    Calculating Lead Times for a Routing

    Trigger:

    Concept

    Manufacturing Lead time is the total time required to manufacture an assembly.

    You can create and calculate lead times from the Routings page after you query on a

    manufacturing item's routing. You can calculate manufacturing lead times for one item, a range

    of items, or a category of items. The calculation updates the lead time attributes of all

    manufacturing items that you include, regardless of whether you manually maintain an item's lead

    times.

    Lead time for items with network routings is calculated using only resources on the primary path.

    In this topic, you will calculate lead time for a routing.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/18/2010 09:38:00 AM Page 1

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    2/20

    System Process DocumentCalculating Lead Times for a Routing

    Procedure

    Step Action

    1. Begin by navigating to the Routings page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    3/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/18/2010 09:38:00 AM Page 3

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    4/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    3. Click the vertical scrollbar.

    Step Action

    4. Click the Routings link.

    Page 4 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    5/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    5. Use the Organizations page to select your organization.

    Last changed on: 1/18/2010 09:38:00 AM Page 5

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    6/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    6. Click the M1 Seattle Manufacturing list item.

    Step Action

    7. Click the OKbutton.

    orPress [Alt+O].

    Page 6 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    7/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    8. Use the Routings page to define the operations for a routing and the sequence to

    perform them.

    You can define a primary or an alternate routing.

    Last changed on: 1/18/2010 09:38:00 AM Page 7

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    8/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    9. Click in the Item field.

    Step Action

    10. Press [F11].

    Page 8 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    9/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    11. Enter the desired information into the Item field. Enter "RT_Routing".

    Last changed on: 1/18/2010 09:38:00 AM Page 9

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    10/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    12. Press [Ctrl+F11].

    Step Action

    13. Click the Tools menu.

    orPress [Alt+T].

    Page 10 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    11/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    14. Click the Compute Lead Times menu.

    orPress [L].

    Last changed on: 1/18/2010 09:38:00 AM Page 11

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    12/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    15. You can note the request ID from the Status bar.

    Step Action

    16. Click the View menu.

    orPress [Alt+V].

    Page 12 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    13/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    17. Click the Requests menu.

    orPress [R].

    Last changed on: 1/18/2010 09:38:00 AM Page 13

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    14/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    18. Use the Find Requests page to enter the request ID.

    Step Action

    19. Click the Specific Requests option.

    Page 14 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    15/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    20. Click in the Request ID field.

    Last changed on: 1/18/2010 09:38:00 AM Page 15

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    16/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    21. Enter the desired information into the Request ID field. Enter "5591401".

    Step Action

    22. Click the Find button.

    Page 16 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    17/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    23. Use the Requests page to view the status of your request.

    Last changed on: 1/18/2010 09:38:00 AM Page 17

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    18/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    24. Click the View Details... button.

    orPress [Alt+s].

    Step Action25. Use the Request Detail page to view the details of the request 5591401.

    Page 18 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    19/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    26. Click the OKbutton.

    orPress [Alt+K].

    Last changed on: 1/18/2010 09:38:00 AM Page 19

  • 8/14/2019 Calculating Lead Times for a Routing_SPD

    20/20

    System Process DocumentCalculating Lead Times for a Routing

    Step Action

    27. You can view the detailed log of the report by clicking the View Log button.

    Click the View Log button.

    Step Action

    28. You have completed the Calculating Lead Times for a Routing procedure.

    End of Procedure.