9

Click here to load reader

CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

  • Upload
    lamthuy

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

CAPITAL PROJECT STATUS

REPORT

As of June 21, 2016

I. Planning Projects

II. Construction Projects

III. FY 14 Feasibility Studies

IV. FY 15 Feasibility Studies

Division of Construction

Montgomery County Public Schools

45 West Gude Drive, Suite 4300

Rockville, Maryland 20850

(240)314-1000

Page 2: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

EXPLANATION OF FOLLOWING PROJECT SCHEDULES

Schematic

Start - date of project kick-off meeting (ahead of any Facilities Study Process meetings).

End - date of Board of Education Preliminary Plans Presentation approval meeting.

Design Development

Start - date of pre-DD meeting (may proceed earlier than end of Schematic phase when BOE approval schedule is backed up).

End - date of in-house review meeting with Design Team (Design Team leaves with annoted drawings and written comments to answer).

Construction Documents

Start - date of first working day after DD phase ends.

End - date of in-house review meeting with Design Team (Design Team leaves with annotated drawings, specs, and written comments to answer).

Bidding

Start - date bid documents are available for distribution- Out to Bid Date (CANNOT precede state permission to bid).

End - date bids are received and publicly opened- Bid Date.

Construction

Start - date of BOE meeting that awards construction contract to GC or CM (NOT the same date as Notice to Proceed).

End - date of project completion as recorded in CIP Master Plan (approx start of school, NOT the same date as Construction Contract completion date).

1

Page 3: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

I PLANNING PROJECTS As of June 21, 2016

Notes

MR submission filed with MNCPPC. MR

hearing scheduled for 06/23 /16.

Completing CD's. MEMA disapproved

waiver request and MCPS is appealing. SC

filed 06/08/16. Bldg. permit filed

electronically 06/20/16. Preparing CD

submission to State.

10/08/14 11/10/15

02/17/15 06/16/15

06/17/15 05/31/16*

10/04/16* 11/02/16*

08/01/18

Barnsley ES

Project: Addition

Planner: Szyfer

Proj Mgr: Bagai

Design Architect: WMCRP

Project Start: 10/08/14 Project End: 08/01/18

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

12/13/16*

Notes

Early site package bid award 05/26/16. Site

work prices very high, working on VE with

DPS. No response from MEMA to MCPS

waiver request. Bids received. BOE

approval of site and GMP by CM Hess

scheduled for 06/27/16.

11/07/14 10/13/15

03/26/15 07/01/15

07/02/15 02/10/16

04/20/16 05/18/16

08/01/18

BCC HS

Project: Addition

Planner: Szyfer

Proj Mgr: Tokar

Design Architect: SEI

Project Start: 11/07/14 Project End: 08/01/18

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

06/27/16*

Notes

CD proceeding. MEMA disapproved

waiver request and MCPS is appealing. SC

permit received. 99% CD in-house review

held 06/14/16. 100% CD submisison to

State being prepared.

11/11/14 12/08/15

02/26/15 07/22/15

07/23/15 06/14/16

09/27/16* 10/26/16*

08/01/18

Diamond ES

Project: Addition

Planner: Szyfer

Proj Mgr: Bagai

Design Architect: WMCRP

Project Start: 11/11/14 Project End: 08/01/18

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

11/15/16*

Page 2 of 4* DATE CHANGED BY THIS REPORT

Page 4: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

I PLANNING PROJECTS As of June 21, 2016

Notes

Keller CM proceeding on relocating electric

primary service. MEMA Waiver request

disapproved and MCPS is appealing. CD

submisison to state 05/28/16. Filed for SC

permit 02/08/16. Filed for building permit

04/22/16. Meeting with Jillian Storms to

review state CD comments 06/24/16.

09/15/14 10/13/15

02/12/15 07/24/15

07/27/15 03/31/16

09/14/16* 10/12/16*

08/01/18

Kensington Parkwood ES

Project: Addition

Planner: Morris

Proj Mgr: Bagai

Design Architect: GWWO

Project Start: 09/15/14 Project End: 08/01/18

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

11/15/16*

Notes

CM Hess hired for pre-construction

services. State CD submission scheduled

for first week in August. No response to

MEMA waiver request filed in 2015.

10/15/14 09/08/15

03/11/15 05/20/15

05/21/15 06/08/16*

10/11/16* 11/10/16*

08/01/18

North Bethesda MS

Project: Addition

Planner: Szyfer

Proj Mgr: Tokar

Design Architect: Samaha

Project Start: 10/15/14 Project End: 08/01/18

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

12/13/16*

Notes

CD submission to State 05/20/16. Filed

permits with out paying city fees. No permit

approvals yet. State CD comments received

06/10/16. Hiring architectural historian to

submit report to Md Historical Trust.

09/25/14 09/08/15

02/05/15 04/10/15

04/13/15 01/22/16*

08/22/16* 09/22/16*

08/01/18

Richard Montgomery ES #5

Project: New

Planner: Morris

Proj Mgr: Marhamati

Design Architect: WMCRP

Project Start: 09/25/14 Project End: 08/01/18

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

10/24/16*

Page 3 of 4* DATE CHANGED BY THIS REPORT

Page 5: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

I PLANNING PROJECTS As of June 21, 2016

Notes

MNCPPC Mandatory Referral filed

10/03/15. Staff review coments discussed.

MR response meeting to be held with

MNCPPC. Studying 4th floor addition and

structured tennis courts over parking on

grade. Met with Joe Pospicil of DOT

regarding safe access off Meadowbrook Rd.

**2019 Building, per approved budget.

**2020 Sitework completion per approved

09/04/13 01/13/15

04/04/14 02/11/15

02/12/15 05/19/16*

03/01/17 04/01/17

08/01/19**

Seneca Valley HS

Project: Revitalization/Expansion

Planner: Szyfer

Proj Mgr: Tokar

Design Architect: Moseley

Project Start: 09/04/13 Project End: 08/01/19**

Schematic

Design Dev

Const Docs

Bidding

Construction

EndStart

X

06/01/17

Page 4 of 4* DATE CHANGED BY THIS REPORT

Page 6: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

School Const Start Const End Proj Mgr Planner Design Architect Contractor Inspector

II CONSTRUCTION PROJECTS As of June 21, 2016

12/09/14 2016/08/01 Marhamati Morris HCM Dustin (CM) DonahueFarquhar MS

10/27/14 2016/08/01 Marhamati Morris Grimm+Parker Hess (CM) RotzHallie Wells

MS(Clarksburg/Damascus

MS)

02/10/15 2016/08/01 Tokar Morris SEI Dustin (CM) BadstibnerJulius West MS

01/13/15 2016/08/01 Bagai Szyfer MWB Hess (CM) BadstibnerWood Acres ES

08/20/15 2017/08/01 Marhamati Szyfer Samaha Dustin Construction DonahueBCC Middle School #2

12/08/15 2017/08/01 Bagai Szyfer Lukmire Keller Brothers RotzBrown Station ES

12/08/15 2017/08/01 Tokar Szyfer Moseley Henley RotzWayside ES

01/12/16 2017/08/01 DeRosa Morris GWWO Meridian (CM) CoulterWheaton Woods ES

04/19/16 2018/01/01 DeRosa Szyfer Grimm and Parker Oak Contracting CoulterEdison HS

Page 1 of 2

Page 7: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

School Const Start Const End Proj Mgr Planner Design Architect Contractor Inspector

II CONSTRUCTION PROJECTS As of June 21, 2016

08/21/13 2018/08/01 DeRosa Szyfer Grimm & Parker Oak (CM) CoulterWheaton HS Site

Page 2 of 2

Page 8: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

School Project Type Planner Project Mgr Feas Architect BOE Award Arc Final Report

As of June 21, 2016FY 2014

III FEASIBILITY STUDIES

Burning Tree ES Addition Szyfer Marhamati Muse 05/13/14 Draft review.

Downcounty ES Capacity Study Szyfer Tokar Lukmire 12/09/14 Report finalized.

Gaithersburg Cluster Capacity Study Morris Bagai Moseley 12/09/14 Report finalized.

J Leleck@Broad Acr Addition Morris Marhamati Proffitt 05/13/14 Draft review.

Lake Seneca ES Addition Morris DeRosa Delmar 06/03/14 Draft review.

Loiederman MS Addition Szyfer Tokar SEI 06/03/14 Draft review

South Lake ES Addition Morris Marhamati GWWO 06/17/14 Draft review.

Whitman HS Addition Szyfer DeRosa JK Architect 04/29/14 Draft review.

Page 1 of 1

Page 9: CAPITAL PROJECT STATUS REPORT - Montgomery County … · CAPITAL PROJECT STATUS. REPORT. As of June 21, 2016. ... date of first working day after DD phase ... School Project Type

School Project Type Planner Project Mgr Feas Architect BOE Award Arc Final Report

As of June 21, 2016FY 2015

IV FEASIBILITY STUDIES

Belmont ES Rev/Ex Morris DeRosa Delmar 04/14/15 Need LCC

Cold Spring ES Rev/Ex Szyfer Bagai Muse 04/14/15 Need LCC

Dufief/Carson ES Rev/Ex Morris Marharmati WMCRP 03/30/15 Need LCC.

E. Brooke Lee MS Addition Szyfer Bagai Lukmire 05/26/15 Draft Review.

Ewing Center Reopen Szyfer Marhamati HCM 05/12/15 Draft Review.

Fields Road ES/Cars Addition Morris Marharmati Proffitt 05/12/15 Draft Review.

Johnson, Walter HS Addition Szyfer Tokar Samaha 05/26/15 Draft Review.

Jones Lane/Carson Addition Morris Marhamati Proffitt 05/12/15 Draft review.

Neelsville MS Addition Morris Tokar HCM 06/16/15 Draft Review.

Parkland MS Addition Morris Bagai Moseley 06/16/15 Draft Review.

SSI Middle School Addition Szyfer Tokar Lukmire 01/13/15 Report finalized.

Stonegate ES Rev/Ex Morris Bagai Smolen 05/12/15 Need LCC.

Takoma Park MS Addition Morris Marharmati Smolen 05/26/15 Draft Review.

Thomas Wootton Rev/Ex Szyfer Tokar Samaha 04/27/15 Need LCC.

Tilden MS/Rock Terr Rev/Ex Szyfer DeRosa Samaha 06/29/15 Need LCC.

Page 1 of 1