CAPITAL PROJECT STATUS
REPORT
As of June 21, 2016
I. Planning Projects
II. Construction Projects
III. FY 14 Feasibility Studies
IV. FY 15 Feasibility Studies
Division of Construction
Montgomery County Public Schools
45 West Gude Drive, Suite 4300
Rockville, Maryland 20850
(240)314-1000
EXPLANATION OF FOLLOWING PROJECT SCHEDULES
Schematic
Start - date of project kick-off meeting (ahead of any Facilities Study Process meetings).
End - date of Board of Education Preliminary Plans Presentation approval meeting.
Design Development
Start - date of pre-DD meeting (may proceed earlier than end of Schematic phase when BOE approval schedule is backed up).
End - date of in-house review meeting with Design Team (Design Team leaves with annoted drawings and written comments to answer).
Construction Documents
Start - date of first working day after DD phase ends.
End - date of in-house review meeting with Design Team (Design Team leaves with annotated drawings, specs, and written comments to answer).
Bidding
Start - date bid documents are available for distribution- Out to Bid Date (CANNOT precede state permission to bid).
End - date bids are received and publicly opened- Bid Date.
Construction
Start - date of BOE meeting that awards construction contract to GC or CM (NOT the same date as Notice to Proceed).
End - date of project completion as recorded in CIP Master Plan (approx start of school, NOT the same date as Construction Contract completion date).
1
I PLANNING PROJECTS As of June 21, 2016
Notes
MR submission filed with MNCPPC. MR
hearing scheduled for 06/23 /16.
Completing CD's. MEMA disapproved
waiver request and MCPS is appealing. SC
filed 06/08/16. Bldg. permit filed
electronically 06/20/16. Preparing CD
submission to State.
10/08/14 11/10/15
02/17/15 06/16/15
06/17/15 05/31/16*
10/04/16* 11/02/16*
08/01/18
Barnsley ES
Project: Addition
Planner: Szyfer
Proj Mgr: Bagai
Design Architect: WMCRP
Project Start: 10/08/14 Project End: 08/01/18
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
12/13/16*
Notes
Early site package bid award 05/26/16. Site
work prices very high, working on VE with
DPS. No response from MEMA to MCPS
waiver request. Bids received. BOE
approval of site and GMP by CM Hess
scheduled for 06/27/16.
11/07/14 10/13/15
03/26/15 07/01/15
07/02/15 02/10/16
04/20/16 05/18/16
08/01/18
BCC HS
Project: Addition
Planner: Szyfer
Proj Mgr: Tokar
Design Architect: SEI
Project Start: 11/07/14 Project End: 08/01/18
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
06/27/16*
Notes
CD proceeding. MEMA disapproved
waiver request and MCPS is appealing. SC
permit received. 99% CD in-house review
held 06/14/16. 100% CD submisison to
State being prepared.
11/11/14 12/08/15
02/26/15 07/22/15
07/23/15 06/14/16
09/27/16* 10/26/16*
08/01/18
Diamond ES
Project: Addition
Planner: Szyfer
Proj Mgr: Bagai
Design Architect: WMCRP
Project Start: 11/11/14 Project End: 08/01/18
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
11/15/16*
Page 2 of 4* DATE CHANGED BY THIS REPORT
I PLANNING PROJECTS As of June 21, 2016
Notes
Keller CM proceeding on relocating electric
primary service. MEMA Waiver request
disapproved and MCPS is appealing. CD
submisison to state 05/28/16. Filed for SC
permit 02/08/16. Filed for building permit
04/22/16. Meeting with Jillian Storms to
review state CD comments 06/24/16.
09/15/14 10/13/15
02/12/15 07/24/15
07/27/15 03/31/16
09/14/16* 10/12/16*
08/01/18
Kensington Parkwood ES
Project: Addition
Planner: Morris
Proj Mgr: Bagai
Design Architect: GWWO
Project Start: 09/15/14 Project End: 08/01/18
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
11/15/16*
Notes
CM Hess hired for pre-construction
services. State CD submission scheduled
for first week in August. No response to
MEMA waiver request filed in 2015.
10/15/14 09/08/15
03/11/15 05/20/15
05/21/15 06/08/16*
10/11/16* 11/10/16*
08/01/18
North Bethesda MS
Project: Addition
Planner: Szyfer
Proj Mgr: Tokar
Design Architect: Samaha
Project Start: 10/15/14 Project End: 08/01/18
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
12/13/16*
Notes
CD submission to State 05/20/16. Filed
permits with out paying city fees. No permit
approvals yet. State CD comments received
06/10/16. Hiring architectural historian to
submit report to Md Historical Trust.
09/25/14 09/08/15
02/05/15 04/10/15
04/13/15 01/22/16*
08/22/16* 09/22/16*
08/01/18
Richard Montgomery ES #5
Project: New
Planner: Morris
Proj Mgr: Marhamati
Design Architect: WMCRP
Project Start: 09/25/14 Project End: 08/01/18
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
10/24/16*
Page 3 of 4* DATE CHANGED BY THIS REPORT
I PLANNING PROJECTS As of June 21, 2016
Notes
MNCPPC Mandatory Referral filed
10/03/15. Staff review coments discussed.
MR response meeting to be held with
MNCPPC. Studying 4th floor addition and
structured tennis courts over parking on
grade. Met with Joe Pospicil of DOT
regarding safe access off Meadowbrook Rd.
**2019 Building, per approved budget.
**2020 Sitework completion per approved
09/04/13 01/13/15
04/04/14 02/11/15
02/12/15 05/19/16*
03/01/17 04/01/17
08/01/19**
Seneca Valley HS
Project: Revitalization/Expansion
Planner: Szyfer
Proj Mgr: Tokar
Design Architect: Moseley
Project Start: 09/04/13 Project End: 08/01/19**
Schematic
Design Dev
Const Docs
Bidding
Construction
EndStart
X
06/01/17
Page 4 of 4* DATE CHANGED BY THIS REPORT
School Const Start Const End Proj Mgr Planner Design Architect Contractor Inspector
II CONSTRUCTION PROJECTS As of June 21, 2016
12/09/14 2016/08/01 Marhamati Morris HCM Dustin (CM) DonahueFarquhar MS
10/27/14 2016/08/01 Marhamati Morris Grimm+Parker Hess (CM) RotzHallie Wells
MS(Clarksburg/Damascus
MS)
02/10/15 2016/08/01 Tokar Morris SEI Dustin (CM) BadstibnerJulius West MS
01/13/15 2016/08/01 Bagai Szyfer MWB Hess (CM) BadstibnerWood Acres ES
08/20/15 2017/08/01 Marhamati Szyfer Samaha Dustin Construction DonahueBCC Middle School #2
12/08/15 2017/08/01 Bagai Szyfer Lukmire Keller Brothers RotzBrown Station ES
12/08/15 2017/08/01 Tokar Szyfer Moseley Henley RotzWayside ES
01/12/16 2017/08/01 DeRosa Morris GWWO Meridian (CM) CoulterWheaton Woods ES
04/19/16 2018/01/01 DeRosa Szyfer Grimm and Parker Oak Contracting CoulterEdison HS
Page 1 of 2
School Const Start Const End Proj Mgr Planner Design Architect Contractor Inspector
II CONSTRUCTION PROJECTS As of June 21, 2016
08/21/13 2018/08/01 DeRosa Szyfer Grimm & Parker Oak (CM) CoulterWheaton HS Site
Page 2 of 2
School Project Type Planner Project Mgr Feas Architect BOE Award Arc Final Report
As of June 21, 2016FY 2014
III FEASIBILITY STUDIES
Burning Tree ES Addition Szyfer Marhamati Muse 05/13/14 Draft review.
Downcounty ES Capacity Study Szyfer Tokar Lukmire 12/09/14 Report finalized.
Gaithersburg Cluster Capacity Study Morris Bagai Moseley 12/09/14 Report finalized.
J Leleck@Broad Acr Addition Morris Marhamati Proffitt 05/13/14 Draft review.
Lake Seneca ES Addition Morris DeRosa Delmar 06/03/14 Draft review.
Loiederman MS Addition Szyfer Tokar SEI 06/03/14 Draft review
South Lake ES Addition Morris Marhamati GWWO 06/17/14 Draft review.
Whitman HS Addition Szyfer DeRosa JK Architect 04/29/14 Draft review.
Page 1 of 1
School Project Type Planner Project Mgr Feas Architect BOE Award Arc Final Report
As of June 21, 2016FY 2015
IV FEASIBILITY STUDIES
Belmont ES Rev/Ex Morris DeRosa Delmar 04/14/15 Need LCC
Cold Spring ES Rev/Ex Szyfer Bagai Muse 04/14/15 Need LCC
Dufief/Carson ES Rev/Ex Morris Marharmati WMCRP 03/30/15 Need LCC.
E. Brooke Lee MS Addition Szyfer Bagai Lukmire 05/26/15 Draft Review.
Ewing Center Reopen Szyfer Marhamati HCM 05/12/15 Draft Review.
Fields Road ES/Cars Addition Morris Marharmati Proffitt 05/12/15 Draft Review.
Johnson, Walter HS Addition Szyfer Tokar Samaha 05/26/15 Draft Review.
Jones Lane/Carson Addition Morris Marhamati Proffitt 05/12/15 Draft review.
Neelsville MS Addition Morris Tokar HCM 06/16/15 Draft Review.
Parkland MS Addition Morris Bagai Moseley 06/16/15 Draft Review.
SSI Middle School Addition Szyfer Tokar Lukmire 01/13/15 Report finalized.
Stonegate ES Rev/Ex Morris Bagai Smolen 05/12/15 Need LCC.
Takoma Park MS Addition Morris Marharmati Smolen 05/26/15 Draft Review.
Thomas Wootton Rev/Ex Szyfer Tokar Samaha 04/27/15 Need LCC.
Tilden MS/Rock Terr Rev/Ex Szyfer DeRosa Samaha 06/29/15 Need LCC.
Page 1 of 1