Case Study of Vlf Tan Delta Partial Discharge

Embed Size (px)

Citation preview

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    1/38

    Case Study of VLF / Tan Delta & Partial Discharge

    Acceptance Testing of New 23kV Cables

    Subcommittee F

    Fall ICC Meeting Seattle

    November 14, 2012

    Timothy P Hayden PE

    [email protected]

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    2/38

    2

    Overview

    Testing Equipment

    History of VLF Testing & Procedures

    Project Overview

    Test Results

    Failed Splice Analysis

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    3/38

    Testing Equipment

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    4/38

    6

    Test Equipment

    Second Generation

    Sinusoidal Waveform

    0.1 Hz maximum

    60 kV DC / 43kV AC

    Bluetooth communication

    for Tan Delta

    Partial Discharge Add On

    Only 1 PD set

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    5/38

    History of Testing Procedures

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    6/38

    8

    Introduction of VLF Testing

    Major cable outage in Massachusetts in July 2003

    PSC ordered review of the cause of the outage

    Root cause overuse of DC testing methods on 1970s &

    1980s vintage XLPE insulation

    VLF testing with Tan Delta analysis introduced

    Test sets purchased

    New Electric Operating Procedure (EOP) developed

    The new procedure required use of VLF equipment whenavailable

    The procedure also limited use of DC testing equipment

    Both voltage level and test time

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    7/38

    9

    First Electr ic Operating Procedure 2004

    First procedure used test voltage levels from 400.2

    Many existing cables tested experienced a failure

    New equipment (VLF) blamed for causing cable failures

    Damaging the insulation

    Management became reluctant to test any in service cable

    Explained that the test was finding existing weak spots

    Management was not convinced

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    8/38

    10

    Withstand (Maintenance) Test Voltage Levels

    Second procedure (2007) modified test voltage levels

    No change to acceptance test levels

    Withstand (or Maintenance) test broken into 2 criteria

    Maximum level remained per IEEE 400.2

    Minimum level based upon electric system configuration

    Effectively Grounded 125% of normal L-G voltage

    Delta or ineffectively grounded 100% of normal L-L voltage

    Single point grounded, grounding bank, resistance grounded

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    9/38

    11

    Current Testing Procedures

    All new cables shall be acceptance tested

    Significant length

    Not a replaced section in an existing cable

    When the entire circuit is new

    VLF (sinusoidal) with Tan Delta analysis

    0.1 Hz standard

    Test voltages from IEEE 400.2

    Test duration = 60 minutes

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    10/38

    Project Overview

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    11/38

    16

    Project Overview

    New 23kV Sub-transmission Cable

    1000kcMil copper, 260 mils EPR, JCN (18#14 round wire),

    LLDPE jacket

    2 cables per phase due to loading

    Spliced to existing cable after river crossing

    1000kcMil copper, 260 mils XLPE, Jacketed, drain wire shield,

    LLDPE jacket

    New cable from supply sub across river ~ 2200

    Old Cable from far side of river to next substation ~ 2500

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    12/38

    17

    Plan View Not to Scale

    New Manholes

    New Manholes

    River Crossing

    Existing Manhole

    & Cable

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    13/38

    18

    Circuit 2339 Cable Installation

    New cable was installed from the source sub

    Across the river

    To an existing manhole # 597

    Total distance of ~ 2200

    Cold shrink termination in substation

    Heat Shrink End Seal in MH 597

    Acceptance Tested from Substation with Tan Delta Analysis

    31kV ultimate voltage, 60 minute duration

    Cable sets known as 2339X and 2339Y

    Therefore 6 different phases tested

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    14/38

    VLF / Tan Delta Test Results / Analysis

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    15/38

    20

    Circuit 2339Y Tan Delta Results

    New CableOnly

    Suspect

    moisture on

    terminations

    at the start

    of A phase

    test

    Suitable for

    service

    TD 6.5

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    16/38

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    17/38

    22

    Circuit 2339X Tan Delta Results

    New CableOnly

    Crewreportedtest set

    tripped outon B phase

    Crewassumedproblem

    with test set B phase not

    suitable forservice

    TD 11

    TD 46

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    18/38

    23

    Circuit 2339

    The test crew did not report the problem with B phase of the2339X cable to the cable crew or project management

    In fact, they reported the cable as being ready for service

    Accustomed to DC testing if the set doesnt trip out, cable

    is OK

    However, they did report the set as tripping out at least one

    time

    Heat shrink end seals removed and splices to old cable installed

    in MH 597 Old cable length to substation ~ 2500

    Total cable length now ~ 4700

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    19/38

    24

    Circuit 2339 Y Old and New Cable

    Old & NewCable ~ 50%

    of each

    5 minute test

    Max 23.0kV

    Acceptance

    test TD was

    6.5 (slide 21)

    Acceptablefor service

    TD 8 - 10

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    20/38

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    21/38

    26

    Tan Delta

    Tan Delta

    Ratio of IRto IC

    IR (leakage current) should be

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    22/38

    27

    Circuit 2339 X Tan Delta Analysis

    Tan Delta expected to decrease

    Length of cable more than doubled

    Test voltage 75% of acceptance

    Tan Delta decreased by 50%

    Still much higher than other phases

    Original IRstill there, IC~ doubled, TD ~ halved

    Test Type Length Test Voltage Phase Tan Delta

    Accept 2200 31.0

    A 11

    B 46

    C 11

    Pickup 4700 23.0A 12B 24

    C 12

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    23/38

    28

    Circuit 2339 X Retest of B Phase Only

    Retest ofcompletecable

    Results still

    notacceptable

    TD of 17.2

    SD @ 23kVwas 0.28%

    Still higherthan A and Cphases

    TD 17.2

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    24/38

    29

    2339 X Action Plan

    Project manager wanted to put cable into service

    The other 2 sub-transmission cables yet to be completed

    Project in danger of running behind schedule

    Ultimately convinced him that this cable was not suitable for

    service in current condition

    If this cable were to fail while the second circuit was out of

    service for this project, only a single circuit would remain

    Chance of forced outages high if that were to occur

    Need to remove the splice between the new cable and the

    existing cable and re-test

    Partial discharge test available

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    25/38

    Partial Discharge Test Results

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    26/38

    31

    2339 X Partial Discharge Test

    Splice removed between the new cable and the old cable

    Cable prepped and an air termination installed

    Isolated in the manhole

    Partial Discharge Test performed

    Using VLF at 0.1 Hz

    Tested at 25.0 and 28.0 kV

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    27/38

    32

    2339 X Partial Discharge Test 25.0 kV

    PD test

    25kV

    225 feetfrom

    substation

    termination

    Location225 feet

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    28/38

    33

    2339 X Partial Discharge Test 28.0 kV

    Location250 feet

    PD test

    25kV

    250 feetfrom

    substation

    termination

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    29/38

    34

    2339 X Partial Discharge Test

    The conduit plan showed the first manhole (592) to be 150conduit feet from the riser

    Due to station and manhole conditions, actual cable feet from

    the manhole to the termination is closer to 200 225 feet

    It become logical to suspect the splice in this manhole as beingthe problem

    All cable tested in the factory

    Relatively short pull length

    Low chance of problem being in the cable

    Splice in this manhole (592) was removed and replaced

    B phase acceptance test repeated

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    30/38

    35

    Circuit 2339 X B Phase after Repair

    Splicereplaced

    60 minute

    acceptance

    test

    31.0kV

    A phase TD

    was 11.2

    C phase TDwas 11.6

    Acceptable

    for service

    TD 11.5

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    31/38

    Failure Analysis of Removed Splice

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    32/38

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    33/38

    38

    Failure Analysis

    Splice Body removed from cable

    Left side cable Manufacturer A, Right side Manufacturer B

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    34/38

    39

    Failure Analysis

    Unable to determine the exact splice body alignment on thecable

    Since splice body was removed prior to receiving the splice

    Alignment is critical insulation interface must be fully

    engaged with cable insulation However, marks remained where the splice body was positioned

    Alignment was OK

    There was visible tracking on the interface of side A

    There were matching tracks on that side of the splice body

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    35/38

    40

    Failure Analysis

    Cutbacks were correct per template

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    36/38

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    37/38

    42

    Failure Analysis

    Failure believed to be due to contamination on interface Dirt from cable jacket where splice body was parked?

    Improper cleaning?

    Other source?

  • 8/13/2019 Case Study of Vlf Tan Delta Partial Discharge

    38/38

    Questions?