Upload
ruben-quispe
View
218
Download
0
Embed Size (px)
Citation preview
7/29/2019 Caso 3 - Control de La Sobrerotura
1/3
HONG KONG, CHINA
74 FACE DRILLING
Introduction
The development of Hong Kong as a major
southern gateway for China continues
apace. Integral to the overall plan is the
enlargement of the freight railway system to
handle the huge volumes of goods coming
through the container port, which is now the
largest in the world after Rotterdam. We
describe here two major railway tunnel con-
tracts at which new generation Atlas Copco
Rocket Boomer drillrigs equipped with
CAN-bus control systems worked.
MTRC Pak Shing Kok Tunnels
The Hong Kong MTRC Pak Shing
Kok tunnels comprise a complex of five
interconnected tunnels driven as nine
tunnels totalling 6 km in length. The
tunnels have a cross-section of some
35 sq m and are located in crystalline
pyroclastic rocks, resulting in high bit
wear. For the drill and blast operations, the
contractor Hyundai-Kier Joint Venture
employed three Atlas Copco Rocket Boomer
L2 C drillrigs. These were two-boom rigswith a CAN-bus based control system.
The rigs were equipped with ABC
Regular boom navigation system, with
which the operator guides the booms and
feeds to the correct positions using a preset
drill pattern presented on the display
screen in the cab of the drillrig. The feedscan host up to 14 ft-long rods to provide a
maximum hole depth of 4.2 m.
The rock was hard and abrasive, but not
as brittle as regular hard crystalline
basement rock. As a result, expectations
for penetration would normally be on the
low side, and bit wear would be high.
However, the average penetration achieved
at Pak Shing Kok was in the range of
2.5 m/min, and the service lives of bits,
rods and shanks was around 400 m,
8-9,000 m, and 8-9,000 m respectively.
These results are considered as good,taking into account the high penetration
rate.
A single operator controlled the two
booms on each machine, and the total
drilling time, including positioning, for a
70-hole, 4 m round was 1.5 to 2 h. As the
manual moving of the boom from one hole
position to the next generally took about
40 to 50 seconds, the operator was busy
with the levers for two thirds of the drilling
time. The tunnels are being concrete lined,
so it is very important to keep overbreak ata low level (Fig 1 overleaf).
Controlling Overbreak inHong Kong
ComputerizationImproves EfficiencyThe use of new generation CAN-busdrillrigs in Hong Kong has been moni-tored at two different jobsites. Thefirst is at Pak Shing Kok, where AtlasCopco Rocket Boomer L2C drillrigsequipped with ABC Regular workedfor Hyundai-Kier; and the second is atWest Rail, where larger Rocket
Boomer WL3 C drillrigs worked forNishimatsu and Dragages. Despitehard and abrasive rock in bothsituations, good average penetrationwas achieved, allied to economicconsumption of drillbits and rods.Operator wages were reduced dramat-ically, thanks to computerization ofthe drilling operation, and profilingwas as good as expected, given theother variables involved.
Rocket Boomer WL3 C drillrigs working
for Nishimatsu and Dragages at a
110 sq m face.
7/29/2019 Caso 3 - Control de La Sobrerotura
2/3
Tunnel No 6 was the first to be excav-ated, and the objective was to keep
overbreak low by demanding smaller
margins than usual, and the consequence
was too much underbreak. Some of the
underbreak is explained by application of
too much shotcrete for primary support.
Certainly, better results with respect to
overbreak have been achieved on other
projects, but it always comes down to the
ambition of the management and the
incentive and skill of the labour.
West Rail Contract DB 350
The West Rail contract DB 350 included
a 5 km-long double-track tunnel located
in the Repulse bay formation, which
comprises mainly crystalline pyroclastic
rocks. The joint venture companies
Nishimatsu and Dragages split the tunnel
half each.
Nishimatsu used the new generation
Atlas Copco Rocket Boomer WL3C CAN-
bus drillrigs for face work. The tunnel
design, which was produced by the jointventure, is a double-track single tube tunnel
with a cross-section of 110 sq m. A concrete
wall along the centre-line separates the two
tracks from each other. The two WL3C
drillrigs had feeds long enough to handle
5.8 m holes. The drilled length of the
rounds varied generally from 5.0 to 5.8 m.
In poor rock, these long rounds were short-
ened. This is important to bear in mind
when overbreak is discussed later. The rigs
were equipped with ABC Total, which
moves the booms and feeds to new positionsautomatically, after each hole is drilled.
The two rigs were positioned side byside at the tunnel face, and each drilled 77
holes of the total 154 holes for the 110 sq m
face, plus three 4 in holes for the parallel
cut. The contour holes were given a spacing
of 35 to 40 cm. Generally, all but the con-
tour and the bottom holes were drilled in
the Total mode. The pull of each round
was about 90%. Two rounds per day, 25
days per month gave a production of 200-
220 m per month. If the perimeter profile
was free of protruding rock, automatic
drilling was also used for the contour holes.The wear on drilling tools was the same
as for the MTRC tunnels described earlier,
with the exception of the bit life, which
was around 500 m. Here again, it can be
concluded that the CAN-bus rig treated the
drilling tools well.
HONG KONG, CHINA
FACE DRILLING 75
Control panel of the new Rocket
Boomer WL3 C.
Fig 1. Profile results at West Railtunnel contract D&B 350 chainage
1556 to 1997.
West rail tunnel contract D & B 350
Hong Kong Overbreak (m)
(after shotcrete support)
Frequency
Frequency
Overbreak (m) Underbreak (m)
West rail tunnel contract D & B 350
Hong Kong Underbreak (m)
(after shotcrete support)
7/29/2019 Caso 3 - Control de La Sobrerotura
3/3
One man operated the three-boom rig,
and when the Total mode was utilized the
booms had no downtime, even for shorter
rounds. The time for the drilling operation,
including setup, was in the range of
2-2.5 h, and the penetration rate for the
48 mm spherical button bits was
2.5 m/min. In cases where only one drillrig
was used at the face, the drilling of a full
round took 3.5 to 4 h.Considering the length of the round,
with respect to the poorer rock quality,
overbreak could not match the result from
the MTRC tunnels. Without any splitting
on rock-classes, the results from 450 m of
tunnel are shown in Fig 2 below. Here, as
in the MTRC project, the drilling of the
contour holes starts 10 cm outside the
theoretical line, and the bottom holes
30 cm outside the theoretical line. What is
surprisingly encouraging, is that under-
break is found only in half the surveyed
sections and, where found, only small
quantities are registered. As the deviation
is a multiplication of 2x the length of the
hole, a 5.5 m-long hole can be expected to
deviate 50% more than a 4 m-long hole.
Consequently, the underbreak ought to bemore embarrassing than in the MTRC case.
Information on the rock quality provid-
ed by the contractor shows that almost all
excavation is in rock having a value higher
than 10, which can be considered as good.
Overbreak caused by geology should not
have been dominating in this case.
Conclusions
It is very important for machine suppliers
to have good working relationships with
experienced customers, as they, to someextent, become partners in the development
of new equipment. Atlas Copco believes that
its new generation drillrigs are profitable tools
when chasing costs in tunnel construction.
Improvements, such as better drill steel
economy, savings on operator wages, and
higher utilization have resulted in a good
reception of the new series of drillrigs in
Hong Kong. While the results for overbreak
are not conclusive, they are favourable, and
there is no doubt that the higher accuracy
of the CAN-bus drillrigs is a contributingfactor. s
HONG KONG, CHINA
76 FACE DRILLING
Rocket Boomer WL3 Cs used at West
Rail.
Fig 2. Profile results at contract 611,
MTRC.
Over&Underbreak(m)
Tunnel 1-9
Contract 611, MTRC Hong Kong
Over and Underbreak
Overbreak
Underbreak