    System Process DocumentCalculating Lead Times

    Department

    Responsibility/Role

    File Name 27760314.docRevision

    Document Generation Date 18/01/2010 09:40:00

    Date Modified 1/18/2010 09:40:00 AM

    Last Changed by

    Status

    Calculating Lead Times

    Trigger:

    Concept

    You can calculate manufacturing lead times for one item, a range of items, or a category of items.

    The calculation updates the lead time attributes of all manufacturing items that you include,

    regardless of whether you manually maintain an item's lead times. Leadtime for items with

    network routings is calculated using only resources on the primary path.

    Prerequisites for calculating lead times are:

    You must define a bill of material for the parent item and its member items for which

    lead time is to be calculated.

    You must define a routing for each item that will be used in the lead time calculation.

    You must define a lead time lot size for the parent item for which lead time is to be

    calculated.

    In this topic, you will calculate lead times.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/18/2010 09:40:00 AM Page 1

  • 8/14/2019 Calculating Lead Times_SPD

    2/27

    System Process DocumentCalculating Lead Times

    Procedure

    Step Action

    1. Begin by navigating to the Calculate Lead Times page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    3/27

    System Process DocumentCalculating Lead Times

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/18/2010 09:40:00 AM Page 3

  • 8/14/2019 Calculating Lead Times_SPD

    4/27

    System Process DocumentCalculating Lead Times

    Step Action

    3. Click the vertical scrollbar.

    Step Action

    4. Click the Lead Times link.

    Page 4 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    5/27

    System Process DocumentCalculating Lead Times

    Step Action

    5. Use the Organizations page to select your organization.

    Last changed on: 1/18/2010 09:40:00 AM Page 5

  • 8/14/2019 Calculating Lead Times_SPD

    6/27

    System Process DocumentCalculating Lead Times

    Step Action

    6. Click the M1 Seattle Manufacturing list item.

    Step Action

    7. Click the OKbutton.

    orPress [Alt+O].

    Page 6 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    7/27

    System Process DocumentCalculating Lead Times

    Step Action

    8. Use the Submit a New Request page to enter either a single request or a set.

    Last changed on: 1/18/2010 09:40:00 AM Page 7

  • 8/14/2019 Calculating Lead Times_SPD

    8/27

    System Process DocumentCalculating Lead Times

    Step Action

    9. Click the OKbutton.

    orPress [Alt+O].

    Step Action10. Use the Calculate Lead Times page to enter the request name.

    Page 8 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    9/27

    System Process DocumentCalculating Lead Times

    Step Action

    11. Click in the Name field.

    Last changed on: 1/18/2010 09:40:00 AM Page 9

  • 8/14/2019 Calculating Lead Times_SPD

    10/27

    System Process DocumentCalculating Lead Times

    Step Action

    12. Enter the desired information into the Name field. Enter "Calculate

    Manufacturing Lead Times GUI".

    Step Action

    13. Click in the Parameters field.

    Page 10 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    11/27

    System Process DocumentCalculating Lead Times

    Step Action

    14. Use the Parameters page to enter the parameters for calculating manufacturing

    lead times of the item.

    Last changed on: 1/18/2010 09:40:00 AM Page 11

  • 8/14/2019 Calculating Lead Times_SPD

    12/27

    System Process DocumentCalculating Lead Times

    Step Action

    15. Click in the Item field.

    Step Action

    16. Use the System Items page to enter the name of the item.

    Page 12 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    13/27

    System Process DocumentCalculating Lead Times

    Step Action

    17. Click in the Item field.

    Step Action

    18. Enter the desired information into the Item field. Enter "RT_Routing".

    Last changed on: 1/18/2010 09:40:00 AM Page 13

  • 8/14/2019 Calculating Lead Times_SPD

    14/27

    System Process DocumentCalculating Lead Times

    Step Action

    19. Click the OKbutton.

    orPress [Alt+O].

    Page 14 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    15/27

    System Process DocumentCalculating Lead Times

    Step Action

    20. Click in the Date field.

    Step Action

    21. Enter the desired information into the Date field. Enter "04-DEC-2004 10:16:26".

    Last changed on: 1/18/2010 09:40:00 AM Page 15

  • 8/14/2019 Calculating Lead Times_SPD

    16/27

    System Process DocumentCalculating Lead Times

    Step Action

    22. Click the OKbutton.

    orPress [Alt+O].

    Page 16 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    17/27

    System Process DocumentCalculating Lead Times

    Step Action

    23. Click the Submit button.

    Step Action

    24. Use the Decision page to note the request ID and you can also submit another

    request.

    Last changed on: 1/18/2010 09:40:00 AM Page 17

  • 8/14/2019 Calculating Lead Times_SPD

    18/27

    System Process DocumentCalculating Lead Times

    Step Action

    25. Click the No button.

    orPress [Alt+N].

    Page 18 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    19/27

  • 8/14/2019 Calculating Lead Times_SPD

    20/27

    System Process DocumentCalculating Lead Times

    Step Action

    28. Click the Requests menu.

    Page 20 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    21/27

    System Process DocumentCalculating Lead Times

    Step Action

    29. Use the Find Requests page to enter the request Id.

    Step Action

    30. Click the Specific Requests option.

    Last changed on: 1/18/2010 09:40:00 AM Page 21

  • 8/14/2019 Calculating Lead Times_SPD

    22/27

    System Process DocumentCalculating Lead Times

    Step Action

    31. Click in the Request ID field.

    Page 22 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    23/27

    System Process DocumentCalculating Lead Times

    Step Action

    32. Enter the desired information into the Request ID field. Enter "5596472".

    Step Action

    33. Click the Find button.

    orPress [Alt+i].

    Last changed on: 1/18/2010 09:40:00 AM Page 23

  • 8/14/2019 Calculating Lead Times_SPD

    24/27

    System Process DocumentCalculating Lead Times

    Step Action

    34. Use the Requests page to view the status of the request ID that you had submitted.

    Page 24 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    25/27

    System Process DocumentCalculating Lead Times

    Step Action

    35. Click the View Details... button.

    orPress [Alt+s].

    Step Action36. Click the OKbutton.

    Last changed on: 1/18/2010 09:40:00 AM Page 25

  • 8/14/2019 Calculating Lead Times_SPD

    26/27

    System Process DocumentCalculating Lead Times

    Step Action

    37. Click the View Log button.

    Page 26 Last changed on: 1/18/2010 09:40:00 AM

  • 8/14/2019 Calculating Lead Times_SPD

    27/27

    System Process DocumentCalculating Lead Times

    Step Action

    38. You have completed the Calculating Lead Times procedure.