Caso 3 - Control de La Sobrerotura

Embed Size (px)

Citation preview

  • 7/29/2019 Caso 3 - Control de La Sobrerotura

    1/3

    HONG KONG, CHINA

    74 FACE DRILLING

    Introduction

    The development of Hong Kong as a major

    southern gateway for China continues

    apace. Integral to the overall plan is the

    enlargement of the freight railway system to

    handle the huge volumes of goods coming

    through the container port, which is now the

    largest in the world after Rotterdam. We

    describe here two major railway tunnel con-

    tracts at which new generation Atlas Copco

    Rocket Boomer drillrigs equipped with

    CAN-bus control systems worked.

    MTRC Pak Shing Kok Tunnels

    The Hong Kong MTRC Pak Shing

    Kok tunnels comprise a complex of five

    interconnected tunnels driven as nine

    tunnels totalling 6 km in length. The

    tunnels have a cross-section of some

    35 sq m and are located in crystalline

    pyroclastic rocks, resulting in high bit

    wear. For the drill and blast operations, the

    contractor Hyundai-Kier Joint Venture

    employed three Atlas Copco Rocket Boomer

    L2 C drillrigs. These were two-boom rigswith a CAN-bus based control system.

    The rigs were equipped with ABC

    Regular boom navigation system, with

    which the operator guides the booms and

    feeds to the correct positions using a preset

    drill pattern presented on the display

    screen in the cab of the drillrig. The feedscan host up to 14 ft-long rods to provide a

    maximum hole depth of 4.2 m.

    The rock was hard and abrasive, but not

    as brittle as regular hard crystalline

    basement rock. As a result, expectations

    for penetration would normally be on the

    low side, and bit wear would be high.

    However, the average penetration achieved

    at Pak Shing Kok was in the range of

    2.5 m/min, and the service lives of bits,

    rods and shanks was around 400 m,

    8-9,000 m, and 8-9,000 m respectively.

    These results are considered as good,taking into account the high penetration

    rate.

    A single operator controlled the two

    booms on each machine, and the total

    drilling time, including positioning, for a

    70-hole, 4 m round was 1.5 to 2 h. As the

    manual moving of the boom from one hole

    position to the next generally took about

    40 to 50 seconds, the operator was busy

    with the levers for two thirds of the drilling

    time. The tunnels are being concrete lined,

    so it is very important to keep overbreak ata low level (Fig 1 overleaf).

    Controlling Overbreak inHong Kong

    ComputerizationImproves EfficiencyThe use of new generation CAN-busdrillrigs in Hong Kong has been moni-tored at two different jobsites. Thefirst is at Pak Shing Kok, where AtlasCopco Rocket Boomer L2C drillrigsequipped with ABC Regular workedfor Hyundai-Kier; and the second is atWest Rail, where larger Rocket

    Boomer WL3 C drillrigs worked forNishimatsu and Dragages. Despitehard and abrasive rock in bothsituations, good average penetrationwas achieved, allied to economicconsumption of drillbits and rods.Operator wages were reduced dramat-ically, thanks to computerization ofthe drilling operation, and profilingwas as good as expected, given theother variables involved.

    Rocket Boomer WL3 C drillrigs working

    for Nishimatsu and Dragages at a

    110 sq m face.

  • 7/29/2019 Caso 3 - Control de La Sobrerotura

    2/3

    Tunnel No 6 was the first to be excav-ated, and the objective was to keep

    overbreak low by demanding smaller

    margins than usual, and the consequence

    was too much underbreak. Some of the

    underbreak is explained by application of

    too much shotcrete for primary support.

    Certainly, better results with respect to

    overbreak have been achieved on other

    projects, but it always comes down to the

    ambition of the management and the

    incentive and skill of the labour.

    West Rail Contract DB 350

    The West Rail contract DB 350 included

    a 5 km-long double-track tunnel located

    in the Repulse bay formation, which

    comprises mainly crystalline pyroclastic

    rocks. The joint venture companies

    Nishimatsu and Dragages split the tunnel

    half each.

    Nishimatsu used the new generation

    Atlas Copco Rocket Boomer WL3C CAN-

    bus drillrigs for face work. The tunnel

    design, which was produced by the jointventure, is a double-track single tube tunnel

    with a cross-section of 110 sq m. A concrete

    wall along the centre-line separates the two

    tracks from each other. The two WL3C

    drillrigs had feeds long enough to handle

    5.8 m holes. The drilled length of the

    rounds varied generally from 5.0 to 5.8 m.

    In poor rock, these long rounds were short-

    ened. This is important to bear in mind

    when overbreak is discussed later. The rigs

    were equipped with ABC Total, which

    moves the booms and feeds to new positionsautomatically, after each hole is drilled.

    The two rigs were positioned side byside at the tunnel face, and each drilled 77

    holes of the total 154 holes for the 110 sq m

    face, plus three 4 in holes for the parallel

    cut. The contour holes were given a spacing

    of 35 to 40 cm. Generally, all but the con-

    tour and the bottom holes were drilled in

    the Total mode. The pull of each round

    was about 90%. Two rounds per day, 25

    days per month gave a production of 200-

    220 m per month. If the perimeter profile

    was free of protruding rock, automatic

    drilling was also used for the contour holes.The wear on drilling tools was the same

    as for the MTRC tunnels described earlier,

    with the exception of the bit life, which

    was around 500 m. Here again, it can be

    concluded that the CAN-bus rig treated the

    drilling tools well.

    HONG KONG, CHINA

    FACE DRILLING 75

    Control panel of the new Rocket

    Boomer WL3 C.

    Fig 1. Profile results at West Railtunnel contract D&B 350 chainage

    1556 to 1997.

    West rail tunnel contract D & B 350

    Hong Kong Overbreak (m)

    (after shotcrete support)

    Frequency

    Frequency

    Overbreak (m) Underbreak (m)

    West rail tunnel contract D & B 350

    Hong Kong Underbreak (m)

    (after shotcrete support)

  • 7/29/2019 Caso 3 - Control de La Sobrerotura

    3/3

    One man operated the three-boom rig,

    and when the Total mode was utilized the

    booms had no downtime, even for shorter

    rounds. The time for the drilling operation,

    including setup, was in the range of

    2-2.5 h, and the penetration rate for the

    48 mm spherical button bits was

    2.5 m/min. In cases where only one drillrig

    was used at the face, the drilling of a full

    round took 3.5 to 4 h.Considering the length of the round,

    with respect to the poorer rock quality,

    overbreak could not match the result from

    the MTRC tunnels. Without any splitting

    on rock-classes, the results from 450 m of

    tunnel are shown in Fig 2 below. Here, as

    in the MTRC project, the drilling of the

    contour holes starts 10 cm outside the

    theoretical line, and the bottom holes

    30 cm outside the theoretical line. What is

    surprisingly encouraging, is that under-

    break is found only in half the surveyed

    sections and, where found, only small

    quantities are registered. As the deviation

    is a multiplication of 2x the length of the

    hole, a 5.5 m-long hole can be expected to

    deviate 50% more than a 4 m-long hole.

    Consequently, the underbreak ought to bemore embarrassing than in the MTRC case.

    Information on the rock quality provid-

    ed by the contractor shows that almost all

    excavation is in rock having a value higher

    than 10, which can be considered as good.

    Overbreak caused by geology should not

    have been dominating in this case.

    Conclusions

    It is very important for machine suppliers

    to have good working relationships with

    experienced customers, as they, to someextent, become partners in the development

    of new equipment. Atlas Copco believes that

    its new generation drillrigs are profitable tools

    when chasing costs in tunnel construction.

    Improvements, such as better drill steel

    economy, savings on operator wages, and

    higher utilization have resulted in a good

    reception of the new series of drillrigs in

    Hong Kong. While the results for overbreak

    are not conclusive, they are favourable, and

    there is no doubt that the higher accuracy

    of the CAN-bus drillrigs is a contributingfactor. s

    HONG KONG, CHINA

    76 FACE DRILLING

    Rocket Boomer WL3 Cs used at West

    Rail.

    Fig 2. Profile results at contract 611,

    MTRC.

    Over&Underbreak(m)

    Tunnel 1-9

    Contract 611, MTRC Hong Kong

    Over and Underbreak

    Overbreak

    Underbreak