to Door Outreach
o Prior to construction visit each affected business/residence within the project corridoro Identify a contact person for each affected stakeholdero Provide expectation for the project impactso Develop relationship with project team to minimize public complaints during
construction
• Risk Analysis o Identify each construction operation and its effect on adjacent propertieso Include contact information obtained during door to dooro Use the database to proactively inform the affected parties before operations
• Risk Management• Identify possible risks during construction• Assess the risk probability and impact to time, money and public goals• Develop a risk response strategy